PROCUREMENT PLAN Updated on November 6, 2020 I. General 1. Project information: Country : INDONESIA Borrower : Republic of Indonesia Project Name : Program to Accelerate Agrarian Reform (One Map Project) Loan/Credit No. : IBRD Loan No. 8897-ID Project Implementing Agency (PIA) : Ministry of Agrarian & Spatial Planning / National Land Agency (BPN) and Geospatial Information Agency (BIG) 2. Bank’s approval Date of the procurement Plan Original : June 4, 2018 This version : November 6, 2020 3. Date of General Procurement Notice: April 2019 4. Period covered by this procurement plan: June 4, 2018 – Project Closing Date (Dec 31, 2023) 5. Exchange Rate: Only for planning purposes, 1 USD = IDR 14.000 II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Approved Selection Procurement Prior Method Threshold Review Threshold Works (including turnkey, supply & installation of plant and equipment, and PPP) International Open ≥ US$ 25 million ≥ US$ 10 million National Open at or above US$ 200k and ≥ US$ 10 million less than US$ 25 million Request for Quotation < US$ 200k N/A Direct Selection Subject to conditions as ≥ US$ 10 million per paragraph 6.8, 6.9 and 6.10 of the Procurement Regulations Goods and information technology International Open ≥ US$ 2 million ≥ US$ 2 million National Open at or above US$ 100k and ≥ US$ 2 million less than US$ 2 million Request for Quotation < US$ 100k N/A Direct Selection Subject to conditions as ≥ US$ 2 million per paragraph 6.8, 6.9 and 6.10 of the Procurement Regulations Non-Consulting Services International Open ≥ US$ 10 million ≥ US$ 2 million National Open at or above US$ 100k and ≥ US$ 2 million Type of Procurement Approved Selection Procurement Prior Method Threshold Review Threshold less than US$ 10 Request for Quotation < US$ 100k N/A Direct Selection Subject to conditions as ≥ US$ 2 million per paragraph 6.8, 6.9 and 6.10 of the Procurement Regulations 2. Pre-qualification : Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM) 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of Program to Accelerate Agrarian Reform 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary Activities (Contracts) for Goods, Works and Non-Consulting Services 1 2 3 4 5 Ref. Description Estimated Packages Review No. Cost by Bank (US$ mil.) (Prior / Post) 1. RFB-Open International Goods/IT System3)4) 6.170 1 Prior Works Non-Consulting Services 2. RFB-Open National Goods/IT System1) 3.143 2 Post Works 0.17 1 Post Non-Consulting 68.418 34 Prior/Post Services 2) 4. RFQ Goods/IT System 0.071 1 Post Works 0.016 1 Post Non-Consulting 0.222 3 Post Services 5. Direct Contracting Goods/IT System Works 1 2 3 4 5 Ref. Description Estimated Packages Review No. Cost by Bank (US$ mil.) (Prior / Post) Non-Consulting Services Total A 78.057 43 Remarks: 1) One package with 7 lots 2) 4 packages each consisting 7 lots; One package consisting 2 lots; 4 packages (23 lots) under Prior Review 3) No Domestic Preference 4) Retender B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Type of Procurement Approved Selection Procurement Prior Method Threshold Review Threshold Consultants: firms International Open (Firms) ≥ US$ 400k ≥ US$ 1 million - QCBS, QBS, LCS, FBS and CQS National Open (Firms) - < US$ 400k - QCBS, QBS, LCS, FBS and CQS Direct Selection Subject to conditions as ≥ US$ 1 million per paragraph 7.13, 7.14 and 7.15 of the Procurement Regulations Consultants: individuals Competitive Selection All ≥ US$ 300k or as stated in the procurement plan Direct Selection Subject to conditions as ≥ US$ 300k per paragraph 7.39 of the Procurement Regulations 2. Short list comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary Activities (Contracts) for Consultant Services 1 2 3 4 5 6 Ref. Description Contract Estimate Package Review No. Type d s/ by Bank Cost Position (Prior/Post) (US$ s mil.) 1. Summary of (Time- 2.331 1 Prior contracts that will Based be let under QCBS /Lump- under Sum) International Open Selection 2. Summary of (Time- 4.650 12 Post contracts that will Based be let under QCBS /Lump- under National Sum) Open Selection 3. Summary of contracts that will be let under other methods 4. Summary of (Time- 1.234 52 Post individual Based consultant /Lump- contracts that will Sum) be let under competitive selection 5. Summary of (Time- 0.748 26 Post number of Based individual /Lump- consultant Sum) contracts that will be let under Direct Selection Total 8.963 91 PROCUREMENT Indonesia : Program to Accelerate Agrarian Reform (One Map Project) PLAN General Information Country: Indonesia Bank’s Approval Date of the Original Procurement Plan: 2019-04-12 2020-11-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160661 GPN Date: Project Name: Program to Accelerate Agrarian Reform (One Map Project) Loan / Credit No: IBRD / 88970, TF / A7044 Ministry of Agrarian and Spatial Planning / National Land Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ID-ATR/BPN-108910-CW- Project Management, Pending Request for Single Stage - One 2019-12- RFB / Renovation of Archive IBRD / 88970 Institutional Development Post Open - National 165,866.00 0.00 Implementat 2019-04-27 2019-06-22 Quotations Envelope 19 Building/Modern Archive and Monitoring ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-108912-GO- Project Management, Pending Single Stage - One RFB / Procurement of upgrade IBRD / 88970 Institutional Development Prior Request for Bids Open - National 2,389,459.00 0.00 Implementati 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-01-25 Envelope office equipment and Monitoring on ID-ATR/BPN-108911-GO- RFB / Procurement of hardware for strengthening Participatory Mapping and Single Stage - One Land Information System IBRD / 88970 Prior Request for Bids Open - International 6,652,975.00 0.00 Canceled 2019-04-08 2020-02-19 2020-02-14 2020-04-30 2020-03-30 2020-05-19 2020-05-08 2020-06-29 2020-12-26 Agrarian Reform Envelope (Data Center / Disaster Recovery Center infrastructure) ID-ATR/BPN-194098-GO- RFB / Retender: Procurement of Hardware for Strengthening Under Participatory Mapping and Single Stage - One Land Information System IBRD / 88970 Prior Request for Bids Open - International 6,170,000.00 0.00 Implementati 2020-09-21 2020-10-12 2020-09-26 2020-10-14 2020-11-07 2020-12-07 2021-01-11 2021-04-11 Agrarian Reform Envelope (Data Center/Disaster on Recovery Center Infrastructure) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-103258-NC- RFB / Pilot Project Fit For Purpose : Project to Accelerate Agrarian Project Management, Reform in Kalimantan Timur Single Stage - One IBRD / 88970 Institutional Development Post Request for Bids Open - National 383,802.00 233,441.69 Signed 2019-03-15 2019-04-08 2019-03-20 2019-04-10 2019-05-09 2019-04-24 2019-05-17 2019-05-15 2019-06-20 2019-10-12 and Kalimantan Selatan Envelope and Monitoring Province Methods: Participatory Mapping (PM) and Collaborative (CO) PTSL ID-ATR/BPN-106238-NC- RFB / Pilot Project Fit For Project Management, Purpose : Single Stage - One IBRD / 88970 Institutional Development Post Request for Bids Open - National 170,968.00 69,189.96 Signed 2019-03-25 2019-04-09 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-31 2019-07-15 2019-06-19 2020-01-11 Project to Accelerate Agrarian Envelope and Monitoring Reform in Jambi Province Method: General PTSL ID-ATR/BPN-106239-NC- RFB / Pilot Project Fit For Purpose : Project to Accelerate Agrarian Project Management, Single Stage - One Reform in Kalimantan Tengah IBRD / 88970 Institutional Development Post Request for Bids Open - National 426,863.00 233,043.91 Signed 2019-03-25 2019-04-09 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-31 2019-07-15 2019-06-20 2020-01-11 Envelope and Kalimantan Barat Province and Monitoring Methods: Community Driven (CD) and Collaborative (CO) PTSL ID-ATR/BPN-106240-NC- RFB / Pilot Project Fit For Purpose Project to Accelerate Agrarian Project Management, Single Stage - One Reform in Riau and Sumatera IBRD / 88970 Institutional Development Post Request for Bids Open - National 342,880.00 232,948.36 Signed 2019-03-25 2019-04-08 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-17 2019-07-15 2019-06-18 2020-01-11 Envelope Selatan Province and Monitoring Methods: Participatory Mapping (PM) and Community Driven (CD) PTSL ID-ATR/BPN-108465-NC- RFB / Participatory Mapping with Survey (PTSL): 7 lot Under Participatory Mapping and Single Stage - One (South Sumatera, Riau, Jambi, IBRD / 88970 Post Request for Bids Open - National 9,356,886.00 0.00 Implementati 2019-06-15 2019-08-13 2019-06-20 2019-08-01 2019-09-30 2019-08-31 2019-10-23 2019-10-05 2020-03-03 Agrarian Reform Envelope West Kalimantan, Central on Kalimantan, East Kalimantan, South Kalimantan) ID-ATR/BPN-108475-NC- RFB / Quality Control for Participatory Mapping with Pending Survey (PTSL): 7 lot (South Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 1,053,482.00 0.00 Implementati 2019-06-15 2019-06-20 2019-08-01 2019-08-31 2019-10-05 2020-04-02 Sumatera, Riau, Jambi, West Agrarian Reform Envelope on Kalimantan, South Kalimantan, East Kalimantan, Central Kalimantan) Page 1 ID-ATR/BPN-108601-NC- Pending RFB / Event Organizer for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 176,407.00 0.00 Implementati 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-01-25 Technical Assessment of Agrarian Reform Envelope on Forest Boundary Demarcation ID-ATR/BPN-108603-NC- Pending RFB / Event Organizer for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 96,429.00 0.00 Implementati 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-01-25 Technical Assessment of Agrarian Reform Envelope on Document Digitation ID-ATR/BPN-108605-NC- RFB / Procurement of IT Pending Participatory Mapping and Single Stage - One Support for Scanning and IBRD / 88970 Post Request for Bids Open - National 1,060,979.00 0.00 Implementati 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Agrarian Reform Envelope Digital Filing (Digitalization): 7 on lots ID-ATR/BPN-108606-NC- RFB / Event Organizer for Project Management, Pending Single Stage - One Workshop Procurement, IBRD / 88970 Institutional Development Post Request for Bids Open - National 140,601.00 0.00 Implementati 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Envelope Financial Management and and Monitoring on Project Management ID-ATR/BPN-108607-NC- RFB / Event Organizer for Project Management, Pending Single Stage - One Workshop International IBRD / 88970 Institutional Development Post Request for Bids Open - National 71,429.00 0.00 Implementati 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Envelope Experience on Single Land and Monitoring on Administration ID-ATR/BPN-108628-NC- Project Management, Pending Single Stage - One RFB / Event Organizer for IBRD / 88970 Institutional Development Post Request for Bids Open - National 54,739.00 0.00 Implementati 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Envelope Workshop Geospatial Industry and Monitoring on ID-ATR/BPN-108631-NC- Project Management, Pending Single Stage - One RFB / Event Organizer for IBRD / 88970 Institutional Development Post Request for Bids Open - National 714,286.00 0.00 Implementati 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Envelope Public Campaign and Monitoring on ID-ATR/BPN-108632-NC- Pending RFB / Event Organizer for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 142,857.00 0.00 Implementati 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Implementation Assessment Agrarian Reform Envelope on on Pres Decree No. 86/2018 ID-ATR/BPN-108602-NC- Under Participatory Mapping and Single Stage - One RFB / Forest Boundary IBRD / 88970 Post Request for Bids Open - National 1,505,248.00 0.00 Implementati 2019-06-01 2020-02-20 2020-03-20 2020-03-31 2020-04-27 2020-10-24 Agrarian Reform Envelope Demarcation: 5 lots on ID-ATR/BPN-202001-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Prior Request for Bids Open - National 3,100,000.00 2,324,630.07 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-24 2020-12-04 Agrarian Reform Envelope (220.000 parcel with 5 lots) of South Sumatera 2020 ID-ATR/BPN-202002-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Prior Request for Bids Open - National 5,000,000.00 3,523,222.39 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-28 2020-12-04 Agrarian Reform Envelope (280.000 parcel with 7 lots) of West Kalimantan 2020 ID-ATR/BPN-202003-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Prior Request for Bids Open - National 5,000,000.00 3,724,942.67 Signed 2020-04-27 2020-05-04 2020-05-01 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-06 2020-09-11 2020-12-03 Agrarian Reform Envelope (280.000 parcel with 6 lots) of South Kalimantan 2020 ID-ATR/BPN-202004-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Prior Request for Bids Open - National 3,900,000.00 2,815,680.48 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-23 2020-12-04 Agrarian Reform Envelope (220.000 parcel with 5 lots) of Central Kalimantan 2020 ID-ATR/BPN-177786-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Post Request for Bids Open - National 1,670,000.00 0.00 Implementati 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-06-29 2020-10-27 Agrarian Reform Envelope (90.000 parcel with 2 lots) of on Riau 2020 ID-ATR/BPN-177794-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Post Request for Bids Open - National 1,550,000.00 0.00 Implementati 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-06-29 2020-10-27 Agrarian Reform Envelope (110.000 parcel with 3 lots) of on Jambi 2020 ID-ATR/BPN-177789-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Post Request for Bids Open - National 1,850,000.00 0.00 Implementati 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-06-29 2020-10-27 Agrarian Reform Envelope (100.000 parcel with 2 lots) of on East Kalimantan 2020 ID-ATR/BPN-177801-NC- RFB / Quality Control for Pending Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 258,000.00 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-06-15 2020-07-06 2020-11-03 Agrarian Reform Envelope Survey (PTSL) of South on Sumatera 2020 ID-ATR/BPN-177796-NC- Pending RFB / Quality Control for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 106,000.00 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-06-15 2020-07-06 2020-11-03 Participatory Mapping with Agrarian Reform Envelope on Survey (PTSL) of Riau 2020 ID-ATR/BPN-177803-NC- Pending RFB / Quality Control for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 130,000.00 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-06-15 2020-07-06 2020-11-03 Participatory Mapping with Agrarian Reform Envelope on Survey (PTSL) of Jambi 2020 ID-ATR/BPN-177806-NC- RFB / Quality Control for Pending Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 348,000.00 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-07-29 2020-11-26 Agrarian Reform Envelope Survey (PTSL) of West on Kalimantan 2020 Page 2 ID-ATR/BPN-177799-NC- RFB / Quality Control for Pending Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 348,000.00 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-06-15 2020-07-06 2020-11-03 Agrarian Reform Envelope Survey (PTSL) of South on Kalimantan 2020 ID-ATR/BPN-177804-NC- RFB / Quality Control for Pending Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 125,000.00 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-06-15 2020-07-06 2020-11-03 Agrarian Reform Envelope Survey (PTSL) of East on Kalimantan 2020 ID-ATR/BPN-177809-NC- RFB / Quality Control for Pending Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 273,000.00 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-06-15 2020-07-06 2020-11-03 Agrarian Reform Envelope Survey (PTSL) of Central on Kalimantan 2020 ID-ATR/BPN-188254-NC- Pending Participatory Mapping and Single Stage - One RFB / Peta Tematik IBRD / 88970 Post Request for Bids Open - National 1,810,803.33 0.00 Implementati 2020-08-12 2020-08-17 2020-09-28 2020-10-28 2020-11-25 2020-12-31 Agrarian Reform Envelope Pertanahan dan Ruang PTPR on ID-ATR/BPN-177811-NC- RFB / Procurement of IT Pending Support for Scanning and Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 1,698,472.00 0.00 Implementati 2020-04-27 2020-05-02 2020-06-13 2020-07-13 2020-08-10 2020-12-08 Digital Filing (Digitalization) Agrarian Reform Envelope on 2020 7 (seven) Provinces / 7 (seven) Lot ID-ATR/BPN-192782-NC- Pending RFQ / Event Organizer (EO) for Participatory Mapping and Request for Single Stage - One IBRD / 88970 Post Limited 121,000.00 0.00 Implementati 2020-08-08 2020-09-19 2020-11-18 Forest Boundary Demarcation Agrarian Reform Quotations Envelope on Coordination Meetings ID-ATR/BPN-204226-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Phase-4 IBRD / 88970 Post Request for Bids Open - National 1,689,722.00 0.00 Implementati 2020-11-06 2020-11-11 2020-12-23 2021-01-22 2021-02-26 2021-07-26 Agrarian Reform Envelope (140.000 parcel) of Riau 2021 on - (3 Lots) ID-ATR/BPN-204231-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Phase IBRD / 88970 Post Request for Bids Open - National 1,736,319.00 0.00 Implementati 2020-11-06 2020-11-11 2020-12-23 2021-01-22 2021-02-26 2021-07-26 Agrarian Reform Envelope (110.000 parcel) of East on Kalimantan 2021 - ( 3 Lots) ID-ATR/BPN-203978-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Phase-4 IBRD / 88970 Prior Request for Bids Open - National 3,620,833.00 0.00 Implementati 2020-11-06 2020-11-11 2020-12-23 2021-01-22 2021-02-26 2021-07-26 Agrarian Reform Envelope (300.000 parcel) of South on Sumatera 2021 - (7 Lots) ID-ATR/BPN-204229-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Phase-2 IBRD / 88970 Prior Request for Bids Open - National 2,655,277.00 0.00 Implementati 2020-11-06 2020-11-11 2020-12-23 2021-01-22 2021-02-26 2021-07-26 Agrarian Reform Envelope (220.000 parcel) of Jambi on 2021 - (6 Lots) ID-ATR/BPN-203979-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Phase IBRD / 88970 Prior Request for Bids Open - National 4,735,416.00 0.00 Implementati 2020-11-06 2020-11-11 2020-12-23 2021-01-22 2021-02-26 2021-07-26 Agrarian Reform Envelope (300.000 parcel) of South on Kalimantan 2021 (8 Lots) ID-ATR/BPN-204232-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) phase IBRD / 88970 Prior Request for Bids Open - National 3,472,638.00 0.00 Implementati 2020-11-06 2020-11-11 2020-12-23 2021-01-22 2021-02-26 2021-07-26 Agrarian Reform Envelope (220.000 parcel) of Central on Kalimantan 2021 - (5 Lots) ID-ATR/BPN-203977-NC- RFB / Quality Control for Pending Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 1,979,166.00 0.00 Implementati 2021-01-05 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-09-24 Agrarian Reform Envelope Survey Phase 4 (PTSL) in 7 on Provinces FY 2021 (7 Lots) ID-ATR/BPN-203980-NC- Pending Participatory Mapping and Single Stage - One RFB / Forest Area Boundary IBRD / 88970 Post Request for Bids Open - National 1,162,525.00 0.00 Implementati 2021-01-05 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-07-13 Agrarian Reform Envelope Situation Map FY 2021 (5 on Lots) ID-ATR/BPN-203975-NC- Pending RFB / Procurement of Participatory Mapping and Single Stage - One IBRD / 88970 Prior Request for Bids Open - National 2,975,000.00 0.00 Implementati 2020-12-01 2020-12-06 2021-01-17 2021-02-16 2021-03-23 2021-09-19 Digitalization in 7 Provinces Agrarian Reform Envelope on FY2021 (7 Lots) ID-ATR/BPN-204240-NC- Pending RFB / Event Organizer for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 207,077.00 0.00 Implementati 2021-01-05 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-06-11 Evaluation Meeting Forest Agrarian Reform Envelope on Area Boundary in 5 Provinces ID-ATR/BPN-204227-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Phase-2 IBRD / 88970 Prior Request for Bids Open - National 5,208,958.00 0.00 Implementati 2020-11-23 2020-11-28 2021-01-09 2021-02-08 2021-03-15 2021-08-12 Agrarian Reform Envelope (330.000 parcel) of West on Kalimantan 2021 - (7 Lots) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-106571-CS- QCBS / Method Analysis and Project Management, Quality And Cost- Pending Quality Control of Pilot Project IBRD / 88970 Institutional Development Post Open - National 128,571.00 0.00 2019-06-03 2019-06-24 2019-08-07 2019-09-04 2019-10-04 2019-11-08 2019-12-13 2020-12-12 Based Selection Implementation Fit For Purpose Cadastral and Monitoring Mapping Page 3 ID-ATR/BPN-108901-CS- QCBS / Consulting Services Participatory Mapping and Quality And Cost- Pending for Development of Land IBRD / 88970 Prior Open - International 2,331,034.00 0.00 2019-04-08 2019-04-29 2019-06-12 2019-07-10 2019-08-09 2019-09-13 2019-10-18 2020-10-17 Agrarian Reform Based Selection Implementation Information System, portal and e-Services ID-ATR/BPN-108902-CS- QCBS / Pilot Project Analysis Project Management, Quality And Cost- Pending Consultant and Data Quality IBRD / 88970 Institutional Development Post Open - National 128,571.00 0.00 2019-04-08 2019-04-29 2019-06-12 2019-07-10 2019-08-09 2019-09-13 2019-10-18 2020-10-17 Based Selection Implementation Control for Participatory and Monitoring Mapping ID-ATR/BPN-108903-CS- Project Management, QCBS / Legal and Institutional Quality And Cost- Pending IBRD / 88970 Institutional Development Post Open - National 85,714.00 0.00 2019-05-01 2019-05-22 2019-07-05 2019-08-02 2019-09-01 2019-10-06 2019-11-10 2020-11-09 Framework Consulting Based Selection Implementation and Monitoring Services ID-ATR/BPN-108906-CS- Project Management, QCBS / Vulnerability Mapping, Quality And Cost- Pending IBRD / 88970 Institutional Development Post Open - National 321,429.00 0.00 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 social monitoring and impact Based Selection Implementation and Monitoring assessment ID-ATR/BPN-108907-CS- QCBS / Consulting Services Project Management, Quality And Cost- Pending for Project Management IBRD / 88970 Institutional Development Post Open - National 142,857.00 0.00 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 Based Selection Implementation Information System and Monitoring Development ID-ATR/BPN-108908-CS- Project Management, QCBS / Consulting Services Quality And Cost- Pending IBRD / 88970 Institutional Development Post Open - International 607,143.00 0.00 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 for Communication and Public Based Selection Implementation and Monitoring Relations ID-ATR/BPN-116152-CS- Geospatial Data QCBS / Consulting Services Infrastructure for Quality And Cost- Pending TF / A7044 Post Open - National 107,143.00 0.00 2019-06-24 2019-07-15 2019-07-29 2019-08-26 2019-09-02 2019-09-12 2019-10-03 2020-03-31 for Review Geospatial Data Environmental and Natural Based Selection Implementation Infrastructure an Services Resource Management INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-108914-CS- Project Management, Individual Pending INDV / Project Management IBRD / 88970 Institutional Development Post Consultant Open 37,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Advisor and Monitoring Selection ID-ATR/BPN-108917-CS- Project Management, Individual Pending INDV / Safeguards IBRD / 88970 Institutional Development Post Consultant Open 30,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Coordinator and Monitoring Selection ID-ATR/BPN-108918-CS- Project Management, Individual Pending INDV / Monitoring and IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Evaluation Specialist and Monitoring Selection ID-ATR/BPN-108919-CS- Project Management, Individual Pending INDV / Communication IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-108920-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 22,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / ICT specialist Implementation and Monitoring Selection ID-ATR/BPN-108921-CS- Project Management, Individual Pending INDV / Legal expert ( IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation consultant on land law policy) and Monitoring Selection Project Management, Individual ID-ATR/BPN-108922-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 56,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / Liasion PCC Implementation and Monitoring Selection ID-ATR/BPN-108923-CS- Project Management, Individual Pending INDV / Strategic Planning IBRD / 88970 Institutional Development Post Consultant Open 125,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Specialist (International) and Monitoring Selection ID-ATR/BPN-108924-CS- Project Management, Individual INDV / Social and Pending IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Environmental Specialist for Implementation and Monitoring Selection Pilot Participatory Mapping Project Management, Individual ID-ATR/BPN-108925-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 12,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / FM Assistant Implementation and Monitoring Selection Project Management, Individual ID-ATR/BPN-108926-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 12,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / Procurement Assistant Implementation and Monitoring Selection ID-ATR/BPN-108927-CS- Project Management, Individual Pending INDV / Junior Public IBRD / 88970 Institutional Development Post Consultant Open 12,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Awareness Specilaist and Monitoring Selection ID-ATR/BPN-108928-CS- Project Management, Individual Pending INDV / Junior Public IBRD / 88970 Institutional Development Post Consultant Open 52,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Awareness Specilaist and Monitoring Selection ID-ATR/BPN-108929-CS- Project Management, Individual Pending INDV / Regional Project IBRD / 88970 Institutional Development Post Consultant Open 140,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Technical Advisor and Monitoring Selection ID-ATR/BPN-108930-CS- Project Management, Individual Pending INDV / Regional Project IBRD / 88970 Institutional Development Post Consultant Open 140,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Operations Advisor and Monitoring Selection Page 4 Project Management, Individual ID-ATR/BPN-108931-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 20,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / Project Administrator Implementation and Monitoring Selection ID-ATR/BPN-108915-CS- Project Management, Individual Pending INDV / Financial Management IBRD / 88970 Institutional Development Post Consultant Open 30,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Specialist and Monitoring Selection ID-ATR/BPN-116146-CS- Project Management, Individual Pending INDV / Project Management TF / A7044 Institutional Development Post Consultant Open 26,786.00 0.00 2018-12-03 2018-12-22 2018-12-24 2019-01-01 2019-05-31 Implementation Advisor and Monitoring Selection ID-ATR/BPN-116153-CS- Project Management, Individual Pending INDV / Communication TF / A7044 Institutional Development Post Consultant Open 14,286.00 0.00 2019-02-01 2019-02-23 2019-03-02 2019-03-15 2019-05-31 Implementation Specialist and Monitoring Selection ID-ATR/BPN-116154-CS- Project Management, Individual Pending INDV / Safeguards TF / A7044 Institutional Development Post Consultant Open 8,571.00 0.00 2019-01-02 2019-01-19 2019-01-22 2019-02-01 2019-05-31 Implementation Coordinator and Monitoring Selection ID-ATR/BPN-116151-CS- Project Management, Individual Pending INDV / Monitoring & TF / A7044 Institutional Development Post Consultant Open 7,500.00 0.00 2019-02-18 2019-02-26 2019-02-27 2019-03-01 2019-05-31 Implementation Evaluation Specilaist and Monitoring Selection ID-ATR/BPN-116145-CS- Project Management, Individual Pending INDV / Junior Public TF / A7044 Institutional Development Post Consultant Open 6,429.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-07 Implementation Awareness Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-116148-CS- Pending TF / A7044 Institutional Development Post Consultant Open 10,714.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-07 INDV / PCC Liaison Officer Implementation and Monitoring Selection Project Management, Individual ID-ATR/BPN-116147-CS- Pending TF / A7044 Institutional Development Post Consultant Open 12,857.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-07 INDV / Legal Advisor Implementation and Monitoring Selection ID-ATR/BPN-116150-CS- Project Management, Individual Pending INDV / Survey and Mapping TF / A7044 Institutional Development Post Consultant Open 12,429.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-31 Implementation Specialist for Pilot Project and Monitoring Selection ID-ATR/BPN-116149-CS- Project Management, Individual Pending INDV / Assistant Safeguard TF / A7044 Institutional Development Post Consultant Open 3,750.00 0.00 2019-05-24 2019-06-07 2019-06-09 2019-06-13 2019-11-30 Implementation Coordinator and Monitoring Selection Project Management, Individual ID-ATR/BPN-108916-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 30,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / Procurement Specialist Implementation and Monitoring Selection ID-ATR/BPN-177827-CS- Project Management, Individual Pending INDV / Project Management IBRD / 88970 Institutional Development Post Consultant Direct 59,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Advisor and Monitoring Selection ID-ATR/BPN-177834-CS- Project Management, Individual Pending INDV / Financial Management IBRD / 88970 Institutional Development Post Consultant Direct 37,250.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-177837-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 45,500.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / Procurement Specialist Implementation and Monitoring Selection ID-ATR/BPN-178294-CS- Project Management, Individual Pending INDV / Monitoring and IBRD / 88970 Institutional Development Post Consultant Direct 28,200.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Evaluation Consultant and Monitoring Selection ID-ATR/BPN-177842-CS- Project Management, Individual Pending INDV / Safeguards IBRD / 88970 Institutional Development Post Consultant Direct 24,900.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Coordinator and Monitoring Selection ID-ATR/BPN-177843-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 1 (Sumsel) and Monitoring Selection ID-ATR/BPN-178145-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 2 (Jambi) and Monitoring Selection ID-ATR/BPN-178144-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 3 (Riau) and Monitoring Selection ID-ATR/BPN-178143-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 4 (Kalbar) and Monitoring Selection ID-ATR/BPN-178122-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 5 (Kalteng) and Monitoring Selection ID-ATR/BPN-178140-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 6 (Kaltim) and Monitoring Selection ID-ATR/BPN-178141-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 7 (Kalsel) and Monitoring Selection ID-ATR/BPN-178299-CS- Project Management, Individual INDV / Program Officer (5 Pending IBRD / 88970 Institutional Development Post Consultant Direct 40,000.00 0.00 2020-01-15 2020-01-18 2020-01-19 2020-01-27 2020-12-31 Person) and Access Reform Implementation and Monitoring Selection Officer (1 Person) Project Management, Individual ID-ATR/BPN-178296-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 33,100.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / PCC Liaison Adviser Implementation and Monitoring Selection Page 5 ID-ATR/BPN-177840-CS- Project Management, Individual Pending INDV / Communication IBRD / 88970 Institutional Development Post Consultant Direct 29,000.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-178302-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 21,000.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / PCC liaison Officer Implementation and Monitoring Selection ID-ATR/BPN-177836-CS- Project Management, Individual Pending INDV / Financial Management IBRD / 88970 Institutional Development Post Consultant Direct 21,000.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Assistant and Monitoring Selection Project Management, Individual ID-ATR/BPN-177839-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 21,000.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / Procurement Assistant Implementation and Monitoring Selection Project Management, Individual ID-ATR/BPN-178148-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 12,500.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / Graphic Designer Implementation and Monitoring Selection ID-ATR/BPN-177831-CS- Project Management, Individual Pending INDV / Project Management IBRD / 88970 Institutional Development Post Consultant Open 13,800.00 0.00 2019-12-20 2020-02-07 2020-02-28 2020-03-27 2020-12-31 Implementation Assistant and Monitoring Selection Project Management, Individual ID-ATR/BPN-178119-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 37,250.00 0.00 2019-12-20 2019-12-26 2019-12-28 2020-01-02 2020-12-31 INDV / Legal Specialist Implementation and Monitoring Selection ID-ATR/BPN-181543-CS- Project Management, Individual Pending INDV / Survey and Mapping IBRD / 88970 Institutional Development Post Consultant Open 11,750.00 0.00 2020-07-01 2020-08-04 2020-08-11 2020-09-01 2021-02-28 Implementation Specialist and Monitoring Selection ID-ATR/BPN-178301-CS- Project Management, Individual Pending INDV / Transformation Digital IBRD / 88970 Institutional Development Post Consultant Direct 6,200.00 0.00 2020-01-15 2020-01-18 2020-01-19 2020-01-27 2020-07-25 Implementation Specialist [National] and Monitoring Selection ID-ATR/BPN-178298-CS- Project Management, Individual Pending INDV / Land Tenure Expert IBRD / 88970 Institutional Development Post Consultant Open 10,400.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-22 2020-10-19 Implementation (National) and Monitoring Selection ID-ATR/BPN-178297-CS- Project Management, Individual Pending INDV / Land Tenure Expert IBRD / 88970 Institutional Development Post Consultant Open 51,800.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-22 2020-10-19 Implementation (International ) and Monitoring Selection ID-ATR/BPN-178150-CS- Project Management, Individual Pending INDV / Knowledge IBRD / 88970 Institutional Development Post Consultant Open 10,400.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-08 2020-12-31 Implementation Management & Data Officer and Monitoring Selection ID-ATR/BPN-187783-CS- Project Management, Individual Pending INDV / Spatial Analyst for IBRD / 88970 Institutional Development Post Consultant Open 51,800.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-15 2020-12-31 Implementation Land Parcels Sp. and Monitoring Selection ID-ATR/BPN-178295-CS- Project Management, Individual Pending INDV / Transformation Digital IBRD / 88970 Institutional Development Post Consultant Open 51,800.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-22 2020-10-19 Implementation Specialist [International] and Monitoring Selection ID-ATR/BPN-178300-CS- Project Management, Individual Pending INDV / Capacity Building IBRD / 88970 Institutional Development Post Consultant Open 2,800.00 0.00 2020-06-05 2020-07-24 2020-08-07 2020-09-11 2020-10-01 Implementation Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-181544-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 21,000.00 0.00 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2020-08-28 INDV / Consultant 3D Implementation and Monitoring Selection ID-ATR/BPN-187781-CS- Project Management, Individual INDV / Legal Specialist Pending IBRD / 88970 Institutional Development Post Consultant Open 10,417.00 0.00 2020-08-03 2020-09-21 2020-10-05 2020-11-02 2020-12-31 (Supporting for Implementation and Monitoring Selection Transformation digital) ID-ATR/BPN-187780-CS- Project Management, Individual INDV / Financial Specialist Pending IBRD / 88970 Institutional Development Post Consultant Open 10,417.00 0.00 2020-08-03 2020-09-21 2020-10-05 2020-11-02 2020-12-31 (Supporting for Implementation and Monitoring Selection Transformation digital) ID-ATR/BPN-187777-CS- Project Management, Individual INDV / IT Specialist Pending IBRD / 88970 Institutional Development Post Consultant Open 10,417.00 0.00 2020-08-03 2020-09-21 2020-10-05 2020-11-02 2020-12-31 (Supporting for Implementation and Monitoring Selection Transformation digital) ID-ATR/BPN-187797-CS- Project Management, Individual INDV / Feedback and Pending IBRD / 88970 Institutional Development Post Consultant Open 8,333.00 0.00 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2020-12-31 Grievance Redress Mechanism Implementation and Monitoring Selection (FGRM) Officer ID-ATR/BPN-187776-CS- INDV / Project Planning and Project Management, Individual Management Specialist IBRD / 88970 Institutional Development Post Consultant Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 (Supporting for and Monitoring Selection Transformation Digital) ID-ATR/BPN-187772-CS- INDV / Project Risk Project Management, Individual Management Specialist IBRD / 88970 Institutional Development Post Consultant Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 (Supporting for and Monitoring Selection Transformation Digital) ID-ATR/BPN-187770-CS- INDV / Land Information Project Management, Individual System Development IBRD / 88970 Institutional Development Post Consultant Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 Specialist (Supporting for and Monitoring Selection Transformation Digital) ID-ATR/BPN-187774-CS- Project Management, Individual INDV / Digital Communication Under IBRD / 88970 Institutional Development Post Consultant Direct 52,083.00 0.00 2020-08-03 2020-08-24 2020-08-13 2020-08-27 2020-09-24 2020-12-31 Specialist (Supporting for Implementation and Monitoring Selection Transformation Digital) Page 6 ID-ATR/BPN-187799-CS- Project Management, Individual Pending INDV / Administrator Support IBRD / 88970 Institutional Development Post Consultant Open 21,875.00 0.00 2020-08-07 2020-09-25 2020-10-09 2020-11-06 2020-12-31 Implementation at 7 Provinces (7 Packages) and Monitoring Selection Project Management, Individual ID-ATR/BPN-201161-CS- Pending TF / A7044 Institutional Development Post Consultant Direct 6,944.00 0.00 2020-10-25 2020-11-02 2020-11-07 2020-11-15 2020-12-30 INDV / Risk Screening Support Implementation and Monitoring Selection ID-ATR/BPN-203395-CS- Project Management, Individual Pending INDV / Project Manager for IBRD / 88970 Institutional Development Post Consultant Open 10,417.00 0.00 2020-09-01 2020-09-27 2020-10-04 2020-10-25 2020-12-31 Implementation PMO Digital Transformation and Monitoring Selection ID-ATR/BPN-203397-CS- Project Management, Individual INDV / Safeguard Specialist Pending IBRD / 88970 Institutional Development Post Consultant Open 3,125.00 0.00 2020-09-01 2020-09-27 2020-10-11 2020-11-01 2020-12-31 for Pilot Project Land Implementation and Monitoring Selection Redistribution ID-ATR/BPN-203401-CS- Project Management, Individual INDV / Project Management Pending IBRD / 88970 Institutional Development Post Consultant Open 3,160.00 0.00 2020-09-01 2020-09-27 2020-10-11 2020-11-01 2020-12-31 Assistant for Pilot Project Land Implementation and Monitoring Selection Redistribution ID-ATR/BPN-203400-CS- Project Management, Individual INDV / Communication Pending IBRD / 88970 Institutional Development Post Consultant Open 3,125.00 0.00 2020-09-01 2020-09-27 2020-10-11 2020-11-01 2020-12-31 Specialit for Pilot Project Land Implementation and Monitoring Selection Redistribution ID-ATR/BPN-203402-CS- Project Management, Individual Pending INDV / Procurement Assistant- IBRD / 88970 Institutional Development Post Consultant Open 3,472.00 0.00 2020-10-01 2020-10-27 2020-11-10 2020-12-01 2020-12-31 Implementation 2 (short term) and Monitoring Selection Project Management, Individual ID-ATR/BPN-204257-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2020-11-13 2021-01-01 2021-01-15 2021-02-05 2021-12-22 INDV / Public Policy SP. (PMU) Implementation and Monitoring Selection Project Management, Individual ID-ATR/BPN-204256-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2020-11-13 2021-01-01 2021-01-15 2021-02-05 2021-12-22 INDV / Stategic Planner (PMU) Implementation and Monitoring Selection ID-ATR/BPN-204249-CS- Project Management, Individual INDV / Business Process and Pending IBRD / 88970 Institutional Development Post Consultant Open 12,153.00 0.00 2021-01-05 2021-02-23 2021-03-09 2021-04-06 2021-11-02 Regular Consultant for Land Implementation and Monitoring Selection Redistribution ID-ATR/BPN-204248-CS- Project Management, Individual INDV / Land Use Planning Pending IBRD / 88970 Institutional Development Post Consultant Open 4,896.00 0.00 2021-01-05 2021-02-23 2021-03-09 2021-03-30 2021-06-28 Consultant for Land Implementation and Monitoring Selection Redistribution ID-ATR/BPN-204250-CS- Project Management, Individual INDV / Community Pending IBRD / 88970 Institutional Development Post Consultant Open 8,160.00 0.00 2021-01-05 2021-02-23 2021-03-09 2021-04-06 2021-09-03 Empowerment Consultant for Implementation and Monitoring Selection Land Redistribution ID-ATR/BPN-204251-CS- Project Management, Individual INDV / Social Safeguard and Pending IBRD / 88970 Institutional Development Post Consultant Open 4,896.00 0.00 2021-01-05 2021-02-23 2021-03-09 2021-03-30 2021-06-28 Complaint Handling for Land Implementation and Monitoring Selection Redistribution ID-ATR/BPN-204246-CS- Project Management, Individual INDV / TORA Potential Pending IBRD / 88970 Institutional Development Post Consultant Open 114,236.00 0.00 2020-12-01 2021-01-19 2021-02-02 2021-02-23 2021-12-20 Analysis Consultant for Land Implementation and Monitoring Selection Redistribution (7 Consultants) ID-ATR/BPN-204245-CS- INDV / Agrarian Reform Project Management, Individual Pending Assessment Consultant for IBRD / 88970 Institutional Development Post Consultant Open 48,958.00 0.00 2020-12-01 2021-01-19 2021-02-02 2021-02-23 2021-12-20 Implementation Land Redistribution (3 and Monitoring Selection Consultants) ID-ATR/BPN-204244-CS- Project Management, Individual Pending INDV / Bilingual Secretary for IBRD / 88970 Institutional Development Post Consultant Open 5,347.00 0.00 2021-01-05 2021-02-23 2021-03-16 2021-04-20 2021-11-16 Implementation Land Redistribution and Monitoring Selection ID-ATR/BPN-204254-CS- Project Management, Individual INDV / Supporting Staffs for Pending IBRD / 88970 Institutional Development Post Consultant Open 7,778.00 0.00 2021-01-05 2021-02-23 2021-03-09 2021-03-30 2021-10-26 Land Redistribution (2 Implementation and Monitoring Selection Consultants) Page 7