Procurement Plan Balochistan Integrated Water Resources Management and Development Project I. General 1. Bank’s approval Date of the procurement Plan March 19,2016 2. Date of General Procurement Notice: January 2016 3. Period covered by this procurement plan: The procurement period of project covered from year January 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB (Goods) Above US$ 600,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 4 million All 4. NCB (Works) Upto US$ 4 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract 6. Community Driven Development Above US$ 25,000 First contract 2. Pre-qualification. Bidders for $ 15 million shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by Balochistan Government 5. Any Other Special Procurement Arrangements: Some preparatory activities under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) July 9, 2010 [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Estimated Packages Review Comments July 9, 2010 Description of Cost by Bank Assignment US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : PK-Balochistan Integrated Water Resources Management & Development Project PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2016-10-14 2020-01-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154255 GPN Date: 2017-07-10 Project Name: PK-Balochistan Integrated Water Resources Management & Development Project Loan / Credit No: IDA / 58850 Executing Agency(ies): PMU Balochistan Integrated Water Resources Management and Development Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-14383- Component B: Water, CW-RFB / Construction of Open - Single Stage - One IDA / 58850 Infrastructure and Prior Request for Bids 12,906,271.00 11,689,958.60 Signed 2017-05-11 2017-05-16 2017-06-30 2017-07-30 2017-09-03 2020-02-20 Nari Gorge Integrated International Envelope Management Investments Scheme PK-PMU-BIWRMDP-14453- Component B: Water, CW-RFB / Construction of Open - Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids 8,995,675.00 6,475,606.49 Terminated 2017-05-22 2017-05-27 2017-07-11 2017-08-10 2017-09-14 2020-03-02 Gundacha-Nurg Hingri International Envelope Management Investments Integrated Scheme PK-PMU-BIWRMDP-2420- CW-RFB / Nari Gorge Perennial Irrigation Scheme Component B: Water, Single Stage - One - Package 3 of 5 (Luni, IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,510,643.00 0.00 Canceled 2017-02-28 2017-03-07 2017-04-06 2017-05-06 2017-06-17 2018-12-09 Envelope Kurak, Bakhra Ghulam Management Investments Bolak and Marghzani Channels) PK-PMU-BIWRMDP-2419- CW-RFB / Nari Gorge Component B: Water, Single Stage - One Perennial Irrigation Scheme IDA / 58850 Infrastructure and Prior Request for Bids Open - National 1,434,724.00 0.00 Canceled 2017-02-28 2017-03-07 2017-04-06 2017-04-27 2017-06-08 2018-09-01 Envelope - Package 2 of 5 (Dehpal Management Investments Channel) PK-PMU-BIWRMDP-2432- CW-RFB / Gundacha Nurg Hingri Scheme - Package 2 of 2 (Construction of Irrigation Channel, Nurg Component B: Water, Open - Single Stage - One Hingri Off Take Weirs and IDA / 58850 Infrastructure and Post Request for Bids 4,601,570.00 0.00 Canceled 2017-05-09 2017-05-19 2017-07-10 2017-08-04 2017-09-17 2019-09-07 International Envelope Under Sluice, Nurg Hingri Management Investments Channels and Guide Banks, Glacis Fall Structures, Road Culverts, Outlet Structures and Drainage Culverts) PK-PMU-BIWRMDP-2431- CW-RFB / Gundacha Nurg Component B: Water, Hingri Irrigation Scheme - Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,941,491.00 0.00 Canceled 2017-05-09 2017-05-19 2017-06-24 2017-07-15 2017-08-28 2019-08-18 Package 1 of 2 (Construction Envelope Management Investments of Weir, Undersluice and Head Regulator) PK-PMU-BIWRMDP-2427- CW-RFB / Yetabad Flood Component B: Water, Irrigation Scheme - Package Open - Single Stage - One IDA / 58850 Infrastructure and Prior Request for Bids 6,123,689.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-02 2018-11-15 2021-11-14 2 of 6 (Conveyance System International Envelope Management Investments Including Cross Drainage (RD 0+00 to RD 10+750) Page 1 PK-PMU-BIWRMDP-2428- CW-RFB / Yetabad Flood Irrigation Scheme - Package Component B: Water, Open - Single Stage - One 3 of 6 (Conveyance System IDA / 58850 Infrastructure and Prior Request for Bids 6,123,689.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-12 2018-11-25 2021-11-24 International Envelope including Cross Drainage Management Investments Structures RD 10+750 to RD 21+500) PK-PMU-BIWRMDP-2423- Component B: Water, CW-RFB / Yetabad Flood Open - Single Stage - One IDA / 58850 Infrastructure and Prior Request for Bids 9,014,788.00 0.00 Canceled 2018-07-12 2018-07-19 2018-09-07 2018-10-02 2018-11-15 2021-11-14 Irrigation Scheme - Package International Envelope Management Investments 1 of 6 (Weir & Buildings) PK-PMU-BIWRMDP-69116- CW-RFB / Yetabad Flood Component B: Water, Open - Single Stage - One Irrigation Scheme - Package IDA / 58850 Infrastructure and Prior Request for Bids 15,151,815.00 0.00 Canceled 2018-08-15 2018-10-31 2018-10-31 2018-08-20 2019-01-09 2019-02-08 2019-03-15 2020-09-05 International Envelope 2 (Conveyance System KM Management Investments 6+000 to KM 21+500) PK-PMU-BIWRMDP-69112- CW-RFB / Yetabad Flood Component B: Water, Irrigation Scheme - Package Open - Single Stage - One IDA / 58850 Infrastructure and Prior Request for Bids 148,484,235.00 0.00 Canceled 2018-08-15 2018-10-31 2018-10-31 2018-08-20 2019-01-09 2019-02-08 2019-03-15 2020-09-05 1 (Weir and Conveyance International Envelope Management Investments System (KM 0+000 to KM 6+000) PK-PMU-BIWRMDP-79952- Component B: Water, CW-RFB / Construction of Open - Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids 7,464,230.00 0.00 Canceled 2018-11-12 2018-11-17 2019-01-04 2019-02-03 2019-03-10 2021-09-07 Mushkaf Flood Irrigation International Envelope Management Investments Scheme PK-PMU-BIWRMDP-92413- CW-RFQ / Procurement of Works for Production of Component B: Water, Request for Single Stage - One Plants Through Raising of IDA / 58850 Infrastructure and Post Open - National 145,279.00 109,366.58 Signed 2019-01-05 2019-02-01 2019-07-31 Quotations Envelope Nurseries Under B2 Sub Management Investments Component of BIWRMDP at Uthal, Dhadar & Harnai PK-PMU-BIWRMDP-93196- CW-RFB / Procurement of Component B: Water, Under Open - Single Stage - One Civil Works for Nari Gorge IDA / 58850 Infrastructure and Post Request for Bids 4,270,000.00 3,589,182.94 Implementati 2019-01-03 2019-01-08 2019-02-27 2019-03-29 2019-04-26 2021-04-15 International Envelope Integrated Scheme (Package- Management Investments on 01) PK-PMU-BIWRMDP-93197- Component B: Water, CW-RFB / Construction of Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,971,014.00 2,709,109.55 Signed 2019-02-12 2019-02-17 2019-03-31 2019-04-30 2019-05-28 2021-05-27 Nimmi Perennial Irrigation Envelope Management Investments Scheme PK-PMU-BIWRMDP-96459- CW-RFB / Construction of Component B: Water, Open - Single Stage - One Gandacha Nurg-Hingri IDA / 58850 Infrastructure and Prior Request for Bids 8,915,217.00 0.00 Canceled 2019-02-15 2019-02-20 2019-04-03 2019-05-03 2019-06-07 2021-06-06 International Envelope Integrated Scheme (Package- Management Investments 1) PK-PMU-BIWRMDP-97035- Component B: Water, CW-RFB / Construction of Open - Single Stage - One IDA / 58850 Infrastructure and Prior Request for Bids 7,464,230.00 5,946,973.37 Signed 2019-02-06 2019-02-11 2019-03-25 2019-04-24 2019-05-29 2021-05-28 Mushkaf Flood Irrigation International Envelope Management Investments Schemes PK-PMU-BIWRMDP-104392- CW-RFB / Construction of Component B: Water, Water Supply Scheme for 4 Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 775,362.00 0.00 Canceled 2019-03-10 2019-03-15 2019-04-14 2019-05-14 2019-06-18 2019-12-15 villages within the ambit of Envelope Management Investments Nari Gorge Integrated Scheme, Sibi Page 2 PK-PMU-BIWRMDP-113051- CW-RFB / Construction of Component B: Water, Under Single Stage - One Gundacha Nurg Hingri IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,477,220.85 3,642,140.15 Implementati 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 2020-03-02 Envelope Integrated Scheme - Package Management Investments on 2 (Works at Nurg Hingri) PK-PMU-BIWRMDP-73478- CW-RFB / Procurement of Works Yetabad Flood Irrigation Scheme - (Weir Component B: Water, Open - Single Stage - One and Conveyance System (KM IDA / 58850 Infrastructure and Prior Request for Bids 34,997,555.01 0.00 Canceled 2018-08-30 2018-11-15 2018-11-15 2018-09-04 2019-01-24 2019-02-23 2019-03-30 2020-09-20 International Envelope 0+000 to KM 6+000) and Management Investments Conveyance System and Buildings (KM 6+000 to KM 21+500) PK-PMU-BIWRMDP-93985- CW-RFB / Water Supply Component B: Water, Scheme for three villages Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 469,989.00 0.00 Canceled 2019-01-15 2019-01-20 2019-02-19 2019-03-21 2019-04-18 2020-04-17 constituting domain of Envelope Management Investments Mushkaf Flood Irrigation Scheme PK-PMU-BIWRMDP-2437- Component B: Water, Single Stage - One CW-RFB / Flood Protection IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,408,021.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-12 2020-02-25 2022-02-14 Envelope Works - Package 1 of 5 Management Investments PK-PMU-BIWRMDP-2435- CW-RFB / Water Supply Component B: Water, Single Stage - One Schemes Package 2 of 4 - 3 IDA / 58850 Infrastructure and Post Request for Bids Open - National 1,842,458.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-16 2020-02-29 2021-08-22 Envelope Water Supply Schemes in Management Investments District Loralai PK-PMU-BIWRMDP-2441- CW-RFB / Small Scale Component B: Water, Irrigation Schemes in Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 268,568.00 0.00 Canceled 2020-03-16 2020-03-23 2020-04-22 2020-05-20 2020-07-03 2021-12-25 District Khuzdar - Khazeni Envelope Management Investments Bent Perennial Irrigation Scheme PK-PMU-BIWRMDP-2439- CW-RFB / Small Scale Component B: Water, Irrigation Schemes in Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 692,764.00 0.00 Canceled 2019-11-30 2019-12-07 2020-01-06 2020-01-27 2020-03-11 2021-09-02 District Khuzdar - Naik Envelope Management Investments Mohammad Bent Perennial Irrigation Scheme PK-PMU-BIWRMDP-2433- CW-RFB / Drilling & Component A: Institutions, Single Stage - One IDA / 58850 Post Request for Bids Open - National 947,550.00 0.00 Canceled 2020-03-16 2020-03-23 2020-04-22 2020-05-13 2020-06-26 2021-06-26 Development of Groundwater Capacity and Information Envelope Monitoring Wells PK-PMU-BIWRMDP-2429- CW-RFB / Nimmi Perennial Component B: Water, Irrigation Scheme - Package Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,249,665.00 0.00 Canceled 2020-02-20 2020-03-01 2020-03-31 2020-04-21 2020-06-04 2022-05-25 1 of 2 (Construction of Weir, Envelope Management Investments Undersluice, & Head Regulator) PK-PMU-BIWRMDP-2438- Component B: Water, Single Stage - One CW-RFB / Flood Protection IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,323,315.00 0.00 Canceled 2019-11-15 2019-11-22 2019-12-22 2020-01-19 2020-03-03 2022-02-21 Envelope Works - Package 2 of 5 Management Investments Page 3 PK-PMU-BIWRMDP-2430- CW-RFB / Nimmi Perennial Irrigation System - Package 2 of 2 (Construction of Component B: Water, Irrigation Canal System, Open - Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids 4,924,502.00 0.00 Canceled 2020-03-16 2020-03-26 2020-05-15 2020-06-14 2020-07-28 2022-07-18 Guide Banks, Fall Structure, International Envelope Management Investments Road Culverts, Outlet Structures, Drainage Box and Pipe Culverts, Regulators and Aquaducts. PK-PMU-BIWRMDP-2434- CW-RFB / Water Supply Component B: Water, Schemes Package 1 of 4 - Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 297,186.00 0.00 Canceled 2020-02-29 2020-03-07 2020-04-06 2020-04-27 2020-06-10 2021-06-10 Construction of 3 Water Envelope Management Investments Supply Schemes in District Lasbela PK-PMU-BIWRMDP-113054- Component B: Water, CW-RFB / Construction of Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 754,691.00 0.00 Canceled 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 2020-03-02 Nari Gorge Water Supply Envelope Management Investments Scheme PK-PMU-BIWRMDP-68771- CW-RFB / Construction of Command Area Infrastructure Viz. WC, Component B: Water, WST, KT,EWST, EWC ( Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 887,000.00 0.00 Canceled 2020-05-03 2020-05-08 2020-06-19 2020-07-19 2020-08-23 2021-02-19 Perennial and Spate)( Envelope Management Investments Package 1 of 3) NARI GORGE PIS COMMAND AREA INFRSTRUCTURE WORKS PK-PMU-BIWRMDP-96461- Component B: Water, CW-RFB / Construction Nari Open - Single Stage - One IDA / 58850 Infrastructure and Prior Request for Bids 5,268,116.00 0.00 Canceled 2019-02-20 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2021-06-11 Gorge Integrated Scheme International Envelope Management Investments (Package-2) PK-PMU-BIWRMDP-143842- Component B: Water, CW-RFB / Construction Nari Open - Single Stage - One IDA / 58850 Infrastructure and Prior Request for Bids 5,270,000.00 0.00 Canceled 2019-11-30 2019-12-05 2020-01-16 2020-02-15 2020-03-21 2020-09-17 Gorge Integrated Scheme International Envelope Management Investments (Package-2) PK-PMU-BIWRMDP-68772- CW-RFB / Construction of Command Aare Component B: Water, Infrastructures ( Khuskaba Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 518,000.00 0.00 Canceled 2020-03-30 2020-04-04 2020-05-16 2020-06-15 2020-07-20 2021-01-16 FArming) Package 1 of 10 Envelope Management Investments NARI GORGE PIS COMMAND AREA INFRSTRUCTURE WORKS PK-PMU-BIWRMDP-144866- CW-RFB / Works for Construction of Sehan Irrigation Scheme - Lot Component B: Water, Pending Single Stage - One No.1 Construction of Weir, IDA / 58850 Infrastructure and Post Request for Bids Open - National 4,567,000.00 0.00 Implementati 2020-05-29 2020-06-03 2020-07-15 2020-08-14 2020-09-18 2021-03-17 Envelope Undersluice, Head Management Investments on Regulator, Guide Bunds, Main Canal and Related Structures - Civil Works PK-PMU-BIWRMDP-144870- CW-RFB / Works for Construction of Sehan Component B: Water, Pending Irrigation Scheme Package Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,338,000.00 0.00 Implementati 2020-06-29 2020-07-04 2020-08-03 2020-09-02 2020-10-07 2022-03-31 3 of 3 - Construction of Envelope Management Investments on Dis tributaries and Related Hydraulic Structures Page 4 PK-PMU-BIWRMDP-144858- GO-RFB / Civil Works for Construction of Measurement Pending Component A: Institutions, Single Stage - One Weir / Flume and Guard IDA / 58850 Post Request for Bids Open - National 451,612.00 0.00 Implementati 2020-02-17 2020-02-22 2020-03-23 2020-04-22 2020-05-27 2021-01-22 Capacity and Information Envelope Houses as part of on Establishing Phase-I of Hydro-met Network. PK-PMU-BIWRMDP-144874- CW-RFB / Works for Construction of Shab-e- Component B: Water, Pending Maidan Irrigation Scheme Open - Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids 4,683,871.00 0.00 Implementati 2020-03-24 2020-03-29 2020-04-02 2020-05-17 2020-06-21 2021-12-13 Package 1 of 2 - International Envelope Management Investments on Construction of Weir and Main Canal and Related Hydraulic Structures PK-PMU-BIWRMDP-144869- CW-RFB / Works for Construction of Sehan Component B: Water, Pending Single Stage - One Irrigation Scheme Package IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,848,000.00 0.00 Implementati 2020-06-01 2020-06-06 2020-07-06 2020-08-05 2020-09-09 2022-03-03 Envelope 2 of 3 - Construction of Management Investments on Main Canal and Related Hydraulic Structures PK-PMU-BIWRMDP-144876- CW-RFB / Works for Construction of Shab-e- Maidan Irrigation Scheme Component B: Water, Pending Open - Single Stage - One Package 2 of 2 - IDA / 58850 Infrastructure and Post Request for Bids 4,335,483.00 0.00 Implementati 2020-05-18 2020-05-23 2020-07-07 2020-08-06 2020-09-10 2022-03-04 International Envelope Construction of Main Management Investments on Canal, Distributories and Related Hydraulic Structures PK-PMU-BIWRMDP-145601- Component B: Water, Pending CW-RFB / Civil Works for Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 298,426.00 0.00 Implementati 2020-01-24 2020-01-29 2020-02-28 2020-03-29 2020-05-03 2021-05-03 Construction of Nari Gorge Envelope Management Investments on Water Supply Scheme PK-PMU-BIWRMDP-143843- CW-RFB / Works for Watershed & Rangeland Management - Construction of Lose and Pack Stone Component B: Water, Pending Percolation Ditches, Contour Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 1,370,000.00 0.00 Implementati 2020-02-20 2020-02-25 2020-04-07 2020-05-07 2020-06-11 2020-12-08 Trenches, Gabion Structures, Envelope Management Investments on Rangeland Improvement/Rehabilitation with Plantation, Sowing of Seeds, Construction of Stock Water Ponds etc. PK-PMU-BIWRMDP-143841- Component B: Water, Pending CW-RFB / Civil Works for Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 267,567.00 0.00 Implementati 2020-01-24 2020-01-29 2020-02-01 2020-03-02 2020-04-06 2021-04-05 Mushkaf Water Supply Envelope Management Investments on Scheme PK-PMU-BIWRMDP-133752- CW-RFQ / Works for Plant Production Through Raising of Nurseries and Other Allied Activities under B2 Sub component Of Component B: Water, Pending Single Stage - One BIWRMDP Second Phase IDA / 58850 Infrastructure and Post Request for Bids Open - National 300,645.00 0.00 Implementati 2019-10-15 2019-10-20 2019-12-01 2019-12-31 2020-02-04 2020-08-02 Envelope For Following LOTs. Management Investments on LOT 4 – DADAR LOT 5 – HARNAI LOT 6 - SIBI Lot 7 -Uthal Lot 8 - Khuzdar Page 5 PK-PMU-BIWRMDP-153953- CW-RFB / Construction of Component B: Water, Pending Single Stage - One Gundacha Nurg Hingri IDA / 58850 Infrastructure and Post Request for Bids Open - National 3,032,258.00 0.00 Implementati 2020-02-03 2020-02-08 2020-03-09 2020-04-08 2020-05-13 2022-05-13 Envelope Integrated Scheme - Package Management Investments on 1 of 2. PK-PMU-BIWRMDP-153957- CW-RFB / Construction of Component B: Water, Pending Single Stage - One Nari Gorge Integrated IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,709,677.00 0.00 Implementati 2020-01-24 2020-01-29 2020-02-28 2020-03-29 2020-05-03 2022-05-03 Envelope Scheme - Package 2 of 3 - Management Investments on Lining of Khajjak Channels. PK-PMU-BIWRMDP-153960- CW-RFB / Construction of Component B: Water, Pending Nari Gorge Integrated Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 2,025,806.00 0.00 Implementati 2020-01-24 2020-01-29 2020-02-28 2020-03-29 2020-05-03 2022-05-03 Scheme - Package 3 of 3 - Envelope Management Investments on Construction of Arand & Bori Channels PK-PMU-BIWRMDP-153985- CW-RFB / Works for Construction of Sehan Irrigation Scheme - Package Component B: Water, Pending Open - Single Stage - One 1 of 3 - Construction of IDA / 58850 Infrastructure and Post Request for Bids 4,625,806.00 0.00 Implementati 2020-04-13 2020-04-18 2020-06-02 2020-07-02 2020-08-06 2022-01-28 International Envelope Weir, Undersluice, Head Management Investments on Regulator, Guide Bunds, Main Canal and Related Structures GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2336- GO-RFQ / Office Equipment Component C: Project for PMU - Desktops, laptops, Request for Single Stage - One IDA / 58850 Management and Technical Prior Open - National 50,000.00 49,337.27 Signed 2016-10-08 2016-11-03 2016-12-03 printers, scanners, cameras, Quotations Envelope Assistance internet devices, multimedia etc. PK-PMU-BIWRMDP-2338- GO-RFQ / Furniture & Component C: Project Request for Single Stage - One Fixture for PMU at Quetta IDA / 58850 Management and Technical Post Open - National 34,299.00 39,744.82 Completed 2016-10-27 2016-11-29 2016-12-27 Quotations Envelope including Reversible Split Assistance AC for PD Office PK-PMU-BIWRMDP-2406- Component C: Project Request for Single Stage - One GO-RFQ / Procurement of IDA / 58850 Management and Technical Post Open - National 15,314.00 19,553.87 Completed 2016-11-14 2016-12-14 2017-01-13 Quotations Envelope Diesel Generator for PMU Assistance PK-PMU-BIWRMDP-2413- Component C: Project Request for Single Stage - One GO-RFQ / Furniture & IDA / 58850 Management and Technical Post Open - National 25,842.00 27,052.71 Completed 2016-11-18 2016-12-24 2017-01-23 Quotations Envelope Fixture for PIUs at Sibi & Assistance Uthal PK-PMU-BIWRMDP-2414- GO-RFQ / Field Equipment - Component C: Project Relaskops, Clinometers, Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 21,535.00 25,063.67 Signed 2016-12-09 2017-01-12 2017-02-11 Range Finders, Level Quotations Envelope Assistance Machines etc. for Watershed & Rangeland Management PK-PMU-BIWRMDP-2415- Component C: Project GO-RFQ / Procurement of Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 12,443.00 13,146.03 Completed 2016-11-10 2016-12-14 2017-01-13 Video Conference Equipment Quotations Envelope Assistance for PMU Page 6 PK-PMU-BIWRMDP-2417- Component C: Project GO-RFQ / Purchase of Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 47,856.00 29,805.88 Signed 2016-11-30 2017-01-21 2017-02-26 Computer Software - GIS & Quotations Envelope Assistance Autocad PK-PMU-BIWRMDP-14395- Component C: Project GO-RFQ / Purchase of Office Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 72,000.00 72,486.33 Signed 2017-05-11 2017-06-02 2017-06-30 Equipment for PMU & PIUs Quotations Envelope Assistance at Sibi & Uthal PK-PMU-BIWRMDP-14456- GO-RFQ / Purchase of Split Component C: Project Air Conditioners, Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 50,500.00 40,052.89 Signed 2017-05-12 2017-06-05 2017-07-05 Refrigerators etc for PMU & Quotations Envelope Assistance PIUs and Diesel Generators for PIUS PK-PMU-BIWRMDP-18626- NC-RFQ / Purchase of Component C: Project Request for Single Stage - One Software - MS Office, Adobe IDA / 58850 Management and Technical Post Open - National 29,400.00 25,688.50 Signed 2017-08-02 2017-09-01 2017-10-16 Quotations Envelope Pro, Microsoft Project, Assistance Autocad Civil 3D etc. PK-PMU-BIWRMDP-18629- Component C: Project Request for Single Stage - One GO-RFQ / Special Desktop IDA / 58850 Management and Technical Post Open - National 9,375.00 7,467.27 Signed 2017-08-05 2017-09-08 2017-10-23 Quotations Envelope Computers for Arc GIS Assistance PK-PMU-BIWRMDP-2409- GO-RFQ / Procurement of Component C: Project Request for Single Stage - One Office Equipment & IDA / 58850 Management and Technical Post Open - National 43,070.00 0.00 Canceled 2016-11-21 2016-12-25 2017-01-24 Quotations Envelope Generators for PIUs at Sibi Assistance & Uthal PK-PMU-BIWRMDP-34361- Component B: Water, GO-RFQ / Procurement of Request for Single Stage - One IDA / 58850 Infrastructure and Post Open - National 20,000.00 7,284.88 Signed 2017-11-20 2018-01-15 2018-07-14 Furniture for Agriculture Quotations Envelope Management Investments Field Office PK-PMU-BIWRMDP-34363- Component B: Water, GO-RFQ / Procurement of IT Request for Single Stage - One IDA / 58850 Infrastructure and Post Open - National 18,000.00 11,234.74 Signed 2017-11-20 2018-01-15 2018-05-15 Equipment for Agriculture Quotations Envelope Management Investments Field Offices PK-PMU-BIWRMDP-34364- Component B: Water, Request for Single Stage - One GO-RFQ / Procurement of IDA / 58850 Infrastructure and Post Open - National 80,000.00 39,815.82 Signed 2017-11-20 2018-01-15 2018-05-15 Quotations Envelope Survey Equipment Management Investments PK-PMU-BIWRMDP-2408- Component C: Project GO-RFQ / Procurement of Request for Single Stage - One IDA / 58850 Management and Technical Prior Open - National 71,784.00 0.00 Canceled 2016-12-07 2017-01-26 2017-04-26 Additional Vehicles for Quotations Envelope Assistance Project - 3 Door Jeeps PK-PMU-BIWRMDP-2418- GO-RFB / Supply/ installation of Hdyro- meteorological observation Component A: Institutions, Open - Single Stage - One stations, rain gauging IDA / 58850 Post Request for Bids 2,692,000.00 0.00 Canceled 2017-11-19 2017-11-29 2018-01-20 2018-02-19 2018-03-22 2019-09-13 Capacity and Information International Envelope stations, stream gauging stations and groundwater observation wells including establishment of Data Centre PK-PMU-BIWRMDP-96456- GO-RFB / Establishment of Pending Hydro-met networks Pilot Component A: Institutions, Single Stage - One IDA / 58850 Post Request for Bids Open - National 770,000.00 0.00 Implementati 2019-02-11 2019-02-16 2019-03-18 2019-04-17 2019-05-22 2020-05-21 Project (Hydro-met Data Capacity and Information Envelope on Collection and Management System) Page 7 PK-PMU-BIWRMDP-135510- GO-RFB / Procurement of Component B: Water, Pending Goods for Establishment of Single Stage - One IDA / 58850 Infrastructure and Post Request for Bids Open - National 500,000.00 0.00 Implementati 2020-02-17 2020-02-22 2020-03-23 2020-04-22 2020-05-27 2021-01-22 Hydro-met Network Phase-I Envelope Management Investments on (AWS, Sensors, Stream flow Gauging Stations etc) PK-PMU-BIWRMDP-153962- GO-RFB / Procurement of Component B: Water, Pending Single Stage - One Goods for Construction of IDA / 58850 Infrastructure and Post Request for Bids Open - National 406,451.00 0.00 Implementati 2020-03-05 2020-03-10 2020-04-09 2020-05-09 2020-06-13 2021-02-08 Envelope Nari Gorge Water Supply Management Investments on Scheme PK-PMU-BIWRMDP-153979- GO-RFB / Procurement of Component B: Water, Pending Single Stage - One Goods for Construction of IDA / 58850 Infrastructure and Post Request for Bids Open - National 198,806.00 0.00 Implementati 2020-03-05 2020-03-10 2020-04-09 2020-05-09 2020-06-13 2021-02-08 Envelope Mushkaf Water Supply Management Investments on Scheme NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2442- NC-RFQ / Project Website Component C: Project Design Development, Domain Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 2,400.00 2,943.83 Signed 2016-10-20 2016-11-26 2017-01-10 Registration, Hosting, Quotations Envelope Assistance Maintenance and Updating fro One Year PK-PMU-BIWRMDP-18623- NC-DIR / Purchase of 0.3m Component C: Project to 0.5m Resolution Satellite IDA / 58850 Management and Technical Post Direct Selection Direct 54,600.00 0.00 Canceled 2017-07-26 2017-07-31 2017-08-25 2017-10-09 Image for Nari Gorge & Assistance Gundacha Area. PK-PMU-BIWRMDP-19640- Component C: Project NC-DIR / Purchase of Arc IDA / 58850 Management and Technical Post Direct Selection Direct 30,563.00 0.00 Canceled 2017-07-19 2017-07-24 2017-08-15 2017-09-29 GIS - Two Basic & One Assistance Standard Version PK-PMU-BIWRMDP-38144- NC-RFQ / Baseline Component C: Project Request for Single Stage - One sampling(Laboratory Testing) IDA / 58850 Management and Technical Post Open - National 6,000.00 28,014.89 Signed 2018-01-05 2018-03-02 2018-05-01 Quotations Envelope of two integrated schemes Assistance for ESMP PK-PMU-BIWRMDP-45893- NC-RFQ / Baseline Sampling(Laboratory Testing) Component B: Water, Request for Single Stage - One (Ambient IDA / 58850 Infrastructure and Post Open - National 35,000.00 57,805.06 Signed 2018-02-01 2018-02-27 2018-03-15 Quotations Envelope Air/Noise/Water/Soil) for Nur- Management Investments Hingri-Gunacha Irrigation Scheme Scheme for ESMP PK-PMU-BIWRMDP-68865- NC-RFQ / Procurement of Demo Plots (PLL, HEIS, Component B: Water, Livestock, Tunnel farming, Request for Single Stage - One IDA / 58850 Infrastructure and Post Open - National 95,500.00 0.00 Canceled 2019-11-20 2020-01-15 2020-07-13 nurseries, crops) First Lot Quotations Envelope Management Investments GUNDACHA & NARI GUARGE PIS COMMAND AREA INFRSTRUCTURE Page 8 PK-PMU-BIWRMDP-144898- NC-RFQ / PROCUREMENT Component C: Project Pending Request for Single Stage - One OF IDA / 58850 Management and Technical Post Open - National 30,000.00 0.00 Implementati 2020-03-03 2020-03-26 2020-09-22 Quotations Envelope FINANCIAL/ACCOUNTING Assistance on & PAYROLL SOFTWARE PK-PMU-BIWRMDP-65562- NC-RFQ / Environmental Component C: Project Pending Baseline studies (Laboratory Request for Single Stage - One IDA / 58850 Management and Technical Post Open - National 100,000.00 0.00 Implementati 2020-02-05 2020-04-01 2020-09-28 Testing) for different Quotations Envelope Assistance on schemes regarding ESMPs & Checklists CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PMU-BIWRMDP-2240- Component C: Project CS-QCBS / Project Quality And Cost- Open - IDA / 58850 Management and Technical Prior 8,824,655.00 9,597,864.82 Signed 2016-10-18 2016-11-13 2016-11-30 2017-01-05 2017-02-04 2017-03-04 2017-04-03 2022-10-31 Supervision & Based Selection International Assistance Implementation Assistance Consultancy PK-PMU-BIWRMDP-2335- Component C: Project Consultant CS-CQS / Hiring IDA / 58850 Management and Technical Post Qualification Open - National 103,369.00 132,054.03 Signed 2016-11-15 2016-12-13 2017-01-06 2017-01-31 2017-02-24 2022-10-31 Accountancy Firm for Assistance Selection Quarterly Internal Audit PK-PMU-BIWRMDP-2245- Component C: Project Quality And Cost- Open - CS-QCBS / Monitoring & IDA / 58850 Management and Technical Prior 1,758,231.00 0.00 Canceled 2016-10-24 2016-11-21 2016-12-15 2017-01-20 2017-02-19 2017-03-19 2017-04-22 2022-10-30 Based Selection International Evaluation Consultancy Assistance PK-PMU-BIWRMDP-2334- CS-INDV / Hiring of Component C: Project Consultant Accountancy Firm for IDA / 58850 Management and Technical Prior Qualification Open - National 4,786.00 4,173.09 Signed 2016-10-27 2016-11-21 2016-12-15 2016-12-25 2017-01-14 2017-02-13 External Audit of Retroactive Assistance Selection Financing PK-PMU-BIWRMDP-50078- CS-CQS / HIRING A CONSULTING FIRM FOR Component C: Project Consultant THE PREPARATION OF IDA / 58850 Management and Technical Post Qualification Open - National 170,000.00 0.00 Canceled 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2019-01-19 CULTURAL HERITAGE Assistance Selection MANAGEMENT PLAN (CHMP) PK-PMU-BIWRMDP-109329- CS-CQS / Hiring of Audit Component C: Project Consultant Firm to Carryout Special IDA / 58850 Management and Technical Post Qualification Open - National 10,000.00 2,437.30 Signed 2019-04-08 2019-04-23 2019-05-10 2019-05-17 2019-05-21 2019-06-04 Audit of Project Supervision Assistance Selection & Implementation Assistance Consultants PK-PMU-BIWRMDP-2250- Component C: Project Quality And Cost- Open - CS-QCBS / Institutional IDA / 58850 Management and Technical Post 765,697.00 0.00 Canceled 2018-10-15 2018-11-14 2018-12-15 2019-01-29 2019-02-23 2019-03-30 2019-04-30 2020-04-29 Based Selection International Reforms Consultants Assistance PK-PMU-BIWRMDP-135514- Component C: Project Least Cost CS-LCS / Hiring Monitoring IDA / 58850 Management and Technical Post Open - National 550,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2020-10-22 Selection & Evaluation Consultancy Assistance INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9 PK-PMU-BIWRMDP-2315- Component C: Project Individual CS-INDV / Social Safeguards IDA / 58850 Management and Technical Post Consultant Open 103,369.00 4,178.54 Terminated 2016-10-28 2016-12-18 2016-12-25 2017-01-06 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-2317- Component C: Project Individual CS-INDV / Communications IDA / 58850 Management and Technical Post Consultant Open 33,021.00 3,132.42 Terminated 2016-10-28 2016-12-24 2016-12-31 2017-01-12 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-2319- Component C: Project Individual CS-INDV / Water Resources IDA / 58850 Management and Technical Post Consultant Open 87,864.00 6,323.39 Terminated 2016-10-28 2017-01-04 2017-01-11 2017-01-23 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-2320- Component C: Project Individual CS-INDV / Agriculture IDA / 58850 Management and Technical Post Consultant Open 87,864.00 3,613.37 Terminated 2016-11-21 2017-01-07 2017-01-14 2017-01-26 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-2321- Component C: Project Individual CS-INDV / Environmental IDA / 58850 Management and Technical Post Consultant Open 86,141.00 3,611.41 Terminated 2016-10-28 2016-12-30 2017-01-06 2017-01-18 2022-10-31 Safeguards Specialist Assistance Selection PK-PMU-BIWRMDP-2325- Component C: Project Individual CS-INDV / Monitoring & IDA / 58850 Management and Technical Post Consultant Open 117,152.00 1,993.36 Terminated 2016-11-21 2017-01-30 2017-02-06 2017-02-18 2022-10-31 Evaluation Specialist Assistance Selection PK-PMU-BIWRMDP-2326- Component C: Project Individual CS-INDV / Matching Grant IDA / 58850 Management and Technical Post Consultant Open 86,141.00 2,184.24 Terminated 2016-11-21 2017-01-25 2017-02-01 2017-02-13 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-2332- Component C: Project Individual CS-INDV / Gender IDA / 58850 Management and Technical Post Consultant Open 51,685.00 2,183.20 Terminated 2016-11-21 2017-01-13 2017-01-20 2017-02-01 2022-10-31 Development Specialist Assistance Selection PK-PMU-BIWRMDP-2333- Component C: Project Individual CS-INDV / Livestock IDA / 58850 Management and Technical Post Consultant Open 68,338.00 0.00 Canceled 2016-11-21 2017-02-09 2017-02-16 2017-02-28 2022-10-31 Specialist Assistance Selection PK-PMU-BIWRMDP-2318- Component C: Project Individual CS-INDV / Procurement IDA / 58850 Management and Technical Prior Consultant Open 117,152.00 0.00 Canceled 2016-10-27 2016-12-11 2016-12-18 2016-12-30 2022-10-30 Specialist Assistance Selection PK-PMU-BIWRMDP-19626- Component C: Project Individual CS-INDV / Hiring of IDA / 58850 Management and Technical Post Consultant Open 275,071.00 3,320.53 Terminated 2017-07-14 2017-08-16 2017-08-30 2017-09-14 2022-11-06 Procurement Specialist Assistance Selection PK-PMU-BIWRMDP-2308- CS-INDV / Financial Component C: Project Individual Management Specialist at IDA / 58850 Management and Technical Prior Consultant Open 116,769.00 0.00 Canceled 2016-10-08 2016-10-29 2016-11-08 2016-11-18 2022-11-01 Project Management Unit Assistance Selection Quetta PK-PMU-BIWRMDP-26486- Component C: Project Individual CS-INDV / Hiring of IDA / 58850 Management and Technical Post Consultant Open 285,714.00 29,917.08 Signed 2017-09-07 2017-10-03 2017-10-10 2017-10-22 2022-10-31 Financial Management Assistance Selection Specialist PK-PMU-BIWRMDP-38131- CS-CDS / Hiring of Component C: Project Individual Individual IDA / 58850 Management and Technical Post Consultant Limited 3,000.00 26,196.92 Signed 2017-11-27 2017-12-02 2017-12-07 2017-12-15 2018-01-15 Consultant(Environmental Assistance Selection Specialist) for short term PK-PMU-BIWRMDP-7458- Individual CS-INDV / Hiring of Component A: Institutions, IDA / 58850 Post Consultant Open 50,000.00 0.00 Canceled 2017-03-01 2017-04-19 2017-05-10 2017-06-14 2017-11-11 Hydrologist for Design of Capacity and Information Selection Hydro-met Network Page 10 PK-PMU-BIWRMDP-2323- Component C: Project Individual CS-INDV / Training IDA / 58850 Management and Technical Post Consultant Open 72,358.00 0.00 Canceled 2016-11-21 2017-01-19 2017-01-26 2017-02-07 2022-10-31 Management Specialist Assistance Selection PK-PMU-BIWRMDP-60509- Component C: Project Individual CS-INDV / Hiring of IDA / 58850 Management and Technical Post Consultant Open 80,000.00 0.00 Canceled 2018-04-24 2018-06-12 2018-07-03 2018-08-07 2019-02-03 Environmental Safeguard Assistance Selection Specialist PK-PMU-BIWRMDP-61675- CS-INDV / Hiring of Individual Individual Consultant for Component A: Institutions, IDA / 58850 Prior Consultant Direct 9,000.00 0.00 Canceled 2018-05-04 2018-05-06 2018-05-07 2018-05-08 2018-05-22 National Consultative Capacity and Information Selection Workshop foe Establishment of BWRMA PK-PMU-BIWRMDP-61884- CS-INDV / Hiring of Individual Consultant to Facilitate in Holding of Individual Component A: Institutions, National Consultative IDA / 58850 Post Consultant Direct 9,000.00 7,341.82 Completed 2018-05-08 2018-05-08 2018-05-09 2018-05-09 2018-05-19 Capacity and Information Workshop for Establishment Selection of Balochistan Water Resource Management Authority. PK-PMU-BIWRMDP-92788- CS-FBS / Hiring of Component C: Project Individual Individual Consultant - IDA / 58850 Management and Technical Post Consultant Open 15,652.00 1,271.64 Signed 2019-02-05 2019-03-08 2019-03-13 2019-03-27 2020-03-26 Financial Management Assistance Selection Specialist PK-PMU-BIWRMDP-97771- CS-INDV / Hiring of Component C: Project Individual Procurement Specialist to IDA / 58850 Management and Technical Post Consultant Open 15,652.00 1,165.67 Signed 2019-02-05 2019-03-08 2019-03-15 2019-03-30 2020-03-29 work as Individual Assistance Selection Consultant PK-PMU-BIWRMDP-104301- CS-INDV / Selection of Component C: Project Individual Social Safeguards IDA / 58850 Management and Technical Post Consultant Open 13,043.00 1,130.34 Signed 2019-03-10 2019-04-28 2019-05-19 2019-06-23 2019-12-20 Specialist/Individual Assistance Selection Consultant PK-PMU-BIWRMDP-104309- CS-INDV / Selection of Component C: Project Individual Environmental Safeguards IDA / 58850 Management and Technical Post Consultant Open 13,043.00 1,657.00 Signed 2019-03-10 2019-04-28 2019-05-19 2019-06-23 2019-12-20 Specialist/Individual Assistance Selection Consultant Page 11