PROCUREMENT PLAN (Textual Part) Project information: [Bolivia] [BO Community Investment in Rural Areas Project Additional Financing] [P107137] Project Implementation agency: [Emprendimientos Productivos para el Desarrollo Rural Autogestionario (EMPODERAR) Date of the Procurement Plan: [September 29, 2019] Period covered by this Procurement Plan: [2017-2018 Preamble The Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: When approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Basic Norms of the Goods and Services Management System (NB SABS) such arrangements shall be subject to the Procurement Guidelines set on the Credit Agreement. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to the Procurement Guidelines set on the Credit Agreement. Leased Assets: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Bolivia : BO PICAR Community Investment in Rural Areas PLAN General Information Country: Bolivia Bank’s Approval Date of the Original Procurement Plan: 2017-08-18 Revised Plan Date(s): (comma delineated, leave blank if none)2020-10-29 Project ID: P107137 GPN Date: 2017-10-11 Project Name: BO PICAR Community Investment in Rural Areas Loan / Credit No: IDA / 50040, IDA / 57120, IDA / 57130 Executing Agency(ies): EMPODERAR Program WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Contract Description Component Review Type Method Document Amount Amount qualification Document / Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Completion Type (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-001-2017 / Seis 1 - Community Capacity Solicitud de Single Stage - One vehiculos 4 x 4 Tipo IDA / 57120 Posterior Open - National 240,000.00 121,674.10 Finalizado 2017-06-20 2018-09-10 2017-06-25 2017-08-06 2018-11-15 2017-09-05 2018-11-22 2017-10-10 2018-11-26 2018-04-08 2018-12-10 Building ofertas Envelope camioneta GO-002-2017 / Mobiliario 1 - Community Capacity Solicitud de Single Stage - One Sub Regionales UORs - UCN IDA / 57120 Posterior Open - National 14,000.00 11,881.33 Finalizado 2017-07-06 2017-08-31 2017-07-25 2018-02-27 2017-07-31 Building cotizaciones Envelope gestion 2017 GO-003-2017 / Adquisicion de 12 computadoras 1 - Community Capacity Solicitud de Single Stage - One portatiles Area Tecnica IDA / 57120 Posterior Open - National 18,500.00 15,542.69 Finalizado 2017-07-06 2017-08-31 2017-07-26 2018-02-27 2017-07-28 Building cotizaciones Envelope Operativa PICAR - Gestion 2017 GO-004-2017 / Adquisicion de 3 impresoras blanco y 1 - Community Capacity Solicitud de Single Stage - One negro para las UORs y Sub IDA / 57120 Posterior Open - National 3,500.00 1,280.75 Finalizado 2017-07-06 2017-08-31 2017-07-26 2018-02-27 2017-07-28 Building cotizaciones Envelope Regionales del PICAR - Gestion 2017 GO-002-2018 / Adquisicion de 7 computadoras portatiles Area Tecnica Operativa PICAR y de 11 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 45,000.00 0.00 Cancelado 2018-02-20 2018-04-17 2018-10-14 computadoras estacionarias Building cotizaciones Envelope Area Administrativa - Financiera PICAR - Gestion 2018 GO-005-2017 / Adquisicion de equipos de comunicacion (2 centrales telefonicas y 6 1 - Community Capacity Solicitud de Single Stage - One Ejecución IDA / 57120 Posterior Open - National 3,400.00 0.00 2017-10-14 2017-12-09 2018-06-07 aparatos telefonicos) para las Building cotizaciones Envelope pendiente Sub regionales del PICAR - Gestion 2017 GO-006-2017 / Compra de 4 camaras fotograficas para las 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 2,900.00 2,807.53 Finalizado 2017-07-06 2017-08-31 2017-07-26 2018-02-27 2017-07-28 Sub regionales del PICAR - Building cotizaciones Envelope Gestion 2017 GO-007-2017 / Compra 1 Estacion Total para el 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 20,000.00 17,366.14 Finalizado 2017-07-06 2017-08-31 2017-07-26 2018-02-27 2017-07-28 PICAR Area Tecnica Building cotizaciones Envelope Operativa - Gestion 2017 GO-009-2018 / Adquisicion 1 - Community Capacity Solicitud de Single Stage - One dos aires acondicionados sala IDA / 57120 Posterior Open - National 2,400.00 1,107.09 Finalizado 2018-02-20 2018-04-17 2018-05-14 2018-10-14 2018-05-29 Building cotizaciones Envelope servidores GO-008-2017 / Renovacion licencias Office 365 gestion 1 - Community Capacity Adquisición 2017 Se aplica el parrafo 3 IDA / 57120 Posterior Direct 10,200.00 6,197.46 Finalizado 2017-07-03 2017-06-23 2017-07-08 2017-06-30 2017-08-12 2017-06-30 2018-02-08 2017-07-27 Building directa 7 a de las normas de adquisiciones GO-007-2018 / Renovacion licencias Office 365 gestion 1 - Community Capacity Adquisición 2018 Se aplica el parrafo 3 IDA / 57120 Posterior Direct 13,000.00 0.00 Cancelado 2018-07-02 2018-07-07 2018-08-11 2019-02-07 Building directa 7 a de las normas de adquisiciones BO-EMPODERAR-57781-GO- 1 - Community Capacity Solicitud de Single Stage - One Ejecución RFQ / Adquisicion camara IDA / 57120 Posterior Open - National 700.00 0.00 2018-04-14 2018-06-09 2018-12-06 Building cotizaciones Envelope pendiente fotografica BO-EMPODERAR-57788-GO- 1 - Community Capacity Solicitud de Single Stage - One Ejecución RFQ / Adquisicion IDA / 57120 Posterior Open - National 1,445.00 0.00 2018-04-14 2018-06-09 2018-12-06 Building cotizaciones Envelope pendiente termoventiladores Page 1 GO-001-2018 / Mobiliario 1 - Community Capacity Solicitud de Single Stage - One Sub Regionales UOR's - IDA / 57120 Posterior Open - National 13,000.00 12,380.61 Finalizado 2018-03-06 2018-05-01 2018-05-17 2018-10-28 2018-06-11 Building cotizaciones Envelope UCN gestion 2018 GO-003-2018 / Adquisicion de 4 fotocopiadoras de alto 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 17,000.00 16,758.32 Finalizado 2018-02-20 2018-04-17 2018-05-17 2018-10-14 2018-05-29 trafico Sub Regionales Building cotizaciones Envelope PICAR - Gestion 2018 BO-EMPODERAR-58003-GO- RFB / Adquisicion de 23 computadoras portatiles, 7 1 - Community Capacity Solicitud de Single Stage - One computadoras estacionarias, IDA / 57120 Posterior Open - National 115,000.00 100,637.35 Finalizado 2018-04-10 2018-04-24 2018-04-15 2018-05-27 2018-05-24 2018-06-26 2018-06-06 2018-07-31 2018-06-15 2019-01-27 2018-06-30 Building ofertas Envelope 10 impresoras, 1 consola, swichs, un servidor, 4 escanners y 6 data displays GO-006-2018 / Servidor sala de computos - Switch KVM - 1 - Community Capacity Solicitud de Single Stage - One Consola KVM - 2 Switch IDA / 57120 Posterior Open - National 20,100.00 0.00 Cancelado 2018-02-20 2018-04-17 2018-10-14 Building cotizaciones Envelope administrable sala de servidores - Gestion 2018 GO-004-2018 / Adquisicion de 2 escaners de alto trafico 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 8,000.00 0.00 Cancelado 2018-02-20 2018-04-17 2018-10-14 para las Sub regionales del Building cotizaciones Envelope PICAR - Gestion 2018 GO-005-2018 / Adquisicion de 4 impresoras de alto 1 - Community Capacity Solicitud de Single Stage - One trafico para las Sub IDA / 57120 Posterior Open - National 11,200.00 0.00 Cancelado 2018-02-20 2018-04-17 2018-10-14 Building cotizaciones Envelope regionales y UCN del PICAR - Gestion 2018 BO-EMPODERAR-71950-GO- 2 - Community-Driven Solicitud de Single Stage - One RFQ / Adquisicion de IDA / 57120 Posterior Open - National 13,062.00 9,204.05 Finalizado 2018-08-01 2018-09-26 2018-08-30 2019-03-25 2018-08-31 Development Investment cotizaciones Envelope licencias office 365 BO-EMPODERAR-74809-GO- 3 - Coordination, Monitoring Solicitud de Single Stage - One RFQ / Adquisición de IDA / 57120 Posterior Open - National 5,358.00 3,931.98 Finalizado 2018-08-26 2018-10-21 2018-09-25 2019-04-19 2018-09-25 and Evaluation cotizaciones Envelope muebles BO-EMPODERAR-74810-GO- 3 - Coordination, Monitoring Solicitud de Single Stage - One RFQ / Adquisición equipos IDA / 57120 Posterior Open - National 12,828.00 12,290.88 Finalizado 2018-08-26 2018-10-21 2018-09-05 2019-04-19 2018-10-29 and Evaluation cotizaciones Envelope de computación BO-EMPODERAR-74816-GO- RFQ / Adquisición de central 3 - Coordination, Monitoring Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 9,140.00 6,305.64 Finalizado 2018-08-26 2018-10-21 2018-09-05 2019-04-19 2018-09-19 telefónica y aparatos and Evaluation cotizaciones Envelope telefónicos NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Mail de Jhonny Delgadillo de 17.12.14 / Solicitud de No Objecion al Acta de Negociacion suscrita el 8 de diciembre de 2014 y al 1 - Community Capacity Adquisición IDA / 50040 Previa Direct 14,246.00 14,348.77 En ejecución borrador de Adenda para Building directa contratacion directa de PRESAGIO para evaluacion del personal de linea del PICAR NC-001-2017 / Materiales de divulgacion gestion 2017 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 3,700.00 3,545.59 Finalizado 2017-07-08 2017-09-02 2017-07-24 2018-03-01 2017-07-26 Impresion de 5000 folders Building cotizaciones Envelope con imagen institucional NC-002-2017 / Materiales de divulgacion gestion 2017 1 - Community Capacity Solicitud de Single Stage - One Impresion de banners IDA / 57120 Posterior Open - National 7,000.00 868.31 Finalizado 2017-08-08 2017-10-03 2017-10-27 2018-04-01 2017-10-30 Building cotizaciones Envelope rollers pasacalles y otros a requerimiento NC-003-2017 / Materiales de divulgacion gestion 2017 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 7,300.00 6,367.58 Finalizado 2017-09-27 2017-11-22 2017-10-27 2018-05-21 2017-10-30 impresion de manuales a Building cotizaciones Envelope requerimiento NC-001-2018 / Materiales 1 - Community Capacity Solicitud de Single Stage - One de divulgacion gestion 2018 IDA / 57120 Posterior Open - National 32,000.00 14,182.34 Finalizado 2018-03-06 2018-05-01 2018-05-21 2018-10-28 2018-06-05 Building cotizaciones Envelope a requerimiento NC-002-2018 / Elaboracion de letreros de identificacion de proyectos para los 1 - Community Capacity Solicitud de Single Stage - One departamentos de IDA / 57120 Posterior Open - National 49,000.00 0.00 Cancelado 2018-07-07 2018-09-01 2019-02-28 Building cotizaciones Envelope Cochabamba - Chuquisaca - La Paz - Oruro - Potosi - Gestion 2018 Page 2 NC-003-2018 / Transporte y colocado de letreros de identificacion de proyectos 1 - Community Capacity Solicitud de Single Stage - One para los departamentos de IDA / 57120 Posterior Open - National 35,400.00 0.00 Cancelado 2018-09-06 2018-11-01 2019-04-30 Building cotizaciones Envelope Cochabamba - Chuquisaca - La Paz - Oruro - Potosi - Gestion 2018 NC-004-2017 / Elaboracion de 41 letreros de identificacion de proyectos 1 - Community Capacity Solicitud de Single Stage - One para los departamentos de IDA / 57120 Posterior Open - National 14,942.00 0.00 Cancelado 2017-10-07 2017-12-02 2018-05-31 Building cotizaciones Envelope Cochabamba - Chuquisaca - La Paz - Oruro - Potosi - Gestion 2017 NC-005-2017 / Instalacion de 41 letreros de identificacion de proyectos 1 - Community Capacity Solicitud de Single Stage - One para los departamentos de IDA / 57120 Posterior Open - National 14,942.00 0.00 Cancelado 2017-10-07 2017-12-02 2018-05-31 Building cotizaciones Envelope Cochabamba - Chuquisaca - La Paz - Oruro - Potosi Gestion 2017 BO-EMPODERAR-40809-NC- RFQ / Impresión cartilla Institucional del MDRyT, 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 21,012.00 7,163.53 Finalizado 2017-12-22 2017-12-26 2018-02-26 2017-12-31 2018-03-29 agenda Institucional del Building cotizaciones Envelope MDRyT y memoria institucional del MDRyT BO-EMPODERAR-60556-NC- RFQ / Elaboracion de 90 letreros de identificacion de 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 47,230.00 26,845.15 Finalizado 2018-04-29 2018-06-24 2018-05-21 2018-12-21 2018-06-20 proyectos para la Unidad Building cotizaciones Envelope Operativa Departamental Chuquisaca BO-EMPODERAR-60559-NC- RFQ / Elaboracion de 90 letreros de identificacion de 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 47,230.00 29,696.09 Finalizado 2018-04-29 2018-06-24 2018-07-25 2018-12-21 2018-08-24 proyectos para la Unidad Building cotizaciones Envelope Operativa Departamental Oruro BO-EMPODERAR-60561-NC- RFQ / Colocado de 90 letreros de identificacion de 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 32,800.00 16,260.49 Finalizado 2018-04-29 2018-06-24 2018-08-07 2018-12-21 2018-09-07 proyectos para la Unidad Building cotizaciones Envelope Operativa Departamental Chuquisaca BO-EMPODERAR-60565-NC- RFQ / Colocado de 90 letreros de identificacion de 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 32,800.00 45,586.11 Finalizado 2018-04-29 2018-06-24 2018-05-21 2018-12-21 2018-06-21 proyectos para la Unidad Building cotizaciones Envelope Operativa Departamental Oruro BO-EMPODERAR-74792-NC- RFQ / Elaboración de señalética, letreros de 3 - Coordination, Monitoring Solicitud de Single Stage - One identificación externa e IDA / 57120 Posterior Open - National 5,204.00 1,092.62 Finalizado 2018-08-26 2018-10-21 2018-09-05 2019-04-19 2018-09-20 and Evaluation cotizaciones Envelope interna en la UCN y en las unidades operativas departamentales BO-EMPODERAR-74795-NC- 3 - Coordination, Monitoring Solicitud de Single Stage - One RFQ / Impresión de afiches IDA / 57120 Posterior Open - National 8,747.00 6,439.94 Finalizado 2018-08-26 2018-10-21 2018-09-05 2019-04-19 2018-09-26 and Evaluation cotizaciones Envelope institucionales BO-EMPODERAR-74799-NC- 3 - Coordination, Monitoring Solicitud de Single Stage - One RFQ / Fabricación de globos IDA / 57120 Posterior Open - National 6,925.00 6,874.10 Finalizado 2018-08-26 2018-10-21 2018-09-05 2019-04-19 2018-09-26 and Evaluation cotizaciones Envelope inflables BO-EMPODERAR-74801-NC- 3 - Coordination, Monitoring Solicitud de Single Stage - One RFQ / Impresión de folders IDA / 57120 Posterior Open - National 5,103.00 4,487.70 Finalizado 2018-08-26 2018-10-21 2018-09-05 2019-04-19 2018-09-26 and Evaluation cotizaciones Envelope institucionales BO-EMPODERAR-74804-NC- 3 - Coordination, Monitoring Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 5,194.00 1,682.34 Finalizado 2018-08-26 2018-10-21 2018-09-17 2019-04-19 2018-09-26 RFQ / Impresión de trípticos and Evaluation cotizaciones Envelope BO-EMPODERAR-81461-NC- 2 - Community-Driven Solicitud de Single Stage - One RFQ / Impresión de IDA / 57130 Posterior Open - National 1,749.27 1,736.61 Finalizado 2018-10-15 2018-12-10 2018-10-23 2019-06-08 2018-11-12 Development Investment cotizaciones Envelope SEPARATA del PICAR BO-EMPODERAR-81799-NC- RFQ / Manual de campo de 2 - Community-Driven Solicitud de Single Stage - One IDA / 57130 Posterior Open - National 10,962.09 10,480.12 Finalizado 2018-10-17 2018-12-12 2018-11-19 2019-06-10 2018-11-27 procesos administrativos Development Investment cotizaciones Envelope adquisiciones y contrataciones BO-EMPODERAR-90454-NC- 3 - Coordination, Monitoring Solicitud de Single Stage - One RFQ / Impresión agendas IDA / 57120 Posterior Open - National 11,116.00 11,034.73 Finalizado 2018-12-15 2019-02-09 2018-12-20 2019-08-08 2018-12-26 and Evaluation cotizaciones Envelope institucionales BO-EMPODERAR-102632- NC-DIR / CONTRATACION 1 - Community Capacity Adquisición CONSULTOR DE LINEA: IDA / 57120 Posterior Direct 24,640.00 49,981.68 Firmado 2019-02-22 2019-02-26 2019-02-27 2019-02-26 2019-04-03 2019-03-01 2019-09-30 Building directa ESPECIALISTA FINANCIERO DEL PICAR. Page 3 BO-EMPODERAR-102633- NC-DIR / CONTRATACION 1 - Community Capacity Adquisición CONSULTOR DE LINEA: IDA / 57120 Posterior Direct 24,640.00 49,981.68 Firmado 2019-02-22 2019-02-26 2019-02-27 2019-02-26 2019-04-03 2019-03-01 2019-09-30 Building directa CORDINADOR TECNICO DEL PICAR. BO-EMPODERAR-114493- NC-RFQ / IMPRESION DE 3 - Coordination, Monitoring Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 7,300.00 4,703.33 Finalizado 2019-05-15 2019-07-10 2019-05-27 2020-01-06 2019-06-13 AFICHES INFORMATIVOS and Evaluation cotizaciones Envelope DEL PROYECTO PICAR BO-EMPODERAR-115138- 3 - Coordination, Monitoring Solicitud de Single Stage - One NC-RFQ / IMPRESION DE IDA / 57120 Posterior Open - National 1,310.00 1,198.26 Finalizado 2019-05-21 2019-07-16 2019-05-30 2020-01-12 2019-06-24 and Evaluation cotizaciones Envelope BIPTICOS INFORMATIVOS BO-EMPODERAR-122560- NC-RFQ / FABRICACION DE 50 LETREROS DE 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 25,900.00 25,249.46 Finalizado 2019-07-17 2019-09-11 2019-08-30 2020-03-09 2019-09-30 DIFUCION DEL PICAR - Building cotizaciones Envelope DEPARTAMENTAL DE ORURO BO-EMPODERAR-122600- NC-RFQ / FABRICACION DE 50 LETREROS DE 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 25,900.00 23,499.64 Finalizado 2019-07-17 2019-09-11 2019-12-20 2020-03-09 2020-01-20 DIFUSION DEL PICAR - Building cotizaciones Envelope DEPARTAMENTAL DE CHUQUISACA BO-EMPODERAR-134940- 1 - Community Capacity Solicitud de Single Stage - One NC-RFQ / impresión manual IDA / 57120 Posterior Open - National 7,945.00 7,881.42 Finalizado 2019-09-23 2019-11-18 2019-10-18 2020-05-16 2019-10-31 Building cotizaciones Envelope de campo BO-EMPODERAR-136005- NC-RFQ / Colocado de 50 letreros de identificación de 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 18,230.00 15,762.83 Finalizado 2019-10-01 2019-11-26 2019-11-08 2020-05-24 2020-02-20 proyectos para la Unidad Building cotizaciones Envelope Operativa Departamental Chuquisaca BO-EMPODERAR-136015- NC-RFQ / Colocado de 50 letreros de identificación de 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 18,230.00 25,249.46 Finalizado 2019-10-01 2019-11-26 2019-08-30 2020-05-24 2019-10-02 proyectos para la Unidad Building cotizaciones Envelope Operativa Departamental Oruro BO-EMPODERAR-149040- NC-RFQ / IMPRESIÓN DE 1 - Community Capacity Solicitud de Single Stage - One IDA / 57120 Posterior Open - National 1,250.00 1,156.87 Finalizado 2019-12-16 2020-02-10 2019-12-26 2020-08-08 2019-12-27 ADHESIVOS PARA EL Building cotizaciones Envelope PROYECTO PICAR BO-EMPODERAR-202117- NC-RFQ / SERVICIO DE EMPASTE Y FOTOCOPIA PARA LA UNIDAD 3 - Coordination, Monitoring Solicitud de Single Stage - One Ejecución IDA / 57120 Posterior Open - National 14,350.00 0.00 2020-11-05 2020-11-16 2020-12-21 OPERATIVA and Evaluation cotizaciones Envelope pendiente DEPARTAMENTAL DE ORURO - PROYECTO PICAR BO-EMPODERAR-202118- NC-RFQ / SERVICIO DE EMPASTE Y FOTOCOPIA PARA LA UNIDAD 3 - Coordination, Monitoring Solicitud de Single Stage - One Ejecución IDA / 57120 Posterior Open - National 10,500.00 0.00 2020-11-05 2020-11-16 2020-12-21 OPERATIVA and Evaluation cotizaciones Envelope pendiente DEPARTAMENTAL DE COCHABAMBA - PROYECTO PICAR BO-EMPODERAR-202119- NC-RFQ / SERVICIO DE EMPASTE Y FOTOCOPIA PARA LA UNIDAD 3 - Coordination, Monitoring Solicitud de Single Stage - One Ejecución IDA / 57120 Posterior Open - National 10,950.00 0.00 2020-11-05 2020-11-16 2020-12-21 OPERATIVA and Evaluation cotizaciones Envelope pendiente DEPARTAMETAL DE POTOSI - PROYECTO PICAR BO-EMPODERAR-202120- NC-RFQ / SERVICIO DE EMPASTE Y FOTOCOPIA 3 - Coordination, Monitoring Solicitud de Single Stage - One Ejecución PARA LA UNIDAD IDA / 57120 Posterior Open - National 7,000.00 0.00 2020-11-05 2020-11-16 2020-12-21 and Evaluation cotizaciones Envelope pendiente OPERATIVA DEPARTAMENTAL DE LA PAZ - PROYECTO PICAR CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-001-2017 / Auditoria tecnica fiduciaria 1 - Community Capacity Selección basada IDA / 57120 Posterior Open - National 80,000.00 0.00 Cancelado 2017-11-01 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 ambiental y Adquisiciones Building en el menor costo gestiones 2017 y 2018 CS-002-2017 / Auditorias 1 - Community Capacity Selección basada IDA / 57120 Posterior Open - National 80,000.00 14,743.56 Finalizado 2017-11-01 2018-01-11 2017-11-22 2018-01-05 2018-04-11 2018-02-02 2018-04-11 2018-03-04 2018-04-25 2018-04-08 2018-05-09 2018-05-13 2018-05-15 2018-11-09 2018-06-29 Financieras 2017 - 2018 Building en el menor costo Page 4 CS-003-2017 / Auditoria Tecnica - Fiduciaria - 1 - Community Capacity Selección basada IDA / 57120 Posterior Open - National 170,000.00 145,994.46 Finalizado 2017-09-06 2013-12-13 2017-09-27 2017-11-10 2018-01-10 2017-12-08 2018-02-09 2018-01-07 2018-03-09 2018-02-11 2018-04-06 2018-03-18 2018-04-20 2019-03-18 2018-12-06 Ambiental 2014 - 2015 - Building en calidad y costo 2016 CS-004-2017 / Evaluacion de impacto Proyecto de 1 - Community Capacity Selección basada Inversion Comunitaria en IDA / 57120 Posterior Open - National 100,000.00 0.00 Cancelado 2017-09-22 2017-10-13 2017-11-26 2017-12-24 2018-01-23 2018-02-27 2018-04-03 2019-04-03 Building en calidad y costo Areas Rurales Inicial 2012- 2017 CS-002-2018 / Evaluacion Selección basada 1 - Community Capacity de medio termino PICAR IDA / 57120 Posterior en calificaciones Open - National 49,000.00 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Building 2017 - 2018 de consultores Selección basada CS-005-2017 / Seleccion de 1 - Community Capacity IDA / 57120 Posterior en calificaciones Open - National 12,000.00 17,281.62 Finalizado 2017-07-01 2017-06-06 2017-07-22 2017-09-04 2017-09-01 2017-10-04 2017-11-13 2017-11-08 2017-11-14 2018-05-07 2018-11-13 personal 2017-2018 Building de consultores Selección basada CS-006-2017 / Evaluacion al 1 - Community Capacity IDA / 57120 Posterior en calificaciones Open - National 12,000.00 6,362.98 Finalizado 2017-10-04 2017-11-01 2017-10-25 2017-12-08 2018-11-28 2018-01-07 2017-12-07 2018-02-11 2017-12-08 2018-08-10 2018-01-02 personal Gestion 2017 - 2018 Building de consultores CS-008-2017 / Ejecucion del proceso de planificacion 1 - Community Capacity Selección basada participativa comunitaria en IDA / 57120 Posterior Open - National 127,800.00 115,872.32 Finalizado 2017-06-11 2017-05-19 2017-07-02 2017-08-15 2017-08-03 2017-09-12 2017-09-05 2017-10-12 2017-09-15 2017-11-16 2017-09-26 2017-12-21 2017-10-06 2018-12-21 2018-12-31 Building en calidad y costo el marco del PICAR (UOR Valles - Paquete 1) CS-009-2017 / Ejecucion del proceso de planificacion 1 - Community Capacity Selección basada participativa comunitaria en IDA / 57120 Posterior Open - National 131,400.00 117,806.25 Finalizado 2017-06-11 2017-05-19 2017-07-02 2017-08-15 2017-08-03 2017-09-12 2018-09-05 2017-10-12 2017-09-15 2017-11-16 2017-09-26 2017-12-21 2017-10-06 2018-12-21 2018-12-31 Building en calidad y costo el marco del PICAR (UOR Valles - Paquete 2) CS-010-2017 / Ejecucion del proceso de planificacion 1 - Community Capacity Selección basada participativa comunitaria en IDA / 57120 Posterior Open - National 108,000.00 2.28 Finalizado 2017-06-11 2017-05-19 2017-07-02 2017-08-15 2017-08-03 2017-09-12 2017-09-05 2017-10-12 2017-09-14 2017-11-16 2017-09-26 2017-12-21 2017-10-06 2018-12-21 2018-10-08 Building en calidad y costo el marco del PICAR (UOR Valles - Paquete 3) CS-011-2017 / Ejecucion del proceso de planificacion 1 - Community Capacity Selección basada participativa comunitaria en IDA / 57120 Posterior Open - National 84,600.00 100,966.99 Finalizado 2017-06-11 2017-05-19 2017-07-02 2017-08-15 2017-08-03 2017-09-12 2017-09-05 2017-10-12 2017-09-15 2017-11-16 2017-09-26 2017-12-21 2017-10-06 2018-12-21 2018-12-31 Building en calidad y costo el marco del PICAR (UOR Valles - Paquete 4) CS-012-2017 / Ejecucion del proceso de planificacion 1 - Community Capacity Selección basada participativa comunitaria en IDA / 57120 Posterior Open - National 138,600.00 136,302.03 Finalizado 2017-06-11 2017-05-19 2017-07-02 2017-08-15 2017-08-03 2017-09-12 2017-09-08 2017-10-12 2017-09-18 2017-11-16 2017-09-26 2017-12-21 2017-10-17 2018-12-21 2018-11-16 Building en calidad y costo el marco del PICAR (UOR Altiplano - Paquete 5) CS-013-2017 / Ejecucion del proceso de planificacion 1 - Community Capacity Selección basada participativa comunitaria en IDA / 57120 Posterior Open - National 160,200.00 172,787.69 Finalizado 2017-06-11 2017-05-19 2017-07-02 2017-08-15 2017-08-03 2017-09-12 2017-09-08 2017-10-12 2017-09-18 2017-11-16 2017-09-26 2017-12-21 2017-10-13 2018-12-21 2018-12-31 Building en calidad y costo el marco del PICAR (UOR Altiplano - Paquete 6) CS-014-2017 / Ejecucion del proceso de planificacion 1 - Community Capacity Selección basada participativa comunitaria en IDA / 57120 Posterior Open - National 127,800.00 125,306.53 Finalizado 2017-06-11 2017-05-19 2017-07-02 2017-08-15 2017-08-03 2017-09-12 2017-09-08 2017-10-12 2017-09-18 2017-11-16 2017-09-26 2017-12-21 2017-10-13 2018-12-21 2018-11-16 Building en calidad y costo el marco del PICAR (UOR Altiplano - Paquete 7) CS-015-2017 / Ejecucion del proceso de planificacion 1 - Community Capacity Selección basada participativa comunitaria en IDA / 57120 Posterior Open - National 126,000.00 128,328.67 Finalizado 2017-06-11 2017-05-19 2017-07-02 2017-08-15 2017-08-03 2017-09-12 2017-09-08 2017-10-12 2017-09-18 2017-11-16 2017-09-26 2017-12-21 2017-10-13 2018-12-21 2018-12-31 Building en calidad y costo el marco del PICAR (UOR Altiplano - Paquete 8) CS-003-2018 / Produccion Selección basada 1 - Community Capacity videos con informacion de IDA / 57120 Posterior en calificaciones Open - National 40,000.00 0.00 Cancelado 2018-10-15 2018-11-05 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Building logros del EMPODERAR de consultores CS-001-2018 / Estudio que mida el grado de satisfacción de los beneficiarios con el Selección basada proceso de la PPC en 1 - Community Capacity IDA / 57120 Posterior en calificaciones Open - National 49,000.00 0.00 Cancelado 2018-09-14 2018-10-05 2018-11-18 2018-12-18 2019-01-22 2019-07-21 relación a los proyectos Building de consultores identificados en su comunidad en las gestiones 2016 y 2017 BO-EMPODERAR-57793-CS- QCBS / EVALUACION DEL DESEMPEÑO DEL PROYECTO DE INVERSIÓN COMUNITARIA EN ÁREAS RURALES (PICAR) Y DEL GRADO DE SATISFACCIÓN 1 - Community Capacity Selección basada DE LOS BENEFICIARIOS IDA / 57120 Posterior Open - National 102,041.00 52,250.36 Finalizado 2018-04-09 2018-01-12 2018-04-30 2018-06-13 2018-08-10 2018-07-11 2018-09-17 2018-08-10 2018-10-03 2018-09-14 2018-10-15 2018-10-19 2018-10-22 2019-10-19 2019-01-21 Building en calidad y costo CON EL PROCESO DE LA PLANIFICACION PARTICIPATIVA COMUNITARIA Y RESULTADOS DE LOS SUBPROYECTOS PRIMERA FASE Page 5 BO-EMPODERAR-98351-CS- QCBS / AUDITORIA DE 1 - Community Capacity Selección basada IDA / 57130 Posterior Open - National 36,444.00 0.00 Cancelado 2019-02-28 2019-03-21 2019-05-04 2019-06-01 2019-07-01 2019-08-05 2019-09-09 2020-09-08 ADQUISICIONES GESTIÓN Building en calidad y costo 2018 Y 2019 DEL PICAR BO-EMPODERAR-102664-CS- CQS / AUDITORIA ESPECIAL DE ADQUISICIONES Y CONTRATACIONES DEL PROYECTO DE INVERSION COMUNITARIA EN AREAS Selección basada RURALES 1 - Community Capacity IDA / 57120 Posterior en calificaciones Open - National 36,444.00 22,849.71 Finalizado 2019-02-22 2019-08-01 2019-03-15 2019-04-28 2019-09-23 2019-05-28 2019-10-15 2019-07-02 2019-10-21 2019-12-29 2019-12-27 CORRESPONDIENTE A LOS Building de consultores PERIODOS COMPRENDIDOS ENTRE 01 DE MAYO DE 2017 Y 31 DICIEMBRE DE 2018 Y EL 01 DE ENERO DE 2019 Y EL 30 DE NOVIEMBRE DE 2019. BO-EMPODERAR-153324-CS- QCBS / “AUDITORIA DE LOS ESTADOS FINANCIEROS CORRESPONDIENTE AL 1 - Community Capacity Selección basada IDA / 57120 Posterior Open - National 29,250.00 0.00 Cancelado 2020-01-09 2020-01-12 2020-02-13 2020-03-12 2020-03-13 2020-03-17 2020-03-20 2020-04-30 PERIODO COMPRENDIDO Building en calidad y costo ENTRE EL 1 DE ENERO DE 2019 Y EL 30 DE ABRIL DE 2020 (AUDITORIA DE CIERRE). BO-EMPODERAR-153461-CS- QCBS / INFORME DE CIERRE DEL PROYECTO PICAR, QUE COMPRENDE EL ESTUDIO DE: EVALUACIÓN DE LOS IMPACTOS POR 1 - Community Capacity Selección basada TIPOLOGIA DE SUB IDA / 57120 Posterior Open - National 102,000.00 0.00 Cancelado 2020-01-10 2020-01-20 2020-02-09 2020-03-12 2020-03-16 2020-03-17 2020-03-20 2020-03-22 2020-04-30 Building en calidad y costo PROYECTOS EJECUTADOS POR EL PROYECTO, EVALUACIÓN SOCIAL Y GÉNERO DEL PROYECTO, SISTEMATIZACION DE LA INFORMACIÓN AMBIENTAL BO-EMPODERAR-183738-CS- CQS / ESTUDIO DEL PROYECTO PICAR PARA DEFINIR LINEAMIENTOS 1 - Community Capacity Selección basada DE POLÍTICA PÚBLICA IDA / 57130 Posterior Open - National 100,000.00 0.00 Cancelado 2020-07-13 2020-07-13 2020-07-29 2020-08-11 2020-09-08 2020-09-15 2020-09-22 2020-09-28 2020-11-27 Building en calidad y costo QUE MEJORE LA GESTIÓN DEL DESARROLLO RURAL EN BOLIVIA BO-EMPODERAR-184278-CS- CQS / ESTUDIO DEL PROYECTO PICAR PARA DEFINIR LINEAMIENTOS Selección basada 1 - Community Capacity DE POLÍTICA PÚBLICA IDA / 57120 Posterior en calificaciones Open - National 50,000.00 49,239.68 Firmado 2020-07-14 2020-07-21 2020-07-28 2020-08-14 2020-08-11 2020-08-19 2020-08-18 2020-08-24 2020-08-21 2020-10-23 Building QUE MEJORE LA de consultores GESTION DEL DESARROLLO RURAL EN BOLIVIA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-002-2017 / Contratacion 20 Acompanantes para 1 - Community Capacity IDA / 57120 Posterior Individual Open 160,000.00 34,657.38 Finalizado 2017-05-01 2017-06-09 2017-06-19 2017-07-10 2017-08-14 2017-11-15 2018-02-10 2018-07-31 proyectos a ejecutarse en la Building gestion 2017 CI-003-2017 / Contratacion 30 acompanantes para 1 - Community Capacity IDA / 57120 Posterior Individual Open 240,000.00 1,275,162.67 Firmado 2018-01-01 2017-10-22 2018-02-19 2018-12-07 2018-03-12 2018-12-07 2018-04-16 2018-12-07 2018-10-13 proyectos a ejecutarse en la Building gestion 2018 CI-004-2017 / Contratacion 10 Facilitadores para la 1 - Community Capacity IDA / 57120 Posterior Individual Open 70,000.00 9,008.67 Finalizado 2017-05-01 2017-07-04 2017-06-19 2017-07-10 2017-10-25 2017-08-14 2017-11-22 2018-02-10 2017-12-22 elaboracion de proyectos en Building la gestion 2017 CI-005-2017 / Contratacion 10 Facilitadores para la 1 - Community Capacity IDA / 57120 Posterior Individual Open 70,000.00 222,382.20 Finalizado 2018-01-01 2017-10-15 2018-02-19 2018-12-11 2018-03-12 2018-12-11 2018-04-16 2018-05-24 2018-10-13 2018-07-10 elaboracion de proyectos en Building la gestion 2018 CI-006-2017 / Contratacion 1 - Community Capacity 10 Asistentes Tecnicos IDA / 57120 Posterior Individual Open 18,000.00 0.00 En ejecución 2017-05-01 2017-10-15 2017-06-19 2018-04-02 2017-07-10 2018-05-04 2017-08-14 2018-02-10 Building Gestion 2017 CI-007-2017 / Contratacion 1 - Community Capacity 10 Asistentes Tecnicos IDA / 57120 Posterior Individual Open 18,000.00 0.00 En ejecución 2018-01-01 2018-01-02 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Building Gestion 2018 Page 6 CI-008-2017 / Coordinador 1 - Community Capacity IDA / 57120 Posterior Individual Open 39,291.00 0.00 Cancelado 2017-07-01 2017-08-19 2017-09-09 2017-10-14 2018-04-12 Tecnico Building CI-009-2017 / Especialista 1 - Community Capacity IDA / 57120 Posterior Individual Open 43,656.00 26,004.05 Finalizado 2017-05-01 2017-05-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-02-28 Financiero Building CI-011-2017 / Especialista 1 - Community Capacity IDA / 57120 Posterior Individual Open 35,408.00 32,515.15 Firmado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 en Infraestructura Rural Building CI-012-2017 / Especialista 1 - Community Capacity IDA / 57120 Posterior Individual Open 35,408.00 31,039.03 Firmado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 en Genero Building CI-013-2017 / Analista de 1 - Community Capacity IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2020-04-30 desembolsos Building CI-014-2017 / Analista 1 - Community Capacity IDA / 57120 Posterior Individual Open 34,117.00 33,845.26 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-02-28 Financiero Building CI-015-2017 / Asistente 1 - Community Capacity IDA / 57120 Posterior Individual Open 26,557.00 23,185.21 Firmado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 Contable Building CI-016-2017 / Encargado de 1 - Community Capacity Transparencia del Programa IDA / 57120 Posterior Individual Open 26,557.00 15,818.81 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2020-04-30 Building EMPODERAR CI-017-2017 / Operador 1 - Community Capacity IDA / 57120 Posterior Individual Open 35,408.00 21,091.17 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-03 2018-02-10 2020-02-16 Regional UOR Altiplano Building CI-018-2017 / Oficial de 1 - Community Capacity Proyectos Productivos UOR IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2018-12-31 Building Altiplano CI-019-2017 / Oficial de 1 - Community Capacity Proyectos Productivos UOR IDA / 57120 Posterior Individual Open 32,274.00 23,979.18 Rescindido 2017-05-01 2018-03-12 2017-06-19 2018-03-12 2017-07-10 2018-03-12 2017-08-14 2018-03-12 2018-02-10 Building Altiplano CI-020-2017 / Oficial de 1 - Community Capacity Proyectos de Infraestructura IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2020-04-30 Building Rural UOR Altiplano CI-021-2017 / Oficial de 1 - Community Capacity Proyectos de Infraestructura IDA / 57120 Posterior Individual Open 29,046.00 19,224.31 Finalizado 2017-07-01 2017-01-02 2017-08-19 2017-05-02 2017-09-09 2017-05-02 2017-10-14 2017-05-02 2018-04-12 2020-04-30 Building Rural UOR Altiplano CI-022-2017 / Analista 1 - Community Capacity IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2018-01-02 2017-06-19 2018-01-02 2017-07-10 2018-01-02 2017-08-14 2018-01-02 2018-02-10 2019-11-30 Fiduciario UOR Altiplano Building CI-023-2017 / Analista 1 - Community Capacity IDA / 57120 Posterior Individual Open 29,046.00 19,224.31 Finalizado 2017-07-01 2017-01-02 2017-08-19 2017-05-02 2017-09-09 2017-05-02 2017-10-14 2017-05-02 2018-04-12 2020-04-30 Fiduciario UOR Altiplano Building CI-024-2017 / Asistente 1 - Community Capacity administrativo Contable UOR IDA / 57120 Posterior Individual Open 15,480.00 5,040.26 Finalizado 2017-07-01 2018-04-08 2017-08-19 2018-05-30 2017-09-09 2018-06-19 2017-10-14 2018-06-19 2018-04-12 2018-12-31 Building Altiplano CI-025-2017 / Asistente 1 - Community Capacity Mensajero - Chofer UOR IDA / 57120 Posterior Individual Open 14,828.00 8,832.42 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-11-30 Building Altiplano CI-026-2017 / Asistente 1 - Community Capacity Mensajero - Chofer UOR IDA / 57120 Posterior Individual Open 14,828.00 8,832.42 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2020-04-30 Building Altiplano CI-027-2017 / Asistente 1 - Community Capacity administrativo Secretaria IDA / 57120 Posterior Individual Open 14,828.00 18,887.64 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2018-12-31 Building UOR Altiplano CI-028-2017 / Operador 1 - Community Capacity IDA / 57120 Posterior Individual Open 35,408.00 21,091.17 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2020-07-31 Regional UOR Valles Building CI-029-2017 / Oficial de 1 - Community Capacity Proyectos Productivos UOR IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-05-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2020-04-30 Building Valles CI-031-2017 / Oficial de 1 - Community Capacity Proyectos de Infraestructura IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-12-31 Building Rural UOR Valles CI-032-2017 / Oficial de 1 - Community Capacity Proyectos de Infraestructura IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-11-30 Building Rural UOR Valles CI-033-2017 / Analista 1 - Community Capacity IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-11-30 Fiduciario UOR Valles Building CI-034-2017 / Analista 1 - Community Capacity IDA / 57120 Posterior Individual Open 32,274.00 1,602.03 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2020-04-30 Fiduciario UOR Valles Building CI-035-2017 / Asistente 1 - Community Capacity administrativo Contable UOR IDA / 57120 Posterior Individual Open 15,480.00 6,143.22 Finalizado 2017-07-01 2018-04-06 2017-08-19 2018-04-27 2017-09-09 2018-04-27 2017-10-14 2018-05-07 2018-04-12 2018-12-31 Building Valles Page 7 CI-036-2017 / Asistente 1 - Community Capacity administrativo Secretaria IDA / 57120 Posterior Individual Open 14,828.00 5,014.45 Finalizado 2017-05-01 2017-09-26 2017-06-19 2018-06-13 2017-07-10 2018-06-20 2017-08-14 2018-06-20 2018-02-10 2018-12-31 Building UOR Valles CI-037-2017 / Asistente 1 - Community Capacity Mensajero - Chofer UOR IDA / 57120 Posterior Individual Open 14,828.00 8,832.42 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2020-04-30 Building Valles CI-038-2017 / Asistente 1 - Community Capacity Mensajero - Chofer UOR IDA / 57120 Posterior Individual Open 14,828.00 8,832.42 Finalizado 2017-05-01 2017-05-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-11-30 Building Valles CI-039-2017 / Gestor 1 - Community Capacity IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-01-02 2017-06-19 2019-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-11-30 Fortalecimiento Comunitario Building CI-050-2017 / Analista en Adquisiciones EMPODERAR PICAR. Se contratara desde el 1-10-17 al Sr Erick Vela Consultor de linea del 1 - Community Capacity IDA / 57120 Posterior Individual Direct 5,180.00 41,758.61 Firmado 2017-10-01 2017-10-03 2017-10-11 2018-10-01 2017-11-01 2018-10-01 2017-12-06 2018-10-01 2018-06-04 EMPODERAR que Building inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-051-2017 / Oficial Proy Productivos UOR EMPODERAR La Paz. Se contratara desde el 1-10-17 al Sr Oscar Cazorla 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 5,180.00 1,719.83 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-09 2017-12-06 2017-10-09 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-052-2017 / Analista Fiduciario UOR EMPODERAR La Paz. Se contratara desde el 1-10-17 al Sr William Murillo 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 5,180.00 1,714.04 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-12 2017-12-06 2017-10-12 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-053-2017 / Analista Fiduciario UOR EMPODERAR La Paz. Se contratara desde el 1-10-17 al Sr Gary Sanchez 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 5,180.00 1,714.04 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-12 2017-12-06 2017-10-12 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-054-2017 / Operador UOR EMPODERAR Potosi. Se contratara desde el 1-10- 17 al Sr Gunnar Rodriguez Consultor de linea del 1 - Community Capacity IDA / 57120 Posterior Individual Direct 7,007.00 2,318.67 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-17 2017-12-06 2017-10-17 2018-06-04 2017-12-31 EMPODERAR que Building inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-055-2017 / Oficial Proy Productivos UOR EMPODERAR Potosi. Se contratara desde el 1-10-17 al Sr Guido Chirinos 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 5,180.00 0.05 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-09 2017-12-06 2017-10-09 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-056-2017 / Analista Fiduciario UOR EMPODERAR Potosi. Se contratara desde el 1-10-17 al Sr Juan Cruz Consultor 1 - Community Capacity de linea del EMPODERAR IDA / 57120 Posterior Individual Direct 5,180.00 1,714.04 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-13 2017-12-06 2017-10-13 2018-06-04 2017-12-31 Building que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria Page 8 CI-057-2017 / Asistente adm Secretaria UOR EMPODERAR Potosi. Se contratara desde el 1-10-17 al Sr Sulma Aceytuno 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 2,380.00 787.55 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-09 2017-12-06 2017-10-09 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-058-2017 / Asistente administrativo Chofer UOR EMPODERAR Potosi. Se contratara desde el 1-10-17 al Sr Victor Martinez 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 2,380.00 787.55 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-09 2017-12-06 2017-10-09 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-059-2017 / Oficial Proy Productivos UOR EMPODERAR Potosi. Se contratara desde el 1-10-17 al Sr Marcelo Ramos 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 5,180.00 1,719.83 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-09 2017-12-06 2017-10-09 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-060-2017 / Oficial Proy Productivos UOR EMPODERAR Cochabamba. Se contratara desde el 1-10- 17 al Sr Daniel Estivariz 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 5,180.00 1,719.83 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-09 2017-12-06 2017-10-09 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-061-2017 / Oficial Proy. Productivos UOR EMPODERAR La Paz. Se contratara desde el 1-10-17 al Sr Noelia Burgos 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 5,180.00 1,714.04 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-09 2017-12-06 2017-10-09 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-062-2017 / Analista Fiduciario UOR EMPODERAR Cochabamba. Se contratara desde el 1-10- 17 al Sr Victor Torrico 1 - Community Capacity Consultor de linea del IDA / 57120 Posterior Individual Direct 5,180.00 1,714.04 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-11 2017-12-06 2017-10-11 2018-06-04 2017-12-31 Building EMPODERAR que inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-063-2017 / Asistente adm Chofer UOR EMPODERAR Cochabamba. Se contratara desde el 1-10-17 al Sr Gonzalo Tapia Consultor de 1 - Community Capacity IDA / 57120 Posterior Individual Direct 2,380.00 787.55 Finalizado 2017-10-01 2017-09-26 2017-10-11 2017-11-01 2017-10-09 2017-12-06 2017-10-09 2018-06-04 2017-12-31 linea del EMPODERAR que Building inicialmente fue contratado en un proceso competitivo. Se aplica el parrafo 5 6 a de las normas de consultoria CI-001-2017 / Ajuste del Sistema de Informacion Gerencial Georeferenciado - 1 - Community Capacity IDA / 57120 Posterior Individual Direct 15,000.00 12,112.47 Finalizado 2017-07-31 2017-08-01 2017-08-10 2017-11-06 2017-08-31 2017-11-14 2017-10-05 2017-11-15 2018-04-03 2018-05-14 SIGG Se aplica el parrafo Building 5 6 a de las normas de consultoria BO-EMPODERAR-34851-CS- INDV / Contratacion del 1 - Community Capacity IDA / 57120 Posterior Individual Direct 35,091.00 0.00 En ejecución 2017-10-31 2017-01-02 2017-11-10 2017-12-01 2018-01-05 2018-07-04 Coordinador General del Building EMPODERAR CI-030-2017 / Oficial de 1 - Community Capacity Proyectos Productivos UOR IDA / 57120 Posterior Individual Open 32,274.00 19,224.31 Finalizado 2017-05-01 2017-01-02 2017-06-19 2017-05-02 2017-07-10 2017-05-02 2017-08-14 2017-05-02 2018-02-10 2019-11-30 Building Valles Page 9 BO-EMPODERAR-50973-CS- 1 - Community Capacity CQS / Contratación de IDA / 57120 Posterior Individual Open 16,337.55 8,563.53 Finalizado 2018-03-01 2018-04-26 2018-04-19 2018-05-10 2018-06-14 2018-07-23 2018-12-11 2018-12-31 Building Analista Financiero II UCN BO-EMPODERAR-50977-CS- INDV / Contratación de 1 - Community Capacity IDA / 57120 Posterior Individual Open 16,377.55 8,563.53 Finalizado 2018-03-01 2018-04-26 2018-04-19 2018-05-10 2018-06-14 2018-07-23 2018-12-11 2018-12-31 Analista de Desembolso II Building UCN BO-EMPODERAR-51901-CS- INDV / Preparación del 1 - Community Capacity Informe de Evaluación de IDA / 57120 Posterior Individual Open 5,102.04 5,061.46 Finalizado 2018-03-01 2018-03-04 2018-04-19 2018-04-04 2018-05-10 2018-04-05 2018-06-14 2018-04-06 2018-12-11 2018-05-22 Building Medio Termino del Proyecto PICAR BO-EMPODERAR-55375-CS- 1 - Community Capacity INDV / Oficial De IDA / 57120 Posterior Individual Open 36,257.14 16,511.65 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-12 2019-01-01 2018-12-31 Building Infraestructura UOD ORURO BO-EMPODERAR-55377-CS- 1 - Community Capacity INDV / Analista Fiduciario IDA / 57120 Posterior Individual Open 36,257.14 16,054.98 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-20 2019-01-01 2018-12-31 Building UOD ORURO BO-EMPODERAR-55380-CS- 1 - Community Capacity INDV / Analista Fiduciario IDA / 57120 Posterior Individual Open 36,257.14 16,511.65 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-12 2019-01-01 2018-12-31 Building UOD ORURO BO-EMPODERAR-55381-CS- 1 - Community Capacity INDV / Oficial de Proyectos IDA / 57120 Posterior Individual Open 36,257.14 16,452.13 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-12 2019-01-01 2018-12-31 Building Productivos UOD LA PAZ BO-EMPODERAR-55383-CS- INDV / Oficial de 1 - Community Capacity IDA / 57120 Posterior Individual Open 36,257.14 15,940.81 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-22 2019-01-01 2018-12-31 Infraestructura UOD LA Building PAZ BO-EMPODERAR-55386-CS- INDV / Oficial de 1 - Community Capacity IDA / 57120 Posterior Individual Open 36,257.14 16,511.65 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-12 2019-01-01 2018-12-31 Infraestructura UOD LA Building PAZ BO-EMPODERAR-55387-CS- 1 - Community Capacity INDV / Oficial de Proyectos IDA / 57120 Posterior Individual Open 36,257.14 16,395.75 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-13 2019-01-01 2018-12-31 Building Productivos UOD POTOSI BO-EMPODERAR-55388-CS- 1 - Community Capacity INDV / Oficial de IDA / 57120 Posterior Individual Open 36,257.14 16,395.75 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-13 2019-01-01 2018-12-31 Building Infraestructura UOD POTOSI BO-EMPODERAR-55392-CS- 1 - Community Capacity INDV / Oficial de IDA / 57120 Posterior Individual Open 36,257.14 16,455.07 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-13 2019-01-01 2018-12-31 Building Infraestructura UOD POTOSI BO-EMPODERAR-55393-CS- 1 - Community Capacity INDV / Analista Fiduciario IDA / 57120 Posterior Individual Open 36,257.14 16,455.07 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-13 2019-01-01 2018-12-31 Building UOD POTOSI BO-EMPODERAR-55400-CS- INDV / Oficial de 1 - Community Capacity IDA / 57120 Posterior Individual Open 36,257.14 15,368.98 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-04-02 2019-01-01 2018-12-31 Infraestructura de la UOD Building COCHABAMBA BO-EMPODERAR-55402-CS- 1 - Community Capacity INDV / Analista Fiduciario IDA / 57120 Posterior Individual Open 36,257.14 16,511.65 Finalizado 2018-03-22 2017-11-19 2018-05-10 2018-05-31 2018-07-05 2018-03-12 2019-01-01 2018-12-31 Building de la UOD COCHABAMBA BO-EMPODERAR-57374-CS- 2 - Community-Driven INDV / Asistente mensajero IDA / 57130 Posterior Individual Open 6,347.00 0.00 Cancelado 2018-04-16 2018-06-04 2018-06-25 2018-07-30 2019-01-26 Development Investment UOD Chochabamba BO-EMPODERAR-68308-CS- INDV / Asistente 2 - Community-Driven Administrativo Secretaria IDA / 57130 Posterior Individual Direct 15,480.00 4,376.10 Finalizado 2018-06-28 2017-09-26 2018-07-08 2018-07-23 2018-07-29 2018-07-23 2018-09-02 2018-07-23 2019-03-01 2018-07-31 Development Investment Unidad Operativa Departamental La Paz BO-EMPODERAR-68448-CS- INDV / Asistente 2 - Community-Driven Administrativo Secretaria IDA / 57130 Posterior Individual Direct 15,480.00 4,698.75 Finalizado 2018-06-29 2017-09-15 2018-07-09 2018-07-02 2018-07-30 2018-07-02 2018-09-03 2018-07-02 2019-03-02 2018-12-31 Development Investment Unidad Operativa Departamental Potosí BO-EMPODERAR-79775-CS- INDV / Auxiliar 2 - Community-Driven Administrativo de la Unidad IDA / 57130 Posterior Individual Direct 31,804.45 14,771.19 Firmado 2018-09-26 2018-09-26 2018-10-06 2018-09-26 2018-10-27 2018-09-27 2018-12-01 2018-10-01 2019-05-30 Development Investment de Coordinación Nacional (UCN) BO-EMPODERAR-84709-CS- CDS / Desarrollo de la plataforma de 3 - Coordination, Monitoring Selección directa IDA / 57120 Posterior Direct 48,105.00 0.00 Cancelado 2018-10-30 2018-11-27 2018-11-09 2019-01-13 2019-07-12 retroalimentación ciudadana and Evaluation de consultores para em Proyecto EMPODERAR PICAR Page 10 BO-EMPODERAR-84719-CS- CDS / DESARROLLO DE APLICACIONES MOVILES ANDROID DE REGISTRO DE INFORMACIÓN PARA 3 - Coordination, Monitoring Selección directa IDA / 57120 Posterior Direct 18,370.00 16,399.13 Finalizado 2018-10-30 2018-11-28 2018-11-09 2018-11-29 2019-01-13 2018-12-10 2019-07-12 2019-09-06 LOS SISTEMAS DE and Evaluation de consultores INFORMACIÓN GERENCIAL GEOREFERENCIADOS DEL EMPODERAR (PICAR Y DEL PAR II) BO-EMPODERAR-86190-CS- INDV / Asistente 2 - Community-Driven Administrativo II de la IDA / 57120 Posterior Individual Direct 12,495.00 4,246.89 Finalizado 2018-11-07 2018-11-07 2018-11-17 2018-12-03 2018-12-08 2018-12-03 2019-01-12 2018-12-03 2019-07-11 2020-04-30 Development Investment Unidad de Coordinación Nacional BO-EMPODERAR-86191-CS- INDV / Analista Fiduciario 2 - Community-Driven IDA / 57120 Posterior Individual Direct 21,858.00 21,698.99 Finalizado 2018-11-07 2018-11-07 2018-11-17 2018-12-03 2018-12-08 2018-12-03 2019-01-12 2018-12-03 2019-07-11 2020-04-30 de la Unidad Operativa Development Investment Departamental La Paz BO-EMPODERAR-87586-CS- CQS / ASISTENTE ADMINISTRATIVO - 3 - Coordination, Monitoring CHÓFER UNIDAD IDA / 57130 Posterior Individual Open 10,495.00 9,443.82 Finalizado 2018-11-27 2018-11-01 2019-01-15 2018-11-09 2019-02-05 2018-11-14 2019-03-12 2018-11-15 2019-09-08 2020-04-30 and Evaluation OPERATIVA DEPARTAMENTAL DE POTOSÍ BO-EMPODERAR-98352-CS- INDV / PREPARACIÓN DE 1 - Community Capacity IDA / 57130 Posterior Individual Open 6,690.00 0.00 Cancelado 2019-02-01 2019-03-22 2019-04-12 2019-05-17 2019-11-13 INFORME DE MEDIO Building TERMINO PARA EL PICAR BO-EMPODERAR-98354-CS- INDV / 20 FACILITADORES CONSULTORES POR PRODUCTO, PARA LAS COMUNIDADES BENEFICIARIAS DEL 1 - Community Capacity PICAR 2019, IDA / 57130 Posterior Individual Open 120,000.00 252,877.43 Finalizado 2019-02-01 2019-01-15 2019-03-22 2019-01-16 2019-04-12 2019-01-28 2019-05-17 2019-09-16 2019-11-13 2020-03-28 Building RESPONSABLES DE REALIZAR EL ESTUDIO A DISEÑO FINAL DE PROYECTOS PRIORIZADOS POR LAS COMUNIDADES BENEFICIARIAS. BO-EMPODERAR-98353-CS- CQS / 80 ACOMPAÑANTES CONSULTORES POR PRODUCTO PARA LAS COMUNIDADES BENEFICIARIAS DEL 1 - Community Capacity PICAR, RESPONSABLE DE IDA / 57120 Posterior Individual Open 493,148.00 894,907.92 Firmado 2019-02-01 2019-02-28 2019-03-22 2019-02-28 2019-04-12 2019-02-28 2019-05-17 2020-02-10 2019-11-13 2020-09-30 Building LA EJECUCIÓN DE LAS ACTIVIDADES, IMPLEMENTACION FÍSICA, FINANCIERA Y TÉCNICA DE LOS PROYECTOS COMUNALES. BO-EMPODERAR-102634-CS- CDS / AUDITORIA DE LOS ESTADOS FINANCIEROS DEL PROYECTO DE INVERSION COMUNITARIA 1 - Community Capacity Selección directa EN AREAS RURALES IDA / 57120 Posterior Direct 20,000.00 25,536.61 Finalizado 2019-02-22 2019-02-26 2019-03-04 2019-02-26 2019-05-08 2019-04-22 2019-11-04 2019-06-28 Building de consultores CORRESPONDIENTE AL PERIODO COMPRENDIDO ENTRE EL 01 DE ENERO DE 2018 Y EL 31 DICIEMBRE DE 2018. BO-EMPODERAR-106219-CS- CDS / EJECUCION DE 13 PROCESOS DE PLANIFICACION PARTICIPATIVA 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 25,000.00 22,960.05 Finalizado 2019-03-14 2019-03-21 2019-03-24 2019-04-08 2019-05-28 2019-05-29 2019-11-24 2019-07-29 COMUNITARIA EN EL Building de consultores MARCO DEL PICAR (UNIDAD OPERATIVA DEPARTAMENTAL LA PAZ). BO-EMPODERAR-106220-CS- CDS / EJECUCION DE 12 PROCESOS DE PLANIFICACION PARTICIPATIVA 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 25,000.00 20,959.13 Finalizado 2019-03-14 2019-03-21 2019-03-24 2019-04-08 2019-05-28 2019-05-21 2019-11-24 2019-07-19 COMUNITARIA EN EL Building de consultores MARCO DEL PICAR (UNIDAD OPERATIVA DEPARTAMENTAL DE ORURO). Page 11 BO-EMPODERAR-106221-CS- CDS / EJECUCION DE 10 PROCESOS DE PLANIFICACION PARTICIPATIVA 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 17,000.00 16,326.19 Finalizado 2019-03-14 2019-03-21 2019-03-24 2018-04-08 2019-05-28 2019-05-15 2019-11-24 2019-07-14 COMUNITARIA EN EL Building de consultores MARCO DEL PICAR (UNIDAD OPERATIVA DEPARTAMENTAL DE POTOSI). BO-EMPODERAR-106222-CS- CDS / EJECUCION DE 18 PROCESOS DE PLANIFICACION PARTICIPATIVA 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 35,000.00 31,907.37 Finalizado 2019-03-14 2019-03-21 2019-03-24 2019-04-08 2019-05-28 2019-05-15 2019-11-24 2019-07-18 COMUNITARIA EN EL Building de consultores MARCO DEL PICAR (UNIDAD OPERATIVA DEPARTAMENTAL CHUQUISACA). BO-EMPODERAR-106223-CS- CDS / EJECUCION DE 10 PROCESOS DE PLANIFICACION PARTICIPATIVA 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 18,000.00 16,087.73 Finalizado 2019-03-14 2019-03-21 2019-03-24 2019-04-08 2019-05-28 2019-05-23 2019-11-24 2019-08-22 COMUNITARIA EN EL Building de consultores MARCO DEL PICAR (UNIDAD OPERATIVA DEPARTAMENTAL COCHABAMBA). BO-EMPODERAR-114488-CS- CDS / SELECCIÓN DEL PERSONAL TECNICO PARA LA UNIDAD DE 1 - Community Capacity Selección directa COORDINACION IDA / 57120 Posterior Direct 5,300.00 3,927.64 Finalizado 2019-05-10 2019-05-10 2019-05-20 2019-05-14 2019-07-24 2019-05-24 2020-01-20 2019-08-15 Building de consultores NACIONAL Y LAS UNIDADES OPERATIVAS DEPARTAMENTALES DEL PICAR (2019) BO-EMPODERAR-115959-CS- CDS / PRODUCCIÓN DE 12 VIDEOS INFORMATIVOS Y 1 - Community Capacity Selección directa 3 SPOTS DE LOGROS DEL IDA / 57120 Posterior Direct 13,250.00 13,111.43 Finalizado 2019-05-21 2019-05-22 2019-05-31 2019-06-07 2019-08-04 2019-06-18 2020-01-31 2019-07-15 Building de consultores PROYECTO DE INVERSIÓN COMUNITARIA EN ÁREAS RURALES - PICAR BO-EMPODERAR-125722-CS- INDV / OFICIAL DE PROYECTOS PRODUCTIVOS 1 - Community Capacity PARA LA UNIDAD IDA / 57120 Posterior Individual Open 9,200.00 5,420.82 Finalizado 2019-07-31 2019-05-24 2019-09-18 2019-07-29 2019-10-09 2019-09-02 2019-11-13 2019-09-02 2020-05-11 2019-11-30 Building OPERATIVA DEPARTAMENTAL DE ORURO BO-EMPODERAR-125724-CS- INDV / OFICIAL DE PROYECTOS PRODUCTIVOS 1 - Community Capacity PARA LA UNIDAD IDA / 57120 Posterior Individual Open 9,200.00 5,420.82 Finalizado 2019-07-31 2019-05-26 2019-09-18 2019-07-29 2019-10-09 2019-09-02 2019-11-13 2019-09-02 2020-05-11 2019-11-30 Building OPERATIVA DEPARTAMENTAL DE COCHABAMBA BO-EMPODERAR-125727-CS- INDV / ANALISTA FIDUCIARIO PARA LA 1 - Community Capacity IDA / 57120 Posterior Individual Open 9,200.00 7,227.77 Finalizado 2019-07-31 2019-05-24 2019-09-18 2019-07-29 2019-10-09 2019-09-02 2019-11-13 2019-09-02 2020-05-11 2020-04-30 UNIDAD OPERATIVA Building DEPARTAMENTAL DE COCHABAMBA BO-EMPODERAR-125728-CS- INDV / ANALISTA FIDUCIARIO PARA LA 1 - Community Capacity IDA / 57120 Posterior Individual Open 9,200.00 5,420.82 Finalizado 2019-07-31 2019-05-24 2019-09-18 2019-07-29 2019-10-09 2019-09-04 2019-11-13 2019-09-04 2020-05-11 2020-04-30 UNIDAD OPERATIVA Building DEPARTAMENTAL DE POTOSI BO-EMPODERAR-125772-CS- INDV / OFICIAL DE PROYECTOS PRODUCTIVOS 1 - Community Capacity PARA LA UNIDAD IDA / 57120 Posterior Individual Open 9,200.00 5,420.82 Finalizado 2019-07-31 2019-05-31 2019-09-18 2019-07-29 2019-10-09 2019-09-02 2019-11-13 2019-09-02 2020-05-11 2020-04-30 Building OPERATIVA DEPARTAMENTAL DE LA PAZ BO-EMPODERAR-129807-CS- CDS / CONTRATACION DE CONSULTOR DE LINEA OFICIAL DE PROYECTOS 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 7,500.00 5,059.44 Finalizado 2019-08-30 2019-08-30 2019-09-09 2019-09-16 2019-11-13 2019-09-24 2020-05-11 2020-05-31 PRODUCTIVOS PARA LA Building de consultores UNIDAD OPERATIVA DEPARTAMENTAL DE LA PAZ - PICAR BO-EMPODERAR-135992-CS- CDS / DESARROLLO DEL MÓDULO DE 3 - Coordination, Monitoring Selección directa IDA / 57120 Posterior Direct 13,330.00 13,217.64 Finalizado 2019-09-27 2019-10-03 2019-10-07 2019-11-07 2019-12-11 2019-11-11 2020-06-08 2020-07-31 INFORMACIÓN GERENCIAL and Evaluation de consultores PARA EL PROGRAMA EMPODERAR Page 12 BO-EMPODERAR-151423-CS- INDV / CONTRATACIÓN DE RESPONSABLE 2 - Community-Driven AMBIENTAL PARA EL IDA / 57120 Posterior Individual Direct 8,320.00 7,958.29 Finalizado 2019-12-20 2020-01-02 2019-12-30 2020-01-02 2020-01-02 2020-01-02 2020-01-02 2020-01-02 2020-04-30 2020-04-30 Development Investment PROYECTO DE INVERSIÓN COMUNITARIA EN ÁREAS RURALES BO-EMPODERAR-152042-CS- INDV / Oficial de Proyectos 2 - Community-Driven Productivos para la Unidad IDA / 57120 Posterior Individual Direct 3,565.83 7,140.91 Finalizado 2019-12-27 2020-01-02 2020-01-02 2020-01-02 2020-01-02 2020-01-02 2020-01-02 2020-01-02 2020-04-30 2020-04-30 Development Investment Operativa Departamental de Chuquisaca PICAR BO-EMPODERAR-153320-CS- CDS / AUDITORIA ESPECIAL DE ADQUISICIONES Y CONTRATACIONES (ENCARGO DE ASEGURAMIENTO RAZONABLE DE 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 43,820.00 58,488.02 Firmado 2020-01-09 2020-01-21 2020-01-14 2020-01-24 2020-02-17 2020-06-30 2020-04-30 ADQUISICIONES Y Building de consultores CONTRATACIONES) CORRESPONDIENTE A LOS PERIODOS COMPRENDIDOS ENTRE EL 1 DE ENERO DE 2019 Y EL 31 DE MARZO DE 2020. BO-EMPODERAR-154199-CS- CDS / AUDITORIA DE LOS ESTADOS FINANCIEROS CORRESPONDIENTE AL 1 - Community Capacity Selección directa PERIODO COMPRENDIDO IDA / 57120 Posterior Direct 29,250.00 43,179.07 Finalizado 2020-01-16 2020-01-20 2020-01-21 2020-01-30 2020-03-02 2020-02-28 2020-08-29 2020-07-27 Building de consultores ENTRE EL 1 DE ENERO DE 2019 Y EL 30 DE ABRIL DE 2020 (AUDITORIA DE CIERRE) BO-EMPODERAR-154621-CS- INDV / INFORME DE EVALUACIÓN SOCIAL Y 1 - Community Capacity GENERO DEL PROYECTO IDA / 57120 Posterior Individual Open 10,000.00 9,970.93 Finalizado 2020-01-20 2020-01-24 2020-03-06 2020-02-13 2020-03-10 2020-02-14 2020-03-15 2020-02-18 2020-04-30 2020-07-31 Building DE INVERSIÓN COMUNITARIA EN AREAS RURALES - PICAR BO-EMPODERAR-154628-CS- INDV / CONSULTORIA PARA SISTEMATIZAR LA INFORMACIÓN AMBIENTAL DE LOS 1 - Community Capacity IDA / 57120 Posterior Individual Open 10,000.00 8,783.39 Finalizado 2020-01-20 2020-01-24 2020-03-06 2020-02-14 2020-03-10 2020-02-14 2020-03-15 2020-02-19 2020-04-30 2020-07-31 SUBPROYECTOS Building FINANCIADOS POR EL PROYECTO DE INVERSIÓN COMUNITARIA EN AREAS RURALES (PICAR) BO-EMPODERAR-156390-CS- CDS / Evaluación del grado de satisfacción de los beneficiarios con el proceso 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 100,000.00 99,633.04 Firmado 2020-01-28 2020-02-14 2020-02-02 2020-02-20 2020-03-05 2020-03-05 2020-04-30 de la planificación Building de consultores participativa comunitaria y resultados de los subproyectos (Tercera Fase). BO-EMPODERAR-173940-CS- INDV / RESPONSABLE AMBIENTAL PARA LA 2 - Community-Driven UNIDAD DE IDA / 57120 Posterior Individual Direct 4,050.00 3,979.15 Finalizado 2020-05-15 2020-06-01 2020-05-21 2020-06-01 2020-05-21 2020-06-01 2020-06-01 2020-06-01 2020-07-31 2020-07-31 Development Investment COORDINACIÓN NACIONAL DEL PROYECTO PICAR BO-EMPODERAR-173941-CS- INDV / OFICIAL DE PROYECTOS PRODUCTIVOS PARA LA UNIDAD 2 - Community-Driven IDA / 57120 Posterior Individual Direct 3,600.00 8,926.14 Firmado 2020-05-15 2020-06-01 2020-05-21 2020-06-01 2020-05-21 2020-06-01 2020-06-01 2020-06-01 2020-07-31 OPERATIVA Development Investment DEPARTAMENTAL DE CHUQUISACA DEL PROYECTO PICAR BO-EMPODERAR-173942-CS- INDV / OFICIAL DE PROYECTOS PRODUCTIVOS PARA LA UNIDAD 2 - Community-Driven IDA / 57120 Posterior Individual Direct 3,600.00 8,926.14 Firmado 2020-05-15 2020-06-01 2020-05-21 2020-06-01 2020-05-21 2020-06-01 2020-06-01 2020-06-01 2020-07-31 OPERATIVA Development Investment DEPARTAMENTAL DE LA PAZ DEL PROYECTO PICAR BO-EMPODERAR-175159-CS- INDV / OFICIAL DE PROYECTOS PRODUCTIVOS 2 - Community-Driven PARA LA UNIDAD IDA / 57120 Posterior Individual Direct 3,600.00 8,926.14 Firmado 2020-05-22 2020-06-01 2020-05-28 2020-06-01 2020-05-28 2020-06-01 2020-06-01 2020-06-01 2020-07-31 Development Investment OPERATIVA DEPARTAMENTAL DE ORURO Page 13 BO-EMPODERAR-175161-CS- INDV / AUXILIAR CONTABLE UNIDAD 2 - Community-Driven IDA / 57120 Posterior Individual Direct 1,605.00 3,978.28 Firmado 2020-05-22 2020-06-01 2020-05-28 2020-06-01 2020-05-28 2020-06-01 2020-06-01 2020-06-01 2020-07-31 OPERATIVA Development Investment DEPARTAMENTAL DE ORURO BO-EMPODERAR-175167-CS- INDV / ANALISTA FIDUCIARIO UNIDAD 2 - Community-Driven IDA / 57120 Posterior Individual Direct 3,600.00 7,438.52 Firmado 2020-05-22 2020-06-05 2020-05-28 2020-06-05 2020-05-28 2020-06-05 2020-06-01 2020-06-05 2020-07-31 OPERATIVA Development Investment DEPARTAMENTAL DE LA PAZ BO-EMPODERAR-175169-CS- INDV / OFICIAL DE PROYECTOS PRODUCTIVOS 2 - Community-Driven PARA LA UNIDAD IDA / 57120 Posterior Individual Direct 3,600.00 8,926.14 Firmado 2020-05-22 2020-06-01 2020-05-28 2020-06-01 2020-05-28 2020-06-01 2020-06-01 2020-06-01 2020-07-31 Development Investment OPERATIVA DEPARTAMENTAL DE POTOSI BO-EMPODERAR-175174-CS- INDV / ANALISTA FIDUCIARIO PARA LA 2 - Community-Driven IDA / 57120 Posterior Individual Direct 3,600.00 8,926.14 Firmado 2020-05-22 2020-06-01 2020-05-28 2020-06-01 2020-05-28 2020-06-01 2020-06-01 2020-06-01 2020-07-31 UNIDAD OPERATIVA Development Investment DEPARTAMENTAL DE POTOSI BO-EMPODERAR-175178-CS- INDV / ANALISTA FIDUCIARIO PARA LA 2 - Community-Driven IDA / 57120 Posterior Individual Direct 3,600.00 8,926.14 Firmado 2020-05-22 2020-06-01 2020-05-28 2020-06-01 2020-05-28 2020-06-01 2020-06-01 2020-06-01 2020-07-31 UNIDAD OPERATIVA Development Investment DEPARTAMENTAL DE COCHABAMBA BO-EMPODERAR-175180-CS- INDV / OFICIAL DE PROYECTOS PRODUCTIVOS 2 - Community-Driven PARA LA UNIDAD IDA / 57120 Posterior Individual Direct 3,600.00 8,926.14 Firmado 2020-05-22 2020-06-01 2020-05-28 2020-06-01 2020-05-28 2020-06-01 2020-06-01 2020-06-01 2020-07-31 Development Investment OPERATIVA DEPARTAMENTAL DE COCHABAMBA BO-EMPODERAR-181499-CS- INDV / OFICIAL DE INFRAESTRUCTURA PARA 2 - Community-Driven IDA / 57120 Posterior Individual Direct 1,780.00 7,140.91 Firmado 2020-06-23 2020-07-01 2020-06-29 2020-07-01 2020-06-29 2020-07-01 2020-07-01 2020-07-01 2020-07-31 LA UNIDAD OPERATIVA Development Investment DEPARTAMENTAL DE LA PAZ BO-EMPODERAR-181508-CS- INDV / ANALISTA DE DESEMBOLSOS PARA LA 2 - Community-Driven UNIDAD DE IDA / 57120 Posterior Individual Direct 2,875.00 2,142.22 Firmado 2020-06-23 2020-06-24 2020-06-25 2020-06-24 2020-06-25 2020-06-24 2020-06-25 2020-06-24 2020-07-31 Development Investment COORDINACION NACIONAL DEL PROYECTO PICAR BO-EMPODERAR-183262-CS- CDS / AUDITORÍA DE LOS ESTADOS FINANCIEROS DEL PROYECTO PICAR, FINANCIADO MEDIANTE LOS CONVENIOS DE CREDITO AIF 5712-BO Y 1 - Community Capacity Selección directa IDA / 57120 Posterior Direct 40,000.00 31,246.92 Firmado 2020-07-08 2020-07-10 2020-07-13 2020-07-15 2020-07-30 2020-07-31 2020-09-28 5713-BO, Building de consultores CORRESPONDIENTE AL PERIODO COMPRENDIDO ENTRE EL 1 DE ENERO DE 2020 y EL 31 DE JULIO DE 2020 (AUDITORIA DE CIERRE). BO-EMPODERAR-183983-CS- INDV / AUXILIAR CONTABLE PARA LA 2 - Community-Driven UNIDAD OPERATIVA IDA / 57120 Posterior Individual Open 5,585.00 2,413.47 Firmado 2020-07-13 2020-07-07 2020-07-30 2020-07-24 2020-07-31 2020-07-24 2020-07-31 2020-07-31 2020-10-29 Development Investment DEPARTAMENTAL DE CHUQUISACA DEL PROYECTO PICAR BO-EMPODERAR-198823-CS- CQS / CONTRATACION DE CONSULTOR PARA REALIZAR LA MEMORIA 1 - Community Capacity IDA / 57120 Posterior Individual Open 10,000.00 0.00 En ejecución 2020-10-08 2020-10-22 2020-10-25 2020-10-27 2020-11-01 2020-12-16 DE CIERRE DEL Building PROYECTO DE INVERSION COMUNITARIA EN AREAS RURALES - PICAR Page 14