DRAFT PROCUREMENT PLAN (Works) Municipal Governance and Services Project (MGSP) Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 MGSP/NCC/W-01 Construction of road & embankment km 1.000 1 120.00 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 protection along the river Shitalakhya starting from Bandar 01 no Kheya Ghat upto Tribini khal with necessary beautification 2 MGSP/NCC/W-02 Improvement of Mobarak Shah road km 0.950 1 74.44 NCB BG No 28-03-2014 30-05-2014 30-04-2015 and road side drain with footpath 3 MGSP/NCC/W-03 (a). Improvement of Jallerpar road and road km 0.575 1 37.94 NCB BG No 25-04-2014 27-06-2014 27-05-2015 side drain with footpath starting from Jimkhana bridge to Joy Gobidha School via Paikpara bridge. (b). Improvement of Shah Suja road km 1.045 starting from Foodland Bakery to Choto Kabarstan with Nayapara link road and Bhuyanpara link road. 4 MGSP/NCC/W-04 (a). Construction of drain starting from 2 km 0.685 1 31.50 NCB BG No 25-05-2014 27-07-2014 27-06-2015 no.Rail Gate to ex BKMEA president Mr.Fazlul Haque's house via Golachipa Sugandha Bakery. (b). Construction of footpath cum drain by km 0.270 the side of Khalghat road. 5 MGSP/NCC/W-05 Rehabilitation work of T-hossain road km 0.760 1 73.10 NCB BG Yes 25-06-2014 27-08-2014 27-07-2015 starting from Nobiganj ghat to Modonganj -Modonpur road by RCC road, drain and electrification work in word no. 24 under Narayanganj CC (ch. 2013-2014) H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Sub-total of Narayanganj km 4.525 5 263.88 5 MGSP/TAN/W-01 Rehabilitation road from R&H Victoria km 3.615 1 33.30 NCB BG No 28-03-2014 30-05-2014 30-04-2015 road to Baray R&H Road via Adi Tangail Textile mill to Mirarbetka LGED road. 6 MGSP/TAN/W-02 (a). Improvement road from Alowa Amtola km 1.090 1 43.80 NCB BG No 28-04-2014 30-06-2014 30-05-2015 to Sontosh Bayan para bridge. (b). Improvement Bazitpur Thakurbari road. km 0.350 .(c). Rehabilitation road from Gala Verchand km 1.340 road H/O Joaher Ali to Dharerbari road. (d). Improvement road starting Hazraghat km 1.500 morh to Bailla Madrasa moar. (e). Improvement Sakrail Saruti road from km 1.710 Omarpur road to Sakrail Bazar. (f). Rehabilitation of road starting from km 6.220 Central Graveyard R & H road to Putiajani Bazar R&H road via Sajujbag. (g). Rehabilitation of of Stand road km 2.100 starting from Babystand R&H road to Bottola Bazar. 7 MGSP/TAN/W-03 Construction of Bypass Road Leading km 4.000 1 57.10 NCB BG No 25-05-2014 27-06-2014 27-05-2015 from Kagmari Bridge upto Tangail Zilla porisad. Sub-total of Tangail km 21.925 3 134.20 H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 8 MGSP/ELN/W-01 (a). Improvement road with side drain and km 3.030 1 57.70 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 culverts from R&H National Highway to Baganbari super market. (b). Improvement road with roadside drain, km 2.880 bridge from R&H National Highway and Vabla play ground. Sub-total of Elenga km 5.910 1 57.70 9 MGSP/MAD/W-01 (a). Improvement of Madaripur Main road km 1.360 1 46.78 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 from police line moar RHD road to Puran bazaar Muchi bari More(Ch.00- 1+360m) (b). Construction of RCC Drain on Left km 1.360 Side Madaripur Main Road Stating From Police Line More(RHD Road) to Puran Bazar Muchi Bari More (Ch o.oo to 1+360 m) .(c). Construction of Brick Drain on Right km 1.360 Side Madaripur Main Road Stating From Police Line More(RHD Road) to Puran Bazar Muchi Bari More (Ch o.oo to 1+360 m) (d). Construction Footpatht Both Side km 1.360 Madaripur Main Road Stating From Police Line More(RHD Road) to Puran Bazar Muchi Bari More (Ch o.oo to 1+360 m 10 MGSP/MAD/W-02 (a). Construction of RCC Road at km 0.342 1 29.87 NCB BG No 28-02-2014 30-04-2014 30-03-2015 Shahid Bachu Sarak Starting from Kazir More to Howlader Godi. (Ch. 1230.00-1572.00m) H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (b). Construction of Amin Uddin km 0.430 Howlader Sarak RCC Road With Brick Massonary Drain. (Ch. 0.00- 430.00m) (c) Construction of RCC Road at km 0.440 Hamid Sikder Sarak Starting from RHD Road to Hamid Akondo Sarak. (Ch. 0.00-440.00m) (d). Construction of Shahid Surjo Sarak km 0.433 RCC Road With Brick Massonary Drain. (Part-1: 330.00m & Part-2: 103.00m) 11 MGSP/MAD/W-03 (a). Construction of RCC Road at km 0.365 1 19.28 NCB BG No 25-03-2014 27-05-2014 27-04-2015 Shahid Harun Sarak Starting from Madaripur Main Road to Dorgha Sharif Road. (Ch. 0.00-365.00m) (b). Construction of RCC Road Starting km 0.205 from Shahid Bachu Sarak to Stadium road. (Ch. 0.00-205.00m) (c) Construction of Jotish Dey Sarak km 0.192 RCC Road With Brick Massonary Drain. (Ch. 0.00-192.00m) H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (d). Rehabilitation of Charmuguria km 1.030 Abu Munsi Goli & Nasimnagor Graveyard road Starting from Kumar riaver to Charmuguria Hazrapur main road.(Ch0.00m to 1030.00m) (e). Improvement of the Pakdi km 0.280 Peshker Bari road starting from Charmuguria Puraton road to Beri badh (Ch0.00m to 280.00m) (f). Rehabiltation of Sultan km 0.425 Howlader Bituminous Carpetting road starting from RHD main road to end of Pouro area.(Ch0.00m to 425.00m) Sub-total of Madaripur km 9.582 3 95.93 12 MGSP/SHA/W-01 (a). Construction of road from RHD Road km 1.780 1 45.80 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 to Nilkandi via RHD road to house of Mr.Opu Ghos. (b). Construction of road from Bus Stand km 1.500 north side to house of Mr. Ohab Ali Munshi via house of Mr.Kongso Bonik. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 .(c). Construction of road from Pourashava km 1.020 BC road to house of Mr.Onu Chaudhary and house of Mojid Chairman via Sadar Hospital to house of Salma Councilor 13 MGSP/SHA/W-02 (a). Construction of road from RHD road at km 1.600 1 37.90 NCB BG No 25-03-2014 27-05-2014 27-04-2015 Ansar VDP barak to Baghia canel via Palong High School. (b). Construction of road from Police Line km 2.760 to house of Mr.Siddik Munshi via Shariatpur Stadium to house of Mr.Abdul Hai Sikder Sub-total of Shariatpur km 8.660 2 83.70 14 MGSP/GOP/W-01 (a). Construction of Dhalibari road to Fire km 3.855 1 40.60 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 service road via Faringabari road & German mission road (b). Construction of Kabarstan road to km 2.725 Arambag Yusuf Drivers house via Biswasbari road & Biswasbari 1st lane 15 MGSP/GOP/W-02 (a). Construction of Joggeshar road to BB km 2.800 1 45.80 NCB BG No 25-03-2014 27-05-2014 27-04-2015 road via Power house road & Udayan road (b). Construction of Janat road to km 2.950 Chandmari road via Amena School road & chachaniakandi road .(c). Construction of Panchuria BB road to S km 4.600 P Office road via Asram road, Natun school road, Bodor road & Mohammadpar road Sub-total of Gopalganj km 16.930 2 86.40 H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 MGSP/BLK/W-01 (a). Construction of road at Dhaka - km 0.500 1 38.00 NCB BG No 28-02-2014 30-04-2014 30-03-2015 Mymensingh Highway near Khironnodi bridge to Central Eidgah. (b). Construction of road at Dhaka- km 2.405 Mymensingh Highway to Bhaluka Health Complex & Trauma Center via Bhandhabu moar. .(c). Construction of road at Bhaluka Degree km 1.500 College to Golam Mustafa's house via Chaprabari Primary School. (d). Construction of road at Bhaluka- km 0.500 Gofforgoan Highway to Chaprabari road. 17 MGSP/BLK/W-02 (a). Construction of road at Gofforgoan km 1.400 1 44.00 NCB BG Yes 25-03-2014 27-05-2014 27-04-2015 Highway near Fire Service moar to Biruniya road via Bhaluka Fazil (b). Madrasa. Construction of road at Russell km 1.200 Spinning Mill to house of Lebu member. .(c). Construction of road from Bhaluka Bus km 1.600 Stand to Sub-registry Office including Pilot High School gate and Bhaluka bazar internal road. (d). Development of road at Faruk Fishiries km 0.700 to Mr. Borkot Councilor's house. (e). Development of road at Shaik km 1.150 Johiruddin house to Roton Agro moar. Sub-total of Bhaluka km 10.955 2 82.00 H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 18 MGSP/TRI/W-01 (a). Improvement of Commissioner road km 1.00 1 38.10 NCB BG No 28-02-2014 30-04-2014 30-03-2015 from Mr Lalu's shop to Dhaka Mymensingh highway. (b). Rehabilitation of fishery road from km 2.51 Dhaka road to Medherpar end point of Pourashava. .(c). Construction of Fulbari road. km 3.05 (d). Improvement of Bazit Ali road from km 0.36 Trishal Dhanikhol road to Nodirpar. 19 MGSP/TRI/W-02 (a). Construction of Trishal - Dhanikhol km 1.20 1 45.20 NCB BG Yes 25-03-2014 27-05-2014 27-04-2015 road near Etimkhana Madrasa to Ex Commissioner Mustafa's house. (b). Improvement of Baparipara road from km 2.00 Dhaka roa to Bapari Bari. .(c). Improvement of road from Trishal km 0.75 Nazrul Museum to Fulbaria road. (d). Development of road from Trishal- km 0.73 Dhanikhola road near Etimkhana Madrasha to Ex-Commissioner Mostafa's house. (e). Construction of RCC drain beside km 0.980 Commissioner road from Mr Lalu's shop to Dhaka Mymensingh highway. Sub-total of Trishal km 12.578 2 83.30 20 MGSP/MDI/W-01 Construction of road from Amtala km 1.180 1 49.60 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 Masjid at Kotoalir char upto old rail line. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 21 MGSP/MDI/W-02 (a). Construction of road from Bow Bazaar km 1.071 1 39.30 NCB BG No 25-03-2014 27-05-2014 27-04-2015 to Tatapar UPHCP Hospital. (b). Construction of road from Faith km 1.250 General Hospital to Habibur Rahman house via Ikbal house. Sub-total of Madhabdi km 3.501 2 88.90 22 MGSP/BHB/W-01 Construction of Bhairab Bazaar km 3.000 1 40.30 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 Internal road. 23 MGSP/BHB/W-02 (a). Construction & widening of Kalipur to km 2.000 1 42.90 NCB BG Yes 28-03-2014 30-05-2014 30-04-2015 Ramshankkarpur road. (b). Construction of road from Ghastalaghat km 1.260 towards north direction up to Bhairab Kishoreganj Highway via Upazila complex, Haji Asmat college & Stadium. 24 MGSP/BHB/W-03 Construction of Chandiber road. km 3.900 1 47.20 NCB BG Yes 25-04-2014 27-06-2014 27-05-2015 Construction of road at Bhairabpur km 1.050 South Para Sub-total of Bhairab km 11.210 3 130.40 25 MGSP/SHE/W-01 Construction of road at Dhunat road km 2.950 1 31.90 NCB BG No 28-02-2014 30-04-2014 30-03-2015 Doctors' Clinic to Hajipur Highway road vai Sherpur Thana including roadside drain. Construction of road from Dr. Asraf's km 1.200 Chember to Sherpur Thans via Prince's Saw Mill including road side drain. 26 MGSP/SHE/W-02 (a). Construction of road at Dublagari Cold km 2.400 1 32.50 NCB BG No 28-03-2014 30-05-2014 30-04-2015 Storage to Mr. Aktaru Zaman house via ABC Eye Hospital including roadside drain. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (b). Construction of road at Highway km 0.800 Upazila Porishod Gate Pintu shop to Shisu Park vai Shapla Chattor. .(c). Construction of road from house of km 0.700 Engineer Rashid to AC Land Office via National Highway including road side drain. (d). Construction of road at Highway Don km 0.350 Pharmacy to Gora Store including road side drain. 27 MGSP/SHE/W-03 (a). Construction of road at AC Land Office km 1.700 1 31.50 NCB BG No 25-04-2014 27-06-2014 27-05-2015 to Uttor Bahini Maha Shosan including road side drain. (b). Construction of road from Highway km 1.150 Road Dada Enterprize to Madrasha Gate of Dhunat road vai Mosla market. Sub-total of Sherpur km 11.250 3 95.90 29 MGSP/RCC/W-01 (a). Improvement of Nisbetgonj road from km 2.500 1 36.60 NCB BG No 28-02-2014 30-04-2014 30-03-2015 Cachari Bazaar to Central Bus Terminal. (b). Improvement of Terminal road form km 2.200 Shapla Moar to Central Bus Terminal .(c). Rehabilitation of RK Road to Lalbag km 0.905 Hat via 20 megawatt (d). Rehabilitation of Adorsho Para road km 1.815 and internal road of Adorsho Para (e). Rehabilitation of road from Tazhat Rail km 1.500 gate to Chalk Bazer Via City Biscuit Factory. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (f). Rehabilitation of road starting from km 0.700 Bongobondu Hospital upto Girls' School. 30 MGSP/RCC/W-02 (a). Construction of drain from Mouvasa to km 1.250 1 31.00 NCB BG No 28-03-2014 30-05-2014 30-04-2015 KD canal (b). Construction of drain at south side of km 1.200 Terminal road 31 MGSP/RCC/W-03 (a). Construction of drain at RK road from km 1.500 1 30.10 NCB BG No 25-04-2014 27-06-2014 27-05-2015 TV Centre to Check post. (b). Construction of drain from Kerani Para km 0.500 Garian tari to Nasirabad Mosque .(c). Construction of drain from km 0.900 Robertsonganj saw mill to Mondolpara bridge. 32 MGSP/RCC/W-04 (a). Construction of drain from shop of ex km 0.600 1 31.80 NCB BG No 25-05-2014 27-07-2014 27-06-2015 commissioner Mr.Nurul Haque at Kellabond (b). Construction of drain from Kamar para km 0.470 to Babukhaon road. .(c). Construction of Tatipara drain staring km 0.550 from Pirgachha Bus stand to Tati para existing drain (d). Construction of drain from Rangpur km 0.400 community centre to Pakpara . (e). Construction of drain from Babupara km 0.500 road to city biscuit factory (f). Construction of drain at Dhap km 0.500 Ganganath road (g). Construction of drain from Mohadebpur km 0.650 Kalam’s Godown to Mohadebpur Jame Mosque. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (h). Construction of drain from Dhap Hazi km 0.900 para to Pakar matha Sub-total of Rangpur km 19.540 4 129.50 33 MGSP/SAD/W-01 (a). Construction of Shahid Dr. Zikrul km 1.300 1 39.50 NCB BG No 28-02-2014 30-04-2014 30-03-2015 Haque road from Rail Crossing to Rail Station (b). Construction of Shahid Dr. Zohirul km 3.200 Haque road from Dinajpur road to Boshuniapara last area of Pourashava. 34 MGSP/SDP/W-02 (a). Construction of Shahid Dr. Shamsul km 1.250 1 37.70 NCB BG No 28-03-2014 30-05-2014 30-04-2015 Haque road from Dinajpur road to Shahid Dr Zikrul Haque road via cloth market (b). Construction of Sher-E-Bangl road & km 3.700 Kazi Nazrul Islam road from Bangobondhu road to WAPDA moar. 35 MGSP/SDP/W-03 (a). Construction of road from Panch Matha km 3.000 1 32.50 NCB BG No 25-04-2014 27-06-2014 27-05-2015 moar to Kundol via slaughter house. (b). Construction of road from Kazi Nazrul km 2.600 Islam road to Bangobondhu road via Joshim Bazar. Sub-total of Saidpur km 15.050 3 109.70 36 MGSP/GOB/W-01 (a). Improvement of road from Aminar vita km 1.190 1 35.60 NCB BG No 28-02-2014 30-04-2014 30-03-2015 nearer Mohimagonj road to pourashava boundary. (b). Improvement of road from highway km 0.730 nearer Hamdard to Mohimaganj road via Prodhanpara jam Mosque H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 .(c) Improvement of road from Toslim km 0.560 driver's house to Durgapur pond of Amirul. (d). Improvement of road from highway to km 0.995 Durgapur mor via house of Mr Lutfar MP and from Durgapur moar to Highway via house of Dr. Dulu. (e). Improvement of road from Highway to km 1.595 Durgapur moar via house of Mr Lutfar MP and from Durgapur moar to Highway via house of Dr. Dulu. (f). Improvement of road from Durgapur km 0.466 moar to Highway via house of Dr. Dulu. (g). Construction of road from Highway km 1.228 near JB patrol pump to puraton UP office and from T&T moar to Rajmoti moar. (h). Improvement of road from Aminar vita km 0.660 near Mohimagonj road to Poura boundary. (i). Improvement of road from Sonar Para km 0.275 moar towards north upto Jahidul's rice chatal. (j). Improvement of road from Durgapur km 0.440 moar to Highway via house of Dr.Dulu. (k). Improvement of road from Highway km 0.865 near Mohila collage towards east upto the house of Raju and Romjan. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (l). Improvement of road from Girls' High km 0.655 School moar to Dinajpur road via house of Amirul 37 MGSP/GOB/W-02 Improvement of drain at Chandpur km 1.850 1 33.60 NCB BG No 25-03-2014 27-05-2014 27-04-2015 Govania Road. Sub-total of Gobindaganj km 11.509 2 69.20 38 MGSP/CCC/W-01 Improvement of Nazrul Avenue km 1.550 1 34.90 NCB BG No 28-02-2014 30-04-2014 30-03-2015 39 MGSP/CCC/W-02 (a). Improvement of Chak bazaar Shapla km 0.930 1 31.20 NCB BG No 27-03-2014 30-05-2014 30-04-2015 market to Abdul Awal Road (b). Improvement of Abu Zahid Road km 1.310 .(c) Improvement beside park Road DC km 0.520 office road to Eidgh road (d). Improvement of Otindra Mohan Roy km 0.610 Road (e). Improvement of Munsef Quarter km 1.375 Chowmohani to Habibur Rahman house up to Gomti River par (f). Improvement of N K Bahadur Road km 0.610 (g). Improvement of Hochamia Girls' km 0.350 School to Sorder Bari Graveyard 40 MGSP/CCC/W-03 (a). Improvement of Mogoltoly Shah Suja km 0.610 1 30.20 NCB BG No 25-04-2014 27-06-2014 27-05-2015 Mosque road (b). Improvement of Vatpara Chowmohani km 0.975 up to Pakkar Math road .(c) Improvement of Digamborito road City km 1.310 road to Circular road (d). Improvement of Chartha Chowmohani km 1.000 to EPZ road Sub-total of Comilla km 11.150 3 96.30 H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 41 MGSP/DAD/W-01 (a). Construction of road from Daudkandi km 0.518 1 35.30 NCB BG No 28-02-2014 30-04-2014 30-03-2015 Bazaar to Tuzarvanga Kanu Bepari house road (b). Construction of road from Daudkandi km 0.503 Taltoli Bazaar to Hasanpur road .(c) Construction of road from Daudkandi km 0.762 Hasanpur Yusuf Jamil Babu house to Hasanpur Khalpar road (d). Construction of road from Daudkandi km 0.315 North Stanandi road to Councilor Abdul Hoque’s house via Durga bari road (e). Construction of road from Daudkandi km 0.223 R& H road to West Maizpara Ali Amjad‘s house road (f). Construction of road from Daudkandi km 0.335 west Maizpara bridge to Digirpar Nazrul’s house road (g). Construction of road from Daudkandi km 1.890 R&H road to Daudkandi bazaar Sub-total of Daudkandi km 4.546 1 35.30 42 MGSP/CND/W-01 (a). Improvement of road from Moharong km 0.600 1 45.10 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 house of Moba to house of Moslem Driver. (b). Construction of road from Belashor km 1.100 Kachuarpar to Harong North Para. .(c) Construction of road from Haronng km 1.700 H/O Ansor Ali to Abdulir Par. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (d). Construction of road from Belashor km 0.400 Thangaon Road to Chandina Barer road. (e). Construction of road from Dhaka km 0.500 Chittagong Highway to Rapnagar. (f). Construction of road from Baro km 0.460 Gobindhapur Nath Para at H/O Shymshundor to Dhaka Chittagong Highway via Baro Gobindapur Ali Mia High School. (g). Construction of road from Tolatali km 0.458 Moulabi Bari Jame mosque towards South Baniachong connecting bridge. (h). Development of road from Biswas km 0.609 Primary School to Gobindapur Primary School. (i). Construction of drain from Chandina km 1.500 Bazaar Shah Plaza to Belashor Government Primary School east side & west side RNR road to TMSS office. Sub-total of Chandina km 7.327 1 45.10 43 MGSP/CHM/W-01 (a). Rehabilitation of road from Dhaka km 0.900 1 31.90 NCB BG No 28-02-2014 30-04-2014 30-03-2015 Chiitagong Highway to Natapara H/O Judge Abul Kashem. (b). Rehabilitation of road from Dhaka km 0.522 Chiitagong Highway to Ramrygram H/O Khandaker bari. .(c) Rehabilitation of road from Dhaka km 0.780 Chiitagong Highway to Bidderkhil Jame Mosque Road. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (d). Improvement of road from Dhaka- km 0.925 Chiitagong Highway to Sonakatia H/O Miker Via H/O Jalal Master. (e). Rehabilitation of road from Dhaka km 0.450 Chiitagong Highway to East Chandishkara Laxum road. (f). Rehabilitation of road from Dhaka km 0.850 Chiitagong Highway Nearest BICIC to Pachra H/O Muktijudda Commander Taher. (g). Improvement of road by RCC work km 0.550 from Dhaka-Ctg highway to Sonakatia H/O Jafor Driver. Sub-total of Chaddagram km 4.977 1 31.90 44 MGSP/FNI/W-01 (a). Improvement of Hazrat Phagla Miah km 1.360 1 30.40 NCB BG No 28-02-2014 30-04-2014 30-03-2015 road from Dhaka - Chittagong highway to Feni Comilla Trunk road (b). Improvement of Bijoysingh Dighi west km 1.100 side to Lotif Bhuiyan road. .(c) Improvement of Modhupur Hazi km 1.500 Mukhlesur Rahman road. (d). Improvement of road at Kadal Gazi rail km 0.650 gate to Chowrasta. (e). Improvement of Barahipur Shisu km 0.900 Kishore Academy road, GA academy road to Hospital road upto Rail gate. 45 MGSP/FNI/W-02 (a). Improvement of MES Road Hospital km 1.100 1 31.30 NCB BG No 28-03-2014 30-06-2014 30-04-2015 moar to Sonapur. (b). Improvement of Lomi Hazari Road km 0.410 H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 .(c) Improvement of Bijoy Singh-Abu Bakr road km 1.100 at Circuit House road to Latif Bhuiya road. (d). Improvement at Lomi-Hazari road to km 0.800 Rail gate 46 MGSP/FNI/W-03 (a). Improvement of Hanger road start from km 0.550 1 30.50 NCB BG No 25-04-2014 27-06-2014 27-05-2015 Hospital moar. (b). Improvement of Khiru Shah road. km 1.325 .(c) Improvement of Shibpur Nurani km 0.810 Madrasa road with 1 no cross drain. (d). Improvement of MP Khaju Miah road km 0.600 at Shibpur Tremuhini to Soap Factory. (e). Improvement of Middle Sharipur - km 1.205 Alauddin market to BISIC 48 MGSP/FNI/W-05 Construction of RCC drain at east side km 1.100 1 30.00 NCB BG No 25-05-2014 27-07-2014 27-06-2015 of Feni Comilla Trunk road and Jail road to Daudpur khal. Sub-total of Feni km 14.510 4 122.20 49 MGSP/PAT/W-01 (a). Improvement of road Sanda Market to km 1.800 1 41.50 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 Mager Ghata; via Kalo Fokir tea shop. (b). Improvement of road from Post Office km 1.300 to Sabjer Para Mosque including 5 link roads. .(c) Improvement of Club Road Circle to km 1.000 Post Office including 3 link roads. (d). Improvement of road Dhopa Pukur Par km 1.500 to Suchakradandi Primary School. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (e). Improvement of Cox’s Bazaar road west km 0.550 side from Indropol to Bipo Nondi road. (f). Construction of Hadu Chowdhury Bari km 0.750 road. 50 MGSP/PAT/W-02 (a). Construction of Potiya Kelyshohar km 0.250 1 43.70 NCB BG Yes 25-03-2014 27-05-2014 27-04-2015 road. (b). Construction of Alam road & Pike Para km 1.250 Mohammad Zaman Sikder road. .(c) Development of Prof. Abul Monsur km 1.390 Mohammad Ibrahim road & Improvement of road by Allai to end point of the Okhara. (d). Development of Shean para Buirga Bari km 0.500 road. (e). Development of South Gobinderkhil km 0.750 Jamie mosque road to Bahuly link road. (f). Development of BOC road to Faillatoli km 0.800 link. (g). Development of Moulana Nural Hoque km 0.750 Shah road. (h). Construction of drain with top slab at km 1.000 Potiya Indra pool to Upazila Complex main road Sub-total of Patiya km 13.590 2 85.20 51 MGSP/MIR/W-01 (a). Improvement of Anuram Sahaji Road. km 1.220 1 66.90 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 (b). Improvement of Shahid Mostafa road. km 1.000 H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (f) Improvement of Chandpur-Govania km 5.280 Road Sub-total of Mirsharai km 7.500 1 66.90 52 MGSP/SIT/W-01 (a). Improvement of Dhongazi road. km 0.600 1 48.80 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 (b). Improvement of Bohdder road. km 0.510 .(c) Improvement of Golum Mohiuddin km 0.500 road. (d). Improvement of Samsu Uddin km 0.700 Chairman road. (e). Improvement of Bhuiyanpar road from km 0.400 Chypar road. (f). Improvement of Moulavi par road from km 0.400 Rail line. (g). Improvement of South Suagazi road km 0.400 starting from Shibpur Primary School road. (h). Improvement of Fokirhat BOC road. km 0.500 (i). Construction of RCC Retaining wall km 0.100 along the Hasan Gomosta Road near rail line. (j). Improvement of Tulatoli road. km 0.500 Sub-total of Sitakunda km 4.610 1 48.80 53 MGSP/CHO/W-01 (a). Improvement of road from Tin Bot Tola km 1.072 1 36.50 NCB BG No 28-02-2014 30-04-2014 30-03-2015 to Shubahania Khom via Kazirpara station. (b). Improvement of road from Pourashava km 0.690 Office to Gaonosham Bazaar road. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 .(c) Improvement of road from New Market km 1.025 corner to Nath par road to Army Canteen via Ujjal Shop and Kali Mondir, Hori Mondir and Mahamub Shop to Chowrasta mur connecting road. (d). Improvement of road from Hal Kakara km 2.000 Nobarun Sanga to Fultala, Fultala to Thana mur and Thana mur to Mog Bazar. (e). Improvement of Chiringa Bitussharaf km 0.442 (f). road. Improvement of road from Mog Bazar km 0.670 Farid Showdagor's dokan to Jahir Showdagor's house. 54 MGSP/CHO/W-02 (a). Improvement of road from Matamohori km 2.115 1 42.70 NCB BG Yes 25-03-2014 27-05-2014 27-04-2015 bridge south side to Coch Para Terminal road via Basgat and Asian hospital connecting road. (b). Improvement of road from Jahir km 1.000 Showdagor's house to Haizza Pukur Par via Shyed Alam's house. .(c) Improvement of road from Rain km 0.500 Community Centre of Arkan road to Al- Modina Jame Mosjid. (d). Construction of RCC drian at Chiringa km 0.560 Bitussharaf road. Sub-total of Chakoria km 10.074 2 79.20 55 MGSP/SCC/W-01 (a). Improvement of Howladarpara to km 1.00 1 34.80 NCB BG No 28-02-2014 30-04-2014 30-03-2015 Biresh Chandra School road. (b). Improvement of Link road from km 0.53 Shamimabad to Kanishail H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 .(c) Improvement of Gashitula Nobab road km 1.50 from Osmani Medical road to Kazir Bazar road. 56 MGSP/SCC/W-02 (a). Improvement of Kazir Bazar and km 1.20 1 38.40 NCB BG No 28-03-2014 30-05-2014 30-04-2015 Sheikghat main road. (b). Improvement of Zatarpur main Road km 0.85 .(c) Improvement of road from Shibgonj km 0.95 Akbori Mosque to Baluchar Road 57 MGSP/SCC/W-03 (a). Improvement of road at Block D of km 0.60 1 35.60 NCB BG No 28-04-2014 30-06-2014 30-05-2015 Upashahar (b). Improvement of Mendibag road. km 1.45 .(c) Improvement of road from Kadomtali to km 1.00 Shib Bari. (d). Improvement of Road from Dorgah km 1.00 Moholla to Dorshan 58 MGSP/SCC/W-04 (a). Improvement of Gutatikor Road km 0.70 1 35.20 NCB BG No 28-05-2014 30-07-2014 30-06-2015 (b). Improvement of Road at Perss Club km 0.42 area. .(c) Improvement of Dariapara main Road. km 1.00 (d). Improvement of Lechu Bagan road km 1.00 from Airport road to Housing Estate. (e). Improvement of Kamla Bagan and km 0.80 Kunapara Road 59 MGSP/SCC/W-05 (a). Construction of Darussalam Madrasha km 1.00 1 34.80 NCB BG No 15-06-2014 14-08-2014 13-07-2015 Road (b). Improvement of Road no-3 at km 1.00 Chowkidekhi. .(c) Improvement of Chararpar road km 0.90 H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (d). Construction of drain at Hazaribag area km 0.80 60 MGSP/SCC/W-06 (a). Improvement of road at Soyef Khan- km 1.20 1 35.10 NCB BG No 25-06-2014 27-082014 27-06-2015 Londoni road (b). Improvement of Kadomtali Doriashah km 1.00 Mazar road. .(c) Improvement of Gupaltila road and km 1.00 Baluchar road 61 MGSP/SCC/W-07 (a). Improvement of Link road from km 0.90 1 34.40 NCB BG No 25-07-2014 27-09-2014 27-08-2015 Mirapara to Sabuj bag. (b). Construction of drain at Zindapir Mazar km 0.41 to Zinda bazar. .(c) Construction of drain at Darus Salam km 0.85 Madras road opposite of PDB office, Amberkhana. (d). Construction of drain at Picher Mukh to km 0.45 Kalapara (e). Construction of drain at Kazir Bazar km 0.75 and Sheik ghat (f). Construction of drain at Sheikghat km 1.00 Nobab road. Sub-total of Sylhet km 25.26 7 248.30 62 MGSP/STG/W-01 (a). Improvement of South Lanja Para road km 2.296 1 30.80 NCB BG No 28-02-2014 30-04-2014 30-03-2015 from R&H road to Hazi Zahir Ahmed road via Hobigonj PBS & improvement of South Lenja Para Workshop road from R&H road to Hazi Zahir Ahmed road via Khairul Alam Councilor's house. (b). Improvement of road at Biramchar from km 0.655 Syed Elias Saheb's Boiler to Dhaka Sylhet highway. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 .(c) Improvement of West Lanja Par road km 0.745 from Hazi Zahir Ahmed's house to Shaistagonj kamil Madrasa & Sudiakhola road. 63 MGSP/STG/W-02 (a). Improvement of road from R&H road to km 0.216 1 30.20 NCB BG No 25-03-2014 27-05-2014 27-04-2015 Ubahata Government Primary School. (b). Improvement of road from East Borchor km 1.060 road to Rail Way Pond via BD Mithro Saheb's house. .(c) Improvement of road from km 0.662 Jagannathpur Mohululsonam mosque to Sulaiman's house via Zia Uddin's house d. Improvement of road from Sudikhola km 0.844 BC road to Sudikhola Old BC road via Kodar Ali's house. Sub-total of Shaistagonj km 6.478 2 61.00 64 MGSP/MDP/W-01 (a). Construction of Girder Bridge with km 0.042 1 60.40 NCB BG Yes 28-02-2014 30-04-2014 30-03-2015 Approach road on Sonal River at Noagaon to Ganganagar road. (b). Construction of Bituminous Carpeting km 1.521 road from Highway to Rajghat Road up to end of pourashava. .(c) Construction of Bituminous Carpeting km 0.635 road from Highway to Ganganagar house of Probesh Rishi (d). Construction of RCC road from km 0.715 Gumutia road to West of Kabarsthan road via around Krishnanagar. H/Report/Procurement Plan for 18 months Sl Contract Package Contract description Unit Quantity/ Estimated Procedure Procuremen Prior Planned Planed date Planed date Name of Progress of Remarks No Number Number Cost / t Guideline Review* date of bid of Contract of Contractor Procuremen . (in million Method (PPA/BG) * opening Signing Completion t as of Taka) (Yes/No) (Actual date (Actual date (Actual date ............... OR of bid of Contract of Actual opening) Signing) Completion) Contract Price with Contract Currency) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (e). Construction of protection wall by km 1.520 palisading, gradewall & earth filling from Gas field to Shibpur Bridge in Side khal. Sub-total of Madhabpur km 4.433 1 60.40 Grand-total 277.58 63 2491.31 H/Report/Procurement Plan for 18 months