Page 1 Document of The World Bank Report No: 58369-AZ RESTRUCTURING PAPER ON A POWER TRANSMISSION PROJECT LOAN TO THE REPUBLIC OF AZERBAIJAN OPEN JOINT STOCK COMPANY “AZERENERJI” December 22, 2010 Regional Vice President: Phillipe H. Le Houerou Country Director: Asad Alam Sector Manager / Director: Ranjit Lamech Task Team Leader: Arturo S. Rivera Page 2 EXTENSION OF CLOSING DATE AZERBAIJAN - POWER TRANSMISSION PROJECT P083341 LOAN NUMBER 7294-AZ 1. The closing date for Azerbaijan, Power Transmission Project P0 83341, Loan No. 7294-AZ will be extended from December 31, 2010, to December 31, 2011. 2. Project implementation is progressing well and the Implementation Rating in the last ISR (May 1, 2010) is ‘Satisfactory.’ Disbursement is currently at 83% of the Loan (USD 40.1m out of USD 48m). 3. A major component of the project is a SCADA/EMS system (Supervisory Control and Data Acquisition/Energy Management System) which is progressing well; however while significant progress has been made to date, implementation of such a system is a complex undertaking and additional time is required for completion of the remaining tasks for the system to become fully operational. These tasks are: (a) Provide remain telemetry from stations and substations to SCADA; (b) Commissioning and acceptance testing of Energy Management System; (c) Tuning of Automatic Generation System; (d) Training of personnel; and (e) Migration of dispatching and operations to the new SCADA system. 4. The audit report for the year ending December 30, 2009, with accompanying draft Management Letter has been submitted to the Bank and arrangements for the 2010 audit have been made by Azerenerji. The Bank Financial Management Supervision was carried out by a Financial Management Specialist on December 14, 2010. The current Financial Management arrangements of the project are moderately satisfactory due to improvement in the quality of IFRS and timeliness of their submission but project and entity audits are not always submitted on time. 5. This will be the first extension of the Closing Date for the project.