94689 National Hydromet Modernization Project - 2 Procurement Plan (March, 2013) Contract Issuing BD/RFP Prep of BD/RFP NO to evluation Bids/Proposals Proc Sel Meth Number of lot Bank review submission publication Evaluation SPN/REI report Doc ## Finish Description Type Start COMPONENT A Strengthening Information Communication Technology (ICT) infrastructure and systems delivering weather, climate and hydrological data and information A.1 Strengthening technical capacity for operational hydrometeorological forecasting, reseach on climate and climate change .1. Supply and installation of at least 500 teraflops supercomputer for the Main Computer Center of Roshydromet (including engineering infrastructure modernization) G 1 ICB SIIS1 prior Sep-14 Jun-15 Jun-15 Jul-15 Sep-15 Nov-15 Dec-15 Jun-17 A.2 Development of regional data storage and archiving systems for improved operational user access to Roshydromet's information resources A.2.a Development of information processing, storage and archiving centers G 1 ICB SIIS1 prior Aug-14 Sep-14 Sep-14 Oct-14 Dec-14 Jan-15 Feb-15 Dec-15 at regional and territorial levels of Roshydromet A.3 Improvement of Roshydromet's integrated information and telecommunication system A.3.a Implementation of the main part of the integrated information- telecommunication system (integration of Data Collection Centers, meteorological, hydrological and upper-air stations into an integrated information-telecommunicaton system of Roshydromet) G 1 ICB SIIS1 prior Feb-15 Mar-15 Mar-15 Apr-15 Jun-15 Jul-15 Aug-15 Feb-17 COMPONENT B Modernization of observation networks B.1 Improvement of the meteorological observation network B.1.a Supply of equipment for surface meteorological observation network G 1 ICB PoG prior Dec-14 Jan-15 Jan-15 Feb-15 May-15 May-15 Jun-15 Dec-16 B.1.b Supply and installation of equipment for the agro-meteorological observation network in the North Caucasus and West Siberian G 1 ICB PoG prior Mar-15 Apr-15 Apr-15 May-15 Jul-15 Aug-15 Aug-15 Feb-17 regions NHMP-2 Procurement Plan 1 Contract Issuing BD/RFP Prep of BD/RFP NO to evluation Bids/Proposals Proc Sel Meth Number of lot Bank review submission publication Evaluation SPN/REI report Doc ## Finish Description Type Start B.1. Additional supply of equipment for marine hydrometeorological network G 1 ICB PoG prior Feb-15 Mar-15 Mar-15 Apr-15 Jul-15 Jul-15 Aug-15 Aug-16 B.1.d Supply of mobile automated calibration laboratories G 1 ICB PoG prior Jul-14 Aug-14 Aug-14 Sep-14 Nov-14 Nov-14 Dec-14 Apr-16 B.1.e Supply of etalon of absolute pressure G 1 ICB PoG prior Jul-14 Aug-14 Aug-14 Sep-14 Nov-14 Nov-14 Dec-14 Oct-15 B.1.f Supply of stationary calibration laboratories G 1 ICB PoG prior Apr-15 May-15 May-15 Jun-15 Aug-15 Sep-15 Oct-15 Apr-17 B.2 Improvement of the upper air observation network B.2.a Modernization of aerological network equipment G 1 ICB PoG prior May-14 Jun-14 Jun-14 Jul-14 Oct-14 Oct-14 Nov-14 Jun-16 B.2b Supply of gas generating stations G 1 ICB PoG prior May-15 Jun-15 Jun-15 Jul-15 Sep-15 Oct-15 Nov-15 May-17 B.2.c Supply and installation of profilers – tools for remote profiling of the atmosphere boundary layer temperature G 1 ICB PoG prior Dec-14 Jan-15 Jan-15 Feb-15 May-15 May-15 Jun-15 Jun-16 B.3 Upgrading of regional operational forecasting units B.3.a Supply and installation of satellite data receiving systems G 1 ICB SIIS1 prior Jul-15 Aug-15 Aug-15 Sep-15 Nov-15 Dec-15 Jan-16 Jan-17 B.4 Modernization of the hydrological network B.4.a Modernization of the hydrological network in the Volga River basin, and development of hydrological forecasting technologies G 1 ICB SIIS1 prior Dec-14 Feb-15 Feb-15 Apr-15 Jun-15 Jul-15 Aug-15 Mar-17 B.4.b Supply of mobile hydrological laboratories G 1 ICB PoG prior May-14 Jun-14 Jun-14 Jul-14 Sep-14 Oct-14 Nov-14 May-16 B.4. Modernization and renewal of the specialized hydrological network G 1 ICB PoG prior Nov-15 Dec-15 Dec-15 Jan-16 Mar-16 Apr-16 May-16 Nov-17 B.4.d Upgrading of the systems at the State Hydrological Institute for hydrological data collection, storage and processing, and for delivery of water cadastre information G 1 ICB SIIS1 prior Feb-16 Mar-16 Mar-16 Apr-16 Jul-16 Jul-16 Aug-16 Feb-18 COMPONENT C Institutional and regulatory strengthening, improvement of service delivery to clients and better preparedness for emergencies C.1 Roshydromet's institutional and regulatory strengthening NHMP-2 Procurement Plan 2 Contract Issuing BD/RFP Prep of BD/RFP NO to evluation Bids/Proposals Proc Sel Meth Number of lot Bank review submission publication Evaluation SPN/REI report Doc ## Finish Description Type Start C.1.a Extending functional capacity and implementation of the automated decision management system at Roshydromet regional branches and centers, and research institutions G 1 ICB SIIS1 prior Jul-14 Aug-14 Aug-14 Sep-14 Nov-14 Nov-14 Dec-14 Feb-16 C.1.b Developing guidelines in support of Project implementation CS 7 CQS RFP prior Nov-14 Oct-14 Dec-14 Jan-15 Feb-15 Feb-15 Mar-15 Jan-16 C.1.c Additional outfitting of the training base of regional training centers with elements of distant learning systems, training materials, and training technical support equipment G 1 ICB SIIS1 prior Feb-16 Mar-16 Mar-16 Apr-16 Jul-16 Jul-16 Aug-16 Jun-17 C.1.e Acquintance with the experience of foreign meteorological services TR mult AP ItQ post Aug-14 n/a Sep-14 Oct-14 Nov-14 n/a Nov-14 Nov-16 C.1.f Services of individual consultants CS mult IC n/a post Feb-15 Feb-15 Apr-15 May-15 Jun-15 Jun-15 Jul-15 Nov-18 C.1.g Workshop on Roshydromet-1 implementation results, and targets for Roshydromet-2 implementation period TR 1 AP ItQ post Jul-14 n/a Jul-14 Aug-14 Sep-14 n/a Oct-14 Oct-14 C.2 Improvement of service delivery to clients C.2.a Development and implementation of the Roshydromet information portal G 1 ICB SIIS1 prior Dec-15 Jan-16 Jan-16 Feb-16 Apr-16 May-16 Jun-16 Mar-17 C.2.b Monitoring of user assessment of services provided by Roshydromet institutions and organizations CS 1 QCBS RFP prior Jan-15 Jan-15 Mar-15 Apr-15 Jun-15 Jun-15 Jul-15 Oct-18 .2.c Economic assessment of the use of hydrometeorological data in weather-dependent sectors of the economy CS 1 QCBS RFP prior Nov-15 Nov-15 Jan-16 Feb-16 Mar-16 n/a Apr-16 Feb-17 .2.d Program for media relations to establish and enhance an overall positive imige of Roshydromet CS 2 CQS RFP prior Jun-15 Jul-15 Jul-15 Aug-15 Oct-15 Nov-15 Dec-15 Oct-16 .2.e Publication of adverising materials G 1 SH ItQ prior Oct-14 n/a Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Sep-15 C.2.f Training activities (workshops, round tables, etc.) on the improvement of relations with hydrometeorological data users TR mult AP ItQ post Jan-15 Jan-15 Mar-15 Apr-15 Jun-15 Jun-15 Jul-15 Jul-16 C.3 Improvement of the emergency preparedness system .3.a Supply and installation of situation centers at Roshydromet institutions and organizations G 1 ICB SIIS1 prior Feb-15 Mar-15 Mar-15 Apr-15 Jun-15 Jul-15 Aug-15 Feb-17 NHMP-2 Procurement Plan 3 Contract Issuing BD/RFP Prep of BD/RFP NO to evluation Bids/Proposals Proc Sel Meth Number of lot Bank review submission publication Evaluation SPN/REI report Doc ## Finish Description Type Start C.3.b Supply of automated mobile systems for hydrometeorological support in emergency situations G 1 ICB PoG prior Nov-16 Dec-16 Dec-16 Jan-17 Apr-17 Apr-17 May-17 Jul-18 C.3.c Developing a hydrometeorological security passport for one or two geographical regions CS 1 CQS RFP prior Feb-15 Feb-15 Apr-15 May-15 Jun-15 n/a Jul-15 Mar-16 C.3.d Training activities (workshops, round tables, etc.) on stregthening interagency coordination in emergency situations TR mult AP ItQ post Apr-15 Apr-15 Jun-15 Jul-15 Aug-15 n/a Sep-15 Apr-17 C.4 Strengthening operational capacity, research and develoment of Roshydromet's system C.4.a Study tours for Roshydromet scientists and specialists to the leading foreign hydrometeorological research and operational facilities CBP 1 AP n/a prior Dec-14 n/a Jan-15 Feb-15 Mar-15 n/a Mar-15 Mar-18 COMPONENT D Project Management D.1 Systems Integrator services CS 1 QCBS RFP prior May-14 Apr-14 Jun-14 Jul-14 Oct-14 Nov-14 Nov-14 Dec-17 D.2 Services of individual consultants CS mult IC n/a post Jul-14 n/a n/a n/a n/a n/a Jul-14 Jun-16 D.3 Documentation translation services CS 10 IC n/a post May-14 n/a n/a n/a n/a n/a May-14 Jul-18 D.4 PIU office equipment G mult SH ItQ post Jun-14 n/a Jun-14 Jun-14 Jul-14 n/a Jul-14 Dec-16 D.5 Audit CS mult LCS RFP prior Oct-14 n/a Nov-14 Dec-14 Feb-15 Jan-15 Mar-15 Dec-18 D.6 Operating costs OC n/a n/a n/a n/a n/a n/a n/a n/a Total: NHMP-2 Procurement Plan 4