Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan: Updated Procurement Plan, M 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Agricultural Growth Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2017-08-18 2020-02-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148591 GPN Date: Project Name: Second Agricultural Growth Project Loan / Credit No: IDA / 56050 Executing Agency(ies): Amhara Agricultural Growth Program - Regional Program Coordination Unit WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAGP RPCU-26109-CW- RFB / Construction of Small Scale Irrigation at (Elen Burie Worda and Leza Jabitehena Worda) and Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,481,454.00 1,169,581.86 Signed 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2018-06-13 Debilitation of two Existing Envelope Small Scale Irrigation at (Enfiranze Bahirdar Zuria and Karmuki South Achefer Worda). ET-AAGP RPCU-26207-CW- RFB / Construction of three Small Scale Irrigation at Est Gojam Zone Muga-3 Revere Single Stage - One Debaytelatgen worda and IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,287,109.00 1,010,614.82 Signed 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Envelope Minasie Revere Enmay worda and West Gojame Zone Gunagune-2 Revere Jabitehena worda. ET-AAGP RPCU-26214-CW- RFB / Construction of three new Small scale Irrigation ( Sebatwodel ReverE at South Single Stage - One Gonder Zone Fata worda, IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 2,304,347.00 1,724,296.29 Signed 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Envelope Terngomeder Revere and Yogofolfoy Revere at North Shoa Zone Moretna Jeru WORDA. ET-AAGP RPCU-26215-CW- RFB / Construction of three New Irrigation Awi Zone Guagusa shekudad worda Single Stage - One Sebatayna Revere,Geray-3 IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 2,347,826.00 1,547,734.49 Signed 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Envelope Revere and Laheshembekuma Revere at West Gojam Zone Jabitehena Worda. ET-AAGP RPCU-26217-CW- RFB / Construction two new Irrigation at Gumara rever Awi Zone Ankesha worda and Lomitule Rever at Weast Gojam Zone Yelmana Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,782,607.00 798,832.22 Signed 2017-10-30 2017-11-04 2017-12-16 2018-01-15 2018-02-19 2018-08-18 Worda and Rehabilitation of Envelope three Existing Small scale Irrigation at Dim Revere Awi Zone Zigem woreda, Adagihoye Revere North Shoa Zone Page 1 ET-AAGP RPCU-26089-CW- CDD / Construction of Community Suspended Bridge (Gula Agriculture Marketing and IDA / 56050 Prior Driven Direct 84,284.00 84,284.00 Signed 2017-09-05 2017-09-10 2017-10-15 2018-02-12 Revere Bridge) at West Value Chains Development Gojam Zone Denbecha Worda. ET-AAGP RPCU-26091-CW- CDD / Construction of Community Agriculture Marketing and suspended bridge (Abaye IDA / 56050 Prior Driven Direct 48,707.00 48,707.00 Signed 2017-09-05 2017-09-10 2017-10-15 2018-02-12 Value Chains rever Afaye Kebele) at South Development Gonder Zone Dera Worda. ET-AAGP RPCU-26086-CW- CDD / Construction of Community Agriculture Marketing and Suspended Bridge (Gizane IDA / 56050 Prior Driven Direct 110,153.00 110,153.00 Signed 2017-09-05 2017-09-10 2017-10-15 2018-02-12 Value Chains Revere Bridge) at Awi Zone Development Dangela Worda. ET-AAGP RPCU-26055-CW- DIR / Construction of Community Suspended Bridge (Rebe Agriculture Marketing and IDA / 56050 Prior Driven Direct 72,602.00 72,602.00 Signed 2017-09-05 2017-09-10 2017-10-15 2018-02-12 Revere Bridge Limado Value Chains Development Kebele) at North Gonder Zone Farta Wrda ET-AAGP RPCU-26092-CW- CDD / Construction of Community Agriculture Marketing and Suspended Bridge ( Mugara IDA / 56050 Prior Driven Direct 47,622.00 47,622.00 Signed 2017-09-05 2017-09-10 2017-10-15 2018-02-12 Value Chains Revere Bridge) at East Development Gojam Zone Dejen Worda. ET-AAGP RPCU-26050-CW- DIR / Construction of Community Suspended Bridge (Gelgel Agriculture Marketing and IDA / 56050 Prior Driven Direct 55,810.00 55,810.00 Signed 2017-09-05 2017-09-10 2017-10-15 2018-02-12 cheye River bridge Yesarbate Value Chains Development kebele) at East Gojam Zone Enarje Enawga Woreda ET-AAGP RPCU-26043-CW- DIR / Construction of Community suspended Bridge (Abay Agriculture Marketing and IDA / 56050 Prior Driven Direct 98,092.00 98,092.00 Signed 2017-09-05 2017-09-10 2017-10-15 2018-02-12 River Volva Kebele) at Value Chains Development w/Gojame zone of North Achefer Woreda. ET-AAGP RPCU-26038-CW- DIR / Construction of Community Agriculture Marketing and Suspended Bridge(Dankom IDA / 56050 Prior Driven Direct 73,310.00 73,310.00 Signed 2017-09-05 2017-09-10 2017-10-15 2018-02-12 Value Chains River Bridge) at Awi Zone Development Zigem Woreda. ET-AAGP RPCU-26106-CW- RFB / Construction of three Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 84,284.00 0.00 Canceled 2017-10-25 2017-10-30 2017-12-11 2018-01-10 2018-02-14 2018-08-13 ware house for Cooperative Value Chains Envelope Unions ET-AAGP RPCU-31652-CW- RFB / Construction of Fish Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 397,638.00 524,877.44 Signed 2017-11-30 2017-12-05 2018-01-04 2018-02-03 2018-02-28 2018-07-28 Hatchery at Regional live Services Envelope stock Agency. AM-AGP-CU-NCB-MKT/17 / Construction of primary Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 407,700.00 408,604.60 Signed 2017-03-10 2017-03-15 2017-04-14 2017-05-14 2017-06-03 2017-10-01 market at Andabate and Value Chains Envelope Mekoye Page 2 ET-AAGP RPCU-62928-CW- RFB / Construction of 19 Road side Market Center at Gonder, Dera, Chilga, Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 1,300,000.00 707,493.84 Signed 2018-05-22 2018-05-27 2018-06-26 2018-07-26 2018-08-24 2018-12-22 Bahirdar, S/Achefer, Value Chains Envelope Dangla, Chagni, Jabithina D/markose and Dejen with Three Lots. BOIED/AGP-2/W-12/2018 / Construction of five small scale Irrigation shigez at Single Stage - One Yilmana, Abagenen and IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 2,355,000.00 2,097,164.81 Signed 2018-09-26 2018-10-01 2018-10-31 2018-11-30 2018-12-24 2019-06-22 Envelope Kenntiba at W/denbia,, Aynakoba at E/denbia, and Akely at Alefa worda BOWID/AGP-2-11/2018 / Construction of five small scale Irrigation Berbera-1 and Zinginie Melha-2 at Single Stage - One G/shekudad,,Zingini IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 2,224,000.00 1,992,593.62 Signed 2018-09-26 2018-10-01 2018-10-31 2018-11-30 2018-12-29 2019-06-27 Envelope Expantion at Wonberma, Lahe-2 Upgrading at Jabitehena and Bilkua at wonberma woreda. ET-AAGP RPCU-23864-CW- RFB / Construction of fence Agriculture Marketing and Single Stage - One for semen collection center IDA / 56050 Post Request for Bids Open - National 65,219.00 0.00 Canceled 2017-08-15 2017-08-20 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Value Chains Envelope at Bahir Dar Animal Health Clinic BOWID/NCB/AGP- 2/W/06/2018 / Construction of small scale Irrigations: Zilihi & Biliq at A/guangua, Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 8,443,700.00 7,862,914.91 Signed 2018-01-31 2018-02-05 2018-03-07 2018-04-06 2018-05-11 2019-11-02 Ayehujumer & Ayehu at Envelope G/shekudad and Taba Microearth Dam Awabel worda BONCB/AGP-2/W/7/2018 / Construction of small scale Single Stage - One Irrigations: Zingini Melha , IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 8,282,800.00 510,001.01 Signed 2018-02-06 2018-02-11 2018-03-13 2018-04-12 2018-05-17 2019-11-08 Envelope Berbera 2 /3 & Lifta at G/shekudad worda 3BOWID/NCB/AGP- 2/W/8/2018 / Construction of small scale Irrigations: Under Zembel, Yechereka and Areki Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 7,950,700.00 7,140,881.74 Implementati 2018-02-07 2018-02-12 2018-03-14 2018-04-13 2018-05-18 2019-11-09 at Denbecha, Envelope on Shina Anbesit at Y/Densa and Enenezer Microearth E/Enawga worda BOWID/NCB/AGP- 2/W/9/2018 / Construction of small scale Irrigations: Hamus Wonz at G/ Single Stage - One Begemdir, Lower Dinsira IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 5,845,400.00 5,530,588.23 Signed 2018-02-11 2018-02-16 2018-03-18 2018-04-17 2018-05-22 2019-11-13 Envelope upgrading Burie, Dim upgrading Zigem and Mugechit Microearth Dam Dera worda BOWID/NCB/AGP- 2/W/10/2018 / Construction of small scale Irrigations: Kility Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 6,207,700.00 1,938,464.69 Signed 2018-02-13 2018-02-18 2018-03-20 2018-04-19 2018-05-24 2019-11-15 upgrading A/Achefer, Silla Envelope Jabitehena and Alloberet B/Orana worda Page 3 ET-AAGP RPCU-23866-CW- RFB / Construction of Agriculture Marketing and Single Stage - One Nitrogen Plant Sheds and IDA / 56050 Post Request for Bids Open - National 86,940.00 66,039.62 Signed 2017-08-15 2017-08-20 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Value Chains Envelope Fence at Bahir Dar AI Center ET-AAGP RPCU-26222-CW- RFB / Construction of Three Warehouse for three Cooperatives at Dejen Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 971,064.00 0.00 Canceled 2017-10-23 2017-10-28 2017-12-09 2018-01-08 2018-02-12 2018-08-11 Worda Gion Union, Tsehay Value Chains Envelope Union North Gonder and Kesem Union North shoa Zone. ET-AAGP RPCU-26224-CW- RFB / Construction of warehouse for 8 Primary Cooperative at Awi Zone Workmeda, North Soa Agriculture Marketing and Single Stage - One Siaseber, and Moret, West IDA / 56050 Post Request for Bids Open - National 536,303.00 0.00 Canceled 2017-10-23 2017-10-28 2017-12-09 2018-01-08 2018-02-12 2018-08-11 Value Chains Envelope Gojam Dembecha, South Gonder Dera, Eest Gojam Basolibe and Deber Alias and North Gonder Alefa worda. ET-AAGP RPCU-92349-CW- RFB / Construction of Road Pending Agriculture Marketing and Single Stage - One side market center at IDA / 56050 Post Request for Bids Open - National 545,400.00 0.00 Implementati 2018-10-19 2018-10-24 2018-11-23 2018-12-23 2019-01-27 2019-07-26 Value Chains Envelope Gonder/gumara, Yejubie and on Burie with two lots ET-AAGP RPCU-31641-CW- RFB / Construction of 6 Road side market center( 4 fruit & vegetates market at Agriculture Marketing and Single Stage - One Dera, Basoliben, Burie and IDA / 56050 Prior Request for Bids Open - National 521,340.00 0.00 Canceled 2017-11-20 2017-11-25 2018-01-09 2018-02-08 2018-03-09 2018-08-06 Value Chains Envelope Guagusa shekudad worda and one banana market at Gonder and one for hony at Dangla worda. ET-AAGP RPCU-31641-2- Under CW-RFB / Construction of Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 87,383.00 0.00 Implementati 2017-11-20 2017-11-25 2018-01-09 2018-02-08 2018-03-15 2018-09-11 road side market at Value Chains Envelope on G/shekudad worda Tilli ET-AAGP RPCU-92331-CW- RFB / Construction of six Warehouse for six Cooperatives for Gion Union at Dejen Worda, Tsehay Union at Gonder, Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 2,400,000.00 3,070,246.43 Signed 2019-02-18 2019-02-23 2019-03-25 2019-04-24 2019-05-29 2019-11-25 Kesem Union N/shoa , Value Chains Envelope Merkeb union at Dera/S/Gonder, Damot union at Denbecha W/gojam and Wodera Union at D/birhan N/shewa zone. ET-AAGP RPCU-92337-CW- RFB / Construction of warehouse for 16 Primary Cooperative for Alefa primary union, workemeda, Hmusite, Wade, Agriculture Marketing and Single Stage - One Emeriemeskel, IDA / 56050 Post Request for Bids Open - National 1,750,000.00 1,481,139.48 Signed 2019-02-18 2019-02-23 2019-03-25 2019-04-24 2019-05-29 2019-11-25 Value Chains Envelope Kusayie,Yegelaw, Ginet, Wejel, Arerti, Amebela, Gedeb, Atekie, Zeleke, Zobenet Semate mendukie primary union in four zones with eight lo Page 4 ET-AAGP RPCU-106380-CW- RFB / Construction of three Small Scale Irrigation at Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 646,100.00 618,377.76 Signed 2019-04-02 2019-04-07 2019-05-07 2019-05-28 2019-06-26 2019-11-23 Andasa-medebit, Amergofa- Envelope and koga-Bahirdarzuria worda ET-AAGP RPCU-81517-CW- Request for Single Stage - One RFQ / Establishing vermin IDA / 56050 Agricultural Research Post Limited 55,600.00 0.00 Canceled 2018-12-29 2019-02-17 2019-05-18 Quotations Envelope compost center ET-AAGP RPCU-31636-CW- RFB / Construction of 6 Primary Market Center (4 Milke processing Market at Agriculture Marketing and Single Stage - One Wogera, S/Achefer, Dejen, & IDA / 56050 Post Request for Bids Open - National 832,304.00 0.00 Canceled 2017-10-30 2017-11-04 2017-12-04 2018-01-03 2018-01-28 2018-05-28 Value Chains Envelope Basoliben worda & two Honey Processing market at Gualgua and D/Telategen worda. ET-AAGP RPCU-81516-CW- RFB / Establishing Six Fruit Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 670,300.00 0.00 Canceled 2018-12-31 2019-01-05 2019-02-04 2019-03-06 2019-03-30 2019-09-26 Nursery at six worda with Value Chains Envelope three lots ET-AAGP RPCU-106390-CW- RFB / Construction of Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 916,700.00 0.00 Canceled 2019-04-15 2019-04-20 2019-05-20 2019-06-10 2019-07-09 2020-04-04 Small Scale Irrigation Envelope Ashal Tarmaber worda ET-AAGP RPCU-26218-CW- RFB / Construction of Two Small Scale Irrigation- at Zembele River Denbacha woreda and Tentiba Rivere at Denbia worda And Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,826,128.00 0.00 Canceled 2017-10-30 2017-11-04 2017-12-16 2018-01-15 2018-02-19 2018-08-18 Rihabilitation Of Four Envelope Existing Small Scale Irrigation at Fetam/densra Rever Burie, Sure Revere Ankesha and Robit Revere Tarmaber . ET-AAGP RPCU-106382-CW- RFB / Construction of two ( Abay-3 Small Scale Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,892,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-05-20 2019-06-19 2019-07-18 2020-07-12 Irrigation and Andasa small Envelope scal Irrigation ) at Bahirdar Zuria worda ET-AAGP RPCU-106384-CW- RFB / Construction of two Small Scale Irrigation ( Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 990,000.00 0.00 Canceled 2019-04-22 2019-04-27 2019-05-27 2019-06-17 2019-07-16 2020-03-12 Yechereka-2i at Denbecha Envelope and Thule Upgrading at Yelmana densa worda ) ET-AAGP RPCU-106381-CW- RFB / Construction of two Small Scale Irrigation ( Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 990,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-05-20 2019-06-10 2019-07-09 2020-07-03 Wumbrit Expansion and Envelope Lankichy-Upgrading ) at Dangela worda. ET-AAGP RPCU-106389-CW- RFB / Construction of Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,785,700.00 0.00 Canceled 2019-04-15 2019-04-20 2019-05-20 2019-06-19 2019-07-18 2020-07-12 Small Scale Irrigation at Envelope Fetam-sontom Burie worda Page 5 ET-AAGP RPCU-106387-CW- RFB / Construction of three Small Scale Irrigation at Single Stage - One Hosie Ayehu Guagusa, IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,344,000.00 0.00 Canceled 2019-04-09 2019-04-14 2019-05-14 2019-06-04 2019-07-03 2020-02-28 Envelope Tembel Dangela Gangua and lower Dim at zigem worda ET-AAGP RPCU-106385-CW- RFB / Construction of two Single Stage - One Small Scale Irrigation at IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,679,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-05-20 2019-06-19 2019-07-18 2020-04-13 Envelope Megenagna at Farta and Chugie at Wogera worda GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAGP RPCU-26058-GO- RFQ / Procurement of Project Management, Request for Single Stage - One stationary and office supplies IDA / 56050 Capacity Building and Post Limited 4,608.00 1,705.05 Completed 2017-10-07 2017-11-04 2017-11-18 Quotations Envelope for Regional Project Monitoring and Evaluation Coordination Unit ET-AAGP RPCU-26231-GO- RFB / Procurement of two Project Management, Single Stage - One field Vehicle for Regional IDA / 56050 Capacity Building and Post Request for Bids Open - National 260,870.00 244,094.56 Signed 2017-08-31 2017-09-05 2017-10-17 2017-11-16 2017-12-21 2018-06-19 Envelope Water Irrigation and Mining Monitoring and Evaluation Bureou. ET-AAGP RPCU-26232-GO- RFB / Procurement of of 20 Computers. 4 Medium Project Management, printers,2 Heavy printers, 3 Single Stage - One IDA / 56050 Capacity Building and Post Request for Bids Open - National 40,873.00 108,253.41 Signed 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 2018-06-05 LCD Projectors.2 LCD Envelope Monitoring and Evaluation Printer, 168 pico projector, 4 External Hard Disk, 1 photo copier and 4 hand camera ET-AAGP RPCU-26235-GO- RFB / Procurement of Project Management, Single Stage - One Network Installation IDA / 56050 Capacity Building and Post Request for Bids Open - National 101,086.00 66,409.36 Completed 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 2018-08-04 Envelope Equipment for New Monitoring and Evaluation Program Supported Wordas. ET-AAGP RPCU-31513-GO- RFB / Procurement of 43 Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 65,217.00 35,268.03 Completed 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-01-30 2018-03-31 Leveling Instrument for Envelope Irrigation. ET-AAGP RPCU-31545-GO- RFQ / Procurement of Office Equipment and Electronics Project Management, Request for Single Stage - One (Computer, photocopier, IDA / 56050 Capacity Building and Post Limited 17,652.00 6,545.12 Completed 2017-11-04 2017-12-12 2018-02-10 Quotations Envelope printer, LCD...) for Regional Monitoring and Evaluation Water Irrigation and Energy bureau. Page 6 ET-AAGP RPCU-31615-GO- RFB / Procurement of laboratory Equipment (Safety cabinet, Micro tome, Water bath ...) for Regional Agricultural Public Support Single Stage - One Artificial Incrimination IDA / 56050 Post Request for Bids Open - National 195,653.00 5,840.65 Signed 2017-11-20 2017-11-25 2017-12-25 2018-01-24 2018-02-18 2018-05-19 Services Envelope Center and Procurement of Veterinary Equipment (Binocular, thermometer...) for worda animal health clinic ET-AAGP RPCU-31556-GO- DIR / Procurement of Lime IDA / 56050 Agricultural Research Prior Direct Selection Direct 37,010.00 0.00 Canceled 2017-12-11 2017-12-16 2018-01-19 2018-03-20 for Soil Treatment Demonstration ET-AAGP RPCU-31540-GO- DIR / Procurement of Cion IDA / 56050 Agricultural Research Prior Direct Selection Direct 200,000.00 0.00 Canceled 2017-10-31 2017-11-05 2017-12-04 2018-03-04 Equipment for Seed Germination/Reproduction. ET-AAGP RPCU-80871-GO- Project Management, RFB / Supply Networking Request for Single Stage - One IDA / 56050 Capacity Building and Post Limited 40,000.00 40,344,691.60 Signed 2018-12-19 2019-01-24 2019-03-25 Equipment's and Installation Quotations Envelope Monitoring and Evaluation for seven program wordas ET-AAGP RPCU-81524-GO- Project Management, Under RFB / Procurement of six Single Stage - One IDA / 56050 Capacity Building and Post Request for Bids Open - National 150,000.00 0.00 Implementati 2018-11-26 2018-12-01 2018-12-31 2019-01-15 2019-02-13 2019-04-14 Total station for six zonal Envelope Monitoring and Evaluation on Department/AGP-CU ET-AAGP RPCU-81569-GO- ELC-RFQ / Procurement of Project Management, Electronics (Computer= 2, Request for Single Stage - One IDA / 56050 Capacity Building and Post Limited 7,400.00 4,608.03 Completed 2019-01-05 2019-02-09 2019-03-11 LCD= 2, EVDIO= 6, Quotations Envelope Monitoring and Evaluation Camera= 1) for Regional Coordination unite. ET-AAGP RPCU-81972-GO- RFB / Providing AI Field Equpment (Liquied Nitrogen container,plastic glove, sheath..) and Procurment of Agricultural Public Support Single Stage - One Laboratory materials (Bovine IDA / 56050 Post Request for Bids Open - National 151,850.00 28,485.57 Signed 2018-10-22 2018-10-27 2018-11-26 2018-12-11 2019-01-15 2019-05-15 Services Envelope semen extender, cuvate,sampling tube, Halongen lamp, cover slep..) for Regional laboratory center ET-AAGP RPCU-82070-GO- RFQ / Procurement of Office and Filed Equipment for Regional Environment Forest Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 45,000.00 43,733.13 Completed 2018-12-29 2019-02-16 2019-04-17 and Wilde life Authority Services Quotations Envelope (Digital meter= 12, Freeze=2, Conductivity=1, Furniture 6...) ET-AAGP RPCU-82071-GO- RFB / Equipping Digital Green with video camera=8, Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 133,300.00 189,042.01 Signed 2018-11-19 2018-11-24 2018-12-24 2019-01-08 2019-02-12 2019-05-13 pico projector=48, pico Services Envelope projector stand=170 and Flash memory=170 ET-AAGP RPCU-31511-GO- Under RFB / Equipping Fish Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 95,652.00 0.00 Implementati 2019-02-18 2019-02-23 2019-03-25 2019-04-24 2019-05-19 2019-08-17 Hatchery Center with Services Envelope on Hormone, glove,sheath... Page 7 ET-AAGP RPCU-97791-GO- DIR / Procurement of IBAR Single Stage - One IDA / 56050 Agricultural Research Post Request for Bids Open - National 14,600.00 21,694.78 Signed 2019-02-25 2019-03-02 2019-04-01 2019-04-16 2019-05-14 2019-11-10 BBM for Agricultural Envelope Demonstration ET-AAGP RPCU-31552-GO- DIR / Procurement of IBAR BBM for Agricultural Agricultural Public Support IDA / 56050 Prior Direct Selection Direct 14,600.00 0.00 Canceled 2018-02-26 2018-03-03 2018-04-03 2018-07-02 Demonstration from IBAR Services Engineering PLC which is sole Proprietor for goods. ET-AAGP RPCU-80860-GO- Pending RFB / Procurement of 65 Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 130,000.00 0.00 Implementati 2019-10-14 2019-10-19 2019-11-18 2019-12-03 2019-12-23 2020-06-20 Motor cycle for new AGP Services Envelope on Supported worda ET-AAGP RPCU-31507-GO- RFQ / Procurement Two Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 148,149.00 0.00 Canceled 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-09-18 Truck for Acidic soil Services Envelope management. ET-AAGP RPCU-34940-GO- RFB / Procurement of 410 Single Stage - One IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 75,925.00 0.00 Canceled 2017-12-29 2018-01-08 2018-02-07 2018-03-09 2018-04-03 2018-07-02 Tredel Pump for Micro Envelope Irrigation. ET-AAGP RPCU-31550-GO- RFB / Procurement of Field Project Management, Single Stage - One Equipment(Woki Toki) for IDA / 56050 Capacity Building and Post Request for Bids Open - National 174,565.00 0.00 Canceled 2017-12-31 2018-01-05 2018-02-16 2018-03-18 2018-04-11 2018-07-10 Envelope Regional Water Irrigation Monitoring and Evaluation and Energy bureau ET-AAGP RPCU-31499-GO- Project Management, RFB / Procurement of Total Request for Single Stage - One IDA / 56050 Capacity Building and Post Limited 17,391.00 0.00 Canceled 2017-10-30 2017-11-30 2018-02-28 Station for Bureau of Land Quotations Envelope Monitoring and Evaluation Use and Administration ET-AAGP RPCU-82180-GO- Agricultural Public Support DIR / Procurement of IBAR IDA / 56050 Post Direct Selection Direct 20,000.00 0.00 Canceled 2018-11-19 2018-11-24 2018-12-29 2019-02-27 Services BBM For Soil Mangment ET-AAGP RPCU-97809-GO- RFB / Procurement of Lime Agricultural Public Support Single Stage - One for Soil Treatment IDA / 56050 Post Request for Bids Open - National 360,000.00 0.00 Canceled 2019-02-18 2019-02-23 2019-03-25 2019-04-04 2019-05-02 2019-10-29 Services Envelope Demonstration (60,,000 quintals ) ET-AAGP RPCU-82090-GO- RFQ / Procurement of Lime Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 35,700.00 0.00 Canceled 2019-01-12 2019-03-09 2019-04-08 for soil management (4000 Services Quotations Envelope quantal) ET-AAGP RPCU-62886-GO- RFB / Procurement of Project Management, Single Stage - One Laptop computer for IDA / 56050 Capacity Building and Post Request for Bids Open - National 50,000.00 0.00 Canceled 2018-05-21 2018-05-22 2018-06-22 2018-06-27 2018-07-19 2019-01-15 Envelope Regional Land use and Monitoring and Evaluation Administration Bureau. ET-AAGP RPCU-157869-GO- RFQ / Procurement of Project Management, Pending Request for Single Stage - One Electronics/laptop computer IDA / 56050 Capacity Building and Post Limited 67,000.00 0.00 Implementati 2020-02-16 2020-03-06 2020-03-21 Quotations Envelope and Office Equipment for Monitoring and Evaluation on Regional AGP-CU ET-AAGP RPCU-159166-GO- Pending Agricultural Public Support Request for Single Stage - One RFQ / Procurement of 12 IDA / 56050 Post Limited 56,000.00 0.00 Implementati 2020-03-04 2020-04-06 2020-06-05 Services Quotations Envelope Motorcycle on Page 8 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAGP RPCU-50780-CS- QCBS / Construction Agricultural Public Support Quality And Cost- supervision of Fish hatchery IDA / 56050 Post Open - National 90,000.00 0.00 Canceled 2018-04-10 2018-05-01 2018-06-14 2018-07-12 2018-08-11 2018-09-15 2018-10-20 2019-04-18 Services Based Selection (We prefer the cornet selection methods) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9