PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Western Africa : WAPP APL4 (Phase 1) - Côte d'Ivoire, Sierra Leone, Liberia, and Guinea Power System Re-development PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-02-28 2020-08-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P113266 GPN Date: Project Name: WAPP APL4 (Phase 1) - Côte d'Ivoire, Sierra Leone, Liberia, and Guinea Power System Re-development Loan / Credit No: IDA / D2440, IDA / H7700 Executing Agency(ies): WEST AFRICAN POWER POOL WORKS Procureme Bid Evaluation Activity Reference No. / Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Amount Document / Signed Contract No. Approach Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion (US$) Justification Type Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-24 / Design, Technical Assistance and Supply and Installation of Open - Single Stage - One IDA / H7700 Integration of WAPP A priori Appel d'offres 7,018,205.15 Signé 2018-02-26 2018-05-11 2018-03-14 2018-07-06 2018-04-25 2018-05-25 2018-10-19 2018-06-29 2018-12-19 2018-12-26 SVC, SPS and PMUs- Re- International Envelope Network tendering GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-26 / Acquisition Technical Assistance and Open - Single Stage - One En cours of video conférence IDA / H7700 Integration of WAPP A posteriori Demande de prix 0.00 2018-01-20 2018-03-17 2018-06-17 International Envelope d'exécution equipements Network MOF-REF-28 / Equipment for functioning of the North Supply Alternatives Studies Core PIU (vehicles, office Open - Single Stage - One En attente IDA / D2440 and Project Preparation A posteriori Demande de prix 0.00 2018-06-06 2018-08-01 2018-11-01 equipment, consumables etc- International Envelope d'exécution Support multiple contracts under 100.000 $) BJ-WAPP-97000-GO-RFQ / Technical Assistance and Acquisition of IT, Office Open - Single Stage - One En cours IDA / H7700 Integration of WAPP A posteriori Demande de prix 0.00 2019-03-20 2019-05-15 2019-11-11 equipment and Office International Envelope d'exécution Network supplies (multiple contracts) BJ-WAPP-173726-GO-RFQ / Technical Assistance and NC-Supply Printers and Single Stage - One En attente IDA / H7700 Integration of WAPP A posteriori Demande de prix Open - National 0.00 2020-05-26 2020-07-21 2020-09-21 photocopiers - North Core Envelope d'exécution Network Abuja Office BJ-WAPP-173728-GO-RFQ / Technical Assistance and NC- Field equipment for Single Stage - One En attente IDA / H7700 Integration of WAPP A posteriori Demande de prix Open - National 0.00 2020-05-26 2020-07-21 2020-08-21 ESIA safeguard department- Envelope d'exécution Network North Core Project BJ-WAPP-173733-GO-RFQ / NC- Supply of computer Technical Assistance and Open - Single Stage - One En attente hardware and equipment for IDA / H7700 Integration of WAPP A posteriori Demande de prix 0.00 2020-05-26 2020-07-21 2020-10-21 International Envelope d'exécution North Core-Abuja and local Network Offices NON CONSULTING SERVICES Page 1 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-25 / Tuning of Power System Stabilizers Technical Assistance and Open - Single Stage - One (PSS), Field Testing and IDA / H7700 Integration of WAPP A priori Appel d'offres 4,014,239.34 Signé 2018-04-15 2018-11-04 2018-04-20 2018-12-30 2018-06-01 2019-02-18 2018-07-01 2019-05-13 2018-08-05 2019-08-26 2019-02-01 International Envelope Synchronization of the Network WAPP network. BJ-WAPP-48674-NC-DIR / Technical Assistance and Passation de Acquisition of Integrated IDA / H7700 Integration of WAPP A posteriori marché de gré à Direct 0.00 Annulé 2017-12-01 2018-02-19 2017-12-06 2017-12-01 2018-03-23 2018-06-25 fiduciary management Network gré software BJ-WAPP-106480-NC-DIR / Technical Assistance and Passation de Acquisition of TOMPRO ( En attente IDA / H7700 Integration of WAPP A posteriori marché de gré à Direct 0.00 2019-03-17 2019-03-22 2019-04-26 2019-10-23 integrated fiduciary d'exécution Network gré management software) BJ-WAPP-124404-NC-DIR / Passation de Institutional Framework and En cours NC- Acquisition of TOMPRO- IDA / D2440 A posteriori marché de gré à Direct 0.00 2019-07-31 2019-08-01 2019-08-05 2019-09-09 2020-03-07 Project Oversight d'exécution extended version gré BJ-WAPP-173811-NC-DIR / TESTS at Delta IV power Power Interconnection Passation de plant (Nigeria)-- Contract between Cote d'Ivoire, En attente IDA / H7700 A posteriori marché de gré à Direct 0.00 2020-06-01 2020-06-06 2020-07-11 2020-11-30 with GE INTERNATIONAL Liberia, Sierra Leone and d'exécution gré OPERATIONS NIGERIA Guinea LTD- OEM BJ-WAPP-173812-NC-DIR / Power Interconnection Passation de TESTS at GEREGU power between Cote d'Ivoire, En attente IDA / H7700 A posteriori marché de gré à Direct 0.00 2020-06-01 2020-06-06 2020-07-11 2020-09-30 plant (Nigeria)- contract with Liberia, Sierra Leone and d'exécution gré SIEMENS LTD- OEM Guinea BJ-WAPP-173813-NC-DIR / Power Interconnection TESTS at KAINJI power Passation de between Cote d'Ivoire, En attente plant (Nigeria)-contract with IDA / H7700 A posteriori marché de gré à Direct 0.00 2020-06-01 2020-06-06 2020-07-11 2020-09-30 Liberia, Sierra Leone and d'exécution GE Renewable Energy Hydro gré Guinea France - OEM N.1 BJ-WAPP-173815-NC-DIR / TESTS N.2 at KAINJI Power Interconnection power plant (Nigeria)- Passation de between Cote d'Ivoire, En attente contract with Power China IDA / H7700 A posteriori marché de gré à Direct 0.00 2020-06-01 2020-06-06 2020-07-11 2020-09-30 Liberia, Sierra Leone and d'exécution Huadong Engineering gré Guinea Company Limited - OEM N.2 BJ-WAPP-173816-NC-DIR / TESTS at AFAM VI power Power Interconnection plant (Nigeria)- contract with Passation de between Cote d'Ivoire, En attente General Electric IDA / H7700 A posteriori marché de gré à Direct 0.00 2020-06-01 2020-06-06 2020-07-11 2020-09-30 Liberia, Sierra Leone and d'exécution International Operations gré Guinea (NIG) Limited (“GEION”) - OEM BJ-WAPP-173817-NC-DIR / Tests N.2 for VRA Power Interconnection Passation de AKOSOMBO power plant between Cote d'Ivoire, En attente IDA / H7700 A posteriori marché de gré à Direct 0.00 2020-06-01 2020-06-06 2020-07-11 2020-09-30 (Ghana)- contract with GE Liberia, Sierra Leone and d'exécution gré Oil and Gas Limited - OEM Guinea N.2 BJ-WAPP-173818-NC-DIR / Power Interconnection Tests at VRA AKOSOMBO Passation de between Cote d'Ivoire, En attente power plant (Ghana) - IDA / H7700 A posteriori marché de gré à Direct 0.00 2020-06-01 2020-06-06 2020-07-11 2020-09-30 Liberia, Sierra Leone and d'exécution contract with ANDRITZ gré Guinea HYDRO - OEM N.2 Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-12 / Feasibility Supply Alternatives Studies Sélection fondée Study of the priority project Open - IDA / D2440 and Project Preparation A priori sur la qualité et 0.00 Annulé 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2020-06-10 selected-St Paul River Proj.- International Support le coût Liberia- AF 2MOF-REF-13 / ESIA Supply Alternatives Studies Sélection fondée Studies for the Priority Open - IDA / D2440 and Project Preparation A priori sur la qualité et 0.00 Annulé 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2020-06-10 Project-St Paul River Proj.- International Support le coût Liberia- AF MOF-REF-14 / Strategic Supply Alternatives Studies Sélection fondée Advisor to support Project's Open - En cours IDA / D2440 and Project Preparation A posteriori sur la qualité et 0.00 2018-09-01 2020-02-09 2018-09-22 2020-03-12 2018-11-05 2018-12-03 2019-01-02 2019-02-06 2019-03-13 2020-03-12 development -St Paul River International d'exécution Support le coût Proj.- Liberia- AF Sélection fondée BJ-WAPP-58133-CS-CQS / Technical Assistance and sur les Open - Evaluation Electricity sub- IDA / H7700 Integration of WAPP A posteriori 221,774.00 Signé 2018-06-01 2018-12-01 2018-06-22 2018-12-06 2018-08-05 2019-04-29 2018-09-04 2019-07-09 2018-10-09 2019-07-29 2019-04-07 qualifications des International sector skills in west Africa Network consultants BJ-WAPP-48547-CS-CQS / Sélection fondée Technical Assistance and North Core Project: Selection sur les Open - IDA / H7700 Integration of WAPP A posteriori 0.00 Annulé 2018-02-12 2018-02-14 2018-02-20 2018-02-28 2018-03-19 2018-09-19 Agency for recruitment of qualifications des International Network IMU key staff consultants MOF-REF-6 / Financial Supply Alternatives Studies Sélection au Open - Audit ITAP/ WAPP for IDA / H7700 and Project Preparation A posteriori 30,078.00 Signé 2018-07-30 2019-02-27 2018-08-20 2019-01-15 2018-10-03 2019-04-24 2018-10-31 2019-05-22 2018-11-30 2019-05-24 2019-01-04 2019-06-03 2019-02-08 2019-06-05 2021-11-29 moindre coût International 2018 - 2019- 2020 period Support MOF-REF-7 / Support to the preparation of the PPAs Supply Alternatives Studies Sélection fondée Open - En attente based on the opportunities IDA / D2440 and Project Preparation A posteriori sur la qualité et 0.00 2018-08-15 2018-09-05 2018-10-19 2018-11-16 2018-12-16 2019-01-20 2019-02-24 2020-02-24 International d'exécution created by the development Support le coût of the CLSG- AF MOF-REF-8 / Organization Sélection fondée Supply Alternatives Studies of a sub-regional workshop sur les Open - En attente IDA / D2440 and Project Preparation A posteriori 0.00 2018-08-30 2018-09-20 2018-11-03 2018-12-03 2019-01-07 2019-07-06 on CLSG market qualifications des International d'exécution Support opportunities- AF consultants MOF-REF-20 / Consultant Sélection fondée Technical Assistance and for preparation of sur les Open - IDA / H7700 Integration of WAPP A posteriori 0.00 Annulé 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2019-02-03 Certification program for qualifications des International Network Operators consultants MOF-REF-9 / Preparation Supply Alternatives Studies Sélection fondée of the technical annexes to Open - En attente IDA / D2440 and Project Preparation A priori sur la qualité et 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-16 2018-09-15 2018-10-20 2018-11-24 2019-11-24 signed PPAs and TSA International d'exécution Support le coût through the CLSG line - AF MOF-REF-11 / Optimization Supply Alternatives Studies Sélection fondée Study to define a priority Open - IDA / D2440 and Project Preparation A posteriori sur la qualité et 355,331.58 Signé 2018-08-20 2019-02-27 2018-09-10 2018-08-24 2018-10-24 2018-10-25 2018-11-21 2018-12-10 2018-12-21 2018-12-18 2019-01-25 2019-01-18 2019-03-01 2019-02-14 2020-02-29 investment project - St Paul International Support le coût River Proj.- Liberia- AF Page 3 BJ-WAPP-81801-CS-QCBS / Supply Alternatives Studies Sélection fondée Technical Assistance to Focal Open - En cours IDA / D2440 and Project Preparation A priori sur la qualité et 0.00 2018-10-15 2018-11-05 2018-10-17 2018-12-19 2018-12-11 2019-01-16 2019-02-05 2019-02-15 2019-02-05 2019-03-22 2019-08-02 2019-04-26 2020-04-25 Point (Phase 2)-St Paul International d'exécution Support le coût River Project- Liberia- AF BJ-WAPP-111608-CS-QCBS Supply Alternatives Studies Sélection fondée Open - En attente / ESIA Ghana -Burkina-Mali IDA / H7700 and Project Preparation A priori sur la qualité et 0.00 2019-04-26 2019-05-17 2019-06-30 2019-07-28 2019-08-27 2019-10-01 2019-11-05 2020-11-04 International d'exécution Interconnection Project Support le coût BJ-WAPP-127634-CS-CQS / Sélection fondée Supply Alternatives Studies LEGAL EXPERT IN sur les Open - En cours IDA / H7700 and Project Preparation A posteriori 0.00 2019-08-30 2019-09-25 2019-09-20 2019-11-03 2019-12-03 2020-01-07 2020-07-05 REGIONAL POWER POOLS qualifications des International d'exécution Support ( firm) consultants BJ-WAPP-130085-CS-QCBS / Feasibility & ESIA studies Supply Alternatives Studies Sélection fondée Open - of the priority project IDA / D2440 and Project Preparation A priori sur la qualité et 3,905,760.90 Signé 2019-09-15 2019-10-05 2019-10-06 2019-10-23 2019-11-19 2019-12-21 2019-12-17 2020-03-02 2020-01-16 2020-05-23 2020-02-20 2020-05-28 2020-03-26 2020-06-05 2021-03-26 International Selected-St Paul River Support le coût Projects - Liberia BJ-WAPP-134263-CS-CQS / Sélection fondée Supply Alternatives Studies Legal Expert Regional Power sur les Open - En cours IDA / H7700 and Project Preparation A posteriori 0.00 2019-09-30 2019-09-25 2019-10-21 2019-12-04 2020-01-03 2020-02-07 2020-08-05 Pool (firm)- AT to Energy qualifications des International d'exécution Support Buyers consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-22 / Technical Technical Assistance and Coordinator for WAPP ( IDA / H7700 Integration of WAPP A priori Individuel Open 0.00 Annulé 2018-01-08 2019-02-28 2018-02-26 2018-03-19 2018-04-23 2019-04-23 Resident) Network Technical Assistance and MOF-REF-23 / Power pool En cours IDA / H7700 Integration of WAPP A priori Individuel Open 0.00 2018-03-30 2018-05-17 2018-05-18 2019-04-30 2018-06-08 2019-06-30 2018-07-13 2019-01-09 Adviser ( Phase 2) - CIC d'exécution Network MOF-REF-16 / Focal Team Supply Alternatives Studies Sélection de PDU counterpart Expert-St En cours IDA / D2440 and Project Preparation A priori consultants par Direct 0.00 2018-02-13 2019-02-28 2018-02-16 2018-02-28 2020-02-28 Paul River Proj.- Liberia- d'exécution Support entente directe AF BJ-WAPP-58084-CS-INDV / Supply Alternatives Studies North Core Project- En cours IDA / H7700 and Project Preparation A priori Individuel Open 0.00 2018-04-10 2018-06-13 2018-05-17 2018-06-07 2019-02-28 2018-07-12 2019-01-08 Implementing Management d'exécution Support Unit (IMU) director BJ-WAPP-59065-CS-INDV / Technical Assistance and Certification program for En cours IDA / H7700 Integration of WAPP A posteriori Individuel Open 0.00 2018-04-13 2018-05-28 2018-06-01 2018-12-20 2018-06-22 2018-07-27 2019-01-23 Operators ( Individual d'exécution Network Consultant) BJ-WAPP-61508-CS-CDS / Review of Environmental Supply Alternatives Studies Sélection de and Social Impact IDA / H7700 and Project Preparation A posteriori consultants par Direct 40,435.00 Achevé 2018-05-02 2018-05-07 2018-05-07 2018-05-21 2018-12-18 2018-05-31 2018-05-25 Assessment (ESIA) Reports Support entente directe for North Core Project MOF-REF-19 / Electricity Technical Assistance and sub-sector skill study for IDA / H7700 Integration of WAPP A posteriori Individuel Open 0.00 Annulé 2018-01-05 2018-03-02 2018-03-23 2018-04-27 2018-07-24 West Africa Network Page 4 BJ-WAPP-58896-CS-INDV / Supply Alternatives Studies N. Core-Monitoring IDA / H7700 and Project Preparation A priori Individuel Open 0.00 Annulé 2018-05-28 2019-02-28 2018-07-04 2018-07-25 2018-08-29 2019-02-25 &Evaluation Specialist Support BJ-WAPP-64381-CS-INDV / Supply Alternatives Studies N. Core- Environmental IDA / H7700 and Project Preparation A priori Individuel Open 0.00 Annulé 2018-05-29 2019-02-28 2018-07-05 2018-07-26 2018-08-30 2019-02-26 Specialist Support Supply Alternatives Studies BJ-WAPP-64383-CS-INDV / IDA / H7700 and Project Preparation A priori Individuel Open 0.00 Annulé 2018-05-28 2019-02-28 2018-07-04 2018-07-25 2018-08-29 2019-02-25 N. Core- Social Safeguards Support BJ-WAPP-64384-CS-INDV / Supply Alternatives Studies N. Core- Sr Financial IDA / H7700 and Project Preparation A priori Individuel Open 0.00 Annulé 2018-05-28 2019-02-28 2018-07-04 2018-07-25 2018-08-29 2019-02-25 Specialist Support BJ-WAPP-64385-CS-INDV / Supply Alternatives Studies N. Core-Sr Electrical IDA / H7700 and Project Preparation A priori Individuel Open 0.00 Annulé 2018-05-28 2019-02-28 2018-07-04 2018-07-25 2018-08-29 2019-02-25 Engineering Support BJ-WAPP-64386-CS-INDV / Supply Alternatives Studies En cours N. Core- Sr Procurement IDA / H7700 and Project Preparation A priori Individuel Open 0.00 2018-05-28 2019-02-28 2018-07-04 2018-07-25 2018-08-29 2019-02-25 d'exécution Specialist Support BJ-WAPP-64388-CS-INDV / Supply Alternatives Studies En cours Panel- Environmental IDA / D2440 and Project Preparation A posteriori Individuel Open 0.00 2018-05-28 2018-09-25 2018-07-16 2018-08-06 2018-09-10 2019-09-10 d'exécution Specialist Support MOF-REF-18 / Two specialists members of Supply Alternatives Studies Panel Experts (Social IDA / D2440 and Project Preparation A posteriori Individuel Open 0.00 Annulé 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2019-06-13 specialist and Support Environmental specialist )- WAPP projects- AF Supply Alternatives Studies BJ-WAPP-64390-CS-INDV / En cours IDA / D2440 and Project Preparation A posteriori Individuel Open 0.00 2018-05-28 2018-09-25 2018-07-16 2018-08-06 2018-09-10 2019-09-10 Panel-Social Specialist d'exécution Support MOF-REF-17 / Panel of 6 Supply Alternatives Studies experts (different specialities)- IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 Annulé 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2019-06-13 WAPP projects- PP Support BJ-WAPP-64416-CS-INDV / Technical Assistance and finalization of the pricing IDA / H7700 Integration of WAPP A posteriori Individuel Open 0.00 Annulé 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-01-09 model for regional power Network transmission Supply Alternatives Studies BJ-WAPP-64392-CS-INDV / En cours IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 2018-05-29 2018-09-25 2018-09-24 2018-10-15 2018-11-19 2019-11-19 Panel-Dam Specialist d'exécution Support Supply Alternatives Studies BJ-WAPP-64395-CS-INDV / En cours IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 2018-05-28 2018-09-25 2018-09-24 2018-10-15 2018-11-19 2019-11-19 Panel- Geologist d'exécution Support Supply Alternatives Studies BJ-WAPP-64396-CS-INDV / En cours IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 2018-05-29 2018-09-25 2018-09-24 2018-10-15 2018-11-19 2019-11-19 Panel- Hydrologiist d'exécution Support BJ-WAPP-64397-CS-INDV / Supply Alternatives Studies Panel- Hydraulic Engineer IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 Annulé 2018-05-29 2018-09-24 2018-10-15 2018-11-19 2019-11-19 Specialist Support Page 5 BJ-WAPP-64398-CS-INDV / Supply Alternatives Studies En cours Panel- Health and Safety IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 2018-05-29 2018-09-25 2018-09-24 2018-10-15 2018-11-19 2019-11-19 d'exécution Specialist Support BJ-WAPP-64399-CS-INDV / Supply Alternatives Studies En cours Panel- Electro-mechanical IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 2018-05-29 2018-09-25 2018-09-24 2018-10-15 2018-11-19 2019-11-19 d'exécution specialist Support BJ-WAPP-88925-CS-CDS / Technical Assistance and Sélection de Technical Assistance fo En attente IDA / D2440 Integration of WAPP A posteriori consultants par Direct 0.00 2018-12-07 2018-12-17 2019-02-20 2019-08-19 Focal Team -Liberia- Phase d'exécution Network entente directe 1-B BJ-WAPP-96229-CS-INDV / Supply Alternatives Studies En cours Senior Accountant Officer ( IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 2019-01-24 2019-01-24 2019-03-14 2019-04-04 2019-05-09 2019-11-05 d'exécution North Core ) Support BJ-WAPP-106481-CS-CDS / Technical Assistance and Sélection de En attente Pricing model for regional IDA / H7700 Integration of WAPP A posteriori consultants par Direct 0.00 2019-03-31 2019-04-10 2019-05-28 2019-11-24 d'exécution power transmission Network entente directe BJ-WAPP-124405-CS-CDS / Sélection de North Core- Recruitment of Institutional Framework and En cours IDA / D2440 A posteriori consultants par Direct 0.00 2019-07-31 2019-08-28 2019-08-10 2019-10-14 2020-04-11 Blueprint Consult Co Ltd- Project Oversight d'exécution entente directe for no key staff selection BJ-WAPP-127670-CS-INDV / Supply Alternatives Studies Technical Expert Regional IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 Annulé 2019-08-25 2019-08-28 2019-10-13 2019-09-13 2019-11-03 2019-09-17 2019-12-08 2020-06-05 Power Pools Support BJ-WAPP-127672-CS-INDV / Supply Alternatives Studies En cours FINANCIAL EXPERT IN IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 2019-08-25 2019-09-24 2019-10-13 2019-11-03 2019-12-08 2020-06-05 d'exécution ENERGY TRADE Support BJ-WAPP-134265-CS-INDV / Supply Alternatives Studies En cours Financial Expert in Energy IDA / H7700 and Project Preparation A posteriori Individuel Open 0.00 2019-09-30 2019-09-24 2019-11-18 2019-12-09 2020-01-13 2020-07-11 d'exécution Trading- TA to buyers Support BJ-WAPP-134262-CS-CDS / Sélection de Institutional Framework and En cours New- Technical Coordinator IDA / H7700 A posteriori consultants par Direct 0.00 2019-09-26 2019-10-01 2019-10-06 2019-07-19 2019-12-10 2020-06-07 Project Oversight d'exécution for WAPP-resident entente directe BJ-WAPP-145246-CS-INDV / Technical Assistance and Consultant to conduct team En cours IDA / H7700 Integration of WAPP A posteriori Individuel Limited 0.00 2019-11-14 2019-12-12 2019-11-19 2019-12-10 2020-01-14 2020-07-12 building workshop for WAPP d'exécution Network Secretariat BJ-WAPP-173802-CS-CDS / Technical Assistance and Sélection de En cours Support to Technical IDA / H7700 Integration of WAPP A posteriori consultants par Direct 0.00 2020-05-21 2020-06-03 2020-05-31 2020-06-30 2020-12-15 d'exécution Working groups-new contract Network entente directe BJ-WAPP-189376-CS-INDV / Technical Assistance and En attente Transaction adviser- North IDA / H7700 Integration of WAPP A posteriori Individuel Limited 0.00 2020-08-21 2020-08-26 2020-09-02 2020-10-14 2021-04-12 d'exécution Core transactions Network Page 6