Page 1 1 36784 Procurement Plan I. General 1. Project information : Country: Mozambique ; Borrower: Government of Mozambique ; Project Name: Market-led Smallholder Development in the Zambezi Valley Project ; Project ID: P093165 ; Credit No.: 4198 . 2. Bank’s approval Date of the procurement Plan Original: April, 2006 ; 3. Date of General Procurement Notice : Not Available 4. Period covered by this procurement plan : September 2006 - August 2008 II. Goods and Works and non-consulting services. 1. Prior Review Threshold : Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments 1. ICB (Goods) US$ 150,000 2. NCB (Goods) US$ 150,000 3. ICB (Works) US$ 150,000 4. NCB (Works) US$ 150,000 2. Prequalification . Not Applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As described in the operation manual. 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements : Not applicable. Page 2 2 6. Procurement Packages with Methods and Time Schedule 1 2 3 4 5 6 7 8 9 Ref. No. Contract (Description) Estimated Cost Procure ment Method Prequali fication (yes/no) Domestic Preference (yes/no) Review by Bank (Prior / Post) Expected Bid-Opening Date Comments WORKS 1 Building rehabilitation / extension at district level LS Post November-06 2 Construction new / rehabilitation at admin. post level NCB Post February-07 3 FMA office upgrade LS Post September-06 VEHICLES 4 Vehicles and motorbikes (year 1) ICB Prior August-06 5 GEF – vehicle and motorbikes (year 1) NCB Post September-06 6 Vehicles and motorbikes (year 2) ICB Prior November-07 7 GEF–motorbikes (year 2) LS Post November-07 8 Bicycle for local credit promoters and key farmers (year 2) LS Post September-07 GOODS & EQUIPMENT 9 Supply of IT equipment – and furniture (year 1) NCB Post September-06 10 Supply of IT equipment and furniture (year 2) LS Post January-08 11 GEF – IT equipment & furniture year 1 LS Post September-06 12 GEF - IT equipment & furniture year 2 LS Post January-08 13 Equipment for local credit promoters & SLG union (1 union - year 2) LS Post March-08 14 Contribution to commercial bank installation cost LS Post March-08 15 Technical equipment for extensionists (years 1& 2) LS Post February-07 16 Simple equipment for adm. level extensionists houses (table & chairs) - (years 1 & 2) LS Post February-07 17 Key farmers equipment (simple agricultural equipment) (year 2) LS Post July-07 18 Inputs for demonstration and applied research (years 1 & 2) LS Post March-07 GEF – Field Research and demonstrations (years 1 & 2) LS Post September-07 Page 3 3 1 2 3 4 5 6 7 8 9 Ref. No. Contract (Description) Estimated Cost Procure ment Method Prequali fication (yes/no) Domestic Preference (yes/no) Review by Bank (Prior / Post) Expected Bid-Opening Date Comments NON- CONSULTING SERVICES 19 Communications campaigns (sub-comp 1.1) – (years 1 & 2) LS Post September-06 20 Advertisement campaigns for agribusiness development (year 2) LS Post July-07 21 Agribusiness & Market information service LS Post May-07 22 Partnerships with outgrowers and contract farming LS Post April-07 23 GEF - awareness raising & knowledge sharing LS Post July-07 24 MIS system LS Post May-06 III. Selection of Consultants 1. Prior Review Threshold : Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) US$ 100,000 2. Single Source (Firms / Individual) All 3. Individual consultants US$ 50,000 2. Short list comprising entirely of national consultants : Short list of consultants for services, estimated to cost less than US$ 100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. No. Description of Assignment Estimated Cost Selection Method Review by Bank (Prior / Post) Expected Proposals Submission Date Comments COMPONENT 1 1 Group Promotion Advisor (years 1 to 6) IC Prior June-06 2 Service provider - Group promotion - first group of districts (years 1 to 6) QCBS Prior July-06 3 Service provider - Group promotion - second group of districts (years2 to6) QCBS Prior January-07 Page 4 4 1 2 3 4 5 6 7 Ref. No. Description of Assignment Estimated Cost Selection Method Review by Bank (Prior / Post) Expected Proposals Submission Date Comments 4 Literacy campaigns (years 1 & 2) IC Post January-07 5 Rural Finance – TORs preparation and Proposal evaluation (year 1) IC Post October-06 6 Rural Finance - Audit LCS Post December- 07 7 Rural Finance - Service provider (technical support / facilitation) (year 1 to 6) QCBS Prior February- 07 8 Support to commercial bank partnership definition Post September- 07 9 Rural Finance - Product development (year 2) QCBS Post December- 07 10 Capacity Development Advisor (years 1 to 6) IC Prior June-06 11 District Project Facilitators (district 1 & 2) - 2 contracts (years 1 to 6) IC Prior June-06 12 District Project Facilitators (district 3, 4, 5) - 3 contracts (years mid-2 to 6) IC Prior January-08 13 Driver (district 1 & 2) - (years 1 to 6) IC Post November- 06 14 Driver (district 3, 4, 5) - (years mid-2 to 6) IC Post November- 06 15 GEF – Service provider - land use planning (years 1 to 6) QCBS Prior March-07 16 GEF – Land use hydrology model QCBS Prior March-07 COMPONENT 2 17 Agribusiness & production advisor (years 1 to 6) IC Prior June-06 18 Agribusiness & market studies (years 1 & 2) CQ Post October 06 19 Input Supply Development Programme QCBS Prior March-07 20 Media production & broadcasting for production & post-harvest (years 1 & 2) IC Post April-07 21 Specialized studies & research (years 1 & 2) – (production...) CQ Post April-07 22 GEF – Environment advisor (years 1 to 6) IC Prior June-06 23 Communication Advisor (years 1 to 6) IC Prior June-06 24 GEF - Environmental studies (years 1 & 2) CQ Post April-07 Page 5 5 1 2 3 4 5 6 7 Ref. No. Description of Assignment Estimated Cost Selection Method Review by Bank (Prior / Post) Expected Proposals Submission Date Comments COMPONENT 3 25 CAEIF Advisor (years 1 to 6) IC Prior November- 06 26 Infrastructure advisor (years 1 to 6) IC Prior March-07 27 IDA - Sub-project formulation and implem. support (year 2) IC Post September- 07 28 GEF - Sub-project formulation and implem. support (year 2) IC Post September- 07 29 ESMF and implementation support (year 2) IC Post June-07 COMPONENT 4 30 Field Management Advisor (years 1 to 6) IC Prior June-06 31 Regional Procurement Advisor/Consultant (years 1 to 3) IC Prior June-06 32 Team assistant (years 1 - 6) IC Post June-06 33 Secretary (years 1 to 6) IC Post September- 06 34 Driver - field management (years 1 to 6) IC Post September- 06 35 Financial Management Specialist/Consultant (years 1 to 3) IC Prior May-06 36 Procurement Specialist/Consultant (years 1 to 2) IC Prior May-06 37 Project external monitoring (years 1 to 6) QCBS Prior September- 06 38 GEF – M&E of GEF activities (years 1 to 6) QCBS Prior September- 06 39 External audit (years 1 &2) LCS Post August-06 Page 6 6 V. Trainings and workshops 1 2 3 4 5 6 7 8 9 Ref. No. Contract (Description) Estimated Cost Procure ment Method Prequali fication (yes/no) Domestic Preference (yes/no) Review by Bank (Prior / Post) Expected Bid-Opening Date Comments COMPONENT 1 1 Rural Finance Training - Commercial bank (year 2) Prior* March-08 Multiple trainings 2 District capacity building - Training sessions (years 1 & 2) Prior December-06 Multiple trainings 3 District capacity building - Coaching & on-the job training (years 1 & 2) Prior March-07 Multiple trainings COMPONENT 2 6 Business & technical training for micro & small enterprises (years 1 & 2) Prior May-07 Multiple trainings Agribusiness & marketing study tours & workshops (years 1 & 2) Prior May-07 Multiple 4 Extensionists training and refreshment (years 1 & 2) Prior February-07 Multiple trainings 5 Specialized trainings for producer groups (years 1 & 2) Prior May-07 Multiple trainings 10 GEF - Environmental study tours & workshops (years 1 & 2) Prior May-07 Multiples GEF – Environmental specialized trainings Prior May-07 Multiples COMPONENT 3 ESMF Training (year 1) Prior May-07 COMPONENT 4 11 Training on WB & project guidelines & procedures (years 1 & 2) Prior November-06 Multiple trainings 12 Launching workshop (year 1) Prior November-06 Page 7 7 VI. Matching-grant and grants 1 2 3 4 5 6 7 8 9 Ref. No. Contract (Description) Estimated Cost Procu- rement Method 1 Prequal ification (yes/no) Domestic Preference (yes/no) Review by Bank (Prior / Post) Expected Bid-Opening Date Comments 1 Window 1: Agriculturally related infrastructure (year 2) March-08 2 Window 2: Small-scale Agricultural Investment (year 2) November-07 3 Window 3: Natural Resource Management (year 2) November-07 4 ESMF Compensation and relocation November-07 1 This will be governed by the provisions in the operation manual or a dedicated manual, approved by the World Bank. Page 8 8