Procurement Plan PNG Productive Partnerships in Agriculture project (PPAP) p110959 I. General 1. Bank’s approval Date of the procurement Plan October 8, 2018 2. Date of General Procurement Notice: July 22, 2011 3. Period covered by this procurement plan: October 2018 - June 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: 2. Procurement Method Prior Review Threshold Comments Works (including turnkey, US$1,000,000 Contracts at or above the supply & installation of plant thresholds are subject to the and equipment, and PPP) Bank’s procurement prior review. Goods, information technology US$500,000 Contracts at or above the and non-consulting services thresholds are subject to the Bank’s procurement prior review. 2. Prequalification. N/A 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P110959 March 15, 2010 issued by Department of Agriculture and Livestock, PNG Cocoa Board, PNG Coffee Industry Corporation 5. Any Other Special Procurement Arrangements: N/A July 9, 2010 6. Summary of the Procurement Packages: DAL: Activity Loan / Credit Estimated Reference No. / Review Type Category Market Approach No. Amount (US$) Description: IC-157 / Coconut and Rubber Value Consultant IDA-54110 Post Open 65,700.00 Chain Study for Services PACD - Lead Consultant IC-158 / Coconut and Rubber Value Consultant IDA-54110 Post Open 28,800.00 Chain Study for Services PACD - Support Consultant IC-159 / Spice (Alternate Cash Crops) Value Consultant IDA-54110 Post Open 43,800.00 Chain Study for Services PACD - Lead Consultant IC-160 / Spice (Alternate Cash Crops) Value Consultant IDA-54110 Post Open 20,000.00 Chain Study for Services PACD - Support Consultant IC-161 / Small Livestock Value Consultant Chain Study for IDA-54110 Post Open 43,800.00 Services PACD - Lead Consultant IC-162 / Small Livestock Value Consultant Chain for PACD IDA-54110 Post Open 20,000.00 Services - Support Consultant July 9, 2010 IC-164 / Environment and Social Consultant Safeguard IDA-54110 Post Open 34,000.00 Services Specialist for PACD - Lead Consultant IC-165 / Environment and Social Consultant Safeguard IDA-54110 Post Open 15,400.00 Services Specialist for PACD - Support Consultant CIC Activity Reference Loan / Credit Review Estimated Category Market Approach No. / Description: No. Type Amount (US$) IC74 / Technical Consultant Field Officer, Mt. IDA-54110 Post Open 18,850.00 Services Hagen IC117 / Technical Expert (Coffee Berry Borer) to assess Consultant IDA-54110 Post Open 26,700.00 invasion of CBB + Services Awareness Raising Activities IC136 / Coffee Industry Corporation Consultant IDA-54110 Post Open 70,560.00 Staff Training - IT Services Training IC137 / Systems & Process Review - Consultant CIC Financial IDA-54110 Post Open 68,460.00 Services Management Manual IC138 / CIC Strategic Plan - Consultant IDA-54110 Post Open 132,300.00 Review of current Services strategic plan July 9, 2010 IC139 / RPG & Cherry Trade Policy Consultant (There wil be one IDA-54110 Post Open 162,120.00 Services contract covering several activities) IC140 / Assessment of Coffee Grades & Standards (There Consultant will be one contract IDA-54110 Post Open 235,460.00 Services with several activities - training of CIC staffs) IC141 / Upgrading Information Consultant Management in CIC IDA-54110 Post Open 128,100.00 Services (+procurement of IT Software) IC142 / Sustainable Capacity Building Consultant IDA-54110 Post Open 132,300.00 (Extension support, Services Model Gdns etc.) IC145 / Professional Development - CIC Staffs (Biometrics/statistics Consultant training/Report IDA-54110 Post Open 110,460.00 Services Writing + training of CIC Board members on Strategic Planning) CB Activity Reference Loan / Credit Review Estimated Category Market Approach No. / Description: No. Type Amount (US$) IC-150 / Component Consultant 2 Officer- Kokopo IDA-54110 Post Open 45,320.00 Services PMU July 9, 2010 IC-151 / Administrative Consultant IDA-54110 Post Open 11,308.00 Assistance- Kokopo Services PMU IC-152 / Finance & Administrative Consultant IDA-54110 Post Open 11,340.00 Assistance- Arawa Services PMU IC-128 / Civil/Roads Engineer Consultant IDA-54110 Post Open 45,860.00 (MOMASE)/Madang Services PMU CW-37 / Rehabilitation of 4.0 Km of Ami – Ningalem Feeder Road, IDA-54110 Post Works Open - National 861,462.00 Albiges/Mamblep LLG, Maprik District, East Sepik Province CW-38 / Rehabilitation of 3.930 Km of Hagama – Nimisoli IDA-54110 Post Works Open - National 758,112.00 Feeder Road, East Yangoru LLG, Yangoru Saussia District, East Sepik CW-39 / Rehabilitation of 2.80 Km of Kiami Feeder Road, IDA-54110 Post Works Open - National 450,606.00 Maprik Wora LLG, Maprik District, East Sepik Province CW-40 / Rehabilitation of 5.0 Km of Urita Feeder Road, Bumbita / IDA-54110 Post Works Open - National 762,882.00 Muhian LLG, Maprik District, East Sepik Province July 9, 2010 CW-41 / Rehabilitation of 1.770 Km of Jame Feeder Road, IDA-54110 Post Works Open - National 333,582.00 Maprik Wora LLG, Maprik District, East Sepik Province CW-42 / Construction of Kavavar Bridge, Lower Sikut, Sinivit IDA-47160 Post Works Open - National 699,600.00 LLG, Pomio District, East New Britain Province. CW-43 / CB Office IDA-54110 Prior Works Open - National 1,000,000.00 Extension GO-79 / PNG CCIL Dormitory Request for IDA-54110 Post Goods 12,084.00 Renovation- Tavilo Quotations Head Office GO-80 / Cadmium Smoke Taint Request for IDA-54110 Post Goods 25,000.00 Sampling & Lab Quotations Testing CF-11 / Radio Non-Consultant Request for TF-93093 Post 36,900.00 Drama Production Services Quotations III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment Consultants: firms USD$500,000 Contracts at or above the thresholds are subject to the Bank’s procurement prior review. Consultants: individuals USD$200,000 Contracts at or above the thresholds are subject to the Bank’s procurement prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_100,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. July 9, 2010 PROCUREMENT Papua New Guinea : PNG Productive Partnerships in Agriculture PLAN General Information Country: Papua New Guinea Bank’s Approval Date of the Original Procurement Plan: 2018-10-15 2019-12-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P110959 GPN Date: Project Name: PNG Productive Partnerships in Agriculture Loan / Credit No: IDA / 54110, COFN / C1370 Executing Agency(ies): Coffee Industry Corporation WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CIC-99686-CW-RFB / CW.44.CIC Sub-station - Institutional Strengthening Single Stage - One IDA / 54110 Post Request for Bids Open - National 50,400.00 39,136.50 Completed 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 Renovation (Transit Unit - and Industry Coordination Envelope Building maintenance) PG-CIC-104520-CW-RFB / Under CW.31-CSTB 3677-Rehab of Market Access Single Stage - One IDA / 54110 Post Request for Bids Open - National 310,896.50 0.00 Implementati 2019-04-11 2019-04-16 2019-05-28 2019-06-27 2019-08-01 2019-12-29 3.0km Feeder Road: Kamda Infrastructure Envelope on to Waipip, WHP. PG-CIC-104525-CW-RFB / CW.32-CSTB 3678-Rehab of Under Market Access Single Stage - One 4.0km Feeder Road: Nondugl IDA / 54110 Post Request for Bids Open - National 723,667.56 0.00 Implementati 2019-04-11 2019-04-16 2019-05-28 2019-06-27 2019-08-01 2019-12-29 Infrastructure Envelope Station to Bonong Wo, on Jiwaka Province. PG-CIC-104527-CW-RFB / CW.33-CSTB 3679-Rehab of Pending Market Access Single Stage - One 5.0km of Kuk Old DPI to IDA / 54110 Post Request for Bids Open - National 845,878.15 0.00 Implementati 2019-04-11 2019-04-16 2019-05-28 2019-06-27 2019-08-01 2019-12-29 Infrastructure Envelope Muglamp LLG Feeder Road, on WHP PG-CIC-104726-CW-RFB / Under CW.50-Upgrading of CIC's Institutional Strengthening Single Stage - One IDA / 54110 Post Request for Bids Open - National 17,524.09 0.00 Implementati 2019-04-10 2019-04-15 2019-05-10 2019-06-09 2019-07-14 2020-01-10 Head office & Warehouse and Industry Coordination Envelope on Electrical works. PG-CIC-110105-CW-RFB / CW.51-Genset Connections to Institutional Strengthening Single Stage - One Microlab, Training Center, IDA / 54110 Post Request for Bids Open - National 43,350.00 37,335.32 Signed 2019-04-11 2019-04-16 2019-05-28 2019-06-27 2019-08-01 2019-10-30 and Industry Coordination Envelope Workshop and Farm Office, Aiyura PG-CIC-104514-CW-RFB / CW.30-CSTB 3676-Rehab of Pending Market Access Single Stage - One 4.0km Feeder Road: Avi IDA / 54110 Post Request for Bids Open - National 605,872.95 0.00 Implementati 2019-04-12 2019-04-17 2019-05-29 2019-06-28 2019-08-02 2019-12-30 Infrastructure Envelope Market to Kamdika Village, on Jiwaka Province. PG-CIC-104530-CW-RFB / Pending CW.20-CSTB 3675Rehab of Market Access Single Stage - One IDA / 54110 Post Request for Bids Open - National 1,537,338.65 0.00 Implementati 2019-04-12 2019-04-17 2019-05-29 2019-06-28 2019-08-02 2019-12-30 12.89km of Yasubi to Takai Infrastructure Envelope on Purosa Feeder Road, EHP. PG-CIC-104529-CW-RFB / CW.34-CSTB 3680-Rehab of Pending Market Access Single Stage - One 4.0km of Avi Block - 1 & IDA / 54110 Post Request for Bids Open - National 553,448.62 0.00 Implementati 2019-04-11 2019-04-16 2019-05-28 2019-06-27 2019-08-01 2019-12-29 Infrastructure Envelope 2 Access Feeder Road, Avi on LLG, Jiwaka Province. Page 1 PG-CIC-129311-CW-RFB / CW.55-Maintenance of Two (2) Log Bridges along the Under feeder road that serves Market Access Single Stage - One IDA / 54110 Post Request for Bids Open - National 11,740.00 0.00 Implementati 2019-09-02 2019-09-07 2019-09-12 2019-09-17 2019-09-27 2019-12-26 coffee farmers of the Infrastructure Envelope on Hatavile Partnership under component 2-Eastern Highlands Province. PG-CIC-129324-CW-RFB / CW.57-Rehabilitation of Under Market Access Single Stage - One 7.3km Awande junction to IDA / 54110 Post Request for Bids Open - National 149,190.00 0.00 Implementati 2019-09-02 2019-09-07 2019-09-12 2019-09-17 2019-09-27 2019-12-26 Infrastructure Envelope Yasubi 2 Mile road in on Eastern Highlands Province. PG-CIC-130112-CW-RFB / Under CSTB 3188-Rehab of 5.10km Market Access Single Stage - One IDA / 54110 Post Request for Bids Open - National 783,642.01 0.00 Implementati 2019-09-06 2019-09-11 2019-09-16 2019-09-21 2019-10-05 2019-12-24 of Kapalku to Ngumbkora Infrastructure Envelope on Feeder Road-Jiwaka Province PG-CIC-130114-CW-RFB / Under CSTB 3189-Rehabilitation of Market Access Single Stage - One IDA / 54110 Post Request for Bids Open - National 836,525.84 0.00 Implementati 2019-09-06 2019-09-11 2019-09-18 2019-09-25 2019-10-05 2019-12-24 4.0km of Sigri to Girabw Infrastructure Envelope on Feeder Road in Jiwaka Prov PG-CIC-130115-CW-RFB / CW.58-Rehabilitation of 0.55km Kuk Road Extension Market Access Single Stage - One from Muli Gate to Tipi IDA / 54110 Post Request for Bids Open - National 81,790.00 102,155.30 Signed 2019-09-06 2019-09-11 2019-09-16 2019-09-23 2019-10-05 2019-12-24 Infrastructure Envelope Creek-Muglamp LLG, Dei District, Western Highlands Province. PG-CIC-129315-CW-RFB / CW.56-Rehabilitation of Market Access Single Stage - One IDA / 54110 Post Request for Bids Open - National 113,450.00 115,358.90 Signed 2019-09-02 2019-09-07 2019-09-12 2019-09-17 2019-09-27 2019-12-26 2.18KM Avi Block to Omben Infrastructure Envelope Road in Jiwaka Province. PG-CIC-145545-CW-RFB / CW.64-Rehabilitation of various sections as identified Pending by recent World Bank Market Access Single Stage - One COFN / C1370 Post Request for Bids Open - National 144,830.00 0.00 Implementati 2019-11-14 2019-11-16 2019-11-18 2019-11-20 2019-11-27 2019-12-17 Mission of the 5.1 KM Infrastructure Envelope on Kapalku to Ngumbkora Road in North Waghi District, Jiwaka Province PG-CIC-145759-CW-RFB / CW.66-Rehabilitation of various sections as identified Pending by recent World Bank Market Access Single Stage - One COFN / C1370 Post Request for Bids Open - National 143,040.00 0.00 Implementati 2019-11-15 2019-11-17 2019-11-19 2019-11-21 2019-11-25 2019-12-20 Mission of the 2.55KM Infrastructure Envelope on Kamda to Waipip Road in Tambul Nebilyer District, Western Highlands Province PG-CIC-145758-CW-RFB / CW.65-Rehabilitation of various sections as identified Pending by recent World Bank Market Access Single Stage - One COFN / C1370 Post Request for Bids Open - National 115,920.00 0.00 Implementati 2019-11-15 2019-11-17 2019-11-19 2019-11-21 2019-11-25 2019-12-20 Mission of the 4.0KM of Infrastructure Envelope on Sigiri to Girabw Road in North Waghi District, Jiwaka Province GOODS Page 2 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CIC-96589-GO-RFQ / Under Institutional Strengthening Request for Single Stage - One GD.90.1-CBB Preventative IDA / 54110 Post Open - National 63,000.00 0.00 Implementati 2019-01-30 2019-03-13 2019-03-27 and Industry Coordination Quotations Envelope Equipment-Chemicals on PG-CIC-99455-GO-RFQ / Pending Printing of Regulatory Policy Institutional Strengthening Request for Single Stage - One IDA / 54110 Post Open - National 92,610.00 0.00 Implementati 2019-03-05 2019-04-02 2019-05-02 Guidelines (RPG) GD.99-RPG and Industry Coordination Quotations Envelope on for Coffee PG-CIC-104947-GO-RFQ / Institutional Strengthening Request for Single Stage - One GD.91-Upgrading of CIC IT IDA / 54110 Post Open - National 9,521.10 9,685.83 Completed 2019-03-13 2019-04-10 2019-05-10 and Industry Coordination Quotations Envelope Network Switches PG-CIC-104948-GO-RFQ / GD.92-Laboratory Materials Under Institutional Strengthening Request for Single Stage - One for mass production of IDA / 54110 Post Open - National 49,807.70 0.00 Implementati 2019-03-13 2019-04-07 2019-05-07 and Industry Coordination Quotations Envelope Beaveria Fungus (against on CBB pest). PG-CIC-104951-GO-RFQ / Pending GD.80-Procurement of CIC Institutional Strengthening Request for Single Stage - One IDA / 54110 Post Open - National 52,020.00 0.00 Implementati 2019-03-15 2019-04-17 2019-06-16 Coffee Grading facility and Industry Coordination Quotations Envelope on (WHSS/Aiyura/Lae). PG-CIC-104931-GO-RFQ / GD.83.1-1 x Vehicles for Pending Request for Single Stage - One Coffee PMU & PPAP Sub- IDA / 54110 Productive Partnerships Post Open - National 61,342.27 0.00 Implementati 2019-04-16 2019-05-06 2019-05-13 Quotations Envelope office, Mt Hagen (5x Door -7 on Seaters). PG-CIC-104934-GO-RFQ / Institutional Strengthening Request for Single Stage - One GD.90-CBB Protective IDA / 54110 Post Open - National 25,022.19 25,455.27 Completed 2019-03-13 2019-04-07 2019-04-12 and Industry Coordination Quotations Envelope Equipment. PG-CIC-110099-GO-RFQ / Pending GD.103-Equipment to Institutional Strengthening Request for Single Stage - One IDA / 54110 Post Open - National 104,160.00 0.00 Implementati 2019-04-16 2019-06-11 2019-09-09 R&GSD-Honey Bee and Industry Coordination Quotations Envelope on Extraction Equipment PG-CIC-110102-GO-RFQ / GD.105-Sustainable Capacity Institutional Strengthening Request for Single Stage - One Building (Extension Support, IDA / 54110 Post Open - National 144,500.00 110,999.70 Completed 2019-04-16 2019-06-11 2019-08-10 and Industry Coordination Quotations Envelope Model Gardens-(Purch of Coffee Rehab Tools) PG-CIC-110096-GO-RFQ / GD.100-Procurement of Institutional Strengthening Request for Single Stage - One IDA / 54110 Post Open - National 147,000.00 128,475.63 Completed 2019-04-16 2019-05-26 2019-07-25 Hardware & Core Systems and Industry Coordination Quotations Envelope Software PG-CIC-110098-GO-RFQ / Under GD.102-HRMIS-Human Institutional Strengthening Request for Single Stage - One IDA / 54110 Post Open - National 73,500.00 0.00 Implementati 2019-04-16 2019-06-11 2019-09-09 Resource Management and Industry Coordination Quotations Envelope on Information System for CIC PG-CIC-111115-GO-RFQ / Institutional Strengthening Request for Single Stage - One GD.106-Communication IDA / 54110 Post Open - National 17,340.00 23,340.54 Signed 2019-04-23 2019-05-28 2019-06-11 and Industry Coordination Quotations Envelope Support Material NON CONSULTING SERVICES Page 3 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CIC-130116-NC-DIR / CF.29-Video Shooting, Market Access Request for Single Stage - One Production & Broadcasting of IDA / 54110 Post Open - National 14,700.00 12,335.63 Signed 2019-09-10 2019-10-05 2019-11-04 Infrastructure Quotations Envelope the Rehabilitation of Coffee Economic Roads. PG-CIC-143171-NC-DIR / Pending CF.29-Broadcasting On Institutional Strengthening IDA / 54110 Post Direct Selection Direct 12,280.00 0.00 Implementati 2019-11-25 2019-11-27 2019-12-03 2019-12-28 Television- Video Production and Industry Coordination on on Coffee Roads. PG-CIC-142128-NC-RFQ / IC.628-Service Provider - Pending Request for Single Stage - One Production of a 30 min IDA / 54110 Productive Partnerships Post Open - National 13,860.00 0.00 Implementati 2019-10-28 2019-11-22 2019-12-12 Quotations Envelope Video Documentary for on Coffee Component CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IC140 / Assessment of Coffee Grades & Standards Consultant (There will be one contract Institutional Strengthening Open - Pending IDA / 54110 Prior Qualification 132,300.00 0.00 2019-04-12 2019-04-26 2019-05-24 2019-06-07 2019-07-05 2019-12-12 with several activities - and Industry Coordination International Implementation Selection training of CIC staff and coffee stakeholders) PG-CIC-113212-CS-CQS / Consultant CF.26-National Coffee Institutional Strengthening IDA / 54110 Post Qualification Open - National 59,200.00 0.00 Canceled 2019-05-03 2019-05-08 2019-05-18 2019-05-23 2019-06-02 2019-06-30 Symposium-PHAMA PLUS and Industry Coordination Selection Activities PG-CIC-114034-CS-CQS / Consultant Institutional Strengthening CF.25-CIC Board Members IDA / 54110 Post Qualification Open - National 26,110.00 0.00 Canceled 2019-05-08 2019-05-29 2019-06-12 2019-06-26 2019-07-24 2019-12-21 and Industry Coordination Training-PNG IOD Selection PG-CIC-114037-CS-CQS / CF.26-PHAMA PLUS (Pacific Consultant Institutional Strengthening Horticultural & Agricultural IDA / 54110 Post Qualification Open - National 59,200.00 0.00 Canceled 2019-05-08 2019-05-22 2019-06-19 2019-06-26 2019-07-10 2019-12-27 and Industry Coordination Market Access-Plus Selection Programme) Activities PG-CIC-114023-CS-CQS / Consultant Institutional Strengthening CF.24-Review of CIC IDA / 54110 Post Qualification Open - National 62,910.00 0.00 Canceled 2019-05-08 2019-05-22 2019-06-19 2019-07-03 2019-07-15 2019-12-22 and Industry Coordination Stakeholders Constitution Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IC145 / Professional Development - CIC Staffs (Biometrics/statistics Individual Institutional Strengthening Pending training/Report Writing + IDA / 54110 Post Consultant Open 110,460.00 0.00 2018-10-15 2018-12-19 2018-12-26 2019-01-09 2019-11-05 and Industry Coordination Implementation training of CIC Board Selection members on Strategic Planning) Page 4 IC136 / Coffee Industry Individual Institutional Strengthening Pending Corporation Staff Training - IDA / 54110 Post Consultant Open 70,560.00 0.00 2018-11-09 2019-01-06 2019-01-13 2019-01-27 2019-03-28 and Industry Coordination Implementation IT Training Selection IC137 / Systems & Process Individual Institutional Strengthening Review - CIC Financial IDA / 54110 Post Consultant Open 68,460.00 0.00 Canceled 2018-12-05 2019-02-08 2019-02-15 2019-03-01 2019-05-30 and Industry Coordination Management Manual Selection IC141 / Upgrading Individual Information Management in Institutional Strengthening IDA / 54110 Post Consultant Open 128,100.00 0.00 Canceled 2018-11-02 2019-01-06 2019-01-13 2019-01-27 2019-04-27 CIC (+procurement of IT and Industry Coordination Selection Softwares) IC142 / Sustainable Individual Institutional Strengthening Capacity Building (Extension IDA / 54110 Post Consultant Open 132,300.00 0.00 Canceled 2018-11-30 2019-02-03 2019-02-10 2019-02-24 2019-12-21 and Industry Coordination support, Model Gdns etc.) Selection Individual IC74 / Technical Field Institutional Strengthening Pending IDA / 54110 Post Consultant Open 18,850.00 0.00 2018-11-02 2019-01-06 2019-01-13 2019-01-27 2019-06-30 Officer, Mt. Hagen and Industry Coordination Implementation Selection IC626 / Production of Individual Institutional Strengthening Pending Coffee Industry Strategic & IDA / 54110 Post Consultant Open 46,200.00 0.00 2019-01-25 2019-02-27 2019-03-06 2019-03-20 2019-05-09 and Industry Coordination Implementation Business Plan. Selection IC169 / Procurement Individual Officer, Component 2, IDA / 54110 Productive Partnerships Post Consultant Open 33,600.00 0.00 Canceled 2019-01-18 2019-02-08 2019-02-15 2019-03-01 2019-06-30 Mt.Hagen-WHSS Selection IC117 / Technical Expert Individual (Coffee Berry Borer (CBB)) Institutional Strengthening Under IDA / 54110 Post Consultant Open 26,700.00 0.00 2018-04-30 2018-07-04 2018-07-11 2018-07-25 2018-08-24 to assess invasion of CBB + and Industry Coordination Implementation Selection Awareness Raising Activities IC138 / CIC Strategic Plan Individual Institutional Strengthening Pending - Review of current strategic IDA / 54110 Post Consultant Open 132,300.00 0.00 2018-10-22 2018-12-19 2019-01-02 2019-01-16 2019-11-12 and Industry Coordination Implementation plan Selection IC139 / RPG & Cherry Individual Trade Policy (There will be Institutional Strengthening Pending IDA / 54110 Post Consultant Open 162,120.00 0.00 2018-11-23 2019-01-27 2019-02-03 2019-02-17 2019-05-18 one contract covering several and Industry Coordination Implementation Selection activities) PG-CIC-104924-CS-INDV / IC.628-Service Provider - Individual Institutional Strengthening Production of a 30 min IDA / 54110 Post Consultant Open 8,670.00 0.00 Canceled 2019-04-11 2019-05-30 2019-06-20 2019-07-25 2019-12-22 and Industry Coordination Video Documentary for Selection Coffee Component. PG-CIC-104478-CS-INDV / IC.175-Software Engineer to Individual develop and implement IDA / 54110 Productive Partnerships Post Consultant Direct 28,650.00 52,572.92 Signed 2019-03-06 2019-03-16 2019-03-21 2019-04-04 2019-07-03 Coffee Information Selection Management Systems (CIMS) for Coffee PMU. PG-CIC-112794-CS-INDV / Individual Institutional Strengthening Pending IC.181-Community Liaision IDA / 54110 Post Consultant Direct 10,120.00 0.00 2019-05-01 2019-05-11 2019-05-18 2019-06-01 2019-06-30 and Industry Coordination Implementation & Lands Officer (CLLO) Selection PG-CIC-113209-CS-INDV / Individual Institutional Strengthening Pending IC .182-Information and IDA / 54110 Post Consultant Direct 9,210.00 0.00 2019-05-03 2019-05-08 2019-05-15 2019-05-29 2019-06-30 and Industry Coordination Implementation Communication Officer (ICO) Selection PG-CIC-113211-CS-INDV / Individual IC.183-Assistant Monitoring Institutional Strengthening Pending IDA / 54110 Post Consultant Direct 8,600.00 0.00 2019-05-10 2019-05-20 2019-05-25 2019-06-13 2019-06-30 & Evaluation Officer and Industry Coordination Implementation Selection (AM&EO)-Mt Hagen Page 5 PG-CIC-111125-CS-CQS / IC.630-Design, Develop and Individual Institutional Strengthening Under Implement CMS Intranet for IDA / 54110 Post Consultant Open 34,680.00 0.00 2019-05-08 2019-05-27 2019-06-03 2019-06-17 2019-12-14 and Industry Coordination Implementation CIC (changed from GD.101- Selection CMS-Intranet for CIC) PG-CIC-133935-CS-INDV / Individual Institutional Strengthening IC.635-Data Entry Officer- IDA / 54110 Post Consultant Limited 2,600.00 0.00 Canceled 2019-09-12 2019-09-17 2019-09-22 2019-10-02 2019-12-31 and Industry Coordination Accounts Selection PG-CIC-139775-CS-INDV / Individual IC.637-Coffee Industry Institutional Strengthening IDA / 54110 Post Consultant Open 28,900.00 0.00 Under Review 2019-10-23 2019-11-07 2019-11-12 2019-11-22 2019-12-22 Corporation Business Plan and Industry Coordination Selection Consultant PG-CIC-133939-CS-INDV / Individual Institutional Strengthening IC.636-Financial Management IDA / 54110 Post Consultant Limited 6,940.00 0.00 Canceled 2019-09-12 2019-09-17 2019-09-22 2019-10-02 2019-12-31 and Industry Coordination Consultant Selection PG-CIC-143173-CS-CDS / Institutional Strengthening Pending IC.638-Coffee Curriculum COFN / C1370 Post Direct Selection Direct 37,860.00 0.00 2019-10-29 2019-11-08 2019-12-09 2019-12-29 and Industry Coordination Implementation Consultant PG-CIC-142149-CS-CDS / IC.627-Service Provider - Pending IDA / 54110 Productive Partnerships Post Direct Selection Direct 12,850.00 0.00 2019-10-23 2019-11-02 2019-11-17 2019-12-27 Illustrator (Coffee Extension Implementation Manual) Page 6