PRIVATE SECTOR COMPETITIVENESS AND ECONOMIC DIVERSIFICATION PROJECT – ADDITIONAL FINANCING I. General 1. Bank’s approvalDate of the procurement Plan[15 November 2017] 2. Date of General Procurement Notice: 18 October 2017 3. Period covered by this procurement plan: The procurement period of project covered from year July 2017 to January 2022 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project – PSCEDP Phase II 3. Any Other Special Procurement Arrangements: No packages will be financed under retroactive financing 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preferenc by Bank US$M e (Prior / (yes/no) Post) Summary of the NIL NIL No NIL ICB (Works) Summary of the NIL NIL No NIL ICB (Goods) Summary of the 2.05 3 No NIL NCB (Works) Summary of the NIL NIL No NIL NCB (Goods) Summary of the NIL NIL No NIL ICB (Non- Consultant Services) Summary of the 0.25 4 No NIL SHOPPING (Goods) Summary of the NIL NIL No NIL DC (Goods) 1 2 3 4 5 6 7 Ref Contract Estimated Packages Domestic Review Comments . (Description) Cost Preferenc by Bank No. US$ M e (Prior / (yes/no) Post) GOODS Procure hardware equipment 0.075 Post for OBFC& Collateral Registry Public Access Sites Nil Procure furniture for OBFC & 0.05 Nil Post Collateral Registry Public Access Sites Procure furniture and 0.05 Nil Post equipment for PMU Farm Implements (chemicals & 8 Post fertilizers) 0.075 TOTAL 0.25 1 2 3 4 5 6 7 Review Comments Estimate Domestic by Bank Ref. Contract d Packages Preferenc (Prior / No. (Description) Cost e Post) US$ M (yes/no) WORKS Construction of Tourism 1.5 Prior Information Centre NCB No Upgrade Irrigation System at 0.25 Post Mahobong NCB No Development of the pilot Post nursery 0.3 NCB No TOTAL 2.05 1 2 3 4 5 6 7 Ref. Contract Estimate Packages Domestic Review Comments No. (Description) d Preferenc by Bank Cost e (Prior / US$ M (yes/no) Post) NON-CONSULTING SERVICES Systems support and Nil maintenance for MCC Construction Permit 0.03 No Prior Nil Implementation of OBFC communication strategy 0.1 No Post Mobile application system for Nil Collateral Registry and leasing 0.1 No Post Nil Communication strategy for leasing and secured transactions 0.12 No Post Design and Production of Nil Investment Promotion Material for Horticulture 0.05 No Post Investment Promotion Nil Roadshow for Horticulture 0.05 No Post TOTAL 0.45 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Review Expected Comments Estimate by Proposal d Bank Submissio Ref Cost US (Prior / n No. Description of Assignment $ Post) Date Engage a consulting firm for transformation of OBFC into a semi-autonomous legal entity; Implement the Business Registration and Licensing Law (including the design & implementation of e-licensing portal); Design and implement an inspection framework including 0.88 development of risk assessment tools, training modules, inspection manuals and checklists; and streamline OBFC business processes to align them with World Bank DB requirements for improvement of the country’s DB performance on starting a business; integration of OBFC Business Registration with LRA TIN system - Prior June 2018 Engage a consulting firm for review of credit related laws to provide for collection of consumer data including information on businesses; provide Technical Assistance to CBL and Credit Providers Association for development of systems and processes; and facilitate improvement of Prior April the country’s performance on getting credit DB indicator 0.475 2018 TA for Central Bank of Lesotho (CBL) for Financial Leasing including development and implementation of November Investment Promotion Program 0.25 Prior 2017 Engage a Technical Advisor for Secured Transactions to improve access to finance and improve the country’s performance on getting a credit DB indicator 0.1 Post May 2018 Engage a consulting firm to review existing procedures for customs and other border Agencies, and develop and implement a trade automation system for all, and upgrade ASYCUDAWorld 1.3 Prior July 2018 Implementation support to the new entity(ies) post re- organisation of LNDC including implementation of February Management Information System or LNDC 0.8 Prior 2018 Horticulture Technical Advisor November 0.5 Prior 2017 Consultants to staff PMU (including LEAP) 2.31 Prior Only contracts and / or >US$0.4m to be Post July 2017 prior review TA for development and implementation of Insolvency Law to facilitate modernization of the Insolvency Regime 0.1 February and improvement on DB insolvency indicator Post 2018 TA for OPC institutional assessment in the areas of 0.15 technology, skills, human resources and sectoral strategic April plan Post 2018 Develop and implement a comprehensive Private Sector Strategy which includes inter alia a Coherent Incentive Regime and Trade Strategy February 0.15 Post 2018 TA for the development and implementation of linkages February program 0.125 Post 2018 Investment Promotion activities Develop and implement Business Plan for Crafts 0.25 Post July 2017 October Management of Pilot Nursery 0.2 Post 2018 Engage consultant to develop and facilitate implementation of quality and standards capacity building 0.1 September program Post 2018 0.05 April Set-up governance structures for sustainability of orchards Post 2018 Engage a Business Development Consultant for basic November business training of the farmers 0.05 Post 2017 0.1 March Develop an exit strategy for the orchards Post 2018 Develop and implement a business plan for the research February centre 0.25 Post 2018 Develop and implement a marketing and distribution strategy 0.15 Post May 2018 February Conduct a feasibility study for a packhouse 0.1 Post 2019 Alignment of country irrigation plans with horticulture March suitability maps 0.1 Post 2018 TA for development of Horticulture Investment Attraction February Strategy and Action Plan 0.1 Post 2018 Casual Labourers 0.45 On-going February Implementation of Horticulture Business Plan 0.1 Post 2018 April Engage Part-time Communications Specialist 0.03 Post 2018 TOTAL 6.92 PROCUREMENT Lesotho : Second Private Sector Competitiveness and Economic Diversification Prj PLAN General Information Country: Lesotho Banks Approval Date of the Original Procurement Plan: 2017-12-01 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-05-04 Project ID: P144933 GPN Date: 2017-10-25 Project Name: Second Private Sector Competitiveness and Economic Diversification Prj Loan / Credit No: IDA / 59610, IDA / 53090 Executing Agency(ies): Ministry of Trade and Industry WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-34651-CW-RFB / Supporting Economic Single Stage - One Pending Construction of Tourism IDA / 59610 Post Request for Bids Open - National 1,500,000.00 0.00 2018-09-06 2018-09-11 2018-10-23 2018-11-22 2018-12-27 2019-06-25 Diversification Envelope Implementation Information and Crafts Centre LS-MTI-35966-CW-RFB / Supporting Economic Single Stage - One Upgrade Irrigation System at IDA / 59610 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2018-02-08 2018-02-13 2018-03-27 2018-04-26 2018-05-31 2018-11-27 Diversification Envelope Mahobong LS-MTI-35967-CW-RFB / Supporting Economic Single Stage - One Pending IDA / 59610 Post Request for Bids Open - National 300,000.00 0.00 2018-09-24 2018-09-29 2018-11-10 2018-12-10 2019-01-14 2019-07-13 Development of the pilot nursery Diversification Envelope Implementation GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-34650-GO-RFQ / Request for Single Stage - One Procure Furniture and equipment IDA / 59610 Project Implementation Post Limited 50,000.00 3,707.26 Signed 2018-02-03 2018-03-20 2018-03-31 2018-04-09 2018-09-27 Quotations Envelope for PMU LS-MTI-35968-GO-RFQ / Farm Supporting Economic Request for Single Stage - One implements (chemical & IDA / 59610 Post Limited 75,000.00 0.00 Canceled 2019-03-09 2019-05-04 2019-10-31 Diversification Quotations Envelope fertilizers) LS-MTI-49601-GO-RFQ / Improving the Business Request for Single Stage - One Procure IT Equipment for Office IDA / 59610 Post Limited 50,000.00 37,636.88 Signed 2018-03-05 2018-03-09 2018-04-30 2018-04-10 2018-10-27 Environment Quotations Envelope of Parliamentary Counsel LS-MTI-49713-GO-RFB / Supply and Installation of Equipment Improving the Business Single Stage - One Under IDA / 59610 Post Request for Bids Open - National 400,000.00 0.00 2018-03-19 2018-03-09 2018-03-24 2018-04-05 2018-05-05 2018-04-16 2018-06-04 2018-07-09 2019-01-05 for ASYCUDAWorld Backup and Environment Envelope Implementation Redundancy LS-MTI-34588-GO-RFQ / Procure Furniture for OBFC and Improving the Business Request for Single Stage - One Pending IDA / 59610 Post Limited 50,000.00 0.00 2018-06-09 2018-08-04 2019-01-31 Collateral Registry Public Environment Quotations Envelope Implementation Access Sites LS-MTI-34586-GO-RFQ / Procure hardware equipment for Improving the Business Request for Single Stage - One Pending IDA / 59610 Post Limited 75,000.00 0.00 2018-06-09 2018-08-04 2019-01-31 OBFC and Collateral Registry Environment Quotations Envelope Implementation Public Access Sites LS-MTI-60876-GO-RFB / Supporting Economic Single Stage - One Pending Procure IT equipment for single IDA / 59610 Post Request for Bids Open - National 200,000.00 0.00 2018-10-12 2018-10-17 2018-11-28 2018-12-28 2019-02-01 2019-07-31 Diversification Envelope Implementation window LS-MTI-61020-GO-RFB / Improving the Business Single Stage - One Pending Procure ICT Equipment for online IDA / 53090 Post Request for Bids Open - National 150,000.00 0.00 2018-10-01 2018-10-06 2018-11-17 2018-12-17 2019-01-21 2019-07-20 Environment Envelope Implementation e-Licensing LS-MTI-55276-GO-RFB / Supporting Economic Single Stage - One Pending Procure material for upgrade of IDA / 59610 Post Request for Bids Open - National 250,000.00 0.00 2019-05-06 2019-05-11 2019-06-22 2019-07-22 2019-08-26 2020-02-22 Diversification Envelope Implementation irrigation system at Mahobong NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-35718-NC-DIR / Systems support and Improving the Business maintenance for Maseru City IDA / 59610 Prior Direct Selection Direct 30,000.00 14,722.48 Signed 2017-11-17 2018-03-12 2017-11-22 2018-04-12 2017-12-27 2018-04-30 2018-06-25 Environment Council (MCC) Construction Permit LS-MTI-35738-NC-RFQ / Design and Production of Investment Supporting Economic Request for Single Stage - One Pending IDA / 59610 Post Limited 50,000.00 0.00 2018-08-12 2018-10-07 2019-04-05 Promotion Material for Diversification Quotations Envelope Implementation Horticulture LS-MTI-35965-NC-RFQ / Supporting Economic Request for Single Stage - One Pending Investment Promotion Roadshow IDA / 59610 Post Limited 50,000.00 0.00 2018-08-25 2018-10-20 2019-04-18 Diversification Quotations Envelope Implementation for Horticulture LS-MTI-35995-NC-DIR / IDA / 59610 Project Implementation Prior Direct Selection Direct 20,000.00 21,970.00 Signed 2017-11-17 2018-04-05 2017-11-22 2018-04-16 2017-12-27 2018-05-04 2018-06-25 Financial Management System LS-MTI-35722-NC-RFB / Implementation of One Business Improving the Business Single Stage - Two IDA / 59610 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2018-02-08 2018-02-13 2018-03-27 2018-06-09 2018-07-14 2019-01-10 Facilitation Centre (OBFC) Environment Envelope communication strategy Page 1 LS-MTI-35733-NC-RFB / Communication Strategy for Improving the Business Single Stage - Two Pending IDA / 59610 Post Request for Bids Open - National 120,000.00 0.00 2018-07-31 2018-08-05 2018-09-16 2018-11-29 2019-01-03 2019-07-02 Leasing and Secured Environment Envelope Implementation Transactions LS-MTI-60868-NC-RFB / Procure services of a communication's Improving the Business Single Stage - One Pending company for implementation of IDA / 59610 Post Request for Bids Open - National 120,000.00 0.00 2018-07-17 2018-07-22 2018-09-02 2018-10-02 2018-11-06 2019-05-05 Environment Envelope Implementation communications strategy for insolvency LS-MTI-60907-NC-RFQ / Supply Improving the Business Request for Single Stage - One Pending of Internet Services (ISP) for IT IDA / 59610 Post Limited 50,000.00 0.00 2018-06-16 2018-08-11 2019-02-07 Environment Quotations Envelope Implementation Redundancy LS-MTI-60926-NC-DIR / Procure Improving the Business Pending services of a consulting firm for IDA / 53090 Prior Direct Selection Direct 25,000.00 0.00 2018-05-21 2018-05-26 2018-06-30 2018-12-27 Environment Implementation Client Satisfaction Survey LS-MTI-61026-NC-DIR / procure services of a Consultant for Improving the Business Pending training of Maseru City Council IDA / 53090 Prior Direct Selection Direct 5,000.00 0.00 2018-09-03 2018-09-08 2018-10-13 2019-04-11 Environment Implementation (MCC) staff on the Construction Permit system CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-35970-CS-QCBS / Implementation support to the new entity post re-organisation of Supporting Economic Quality And Cost- IDA / 59610 Prior Open - International 800,000.00 0.00 Canceled 2018-01-15 2018-02-05 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 LNDC including implementation Diversification Based Selection of Management and Information system for LNDC LS-MTI-35971-CS-CQS / Develop and implement a Consultant comprehensive Private Sector Supporting Economic Under IDA / 59610 Post Qualification Open - International 150,000.00 0.00 2018-01-24 2018-04-17 2018-02-14 2018-03-30 2018-04-29 2018-06-03 2018-11-30 Strategy which includes inter alia Diversification Implementation Selection a Coherent Incentive Regime and Trade Strategy LS-MTI-35979-CS-CQS / Engage a consultant to develop Consultant Supporting Economic and facilitate implementation of IDA / 59610 Post Qualification Open - International 100,000.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-07-10 Diversification quality and standards capacity Selection building program LS-MTI-35996-CS-QCBS / Engage a consulting firm for transformation of OBFC into a semi-autonomous legal entity, implement business registration Improving the Business Quality And Cost- Under IDA / 59610 Prior Open - International 880,000.00 0.00 2018-06-04 2018-06-25 2018-08-08 2018-09-05 2018-10-05 2018-11-09 2018-12-14 2019-12-14 & licencing law, design and Environment Based Selection Implementation implement an inspection framework to improve country's DB performance on starting a business LS-MTI-43391-CS-QCBS / Supporting Economic Quality And Cost- Develop and Implement Business IDA / 59610 Post Open - International 250,000.00 235,268.60 Signed 2018-01-19 2018-03-07 2018-02-09 2018-04-04 2018-03-25 2018-04-04 2018-04-22 2018-04-30 2018-05-22 2018-04-10 2018-06-26 2018-04-17 2018-07-31 2018-04-27 2019-07-31 Diversification Based Selection Plan for Crafts LS-MTI-35969-CS-QCBS / Engage a consulting firm to review the existing procedures for customs & other border Improving the Business Quality And Cost- IDA / 59610 Prior Open - International 1,300,000.00 0.00 Canceled 2018-06-07 2018-06-28 2018-08-11 2018-09-08 2018-10-08 2018-11-12 2018-12-17 2019-12-17 Agencies, develop and Environment Based Selection implement a trade automation system for all and upgrade ASYCUDAWorld LS-MTI-35984-CS-QCBS / Develop and implement a Supporting Economic Quality And Cost- IDA / 59610 Post Open - International 250,000.00 0.00 Canceled 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 business plan for the research Diversification Based Selection centre LS-MTI-35985-CS-CQS / Consultant Develop and implement a Supporting Economic IDA / 59610 Post Qualification Open - International 150,000.00 0.00 Canceled 2018-05-07 2018-05-28 2018-07-11 2018-08-10 2018-09-14 2019-03-13 marketing and distribution Diversification Selection strategy LS-MTI-49694-CS-UN / Engage a consulting firm for transformation of OBFC into a semi-autonomous legal entity, Improving the Business Under IDA / 59610 Prior UN Agencies (Direct) Direct 880,000.00 0.00 2018-04-18 2018-10-15 implement the business Environment Implementation registration & licensing and design & implement inspection framework LS-MTI-49715-CS-UN / Improving the Business Under Upgrading of ASYCUDAWorld IDA / 59610 Prior UN Agencies (Direct) Direct 500,000.00 0.00 2018-05-09 2018-11-05 Environment Implementation System LS-MTI-60912-CS-CQS / Procure services of consulting Consultant firm to develop and implement a Supporting Economic Pending IDA / 59610 Post Qualification Open - National 100,000.00 0.00 2018-06-29 2018-07-20 2018-09-02 2018-10-02 2018-11-06 2019-05-05 marketing and distribution Diversification Implementation Selection strategy based on demand and supply assessment results LS-MTI-60929-CS-CQS / Procure services of a consulting Consultant Supporting Economic Pending firm to develop a diaspora IDA / 53090 Prior Qualification Open - National 50,000.00 0.00 2018-06-29 2018-07-20 2018-09-02 2018-10-02 2018-11-06 2019-05-05 Diversification Implementation engagement strategy for Selection investment attraction Page 2 LS-MTI-61023-CS-CQS / Consultant Procure services of a consulting Improving the Business Pending IDA / 53090 Post Qualification Open - National 20,000.00 0.00 2018-06-13 2018-07-04 2018-08-17 2018-09-16 2018-10-21 2019-04-19 firm for Construction Permit Environment Implementation Selection System audit LS-MTI-61221-CS-CQS / Consultant Pending Procure Services of a Media Firm IDA / 59610 Project Implementation Post Qualification Open - National 50,000.00 0.00 2018-05-21 2018-06-11 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Implementation for Project's Publicity Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-35616-CS-CDS / TA for Central Bank of Lesotho for Improving the Business Financial Leasing including IDA / 59610 Prior Direct Selection Direct 250,000.00 0.00 Canceled 2017-11-07 2018-02-13 2017-11-17 2018-03-20 2018-01-21 2018-07-20 Environment development and implementation of Investment Promotion Program LS-MTI-35622-CS-INDV / TA for development and implementation of Insolvency Law to facilitate Improving the Business Individual Consultant IDA / 59610 Post Open 100,000.00 0.00 Canceled 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 modernization of the Insolvency Environment Selection Regime and improvement on DB insolvency indicator LS-MTI-35623-CS-INDV / TA for Office of Parliamentary Council institutional assessment in the Improving the Business Individual Consultant IDA / 59610 Post Open 150,000.00 0.00 Canceled 2018-01-10 2018-02-28 2018-03-21 2018-04-25 2018-10-22 areas of technology, skills, Environment Selection human resources and sectoral strategic plan LS-MTI-35628-CS-INDV / Supporting Economic Individual Consultant IDA / 59610 Prior Open 50,000.00 0.00 Canceled 2017-11-15 2018-01-03 2018-01-24 2018-02-28 2018-08-27 Horticulture Technical Advisor Diversification Selection LS-MTI-35972-CS-INDV / Technical Advisor for the Supporting Economic Individual Consultant IDA / 59610 Post Open 125,000.00 0.00 Canceled 2018-01-29 2018-03-19 2018-04-09 2018-05-14 2018-11-10 development and implementation Diversification Selection of linkages program LS-MTI-35981-CS-INDV / Engage a Business Development Supporting Economic Individual Consultant IDA / 59610 Post Open 50,000.00 0.00 Canceled 2017-11-17 2018-01-05 2018-01-26 2018-03-02 2018-08-29 Consultant for basic business Diversification Selection training of the farmers LS-MTI-35982-CS-INDV / Supporting Economic Individual Consultant Develop an exit strategy for the IDA / 59610 Post Open 100,000.00 0.00 Canceled 2018-03-01 2018-04-19 2018-05-10 2018-06-14 2018-12-11 Diversification Selection orchards LS-MTI-35993-CS-INDV / Individual Consultant Engage a Part-time IDA / 59610 Project Implementation Post Open 30,000.00 0.00 Canceled 2018-04-10 2018-05-29 2018-06-19 2018-07-24 2019-01-20 Selection Communications Specialist LS-MTI-35994-CS-INDV / Consultants to staff Project Individual Consultant IDA / 59610 Project Implementation Prior Direct 2,314,428.00 0.00 Canceled 2017-11-13 2017-11-23 2017-12-14 2018-01-18 2018-07-17 Management Unit (including Selection LEAP staff) LS-MTI-44592-CS-CDS / Review of the Structure and Functioning Supporting Economic IDA / 59610 Prior Direct Selection Direct 120,000.00 115,600.00 Signed 2018-01-31 2018-01-25 2018-02-10 2018-03-20 2018-04-16 2018-04-27 2018-10-13 of LNDC - Phase II Diversification Implementation LS-MTI-44594-CS-CDS / Engage a consulting firm for transformation of OBFC into a semi-autonomous legal entity, Improving the Business IDA / 59610 Prior Direct Selection Direct 880,000.00 0.00 Canceled 2018-02-01 2018-01-25 2018-02-11 2018-04-17 2018-10-14 implement Business Registration Environment and Licensing Law, design and implement an inspection framework LS-MTI-35980-CS-INDV / Set-up Supporting Economic Individual Consultant governance structures for IDA / 59610 Post Open 50,000.00 0.00 Canceled 2018-04-02 2018-05-21 2018-06-11 2018-07-16 2019-01-12 Diversification Selection sustainability of orchards LS-MTI-35989-CS-INDV / Alignment of country irrigation Supporting Economic Individual Consultant IDA / 59610 Post Open 100,000.00 0.00 Canceled 2018-03-08 2018-04-26 2018-05-17 2018-06-21 2018-12-18 plans with horticulture suitability Diversification Selection maps LS-MTI-35990-CS-INDV / Technical Advisor for Supporting Economic Individual Consultant development of Horticulture IDA / 59610 Post Open 100,000.00 0.00 Canceled 2018-02-09 2018-03-30 2018-04-20 2018-05-25 2018-11-21 Diversification Selection Investment Attraction Strategy and Action Plan LS-MTI-35991-CS-INDV / Supporting Economic Individual Consultant Implementation of Horticulture IDA / 59610 Post Open 100,000.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 Diversification Selection Business Plan LS-MTI-49597-CS-CDS / Technical Advisor to provide Improving the Business Under IDA / 59610 Prior Direct Selection Direct 100,000.00 116,231.50 2018-02-28 2018-03-12 2018-03-10 2018-03-26 2018-05-14 2018-11-10 support to the Office of Environment Implementation Parliamentary Counsel LS-MTI-49687-CS-CDS / Individual Consultant Procure Services of a Project IDA / 59610 Project Implementation Post Open 175,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Accountant LS-MTI-49689-CS-CDS / Individual Consultant Procure Services o a Project IDA / 59610 Project Implementation Post Open 125,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Manager Page 3 LS-MTI-49615-CS-CDS / Individual Consultant Procure Services of a Project IDA / 59610 Project Implementation Post Open 78,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Driver LS-MTI-49626-CS-CDS / Individual Consultant IDA / 59610 Project Implementation Post Open 148,000.00 0.00 Canceled 2018-03-05 2018-03-07 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Procure services of LEAP Officer Selection LS-MTI-49627-CS-CDS / Individual Consultant Procure services of an Office IDA / 59610 Project Implementation Post Open 24,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Assistant LS-MTI-49632-CS-CDS / Individual Consultant Procure services of a IDA / 59610 Project Implementation Post Open 353,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Procurement Manager LS-MTI-49635-CS-CDS / Individual Consultant Procure Services of an IDA / 59610 Project Implementation Post Open 172,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Administrative Secretary LS-MTI-49678-CS-CDS / Individual Consultant Procure Services of a Financial IDA / 59610 Project Implementation Post Open 353,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Manager LS-MTI-49682-CS-CDS / Individual Consultant Procure Services f a LEAP IDA / 59610 Project Implementation Post Open 187,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Manager LS-MTI-49683-CS-CDS / Procure services of a Horticulture IDA / 59610 Project Implementation Prior Direct Selection Direct 386,000.00 384,127.99 Signed 2018-02-28 2018-04-05 2018-03-10 2018-04-11 2018-05-14 2017-04-19 2018-11-10 Coordinator and M&E Specialist LS-MTI-49686-CS-CDS / Individual Consultant Procure Services of a IDA / 59610 Project Implementation Post Open 112,000.00 0.00 Canceled 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Selection Receptionist & IT Support LS-MTI-51812-CS-INDV / Individual Consultant Procure services of Deputy IDA / 59610 Project Implementation Post Open 340,000.00 0.00 Canceled 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Selection Project Manager LS-MTI-51863-CS-INDV / Supporting Economic Individual Consultant Procure services of a Horticulture IDA / 59610 Post Open 87,000.00 0.00 Canceled 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Diversification Selection Field Manager LS-MTI-51866-CS-INDV / Supporting Economic Individual Consultant Procure services of a Farm IDA / 59610 Post Open 87,000.00 0.00 Canceled 2018-03-12 2018-04-30 2018-05-21 2018-06-25 2018-12-22 Diversification Selection Manager LS-MTI-55049-CS-CDS / Procure services of a Project IDA / 59610 Project Implementation Post Direct Selection Direct 78,000.00 77,311.31 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Driver LS-MTI-55057-CS-CDS / Procure Services of a LEAP IDA / 59610 Project Implementation Post Direct Selection Direct 148,000.00 147,547.74 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-18 2018-06-17 2017-04-19 2018-12-14 Officer LS-MTI-55064-CS-CDS / Procure Services of an Office IDA / 59610 Project Implementation Post Direct Selection Direct 24,000.00 23,254.34 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Assistant LS-MTI-55142-CS-CDS / Procure services of an IDA / 59610 Project Implementation Post Direct Selection Direct 172,000.00 169,838.63 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Administrative Secretary LS-MTI-55149-CS-CDS / Procure services of a Project IDA / 59610 Project Implementation Post Direct Selection Direct 175,000.00 151,914.60 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Accountant LS-MTI-55156-CS-CDS / Procure services of a IDA / 59610 Project Implementation Post Direct Selection Direct 112,000.00 110,707.76 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Receptionist LS-MTI-55169-CS-CDS / Procure service of a LEAP IDA / 59610 Project Implementation Post Direct Selection Direct 187,000.00 184,875.14 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Manager LS-MTI-55171-CS-CDS / Procure services of a Project IDA / 59610 Project Implementation Post Direct Selection Direct 125,000.00 123,455.35 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Manager LS-MTI-55172-CS-CDS / Procure services of a IDA / 59610 Project Implementation Post Direct Selection Direct 353,000.00 351,302.51 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Procurement Manager LS-MTI-55254-CS-CDS / Procure Services of a Financial IDA / 59610 Project Implementation Post Direct Selection Direct 353,000.00 349,112.73 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-10 2018-06-17 2017-04-19 2018-12-14 Manager LS-MTI-55258-CS-CDS / Procure services of Deputy IDA / 59610 Project Implementation Post Direct Selection Direct 340,000.00 326,408.44 Signed 2018-04-03 2018-04-05 2018-04-13 2018-04-18 2018-06-17 2018-04-30 2018-12-14 Project Manager LS-MTI-55265-CS-CDS / Procure services of a Farm IDA / 59610 Project Implementation Post Direct Selection Direct 87,000.00 81,594.83 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-18 2018-06-17 2018-04-30 2018-12-14 Manager LS-MTI-55269-CS-CDS / Procure Services of Horticulture IDA / 59610 Project Implementation Post Direct Selection Direct 87,000.00 20,913.22 Signed 2018-04-03 2018-03-28 2018-04-13 2018-04-18 2018-06-17 2018-04-30 2018-12-14 Field Manager LS-MTI-35612-CS-INDV / Engage a Technical Advisor for Secured Transactions to improve Improving the Business Individual Consultant Pending IDA / 59610 Post Open 100,000.00 0.00 2019-02-04 2019-03-25 2019-04-15 2019-05-20 2019-11-16 access to finance and improve Environment Selection Implementation the country's performance on getting a credit DB indicator Page 4 LS-MTI-60858-CS-INDV / Engage a consultant for review Improving the Business Individual Consultant Pending IDA / 59610 Post Open 100,000.00 0.00 2018-06-26 2018-08-14 2018-09-04 2018-10-09 2019-04-07 and amendment of Construction Environment Selection Implementation Permit related laws LS-MTI-60860-CS-CDS / Procure services of a consultant Improving the Business Pending to enable electronic payment IDA / 59610 Prior Direct Selection Direct 10,000.00 0.00 2018-05-31 2018-06-10 2018-08-14 2019-02-10 Environment Implementation module within the construction Permit System LS-MTI-60862-CS-INDV / Procure services of a TA for Improving the Business Individual Consultant Pending IDA / 59610 Post Open 100,000.00 0.00 2018-06-13 2018-08-01 2018-08-22 2018-09-26 2019-03-25 development and implementation Environment Selection Implementation of Insolvency Law LS-MTI-61206-CS-INDV / Supporting Economic Individual Consultant Pending Procure services of a Farm IDA / 59610 Post Open 20,000.00 0.00 2018-06-18 2018-08-06 2018-08-27 2018-10-01 2019-03-30 Diversification Selection Implementation Manager at Mahobong II LS-MTI-61208-CS-INDV / Supporting Economic Individual Consultant Pending Procure services of a Farm IDA / 59610 Post Open 20,000.00 0.00 2018-06-18 2018-08-06 2018-08-27 2018-10-01 2019-03-30 Diversification Selection Implementation Manager at Likhetlane LS-MTI-61211-CS-INDV / Procures Services of a Supporting Economic Individual Consultant Pending IDA / 59610 Prior Direct 12,000.00 0.00 2018-05-18 2018-05-28 2018-06-18 2018-07-23 2019-01-19 Horticulture Infrastructure Diversification Selection Implementation Technician for Mahobong II LS-MTI-61215-CS-CDS / Procure services of a Horticulture Supporting Economic Pending IDA / 59610 Post Direct Selection Direct 12,000.00 0.00 2018-05-11 2018-05-21 2018-07-25 2019-01-21 Infrastructure Technician for Diversification Implementation Likhetlane LS-MTI-61218-CS-INDV / Supporting Economic Individual Consultant Pending Procure services of a Horticulture IDA / 59610 Prior Direct 15,000.00 0.00 2018-05-21 2018-05-31 2018-06-21 2018-07-26 2019-01-22 Diversification Selection Implementation Technical Field Advisor LS-MTI-61226-CS-CDS / Engage consultant to develop and Supporting Economic Pending facilitate implementation of IDA / 53090 Prior Direct Selection Direct 100,000.00 0.00 2018-06-18 2018-06-28 2018-09-01 2019-02-28 Diversification Implementation quality and standards capacity building program LS-MTI-35974-CS-INDV / Supporting Economic Individual Consultant Pending IDA / 59610 Post Open 200,000.00 0.00 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2020-01-25 Management of Pilot Nursery Diversification Selection Implementation Page 5