Page 1 Procurement Plan-Goods Country/Organisation: Project/Programme: AKWA IBOM HIV/AIDS PROGRAMME DEV> PROJECT If Post-Review, No-objection Dates are not needed Credit No: 3556 UNI Spec Proc Notice Advert Contract Implementation Description* Package Number Lot Number Estimated Amount in US $ Procurement Method Pre-or Post Qualification Prior or Post Plan vs. Actual Prep & Submissi No-objection Date On-line UNDB Bid Invitation Bid Closing- Opening Submission Bid Eval Rpt No- objecti Plan vs. Actual Contract Amount in US$'000 Date Contract Date Contract Date Contract Opening of Arrival of If Prequalification Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks 1 - 1.5 wks Plan 1 wk 1.5-3 wks add 7-13 wks Actual Actual List of Contracts AKS/HIV/NS/01/08 N/A 8,550.00 NS Post Plan N/A N/A N/A 3-3-08 17-03-08 N/A N/A Plan 8,550.00 25-03-08 N/A 07--4-08 N/A 20-04-08 Actual Actual date AKS/HIV/NS/02/08 N/A 17,100.00 NS Post Plan NA NA NA 05-03-08 07-04-08 N/A N/A Plan 17,100.00 21-04-08 N/A 28-04-08 N/A 12-05-08 Actual Actual AKS/HIV/NS/03/08 N/A 1,300.00 NS Post Plan N/A N/A N/A 03-03-08 17-03-08 N/A N/A Plan 1,300.00 25-03-08 N/A 07-04-08 N/A 20-04-08 Actual Actual AKS/HIV/NS/04/08 N/A 17,100.00 NS Post Plan N/A N/A N/A 05-03-08 07-04-08 N/A N/A Plan 17,100.00 21-04-08 N/A 28-04-08 N/A 12-05-08 Actual Actual AKS/HIV/NS/05/08 N/A 8,559.00 NS post Plan N/A N/A N/A 03-03-08 17-03-08 N/A N/A Plan 8,550.00 25-03-08 N/A 07-04-08 N/A 20-04-08 Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Total Cost Plan Plan Actual Actual Bid Evaluation Contract Finalization BASIC DATA Bidding Period Draft Bid Documents, including specs and quantities, draft SPN Preventive Commodities(condoms) Production (Printing ) of adapted National workplace policy Printing of NNRIMS Bulletin Norm Duration of Proc Steps Printing of AKSSP Production of BCC Materials 425990PROP0P071ement0Plan0AKS102008.xls 1 of 9 2/21/2008 4:50 AM Page 2 Procurement Plan-Goods Contract Implementation Inspecti on 12-05-08 30-05-08 12-05-08 30-05-08 12-05-08 425990PROP0P071ement0Plan0AKS102008.xls 2 of 9 2/21/2008 4:50 AM Page 3 Procurement Plan-Works Country/Organisation: Project/Programme: Loan #: Description* Package Number Lot Number Lumpsum or Bill of Quantities Procurement Method Estimated Amount in US $ Pre-or Post Qualification Prior or Post Review If Prequalification add 7-13 wks List of Contracts Total Cost 0.00 0.00 Fill gray cells only! Basic Data Norm Duration of Proc Steps 425990PROP0P071ement0Plan0AKS102008.xls 3 of 9 2/21/2008 4:50 AM Page 4 Procurement Plan-Works Country/Organisation: Project/Programme: Loan #: Description* List of Contracts Total Cost Fill gray cells only! Norm Duration of Proc Steps If Post-Review, No-objection Dates are not needed Spec Proc Notice Advert Plan vs. Actual Prep & Submission by Ex Agency No-objection Date On-line UNDB Gateway Nat Press Bid Invitation Date Bid Closing- Opening Submission Bid Eval Rpt No-objection Date Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Bid Evaluation Bidding Period Draft Bid Documents, including specs and quantities, draft SPN 425990PROP0P071ement0Plan0AKS102008.xls 4 of 9 2/21/2008 4:50 AM Page 5 Procurement Plan-Works Country/Organisation: Project/Programme: Loan #: Description* List of Contracts Total Cost Fill gray cells only! Norm Duration of Proc Steps Plan vs. Actual Contract Amount in US$ '000 Date Contract Award Date Contract Advert Date Contract Signature Mobilization Advance Payment Substantial Completion Final Acceptance Plan 1 wk 1.5-3 wks Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan 0.00 Actual 0.00 Contract Finalization Contract Implementation 425990PROP0P071ement0Plan0AKS102008.xls 5 of 9 2/21/2008 4:50 AM Page 6 Procurement Plan-Works Country/Organisation: Project/Programme: Loan #: Description* List of Contracts Total Cost Fill gray cells only! Norm Duration of Proc Steps Final Cost 0.00 0.00 425990PROP0P071ement0Plan0AKS102008.xls 6 of 9 2/21/2008 4:50 AM Page 7 Procurement Plan-Consultants 2 Country/Organisation: For Contracts under projects approved before the May 2002 Guidelines AKWA IBOM HIV?AIDS PROGRAMME DEV> PROJECT If Post-Review, No-objection Dates are not needed Credit #:3556 UNI Contract Type Description* Selection Method Lumpsum or Time-Based Estimated Amount in US$ '000 Prior/Post Review Plan vs. Actual Prep & Submission by Ex Ag No-objection Date On-line UNDB Gateway Nat Press Lead-time before shortlist Submission Date No-objection Date Plan vs. Actual Invitation Date Submission/ Opening Date Submission Evaluation Report (T) No-objection Evaluation Report (T) Opening Financial Proposals Preparation Eval Report (T) (F) Negotiations (N) Plan vs. Actual Submission Date No-objection Date Contract Amount in US$ '000 Contract Award Date Contract Advert Contra ct Signatu re Plan vs. Actual Mobilization Advance Payment Plan 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 1 - 2 wks Plan 4 to 12 wks 2 - 3 wks 0.5 - 2 wks 2 wks 1 - 2 wks 2 wks Plan 1 - 2 wks 1 - 2 wks 1 wk 1 - 3 wks Plan Actual Actual Actual Actual List of Contracts I/C lumpsum 8,550.00 post Plan N/A N/A N/A N/A N/A N/A Plan 4-03-08 21-03-08 N/A N/A N/A 03-04-080 08-04-08 Plan N/A N/A 8,550.00 15-04-08 30-05-08 22-04-08 Plan 22-04-08 Actual Actual Actual Actual CQ lumpsum 8,550.00 prior Plan N/A N/A N/A N/A N/A N/A Plan 23-04-08 02-06-08 N/A N/A N/A 14-06-08 24-06-08 Plan N/A N/A 8,550.00 27-06-08 30-11-08 30-06-08 Plan 30-06-08 Actual Actual Actual Actual TA for State partners forum IC lumpsum 17,100.00 Post Plan N/A N/A N/A N/A N/A N/A Plan 01-04-08 12-05-08 N/A N/A N/A 19-05-08 23-05-08 Plan N/A N/A 17,100.00 30-05-08 30-11-08 03-06-08 Plan 03-06-08 Actual Actual Actual Actual Training Courses for members of SPT IC lumpsum 71,000.00 Prior N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 71000 N/A N/A N/A N/A HAF 3 QCBS lumpsum 146,000.00 Prior Plan 04-03-08 13-03-08 21 -03-08 27-03-08 28-03-08 04-04-08 07-04-08 15-05-08 N/A N/A N/A 16-06-08 01-07-08 Plan N/A N/A 146,000.00 08-07-08 21-07-08 25-07-08 Plan 25-07-08 N/A CQ lumpsum 3,000.00 post Plan N/A N/A N/A N/A N/A N/A Plan 02-5-08 09-06-08 N/A N/A N/A 17-06-08 25-06-08 Plan N/A N/A 3,000.00 02-07-08 30-11-08 11-07-08 Plan 11-07-08 Actual Actual Actual Actual CQ lumpsum 7,500.00 Post Plan N/A N/A N/A N/A N/A N/A Plan 01-04-08 12-05-08 N/A N/A N/A 26-05-08 30-05-08 Plan N/A N/A 7,500.00 03-06-08 30-11-08 09-06-08 Plan 09-06-08 Actual Actual Actual Actual World AIDS DAY CQ lumpsum 8,550.00 Post Plan N/A N/A N/A N/A N/A N/A Plan 01-09-08 14-10-08 N/A N/A N/A 27-10-08 04-11-08 Plan N/A N/A 8,550.00 10-11-08 30-11-08 14-11-08 Plan 14-11-08 TA for AKS Response Review IC lumpsum 5,500.00 Post Plan N/A N/A N/A N/A N/A N/A Plan 01-04-08 12-05-08 N/A N/A N/A 19-05-08 23-05-08 N/A N/A 5,500.00 30-05-08 30-11-08 03-06-08 Plan Plan Plan CQ lumpsum 10,000.00 Post Plan N/A N/A N/A N/A N/A N/A Plan 04-03-08 21-03-08 N/A N/A N/A 03-04-08 08-04-08 N/A N/A 10,000.00 17-04-08 21-07-08 22-04-08 Actual 22-04-08 Actual Actual Plan Plan IC lumpsum 5,000.00 Post Plan N/A N/A N/A N/A N/A N/A Plan 03-04-08 21-04-08 N/A N/A N/A 30-04-08 02-05-08 Actual N/A N/A 5,000.00 12-05-08 21-07-08 19-05-08 Actual 19-05-08 Actual Actual IC lumpsum 3,500.00 Post Plan N/A N/A N/A N/A N/A N/A Plan 23-04-08 30-05-08 N/A N/A N/A 16-06-08 22-06-08 Plan N/A N/A 3,500.00 30-06-08 30-11-08 03-07-08 03-07-08 128,000.00 Actual Actual HAF 2 Grant Disbursement Plan Plan NOTE: 1- HAF 3 The technical and Financial evaluation are done the same time and shortlist is not for WB clearance NOTE: 2 HAF 2 is on- going and is only for disbursement of the grant($128000) - TA for adaptation & adoption of National workplace policy Gender mainstreaming wokshop for internet service providers TA to scale up NNRIMS at all LGAs NNRIMS training for 62 M&E officers of partners in AKS Contract Finalization Norm Duration of Proc Steps Tech. Assistance to faciltateSACA agency status Short List Consultant Proposals Proposal Evaluation and Negotiation for Projects after May 2002 Technical (T) & Financial (F) and Negotions (N) Draft Contract Start off workshop for HAF 3 beneficiaries TA for Mapping of vulnerable groups Request for EOI (where required) Preparation Request for Proposals 425990PROP0P071ement0Plan0AKS102008.xls 7 of 9 2/21/2008 4:50 AM Page 8 Procurement Plan-Consultants 2 Country/Organisation: AKWA IBOM HIV?AIDS PROGRAMME DEV> PROJECT Credit #:3556 UNI Description* List of Contracts TA for State partners forum Training Courses for members of SPT HAF 3 World AIDS DAY TA for AKS Response Review HAF 2 Grant Disbursement NOTE: 1- HAF 3 The technical and Financial evaluation are done the same time and shortlist is not for WB clearance NOTE: 2 HAF 2 is on- going and is only for disbursement of the grant($128000) - TA for adaptation & adoption of National workplace policy Gender mainstreaming wokshop for internet service providers TA to scale up NNRIMS at all LGAs NNRIMS training for 62 M&E officers of partners in AKS Norm Duration of Proc Steps Tech. Assistance to faciltateSACA agency status Start off workshop for HAF 3 beneficiaries TA for Mapping of vulnerable groups Draft Report Final Report Final Cost 10-06-08 30-09-08 N/A 14-07-08 30-08-08 8550 18-06-08 30-08-08 17100 N/A N/A N/A 01-11-08 31-07-09 146000 18-08-08 30-09-08 3000 14-07-08 30-09-08 7500 27-11-08 10-12-08 8550 16-05-08 27-06-08 10000 20-06-08 28-07-08 5000 21-07-08 20--08-08 3500 Contract Implementation 425990PROP0P071ement0Plan0AKS102008.xls 8 of 9 2/21/2008 4:50 AM Page 9 Procurement Plan-Approvals-Consultants 2 Initial Approval Update Dates of Bank Approval of Procurement Plan For Consultants 2 425990PROP0P071ement0Plan0AKS102008.xls 9 of 9 2/21/2008 4:50 AM