Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [[original: Feb. 16, 2012; Revision 1: Feb. 4, 2013;Revision 2: January 2014; Revision 3: October 23, 2014;Revision 4: Feb. 13, 2015; Revision 5: March 17, 2015; Revision 6: December 30, 2015;Revision 7: February 13, 2017;Revision 8: September 8, 2017] 2. Date of General Procurement Notice: March 21, 2013 3. Period covered by this procurement plan: The procurement period of project covered from year Sep 2017 to Dec 2017. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) All 2. NCB (Goods) ≥US$4,000,000 3. Shopping (Goods) N/A 4. ICB (Works) All 5. NCB (Works) ≥US$15,000,000 6. Shopping (Works) N/A 7. (Non-Consultant Services) ≥US$4,000,000 8. Community Participation N/A [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Yes] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project Ningxia Desertification Control and Ecological Protection Project 01/2012 issued by Ningxia Regional PMO 5. Any Other Special Procurement Arrangements: [None] 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. ic Cost Prefere by Bank US$ nce (Prior / Post) million (yes/no) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of 20.98 25 No Post the NCB (Works) Summary of 0.082 1 No Post the NCB (Goods) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) ≥US$2,000,000 2. Single Source (Firms) ≥US$2,000,000 3. Individual ≥US$400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $__equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of number of contracts that will be let under QCBS Summary of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT China : Ningxia Desertification Control and Ecological Protection Project PLAN General Information Country: China Banks Approval Date of the Original Procurement Plan: 2017-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-12-29 Project ID: P121289 GPN Date: Project Name: Ningxia Desertification Control and Ecological Protection Project Loan / Credit No: IBRD / 81590 Executing Agency(ies): Ningxia Forestry Project Management Center WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZW-TJ-73 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 969,696.97 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-16 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-72 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 1,286,181.82 0.00 Canceled 2017-09-15 2017-09-13 2017-09-20 2017-10-20 2017-10-20 2017-11-19 2017-11-16 2017-12-24 2018-08-21 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-74 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,272.73 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-71 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 1,353,696.97 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-16 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-70 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 969,696.97 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-75 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,272.73 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-76 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 827,272.73 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-77 / Zhongwei City Changliushui Baolan Railway Component 1: Controlling Single Stage - One IBRD / 81590 Post Request for Bids Open - National 795,454.55 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 north project area infrastructure Desertification and Degradation Envelope construction in summer 2017 ZW-TJ-69 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 969,696.97 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-68 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 969,696.97 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-67 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 969,696.97 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 ZW-TJ-66 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 969,696.97 0.00 Canceled 2017-09-12 2017-09-13 2017-09-17 2017-10-17 2017-10-20 2017-11-16 2017-11-08 2017-12-21 2018-08-18 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in summer 2017 Page 1 ZW-TJ-81 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,272.73 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-86 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,393.94 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-78 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,272.73 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-82 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,272.73 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-79 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,272.73 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-89 / Zhongwei City Component 1: Controlling Single Stage - One industrial park creating IBRD / 81590 Post Request for Bids Open - National 443,750.00 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope shelterbelts in autumn 2017 ZW-TJ-88 / Zhongwei City Changliushui Baolan Railway Component 1: Controlling Single Stage - One IBRD / 81590 Post Request for Bids Open - National 707,575.75 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 north project area infrastructure Desertification and Degradation Envelope construction in autumn 2017 ZW-TJ-84 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 848,484.85 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-83 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,272.73 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-80 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 727,272.73 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-90 / Zhongwei City Component 1: Controlling Single Stage - One industrial park creating IBRD / 81590 Post Request for Bids Open - National 363,068.18 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope shelterbelts in autumn 2017 ZW-TJ-85 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 810,181.82 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 ZW-TJ-87 / Zhongwei City Changliushui Baolan Railway north area project making straw- Component 1: Controlling Single Stage - One checker sand-barrier for sand IBRD / 81590 Post Request for Bids Open - National 1,177,090.91 0.00 Canceled 2017-09-25 2017-09-30 2017-10-30 2017-11-29 2018-01-03 2018-08-31 Desertification and Degradation Envelope fixation, creating windbreak and sand fixation trees in autumn 2017 GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Controlling Desertification and Degradation YC-HW-1 / Supply of vehicles Component 3: Project Single Stage - One and farm equipment for Livelihood IBRD / 81590 Management, Capacity Building Prior Request for Bids Open - National N 983,490.00 825,104.07 Signed 2016-09-15 2016-11-14 Envelope alternatives and M&E Component 2: Protective Shelterbelt Plantations LT-HW-1 / Litong Xigouyanzi Component 2: Protective Request for Single Stage - One Pending project area forest water - saving IBRD / 81590 Post Open - National 81,667.00 0.00 2017-09-30 2017-11-25 2018-05-24 Shelterbelt Plantations Quotations Envelope Implementation irrigation equipment Page 2 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Controlling Desertification and Degradation NX-ZX-06 / Monitoring and Component 3: Project Consultant Evaluation of Eco-Environmental IBRD / 81590 Management, Capacity Building Prior Qualification Open - International N 291,803.00 285,050.84 Signed 2015-02-12 2015-02-26 Impact and M&E Selection Component 2: Protective Shelterbelt Plantations Component 1: Controlling Desertification and Degradation NX-ZX-05 / Plantation Quality Component 3: Project Consultant and Progress Checking, IBRD / 81590 Management, Capacity Building Prior Qualification Open - International N 295,082.00 288,253.66 Signed 2015-02-12 2015-02-26 Acceptance and Evaluation and M&E Selection Component 2: Protective Shelterbelt Plantations INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3