PROCUREMENT PLAN (Textual Part) Project information: Kosovo Real Estate & Geospatial Infrastructure Project P164555: [country] [Project name] [P-number] Project Implementation agency: Kosovo Cadaster Agency [insert legal name] Date of the Procurement Plan: March 15, 2019 [insert date] Period covered by this Procurement Plan: March 2019-Aug 20123 [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: N/A Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods: N/A as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): N/A. Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable: N/A. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete]. Other Relevant Procurement Information: N/A. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Kosovo : Real Estate & Geospatial Infrastructure Project PLAN General Information Country: Kosovo Bank’s Approval Date of the Original Procurement Plan: 2019-03-20 2021-10-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164555 GPN Date: 2019-08-01 Project Name: Real Estate & Geospatial Infrastructure Project Loan / Credit No: IDA / 63540 K Executing Agency(ies): osovo Cadastre Agency WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual XK-KCA-101526-CW-RFQ / Pending Renovation work for 4 MCOs Request for Single Stage - One 2021-10- IDA / 63540 B: Cadastre Modernization Post Limited 0.00 Implementat 2021-03-15 2021-05-10 (North Mitrovica, Zubin Potok, Quotations Envelope 10 ion Leposaviq, Zvecan) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual XK-KCA-101486-GO-RFB / Single Stage - One Development of software for IDA / 63540 B: Cadastre Modernization Post Request for Bids Open - National 0.00 Canceled 2019-12-02 2019-12-05 2020-01-16 2020-01-20 2020-02-01 2020-07-30 Envelope DQI XK-KCA-101585-GO-RFB / KCLIS-SOA modification to cover the registration of utility cadastre (including C: ICT and Geospatial Single Stage - One interoperability with KCLIS IDA / 63540 Post Request for Bids Open - National 0.00 Canceled 2020-02-10 2020-02-15 2020-03-28 2020-04-21 2020-05-20 2021-08-30 Infrastructure Envelope and NSDI Geoportal), Phase I (development of system prototype) and II (system development) XK-KCA-102911-GO-RFB / Replacement & upgrade of C: ICT and Geospatial Single Stage - One GNSS equipment, including IDA / 63540 Post Request for Bids Open - National 0.00 Canceled 2019-07-17 2020-10-09 2019-07-22 2019-09-02 2019-09-23 2019-10-04 2022-06-30 Infrastructure Envelope software, licenses and equipment XK-KCA-101577-GO-DIR / Cadastre Reconstruction C: ICT and Geospatial IDA / 63540 Post Direct Selection Direct 76,327.60 Completed 2019-02-22 2019-08-09 2019-02-27 2019-08-14 2019-03-22 2019-08-26 2019-08-30 2019-10-25 module - Upgrade of KCLIS Infrastructure SOA to integrate CR Tool XK-KCA-205205-GO-RFQ / Replacement & upgrade of Under C: ICT and Geospatial Request for Single Stage - One GNSS equipment, including IDA / 63540 Post Limited 0.00 Implementati 2020-11-23 2020-12-21 2021-03-30 Infrastructure Quotations Envelope software, licenses and on equipment XK-KCA-101528-GO-RFQ / Pending Request for Single Stage - One IT equipment (PCs, scanner, IDA / 63540 B: Cadastre Modernization Post Limited 0.00 Implementati 2021-07-30 2021-10-01 2021-11-25 Quotations Envelope printer) on XK-KCA-101259-GO-RFQ / Pending Unmanned aerial vehicle Request for Single Stage - One IDA / 63540 B: Cadastre Modernization Post Limited 0.00 Implementati 2022-02-09 2022-04-05 2022-07-10 (including software and Quotations Envelope on training) XK-KCA-101579-GO-RFB / Pending Supply of hardware C: ICT and Geospatial Single Stage - One IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2022-10-15 2022-11-01 2022-12-20 2023-01-22 2023-02-15 2023-06-01 (equipment for data centres Infrastructure Envelope on etc.) and standard licenses XK-KCA-102908-GO-RFB / Pending C: ICT and Geospatial Single Stage - One NSDI Geoportal upgrade and IDA / 63540 Post Request for Bids Open - International 0.00 Implementati 2021-02-07 2021-02-12 2021-03-17 2021-04-01 2021-04-16 2023-08-01 Infrastructure Envelope further development on XK-KCA-101588-GO-RFB / Pending Development of modules for C: ICT and Geospatial Single Stage - One IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2021-05-10 2021-05-15 2021-06-26 2021-07-18 2021-08-10 2022-04-15 surveyors to download data, Infrastructure Envelope on including digital format XK-KCA-101572-GO-RFB / KCLIS-SOA further development and interoperability with other registers and systems, e- Pending C: ICT and Geospatial Single Stage - One services development, IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2021-11-25 2021-11-30 2022-01-11 2022-02-02 2022-03-02 2023-06-20 Infrastructure Envelope software for DQI, registration on of utility cadastre (including interoperability with KCLIS and NSDI Geoportal), upgrading of business processes XK-KCA-217418-GO-RFB / Developing an Pending C: ICT and Geospatial Single Stage - One address/navigation IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2021-06-05 2021-06-10 2021-07-22 2021-08-05 2021-08-18 2021-12-30 Infrastructure Envelope application for mobiles (ARIS on mobiles) for Kosovo Pending XK-KCA-217420-GO-RFQ / C: ICT and Geospatial Request for Single Stage - One IDA / 63540 Post Limited 0.00 Implementati 2021-02-10 2021-04-14 2023-04-14 New Webpage of KCA Infrastructure Quotations Envelope on Pending XK-KCA-217421-GO-RFB / C: ICT and Geospatial Single Stage - One IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2022-10-20 2022-10-25 2022-12-06 2022-12-15 2023-01-15 2023-05-15 Upgrade of KOPOS System Infrastructure Envelope on Page 1 XK-KCA-236215-GO-RFB / Production and installation of Pending tables with address road C: ICT and Geospatial Single Stage - One IDA / 63540 Prior Request for Bids Open - International 0.00 Implementati 2021-06-02 2021-06-07 2021-07-19 2021-08-18 2021-09-22 2022-03-21 names and building address Infrastructure Envelope on signs for remaining Municipalities in Kosovo NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual XK-KCA-101595-NC-RFB / Scanning and metadata entering operators and for updating the indexes of the C: ICT and Geospatial Single Stage - One IDA / 63540 Post Request for Bids Open - National 0.00 Canceled 2019-08-14 2019-08-19 2019-09-30 2019-10-30 2019-11-30 2023-03-10 existing digital archive as per Infrastructure Envelope the standard including modifications of existing software XK-KCA-101258-NC-RFB / Pending Services for cadastre Single Stage - One IDA / 63540 B: Cadastre Modernization Prior Request for Bids Open - International 0.00 Implementati 2021-02-04 2021-02-08 2021-03-12 2021-03-25 2021-04-15 2023-06-20 reconstruction (multiple) in Envelope on 140 cadastral zones Pending XK-KCA-101487-NC-RFB / Single Stage - One IDA / 63540 B: Cadastre Modernization Post Request for Bids Open - National 0.00 Implementati 2021-02-04 2021-02-08 2021-03-14 2021-03-19 2021-04-05 2022-03-16 Data correction Envelope on XK-KCA-102910-NC-RFB / Pending Technical services for data C: ICT and Geospatial Single Stage - One IDA / 63540 Post Request for Bids Open - International 0.00 Implementati 2022-01-08 2022-01-11 2022-02-14 2022-03-04 2022-03-25 2023-06-15 digitization / harmonization Infrastructure Envelope on including licenses Pending XK-KCA-102909-NC-RFB / C: ICT and Geospatial Single Stage - One IDA / 63540 Post Request for Bids Open - International 0.00 Implementati 2022-11-01 2022-11-06 2022-12-18 2023-02-22 2023-03-15 2023-08-30 Orthophoto Infrastructure Envelope on XK-KCA-101594-NC-RFB / Pending C: ICT and Geospatial Single Stage - One Scanning of old archive of IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2021-02-06 2021-02-11 2021-03-18 2021-03-26 2021-04-10 2022-03-30 Infrastructure Envelope priority offices on Pending XK-KCA-217416-NC-RFB / C: ICT and Geospatial Single Stage - One IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2021-02-15 2021-02-20 2021-03-19 2021-04-04 2021-04-29 2021-12-30 Updating new roads segments Infrastructure Envelope on XK-KCA-217417-NC-RFB / Pending Linking addresses to the C: ICT and Geospatial Single Stage - One IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2021-10-05 2021-10-10 2021-11-21 2021-12-21 2022-01-25 2022-11-25 citizens through Civil Status Infrastructure Envelope on Registry XK-KCA-101522-CS-RFQ / Pending Complete BR in previous Request for Single Stage - One IDA / 63540 B: Cadastre Modernization Post Limited 0.00 Implementati 2021-04-04 2021-05-25 2021-12-10 RECAP BCC work (3 MCOs in Quotations Envelope on north) XK-KCA-217415-NC-RFB / Finalization of Address Pending C: ICT and Geospatial Single Stage - One System for 4 MCO’s in Kosovo IDA / 63540 Post Request for Bids Open - National 0.00 Implementati 2021-05-28 2021-06-02 2021-07-12 2021-07-26 2021-08-14 2022-11-27 Infrastructure Envelope (North Mitrovica, Zubin Potok, on Leposavic, Zvecan) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual XK-KCA-101253-CS-CQS / Consultant Development of an updated A: Policy, Legal and Under IDA / 63540 Post Qualification Open - International 0.00 2019-03-01 2019-05-21 2019-03-15 2019-03-28 2019-04-04 2019-04-23 2019-12-02 KCA strategy and business Institutional Support Implementation Selection plan XK-KCA-101256-CS-CQS / Improving CR process, Consultant updating administrative IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 74,549.83 Completed 2019-03-06 2019-05-24 2019-03-22 2019-04-09 2019-08-22 2019-04-16 2019-09-04 2019-04-30 2019-10-03 2019-09-30 2020-07-15 instructions and manual, and Selection Update of Building Register (BR) standards XK-KCA-101263-CS-CQS / Consultant Training for KCA and MCO IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 Canceled 2020-04-02 2020-04-16 2020-05-06 2020-05-18 2020-06-15 2022-06-15 staff Selection XK-KCA-101482-CS-CQS / Consultant Development of standard for IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 Canceled 2020-02-12 2020-02-28 2020-03-17 2020-03-26 2020-04-15 2021-06-30 digital cadastre elaborate Selection XK-KCA-101489-CS-CQS / TA support for updating Consultant existing or creating new IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 Canceled 2019-05-28 2019-06-13 2019-07-09 2019-07-15 2019-07-30 2019-12-20 manuals and Admin Selection instructions for QC XK-KCA-101500-CS-CQS / Consultant Creating an inventory of IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 Canceled 2019-05-14 2019-05-29 2019-06-19 2019-06-24 2019-07-08 2019-11-30 existing utility data held by Selection the municipalities XK-KCA-101522-CS-CQS / Consultant Complete BR in previous IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 Canceled 2020-01-08 2020-01-24 2020-02-19 2020-02-21 2020-03-05 2021-03-05 RECAP BCC work (3 MCOs in Selection north) Page 2 XK-KCA-101569-CS-CQS / Consultant Analyses of the KCLIS-SOA C: ICT and Geospatial IDA / 63540 Post Qualification Open - National 0.00 Canceled 2020-02-04 2020-02-25 2020-03-16 2020-03-25 2020-04-15 2021-10-30 data model review for Infrastructure Selection compliance with the LADM XK-KCA-101593-CS-CQS / Archive and Document Consultant C: ICT and Geospatial Management Strategy, an IDA / 63540 Post Qualification Open - National 0.00 Canceled 2020-05-13 2020-06-03 2020-07-10 2020-07-22 2020-08-17 2021-08-16 Infrastructure action plan and a scanning Selection and indexing standard XK-KCA-102905-CS-CQS / Consultant C: ICT and Geospatial Socio-Economic Benefits IDA / 63540 Post Qualification Open - National 0.00 Canceled 2021-01-05 2021-01-26 2021-02-19 2021-03-15 2021-04-01 2023-03-30 Infrastructure Analysis Selection D. Project Management, Consultant XK-KCA-103710-CS-CQS / Under IDA / 63540 Capacity Building, Public Post Qualification Open - National 0.00 2019-03-05 2021-04-23 2019-03-19 2021-09-15 2019-04-05 2019-04-10 2019-04-25 2019-08-30 Monitoring and Evaluation Implementation Outreach, M&E Selection XK-KCA-102904-CS-CQS / Consultant C: ICT and Geospatial QA/QC, IT Contracts, and IDA / 63540 Post Qualification Open - National 0.00 Canceled 2019-08-22 2019-09-12 2019-10-26 2019-11-25 2019-12-25 2023-02-15 Infrastructure Project Management Selection XK-KCA-101254-CS-CQS / Consultant Support to preparation and A: Policy, Legal and Pending IDA / 63540 Post Qualification Open - National 0.00 2021-02-04 2021-02-22 2021-02-26 2021-03-01 2021-03-15 2021-07-30 implementation of new draft Institutional Support Implementation Selection Cadastre law XK-KCA-101255-CS-CQS / Consultant Land Market Studies, Socio A: Policy, Legal and Pending IDA / 63540 Post Qualification Open - National 0.00 2022-11-20 2022-12-03 2022-12-25 2023-01-03 2023-02-05 2023-07-20 Economic Benefits and Institutional Support Implementation Selection Analyses XK-KCA-101492-CS-QCBS / Quality And Cost- Pending Quality control of CR IDA / 63540 B: Cadastre Modernization Prior Open - National 0.00 2021-02-04 2021-02-18 2021-02-28 2021-03-28 2021-04-05 2021-04-13 2021-05-03 2023-06-20 Based Selection Implementation contractors XK-KCA-101262-CS-CQS / Consultant Pending Implementation of public IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 2021-05-03 2021-05-24 2021-06-08 2021-06-12 2021-08-01 2023-06-20 Implementation awareness strategy plan Selection XK-KCA-101496-CS-CQS / Support to create policy guidelines, legal analysis, Consultant strategy and implementation Pending IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 2022-01-25 2022-02-11 2022-02-28 2022-03-04 2022-03-24 2023-06-05 plan, business processes, Implementation Selection metadata, technical specifications (in line with INSPIRE) XK-KCA-101523-CS-CQS / Consultant Architectural design and Pending IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 2021-02-10 2021-02-26 2021-03-11 2021-03-17 2021-04-05 2021-10-10 supervision of construction Implementation Selection works XK-KCA-101261-CS-CQS / Consultant Public Awareness and Under IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 2021-02-10 2021-05-12 2021-02-24 2021-09-02 2021-03-15 2021-03-30 2021-04-12 2021-06-10 communications strategy and Implementation Selection plan to maximize turnout XK-KCA-101260-CS-CQS / Consultant Pending Training for KCA and MCO IDA / 63540 B: Cadastre Modernization Post Qualification Open - National 0.00 2021-02-10 2021-02-20 2021-03-05 2021-03-09 2021-03-30 2022-06-20 Implementation staff Selection XK-KCA-102902-CS-QCBS / ICT Strategy Implementation C: ICT and Geospatial Quality And Cost- Pending (Sustainable Governance IDA / 63540 Post Open - International 0.00 2023-01-25 2023-02-10 2023-02-17 2023-03-15 2023-03-23 2023-03-31 2023-04-20 2023-07-15 Infrastructure Based Selection Implementation Structure and Maximizing Investment Efficiency) XK-KCA-101591-CS-CQS / Consultant Awareness campaign and C: ICT and Geospatial Pending IDA / 63540 Post Qualification Open - National 0.00 2023-01-20 2023-02-10 2023-03-14 2023-04-02 2023-04-25 2023-07-05 training of external users for e- Infrastructure Implementation Selection services XK-KCA-103712-CS-CQS / D. Project Management, Consultant Under First Customer satisfaction IDA / 63540 Capacity Building, Public Post Qualification Open - National 0.00 2021-05-31 2021-06-09 2021-06-14 2021-09-02 2021-07-11 2021-07-20 2021-08-06 2022-02-15 Implementation survey Outreach, M&E Selection XK-KCA-236216-CS-CQS / D. Project Management, Consultant Pending Second Customer satisfaction IDA / 63540 Capacity Building, Public Post Qualification Open - National 0.00 2022-04-05 2022-04-26 2022-06-09 2022-07-09 2022-08-13 2022-12-30 Implementation survey Outreach, M&E Selection XK-KCA-236217-CS-CQS / D. Project Management, Consultant Pending Third Customer satisfaction IDA / 63540 Capacity Building, Public Post Qualification Open - National 0.00 2023-01-10 2023-01-27 2023-02-22 2023-03-02 2023-04-06 2023-08-31 Implementation survey Outreach, M&E Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual XK-KCA-101264-CS-INDV / Individual Analysis of activities to IDA / 63540 B: Cadastre Modernization Post Consultant Open 0.00 Canceled 2019-06-04 2019-07-07 2019-07-17 2019-07-30 2019-12-25 improve DQI Selection XK-KCA-101515-CS-INDV / Individual Enhance and test the IDA / 63540 B: Cadastre Modernization Post Consultant Open 0.00 Canceled 2020-02-04 2020-03-19 2020-03-30 2020-04-30 2021-08-30 maintenance procedures for Selection the building register REGIP-CD001-CS-INDV / D. Project Management, Head of Project IDA / 63540 Capacity Building, Public Post Direct Selection Direct 90,531.79 Signed 2019-01-24 2019-01-25 2019-01-26 2019-01-25 2019-02-01 2019-02-04 2023-08-31 Implementation Unit (PIU) Outreach, M&E Page 3 D. Project Management, REGIP-CD002-CS-INDV / IDA / 63540 Capacity Building, Public Post Direct Selection Direct 82,768.96 Terminated 2019-01-24 2019-01-25 2019-01-26 2019-01-26 2019-03-01 2019-02-04 2023-08-31 Procurement Specialist Outreach, M&E REGIP-CD003-CS-INDV / D. Project Management, Individual Financial Management IDA / 63540 Capacity Building, Public Post Consultant Open 13,236.00 Signed 2019-01-24 2019-01-25 2019-03-18 2019-02-25 2019-03-19 2019-08-09 2019-04-01 2019-09-02 2023-08-31 Specialist Outreach, M&E Selection D. Project Management, REGIP-CD004-CS-INDV / IDA / 63540 Capacity Building, Public Post Direct Selection Direct 64,847.48 Signed 2019-01-24 2019-01-25 2019-01-25 2019-01-26 2019-02-01 2019-02-04 2023-08-31 Cadastre and GIS Specialist Outreach, M&E REGIP-CD005-CS-INDV / D. Project Management, Communications / Public IDA / 63540 Capacity Building, Public Post Direct Selection Direct 64,847.48 Signed 2019-03-01 2019-01-25 2019-03-07 2019-01-26 2019-03-12 2019-02-04 2023-08-31 Relation Specialist Outreach, M&E XK-KCA-102904--CS-DC-1 C: ICT and Geospatial / First Short Term Cadastre IDA / 63540 Post Direct Selection Direct 2,720.16 Signed 2020-02-24 2020-02-26 2020-02-26 2020-02-28 2020-03-02 2020-03-02 2020-08-31 Infrastructure Expert XK-KCA-102904--CS-DC-2 C: ICT and Geospatial / Second Short Term Cadastre IDA / 63540 Post Direct Selection Direct 2,720.16 Signed 2020-02-24 2020-02-26 2020-02-26 2020-02-28 2020-03-02 2020-03-02 2020-08-31 Infrastructure Expert XK-KCA-102904--CS-DC-3 C: ICT and Geospatial / Third Short Term Cadastre IDA / 63540 Post Direct Selection Direct 2,720.16 Signed 2020-02-24 2020-02-26 2020-02-26 2020-02-28 2020-03-02 2020-03-02 2020-08-31 Infrastructure Expert D. Project Management, Individual REGIP-KCA-006-CS-INDV / Under IDA / 63540 Capacity Building, Public Post Consultant Open 0.00 2020-10-20 2020-10-29 2020-11-13 2020-11-17 2020-12-02 2023-08-31 IT Specialist Implementation Outreach, M&E Selection D. Project Management, Individual REGIP-KCA-007-CS-INDV / Under IDA / 63540 Capacity Building, Public Post Consultant Open 0.00 2020-10-20 2020-10-21 2020-11-13 2020-11-17 2020-12-02 2023-08-31 Legal Specialist Implementation Outreach, M&E Selection REGIP-KCA-008-CS-INDV / D. Project Management, Individual Under National Spatial Data IDA / 63540 Capacity Building, Public Post Consultant Open 0.00 2020-10-20 2020-10-29 2020-11-13 2020-11-16 2020-12-02 2023-08-31 Implementation Infrastructure (NSDI) Specialist Outreach, M&E Selection REGIP-KCA-009-CS-INDV / D. Project Management, Individual Under Monitoring and Evaluation IDA / 63540 Capacity Building, Public Post Consultant Open 0.00 2020-10-20 2020-10-21 2020-11-12 2020-11-16 2020-12-02 2023-08-31 Implementation Specialist Outreach, M&E Selection D. Project Management, Individual REGIP-KCA-010-CS-INDV / Under IDA / 63540 Capacity Building, Public Post Consultant Open 0.00 2020-10-20 2020-10-21 2020-11-12 2020-11-16 2020-12-02 2023-08-31 Cadastre Specialist Implementation Outreach, M&E Selection XK-KCA-101479-CS-INDV / Individual Analysis of activities to Pending IDA / 63540 B: Cadastre Modernization Post Consultant Open 0.00 2021-03-25 2021-04-24 2021-05-03 2021-05-20 2021-11-10 improve DQI and Strategy and Implementation Selection implementation for DQI XK-KCA-101257-CS-INDV / Local professional staff for Individual supporting sub-commissions Pending IDA / 63540 B: Cadastre Modernization Post Consultant Open 0.00 2021-02-10 2021-03-10 2021-03-15 2021-04-02 2023-07-20 of CR (cadsatre and legal Implementation Selection experts) (4 positions for 2 years) XK-KCA-101506-CS-INDV / Individual Pending Creating technical/ admin IDA / 63540 B: Cadastre Modernization Post Consultant Open 0.00 2022-01-30 2022-03-07 2022-03-12 2022-04-05 2022-09-09 Implementation guidelines Selection XK-KCA-101512-CS-INDV / Refine procedures etc based Individual Pending upon pilot and then populate IDA / 63540 B: Cadastre Modernization Prior Consultant Open 0.00 2022-07-15 2022-08-20 2022-09-06 2022-10-01 2023-07-30 Implementation the utility cadastre with data Selection from 3 cities XK-KCA-101517-CS-INDV / Individual Pending Convert, upload and update in IDA / 63540 B: Cadastre Modernization Post Consultant Open 0.00 2021-02-10 2021-03-07 2021-03-12 2021-04-01 2021-12-01 Implementation KCLIS-CM under BCC projects Selection XK-KCA-101510-CS-INDV / Individual Processing utility data from Pending IDA / 63540 B: Cadastre Modernization Post Consultant Open 0.00 2023-01-10 2023-02-15 2023-02-21 2023-03-12 2023-07-12 Pristina municipality into the Implementation Selection utility cadastre as a pilot Individual XK-KCA-102903-CS-INDV / C: ICT and Geospatial Pending IDA / 63540 Post Consultant Open 0.00 2021-03-25 2021-04-20 2021-04-27 2021-05-30 2023-06-30 ICT Technical Training Infrastructure Implementation Selection Individual XK-KCA-101596-CS-INDV / C: ICT and Geospatial Pending IDA / 63540 Post Consultant Open 0.00 2022-03-08 2022-04-12 2022-04-23 2022-05-10 2022-11-15 ITC strategy update Infrastructure Implementation Selection XK-KCA-102906-CS-INDV / Kosovo NSDI Strategy and Individual C: ICT and Geospatial Pending Action Plan (including IDA / 63540 Post Consultant Open 0.00 2023-01-25 2023-02-25 2023-03-05 2023-03-30 2023-07-15 Infrastructure Implementation Engagement Strategy and Selection Action Plan) XK-KCA-102907-CS-INDV / Individual Support NSDI Strategy C: ICT and Geospatial Pending IDA / 63540 Prior Consultant Open 0.00 2023-01-22 2023-02-19 2023-03-02 2023-03-25 2023-07-15 implementation and KCA data Infrastructure Implementation Selection harmonization with INSPIRE XK-KCA-217419-CS-INDV / Local professional staff for Individual C: ICT and Geospatial Pending Finalization of Address IDA / 63540 Post Consultant Open 0.00 2021-04-10 2021-05-07 2021-05-24 2021-06-15 2023-06-15 Infrastructure Implementation Register (4 positions for 2 Selection years) Page 4 XK-KCA-101500-CS-INDV / Creating an inventory of existing utility data held by Individual Pending the municipalities/Local IDA / 63540 B: Cadastre Modernization Post Consultant Open 0.00 2021-03-20 2021-04-25 2021-05-04 2021-06-01 2023-06-01 Implementation professional staff for Utility Selection Cadastre (2 positions for 2 years) D. Project Management, Individual REGIP-KCA-011-CS-INDV / Under IDA / 63540 Capacity Building, Public Post Consultant Open 0.00 2021-07-12 2021-08-18 2021-08-09 2021-08-13 2021-09-06 2023-08-31 Procurement Specialist Implementation Outreach, M&E Selection D. Project Management, Individual XK-KCA-259631-CS-INDV / Pending IDA / 63540 Capacity Building, Public Post Consultant Open 0.00 2021-10-26 2021-12-02 2021-12-06 2022-01-02 2023-08-31 Translator/Interpreter Implementation Outreach, M&E Selection D. Project Management, REGIP-CD012-CS-INDV / Pending IDA / 63540 Capacity Building, Public Post Direct Selection Direct 0.00 2021-07-12 2021-07-19 2021-08-02 2022-07-31 Procurement Consultant Implementation Outreach, M&E Page 5