Sample Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan Original: March, 2016 : Revision: March, 2017 3. Date of General Procurement Notice: February 23, 2016 4. Period covered by this procurement plan: The procurement period of project covered from year May 1, 2016 to April 30, 2021 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Procurement method Prior Review Threshold Threshold US$ US$ 1 NCB (Goods) ; IT and Non-consulting Equivalent and Below US$ Above USD 2 mil. services 1,000,000 2 NCB (Works) Equivalent and Below US$ Above USD 10 mil. 10 million 3 Shopping (Goods) Equivalent and Below US$ None 100,000 4 Shopping (Works) Equivalent and Below US$ None 200,000 2. Prequalification. Bidders for Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual, including the Matching Grants manual, for implementation of the Bank’s funded Loan Project P152441 is developed by GITA on June , 2016. 5. Any Other Special Procurement Arrangements: The project include the provision of matching grants to the Georgian firms and individuals to Broadband for Development program (increasing of the innovation activity). 6. Summary of the Procurement Packages planned during the entire project implementation period (as of March, 2017) 1 2 3 4 5 6 7 Ref. Description Estim Packag Domest Review Comments No. ated es ic Cost Prefere by US$ nce Bank millio (yes/no) (Prior / n Post) Summary of the ICB (Goods) 2.3 6 No Post Summary of the NCB (Works) 0.27 5 No Post Summary of the NCB (Goods) 0.62 4 No Post Summary of the Shopping 0.5 21 No Post (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods Above US$ (Firms) 1,000,000 2. CQS Applicable for assignments with estimation below USD 300K 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packag Review Comments Assignment Cost es by Bank US$ (Prior / million Post) Summary of number of contracts 10.1 5 Prior that will be let under QCBS Summary of number of contracts 1.25 17 Post LCS, FB, CQS that will be let under other methods Summary of number of contracts 5.3 98 Prior/Post The contracts with the staff that will be let under IC positions were signed on the bases of the Prior review Summary of number of contracts 0.005 1 Post that will be let under SSS PROCUREMENT Georgia : Georgia National Innovation Ecosystem (GENIE) Project PLAN General Information Country: Georgia Bank’s Approval Date of the Original Procurement Plan: 2016-08-11 2019-05-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152441 GPN Date: Project Name: Georgia National Innovation Ecosystem (GENIE) Project Loan / Credit No: IBRD / 85950 Executing Agency(ies): Georgias Innovation & Technology Agency WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GE-GITA-2016-CW-RFB / Pending Single Stage - One Renovation Works for 40 IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2018-06-01 2018-06-06 2018-07-06 2018-08-05 2018-09-04 2018-11-03 Envelope CICs on GE-GITA-19083-CW-RFQ / Pending Request for Single Stage - One Renovation Works for IC- IBRD / 85950 Post Open - National 0.00 Implementati 2017-11-04 2017-12-30 2018-01-29 Quotations Envelope Location Two on GE-GITA-2015-CW-RFQ / Under Request for Single Stage - One Renovation Works for IBRD / 85950 Post Open - National 0.00 Implementati 2018-02-20 2018-04-03 2018-07-02 Quotations Envelope Akhmeta CIC on GE-GITA-24405-CW-RFQ / Under Request for Single Stage - One Renovation Works for Telavi IBRD / 85950 Post Open - National 0.00 Implementati 2018-02-20 2018-04-17 2018-07-16 Quotations Envelope RIH on GE-GITA-52392-CW-RFQ / Pending Request for Single Stage - One Minor Renovation Works for IBRD / 85950 Post Open - National 0.00 Implementati 2018-03-17 2018-04-12 2018-05-12 Quotations Envelope Rukhi IC on GE-GITA-2036-CW-RFQ / Request for Single Stage - One Renovation Works for 5 pilot IBRD / 85950 Post Open - National 0.00 Canceled 2019-04-06 2019-05-04 2019-08-02 Quotations Envelope RIH GE-GITA-2037-CW-RFQ / Request for Single Stage - One Renovation Works for 2 pilot IBRD / 85950 Post Open - National 0.00 Canceled 2018-02-05 2018-03-05 2018-06-03 Quotations Envelope RIH GE-GITA-2014-CW-RFQ / Request for Single Stage - One Renovation Works for 6 IBRD / 85950 Post Open - National 0.00 Canceled 2018-01-27 2018-02-24 2018-03-26 Quotations Envelope CICs GE-GITA-2013-CW-RFQ / Request for Single Stage - One Renovation Works for IC- IBRD / 85950 Post Open - National 0.00 Canceled 2017-11-04 2017-12-09 2018-02-07 Quotations Envelope Location One GE-GITA-19084-CW-RFQ / Request for Single Stage - One Renovation Works for IC- IBRD / 85950 Post Open - National 0.00 Canceled 2017-11-04 2017-12-30 2018-02-13 Quotations Envelope Location three GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 GE-GITA-2002-GO-RFQ / Request for Single Stage - One Computers and associated IT IBRD / 85950 Post Open - National 0.00 Canceled 2017-01-20 2017-02-17 2017-03-04 Quotations Envelope equipment for 5 CICs GE-GITA-2042-GO-RFB / Pending Single Stage - One Specialized Lab equipment IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2017-12-01 2017-12-06 2018-01-05 2018-02-04 2018-03-06 2018-06-04 Envelope for RIHs on Pending GE-GITA-2011-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Implementati 2017-09-06 2017-10-11 2017-12-10 Media equipment for 5 CICs Quotations Envelope on Pending GE-GITA-2031-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Implementati 2019-07-06 2019-08-03 2019-09-02 Software for 5 RIH Quotations Envelope on Pending GE-GITA-2033-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Implementati 2019-05-06 2019-06-03 2019-08-02 Furniture for 5 RIH Quotations Envelope on GE-GITA-2005-GO-RFB / Pending Single Stage - One Computers and associated IT IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2018-06-01 2018-06-06 2018-07-06 2018-08-05 2018-09-04 2018-11-03 Envelope equipment for 40 CICs on GE-GITA-2030-GO-RFB / Pending Single Stage - One Computers and associated IT IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2019-02-01 2019-02-06 2019-03-08 2019-04-07 2019-05-07 2019-08-05 Envelope equipment for 5 RIH on GE-GITA-2041-GO-RFB / Pending Single Stage - One Fabrication materials for 5 IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2019-04-01 2019-04-06 2019-05-06 2019-06-05 2019-07-05 2019-09-03 Envelope remaining RIH on GE-GITA-2025-GO-RFQ / Pending Request for Single Stage - One Basic equipment for maker- IBRD / 85950 Post Open - National 0.00 Implementati 2017-09-06 2017-10-04 2017-12-03 Quotations Envelope space for 8 CICs on GE-GITA-2003-GO-RFQ / Request for Single Stage - One Computers and associated IT IBRD / 85950 Post Open - National 6,285.93 Signed 2017-05-27 2017-07-08 2017-07-23 Quotations Envelope equipment for 2 CICs GE-GITA-5753-GO-RFB / Single Stage - One Fablab equipment for 3 pilot IBRD / 85950 Post Request for Bids Open - National 0.00 Canceled 2017-11-01 2017-11-06 2017-12-06 2018-01-05 2018-02-04 2018-04-05 Envelope RIH - phase II GE-GITA-2039-GO-RFB / Pending Single Stage - One FabLab equipment for 5 IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2018-05-01 2018-05-06 2018-06-17 2018-07-17 2018-07-24 2019-07-24 Envelope RIH on GE-GITA-14002-GO-RFQ / Pending Request for Single Stage - One Mini FabLab equipment for IBRD / 85950 Post Open - National 0.00 Implementati 2017-07-05 2017-08-30 2018-02-26 Quotations Envelope Mestia IC on GE-GITA-2024-GO-RFQ / Pending Request for Single Stage - One Basic equipment for maker- IBRD / 85950 Post Open - National 0.00 Implementati 2017-01-20 2017-02-17 2017-03-19 Quotations Envelope space for 2 CICs on GE-GITA-2007-GO-RFQ / Pending Request for Single Stage - One Furniture for 5 CICs - IBRD / 85950 Post Open - National 0.00 Implementati 2018-03-20 2018-04-17 2018-06-01 Quotations Envelope Phase II on Pending GE-GITA-2032-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Implementati 2018-09-08 2018-10-06 2018-11-20 Furniture for 2 pilot RIH Quotations Envelope on Page 2 Pending GE-GITA-24408-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Implementati 2017-10-07 2017-12-02 2018-01-16 Furniture for 1 RIH Quotations Envelope on GE-GITA-24411-GO-RFB / Pending Single Stage - One Computers and associated IT IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2017-09-20 2017-09-25 2017-11-06 2017-12-06 2018-01-10 2018-07-09 Envelope equipment for 1 pilot RIH on GE-GITA-2143-GO-RFQ / Pending Request for Single Stage - One Fabrication materials for 2 IBRD / 85950 Post Open - National 0.00 Implementati 2018-03-25 2018-04-22 2018-06-21 Quotations Envelope pilot RIH on GE-GITA-2040-GO-RFQ / Pending Request for Single Stage - One Fabrication materials for 1 IBRD / 85950 Post Open - National 0.00 Implementati 2018-01-27 2018-02-24 2018-04-25 Quotations Envelope pilot RIH on GE-GITA-2038-GO-RFB / Pending Single Stage - One FabLab equipment for 2 IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2018-01-22 2018-01-27 2018-03-10 2018-04-09 2018-04-16 2018-06-15 Envelope pilot RIH on GE-GITA-12163-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2017-08-06 2017-09-03 2017-10-03 Media equipment for 3 CICs Quotations Envelope GE-GITA-24590-GO-RFB / Pending Single Stage - One FabLab equipment for 1 IBRD / 85950 Post Request for Bids Open - National 0.00 Implementati 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 Envelope pilot RIH on GE-GITA-2006-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 8,631.58 Signed 2018-03-12 2018-04-16 2018-06-15 Furniture for 1 IC (Rukhi) Quotations Envelope GE-GITA-2010-GO-RFQ / Request for Single Stage - One Media equipment for 1 IC IBRD / 85950 Post Open - National 0.00 Canceled 2018-03-19 2018-04-16 2018-06-15 Quotations Envelope (Rukhi) GE-GITA-52510-GO-RFQ / Preparation and Insalation Under of Desing Elemnets Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Implementati 2018-03-19 2018-04-16 2018-07-25 (decorative maps, sign Quotations Envelope on boards, signs and outdoor signs stand boxes with logo) GE-GITA-61402-GO-RFQ / Pending Provision catering services Request for Single Stage - One IBRD / 85950 Post Limited 0.00 Implementati 2018-05-05 2018-05-15 2018-06-14 for the events planned under Quotations Envelope on Matching Grant Program GE-GITA-2026-GO-RFQ / Basic equipment for maker- Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2018-05-24 2018-06-11 2018-08-10 space, for Telavi RIH, Quotations Envelope Akhmeta IC and Rukhi IC. GE-GITA-2012-GO-RFQ / Media Equipment for Telavi Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2018-06-09 2018-07-07 2018-09-05 RIH, Akhmeta IC and Rukhi Quotations Envelope IC GE-GITA-68546-GO-RFQ / Request for Single Stage - One Supply of Telavi RIH and IBRD / 85950 Post Open - National 16,761.16 Signed 2018-07-13 2018-08-08 2018-09-22 Quotations Envelope Akhmeta CIC with furniture GE-GITA-2012-GO-RFQ-1 / Media Equipment for Telavi Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2018-07-25 2018-08-22 2018-10-21 (RIH), Akhmeta (CIC) and Quotations Envelope Rukhi (CIC) Page 3 GE-GITA-2026-GO-RFQ-1 / Basic equipment for maker- Request for Single Stage - One space, for Telavi RIH, IBRD / 85950 Post Open - National 36,162.35 Signed 2018-07-25 2018-08-18 2018-10-17 Quotations Envelope Akhmeta CIC and Rukhi CIC. GE-GITA-71541-GO-RFQ / Supply of Telavi RIH Request for Single Stage - One Akhmeta CIC and Rukhi IBRD / 85950 Post Open - National 0.00 Canceled 2018-08-05 2018-08-29 2018-10-28 Quotations Envelope CIC with Uninterruptible Power Supply (UPS) GE-GITA-71542-GO-RFQ / Supply of Telavi RIH Request for Single Stage - One Akhmeta CIC and Rukhi IBRD / 85950 Post Open - National 5,339.73 Signed 2018-08-05 2018-08-29 2018-10-28 Quotations Envelope CIC with fabrication lab tools GE-GITA-71543-GO-DIR / Supply of Telavi RIH with IBRD / 85950 Post Direct Selection Direct 6,472.76 Signed 2018-07-27 2018-08-01 2018-08-08 2018-10-07 Sewing Embroidery Machine GE-GITA-71545-GO-RFQ / Supply of Telavi RIH Akhmeta CIC and Rukhi Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2018-08-05 2018-08-29 2018-10-28 CIC with CNC machine, 3D Quotations Envelope printers, 3D scanners, UV printers and heat presses GE-GITA-71546-GO-DIR / Supply of Telavi RIH with IBRD / 85950 Post Direct Selection Direct 7,018.88 Signed 2018-08-07 2018-08-12 2018-08-19 2018-10-18 laser engraving machine GE-GITA-71545-GO-RFQ-1 / Supply of Telavi RIH Akhmeta CIC and Rukhi Request for Single Stage - One IBRD / 85950 Post Open - National 92,407.41 Signed 2018-09-05 2018-10-03 2018-12-02 CIC with CNC machine, 3D Quotations Envelope printers, 3D scanners, UV printers and heat presses GE-GITA-71541-GO-RFQ-1 / Supply of Telavi RIH Request for Single Stage - One Akhmeta CIC and Rukhi IBRD / 85950 Post Open - National 6,560.42 Signed 2018-09-05 2018-10-03 2018-12-02 Quotations Envelope CIC with Uninterruptible Power Supply (UPS) GE-GITA-81728-GO-RFQ / Supply of Telavi RIH, Request for Single Stage - One Akhmeta CIC and Rukhi IBRD / 85950 Post Open - National 45,389.51 Signed 2018-10-19 2018-11-09 2018-12-24 Quotations Envelope CIC with computer equipment GE-GITA-94023-GO-RFQ / Pending Audio equipment for Telavi Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Implementati 2019-01-19 2019-02-15 2019-04-01 RIH, Akhmeta CIC and Quotations Envelope on Rukhi CIC. GE-GITA-71544-GO-RFQ / Supply of Telavi RIH and Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2018-08-04 2018-08-28 2018-10-27 Akhmeta CIC with Personal Quotations Envelope Computers for fabrication lab GE-GITA-2012-GO-RFQ-2 / Supply of Telavi RIH, Request for Single Stage - One IBRD / 85950 Post Open - National 7,126.91 Signed 2019-01-21 2019-02-12 2019-04-13 Akhmeta CIC and Rukhi Quotations Envelope CIC with Media Equipment. Page 4 GE-GITA-106800-GO-RFQ / Pending Installation of window blinds Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Implementati 2019-03-30 2019-04-27 2019-06-11 at Telavi RIH and Akhmeta Quotations Envelope on CIC. GE-GITA-2009-GO-RFB / Single Stage - One IBRD / 85950 Post Request for Bids Open - National 0.00 Canceled 2018-07-01 2018-07-06 2018-08-05 2018-09-04 2018-10-04 2018-11-18 Furniture for 40 CICs Envelope GE-GITA-2023-GO-RFB / Single Stage - One Equipment replacement for IBRD / 85950 Post Request for Bids Open - National 0.00 Canceled 2019-03-28 2019-04-02 2019-05-14 2019-06-13 2019-06-20 2019-07-20 Envelope RIHs GE-GITA-2022-GO-RFQ / Equipment Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2020-02-28 2020-03-27 2020-04-26 replacement/upgrades for Quotations Envelope CICs GE-GITA-18050-GO-RFQ / Request for Single Stage - One High end computers for IBRD / 85950 Post Open - National 0.00 Canceled 2017-10-22 2017-11-20 2018-01-19 Quotations Envelope Mestia mini fab-lab GE-GITA-12175-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2018-02-04 2018-03-18 2018-05-02 Furniture for 3 CICs Quotations Envelope GE-GITA-2004-GO-RFQ / Request for Single Stage - One Computers and associated IT IBRD / 85950 Post Open - National 0.00 Canceled 2018-04-04 2018-05-16 2018-07-15 Quotations Envelope equipment for 1 IC (Rukhi) GE-GITA-24418-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2017-10-21 2017-12-16 2018-02-14 Software for 1 pilot RIH Quotations Envelope GE-GITA-2648-GO-RFB / Computers and associated IT Single Stage - One IBRD / 85950 Post Request for Bids Open - National 0.00 Canceled 2018-01-22 2018-01-27 2018-02-26 2018-03-28 2018-04-27 2018-06-26 equipment for 5 CICs and 2 Envelope pilot RIH GE-GITA-2029-GO-RFQ / Request for Single Stage - One IBRD / 85950 Post Open - National 0.00 Canceled 2018-01-20 2018-02-17 2018-03-19 Software for 2 pilot RIH Quotations Envelope NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GE-GITA-94766-NC-RFQ / Provision of broadcasting, Request for Single Stage - One video and photo shooting IBRD / 85950 Post Open - National 28,430.63 Signed 2019-01-21 2019-02-10 2019-03-27 Quotations Envelope services for Matching Grants Program's. GE-GITA-94767-NC-RFQ / Provision catering services Request for Single Stage - One IBRD / 85950 Post Open - National 14,981.50 Signed 2019-01-19 2019-02-08 2019-03-25 for events, planned under Quotations Envelope Matching Grant Program. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 GENIE/CS/CQS-01 / Consultant Preparation of design Under IBRD / 85950 Post Qualification Open - National 33,907.39 2016-11-10 2016-12-01 2017-01-14 2017-02-13 2017-02-20 2017-07-20 documentation for 10 CICs + Implementation Selection 3 RIHs GENIE/CS/CQS-05 / Consultant Assessment of Structural IBRD / 85950 Post Qualification Open - National 0.00 Canceled 2016-10-20 2016-11-10 2016-12-24 2017-01-23 2017-01-30 2017-07-29 Safety for 10 CICs + 3 Selection RIHs GE-GITA-2784-CS-CQS / Consultant Assesment of Structural Under IBRD / 85950 Prior Qualification Open - National 20,859.93 2016-10-30 2016-11-20 2017-01-03 2017-02-02 2017-02-09 2017-08-08 Safety for 10 CICs + 3 Implementation Selection RIHs GENIE/CS/LCS-02 / Project Least Cost Open - IBRD / 85950 Post 9,510.80 Signed 2017-10-25 2017-11-15 2017-12-29 2018-01-26 2018-02-25 2018-04-01 2018-04-15 2018-05-15 audit (2016 and 2017 years) Selection International GENIE/CS/CQS-09 / Consultant Assessment of regulatory Pending IBRD / 85950 Post Qualification Open - National 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-04 2018-01-25 2018-03-26 framework and policy Implementation Selection recommendations GENIE/CS/QCBS-03 / PR Quality And Cost- Pending IBRD / 85950 Prior Open - National 0.00 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-13 2019-03-01 and Media Management Based Selection Implementation GENIE/CS/CQS-02 / Consultant Preparation of design Pending IBRD / 85950 Post Qualification Open - National 0.00 2017-12-01 2017-12-22 2018-02-04 2018-03-06 2018-03-13 2019-03-13 documentation for 40 CICs + Implementation Selection 5 RIHs GENIE/CS/CQS-04 / Consultant Pending RIH/CIC Management IBRD / 85950 Post Qualification Open - National 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-04 2018-01-11 2021-01-10 Implementation Company 2 Selection GENIE/CS/LCS-01 / Least Cost Open - Pending Financial Auditor for MG IBRD / 85950 Post 0.00 2017-10-15 2017-11-05 2017-12-19 2018-01-16 2018-02-15 2018-03-22 2018-04-12 2021-04-11 Selection International Implementation recipients GENIE/CS/CQS-08 / Consultant Development of matching IBRD / 85950 Post Qualification Open - National 57,124.07 Signed 2017-04-15 2017-05-06 2017-06-19 2017-07-19 2017-08-09 2019-01-31 grants web portal IT system Selection GE-GITA-18188-CS-CQS / Consultant Pending Development of the GITA IBRD / 85950 Post Qualification Open - National 0.00 2017-06-20 2017-07-04 2017-08-17 2017-08-24 2017-08-26 2018-02-22 Implementation website Selection GE-GITA-18545-CS-CQS / Consultant Pending Consultancy for the IBRD / 85950 Post Qualification Open - National 0.00 2017-09-01 2017-09-15 2017-10-29 2017-11-03 2017-11-06 2018-05-05 Implementation Specialized lab Selection GE-GITA-2643-CS-CQS / Consultant Open - Pending Impact evaluation for IBRD / 85950 Post Qualification 0.00 2019-12-05 2019-12-26 2020-02-08 2020-03-09 2020-03-30 2020-07-08 International Implementation eCommerce Selection GENIE/CS/CQS-11 / Consultant Development of RIH/CIC Pending IBRD / 85950 Post Qualification Open - National 0.00 2017-10-20 2017-11-10 2017-12-24 2018-01-23 2018-02-13 2020-02-13 beneficiary management Implementation Selection system GENIE/CS/QCBS-01 / Quality And Cost- Open - Pending IBRD / 85950 Prior 0.00 2017-12-01 2017-12-22 2018-02-04 2018-03-04 2018-04-03 2018-05-08 2018-05-29 2018-12-15 eCommerce training Based Selection International Implementation Consultant GE-GITA-18172-CS-CQS / Open - Pending IBRD / 85950 Post Qualification 0.00 2017-10-16 2017-10-30 2017-12-13 2017-12-20 2017-12-28 2018-12-28 IT skills training International Implementation Selection Page 6 Consultant GE-GITA-18557-CS-CQS / Open - IBRD / 85950 Post Qualification 0.00 Canceled 2017-09-01 2017-09-15 2017-10-29 2017-10-30 2017-11-08 2018-05-07 Fablab Hardware Hackathon International Selection Consultant GE-GITA-18548-CS-CQS / Pending IBRD / 85950 Post Qualification Open - National 0.00 2017-09-04 2017-09-18 2017-11-01 2017-11-02 2017-11-10 2018-03-10 TechPark Incubator Demoday Implementation Selection Consultant GE-GITA-18549-CS-CQS / Open - IBRD / 85950 Post Qualification 0.00 Canceled 2017-10-30 2017-11-13 2017-12-27 2017-12-28 2018-01-05 2018-04-05 Bootcamp for programmers International Selection GE-GITA-18550-CS-CQS / Consultant Open - Consultancy to organize IBRD / 85950 Post Qualification 0.00 Canceled 2017-09-01 2017-09-15 2017-10-29 2017-10-30 2017-11-08 2018-06-06 International Mentors Network Selection GE-GITA-18551-CS-CQS / Consultant Open - Travel Technology Startups IBRD / 85950 Post Qualification 0.00 Canceled 2017-09-04 2017-09-18 2017-11-01 2017-11-02 2017-11-10 2018-04-09 International Accelerator Selection GE-GITA-24624-CS-CQS / Consultant Pending Outsourcing of the online IBRD / 85950 Post Qualification Open - National 0.00 2017-08-31 2017-09-21 2017-11-04 2017-12-04 2018-01-08 2022-02-06 Implementation training service platform Selection GE-GITA-5815-CS-CQS / Consultant Development and Under IBRD / 85950 Post Qualification Open - National 0.00 2018-02-05 2018-02-23 2018-03-23 2018-03-30 2018-04-01 2019-09-28 Maintenance of Online BfD Implementation Selection portal GE-GITA-18056-CS-CQS / Consultant Pending BfD Training Provider for IBRD / 85950 Post Qualification Open - National 0.00 2018-04-02 2018-04-16 2018-05-14 2018-05-21 2018-05-28 2019-01-03 Implementation Households Selection GE-GITA-61400-CS-CQS / Provision of broadcasting, video and photo shooting Consultant Under services for Matching Grants IBRD / 85950 Post Qualification Open - National 0.00 2018-05-02 2018-05-09 2018-05-18 2018-05-19 2018-05-20 2018-06-19 Implementation Program's pitching sessions Selection to be held on 24th and 25th of May, 2018. GE-GITA-64173-CS-CQS / Consultancy Services for Consultant Open - Provision of Business IBRD / 85950 Post Qualification 311,053.24 Signed 2018-05-30 2018-06-13 2018-07-04 2018-08-03 2018-08-17 2018-12-15 International Mentoring to Matching Selection Grants Beneficiaries. GE-GITA-5815-CS-CQS - Consultant Under 1 / Development and IBRD / 85950 Post Qualification Open - National 0.00 2018-06-11 2018-06-18 2018-07-05 2018-07-07 2018-07-09 2019-12-01 Implementation Maintenance of Online BfD Selection Portal GE-GITA-18058-CS-CQS / Consultant Georgian MSMEs' E- IBRD / 85950 Post Qualification Open - National 133,277.16 Signed 2018-06-19 2018-06-22 2018-07-20 2018-07-27 2018-07-29 2019-07-29 commerce Capacity Building Selection GE-GITA-69750-CS-FBS / Planning and Implementation of Fixed Budget IBRD / 85950 Post Open - National 0.00 Canceled 2018-07-18 2018-08-08 2018-08-22 2018-09-19 2018-09-26 2018-10-08 2018-10-15 2019-10-15 Communication Campaign for Selection Broadband-for-Development Program GE-GITA-70055-CS-CQS / Consultant Under Assessment of Structural IBRD / 85950 Post Qualification Open - National 0.00 2018-07-23 2018-08-13 2018-09-03 2018-09-10 2018-09-24 2019-03-23 Implementation Safety for 2 CICs. Selection Page 7 GE-GITA-68550-CS-CQS / Provision of consultancy Consultant services for quality Open - IBRD / 85950 Post Qualification 268,574.69 Signed 2018-07-23 2018-08-13 2018-09-10 2018-09-24 2018-10-08 2019-04-06 evaluation and coaching International Selection services for startups under matching grants program. GE-GITA-71847-CS-CQS / Consultant Consultancy services for Open - IBRD / 85950 Post Qualification 128,782.25 Signed 2018-07-31 2018-08-21 2018-09-18 2018-10-02 2018-10-07 2019-12-31 development of pre- International Selection accelerator program GE-GITA-77617-CS-CQS / Consultant Digital Marketing Campaign IBRD / 85950 Post Qualification Open - National 7,532.96 Signed 2018-09-17 2018-10-01 2018-10-20 2018-10-25 2018-10-30 2018-12-29 for Startup Matching Grants Selection Program GE-GITA-83806-CS-QCBS / Consultancy services for Quality And Cost- Open - Under evaluation of project IBRD / 85950 Post 0.00 2018-10-29 2018-11-12 2018-11-18 2018-12-16 2018-12-26 2019-01-01 2019-01-07 2021-01-06 Based Selection International Implementation proposals under Matching Grants program. GE-GITA-85469-CS-CQS / Planning and Consultant Implementation of IBRD / 85950 Post Qualification Open - National 44,632.89 Signed 2018-11-09 2018-11-16 2018-12-05 2018-12-10 2018-12-13 2019-12-13 Communication Campaign for Selection Broadband-for-Development Program GE-GITA-98826-CS-CQS / Consultant Provision of business Open - Under IBRD / 85950 Post Qualification 0.00 2019-02-07 2019-02-21 2019-03-03 2019-03-17 2019-03-22 2020-03-21 mentoring services to startup International Implementation Selection matching grants beneficiaries GE-GITA-101061-CS-LCS / GENIE project financial Least Cost Open - IBRD / 85950 Post 41,300.00 Signed 2019-02-18 2019-03-04 2019-03-11 2019-04-08 2019-04-13 2019-04-21 2019-04-26 2020-06-30 audit for fiscal years 2018 Selection International and 2019 GE-GITA-106657-CS-QCBS / Provision of specialized training in information Quality And Cost- Open - communication technology IBRD / 85950 Prior 0.00 Under Review 2019-03-22 2019-04-12 2019-04-24 2019-05-22 2019-05-29 2019-06-08 2019-06-15 2021-03-31 Based Selection International (ICT), non-ICT and specialized courses for IT specialists. GE-GITA-107040-CS-CQS / Digital Marketing Campaign Consultant Under for Startup and Innovation IBRD / 85950 Post Qualification Open - National 0.00 2019-03-27 2019-04-10 2019-04-29 2019-05-04 2019-05-09 2019-10-26 Implementation Matching Grants Programs Selection for year 2019 GE-GITA-106875-CS-CQS / Facilitation of Science, Consultant Under Technology, Engineering, Art IBRD / 85950 Post Qualification Open - National 0.00 2019-04-15 2019-05-06 2019-05-27 2019-06-06 2019-06-11 2021-03-31 Implementation & Design and Mathematics Selection (STEAM) bootcamps. GENIE/CS/CQS-07 / Start- Consultant up / Entrepreneurship IBRD / 85950 Post Qualification Open - National 0.00 Canceled 2018-03-17 2018-04-07 2018-05-21 2018-05-28 2018-06-04 2018-12-21 bootcamps Selection Consultant GENIE/CS/CQS-13 / CIC Open - IBRD / 85950 Post Qualification 0.00 Canceled 2018-03-01 2018-03-22 2018-05-05 2018-06-04 2018-06-25 2018-08-14 evaluation expert International Selection Page 8 Consultant GENIE/CS/CQS-12 / RIH Open - IBRD / 85950 Post Qualification 0.00 Canceled 2018-03-01 2018-03-22 2018-05-05 2018-06-04 2018-06-25 2018-08-24 evaluation expert International Selection GENIE/CS/CQS-10 / Consultant International market Open - IBRD / 85950 Post Qualification 0.00 Canceled 2017-10-01 2017-10-22 2017-12-05 2018-01-04 2018-01-25 2018-04-25 assessment for Georgia's ICT International Selection and Innovation GENIE/CS/QCBS-04 / Quality And Cost- Open - Innovation acceleration IBRD / 85950 Prior 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-05 2019-01-04 2019-02-08 2019-03-01 2019-09-17 Based Selection International training GE-GITA-18553-CS-CQS / Consultant University Pre-accelerator Open - IBRD / 85950 Post Qualification 0.00 Canceled 2017-09-04 2017-09-18 2017-11-01 2017-11-02 2017-11-10 2018-05-09 Managers' Trainings - ToT, International Selection mentorship, ToT GE-GITA-18546-CS-CQS / Consultant Hackathons in current IBRD / 85950 Post Qualification Open - National 0.00 Canceled 2017-10-02 2017-10-16 2017-11-29 2017-12-06 2017-12-14 2018-05-13 RIH/CIC locations Selection GENIE/CS/CQS-03 / Consultant RIH/CIC Management IBRD / 85950 Post Qualification Open - National 0.00 Canceled 2017-09-15 2017-10-06 2017-11-19 2017-12-19 2017-12-26 2020-12-25 Company 1 Selection GE-GITA-18547-CS-CQS / Consultant Competitions/Olympiads in IBRD / 85950 Post Qualification Open - National 0.00 Canceled 2017-10-02 2017-10-16 2017-11-29 2017-11-30 2017-12-08 2018-05-07 microelectronics and robotics Selection GE-GITA-52385-CS-CQS / Consultant PR Campaign for BfD and IBRD / 85950 Post Qualification Open - National 0.00 Canceled 2018-04-10 2018-05-01 2018-05-29 2018-06-12 2018-07-03 2019-07-03 Grants Selection GENIE/CS/QCBS-06 / IT Quality And Cost- Open - skills training pilot/IT skills IBRD / 85950 Prior 0.00 Canceled 2019-09-02 2019-09-23 2019-11-06 2019-12-04 2020-01-03 2020-02-07 2020-02-28 2021-02-22 Based Selection International training (second location) Consultant GE-GITA-18558-CS-CQS / Open - IBRD / 85950 Post Qualification 0.00 Canceled 2017-09-01 2017-09-15 2017-10-29 2017-10-30 2017-11-07 2018-03-07 Fab Camp/Fablab Workshop International Selection GENIE/CS/QCBS-05 / IT Quality And Cost- Open - skills training pilot/IT skills IBRD / 85950 Prior 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-05 2019-01-04 2019-02-08 2019-03-01 2019-09-17 Based Selection International training (first location) GE-GITA-114123-CS-CQS / Developing Communications Consultant Campaign Concept and IBRD / 85950 Post Qualification Open - National 0.00 Under Review 2019-05-13 2019-06-03 2019-06-24 2019-07-01 2019-07-06 2019-09-04 Implementation Strategy for Selection programs to be implemented under GENIE project. GE-GITA-113102-CS-CQS / Peer Review Evaluation Consultant Open - Pending consulting service for startup IBRD / 85950 Post Qualification 0.00 2019-05-21 2019-06-04 2019-06-28 2019-07-08 2019-07-15 2020-04-10 International Implementation matching grants applications. Selection For 2 calls in 2019. INDIVIDUAL CONSULTANTS Page 9