Procurement Plan I. General 1. Project Information Country: Malawi Project Name: Malawi Agricultural Commercialization Project (AGCOM) Project ID: P158434 2. Project Implementation Agency: Ministry of Agriculture, Irrigation and Water Development (MoAIWD) 3. Date of the Procurement Plan: March, 2018 4. Period Covered by this procurement plan: March, 2018 -31st August,2019 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public Procurement Act, 2003 and The Public Procurement Regulations, 2004, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: o Provision of “set-asides” contracts for small enterprises shall not be applied. o Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis. 1 When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification : N/A VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. VII. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: N/A (b) Works: N/A Domestic preference is not applicable for National Open Competitive Procurement IX. Other Relevant Procurement Information Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc.--NONE X. Procurement Prior Review Thresholds (US$ millions): The overall Project procurement Risk is Substantial. The project being a non-emergency project, there would be generally prior reviews of cases unless specifically indicated in the Procurement Plan as a special measure. Post Review: All contracts not subject to prior review shall be subject to post review. 2 XI. Procurement Prior Review Thresholds Based on High Risk Rating (US$ millions) Works Goods, IT and Non-Consulting Services Shortlist of National Consultants Open Open Request Open Open Request Consulting Engineering International National for International National for Services & Quotation Quotation Construction ≥ < ≥ < ≤ Supervision ≤ ≤ ≤ 5 5 0.2 1.5 1.5 0.1 0.5 0.3 3 PROCUREMENT PACKAGES WITH METHODS AND TIME SCHEDULESOF GOOD AND NON CONSULTANCY A) PROCUREMENT OF GOODS AND NON CONSULTANCY SERVICES Sr. No Contract QTY Unit Est. Cost Review Market Selection Evaluation Procureme Prequalifi Domestic Expected Expected Description (US$) by Bank Approac Method Options nt Process cation Preferenc date of bid/ date of (Prior/ h (Yes/ No) e proposal Contract Post) (Yes/No) opening Signature G.1.01 Double Cabin Post Qualifying No No Vehicles for PIU 10 No 650,000.00 Open RFB criteria Single 15-06-17 25-10-17 and National stage one Implementing Envelope Departments G.1.02 IT Equipment & Various No 100,000.00 Post Limited RFQ Qualifying Single No No Air Conditioners criteria stage one 07-07-17 31-08-17 for PIU Envelope G.1.03 Limited Qualifying Single Procurement of Various No 30,000.00 Post RFQ criteria stage one No No 07-07-17 31-08-17 Furniture for PIU Envelope G.1.04 Irrigation Various No. 70,000.00 Post Limited RFQ Qualifying Single No No 03-03-17 04-04-17 Equipment for the criteria stage one last mile Envelope infrastructure G.1.05 Electricity Various No 50,000.00 Post Limited RFQ Qualifying Single equipment and criteria stage one No No 07-07-17 31-08-17 Accessories for Envelope the last mile infrastructure G.1.06 Water equipment Various No 50,000.00 Post Open RFQ Qualifying Single No No 03-03-17 04-04-17 and accessories National criteria stage one for the last mile Envelope infrastructure G.1.07 Advocacy Various National- Qualifying Single (Sensitization and No 30,000.00 Post Open RFQ criteria stage one No No 15-07-17 30-09-17 awareness) ie Envelope Audio, Visual, Drama and comedies G.1.07 Radio, TV 12 National- Qualifying Single 25-07-17 15-09-17 Airtime for No 90,000.00 Post Open RFQ criteria stage one No No documentaries, Envelope 4 Sr. No Contract QTY Unit Est. Cost Review Market Selection Evaluation Procureme Prequalifi Domestic Expected Expected Description (US$) by Bank Approac Method Options nt Process cation Preferenc date of bid/ date of (Prior/ h (Yes/ No) e proposal Contract Post) (Yes/No) opening Signature Programs and announcements G.1.08 Radio , TV 12 No 50,000.00 National- Qualifying Single 24-07-17 31-09-17 Production Post Open RFQ criteria stage one No No Program Envelope G.1.09 Print Media 10 No 30,000.00 National- Qualifying Single 31-07-17 08-08-17 adverts Post Open RFQ criteria stage one No No Envelope G.1.10 Production and Various No 50,000.00 National- Qualifying Single 15-04-17 30-04-17 Printing of IEC Post Open RFQ criteria stage one No No Materials Envelope 1,200,000.00 PROCUREMENT OF WORKS Sr. No Contract Description QTY Unit Est. Cost Review by Market Selection Evaluatio Procurem Prequali- Domestic Expected Expected (US$) Bank Approach Method n Options ent fication Preferenc date of date of (Prior/ Process ( (Yes/ No) e (Yes/No) bid/ Contract Post) proposal Signature opening G.1.01 Rehabilitation/construction 10 No 1,000,000 Post Open- RFQ Qualifying Single of irrigation infrastructure National Criteria stage one No No 15-02-18 10-04-18 Envelope W.1.0 Construction/rehabilitation 5 No 800,000 Post National- RFQ Qualifying Single No No 2 of access roads Open Criteria stage one 14-02-18 25-04-18 Envelope W.1.0 Installation of clean water 5 No 120,000 Post Open - RFQ Qualifying Single No No 14-03-18 31-04-18 3 facilities National Criteria stage one Envelope W.1.0 Rehabilitation/Drilling of 5 No 70,000.00 Post National- RFQ Qualifying Single No No 19-02-18 09-03-18 4 Boreholes Open criteria stage one Envelope W.1.0 Supply and Installation of 50,000 National- Qualifying Single 5 Solar Power Units 5 No Post Open RFQ criteria stage one Envelope No No 05-03-18 15-05-18 5 Sr. No Contract Description QTY Unit Est. Cost Review by Market Selection Evaluatio Procurem Prequali- Domestic Expected Expected (US$) Bank Approach Method n Options ent fication Preferenc date of date of (Prior/ Process ( (Yes/ No) e (Yes/No) bid/ Contract Post) proposal Signature opening W.1.0 Rehabilitation/maintenance National- Qualifying Single 6 of PIU Office 1 No 100,000.00 Post Open RFQ criteria stage one No No 25-06-17 15-08-17 Envelope W.1.0 Installation of Electricity in 5 No 50,000 Post National- RFQ Qualifying Single 9 Production sites Open criteria stage one No No 25-06-17 15-08-17 Envelope W.1.1 Construction of Rural 5 No 800,000.00 Post National- RFQ Qualifying Single No No 0 Warehouses Open criteria stage one 14-02-18 25-04-18 Envelope 2,990,000.00 CONSULTANCY Sr. No Contract Description QTY Un Est. Cost Revie Market Selection Evaluatio Procure Prequali- Domestic Expected Expected it (US$) w by Approach Method n Options ment fication Preferenc date of bid/ date of “000” Bank Process (Yes/ No) e proposal Contract (Prio (Yes/No) opening Signature r/ Post) C.1.01 Consultancy to deliver capacity 2 No 1,500,000.00 Prior Internation RFB Rated Single building support to POs (Farmer Apex al Open Stage No No 16-07-17 30-09-17 Organization) Two Envelope C.1.02 Consultancy to Assess and Select 1 No 300,000.00 Post National- Single No No 30-07-17 15-09-17 Viable business proposals Shortlisting QCBS Rated Stage Two Envelope C.1.03 Technical Assistance to POs to Post National Rated Single No No 17-07-17 30-09-17 improve production and management 10 No 500,000.00 Shortlisting QCBS Stage Two Envelope Consultancy to develop Project 1 No 30,000.00 Post National Rated Single No No 17-07-17 30-08-17 Implementation Manual (PIM) Shortlisting CQS Stage Two Envelope 6 Sr. No Contract Description QTY Un Est. Cost Revie Market Selection Evaluatio Procure Prequali- Domestic Expected Expected it (US$) w by Approach Method n Options ment fication Preferenc date of bid/ date of “000” Bank Process (Yes/ No) e proposal Contract (Prio (Yes/No) opening Signature r/ Post) C.1.04 Detailed Survey, Design and National Single No No Supervision of 5 No 300,000.00 Post Shortlisting QCBS Rated Stage 15-07-17 30-09-17 construction/rehabilitation of Irrigation Two Infrastructure Envelope C.1.05 Detailed Survey, Design and National Single No No Supervision of 1 No 200,000.00 Post Shortlisting QCBS Rated Stage 15-07-17 30-09-17 construction/rehabilitation of access Two roads Envelope C.106 Detailed Design and Supervision of 1 Single No No Rehabilitation/construction of water No 100,000.00 Post National CQS Rated Stage 30-07-17 15-09-17 facilities Shortlisting Two Envelope C.1.07 Detailed Design and Supervision of Single No No Rehabilitation/construction of 1 No 50,000.00 Post National CQS Rated Stage 30-07-17 15-09-17 electricity facilities Shortlisting Two Envelope C.1.08 Technical Assistance in Land Single No No Management (MITC) 1 No 100,000.00 Post Open CQS Rated Stage 10-08-17 26-10-17 Internation Two al Envelope C.1.09 Technical Assistance for Land Titling Single No No (Ministry of Lands) 1 No 100,000.00 Post Open CQS Rated Stage 10-08-17 26-10-17 Internation Two al Envelope C.1.10 Technical Assistance for SMEs 1 No Single No No Capacity building 100,000.00 Post Open CQS Rated Stage 10-08-17 26-10-17 Internation Two al Envelope C.1.11 Consultancy for Designs and 1 No 200,000.00 Post Single No No Construction Supervision of Rural National QCBS Rated Stage 30-10-17 15-01-18 Warehouses Shortlisting Two Envelope C.1.12 Procurement of PIU Staff (Project 11 No 600,000.00 Post National QCBS Rated Single No No 06-06-17 03-08-17 Coordinator, FM, Procurement, M&E, Stage Environmental etc) Two Envelope C.1.13 Training and Workshops Variou No 150,000.00 Post Open QCBS Rated Single No No 07-08-17 01-09-17 s National Stage 7 Sr. No Contract Description QTY Un Est. Cost Revie Market Selection Evaluatio Procure Prequali- Domestic Expected Expected it (US$) w by Approach Method n Options ment fication Preferenc date of bid/ date of “000” Bank Process (Yes/ No) e proposal Contract (Prio (Yes/No) opening Signature r/ Post) Two Envelope C.1.14 Technical Assistance to review 1 No 80,000.00 Post Open Least Rated Single No No 02-08-17 08-10-17 regulatory and technical issues (MITC) Internation Cost Stage al Bases Two Selection Envelope Consultancy on Investor Survey and 1 No 200,000.00 Post Single No No Demand Assessment National QCBS Rated Stage 30-10-17 15-01-18 Shortlisting Two Envelope 4,520,000.00 Appendix-1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, 8 collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross- debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 9 otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 10 Title of the person signing the Letter: 11 PROCUREMENT Malawi : Malawi Agricultural Commercialization Project PLAN General Information Country: Malawi Bank’s Approval Date of the Original Procurement Plan: 2018-04-03 2020-08-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158434 GPN Date: Project Name: Malawi Agricultural Commercialization Project Loan / Credit No: IDA / 60480 Executing Agency(ies): Ministry of Agriculture, Irrigation and Water Development WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MW-MOAIWD-70900-CW- COMPONENT 4: PROJECT Request for Single Stage - One RFQ / Partitioning and IDA / 60480 COORDINATION AND Post Limited 30,000.00 0.00 Canceled 2018-10-02 2018-11-27 2019-01-26 Quotations Envelope maintenance of offices MANAGEMENT MW-MOAIWD-70981-CW- COMPONENT 4: PROJECT Request for Single Stage - One RFQ / Rehabilitation of IDA / 60480 COORDINATION AND Post Limited 42,000.00 0.00 Canceled 2018-09-24 2018-11-19 2019-01-18 Quotations Envelope office access road MANAGEMENT MW-MOAIWD-148222-CW- RFB / Rehabilitation of Irrigation Schemes under COMPONENT 3: Contingency Emergency Under CONTINGENT Single Stage - One Response in Chikhwawa, IDA / 60480 Post Request for Bids Limited 6,550,000.00 0.00 Implementat 2019-12-06 2019-12-30 2019-12-10 2019-12-31 2019-12-31 2020-01-24 2020-01-07 2020-01-31 2020-01-24 2020-10-20 EMERGENCY RESPONSE Envelope Nsanje, Machinga, Zomba, ion COMPONENT (CERC) Phalombe, Mulanje, Chiradzulu, Thyolo and Dedza MW-MOAIWD-148241-CW- RFB / Rehabilitation of Roads and Bridges under COMPONENT 3: Contingency Emergency Under CONTINGENT Single Stage - One Response in Chiradzulu, IDA / 60480 Post Request for Bids Limited 4,550,000.00 0.00 Implementat 2019-12-06 2019-12-30 2019-12-10 2019-12-31 2019-12-31 2020-01-21 2020-01-07 2020-01-31 2020-01-24 2020-02-05 EMERGENCY RESPONSE Envelope Chikhwawa, Thyolo, ion COMPONENT (CERC) Phalombe, Mulanje, Zomba, Balaka, Machinga, Ntcheu and Dedza Districts MW-MOAIWD-162995-CW- COMPONENT 4: PROJECT Under RFB / Completion of Single Stage - One IDA / 60480 COORDINATION AND Post Request for Bids Open - National 450,000.00 0.00 Implementat 2020-03-22 2020-03-15 2020-03-27 2020-04-01 2020-04-26 2020-05-06 2020-05-27 2020-08-25 Forestry building to house Envelope MANAGEMENT ion AGCOM offices GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-70912-GO- RFQ / Supply of IT COMPONENT 2: SUPPORT Under equipment for PIU and Request for Single Stage - One IDA / 60480 INVESTMENT ENABLING Post Limited 90,000.00 0.00 Implementati 2018-08-28 2019-05-03 2018-10-23 2019-01-21 Ministry of Lands, air Quotations Envelope SERVICES on conditioners for PIU and GPS for Ministry of Lands Page 1 MW-MOAIWD-71411-GO- RFQ / Supply of office COMPONENT 2: SUPPORT Request for Single Stage - One furniture for PIU and IDA / 60480 INVESTMENT ENABLING Post Limited 65,000.00 18,371.87 Signed 2018-09-04 2019-05-03 2018-11-06 2019-05-23 2018-12-18 Quotations Envelope Ministry of Lands and SERVICES kitchen utensils for PIU COMPONENT 4: PROJECT Under MW-MOAIWD-69332-GO- Request for Single Stage - One IDA / 60480 COORDINATION AND Post Limited 1,500.00 0.00 Implementati 2018-08-16 2018-06-18 2018-08-16 2018-08-16 RFQ / Office furniture Quotations Envelope MANAGEMENT on MW-MOAIWD-72209-GO- RFQ / Procurement and COMPONENT 4: PROJECT Request for Single Stage - One installation of an accounting, IDA / 60480 COORDINATION AND Post Limited 37,000.00 0.00 Canceled 2018-08-26 2018-10-28 2019-04-26 Quotations Envelope procurement and M&E MANAGEMENT software MW-MOAIWD-72207-GO- COMPONENT 4: PROJECT Request for Single Stage - One RFQ / Supply of backup IDA / 60480 COORDINATION AND Post Limited 15,000.00 13,957.38 Signed 2018-08-16 2018-07-19 2018-08-16 2018-08-03 2018-08-16 Quotations Envelope diesel generator MANAGEMENT MW-MOAIWD-69328-GO- COMPONENT 2: SUPPORT Single Stage - One RFB / Supply of motor IDA / 60480 INVESTMENT ENABLING Post Request for Bids Open - National 1,000,000.00 1,065,768.34 Signed 2018-11-23 2018-11-14 2018-11-23 2018-11-30 2018-12-14 2018-12-14 2019-01-10 2019-02-22 2019-02-07 2019-04-02 2019-03-21 Envelope vehicles SERVICES MW-MOAIWD-72209-GO- COMPONENT 4: PROJECT RFQ-2 / Supply and IDA / 60480 COORDINATION AND Post Direct Selection Direct 37,000.00 62,667.50 Signed 2019-04-05 2019-04-11 2019-04-10 2019-04-03 2019-05-29 2019-07-01 2019-11-25 Installation of an Accounting MANAGEMENT Software MW-MOAIWD-133740-GO- RFB / Supply, Delivery, COMPONENT 2: SUPPORT Under Open - Single Stage - One Installation and IDA / 60480 INVESTMENT ENABLING Post Request for Bids 600,000.00 0.00 Implementati 2019-09-25 2019-11-04 2019-09-30 2019-11-05 2019-11-11 2019-12-02 2020-01-06 2020-03-02 International Envelope Commissioning of Testing SERVICES on Equipment MW-MOAIWD-133751-GO- RFB / Digitisation of Old COMPONENT 2: SUPPORT Under Records, Design, Supply, Open - Single Stage - One IDA / 60480 INVESTMENT ENABLING Post Request for Bids 660,000.00 0.00 Implementati 2019-09-27 2019-12-02 2019-10-02 2019-12-02 2019-11-13 2020-01-24 2019-12-13 2020-02-14 2020-01-17 2020-07-15 Installation, Test Run and International Envelope SERVICES on Commissioning of Malawi Business Registration System MW-MOAIWD-70183-GO- RFQ / Supply of calendars, COMPONENT 2: SUPPORT Under Request for Single Stage - One diaries, executive note pads IDA / 60480 INVESTMENT ENABLING Post Limited 15,000.00 0.00 Implementati 2019-11-27 2019-11-18 2020-01-11 2020-02-08 Quotations Envelope and leaflets and publishing SERVICES on of trade reforms MW-MOAIWD-72825-GO- COMPONENT 2: SUPPORT Pending Single Stage - One RFQ / Supply field IDA / 60480 INVESTMENT ENABLING Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-01-20 2020-01-25 2020-03-07 2020-04-06 2020-05-11 2020-11-07 Envelope equipment SERVICES on MW-MOAIWD-72645-GO- COMPONENT 2: SUPPORT Pending RFQ / Supply of office Request for Single Stage - One IDA / 60480 INVESTMENT ENABLING Post Limited 20,000.00 0.00 Implementati 2019-11-30 2020-01-25 2020-02-22 furniture for Ministry of Quotations Envelope SERVICES on Lands MW-MOAIWD-133766-GO- COMPONENT 1: DIR / Supply and Delivery IDA / 60480 BUILDING PRODUCTIVE Post Direct Selection Direct 365,000.00 367,292.71 Signed 2019-11-08 2019-11-19 2019-11-13 2019-11-19 2019-12-18 2019-11-24 2020-01-29 of Motor Vehicles ALLIANCES MW-MOAIWD-145149-GO- COMPONENT 2: SUPPORT Pending RFQ / Supply and Delivery Request for Single Stage - One IDA / 60480 INVESTMENT ENABLING Post Limited 92,000.00 0.00 Implementati 2019-11-23 2020-01-04 2020-01-05 of Office and Field Quotations Envelope SERVICES on Equipment Page 2 MW-MOAIWD-145150-GO- COMPONENT 2: SUPPORT Under Request for Single Stage - One RFQ / Supply and Deliver of IDA / 60480 INVESTMENT ENABLING Post Limited 44,000.00 0.00 Implementati 2019-11-30 2020-01-25 2020-03-25 Quotations Envelope Exhibition Booths SERVICES on MW-MOAIWD-145986-GO- COMPONENT 4: PROJECT Pending RFQ / Supply and delivery Request for Single Stage - One IDA / 60480 COORDINATION AND Post Limited 1,100.00 0.00 Implementati 2019-12-01 2020-01-26 2020-02-09 of Fridge and Water Quotations Envelope MANAGEMENT on Dispenser MW-MOAIWD-145959-GO- COMPONENT 4: PROJECT Pending Request for Single Stage - One RFQ / Supply and delivery IDA / 60480 COORDINATION AND Post Limited 520.00 0.00 Implementati 2019-12-01 2020-01-26 2020-02-09 Quotations Envelope of Cash Chest MANAGEMENT on MW-MOAIWD-70901-GO- COMPONENT 2: SUPPORT Request for Single Stage - One RFQ / Supply of office IDA / 60480 INVESTMENT ENABLING Post Limited 60,000.00 0.00 Canceled 2018-09-12 2018-11-14 2019-05-13 Quotations Envelope supplies SERVICES MW-MOAIWD-148310-GO- COMPONENT 2: SUPPORT RFB / Supply and Delivery Open - Single Stage - One IDA / 60480 INVESTMENT ENABLING Prior Request for Bids 7,000,000.00 0.00 Canceled 2019-12-08 2019-12-13 2019-12-27 2020-01-03 2020-01-24 2020-02-21 of Maize Under Contingency International Envelope SERVICES Emergency Response MW-MOAIWD-168488-GO- COMPONENT 3: RFB / Supply and Delivery CONTINGENT Single Stage - One IDA / 60480 Prior Request for Bids Limited 7,000,000.00 6,452,071.39 Signed 2020-04-17 2020-04-22 2020-04-22 2020-05-11 2020-04-29 2020-05-04 2020-05-13 2020-06-01 2020-05-27 2020-06-04 2020-06-26 of Maize for Strategic Grain EMERGENCY RESPONSE Envelope Reserve COMPONENT (CERC) MW-MOAIWD-151661-GO- COMPONENT 3: RFB / Supply and Delivery CONTINGENT Open - Single Stage - One IDA / 60480 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-12-30 2019-12-27 2020-01-04 2019-12-27 2020-01-25 2020-01-20 2020-02-01 2020-03-25 2020-02-22 2020-03-23 of Maize Under Contingency EMERGENCY RESPONSE International Envelope Emergency Response COMPONENT (CERC) MW-MOAIWD-151669-GO- COMPONENT 3: RFB / Supply and Delivery CONTINGENT Open - Single Stage - One of Maize Flour Under IDA / 60480 Prior Request for Bids 3,500,000.00 0.00 Canceled 2019-12-30 2019-12-28 2020-01-04 2020-01-02 2020-01-25 2020-01-20 2020-02-01 2020-02-22 2020-03-23 EMERGENCY RESPONSE International Envelope Contingency Emergency COMPONENT (CERC) Response MW-MOAIWD-181884-GO- RFB / Design, Supply, COMPONENT 2: SUPPORT Under Installation and Open - Single Stage - One IDA / 60480 INVESTMENT ENABLING Post Request for Bids 1,600,000.00 0.00 Implementati 2020-07-17 2020-07-13 2020-07-22 2020-07-13 2020-09-02 2020-10-02 2020-11-06 2022-07-07 Commissioning of Land International Envelope SERVICES on Information Management System (LIMS) MW-MOAIWD-185992-GO- RFQ / Supply and delivery COMPONENT 2: SUPPORT Pending Request for Single Stage - One of Personal Protective IDA / 60480 INVESTMENT ENABLING Post Limited 20,000.00 0.00 Implementati 2020-08-14 2020-09-25 2020-10-25 Quotations Envelope Equipment and IEC SERVICES on Materials NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMPONENT 4: PROJECT MW-MOAIWD-70189-NC- Request for Single Stage - One IDA / 60480 COORDINATION AND Post Limited 7,500.00 0.00 Canceled 2018-09-10 2018-11-05 2019-11-05 RFQ / Cleaning services Quotations Envelope MANAGEMENT MW-MOAIWD-88487-NC- COMPONENT 4: PROJECT Request for Single Stage - One RFQ / Office rental for IDA / 60480 COORDINATION AND Post Limited 20,000.00 13,886.59 Signed 2018-12-08 2018-11-22 2019-01-06 2019-01-01 2020-01-06 Quotations Envelope AGCOM PIU MANAGEMENT Page 3 COMPONENT 4: PROJECT MW-MOAIWD-69316-NC- Request for Single Stage - One IDA / 60480 COORDINATION AND Post Limited 20,000.00 0.00 Canceled 2018-08-15 2018-08-08 2018-09-24 2019-09-24 RFQ / security services Quotations Envelope MANAGEMENT CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOAIWD-71331-CS- QCBS / Consultancy to COMPONENT 2: SUPPORT Quality And Cost- developing an IT IDA / 60480 INVESTMENT ENABLING Post Open - National 50,000.00 100,854.00 Signed 2018-09-04 2019-01-29 2018-09-25 2019-02-06 2018-11-08 2019-04-17 2018-12-06 2019-05-17 2019-01-05 2019-06-07 2019-02-09 2019-07-19 2019-03-16 2019-10-03 2020-03-15 Based Selection system/database to receive SERVICES land survey data MW-MOAIWD-71303-CS- QCBS / Consultancy to COMPONENT 2: SUPPORT Quality And Cost- conduct impact assessment IDA / 60480 INVESTMENT ENABLING Post Open - National 150,000.00 0.00 Canceled 2018-08-22 2018-12-11 2018-09-12 2019-02-06 2018-10-26 2019-04-17 2018-11-23 2019-05-17 2018-12-23 2019-06-07 2019-01-27 2019-07-19 2019-03-03 2019-08-30 Based Selection on customary estate SERVICES registration MW-MOAIWD-71169-CS- QCBS / Consultancy to COMPONENT 2: SUPPORT design, develop and Quality And Cost- IDA / 60480 INVESTMENT ENABLING Post Open - National 60,000.00 0.00 Canceled 2018-08-29 2019-01-18 2018-09-19 2019-02-06 2018-11-02 2019-04-23 2018-11-30 2018-12-30 2019-02-03 2019-03-10 2020-03-09 operationalise Land Based Selection SERVICES Information Management System MW-MOAIWD-73239-CS- COMPONENT 1: Consultant Open - CQS / Agent to Manage IDA / 60480 BUILDING PRODUCTIVE Prior Qualification 240,000.00 0.00 Canceled 2018-08-14 2018-08-16 2018-08-21 2018-08-17 2018-09-02 2018-10-02 2018-10-14 2022-10-13 International Partial Credit Guarantee ALLIANCES Selection Fund MW-MOAIWD-78875-CS- COMPONENT 1: QCBS / Agent to Manage Quality And Cost- Open - IDA / 60480 BUILDING PRODUCTIVE Prior 240,000.00 0.00 Canceled 2018-09-21 2018-09-21 2018-09-28 2018-10-19 2018-10-26 2018-11-26 2018-11-05 2019-06-18 2018-11-26 2018-12-10 2022-12-09 Partial Credit Guarantee Based Selection International ALLIANCES Fund MW-MOAIWD-70984-CS- COMPONENT 4: PROJECT Quality And Cost- Open - Under QCBS / Consultancy to IDA / 60480 COORDINATION AND Post 340,000.00 0.00 2019-01-09 2019-03-19 2019-01-30 2019-05-18 2019-03-15 2019-10-14 2019-04-12 2019-05-12 2019-06-16 2019-07-21 2019-10-19 Based Selection International Implementation conduct baseline survey MANAGEMENT MW-MOAIWD-71165-CS- QCBS / Consultancy to COMPONENT 1: Quality And Cost- Open - Under study structured markerts IDA / 60480 BUILDING PRODUCTIVE Post 205,000.00 0.00 2019-01-08 2019-09-27 2019-01-29 2019-11-04 2019-03-14 2019-04-11 2019-05-11 2019-06-15 2019-07-20 2020-01-16 Based Selection International Implementation and Malawian warehouse ALLIANCES receipt system MW-MOAIWD-69321-CS- QCBS / Consultancy to COMPONENT 2: SUPPORT Quality And Cost- Open - strengthen the capacity of IDA / 60480 INVESTMENT ENABLING Post 300,000.00 401,076.00 Signed 2019-01-16 2018-12-10 2019-01-23 2019-02-06 2019-03-06 2019-04-17 2019-04-20 2019-05-17 2019-05-11 2019-05-30 2019-06-15 2019-07-08 2019-07-13 2019-10-13 2020-07-12 Based Selection International stakeholders in land SERVICES administration MW-MOAIWD-123002-CS- COMPONENT 1: QCBS / Broker for Capacity Quality And Cost- Open - Under IDA / 60480 BUILDING PRODUCTIVE Post 400,000.00 0.00 2019-07-22 2019-07-19 2019-08-12 2019-07-25 2019-09-25 2019-11-20 2019-10-23 2020-01-17 2019-11-22 2020-01-31 2019-12-27 2020-01-31 2023-01-30 Building of Productive Based Selection International Implementation ALLIANCES alliances MW-MOAIWD-70977-CS- COMPONENT 1: Quality And Cost- QCBS / Consultancy to IDA / 60480 BUILDING PRODUCTIVE Post Open - National 82,000.00 0.00 Canceled 2018-09-07 2018-09-28 2018-11-11 2018-12-09 2019-01-08 2019-02-12 2019-03-19 2019-09-15 Based Selection conduct value chain analysis ALLIANCES Page 4 MW-MOAIWD-145988-CS- QCBS / Consultancy Services COMPONENT 3: for construction supervision CONTINGENT Quality And Cost- Under for Road and Bridge works IDA / 60480 Post Open - National 198,000.00 0.00 2019-11-27 2019-12-04 2019-12-11 2019-12-28 2020-01-15 2020-02-05 2020-02-26 2020-03-25 2020-04-22 2020-10-19 EMERGENCY RESPONSE Based Selection Implementation on access roads to selected COMPONENT (CERC) irrigation schemes in central and southern regions MW-MOAIWD-145992-CS- QCBS / Consultancy Services COMPONENT 3: for construction supervision CONTINGENT Quality And Cost- Under for Road and Bridge works IDA / 60480 Post Open - National 220,000.00 0.00 2019-11-27 2019-12-04 2019-12-11 2019-12-28 2020-01-15 2020-02-05 2020-02-26 2020-03-25 2020-04-22 2020-10-19 EMERGENCY RESPONSE Based Selection Implementation on access roads to selected COMPONENT (CERC) irrigation schemes in southern region MW-MOAIWD-148303-CS- LCS / Consultancy Services COMPONENT 3: for construction supervision CONTINGENT Least Cost Pending IDA / 60480 Post Open - National 150,000.00 0.00 2019-12-08 2019-12-15 2020-01-05 2020-01-19 2020-01-26 2020-02-16 2020-03-08 2020-12-03 of irrigation scheme EMERGENCY RESPONSE Selection Implementation rehabilitation in Chikhwawa COMPONENT (CERC) and Nsanje Districts MW-MOAIWD-148306-CS- LCS / Consultancy Services COMPONENT 3: for construction supervision CONTINGENT Least Cost Under of irrigation scheme IDA / 60480 Post Open - National 150,000.00 0.00 2019-12-08 2020-04-02 2019-12-15 2020-05-14 2020-01-05 2020-01-19 2020-01-26 2020-02-16 2020-03-08 2020-12-03 EMERGENCY RESPONSE Selection Implementation rehabilitation in Phalombe, COMPONENT (CERC) Mulanje, Thyolo and Chiradzulu Districts MW-MOAIWD-148309-CS- LCS / Consultancy Services COMPONENT 3: for construction supervision CONTINGENT Least Cost Pending IDA / 60480 Post Open - National 150,000.00 0.00 2019-12-08 2019-12-15 2020-01-05 2020-01-19 2020-01-26 2020-02-16 2020-03-08 2020-12-03 of irrigation scheme EMERGENCY RESPONSE Selection Implementation rehabilitation in Machinga, COMPONENT (CERC) Zomba and Dedza Districts MW-MOAIWD-163474-CS- CQS / Consultancy to Undertake a Scoping Study, COMPONENT 2: SUPPORT Consultant Under Development of a Policy and IDA / 60480 INVESTMENT ENABLING Post Qualification Open - National 30,000.00 0.00 2020-04-12 2020-04-23 2020-04-17 2020-05-14 2020-05-16 2020-05-23 2020-06-11 2020-09-09 Implementation Legislation for Structured SERVICES Selection Markets for Strategic Agriculture Commodities MW-MOAIWD-170380-CS- QCBS / Supervision of COMPONENT 4: PROJECT Quality And Cost- Under construction of forestry IDA / 60480 COORDINATION AND Post Open 30,000.00 0.00 2020-05-03 2020-07-28 2020-05-08 2020-05-27 2020-06-26 2020-07-01 2020-07-15 2020-08-03 2020-11-01 Based Selection Implementation building to house AGCOM MANAGEMENT offices MW-MOAIWD-173273-CS- QCBS / Consultancy to COMPONENT 2: SUPPORT conduct Baseline Survey for Quality And Cost- Open - IDA / 60480 INVESTMENT ENABLING Post 250,000.00 0.00 Under Review 2020-05-25 2020-07-17 2020-06-08 2020-06-22 2020-07-22 2020-08-01 2020-08-29 2020-09-19 2020-12-03 Impact Evaluation of Pilot Based Selection International SERVICES Systematic Adjudication of Customary Estates MW-MOAIWD-175959-CS- COMPONENT 4: PROJECT Consultant CQS / Development and Under IDA / 60480 COORDINATION AND Post Qualification Limited 21,000.00 0.00 2020-06-08 2020-06-04 2020-06-22 2020-07-02 2020-07-21 2020-09-19 management of project Implementation MANAGEMENT Selection website INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 COMPONENT 4: PROJECT Individual MW-MOAIWD-56971-CS- IDA / 60480 COORDINATION AND Prior Consultant Open 90,000.00 152,234.93 Signed 2018-04-03 2018-04-05 2018-04-20 2018-04-16 2018-04-30 2018-08-31 2018-05-17 2018-06-30 2019-05-12 INDV / Project Coordinator MANAGEMENT Selection MW-MOAIWD-56612-CS- COMPONENT 4: PROJECT Individual INDV / Financial IDA / 60480 COORDINATION AND Prior Consultant Open 72,000.00 103,648.01 Signed 2018-04-03 2018-04-05 2018-04-20 2018-04-16 2018-04-30 2018-08-31 2018-05-17 2018-07-01 2019-05-12 Management Specialist, MANAGEMENT Selection MW-MOAIWD-56977-CS- COMPONENT 4: PROJECT Individual INDV / Procurement IDA / 60480 COORDINATION AND Prior Consultant Open 60,000.00 97,168.85 Signed 2018-04-03 2018-04-05 2018-04-20 2018-04-16 2018-04-30 2018-08-31 2018-05-17 2018-06-30 2019-05-12 Specialist MANAGEMENT Selection MW-MOAIWD-56975-CS- COMPONENT 4: PROJECT Individual INDV / Monitoring and IDA / 60480 COORDINATION AND Prior Consultant Open 60,000.00 91,602.60 Signed 2018-04-03 2018-08-31 2018-04-20 2018-04-16 2018-04-30 2019-08-08 2018-05-17 2018-06-30 2019-05-12 Evaluation Specialist MANAGEMENT Selection MW-MOAIWD-72412-CS- COMPONENT 4: PROJECT Individual INDV / Communication IDA / 60480 COORDINATION AND Prior Consultant Open 42,000.00 0.00 Canceled 2018-08-30 2018-11-05 2018-10-18 2018-11-08 2018-12-13 2019-12-13 Specialist MANAGEMENT Selection MW-MOAIWD-72419-CS- COMPONENT 4: PROJECT Individual INDV / Agri business IDA / 60480 COORDINATION AND Prior Consultant Open 42,000.00 0.00 Canceled 2018-08-30 2018-11-05 2018-10-18 2018-11-08 2018-12-13 2019-12-13 Specialist MANAGEMENT Selection MW-MOAIWD-72646-CS- COMPONENT 4: PROJECT Individual INDV / Institutional IDA / 60480 COORDINATION AND Prior Consultant Open 42,000.00 0.00 Canceled 2018-08-30 2018-12-03 2018-10-18 2018-11-08 2018-12-13 2019-12-13 Development Specialist MANAGEMENT Selection MW-MOAIWD-72641-CS- COMPONENT 4: PROJECT Individual INDV / Resilience and IDA / 60480 COORDINATION AND Prior Consultant Open 42,000.00 0.00 Canceled 2018-08-30 2018-11-23 2018-10-18 2018-11-08 2018-12-13 2019-12-13 CSA/Environmental Specialist MANAGEMENT Selection MW-MOAIWD-72648-CS- COMPONENT 4: PROJECT Individual INDV / Social Development IDA / 60480 COORDINATION AND Prior Consultant Open 42,000.00 0.00 Canceled 2018-08-30 2018-11-05 2018-10-18 2018-11-08 2018-12-13 2019-12-13 Specialist MANAGEMENT Selection MW-MOAIWD-72979-CS- COMPONENT 4: PROJECT Individual INDV / Trade Facilitation IDA / 60480 COORDINATION AND Prior Consultant Open 42,000.00 0.00 Canceled 2018-08-30 2018-12-03 2018-10-18 2018-11-08 2018-12-13 2019-12-13 Specialist MANAGEMENT Selection MW-MOAIWD-85374-CS- COMPONENT 2: SUPPORT Individual INDV / Land Surveying / IDA / 60480 INVESTMENT ENABLING Post Consultant Open 42,000.00 49,016.16 Signed 2018-11-13 2018-11-20 2018-12-23 2019-09-16 2019-01-06 2019-09-17 2019-02-03 2019-10-24 2020-02-03 GIS Specialist SERVICES Selection MW-MOAIWD-72408-CS- COMPONENT 4: PROJECT Individual Under INDV / Irrigation/Civil IDA / 60480 COORDINATION AND Post Consultant Open 42,000.00 0.00 2019-04-30 2019-10-28 2019-06-18 2019-07-09 2019-08-13 2020-08-12 Implementation Engineer MANAGEMENT Selection MW-MOAIWD-88473-CS- COMPONENT 4: PROJECT Individual INDV / Assistant Financial IDA / 60480 COORDINATION AND Post Consultant Open 25,000.00 39,212.93 Signed 2018-12-12 2019-03-27 2019-01-21 2019-09-16 2019-02-04 2019-10-01 2019-03-11 2019-10-01 2020-03-10 Management Specialist MANAGEMENT Selection MW-MOAIWD-88475-CS- COMPONENT 4: PROJECT Individual INDV / Senior IDA / 60480 COORDINATION AND Post Consultant Open 18,000.00 1,361.43 Signed 2018-12-12 2018-12-11 2019-01-21 2019-09-16 2019-02-11 2019-09-18 2019-03-18 2019-10-01 2020-03-17 Administrative Assistant MANAGEMENT Selection MW-MOAIWD-88476-CS- COMPONENT 4: PROJECT Individual INDV / ICT / Monitoring IDA / 60480 COORDINATION AND Post Consultant Open 25,200.00 0.00 Canceled 2018-12-12 2018-12-11 2019-01-21 2019-02-11 2019-03-18 2020-03-17 and Evaluation Officer MANAGEMENT Selection MW-MOAIWD-89366-CS- COMPONENT 4: PROJECT Individual INDV / Communication IDA / 60480 COORDINATION AND Post Consultant Open 42,000.00 45,747.74 Signed 2018-12-06 2018-12-06 2019-01-22 2019-04-16 2019-02-12 2019-06-17 2019-03-19 2019-08-12 2020-03-18 Specialist MANAGEMENT Selection Page 6 MW-MOAIWD-89371-CS- COMPONENT 4: PROJECT Individual INDV / Social Development IDA / 60480 COORDINATION AND Post Consultant Open 42,000.00 45,747.74 Signed 2018-12-06 2018-12-06 2019-01-22 2019-04-16 2019-02-12 2019-04-18 2019-03-19 2019-05-06 2020-03-18 Specialist MANAGEMENT Selection MW-MOAIWD-89375-CS- COMPONENT 4: PROJECT Individual INDV / Trade Facilitation IDA / 60480 COORDINATION AND Post Consultant Open 42,000.00 45,747.74 Signed 2018-12-06 2018-12-06 2019-01-22 2019-04-16 2019-02-12 2019-04-30 2019-03-19 2019-05-06 2020-03-18 Specialist MANAGEMENT Selection MW-MOAIWD-89376-CS- COMPONENT 4: PROJECT Individual INDV / Agri Business IDA / 60480 COORDINATION AND Post Consultant Open 42,000.00 45,747.74 Signed 2018-12-06 2018-12-06 2019-01-22 2019-05-12 2019-02-12 2019-05-31 2019-03-19 2019-06-30 2020-03-18 Specialist MANAGEMENT Selection MW-MOAIWD-89377-CS- COMPONENT 4: PROJECT Individual INDV / Environmental IDA / 60480 COORDINATION AND Post Consultant Open 42,000.00 45,747.74 Signed 2018-12-06 2018-12-06 2019-01-22 2019-04-16 2019-02-12 2019-04-18 2019-03-19 2019-06-03 2020-03-18 Safeguards Specialist MANAGEMENT Selection MW-MOAIWD-89378-CS- COMPONENT 4: PROJECT Individual INDV / Institutional IDA / 60480 COORDINATION AND Post Consultant Open 42,000.00 45,747.74 Signed 2018-12-06 2018-12-06 2019-01-22 2019-04-16 2019-02-12 2019-04-18 2019-03-19 2019-06-03 2020-03-18 Development Specialist MANAGEMENT Selection MW-MOAIWD-95429-CS- COMPONENT 2: SUPPORT Individual INDV / Team Leader for the Under IDA / 60480 INVESTMENT ENABLING Prior Consultant Direct 324,500.00 0.00 2019-01-25 2019-02-06 2019-02-04 2019-02-08 2019-02-18 2019-11-14 2019-03-18 2023-05-31 Land Reforms Implementation SERVICES Selection Implementation Unit MW-MOAIWD-95487-CS- INDV / IT and Database COMPONENT 2: SUPPORT Individual Administration Specialist for IDA / 60480 INVESTMENT ENABLING Post Consultant Direct 160,378.00 67,715.52 Signed 2019-01-25 2019-01-23 2019-02-04 2019-02-08 2019-02-18 2019-03-25 2019-03-18 2019-03-28 2023-05-31 the Land Reforms SERVICES Selection Implementation Unit MW-MOAIWD-95514-CS- INDV / Assistant COMPONENT 2: SUPPORT Individual Communication Specialist for IDA / 60480 INVESTMENT ENABLING Post Consultant Direct 160,378.00 39,220.99 Signed 2019-01-25 2019-01-23 2019-02-04 2019-02-08 2019-02-18 2019-03-25 2019-03-18 2019-02-28 2023-05-31 the Land Reforms SERVICES Selection Implementation Unit MW-MOAIWD-88476-CS- COMPONENT 4: PROJECT Individual INDV-2 / ICT IDA / 60480 COORDINATION AND Post Consultant Open 25,250.00 45,748.42 Signed 2019-04-05 2019-04-04 2019-05-24 2019-09-16 2019-06-14 2019-09-18 2019-07-19 2019-10-24 2020-07-18 Expert/Specialist MANAGEMENT Selection MW-MOAIWD-113712-CS- COMPONENT 4: PROJECT Individual INDV / Assistant IDA / 60480 COORDINATION AND Post Consultant Limited 25,000.00 39,212.93 Signed 2019-05-14 2019-05-18 2019-05-28 2019-09-16 2019-06-18 2019-09-18 2019-07-23 2019-10-24 2020-07-22 Procurement Specialist MANAGEMENT Selection MW-MOAIWD-125507-CS- INDV / Quantity Surveyor to Quantify Remaining COMPONENT 4: PROJECT Individual Works and Supervise IDA / 60480 COORDINATION AND Post Consultant Limited 20,000.00 0.00 Canceled 2019-08-12 2019-08-09 2019-08-17 2019-09-07 2019-10-12 2020-04-09 Completion Works on MANAGEMENT Selection Government Building to House AGCOM PIU Offices MW-MOAIWD-71160-CS- COMPONENT 2: SUPPORT Individual INDV / Consultancy to IDA / 60480 INVESTMENT ENABLING Post Consultant Open 100,000.00 0.00 Canceled 2018-12-12 2019-01-30 2019-02-20 2019-03-27 2020-03-26 provide project management SERVICES Selection services MW-MOAIWD-159168-CS- INDV / Consultancy to COMPONENT 2: SUPPORT Individual Undertake Trade, Industry Under IDA / 60480 INVESTMENT ENABLING Post Consultant Open 41,500.00 0.00 2020-02-24 2020-03-06 2020-04-13 2020-05-04 2020-06-08 2020-08-03 and Private Sector Implementation SERVICES Selection Development Sector Performance Review Study MW-MOAIWD-159182-CS- COMPONENT 2: SUPPORT Individual INDV / Consultancy to Under IDA / 60480 INVESTMENT ENABLING Post Consultant Open 24,000.00 0.00 2020-02-24 2020-03-06 2020-04-13 2020-05-04 2020-06-08 2020-08-03 Review National Investment Implementation SERVICES Selection Policy Page 7 MW-MOAIWD-159381-CS- INDV / Individual COMPONENT 2: SUPPORT Individual Consultant to Develop Under IDA / 60480 INVESTMENT ENABLING Post Consultant Open 12,500.00 0.00 2020-02-24 2020-03-06 2020-04-13 2020-05-04 2020-06-08 2020-08-03 Regulations for the Implementation SERVICES Selection Investment and Export Promotion Act MW-MOAIWD-162990-CS- INDV / Consultancy to COMPONENT 3: Individual conduct Environmental and CONTINGENT Under IDA / 60480 Post Consultant Limited 20,000.00 0.00 2020-03-15 2020-04-01 2020-03-20 2020-04-20 2020-04-03 2020-04-22 2020-05-22 Social assessment for EMERGENCY RESPONSE Implementation Selection Nansomba Irrigation Scheme COMPONENT (CERC) in Mulanje District MW-MOAIWD-72981-CS- COMPONENT 4: PROJECT Individual LCS / Development and IDA / 60480 COORDINATION AND Post Consultant Limited 21,000.00 0.00 Canceled 2019-11-27 2020-01-20 2019-12-02 2019-12-23 2020-01-27 2021-01-26 management of project MANAGEMENT Selection website Page 8