Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan: Updated Procurement Plan, M 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] July 9, 2010 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contract (Works) for Prior Review Summary 1.86 4 No Post 1st of the NCB contract (Goods) for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Agricultural Growth Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2017-11-13 2021-02-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148591 GPN Date: Project Name: Second Agricultural Growth Project Loan / Credit No: IDA / 56050 SNNPR - Agricultural Growth Program Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-SNPPR-AGP-36255-CW- RFB / Rehabilitation/Maintenance of vegitable and fruit nurseries Agricultural Public Support Single Stage - One 2018-09- IDA / 56050 Post Request for Bids Open - National 324,910.00 0.00 Canceled 2018-02-09 2018-02-14 2018-03-16 2018-04-15 2018-05-20 on 9 woredas /W/Genet, Services Envelope 17 Goreche, Melega, Gedeb, Bule, Mirab Azerenet, Enemorena Ener, Yem & Shey Bench/ ET-SNPPR-AGP-36364-CW- RFB / Construction of Jinka, Bonga and Arbaminch ARC SSIP (project name Neri, South Ari Woreda, Alega kebele, 40 Single Stage - One 2018-09- IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,584,876.00 674,138.41 Signed 2017-12-20 2018-01-10 2017-12-25 2018-01-24 2018-02-09 2018-02-23 2019-09-02 2018-03-30 2018-03-14 Ha) / (project name Shenba, Envelope 26 Gimbo Woreda, shenba kebele 70 Ha & project name-------- , Arbaminch Zuria Woreda, --- -----kebele, 30 Ha/ ET-SNPPR-AGP-36252-CW- RFB / Rehabilitation of existing modern small scale Single Stage - One 2018-08- irrigation project (project IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 72,202.00 0.00 Canceled 2017-11-22 2017-11-27 2017-12-27 2018-01-26 2018-03-02 Envelope 29 name Bazera, Basketo S/Woreda, Bazerakebele, 60 Ha) ET-SNPPR-AGP-36186-CW- RFB / Construction of New Medium Scale Irrigation Single Stage - One 3,658,673.2 2018-10- Project (project name IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 3,754,512.00 Signed 2017-11-22 2017-11-30 2017-11-27 2017-12-27 2017-12-29 2018-02-25 2019-09-02 2018-04-01 2018-02-02 Envelope 6 28 Megecha-1, Cheha Woreda, Degage/Yesher Kebele, 347 Ha) ET-SNPPR-AGP-36359-CW- RFB / Construction of 3 New Small Scale Irrigation Project (project name Gashume, Esera Woreda,-----------kebele, Single Stage - One 1,462,283.8 2018-07- 70 Ha) (project name Woi, IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,812,055.00 Signed 2017-12-06 2017-11-30 2017-12-11 2018-01-10 2017-12-29 2018-02-09 2019-09-02 2018-03-16 2018-01-30 Envelope 8 14 Decha Woreda, Baska Diri Kebele, 85 Ha) (project name Shore, South Bench Woreda, Gedu Botersaytu Adisalem kebele, 93 Ha) ET-SNPPR-AGP-36217-CW- RFB / Single Stage - One 2018-07- Constructing/Establishing of IDA / 56050 Agricultural Research Post Request for Bids Open - National 11,642.00 0.00 Canceled 2017-11-20 2017-11-25 2017-12-25 2018-02-23 2018-03-30 Envelope 28 Queen Rearing and Beekeeping Training Center ET-SNPPR-AGP-36154-CW- Agriculture Marketing and Request for Single Stage - One 2018-09- RFQ / Construction of liquid IDA / 56050 Post Limited 36,100.00 0.00 Canceled 2018-02-05 2018-04-02 Value Chains Quotations Envelope 29 nitogen production house ET-SNPPR-AGP-36236-CW- RFB / Construction of micro dam on 9 woredas /Mirab Single Stage - One 2018-12- Azerenet, Misrak Azerenet, IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 685,920.00 0.00 Canceled 2018-02-09 2018-02-14 2018-03-16 2018-05-15 2018-06-19 Envelope 16 Alicho Wurriro ,Endegagn, Gumer, Geta, Yem, Benethmay & Melekoza ET-SNPPR-AGP-36248-CW- RFQ / Construction of fish pond digging & poultry production house (This construction type is a new Request for Single Stage - One 2018-06- IDA / 56050 Small Scale Irrigation Post Open - National 6,498.00 0.00 Canceled 2018-03-10 2018-05-18 technology. Which is Quotations Envelope 17 constructed jointly together. The drawing and bill of quantity are prepared as together and the same time) ET-SNPPR-AGP-41170-CW- RFB / Construction of New Small Scale Irrigation Project Single Stage - One 2018-10- (project name Quanquaye, IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 821,426.00 576,749.13 Signed 2017-12-30 2019-09-06 2018-01-04 2018-02-03 2018-02-09 2018-03-20 2019-09-06 2018-04-14 2018-03-06 Envelope 11 Alicho wurriro Woreda, 40 Ha and project name Kecher, Cheha woreda, 70 Ha) ET-SNPPR-AGP-41181-CW- RFB / Construction of New Small Scale Irrigation Project Single Stage - One 2018-10- IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 514,753.00 536,950.76 Completed 2017-12-30 2018-01-10 2018-01-04 2018-02-03 2018-02-09 2018-03-20 2019-09-02 2018-04-14 2018-02-27 (project name Chelechele, Envelope 11 Gedebe Woreda, Banko Chelechel Kebele, 52 Ha) ET-SNPPR-AGP-43742-CW- Agriculture Marketing and Single Stage - One 2018-07- RFB / Construction of liquid IDA / 56050 Post Request for Bids Open - National 36,100.00 0.00 Canceled 2018-01-22 2018-01-27 2018-02-26 2018-03-28 2018-05-02 Value Chains Envelope 31 nitrogen production house Page 1 ET-SNPPR-AGP-58180-CW- RFB / Construction of weger Single Stage - One 2019-01- IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 355,480.00 340,232.35 Signed 2018-04-10 2019-08-05 2018-04-15 2018-05-15 2018-05-15 2018-06-14 2019-08-05 2018-07-19 2018-06-29 SSIP (58 ha, alicho wurriro Envelope 15 woreda) ET-SNPPR-AGP-81123-CW- Single Stage - One 2019-08- RFB / Construction of micro IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,071,428.00 456,909.61 Signed 2018-12-03 2018-11-30 2018-12-08 2019-01-07 2019-01-02 2019-01-22 2019-01-15 2019-02-26 2019-02-19 Envelope 25 dam ET-SNPPR-AGP-83554-CW- RFB / Construction of three Single Stage - One 2,366,765.2 2019-10- small scale irrigation project IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 2,635,714.00 Signed 2018-10-22 2018-11-02 2018-10-27 2018-11-26 2018-12-04 2018-12-26 2019-08-26 2019-01-30 2019-01-09 Envelope 9 27 (bita, gewata and gimbo woredas 375 ha) lot one ET-SNPPR-AGP-83555-CW- RFB / Construction of three Single Stage - One 2019-10- small scale irrigation project IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,950,000.00 901,479.52 Signed 2018-10-22 2018-11-02 2018-10-27 2018-11-26 2018-12-04 2018-12-26 2019-01-14 2019-01-30 2019-01-16 Envelope 27 (tocha, yeki and north ari woredas 329 ha) lot two ET-SNPPR-AGP-83556-CW- RFB / Construction of two Single Stage - One 2019-10- small scale irrigation project IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,021,428.00 474,188.21 Signed 2018-10-22 2018-11-02 2018-10-27 2018-11-26 2018-12-04 2018-12-26 2018-12-14 2019-01-30 2019-01-16 Envelope 27 (geta and gummer woredas 153 ha) lot three ET-SNPPR-AGP-38897-CW- CDD / Construction of Trial bridge /Dawero zone, Tocha Agriculture Marketing and Community Driven 2018-06- Woreda, Gedacheche and IDA / 56050 Prior Direct 41,347.00 0.00 Canceled 2017-12-06 2017-12-29 2017-12-11 2018-01-25 Value Chains Development 24 Gedacheche kebele, bridge name Yechi, span meter 109.38, D-type/ ET-SNPPR-AGP-103638-CW- RFB / Construction of five small scale irrigation project Single Stage - One 2019-12- IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 2,607,142.00 0.00 Canceled 2019-02-27 2019-03-04 2019-04-03 2019-05-03 2019-06-07 /tocha, essera, konta and Envelope 04 basketo woredas 266 ha/ lot one ET-SNPPR-AGP-103182-CW- RFB / Construction of seven small scale irrigation project Single Stage - One 2019-12- IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 3,357,142.00 0.00 Canceled 2019-02-27 2019-03-04 2019-04-03 2019-05-03 2019-06-07 /bursa, gorche, wendogenet, Envelope 04 arbegona, bule and gedeb woredas 425 ha/ lot three ET-SNPPR-AGP-103174-CW- RFB / Construction of Agriculture Marketing and Single Stage - One 2019-12- IDA / 56050 Post Request for Bids Open - National 272,000.00 369,127.77 Signed 2019-02-27 2019-04-25 2019-03-04 2019-04-03 2019-06-24 2019-05-03 2019-08-29 2019-06-07 2019-06-24 warehouse for union Value Chains Envelope 04 /gamogofa zone/ ET-SNPPR-AGP-103642-CW- RFB / Construction of Agriculture Marketing and Single Stage - One 2019-12- IDA / 56050 Post Request for Bids Open - National 272,000.00 335,976.13 Signed 2019-02-27 2019-05-11 2019-03-14 2019-04-13 2019-06-03 2019-05-13 2019-08-29 2019-06-17 2019-07-05 warehouse for union /siltie Value Chains Envelope 14 zone/ ET-SNPPR-AGP-103177-CW- RFB / Construction of Agriculture Marketing and Single Stage - One 2019-12- IDA / 56050 Post Request for Bids Open - National 272,000.00 335,826.13 Signed 2019-02-27 2019-05-21 2019-03-04 2019-04-03 2019-06-28 2019-05-03 2019-08-28 2019-06-07 2019-07-29 warehouse for union /bench Value Chains Envelope 04 maji zone/ ET-SNPPR-AGP-103184-CW- Agricultural Public Support Single Stage - One 2019-12- RFB / Construction of queen IDA / 56050 Post Request for Bids Open - National 357,142.00 298,495.89 Signed 2019-02-27 2019-08-26 2019-03-04 2019-04-03 2019-04-15 2019-05-03 2019-08-26 2019-06-07 2019-06-20 Services Envelope 04 rearing center /keffa zone/ ET-SNNPR-AGP-103646-CW- CDD / Construction of Trial bridge /Dawero zone, Tocha Agricultural Public Support Community Driven 2018-05- Woreda, Gedacheche and IDA / 56050 Post Direct 41,347.00 38,692.56 Signed 2017-12-09 2019-10-09 2017-12-14 2019-10-09 2018-02-02 2017-08-18 Services Development 03 Gedacheche kebele, bridge name Yechi, span meter 109.38, D-type/ ET-SNPPR-AGP-110472-CW- RFQ / Rehabilitation of sala Request for Single Stage - One 2019-09- SSIP /south omo zone north IDA / 56050 Small Scale Irrigation Post Limited 128,725.00 0.00 Canceled 2019-04-21 2019-06-16 Quotations Envelope 14 ari woreda alfaro and shera difty kebele 53 ha/ ET-SNPPR-AGP-111055-CW- RFB / Construction of milk & Agriculture Marketing and Single Stage - One 2020-01- IDA / 56050 Post Request for Bids Open - National 449,999.00 594,070.02 Signed 2019-04-17 2019-08-30 2019-04-22 2019-05-22 2019-05-30 2019-06-06 2019-08-30 2019-07-05 2019-07-05 honey collection and Value Chains Envelope 01 processing center ET-SNNPR-WONDO WO-AGP- 210348-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,720.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sidama Region Wondo Genet Woreda/ ET-SNNPR-MEL-WO-AGP- 210321-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,475.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sidama Region Melga Woreda/ ET-SNNPR-GOR-WO-AGP- 210481-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,480.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sidama Region Gorche Woreda/ Page 2 ET-SNNPR-AGP-ARB-WO- 210318-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,890.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sidama Region Arbegona Woreda/ ET-SNNPR-AGP-SHA-WO- 210316-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,460.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sidama Region Shafamo Woreda/ ET-SNNPR-BUR-WO-AGP- 210339-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,380.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sidama Region Bursa Woreda/ ET-SNNPR-TET-WO-AGP- 210335-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 80,130.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sidama Region Teticha Woreda/ ET-SNNPR-MIR AZ-WO-AGP- 210456-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 81,100.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Siltie Zone Mirab Azernet Woreda/ ET-SNNPR-MIA-WO-AGP- 210314-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,800.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Siltie Zone Misraq Azernet Woreda/ ET-SNNPR-ALI-WO-AGP- 210315-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 78,690.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Siltie Zone Alicho Wuriro Woreda/ ET-SNNPR-ESS-WO-AGP- 210324-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,620.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP/Dawro Zone Essera Woreda/ ET-SNNPR-TOC-WO-AGP- 210482-CW-RFQ / Construction works Pending Request for Single Stage - One 2021-06- forUpgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 78,600.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Dawro Zone Tocha Woreda/ ET-SNNPR-TER ZU-WO-AGP- 210462-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,720.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Dawro Zone Tercha Zuriya Woreda/ ET-SNNPR-KEC-WO-AGP- 210469-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 78,200.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Dawro Zone Kechi Woreda/ ET-SNNPR-DEB ARI-WO-AGP- 210473-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,600.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Debub Omo Zone Debub Ari Woreda/ ET-SNNPR-WUBA-WO-AGP- 210470-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,200.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Debub Omo Zone Wuba Ari Woreda/ ET-SNNPR-BAKA-WO-AGP- 210471-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,900.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Debub Omo Zone Baka Dawla Woreda/ Page 3 ET-SNNPR-SEMEN ARI-AGP- 210496-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 81,800.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Debub Omo Zone Semen Ari Woreda/ ET-SNNPR-BENA-WO-AGP- 210484-CW-RFQ / Construction works for Pending Upgrading and/or Request for Single Stage - One 2021-06- IDA / 56050 Small Scale Irrigation Post Limited 80,800.00 0.00 Implementat 2021-01-01 2021-03-01 Improvement of Quotations Envelope 29 ion ExistingTraditional SSIP /Debub Omo Zone Benatsemay Woreda/ ET-SNNPR-DEC-WO-AGP- 210329-CW-RFQ / Construction works Pending Request for Single Stage - One 2021-06- forUpgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 80,600.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Kaffa Zone Decha Woreda/ ET-SNNPR-GOBA-WO-AGP- 210497-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 80,200.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Keaffa Zone Goba Woreda/ ET-SNNPR-CHEN-WO-AGP- 210483-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,500.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Kaffa Zone Chena Woreda/ ET-SNNPR-SHI-WO-AGP- 210475-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,900.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Kaffa Zone Shisho Ende Woreda/ ET-SNNPR-GIM-WO-AGP- 210341-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,800.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Kaffa Zone Gimbo Woreda/ ET-SNNPR-GEW-WO-AGP- 210479-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,800.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Kaffa Zone Gewata Woreda/ ET-SNNPR-BITA-WO-AGP- 210498-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 81,000.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Kaffa Zone Bita Woreda/ ET-SNNPR-ENE-WO-AGP- 210332-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 80,900.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gurage Zone Enemorna Ener Woreda/ ET-SNNPR-ENOR-WO-AGP- 210499-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 80,700.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gurage Zone Enor Ener Woreda/ ET-SNNPR-END-WO-AGP- 210343-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,500.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gurage Zone Endegagn Woreda/ ET-SNNPR-CH-WO-AGP- 210465-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 77,700.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gurage Zone Cheha Woreda/ ET-SNNPR-GUM-WO-AGP- 210468-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 77,200.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gurage Zone Gumer Woreda/ Page 4 ET-SNNPR-AGP-GETA-WO- 210323-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,800.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gurage Zone Geta Woreda/ ET-SNNPR-BULE-WO-AGP- 210480-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 80,600.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gedeo Zone Bule Woreda/ ET-SNNPR-RAP-WO-AGP- 210477-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 80,100.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gedeo Zone Raphe Woreda/ ET-SNNPR-GED-WO-AGP- 210494-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,200.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gedeo Zone Gedeb Woreda/ ET-SNNPR-CHO-WO-AGP- 210458-CW-RFQ / Construction works for Pending Request for 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post 79,600.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations 29 Improvement of Existing ion Traditional SSIP /Gedeo Zone Chorso Woreda/ ET-SNNPR-DEB BEN-WO-AGP- 210474-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,200.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Bench Sheko Zone Debub Bench Woreda/ ET-SNNPR-SHEY BEN-WO- AGP-210337-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,000.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Bench Sheko Zone Shey Bench Woreda/ ET-SNNPR-SEM BEN-WO-AGP- 210491-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,900.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Bench Sheko Zone Semen Bench Woreda/ ET-SNNPR-GIDI BE-AGP- 210346-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,400.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Bench Sheko Zone Gidi Bench Woreda/ ET-SNNPR-ME-WO-AGP- 210452-CW-RFQ / Construction works for Pending Upgrading and/or Request for Single Stage - One 2021-06- IDA / 56050 Small Scale Irrigation Post Limited 79,800.00 0.00 Implementat 2021-01-01 2021-03-01 Improvement of Existing Quotations Envelope 29 ion Traditional SSIP /Bench Sheko Zone Me'anit Goldiya Bench Woreda/ ET-SNNPR-GAC-WO-AGP- 210478-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 80,000.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Mirab Omo Zone Gachit Woreda/ ET-SNNPR-YEKI-WO-AGP- 210467-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,700.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sheka Zone Yeki Woreda/ ET-SNNPR-AND-WO-AGP- 210472-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,900.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Sheka Zone Andracha Woreda/ ET-SNNPR-MELO-WO-AGP- 210476-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,700.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gofa Zone Melokoza Woreda/ Page 5 ET-SNNPR-MELO GA-WO- AGP-210460-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,300.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Gofa Zone Melo Gada Woreda/ ET-SNNPR-KON-WO-AGP- 210461-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,800.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Konta Special Woreda/ ET-SNNPR-BAS-WO-AGP- 210464-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,600.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Basketo Special Woreda/ ET-SNNPR-YEM-WO-AGP- 210454-CW-RFQ / Construction works for Pending Request for Single Stage - One 2021-06- Upgrading and/or IDA / 56050 Small Scale Irrigation Post Limited 79,700.00 0.00 Implementat 2021-01-01 2021-03-01 Quotations Envelope 29 Improvement of Existing ion Traditional SSIP /Yem Special Woreda/ ET-SNPPR-AGP-2-ICSDDA- 212261-CW-RFQ / Construction of Arbaminch Pending Request for Single Stage - One 2021-08- Agricultural Research Center IDA / 56050 Small Scale Irrigation Post Limited 70,000.00 0.00 Implementat 2021-01-13 2021-03-14 Quotations Envelope 11 for Additional and Remaining ion Works /Gamo Zone Arbaminch Woreda 25 Ha/ ET-SNPPR-AGP-2-ICSDAA- 212255-CW-RFQ / Pending Construction of Quanquaye Request for Single Stage - One 2021-08- IDA / 56050 Small Scale Irrigation Post Limited 156,000.00 0.00 Implementat 2021-01-14 2021-03-15 Small Scale Irrigation Project Quotations Envelope 12 ion for Remaining Works /Gurage Zone Gumer Woreda 40 Ha/ ET-SNPPR-AGP-2-ICSDAA- 212258-CW-RFB / Construction of Petu Small Pending Single Stage - One 2021-09- Scale Irrigation Project for IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 665,000.00 0.00 Implementat 2021-01-03 2021-01-13 2021-02-12 2021-02-27 2021-03-29 Envelope 25 Remaining Works /Bench ion Sheko Zone Semen Bench Woreda 84 Ha/ ET-SNPPR-AGP-2-ICSDDA- 212260-CW-RFB / Pending Construction of Mojo Small Single Stage - One 2021-09- IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 414,000.00 0.00 Implementat 2021-01-03 2021-01-13 2021-02-12 2021-02-27 2021-03-29 Scale Irrigation Project for Envelope 25 ion Remaining Works /Gofa Zone Melokoza Woreda 60 Ha/ GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SNPPR-AGP-36373-GO- RFQ / Purchase of garden Agricultural Public Support Request for Single Stage - One equipments /Prunning IDA / 56050 Post Limited 39,710.00 32,703.79 Completed 2018-01-20 2019-10-10 2018-03-17 2018-02-03 2018-05-16 2018-02-07 Services Quotations Envelope scissor, Saw & rope washer pump/ ET-SNPPR-AGP-36183-GO- RFQ / Purchase of office Project Management, Request for Single Stage - One equipments /IT equipments/ IDA / 56050 Capacity Building and Post Limited 24,072.00 0.00 Canceled 2017-12-16 2018-02-14 2018-04-15 Quotations Envelope laptop computer, Desktop Monitoring and Evaluation computer, Printer & EHD ET-SNPPR-AGP-36320-GO- Project Management, Request for Single Stage - One RFQ / Procurement of office IDA / 56050 Capacity Building and Post Limited 1,444.00 0.00 Canceled 2017-12-16 2018-01-19 2018-02-18 Quotations Envelope furniture /Chair & Table/ Monitoring and Evaluation ET-SNPPR-AGP-36367-GO- RFQ / Purchase of stationary Agricultural Public Support Request for Single Stage - One and office supplies /Saftey IDA / 56050 Post Limited 21,408.00 1,645.80 Signed 2017-12-25 2019-10-10 2018-02-22 2019-07-05 2018-03-24 2018-07-06 Services Quotations Envelope shoe, Rain coat & Sleeping bag/ ET-SNPPR-AGP-36230-GO- Agricultural Public Support Request for Single Stage - One RFQ / Provision of kitchen IDA / 56050 Post Limited 12,636.00 0.00 Canceled 2018-01-03 2018-03-03 2018-04-02 Services Quotations Envelope equipments ET-SNPPR-AGP-36147-GO- Agricultural Public Support Request for Single Stage - One RFQ / Purchase of day old IDA / 56050 Post Limited 1,444.00 0.00 Canceled 2018-03-10 2018-05-01 2018-05-31 Services Quotations Envelope chicken/layers ET-SNPPR-AGP-36385-GO- RFB / Purchase of laboratory equipments /soil testing, seed Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 608,444.00 1,199,574.43 Completed 2017-12-04 2019-08-25 2017-12-09 2018-01-08 2018-01-09 2018-02-22 2019-10-08 2018-03-29 2018-05-17 2018-07-27 2019-05-16 quality analysis, agricultural Services Envelope input testing and soil tesing laboratory equipments/ ET-SNPPR-AGP-36177-GO- RFQ / Procurement of wireless Project Management, information sharing and Request for Single Stage - One IDA / 56050 Capacity Building and Post Limited 25,270.00 0.00 Canceled 2017-12-16 2018-02-10 2018-04-11 control technology system Quotations Envelope Monitoring and Evaluation /Server & Window server (server operating system) Page 6 ET-SNPPR-AGP-36374-GO- RFQ / Procurement of Request for Single Stage - One surveying equipments /Total IDA / 56050 Small Scale Irrigation Post Limited 36,101.00 0.00 Canceled 2018-01-09 2018-03-06 2018-04-05 Quotations Envelope station, Level instrument and GPS ET-SNPPR-AGP-36386-GO- RFQ / Provision of laboratory Agricultural Public Support Request for Single Stage - One equipments /forage seed IDA / 56050 Post Open - National 43,320.00 24,914.14 Completed 2017-12-09 2018-02-13 2018-02-22 2018-04-14 2018-07-02 Services Quotations Envelope multiplication center and animal health/ ET-SNPPR-AGP-36166-GO- Agricultural Public Support Request for Single Stage - One RFQ / Purchase of sexed IDA / 56050 Post Limited 41,516.00 0.00 Canceled 2017-12-02 2018-01-27 2018-02-26 Services Quotations Envelope semen ET-SNPPR-AGP-36382-GO- RFB / Procurement of animal feed processing equipments Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 86,642.00 0.00 Canceled 2018-03-15 2018-03-20 2018-04-19 2018-05-19 2018-06-23 2018-06-27 /feed processing machine & Services Envelope Urea Molases Block (UMB) machine/ ET-SNPPR-AGP-36198-GO- Agricultural Public Support Request for Single Stage - One RFQ / Provision of printing IDA / 56050 Post Open - National 12,635.00 0.00 Canceled 2018-04-07 2018-06-15 2018-07-15 Services Quotations Envelope and publication ET-SNPPR-AGP-36118-GO- RFB / Procurement of vehicles Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 505,415.00 0.00 Canceled 2017-11-20 2017-11-25 2017-12-25 2018-01-24 2018-02-28 2018-06-28 /Dump Truck, Scavator & Services Envelope Station wagon long base/ ET-SNPPR-AGP-36317-GO- DIR / Procurement of Improved agricultural inputs Under Agricultural Public Support for demonestration tecnology IDA / 56050 Post Direct Selection Direct 18,628.00 0.00 Implementati 2018-01-22 2019-10-11 2018-01-27 2019-10-11 2018-03-02 2018-04-11 Services on FTC /Blended fertilizer, Bio on fertilizer, Urea Potassium, Sachet & Vermi worm/ ET-SNPPR-AGP-44465-GO- Agricultural Public Support Single Stage - One RFB / Purchase of sexed IDA / 56050 Post Request for Bids Open - National 41,516.00 0.00 Canceled 2018-02-09 2018-02-19 2018-03-21 2018-04-20 2018-05-14 2018-08-12 Services Envelope semen ET-SNPPR-AGP-44468-GO- RFB / Procurement of wireless Project Management, information sharing and Single Stage - One IDA / 56050 Capacity Building and Post Request for Bids Open - National 25,270.00 0.00 Canceled 2018-02-28 2018-03-10 2018-04-09 2018-05-09 2018-06-02 2018-09-30 control technology system Envelope Monitoring and Evaluation /Server & server operating system/ ET-SNPPR-AGP-44469-GO- RFB / Purchase of office Project Management, Single Stage - One equipments /IT equipments/ IDA / 56050 Capacity Building and Post Request for Bids Open - National 39,700.00 38,056.24 Completed 2018-01-31 2019-08-31 2018-02-10 2018-03-12 2018-09-25 2018-04-11 2019-08-31 2018-05-05 2018-12-19 2018-08-03 2019-01-22 Envelope laptop computer, Desktop Monitoring and Evaluation computer, Printer & EHD......../ ET-SNPPR-AGP-44472-GO- Agricultural Public Support Single Stage - One RFB / Provision of kitchen IDA / 56050 Post Request for Bids Open - National 16,245.00 0.00 Canceled 2018-01-31 2018-02-10 2018-03-12 2018-04-11 2018-05-05 2018-07-04 Services Envelope equipments ET-SNPPR-AGP-44476-GO- Project Management, RFB / Procurement of office Single Stage - One IDA / 56050 Capacity Building and Post Request for Bids Open - National 5,415.00 0.00 Canceled 2018-01-31 2018-02-10 2018-03-12 2018-04-11 2018-05-05 2018-07-04 furniture /Chair, Table, Envelope Monitoring and Evaluation Shelf..../ ET-SNPPR-AGP-44480-GO- Agricultural Public Support Single Stage - One RFB / Procurement of day old IDA / 56050 Post Request for Bids Open - National 1,444.00 0.00 Canceled 2018-02-09 2018-02-19 2018-03-21 2018-04-20 2018-05-14 2018-07-13 Services Envelope chicken/layers ET-SNPPR-AGP-44482-GO- RFB / Procurement of Single Stage - One surveying equipments /Total IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 36,101.00 0.00 Canceled 2018-02-28 2018-03-10 2018-04-09 2018-05-09 2018-06-02 2018-08-31 Envelope station, Level instrument & GPS/ ET-SNPPR-AGP-50503-GO- Agricultural Public Support Request for Single Stage - One RFQ / Purchase of auditorium IDA / 56050 Post Limited 21,660.00 33,037.78 Completed 2018-02-23 2019-08-31 2018-03-03 2018-02-22 2018-03-23 2018-09-06 Services Quotations Envelope seats/chairs/ ET-SNNPR-AGP-56692-GO- Agricultural Public Support Single Stage - One RFB / Purchase of rope and IDA / 56050 Post Request for Bids Open - National 12,635.00 9,418.21 Completed 2018-04-10 2019-08-30 2018-04-15 2018-05-15 2018-05-14 2018-05-25 2019-08-30 2018-06-23 2018-08-30 2018-08-07 2019-02-01 Services Envelope washer pump ET-SNPPR-AGP-79198-GO- Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 98,364.00 47,110.95 Signed 2018-06-10 2018-12-25 2018-06-15 2018-07-15 2019-01-23 2018-07-25 2019-01-25 2018-08-23 2019-02-26 2018-11-21 RFB / Procurement of lime Services Envelope ET-SNPPR-AGP-81227-GO- Single Stage - One RFB / Procurement of motor IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 642,857.00 564,780.68 Completed 2018-10-17 2019-03-29 2018-10-22 2018-11-21 2019-04-29 2018-12-11 2019-04-29 2019-01-10 2019-06-05 2019-05-10 2019-06-18 Envelope cycle ET-SNPPR-AGP-93861-GO- RFB / Procurement of liquid Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 42,857.00 0.00 Canceled 2019-01-16 2019-01-21 2019-02-20 2019-03-07 2019-04-06 2019-07-05 nitrogen container & deep Value Chains Envelope freeze ET-SNPPR-AGP-82441-GO- Agricultural Public Support Single Stage - One RFB / Purchase of bow saw, IDA / 56050 Post Request for Bids Open - National 37,500.00 11,032.80 Completed 2018-10-22 2018-10-23 2018-10-27 2018-11-26 2018-11-22 2018-12-11 2018-12-06 2019-01-10 2019-01-11 2019-02-19 2019-01-16 Services Envelope bow saw blade and scissor ET-SNPPR-AGP-95591-GO- Under RFB / Procurement of earth Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 535,714.00 0.00 Implementati 2019-01-19 2019-02-04 2019-01-24 2019-02-23 2019-03-06 2019-03-25 2019-03-25 2019-04-23 2019-08-21 moving equipment /excavator Services Envelope on and dump truck/ ET-SNPPR-AGP-95593-GO- RFB / Procurement of vehicles Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-01-19 2019-01-24 2019-02-23 2019-03-25 2019-04-24 2019-08-22 /pick up and long base nine Services Envelope seat/ Page 7 ET-SNPPR-AGP-95595-GO- Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 25,714.00 24,948.89 Completed 2019-01-24 2019-02-15 2019-02-27 2019-03-20 2019-03-29 2019-05-15 RFQ / Procurement of scissor Services Quotations Envelope ET-SNPPR-AGP-95596-GO- Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 285,714.00 299,423.52 Signed 2019-01-19 2019-02-04 2019-01-24 2019-02-23 2019-03-05 2019-03-10 2019-04-03 2019-04-09 2019-05-07 2019-07-08 RFB / Procurement of lime Services Envelope ET-SNPPR-AGP-98547-GO- DIR / Procurement of improved agricultural inputs Under /basic, pre basic and certified Agricultural Public Support IDA / 56050 Post Direct Selection Direct 14,027.00 0.00 Implementati 2019-02-03 2019-10-11 2019-02-13 2019-10-11 2019-03-10 2019-04-09 seeds/ for demonestration on Services on FTC /fertlizer, maize, haricobean, wheat, barley, teff, soya bean, vermi worm/ ET-SNPPR-AGP-36142-GO- DIR / Purchase of Improved Agricultural Public Support IDA / 56050 Prior Direct Selection Direct 171,749.00 0.00 Canceled 2017-11-20 2017-12-07 2017-11-25 2018-03-20 2018-01-09 2018-02-08 agricultural technologies /Tie- Services Reger & Aybar BBM/ ET-SNPPR-AGP-36394-GO- DIR / Purchase of basic Improved seed and agricultural inputs for demonestration tecnology on Agricultural Public Support FTC (Hibred parental line IDA / 56050 Prior Direct Selection Direct 265,187.00 0.00 Canceled 2018-02-12 2018-02-17 2018-04-03 2018-07-02 Services seed, Haricot bean, Forage seed & Malt barley)Protein maize, Faba bean, Haircot bean, Cheack pea, Avocado, Improved coffee seed/ ET-SNPPR-AGP-103172-GO- Project Management, RFQ / Procurement of tablet Request for Single Stage - One IDA / 56050 Capacity Building and Post Limited 7,142.00 8,708.06 Completed 2019-03-04 2019-05-24 2019-04-08 2019-06-24 2019-05-08 2019-07-03 computer for upgrading IT Quotations Envelope Monitoring and Evaluation and net work system Project Management, Under ET-SNPPR-AGP-103178-GO- Request for Single Stage - One IDA / 56050 Capacity Building and Post Limited 3,571.00 752.55 Implementati 2019-03-04 2019-10-09 2019-04-15 2019-05-15 RFQ / Purhase of safety shoe Quotations Envelope Monitoring and Evaluation on ET-SNNPR-AGP-36142-GO- DIR / Purchase of Improved Agricultural Public Support IDA / 56050 Post Direct Selection Direct 171,749.00 138,194.24 Completed 2017-12-07 2019-10-09 2017-12-22 2019-10-09 2018-01-26 2018-01-29 2018-07-25 2018-02-08 agricultural technologies /Tie- Services Reger & Aybar BBM/ ET-SNNPR-AGP-36394-GO- DIR / Purchase of basic Improved seed and agricultural inputs for demonestration tecnology on Agricultural Public Support FTC (Hibred parental line IDA / 56050 Post Direct Selection Direct 265,187.00 180,293.46 Signed 2018-02-12 2019-10-11 2018-02-17 2019-10-11 2018-03-24 2018-07-03 2018-05-23 2018-07-03 Services seed, Haricot bean, Forage seed & Malt barley)Protein maize, Faba bean, Haircot bean, Cheack pea, Avocado, Improved coffee seed/ ET-SNPPR-AGP-108166-GO- DIR / Procurement of soil Agricultural Public Support fertility management IDA / 56050 Post Direct Selection Direct 55,000.00 53,348.61 Completed 2019-03-28 2019-04-24 2019-04-07 2019-05-21 2019-05-11 2019-06-24 2019-06-10 2019-06-26 Services technologies /tie ridger and berken maresha/ ET-SNPPR-AGP-110483-GO- RFQ / Provision of improved Agriculture Marketing and Request for Single Stage - One IDA / 56050 Post Limited 22,961.00 12,726.35 Completed 2019-04-19 2019-10-09 2019-06-07 2019-05-09 2019-08-06 2019-05-16 basic forage, forage seeds for Value Chains Quotations Envelope poultry and fish development ET-SNPPR-AGP-111054-GO- RFQ / Purchase of fishery materials and equipments Agriculture Marketing and Request for Single Stage - One /fishing gill net, beach seine IDA / 56050 Post Limited 27,000.00 7,493.33 Completed 2019-04-23 2020-10-14 2019-06-05 2020-04-08 2019-08-04 2020-05-25 Value Chains Quotations Envelope net, wooden fishing boat, life saving jacket, geo memberane.../ ET-SNPPR-AGP-111053-GO- RFB / Procurement of materials /equipments/ for milk and honey collection & processing center /aluminummilk cane, churner, Agriculture Marketing and Single Stage - One IDA / 56050 Post Request for Bids Open - National 131,000.00 44,497.74 Completed 2019-04-19 2019-04-29 2019-04-24 2019-05-24 2019-05-29 2019-06-08 2019-10-08 2019-07-07 2019-07-03 2019-10-05 2019-07-09 cram separator, weighing Value Chains Envelope balance, lactometer, container for cheese making, butter knife..., honey tank, packaging material, honey sive... ET-SNPPR-AGP-113983-GO- RFQ / Procurement bovans breed /day old chickens/ and Pending koek koek or sasso breed Agriculture Marketing and Request for Single Stage - One IDA / 56050 Post Limited 69,000.00 0.00 Implementati 2019-05-12 2019-06-23 2019-07-23 /day old chickens/, grawer Value Chains Quotations Envelope on chicken ration and layers chicken ration, day old chicks feederer and day old waterer ET-SNPPR-AGP-113992-GO- RFQ / Purchase of 100 watt Agriculture Marketing and Request for Single Stage - One IDA / 56050 Post Limited 2,300.00 1,439.51 Completed 2019-05-12 2020-09-30 2019-06-24 2020-04-07 2019-07-04 2020-05-19 light, light cover and electric Value Chains Quotations Envelope wire 1.5 mm tickness ET-SNPPR-AGP-113993-GO- Pending RFQ / Provision office Agriculture Marketing and Request for Single Stage - One IDA / 56050 Post Limited 10,000.00 0.00 Implementati 2019-05-12 2019-06-24 2019-07-24 furniture for milk collection Value Chains Quotations Envelope on and processing center ET-SNPPR-AGP-113982-GO- RFQ / Purchase of 42 Agriculture Marketing and Request for Single Stage - One Improved rams sheep & 420 IDA / 56050 Post Limited 42,000.00 0.00 Canceled 2019-05-12 2019-07-09 2019-08-08 Value Chains Quotations Envelope local ewes sheep and 88 Improved bucks goat Page 8 ET-SNPPR-AGP-113980-GO- Under Agriculture Marketing and Request for Single Stage - One RFQ / Provision of 10 liquid IDA / 56050 Post Limited 43,000.00 11,824.32 Implementati 2019-05-12 2019-10-09 2019-06-23 2019-07-23 Value Chains Quotations Envelope nitrogen container 35 litre on ET-SNPPR-AGP-118275-GO- RFB / Procurement of vehicles Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Limited 430,000.00 394,760.80 Completed 2019-06-06 2019-05-07 2019-06-11 2019-05-07 2019-06-18 2019-05-17 2019-06-25 2019-05-17 2019-07-12 2019-06-14 2019-07-27 2019-06-17 /three station wagon and one Services Envelope double cabin pickup/ ET-SNNPR-AGP-147332-GO- RFQ / Purchase of office Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 14,700.00 12,875.44 Completed 2019-12-16 2020-10-14 2020-01-19 2020-01-21 2020-02-18 2020-01-28 furniture /chair 42, table 28 & Services Quotations Envelope shelf 14/ ET-SNNPR-AGP-147338-GO- RFQ / Provision of IT equipment /30 lap top Agricultural Public Support Request for Single Stage - One computer, 30 desk top IDA / 56050 Post Limited 45,400.00 58,149.68 Completed 2019-12-14 2020-10-02 2020-01-17 2020-01-21 2020-03-17 2020-02-05 Services Quotations Envelope computer, 30 printer, 1 color printer, 1 LCD projector, 1 digital photo camera/ ET-SNNPR-AGP-147335-GO- RFQ / Procurement of garden Agricultural Public Support Request for Single Stage - One equipment /1442 scissors , IDA / 56050 Post Limited 28,400.00 6,724.03 Completed 2019-12-14 2020-09-28 2020-01-17 2019-12-27 2020-03-17 2020-01-28 Services Quotations Envelope 1442 bow saw and 1442 bow saw blade/ ET-SNPPR-AGP-152643-GO- Under RFQ / Provision of grower and Agriculture Marketing and Request for Single Stage - One IDA / 56050 Post Limited 17,400.00 2,165.45 Implementati 2020-01-18 2020-10-14 2020-02-22 2020-03-23 layers concentrate feed 400 Value Chains Quotations Envelope on qunital ET-SNPPR-AGP-152642-GO- RFQ / Purchase of day old Agriculture Marketing and Request for Single Stage - One IDA / 56050 Post Limited 2,500.00 7,296.24 Completed 2020-01-18 2020-10-01 2020-02-22 2020-06-04 2020-03-23 2020-06-05 chicks feederer and waterer Value Chains Quotations Envelope 1600 quantity ET-SNNPR-AGP-152641-GO- DIR / Procurement of day old Under Agriculture Marketing and chicks bovans brown 3600 IDA / 56050 Post Direct Selection Direct 26,200.00 21,286.78 Implementati 2020-03-08 2020-09-28 2020-03-18 2020-09-30 2020-04-07 2020-05-07 Value Chains quantity, and day old chicks on kock kock 10752 quantity ET-SNPPR-AGP-167026-GO- Agricultural Public Support Request for Single Stage - One RFQ / Procurement of 125 cc IDA / 56050 Post Limited 60,000.00 57,476.82 Completed 2020-04-07 2020-10-01 2020-05-18 2020-06-25 2020-06-17 2020-06-30 Services Quotations Envelope motor cycle 28 quantity ET-SNPPR-AGP-171016-GO- RFQ / Procurement of sanitary materials /Protective materials/ for Development Agricultural Public Support Request for Single Stage - One Agents /DA's/ emergency IDA / 56050 Post Limited 18,000.00 22,249.68 Completed 2020-05-05 2020-10-12 2020-06-07 2020-05-21 2020-06-22 2020-05-22 Services Quotations Envelope case /1622 liter sanitizer, 3244 face masks, 1622 liter liquid soap and 1622 hand gloves/ ET-SNPPR-AGP-173957-GO- DIR / Purchase of different types of Improved early generation seeds /basic and Agricultural Public Support IDA / 56050 Post Direct Selection Direct 73,000.00 28,043.84 Completed 2020-05-16 2020-09-26 2020-05-26 2020-09-28 2020-06-12 2020-07-02 2020-06-27 2020-07-06 pre basic seed/ for certified Services seed production /Haricot Bean 20 qt, Barley 109 qt and Wheat 857.50 qt/ ET-SNPPR-AGP-208261-GO- RFB / Procurement of different types of equipment for queen rearing & training center lot 1, Pending Procurement of equipment for Agricultural Public Support Single Stage - One IDA / 56050 Post Request for Bids Open - National 121,300.00 0.00 Implementati 2020-12-06 2020-12-21 2021-01-20 2021-02-04 2021-03-05 2021-07-03 milk collection and processing Services Envelope on center lot 2 and Procurement of equipment for honey collection and processing center lot 3 ET-SNPPR-AGP-208263-GO- RFQ / Procurement of guest Pending house facilities for queen Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 3,750.00 0.00 Implementati 2020-12-21 2021-02-03 2021-03-05 rearing & training center Services Quotations Envelope on /mattress 50, pillow 50, blanket 50, bed sheet 50/ ET-SNPPR-AGP-208275-GO- RFQ / Provision of laboratory equipment for queen rearing Pending Agricultural Public Support Request for Single Stage - One & training center /microscope IDA / 56050 Post Limited 4,540.00 0.00 Implementati 2020-12-21 2021-01-28 2021-04-28 Services Quotations Envelope 1, incubator 1, thermometer on 3, water bath 2, hygrometer 3, ....../ ET-SNPPR-AGP-208264-GO- RFQ / Procurement of office furniture for queen rearing & Pending Agricultural Public Support Request for Single Stage - One training center and honey IDA / 56050 Post Limited 10,400.00 0.00 Implementati 2020-12-21 2021-01-29 2021-02-28 Services Quotations Envelope collection and processing on center /chair 123, table 68 and shelf 15/ ET-SNPPR-AGP-208271-GO- RFQ / Purchase of IT- equipments for queen rearing Pending & training center and honey Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 7,430.00 0.00 Implementati 2020-12-21 2021-02-02 2021-04-03 collection and processing Services Quotations Envelope on center /desktop computer 4, ups 4, printer 4, LCD projector 1, digital camera 1/ ET-SNPPR-AGP-208266-GO- RFQ / Provision of generator Pending Agricultural Public Support Request for Single Stage - One for milk and honey collection IDA / 56050 Post Limited 16,700.00 0.00 Implementati 2020-12-21 2021-02-06 2021-05-07 Services Quotations Envelope and processing center on /quantity 7/ Page 9 ET-SNPPR-AGP-208268-GO- RFQ / Purchase of safety cloth Pending for milk and honey collection Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 6,700.00 0.00 Implementati 2020-12-21 2021-02-02 2021-04-03 and processing center /tuta Services Quotations Envelope on 215, gloves 180, boots 215, gawn 35 and hair nets 35/ ET-SNPPR-AGP-208270-GO- RFQ / Provision of notice board /6/ and building Pending Agricultural Public Support Request for Single Stage - One notification /24/ for queen IDA / 56050 Post Limited 3,950.00 0.00 Implementati 2020-12-21 2021-02-02 2021-03-04 Services Quotations Envelope rearing & training center and on honey collection and processing center ET-SNPPR-AGP-208272-GO- RFQ / Procurement of window Pending curtain /161 meter/ for queen Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 3,410.00 0.00 Implementati 2020-12-21 2021-01-29 2021-02-28 rearing & training center and Services Quotations Envelope on honey collection and processing center ET-SNPPR-AGP-208273-GO- Pending RFQ / Procurement of angle Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 3,850.00 0.00 Implementati 2020-12-21 2021-02-02 2021-03-04 iron bed for queen rearing Services Quotations Envelope on and training center /quantity 50/ ET-SNPPR-AGP-218987-GO- RFQ / Procurement of scion (# Pending Agricultural Public Support Request for Single Stage - One 64590), Avocado Mother Tree IDA / 56050 Post Limited 29,000.00 0.00 Implementati 2021-02-26 2021-03-24 2021-05-23 Services Quotations Envelope (# 1500) and Avocado Seed on (600 kt) for fruit nursery ET-SNPPR-AGP-218985-GO- RFQ / Provision of Farm Tools & equipments (# 75 wheel barrow, # 150 water can, # Pending 150 grafting scissor, # 150 Agricultural Public Support Request for Single Stage - One IDA / 56050 Post Limited 14,000.00 0.00 Implementati 2021-02-26 2021-03-24 2021-05-23 grafting knife, # 30 knapsack Services Quotations Envelope on sprayer, # 51 saw, # 75 zabiya, # 75 shovel, # 72 gesso, # 75 pick, # 75 rake, # 75 pole) for fruit nursery ET-SNPPR-AGP-218988-GO- Pending Agricultural Public Support Request for Single Stage - One RFQ / Purchase of Polytene IDA / 56050 Post Limited 9,600.00 0.00 Implementati 2021-02-26 2021-03-24 2021-05-23 Services Quotations Envelope Bag (1500 kg) for fruit nursery on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SNPPR-AGP-95597-NC- Agricultural Public Support Single Stage - One RFB / Procurement of lime IDA / 56050 Post Request for Bids Open - National 134,957.00 86,387.86 Signed 2019-01-19 2019-10-09 2019-01-29 2019-02-28 2019-04-29 2019-03-30 2019-10-09 2019-04-29 2019-07-07 2019-06-28 Services Envelope transport service CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SNPPR-AGP-44303-CS- QCBS / Site identification, Feasibility Study & Design of Quality And Cost- IDA / 56050 Small Scale Irrigation Post Open - National 162,456.00 0.00 Canceled 2018-01-31 2018-02-15 2018-03-31 2018-04-30 2018-05-30 2018-06-27 2018-07-21 2018-11-18 SSIP (Geta, Endegagn, Gumer, Based Selection Cheha, Enemorena Ener and Yem Woredas) ET-SNPPR-AGP-44320-CS- QCBS / Site identification, Quality And Cost- Feasibility Study & Design of IDA / 56050 Small Scale Irrigation Post Open - National 135,380.00 0.00 Canceled 2018-01-31 2018-02-15 2018-03-31 2018-04-30 2018-05-30 2018-06-27 2018-07-21 2018-11-18 Based Selection SSIP (Gewata, Gimbo, Decha, Chena and Bita Woredas) ET-SNPPR-AGP-44334-CS- QCBS / Site identification, Feasibility Study & Design of Quality And Cost- IDA / 56050 Small Scale Irrigation Post Open - National 162,456.00 0.00 Canceled 2018-01-31 2018-02-15 2018-03-31 2018-04-30 2018-05-30 2018-06-27 2018-07-21 2018-11-18 SSIP (Anderacha, Yeki, South Based Selection Bench, Shey Bench, Menitgoldia and North Bench) ET-SNPPR-AGP-44355-CS- QCBS / Site identification, Feasibility Study & Design of Quality And Cost- Under IDA / 56050 Small Scale Irrigation Post Open - National 189,532.00 0.00 2018-01-31 2019-08-31 2018-02-15 2018-03-31 2018-04-30 2018-05-30 2018-06-27 2018-07-21 2018-11-18 SSIP (Arbegona, Gorche, Based Selection Implementation Malga, Bursa, WondoGenet, Bule and Gedeb Woredas) ET-SNPPR-AGP-44358-CS- QCBS / Site identification, Quality And Cost- Under Feasibility Study & Design of IDA / 56050 Small Scale Irrigation Post Open - National 81,228.00 0.00 2018-01-31 2019-08-31 2018-02-15 2018-03-31 2018-04-30 2018-05-30 2018-06-27 2018-07-21 2018-10-19 Based Selection Implementation SSIP (Alichoworiro, West Azerenet and East Azerenet) ET-SNPPR-AGP-44385-CS- QCBS / Site identification, Feasibility Study & Design of Quality And Cost- IDA / 56050 Small Scale Irrigation Post Open - National 135,380.00 0.00 Canceled 2018-01-31 2018-02-15 2018-03-31 2018-04-30 2018-05-30 2018-06-27 2018-07-21 2018-11-18 SSIP (South Ari, North Ari, Based Selection Benatsemay, Melekoza and Basketo Woredas) ET-SNPPR-AGP-44386-CS- QCBS / Site identification, Quality And Cost- Under Feasibility Study & Design of IDA / 56050 Small Scale Irrigation Post Open - National 81,228.00 0.00 2018-01-31 2018-02-15 2018-03-31 2018-04-30 2018-05-30 2018-06-27 2018-07-21 2018-10-19 Based Selection Implementation SSIP (Tocha, Essera and Konta Woreda) Page 10 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 11