Procurement Plan Jamaica Disaster Vulnerability Reduction Project (P146965) I. General 1. Bank’s approval Date of the procurement Plan: Revision 1 of Updated Procurement Plan, December 2017 2. Date of General Procurement Notice: N/A 3. Period covered by this procurement plan: July 2016 – December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1 million All 2. NCB (Goods) Above US$ 0.1 million n/a 3. ICB (Works) Above US$ 7.5 million All 4. NCB (Works) Above US$ 0.2 million n/a 5. (Non-Consultant Services) Above US$ 1 million All III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2 million 2. Single Source (Firms) Above US$ 1 million 3. Individual Above US$ 0.4 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Jamaica : Jamaica Disaster Vulnerability Reduction Project PLAN General Information Country: Jamaica Bank’s Approval Date of the Original Procurement Plan: 2017-12-18 2020-07-13 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146965 GPN Date: Project Name: Jamaica Disaster Vulnerability Reduction Project Loan / Credit No: IBRD / 85810 Executing Agency(ies): Jamaica Social Investment Fund WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RISK REDUCTION - 13 / Single Stage - One Drainage Works - Church IBRD / 85810 Risk Reduction Post Request for Bids Open - National 750,000.00 602,130.62 Signed 2017-12-01 2018-01-15 2017-12-06 2018-01-17 2018-02-13 2018-05-01 2018-05-30 2018-06-05 2018-07-18 2018-12-02 Envelope Pen UNDERSTANDING RISK - 12 / Construction and Technical Assistance for Upgrading of Towers (Font Request for Single Stage - One IBRD / 85810 Improved Disaster and Post Limited 33,127.00 30,130.35 Completed 2017-02-18 2017-02-17 2017-04-15 2017-03-23 2017-10-12 Hill, Yallahs, UWI, Stoney Quotations Envelope Climate Resilience Hill + minor works at stations) RISK REDUCTION - 3 / Single Stage - One Construction of Yallahs Fire IBRD / 85810 Risk Reduction Post Request for Bids Open - National 1,300,000.00 818,126.34 Signed 2018-09-01 2019-02-14 2018-09-06 2018-11-15 2019-03-19 2018-12-31 2019-04-01 2019-02-04 2019-12-03 2019-08-03 Envelope Station RISK REDUCTION - 1 / Single Stage - One Construction of Montego Bay IBRD / 85810 Risk Reduction Post Request for Bids Open - National 2,500,000.00 4,078,202.17 Signed 2018-10-01 2018-09-20 2018-10-06 2018-12-15 2018-11-06 2019-01-30 2019-01-08 2019-03-06 2019-11-05 2019-09-02 Envelope Fire Station RISK REDUCTION - 2 / Single Stage - One Construction of Port Maria IBRD / 85810 Risk Reduction Post Request for Bids Open - National 1,500,000.00 1,605,219.47 Signed 2018-08-01 2018-10-25 2018-08-06 2018-10-15 2019-01-31 2018-11-30 2019-12-04 2019-01-04 2019-10-22 2019-07-03 Envelope Fire Station RR - 17 - 1 / Port Royal Single Stage - One IBRD / 85810 Risk Reduction Post Request for Bids Open - National 4,730,000.00 6,801,990.50 Signed 2019-03-18 2019-04-16 2019-03-23 2019-06-01 2019-06-18 2019-08-20 2019-07-22 2019-10-07 2020-03-03 2021-04-07 Coastal Revetment Works Envelope RISK REDUCTION - 15 / Pending Open - Single Stage - One Big Pond/Myton Gully IBRD / 85810 Risk Reduction Prior Request for Bids 8,760,000.00 0.00 Implementat 2020-09-07 2020-09-12 2020-11-21 2021-01-06 2021-02-10 2021-08-09 International Envelope Drainage Works ion RISK REDUCTION - 17 / Single Stage - One Port Royal Coastal IBRD / 85810 Risk Reduction Post Request for Bids Open - National 4,730,000.00 0.00 Canceled 2018-06-01 2018-08-20 2018-06-06 2018-08-15 2018-10-23 2018-09-30 2019-01-28 2018-11-04 2019-05-03 Envelope Revetment Works Pending RR - 9 / St. Benedicts Single Stage - One IBRD / 85810 Risk Reduction Post Request for Bids Open - National 450,000.00 0.00 Implementat 2020-10-04 2020-10-09 2020-11-20 2020-12-20 2021-01-24 2021-07-23 Primary Construction Works Envelope ion Technical Assistance for UR - 10 - 1 / Supply & Single Stage - One IBRD / 85810 Improved Disaster and Post Request for Bids Open - National 33,000.00 23,339.03 Completed 2020-01-13 2017-11-20 2020-01-18 2020-02-29 2017-12-01 2020-03-30 2017-12-11 2020-05-04 2017-12-20 2020-10-31 Installation of Pole Mount Envelope Climate Resilience GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UNDERSTANDING RISK - Technical Assistance for Request for Single Stage - One 4 / Supply of Computer IBRD / 85810 Improved Disaster and Post Limited 16,726.00 17,989.29 Completed 2017-02-01 2017-01-27 2017-03-29 2017-03-17 2017-09-25 2020-03-09 Quotations Envelope Server (1) & Monitors (8) Climate Resilience UNDERSTANDING RISK - Technical Assistance for 5 / Supply of Oscilloscope Request for Single Stage - One IBRD / 85810 Improved Disaster and Post Limited 8,986.00 18,900.35 Completed 2017-03-01 2017-03-16 2017-04-26 2017-04-05 2017-10-23 2017-09-19 (1) and Spectrum Analyzer Quotations Envelope Climate Resilience (1) UNDERSTANDING RISK - 9 / Supply & Installation Technical Assistance for Request for Single Stage - One (24 Solar Systems for the IBRD / 85810 Improved Disaster and Post Limited 54,655.00 45,723.51 Completed 2017-04-15 2017-04-11 2017-06-10 2017-08-17 2017-12-07 2018-03-28 Quotations Envelope remote stations + 1 for UWI Climate Resilience CRS) UNDERSTANDING RISK - 11 / Supply & Installation Technical Assistance for (8 Grounding & Lightening Request for Single Stage - One IBRD / 85810 Improved Disaster and Post Limited 50,156.00 39,618.66 Completed 2017-04-30 2017-04-10 2017-06-25 2017-06-19 2017-12-22 2018-04-16 Protection + 3 Quotations Envelope Climate Resilience Communication tower + 1 repair) RISK REDUCTION - 19 / Procurement of *2 Water Single Stage - One IBRD / 85810 Risk Reduction Post Request for Bids Open - National 400,000.00 457,810.48 Signed 2017-12-11 2018-02-13 2017-12-16 2018-01-27 2018-04-11 2018-04-13 2018-04-11 2018-05-18 2018-11-02 2018-11-14 Tanker Trucks (incl. spare Envelope parts & maintenance) RISK REDUCTION - 20 / Procurement of *4 Pumper Single Stage - One IBRD / 85810 Risk Reduction Post Request for Bids Open - National 2,000,000.00 2,214,364.70 Signed 2017-12-11 2018-02-12 2017-12-16 2018-01-27 2018-04-11 2018-04-13 2018-04-30 2018-05-18 2018-12-21 2018-11-14 Trucks (incl. spare parts & Envelope maintenance) PROJECT MANAGEMENT Request for Single Stage - One IBRD / 85810 Project Administration Post Limited 50,000.00 61,118.33 Completed 2017-11-29 2019-04-10 2018-01-24 2018-05-28 2018-07-23 2018-05-29 - 4 / Motor Vehicle Quotations Envelope UNDERSTANDING RISK - Technical Assistance for 3 / Supply of Equipment Request for Single Stage - One IBRD / 85810 Improved Disaster and Post Limited 36,615.00 27,728.10 Completed 2017-02-28 2017-02-24 2017-04-25 2017-04-05 2017-10-22 2017-07-24 (Ethernet Radios + Antenna Quotations Envelope Climate Resilience - Type A & Type B) UNDERSTANDING RISK - Technical Assistance for Request for Single Stage - One 7 / Supply and install IBRD / 85810 Improved Disaster and Post Limited 28,292.00 26,744.01 Completed 2017-11-20 2017-11-21 2018-01-15 2017-12-14 2018-07-14 2019-02-01 Quotations Envelope communication link Climate Resilience UNDERSTANDING RISK Under 6B / Supply of Multiplex IBRD / 85810 Risk Reduction Prior Direct Selection Direct 9,150.00 0.00 2018-03-12 2018-03-17 2018-04-21 2018-10-18 Review Board UNDERSTANDING RISK - 1 / Supply of Equipment (10 Technical Assistance for Single Stage - One siesmometers + 25 IBRD / 85810 Improved Disaster and Post Request for Bids Open - National 409,459.00 322,847.00 Completed 2018-03-26 2017-02-17 2018-03-31 2018-05-12 2017-03-16 2018-06-11 2017-07-18 2018-07-16 2017-09-20 2019-01-12 2018-02-26 Envelope Accelerographs + Climate Resilience Microzonation software) UNDERSTANDING RISK - Technical Assistance for 8 / Supply and install IBRD / 85810 Improved Disaster and Post Direct Selection Direct 12,764.00 18,925.98 Completed 2017-11-30 2017-03-08 2017-12-05 2017-03-31 2018-01-09 2017-04-26 2018-07-08 2017-07-12 fibreglass housing Climate Resilience UNDERSTANDING RISK - Technical Assistance for Request for Single Stage - One 6 / Supply of Computer IBRD / 85810 Improved Disaster and Post Limited 10,000.00 10,956.35 Completed 2017-03-01 2017-02-24 2017-04-26 2017-04-05 2017-10-23 2019-12-19 Quotations Envelope Digitizer Climate Resilience RR - 11 / Equipping St. Pending Benedicts Primary - School Request for Single Stage - One IBRD / 85810 Risk Reduction Post Limited 10,000.00 0.00 Implementati 2020-10-10 2020-12-05 2021-06-03 furniture and administrative Quotations Envelope on items Page 2 RISK REDUCTION - 7 / Pending Equipping for Fire Brigade Single Stage - One IBRD / 85810 Risk Reduction Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-07-06 2020-07-11 2020-08-22 2020-09-21 2020-10-26 2021-04-24 (Fire Fighting & Rescue Envelope on Equipment) RISK REDUCTION - 8 / Pending Equipping for Fire Stations Single Stage - One IBRD / 85810 Risk Reduction Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-09-07 2020-09-12 2020-10-24 2020-11-23 2020-12-28 2021-06-26 (Furniture, Adminstrative Envelope on items) UNDERSTANDING RISK - Technical Assistance for Request for Single Stage - One 10 / Supply & Installation IBRD / 85810 Improved Disaster and Post Limited 7,179.00 0.00 Canceled 2017-11-25 2018-01-20 2018-07-19 Quotations Envelope of Pole Mounts Climate Resilience UR - 17 / Procurement of Technical Assistance for Pending Single Stage - One IT Equipment (incl. for Risk IBRD / 85810 Improved Disaster and Post Request for Bids Open - National 255,000.00 0.00 Implementati 2021-04-05 2021-04-10 2021-05-22 2021-06-21 2021-07-26 2022-01-22 Envelope Atlas) Climate Resilience on UR - 24 / Procurement of goods for Communications Technical Assistance for Pending campaign, social awareness, Request for Single Stage - One IBRD / 85810 Improved Disaster and Post Limited 88,000.00 0.00 Implementati 2021-04-10 2021-06-05 2021-12-02 environmental development, Quotations Envelope Climate Resilience on DRR awareness and education programme NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JM-JSIF-46993-NC-RFQ / Software Training and Technical Assistance for Pending Request for Single Stage - One materials for application to IBRD / 85810 Improved Disaster and Post Limited 25,000.00 0.00 Implementati 2021-04-10 2021-06-05 2021-12-02 Quotations Envelope or use with seismic Climate Resilience on equipment. UNDERSTANDING RISK - Technical Assistance for Pending 30 / Training & Awareness - Request for Single Stage - One IBRD / 85810 Improved Disaster and Post Limited 2,000.00 0.00 Implementati 2021-04-10 2021-06-05 2021-12-02 Hurricane Tips through the Quotations Envelope Climate Resilience on media UNDERSTANDING RISK - 25 / Training & Awareness Technical Assistance for Pending (Workshops, Promotional Single Stage - One IBRD / 85810 Improved Disaster and Post Request for Bids Open - National 300,000.00 0.00 Implementati 2021-04-05 2021-04-10 2021-05-22 2021-06-21 2021-07-26 2022-01-22 Materials, Displays, Envelope Climate Resilience on Communication tools, Videos, etc UNDERSTANDING RISK - 27 / Social Awareness and Technical Assistance for Pending Environmental Development Request for Single Stage - One IBRD / 85810 Improved Disaster and Post Open - National 40,348.00 0.00 Implementati 2021-04-10 2021-06-05 2021-12-02 (social media boosting, social Quotations Envelope Climate Resilience on media management, tv/radio production) UNDERSTANDING RISK - 22 / Training & Awareness Technical Assistance for Pending (Workshops, Promotional Single Stage - One IBRD / 85810 Improved Disaster and Post Request for Bids Open - National 200,000.00 0.00 Implementati 2021-04-05 2021-04-10 2021-05-22 2021-06-21 2021-07-26 2022-01-22 Materials, Displays, Envelope Climate Resilience on Communication tools, Videos, etc) Multiple contracts PROJECT MANAGEMENT - 3 / Study Tours, Training, Pending Request for Single Stage - One Meetings, Events - Venues, IBRD / 85810 Project Administration Post Limited 100,000.00 0.00 Implementati 2021-04-10 2021-06-05 2021-12-02 Quotations Envelope Travel, Accommodations, on Training Materials Page 3 UNDERSTANDING RISK – 25-1 / The Fabrication and Technical Assistance for Pending Installation of 3 billboard Request for Single Stage - One IBRD / 85810 Improved Disaster and Post Limited 23,000.00 0.00 Implementati 2020-07-27 2020-10-05 2021-01-03 signs Islandwide (St. Quotations Envelope Climate Resilience on Thomas, Kingston and St. Mary) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RISK REDUCTION - 5 / Consultancy for Design & Least Cost IBRD / 85810 Risk Reduction Post Open - National 147,500.00 144,248.42 Signed 2017-03-16 2017-03-18 2017-04-06 2017-05-20 2017-05-10 2017-06-17 2017-06-02 2017-07-17 2017-06-19 2017-08-21 2017-06-26 2017-09-25 2017-07-31 2018-03-24 Supervision Services for Selection Yallahs Fire Station RISK REDUCTION - 6 / Consultancy for Design & Least Cost IBRD / 85810 Risk Reduction Post Open - National 147,500.00 144,636.97 Signed 2017-03-16 2017-03-18 2017-04-06 2017-05-20 2017-05-10 2017-06-17 2017-06-02 2017-07-17 2017-06-13 2017-08-21 2017-06-26 2017-09-25 2017-07-31 2018-03-24 Supervision Services for Port Selection Maria Fire Station PROJECT MANAGEMENT Consultant Pending - 5 / Consultancy Firm for IBRD / 85810 Project Administration Post Qualification Open - National 271,046.00 0.00 2021-03-02 2021-03-23 2021-05-06 2021-07-06 2021-08-10 2022-02-06 Implementation Impact Evaluation Selection RISK REDUCTION - 4 / Consultant Consultancy for Design & IBRD / 85810 Risk Reduction Post Qualification Open - National 165,000.00 181,733.33 Signed 2017-01-10 2016-11-20 2017-01-31 2017-03-16 2017-01-12 2017-04-15 2019-12-11 2017-05-20 2017-05-29 2017-11-16 Supervision Services for Selection Montego Bay Fire Station RISK REDUCTION - 16 / Consultant Consultancy for Supervision IBRD / 85810 Risk Reduction Post Qualification Open - National 100,000.00 0.00 Canceled 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 Services (Big Pond/Myton Selection Works) UNDERSTANDING RISK - 24 / Consulting Firm for Coastal Assessments & Technical Assistance for Preliminary Designs - Phase Quality And Cost- IBRD / 85810 Improved Disaster and Post Open - National 1,400,000.00 0.00 Canceled 2017-12-04 2017-12-25 2018-02-07 2018-03-07 2018-04-06 2018-08-05 2018-09-09 2019-09-09 I (Micro-zonation & EBA for Based Selection Climate Resilience 6 Locations) & Phase II (Multi-hazard, Micro-zonation & EBA for 2 Locations) RISK REDUCTION - 14 / Consultant Consultancy for Supervision IBRD / 85810 Risk Reduction Post Qualification Open - National 50,000.00 0.00 Canceled 2018-01-22 2018-02-12 2018-03-28 2018-04-27 2018-06-01 2018-11-28 Services (Church Pen Works) Selection UR - 21 / Procurement of Consulting Firm for Coastal Assessments & Preliminary Designs - EBA for Portland Technical Assistance for Quality And Cost- Cottage, Manchioneal, Ocho IBRD / 85810 Improved Disaster and Post Open - National 1,200,000.00 992,672.37 Signed 2018-10-01 2018-10-11 2018-10-22 2018-12-05 2018-10-06 2019-01-02 2018-11-22 2019-02-01 2018-12-13 2019-03-08 2019-01-30 2019-04-12 2019-09-30 2020-04-11 Based Selection Rios, Morant Bay, Savanah- Climate Resilience La-Mar & Black River and Multi-hazard & EBA for Port Maria & Alligator Pond UR - 23 / Procurement of Consulting Firm to develop Technical Assistance for Consultant and roll out communications IBRD / 85810 Improved Disaster and Post Qualification Open - National 112,000.00 92,502.49 Signed 2018-10-01 2018-09-27 2018-10-22 2018-12-05 2018-11-26 2019-01-04 2019-02-28 2019-02-08 2019-03-08 2019-08-07 campaign and DRR Climate Resilience Selection awareness and education programme Page 4 UR - 16 / Procurement of Consulting Firm for NRIP Technical Assistance for Quality And Cost- Open - Development (including RA), IBRD / 85810 Improved Disaster and Post 631,400.00 221,481.05 Signed 2019-11-18 2019-05-03 2019-12-09 2020-01-22 2019-05-09 2020-02-19 2019-06-19 2020-03-20 2019-07-12 2020-04-24 2019-09-30 2020-05-29 2019-11-28 2021-05-29 Based Selection International and Training (NRIP & RA Climate Resilience Usage, Coordination) UR - 20 - 1 / Procurement of Consulting Firm to conduct Micro-zonation studies in 8 locations (i.e. Technical Assistance for Quality And Cost- Open - Under Port Maria, Manchioneal, IBRD / 85810 Improved Disaster and Post 631,400.00 0.00 2020-01-13 2020-01-02 2020-02-03 2020-01-02 2020-03-18 2020-03-18 2020-04-15 2020-04-23 2020-05-15 2020-06-19 2020-07-24 2021-07-24 Based Selection International Implementation Ocho Rios, Morant Bay, Climate Resilience Savanah-La-Mar , Black River, Alligator Pond & Portland Cottage) UR - 20 / Procurement of Consulting Firm to conduct Micro-zonation studies in 8 Technical Assistance for Consultant locations (i.e. Port Maria, IBRD / 85810 Improved Disaster and Post Qualification Open - National 200,000.00 0.00 Canceled 2018-10-01 2018-10-22 2018-12-05 2019-01-04 2019-02-08 2019-08-07 Manchioneal, Ocho Rios, Climate Resilience Selection Morant Bay, Savanah-La- Mar , Black River, Alligator Pond & Portland Cottage) RR -16-1 / Design Review - Consultant Big Pond/Myton Gully & IBRD / 85810 Risk Reduction Post Qualification Open - National 100,000.00 0.00 Canceled 2018-10-29 2018-11-19 2019-01-02 2019-02-01 2019-03-08 2019-09-04 Myton Bridge Selection RR - 10 / Design & Consultant Pending Supervision of Works for St. IBRD / 85810 Risk Reduction Post Qualification Open - National 50,000.00 0.00 2021-04-04 2021-04-25 2021-06-08 2021-07-08 2021-08-12 2022-02-08 Implementation Benedicts Primary Selection RR - 21 / Environmental Monitoring (Testing - Water, Least Cost Pending Air, Turbidity, Noise, ete) - IBRD / 85810 Risk Reduction Post Open - National 180,000.00 0.00 2021-04-05 2021-04-26 2021-06-09 2021-07-07 2021-08-06 2021-09-10 2021-10-15 2022-04-13 Selection Implementation Coastal Works, Urban Drainage et al INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RISK REDUCTION - 18 / Consultancy for Coastal Design & Supervision IBRD / 85810 Risk Reduction Post Direct Selection Direct 150,000.00 166,130.65 Signed 2017-12-04 2017-10-13 2017-12-14 2018-01-11 2018-02-17 2018-03-14 2018-08-16 Services (Design). Supervision (optional - NWA) UNDERSTANDING RISK - 15 / Project Coordination Technical Assistance for Individual (for National Risk IBRD / 85810 Improved Disaster and Post Consultant Open 100,000.00 28,844.12 Signed 2017-09-05 2017-09-05 2017-10-24 2017-11-09 2017-11-14 2017-11-29 2017-12-19 2017-12-01 2018-06-17 Information Platform (NRIP), Climate Resilience Selection Risk Atlas (RA), Studies) (DRR Specialist) Technical Assistance for UNDERSTANDING RISK - IBRD / 85810 Improved Disaster and Post Direct Selection Direct 120,000.00 120,000.00 Signed 2019-11-01 2019-01-15 2019-11-11 2019-10-28 2020-01-15 2020-03-04 2020-07-13 28 / Building Code Editing Climate Resilience RR - 16 - 2 / Design Individual Review - Big Pond/Myton IBRD / 85810 Risk Reduction Post Consultant Limited 100,000.00 214,227.08 Signed 2020-01-13 2018-11-08 2020-01-18 2018-12-03 2020-02-08 2019-05-24 2020-03-14 2019-05-24 2020-09-10 Gully & Myton Bridge Selection Page 5 UNDERSTANDING RISK - 13 / Researcher in Technical Assistance for Individual Pending Seismology - Stipend, Per IBRD / 85810 Improved Disaster and Post Consultant Open 35,907.00 0.00 2021-04-05 2021-05-24 2021-06-14 2021-07-19 2022-01-15 Implementation diem, Accommodations, Climate Resilience Selection Travel & Research Costs Page 6