PROCUREMENT PLAN Project information: ENHANCING WATERWAY CONNECTIVITY AND WATER SERVICE PROVISION IN COLOMBIA’S PLAN PAZCIFICO Region Project P156880 Project Implementation agency: 1. NATIONAL UNIT FOR THE MANAGEMENT OF DISASTER RISK / UNIDAD NACIONAL DE GESTION DEL RIESGO DE DESASTRES Date of the Procurement Plan: 10/22/2019 Period covered by this Procurement Plan: 10/22/2019 – 12/15/2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the documents previously approved with the Bank will be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is not applicable; Works: Is not applicable PROCUREMENT Colombia : Enhancing Waterway Connectivity and Water Service Provision in Colombia’s Plan Pazcifico PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2019-12-12 2021-10-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156880 GPN Date: 2019-12-09 Project Name: Enhancing Waterway Connectivity and Water Service Provision in Colombia’s Plan Pazcifico Loan / Credit No: IBRD / 87980 N Executing Agency(ies): ational Unit for the Management of Disaster Risk WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8798-003 / Improving Water Supply and Solicitud de Single Stage - One Ejecución 2020-10- Construcción acueducto IBRD / 87980 Sanitation Services in Posterior Open - National 3,967,526.00 0.00 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 ofertas Envelope pendiente 31 Francisco Pizarro participating municipalities PTSP-BIRF8798-005 / Improving Water Supply and Solicitud de Single Stage - One Ejecución 2020-11- Construcción acueducto IBRD / 87980 Sanitation Services in Posterior Open - National 4,046,127.00 0.00 2020-01-27 2020-02-01 2020-03-14 2020-04-13 2020-05-18 ofertas Envelope pendiente 14 Timbiquí participating municipalities PTSP-BIRF8798-006 / Improving Water Supply and Solicitud de Single Stage - One Ejecución 2020-11- Construcción alcantarillado IBRD / 87980 Sanitation Services in Posterior Open - National 3,760,945.00 0.00 2020-01-20 2020-01-25 2020-03-07 2020-04-06 2020-05-11 ofertas Envelope pendiente 07 municipio seleccionado participating municipalities PTSP-BIRF8798-007 / Mantenimiento de las Improving Waterway instalaciones portuarias y Solicitud de Single Stage - One Ejecución 2020-11- IBRD / 87980 Transport in participating Posterior Open - National 962,000.00 0.00 2020-01-27 2020-02-01 2020-03-14 2020-04-13 2020-05-18 equipos de Señalización y ofertas Envelope pendiente 14 municipalities Seguridad durante el periodo de ejecución de las obras PTSP-BIRF8798-0060 / Improving Waterway Construcción del muelle y Solicitud de Single Stage - One 2021-07- IBRD / 87980 Transport in participating Posterior Open - National 1,336,814.00 0.00 Cancelado 2020-08-15 2020-08-28 2020-08-20 2020-09-18 2020-10-15 2020-10-06 2020-11-21 terminal portuario del ofertas Envelope 19 municipalities municipio de La Tola (Nariño) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Capacity Building and Institutional Strengthening PTSP-BIRF8798-0052 / for waterway transport Solicitud de Single Stage - One Ejecución Adquirir motobombas y IBRD / 87980 operators and water supply Posterior Open - National 198,804.00 0.00 2020-07-13 2020-09-07 2020-10-07 cotizaciones Envelope pendiente accesorios hidráulicos and sanitation service providers in participating municipalities Capacity Building and Institutional Strengthening PTSP-BIRF8798-0053 / for waterway transport Solicitud de Single Stage - One Ejecución Adquirir tanques para IBRD / 87980 operators and water supply Posterior Open - National 246,330.00 0.00 2020-07-13 2020-09-07 2020-10-07 cotizaciones Envelope pendiente almacenamiento de agua and sanitation service providers in participating municipalities Capacity Building and Institutional Strengthening PTSP-BIRF8798-0056 / for waterway transport Solicitud de Single Stage - One Ejecución Adquirir filtros purificadores IBRD / 87980 operators and water supply Posterior Open - National 100,274.00 0.00 2020-07-13 2020-09-07 2020-10-22 cotizaciones Envelope pendiente de agua and sanitation service providers in participating municipalities Capacity Building and Institutional Strengthening PTSP-BIRF8798-0054 / for waterway transport Adquirir plantas de Solicitud de Single Stage - One Ejecución IBRD / 87980 operators and water supply Posterior Open - National 140,278.00 0.00 2020-07-13 2020-09-07 2020-11-06 tratamiento de agua potable cotizaciones Envelope pendiente and sanitation service portátiles providers in participating municipalities NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-010 / Interventoría de la Ejecución Improving Waterway Selección basada Ejecución de Obras de muelles, Obras IBRD / 87980 Transport in participating Posterior Open - International 1,326,080.00 0.00 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-08-07 en calidad y costo pendiente de Señalización y Seguridad municipalities en Navegación PTSP-BIRF8798-011 / Project Management and Selección basada Implementación del plan de Ejecución IBRD / 87980 Environmental and Social Posterior en calificaciones Open - National 100,000.00 0.00 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 información, comunicación y pendiente Management de consultores participación PTSP-BIRF8798-012 / Improving Water Supply and Selección basada Actualizacion de estudios IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 74,600.00 0.00 Cancelado 2020-01-27 2020-02-17 2020-04-01 2020-05-01 2020-06-05 2020-12-02 Acueducto Francisco Pizarro participating municipalities de consultores Page 1 PTSP-BIRF8798-014 / Improving Water Supply and Interventoria Obras Selección basada Ejecución IBRD / 87980 Sanitation Services in Posterior Open - National 275,138.00 0.00 2020-01-13 2020-02-03 2020-03-18 2020-04-15 2020-05-15 2020-06-19 2020-07-24 2021-01-20 Alcantarillado Francisco en el menor costo pendiente participating municipalities Pizarro PTSP-BIRF8798-015 / Improving Water Supply and Actualizacion de estudios Selección basada IBRD / 87980 Sanitation Services in Posterior Open - National 275,138.00 0.00 Cancelado 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 Alcantarillado Francisco en el menor costo participating municipalities Pizarro PTSP-BIRF8798-017 / Improving Water Supply and Selección basada Ejecución Interventoría obras Acueducto IBRD / 87980 Sanitation Services in Posterior Open - National 323,690.00 0.00 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 en el menor costo pendiente Timbiquí participating municipalities PTSP-BIRF8798-018 / Improving Water Supply and Selección basada Actualizacion de estudios IBRD / 87980 Sanitation Services in Posterior Open - National 302,814.00 0.00 Cancelado 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 en el menor costo Alcantarillado Timbiquí participating municipalities PTSP-BIRF8798-019 / Improving Water Supply and Selección basada Ejecución Interventoría obras IBRD / 87980 Sanitation Services in Posterior Open - National 275,285.00 0.00 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-02-03 en el menor costo pendiente Alcantarillado Timbiquí participating municipalities Capacity Building and Institutional Strengthening for waterway transport PTSP-BIRF8798-020 / Selección basada Ejecución IBRD / 87980 operators and water supply Posterior Open - International 700,000.00 0.00 2020-02-17 2020-03-09 2020-04-22 2020-05-20 2020-06-19 2020-07-24 2020-08-28 2021-08-28 Fortalecimiento institucional en calidad y costo pendiente and sanitation service providers in participating municipalities PTSP-BIRF8798-021 / Capacity Building and Actualizacion de planes Institutional Strengthening maestros de acueducto para for waterway transport Selección basada Ejecución Olaya Herrera, La Tola, IBRD / 87980 operators and water supply Posterior Open - International 900,000.00 0.00 2020-02-24 2020-03-16 2020-04-29 2020-05-27 2020-06-26 2020-07-31 2020-09-04 2021-09-04 en calidad y costo pendiente Mosquera, Francisco Pizarro, and sanitation service Lopez de Micay and Santa providers in participating Barbara de Iscuande municipalities PTSP-BIRF8798-022 / Improving Water Supply and Selección basada Interventoría Actualizacion de IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 5,425.00 0.00 Cancelado 2020-01-27 2020-02-17 2020-04-01 2020-05-01 2020-06-05 2020-12-02 estudios Acueducto Francisco participating municipalities de consultores Pizarro PTSP-BIRF8798-023 / Improving Water Supply and Selección basada Interventoría Actualizacion de IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 8,447.00 0.00 Cancelado 2020-01-20 2020-02-10 2020-03-25 2020-04-24 2020-05-29 2020-11-25 estudios Acueducto Timbiquí participating municipalities de consultores PTSP-BIRF8798-024 / Improving Water Supply and Selección basada Interventoría Actualizacion de IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 22,011.00 0.00 Cancelado 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 estudios Alcantarillado participating municipalities de consultores Francisco pizarro PTSP-BIRF8798-025 / Improving Water Supply and Selección basada Interventoría Actualizacion de IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 24,225.00 0.00 Cancelado 2020-02-10 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 estudios Alcantarillado participating municipalities de consultores Timbiquí PTSP-BIRF8798-026 / Project Management and Selección basada Ejecución Evaluación de medio término IBRD / 87980 Environmental and Social Posterior Open - National 174,000.00 0.00 2021-02-22 2021-03-15 2021-04-28 2021-05-26 2021-06-25 2021-07-30 2021-09-03 2022-09-03 en calidad y costo pendiente y final Management PTSP-BIRF8798-008 / Improving Waterway Estudios y Diseños definitivos Selección basada IBRD / 87980 Transport in participating Previa Open - International 1,169,532.00 0.00 En ejecución 2020-05-19 2020-06-15 2020-06-09 2020-07-08 2020-07-08 2020-09-21 2020-08-05 2020-11-20 2020-08-20 2021-01-29 2020-09-24 2021-06-01 2020-10-18 2021-10-18 para los muelles y en calidad y costo municipalities señalización PTSP-BIRF8798-009 / Improving Waterway Selección basada Interventoría de Estudios de IBRD / 87980 Transport in participating Posterior en calificaciones Open - National 350,763.00 0.00 Cancelado 2020-05-19 2020-06-24 2020-06-09 2020-07-23 2020-08-22 2020-10-05 2021-10-05 muelles y estudios de municipalities de consultores señalización PTSP-BIRF8798-0009 / Improving Waterway Interventoría de Estudios y Selección basada IBRD / 87980 Transport in participating Posterior Open - National 350,763.00 0.00 En ejecución 2020-07-07 2020-07-06 2020-07-28 2020-09-10 2020-10-08 2020-11-07 2020-12-12 2021-01-16 2022-01-16 Diseños de Muelles y en calidad y costo municipalities señalización PTSP-BIRF8798-0058 / Interventoría técnica, administrativa, financiera, Improving Waterway Selección basada legal, ambiental y social de la IBRD / 87980 Transport in participating Posterior Open - National 230,726.00 0.00 En ejecución 2020-07-21 2020-07-18 2020-08-11 2020-09-24 2020-10-22 2020-11-21 2020-12-26 2021-01-30 2021-10-27 en calidad y costo construcción del muelle y municipalities terminal portuario en el municipio de La Tola (Nariño) PTSP-BIRF8798-0059 / Consultoría para la Capacity Building and estructuración del modelo de Institutional Strengthening administración, operación y for waterway transport Selección basada mantenimiento de los IBRD / 87980 operators and water supply Posterior en calificaciones Open - National 101,414.00 0.00 En ejecución 2020-07-21 2020-07-18 2020-08-11 2020-09-24 2020-10-24 2020-11-28 2021-05-27 terminales portuarios fluviales and sanitation service de consultores de los municipios del Pacífico providers in participating sur de Colombia, con municipalities aplicación piloto en el municipio de La Tola (Nariño). PTSP-BIRF8798-0057 / Actualización, ajuste y Improving Water Supply and Selección basada complementación de los IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 100,013.00 0.00 En ejecución 2020-09-30 2020-10-21 2020-10-15 2020-11-22 2020-12-07 2021-01-11 2021-07-10 estudios y diseños acueducto participating municipalities de consultores Francisco Pizarro PTSP-BIRF8798-072 / CONSULTORÍA PARA LA ELABORACIÓN DE LOS ESTUDIOS Y DISEÑOS DEL Improving Water Supply and Selección basada SISTEMA DE IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 172,700.00 0.00 En ejecución 2021-03-24 2021-05-06 2021-04-08 2021-05-16 2021-05-31 2021-07-05 2022-03-02 ALCANTARILLADO DE LA participating municipalities de consultores CABECERA URBANA DEL MUNICIPIO DE TIMBIQUÍ, DEPARTAMENTO DEL CAUCA Page 2 PTSP-BIRF8798-073 / CONSULTORÍA PARA LA ELABORACIÓN DE LOS ESTUDIOS Y DISEÑOS DEL Improving Water Supply and Selección basada SISTEMA DE IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 184,250.00 0.00 En ejecución 2021-03-24 2021-05-20 2021-04-08 2021-05-16 2021-05-31 2021-07-05 2022-03-02 ALCANTARILLADO DE LA participating municipalities de consultores CABECERA URBANA DEL MUNICIPIO DE FRANCISCO PIZARRO, DEPARTAMENTO DE NARIÑO PTSP-BIRF8798-074 / PRESTAR LOS SERVICIOS DE INTERVENTORÍA (SUPERVISIÓN) TÉCNICA, ADMINISTRATIVA, FINANCIERA, LEGAL, Improving Water Supply and Selección basada AMBIENTAL Y SOCIAL PARA IBRD / 87980 Sanitation Services in Posterior Open - National 93,030.00 0.00 Cancelado 2021-03-24 2021-04-14 2021-05-18 2021-05-23 2021-06-07 2021-06-22 2021-07-18 2022-04-22 en calidad y costo LOS ESTUDIOS Y DISEÑOS DE participating municipalities LOS SISTEMAS DE ALCANTARILLADO DE LOS MUNICIPIOS DE TIMBIQUÍ, DEPARTAMENTO DEL CAUCA, Y FRANCISCO PIZARRO, D PTSP-BIRF8798-078 / Prestar los servicios de interventoría (supervisión) técnica, administrativa, financiera, Improving Water Supply and legal, ambiental y social para Selección basada IBRD / 87980 Sanitation Services in Posterior Open - National 46,512.00 0.00 Cancelado 2021-05-13 2021-06-03 2021-07-07 2021-07-12 2021-07-27 2021-08-11 2021-09-06 2022-06-11 los estudios y diseños del en calidad y costo participating municipalities sistema de alcantarillado en los municipios del pacifico sur de los departamentos de cauca y nariño. PTSP-BIRF8798-080 / PRESTAR LOS SERVICIOS DE INTERVENTORÍA (SUPERVISIÓN) TÉCNICA, ADMINISTRATIVA, FINANCIERA, LEGAL, Improving Water Supply and Selección basada AMBIENTAL Y SOCIAL PARA IBRD / 87980 Sanitation Services in Posterior en calificaciones Open - National 60,550.00 0.00 En ejecución 2021-05-25 2021-06-09 2021-06-09 2021-07-19 2021-08-03 2021-09-01 2022-05-29 LOS ESTUDIOS Y DISEÑOS DE participating municipalities de consultores LOS SISTEMAS DE ALCANTARILLADO DE LOS MUNICIPIOS DE TIMBIQUÍ, DTO DEL CAUCA, Y FRANCISCO PIZARRO DTO NARIÑO. PTSP-BIRF8798-082 / PRESTAR LOS SERVICIOS DE INTERVENTORÍA (SUPERVISIÓN) TÉCNICA, ADMINISTRATIVA, FINANCIERA, LEGAL, Improving Water Supply and Selección basada AMBIENTAL, SOCIAL Y DE IBRD / 87980 Sanitation Services in Previa Open - International 1,640,447.00 0.00 En ejecución 2021-07-12 2021-10-04 2021-07-16 2021-08-14 2021-09-27 2021-10-12 2021-11-16 2021-12-10 2023-12-15 en calidad y costo SEGURIDAD Y SALUD EN EL participating municipalities TRABAJO PARA LOS ESTUDIOS, DISEÑOS Y OBRAS DE LOS SISTEMAS DE ACUEDUCTO Y ALCANTARILLADO EN LOS MUNICIPIOS DEL INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-001 / Líder Project Management and de Conectividad de IBRD / 87980 Environmental and Social Posterior Individual Open 23,598.00 0.00 En ejecución 2019-11-25 2020-01-02 2019-12-04 2019-12-05 2019-12-15 2020-04-13 Transporte Management Project Management and PTSP-BIRF8798-028 / IBRD / 87980 Environmental and Social Posterior Individual Limited 17,032.00 0.00 En ejecución 2020-01-27 2020-01-28 2020-02-01 2020-02-08 2020-03-07 2020-07-05 Especialista Ambiental Management PTSP-BIRF8798-029 / Enlace Project Management and Social de Conectividad de IBRD / 87980 Environmental and Social Posterior Individual Open 7,759.00 0.00 En ejecución 2020-01-27 2020-01-28 2020-03-16 2020-03-23 2020-04-20 2020-08-18 Transporte Management PTSP-BIRF8798-030 / Enlace Project Management and Social de Conectividad de IBRD / 87980 Environmental and Social Posterior Individual Open 7,759.00 0.00 En ejecución 2020-01-27 2020-01-28 2020-03-16 2020-03-23 2020-04-20 2020-08-18 Transporte Management PTSP-BIRF8798-031 / Apoyo Project Management and Técnico del Componente de IBRD / 87980 Environmental and Social Posterior Individual Limited 7,759.00 0.00 En ejecución 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-06 2020-07-04 Conectividad de Transporte y Management Provisión de Agua PTSP-BIRF8798-032 / Apoyo Project Management and Técnico del Componente de IBRD / 87980 Environmental and Social Posterior Individual Limited 7,759.00 0.00 En ejecución 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-10 2020-07-08 Conectividad de Transporte y Management Provisión de Agua PTSP-BIRF8798-033 / Project Management and Especialista de Conectividad IBRD / 87980 Environmental and Social Posterior Individual Limited 17,032.00 0.00 En ejecución 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-10 2020-07-08 de Transporte Management PTSP-BIRF8798-034 / Project Management and Viabilizador de Proyectos ante IBRD / 87980 Environmental and Social Posterior Individual Limited 17,032.00 0.00 En ejecución 2020-01-31 2020-01-31 2020-02-05 2020-03-16 2020-02-15 2020-03-10 2020-07-08 INVIAS Management PTSP-BIRF8798-035 / Especialista en Agua y Project Management and Saneamiento Básico - IBRD / 87980 Environmental and Social Posterior Individual Direct 17,302.00 0.00 En ejecución 2020-02-26 2020-03-11 2020-03-04 2020-03-09 2020-03-19 2020-07-17 Recontratación JAIRO Management ALBERTO PÉREZ GÓMEZ PTSP-BIRF8798-036 / Directora Ejecutiva / Project Management and Coordinadora del Proyecto IBRD / 87980 Environmental and Social Posterior Individual Direct 17,596.00 0.00 En ejecución 2020-02-26 2020-03-07 2020-03-12 2020-03-22 2021-03-21 FTSP - Recontratación LUZ Management AMANDA PULIDO Page 3 PTSP-BIRF8798-037 / Líder Project Management and Ambiental - Recontratación IBRD / 87980 Environmental and Social Posterior Individual Limited 15,009.00 0.00 En ejecución 2020-02-27 2020-03-11 2020-03-03 2020-03-08 2020-03-18 2021-03-17 RUTH ALEJANDRA CATACOLI Management JIMENEZ PTSP-BIRF8798-038 / Líder Project Management and Financiera - Recontratación IBRD / 87980 Environmental and Social Posterior Individual Direct 15,009.00 0.00 En ejecución 2020-02-26 2020-03-07 2020-03-12 2020-03-22 2021-03-21 CLAUDIA AGUDELO SEDANO Management PTSP-BIRF8798-039 / Líder Project Management and de Adquisiciones - IBRD / 87980 Environmental and Social Posterior Individual Direct 15,009.00 0.00 En ejecución 2020-02-26 2020-03-07 2020-03-12 2020-03-22 2021-03-21 Recontratación ELKIN ADOLFO Management PINILLA CAÑÓN PTSP-BIRF8798-040 / Líder Project Management and de Seguridad - Recontratación IBRD / 87980 Environmental and Social Posterior Individual Direct 15,009.00 0.00 En ejecución 2020-02-26 2020-03-07 2020-03-12 2020-03-22 2021-03-21 WILSON LAVERDE FLÓREZ Management PTSP-BIRF8798-041 / Project Management and Especialista Financiera - IBRD / 87980 Environmental and Social Posterior Individual Direct 11,355.00 0.00 En ejecución 2020-02-26 2020-03-07 2020-03-12 2020-03-22 2021-03-21 Recontratación SANDRA Management LORENA PEÑA PTSP-BIRF8798-042 / Líder Componente Agua y Project Management and Saneamiento Básico - IBRD / 87980 Environmental and Social Posterior Individual Direct 37,523.00 0.00 En ejecución 2020-03-24 2020-04-01 2020-04-03 2020-04-08 2020-04-18 2021-04-18 Recontratación FABIOLA Management IGUARAN ARAUJO PTSP-BIRF8798-043 / Líder Project Management and Social - Recontratación KELLY IBRD / 87980 Environmental and Social Posterior Individual Direct 15,009.00 0.00 En ejecución 2020-04-06 2020-04-16 2020-04-21 2020-05-01 2021-04-30 LORENA RUIZ GARCIA Management PTSP-BIRF8798-044 / Project Management and Especialista de Adquisiciones IBRD / 87980 Environmental and Social Posterior Individual Direct 56,773.00 0.00 En ejecución 2020-04-16 2020-04-26 2020-05-01 2020-05-11 2021-05-10 BM - Recontratación JOHN Management MAURICIO OTALVARO CORTES PTSP-BIRF8798-045 / Actualización, Ajustes y Complemento de los Diseños Improving Water Supply and Selección directa Ejecución para la Optimización y IBRD / 87980 Sanitation Services in Posterior Direct 69,865.00 0.00 2020-05-07 2020-05-17 2020-06-06 2020-09-19 de consultores pendiente Ampliación del Acueducto del participating municipalities Municipio de Timbiquí - Cauca PTSP-BIRF8798-046 / Project Management and Ejecución Especialista de Planeación y IBRD / 87980 Environmental and Social Posterior Individual Limited 11,355.00 0.00 2020-05-07 2020-05-12 2020-06-02 2020-07-07 2021-01-03 pendiente Seguimiento Management PTSP-BIRF8798-047 / Líder Project Management and de Conectividad - IBRD / 87980 Environmental and Social Posterior Individual Direct 75,046.00 0.00 En ejecución 2020-05-14 2020-06-12 2020-05-24 2020-05-29 2020-06-08 2021-06-07 Recontratación DIEGO Management FERNANDO DUQUE BASTIDAS Project Management and PTSP-BIRF8798-052 / Líder Ejecución IBRD / 87980 Environmental and Social Posterior Individual Limited 15,009.00 0.00 2020-06-24 2020-07-04 2020-07-09 2020-07-19 2021-07-18 de Planeación y Seguimiento pendiente Management PTSP-BIRF8798-048 / Interventoría de Estudios y Improving Water Supply and Diseños Acueducto y IBRD / 87980 Sanitation Services in Posterior Individual Direct 13,932.00 0.00 En ejecución 2020-06-12 2020-07-09 2020-06-22 2020-07-02 2020-07-17 2021-07-16 Alcantarillado de Timbiquí y participating municipalities Francisco Pizarro - Director de Interventoría PTSP-BIRF8798-049 / Interventoría de Estudios y Improving Water Supply and Diseños Acueducto y IBRD / 87980 Sanitation Services in Posterior Individual Direct 4,917.00 0.00 En ejecución 2020-06-12 2020-07-09 2020-06-22 2020-07-02 2020-07-17 2021-07-16 Alcantarillado de Timbiquí y participating municipalities Francisco Pizarro - Especialista Electromecánico PTSP-BIRF8798-050 / Interventoría de Estudios y Improving Water Supply and Diseños Acueducto y IBRD / 87980 Sanitation Services in Posterior Individual Direct 8,072.00 0.00 En ejecución 2020-06-12 2020-07-09 2020-06-22 2020-07-02 2020-07-17 2021-07-16 Alcantarillado de Timbiquí y participating municipalities Francisco Pizarro - Especialista Estructural PTSP-BIRF8798-051 / interventoría de Estudios y Improving Water Supply and Diseños Acueducto y IBRD / 87980 Sanitation Services in Posterior Individual Direct 5,818.00 0.00 En ejecución 2020-06-04 2020-07-09 2020-06-14 2020-06-24 2020-07-09 2021-07-08 Alcantarillado de Timbiquí y participating municipalities Francisco Pizarro - Especialista Geotécnia PTSP-BIRF8798-061 / AUDITORÍA DE LOS ESTADOS FINANCIEROS DE PROPÓSITO ESPECIAL Y ASEGURAMIENTO Project Management and RAZONABLE SOBRE LOS Selección directa IBRD / 87980 Environmental and Social Posterior Direct 10,200.00 0.00 En ejecución 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-08 2021-07-07 PROCESOS DE ADQUISICIONES de consultores Management DEL PROYECTO/PROGRAMA FINANCIADO POR EL BID Y EL BANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8798-062 / Directora Ejecutiva / Project Management and Coordinadora del Proyecto IBRD / 87980 Environmental and Social Posterior Individual Direct 12,900.00 0.00 En ejecución 2021-02-26 2021-03-15 2021-03-08 2021-03-13 2021-03-18 2022-03-17 FTSP - Recontratación LUZ Management AMANDA PULIDO PTSP-BIRF8798-063 / Líder Componente Agua y Project Management and Saneamiento Básico - IBRD / 87980 Environmental and Social Posterior Individual Direct 27,500.00 0.00 En ejecución 2021-03-01 2021-03-15 2021-03-11 2021-03-16 2021-04-08 2022-04-07 Recontratación FABIOLA Management IGUARAN ARAUJO Page 4 PTSP-BIRF8798-064 / Líder Project Management and de Adquisiciones - IBRD / 87980 Environmental and Social Posterior Individual Direct 11,000.00 0.00 En ejecución 2021-02-26 2021-03-15 2021-03-08 2021-03-13 2021-03-18 2022-03-17 Recontratación ELKIN ADOLFO Management PINILLA CAÑÓN PTSP-BIRF8798-065 / Líder Project Management and Financiera - Recontratación IBRD / 87980 Environmental and Social Posterior Individual Direct 11,000.00 0.00 En ejecución 2021-02-26 2021-03-15 2021-03-08 2021-03-13 2021-03-18 2022-03-17 CLAUDIA AGUDELO SEDANO Management PTSP-BIRF8798-066 / Líder Project Management and Social - Recontratación KELLY IBRD / 87980 Environmental and Social Posterior Individual Direct 11,000.00 0.00 En ejecución 2021-03-19 2021-03-15 2021-03-29 2021-04-03 2021-04-23 2022-04-22 LORENA RUIZ GARCIA Management PTSP-BIRF8798-067 / Líder Project Management and de Seguridad - Recontratación IBRD / 87980 Environmental and Social Posterior Individual Direct 11,000.00 0.00 En ejecución 2021-02-26 2021-03-15 2021-03-08 2021-03-13 2021-03-22 2022-03-21 WILSON LAVERDE FLÓREZ Management PTSP-BIRF8798-068 / Contratación Líder Ambiental para la ejecución y cumplimiento de los Marcos Project Management and Selección directa de Gestión Ambiental IBRD / 87980 Environmental and Social Posterior Direct 5,496.00 0.00 En ejecución 2021-03-08 2021-03-15 2021-03-09 2021-03-22 2021-09-21 de consultores adoptados para la ejecución Management del Fondo para el desarrollo del Plan Todos Somos PAZcífico - Fernando Rey PTSP-BIRF8649-070 / Project Management and Especialista Financiera - IBRD / 87980 Environmental and Social Posterior Individual Direct 8,315.00 0.00 En ejecución 2021-03-08 2021-03-15 2021-03-09 2021-03-14 2021-03-18 2022-03-17 Recontratación Sandra Lorena Management Peña PTSP-BIRF8649-069 / Project Management and Especialista de Adquisiciones Selección directa IBRD / 87980 Environmental and Social Posterior Direct 20,079.00 0.00 En ejecución 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2022-03-14 - Contratación Tulio José de consultores Management Fuentes PTSP-BIRF8649-071 / Especialista de Planeación y Seguimiento. - Brindar apoyo profesional en la gestión de Project Management and planificación, monitoreo y IBRD / 87980 Environmental and Social Posterior Individual Open 10,394.00 0.00 En ejecución 2021-03-11 2021-03-15 2021-03-16 2021-03-17 2021-03-25 2021-09-24 seguimiento a las actividades Management del Fondo para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8798-075 / Contratación Líder Fortalecimiento Institucional para Liderar la Project Management and implementación y ejecución Selección directa IBRD / 87980 Environmental and Social Posterior Direct 5,496.00 0.00 Cancelado 2021-04-14 2021-04-19 2021-05-17 2021-11-16 de los componentes de de consultores Management Capacidad y Fortalecimiento Institucional de Agua y Saneamiento Básico - Jorge Silva PTSP-BIRF8798-076 / Contratación Líder Fortalecimiento Institucional para Liderar la implementación y ejecución Project Management and de los componentes de IBRD / 87980 Environmental and Social Posterior Individual Direct 5,496.00 0.00 En ejecución 2021-04-15 2021-04-19 2021-04-22 2021-04-23 2021-05-17 2021-11-16 Capacidad y Fortalecimiento Management Institucional de Agua y Saneamiento Básico para el desarrollo del Plan Todos Somos PAZcífico - Jorge Silva. PTSP-BIRF8798-077 / Project Management and Especialista de Adquisiciones IBRD / 87980 Environmental and Social Posterior Individual Direct 8,315.00 0.00 En ejecución 2021-04-22 2021-04-26 2021-04-24 2021-04-26 2021-05-04 2022-05-03 - Recontratación JOHN Management MAURICIO OTÁLVARO CORTÉS PTSP-BIRF8798-079 / Líder Project Management and de Conectividad - IBRD / 87980 Environmental and Social Posterior Individual Direct 54,958.00 0.00 En ejecución 2021-05-18 2021-05-26 2021-05-20 2021-05-24 2021-06-08 2022-06-07 Recontratación DIEGO Management FERNANDO DUQUE BASTIDAS PTSP-BIRF8798-081 / Líder Project Management and de Planeación y Seguimiento IBRD / 87980 Environmental and Social Posterior Individual Direct 10,992.00 0.00 En ejecución 2021-06-09 2021-06-10 2021-06-19 2021-06-24 2021-06-30 2022-06-29 - Recontratación Joan Natalie Management Garzón PTSP-BIRF8798-083 / AUDITORÍA DE LOS ESTADOS FINANCIEROS DE PROPÓSITO ESPECIAL Y ASEGURAMIENTO Project Management and RAZONABLE SOBRE LOS Selección directa Ejecución IBRD / 87980 Environmental and Social Posterior Direct 21,808.00 0.00 2021-09-06 2021-09-26 2021-12-23 2022-06-21 PROCESOS DE ADQUISICIONES de consultores pendiente Management DEL PROYECTO/PROGRAMA FINANCIADO POR EL BID Y EL BANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8798-084 / Líder Project Management and Ejecución Ambiental FTSP - IBRD / 87980 Environmental and Social Posterior Individual Direct 5,935.00 0.00 2021-09-09 2021-09-09 2021-09-20 2021-09-23 2022-03-22 pendiente Recontratación Fernando Rey Management PTSP-BIRF8798-085 / Especialista de Planeación y Project Management and Ejecución Seguimiento FTSP - IBRD / 87980 Environmental and Social Posterior Individual Direct 22,425.00 0.00 2021-09-09 2021-09-17 2021-09-17 2021-09-27 2022-09-26 pendiente Recontratación Natalia García Management Medina Capacity Building and Institutional Strengthening PTSP-BIRF8798-086 / Líder for waterway transport de Fortalecimiento Ejecución IBRD / 87980 operators and water supply Posterior Individual Direct 11,870.00 0.00 2021-10-19 2021-10-19 2021-10-26 2021-11-11 2022-11-10 Institucional - Recontratación pendiente and sanitation service Jorge Ernesto Silva providers in participating municipalities Page 5