PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Senegal : Senegal Inclusive and Sustainable Agribusiness Development Project PLAN General Information Country: Senegal Bank’s Approval Date of the Original Procurement Plan: 2018-02-23 2019-09-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P124018 GPN Date: Project Name: Senegal Inclusive and Sustainable Agribusiness Development Project Loan / Credit No: IDA / 53340 Executing Agency(ies): AGRIBUSINESS DEVELOPMENT PROJECT WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual T-PDIDAS-001-2017 / Component 1: Support to Single Stage - One Travaux de serres de 3000 IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2017-09-04 2017-10-30 2018-04-28 sector actors Envelope m2 à Saint-Louis T-PDIDAS-002-2017 / Component 1: Support to Single Stage - One Travaux de réhabilitation de IDA / 53340 A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2017-08-31 2017-09-05 2017-10-17 2017-11-16 2017-12-21 2018-06-19 sector actors Envelope l'Agropole de MPAL T-PDIDAS-003-2017 / Component 1: Support to Single Stage - One En attente Travaux d'aménagement des IDA / 53340 A posteriori Demande de prix Limited 28,000.00 0.00 2017-09-10 2017-11-05 2018-05-04 sector actors Envelope d'exécution mares et toufndés T-PDIDAS-004-2017 / Component 1: Support to Single Stage - One En attente Travaux d'aménagement des IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 2017-09-05 2017-10-31 2018-04-29 sector actors Envelope d'exécution pare feu T-PDIDAS-005-2017 / Component 1: Support to Single Stage - One En attente Travaux de matérialisation IDA / 53340 A posteriori Appel d'offres Open - National 220,000.00 0.00 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2018-06-13 sector actors Envelope d'exécution des POAS T-PDIDAS-006-2017 / Travaux de construction des Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 900,000.00 0.00 2016-12-23 2016-12-28 2017-02-08 2017-03-10 2017-04-14 2017-10-11 bureaux fonciers des neuf sector actors Envelope d'exécution communes cibles T-PDIDAS-007-2017 / Component 2: Development Travaux d'aménagement du of irrigation infrastructure Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 340,000.00 0.00 2017-08-14 2017-08-19 2017-09-30 2017-10-30 2017-12-04 2018-06-02 site pilote de Ngnith( and natural resources Envelope d'exécution relance lots1,2 et 3) management T-PDIDAS-011-2017 / Component 2: Development Travaux d'aménagement de of irrigation infrastructure Single Stage - One En attente pépinière communautaire par IDA / 53340 A posteriori Appel d'offres Open - National 160,000.00 0.00 2017-08-14 2017-08-19 2017-09-30 2017-10-30 2017-12-04 2018-06-02 and natural resources Envelope d'exécution forêt ou réserve( clôtures, management points d'eau, magasins etc.) T-PDIDAS-001-2018 / Component 2: Development Travaux du canal du shunt of irrigation infrastructure Open - Single Stage - One En cours IDA / 53340 A priori Appel d'offres 14,257,539.83 0.00 2018-04-09 2018-04-14 2018-05-26 2018-06-25 2018-07-30 2019-01-26 et ouvrages associés dans le and natural resources International Envelope d'exécution cadre du PDIDAS management T-PDIDAS-002-2018 / Travaux de faucardage, de Component 2: Development curage et de génie civil pour of irrigation infrastructure Single Stage - One IDA / 53340 A priori Appel d'offres Open - National 9,468,098.42 11,771,595.66 Signé 2017-12-24 2017-12-29 2018-02-09 2018-03-11 2018-04-15 2018-10-12 la remise en eau du bassin and natural resources Envelope du Ngalam incluant la zone management des trois marigots T-PDIDAS-024-2018 / Travaux de réfection de la Component 1: Support to Single Stage - One En attente salle d'archives du cadastre IDA / 53340 A posteriori Appel d'offres Open - National 100,000.00 0.00 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 2019-02-16 sector actors Envelope d'exécution et domaines de Saint-louis et Louga Component 2: Development T-PDIDAS-025-2018 / of irrigation infrastructure Single Stage - One En attente Travaux des infrastructures IDA / 53340 A posteriori Appel d'offres Open - National 2,200,000.00 0.00 2018-05-07 2018-05-12 2018-06-23 2018-07-23 2018-08-27 2019-02-23 and natural resources Envelope d'exécution d'irrigations secondaires management Component 2: Development T-PDIDAS-026-2018 / of irrigation infrastructure Single Stage - One En attente Travaux d'aménagement du IDA / 53340 A posteriori Appel d'offres Open - National 400,000.00 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 and natural resources Envelope d'exécution site pilote de Ngnith management T-PDIDAS-027-2018 / Travaux d'aménagement de Component 2: Development Pépinière communautaire of irrigation infrastructure Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 300,000.00 0.00 2018-03-28 2018-04-02 2018-05-14 2018-06-13 2018-07-18 2019-01-14 par forêt ou réserve and natural resources Envelope d'exécution (Clôtures, Points d'eau, management Magasins etc.) Page 1 T-PDIDAS-028-2018 / Component 2: Development Travaux de matérialisation of irrigation infrastructure Single Stage - One En attente des limites des forêts et IDA / 53340 A posteriori Appel d'offres Open - National 190,000.00 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2019-01-05 and natural resources Envelope d'exécution réserves (Bornage, management pancartage, etc.) T-PDIDAS-016-2017 / Travaux de construction des Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 900,000.00 0.00 2016-12-22 2016-12-27 2017-02-07 2017-03-09 2017-04-13 2017-10-10 bureaux fonciers des 9 sector actors Envelope d'exécution communes cibles T-PDIDAS-012-2017 / Component 2: Development Travaux de matérialisation of irrigation infrastructure Single Stage - One En attente des limites des forêts et IDA / 53340 A posteriori Appel d'offres Open - National 180,000.00 0.00 2017-08-14 2017-08-19 2017-09-30 2017-10-30 2017-12-04 2018-06-02 and natural resources Envelope d'exécution réserves(Bornage, pancartage management etc.) T-PDIDAS-029-2018 / Réalisation des travaux et de prestations de services de Component 2: Development la parcelle test goutte à of irrigation infrastructure Single Stage - One En attente goutte et d'aspersion par IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2018-07-03 2018-08-28 2019-02-24 and natural resources Envelope d'exécution solaire/Relance du lot 3 du management marché de travaux d'aménagement du site pilote de Gnith T-PDIDAS-001-2019 / Travaux de réfection de la Component 1: Support to Single Stage - One En cours salle d'archives du cadastre IDA / 53340 A posteriori Appel d'offres Open - National 100,000.00 0.00 2019-03-04 2019-03-09 2019-04-20 2019-05-20 2019-06-24 2019-12-21 sector actors Envelope d'exécution et domaines de st-louis et Louga T-PDIDAS-002-2019 / Component 2: Development Travaux du canal du shunt of irrigation infrastructure Open - Single Stage - One En attente IDA / 53340 A priori Appel d'offres 14,000,000.00 0.00 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 et ouvrages associés dans le and natural resources International Envelope d'exécution cadre du PDIDAS management Component 2: Development T-PDIDAS-003-2019 / of irrigation infrastructure Open - Single Stage - One En attente Travaux des infrastructures IDA / 53340 A priori Appel d'offres 16,000,000.00 0.00 2019-04-16 2019-04-21 2019-06-02 2019-07-02 2019-08-06 2020-02-02 and natural resources International Envelope d'exécution secondaires management Component 2: Development T-PDIDAS-004-2019 / of irrigation infrastructure Open - Single Stage - One En attente Travaux des infrastructures IDA / 53340 A priori Appel d'offres 10,000,000.00 0.00 2019-03-12 2019-03-17 2019-04-28 2019-05-28 2019-07-02 2019-12-29 and natural resources International Envelope d'exécution tertiaires management Component 2: Development T-PDIDAS-005-2019 / of irrigation infrastructure Single Stage - One En attente Travaux pour les sous IDA / 53340 A posteriori Appel d'offres Open - National 2,800,000.00 0.00 2019-04-23 2019-04-28 2019-06-09 2019-07-09 2019-08-13 2020-02-09 and natural resources Envelope d'exécution projets de st louis management Component 2: Development T-PDIDAS-006-2019 / of irrigation infrastructure Single Stage - One En attente Travaux pour les sous IDA / 53340 A posteriori Appel d'offres Open - National 1,600,000.00 0.00 2019-04-25 2019-04-30 2019-06-11 2019-07-11 2019-08-15 2020-02-11 and natural resources Envelope d'exécution projets de Louga management T-PDIDAS-008-2019 / Travaux de substitution aux Component 2: Development offres foncières de Yetty of irrigation infrastructure Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 682,000.00 0.00 2019-06-06 2019-06-11 2019-07-23 2019-08-22 2019-09-26 2020-03-24 Yone ,Khatète ,Khelcom and natural resources Envelope d'exécution Diop, Bidieum Mouride et management Gantour du PDIDAS. Component 2: Development T-PDIDAS-009-2019 / of irrigation infrastructure Open - Single Stage - One En cours Travaux des infrastructures IDA / 53340 A priori Appel d'offres 30,246,475.79 0.00 2019-08-16 2019-08-21 2019-10-02 2019-11-01 2019-12-06 2020-06-03 and natural resources International Envelope d'exécution secondaires et tertiaires management GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual F- PDIDAS-002-2017 / Acquisition de matériaux et Component 1: Support to Single Stage - One de matériels pour la mise IDA / 53340 A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2017-07-31 2017-08-05 2017-09-16 2017-10-16 2017-11-20 2018-05-19 sector actors Envelope en place de dispositif anti- corrosif F- PDIDAS-006-2017 / Component 1: Support to Single Stage - One Acquisition de mobilier de IDA / 53340 A posteriori Demande de prix Limited 2,600.00 0.00 Annulé 2017-08-13 2017-10-08 2018-04-06 sector actors Envelope bureau pour l'UEP APIX F- PDIDAS-007-2017 / Component 1: Support to Single Stage - One Acquisition de boutures IDA / 53340 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2017-08-16 2017-10-11 2018-04-09 sector actors Envelope (matériel végétal)pour l'ISRA Page 2 F- PDIDAS-013-2017 / Component 1: Support to Single Stage - One En attente Acquisition de carburant IDA / 53340 A posteriori Demande de prix Limited 10,800.00 0.00 2017-08-07 2017-10-02 2018-03-31 sector actors Envelope d'exécution pour les agents fonciers F- PDIDAS-014-2017 / Acquisition de matériels Component 1: Support to Single Stage - One En attente informatiques pour les IDA / 53340 A posteriori Demande de prix Limited 18,960.00 0.00 2017-08-19 2017-10-14 2018-04-12 sector actors Envelope d'exécution agents fonciers de l'UCP et la DHORT F- PDIDAS-015-2017 / Component 1: Support to Single Stage - One En attente Acquisition d'images IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 2017-09-08 2017-11-03 2018-05-02 sector actors Envelope d'exécution satellitaires F- PDIDAS-016-2017 / Acquisition de 15 GPS de levées parcellaires, d'un GPS Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 82,000.00 0.00 2017-08-07 2017-08-12 2017-09-23 2017-10-23 2017-11-27 2018-05-26 différentiel pour le cadastre sector actors Envelope d'exécution de louga, de 15 GPS et tablettes pour les enquêteurs F- PDIDAS-017-2017 / Acquisition d'une station Component 1: Support to Single Stage - One En attente totale pour le cadastre de IDA / 53340 A posteriori Demande de prix Limited 30,000.00 0.00 2017-08-28 2017-10-23 2018-04-21 sector actors Envelope d'exécution louga pour la sécurisation foncière F- PDIDAS-018-2017 / Location de bureau pour Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 7,200.00 0.00 2017-08-27 2017-10-22 2018-04-20 l'équipe de la régularisation sector actors Envelope d'exécution foncière Component 2: Development F- PDIDAS-019-2017 / of irrigation infrastructure Single Stage - One En attente Acquisition d'équipements de IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2017-08-09 2017-08-14 2017-09-25 2017-10-25 2017-11-29 2018-05-28 and natural resources Envelope d'exécution pépinières communautaires management F- PDIDAS-020-2017 / Component 2: Development Acquisition de matériel of irrigation infrastructure Single Stage - One En attente d'inventaire et de géo IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2017-08-09 2017-08-14 2017-09-25 2017-10-25 2017-11-29 2018-05-28 and natural resources Envelope d'exécution référencement pour l'UEP management ANGMV F- PDIDAS-021-2017 / Component 2: Development Acquisition d'un logiciel of irrigation infrastructure Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 28,000.00 0.00 2017-08-21 2017-10-16 2018-04-14 TOMPRO multi projet et and natural resources Envelope d'exécution d'un logiciel MS PROJECT management F- PDIDAS-022-2017 / Component 3: Coordination, Acquisition d'équipements de Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 30,000.00 0.00 2017-09-06 2017-11-01 2018-04-30 téléconférence et de Evaluation (GEF: US$0.5 Envelope d'exécution téléphonie million; IDA: US$6 million) F- PDIDAS-023-2017 / Component 3: Coordination, Acquisition d'équipements Impact Monitoring and Single Stage - One En attente informatiques et de IDA / 53340 A posteriori Appel d'offres Open - National 80,000.00 0.00 2017-08-08 2017-08-13 2017-09-24 2017-10-24 2017-11-28 2018-05-27 Evaluation (GEF: US$0.5 Envelope d'exécution géolocalisation pour le suivi million; IDA: US$6 million) évaluation F- PDIDAS-024-2017 / Component 3: Coordination, Acquisition de matériels de Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 3,000.00 0.00 2017-08-15 2017-10-10 2018-04-08 bureau et bureautique pour Evaluation (GEF: US$0.5 Envelope d'exécution la DHORT million; IDA: US$6 million) F- PDIDAS-025-2017 / Component 3: Coordination, Acquisition d'équipements Impact Monitoring and Single Stage - One IDA / 53340 A posteriori Demande de prix Limited 6,000.00 0.00 Annulé 2017-08-23 2017-10-18 2018-04-16 informatiques pour la Evaluation (GEF: US$0.5 Envelope DAPSA million; IDA: US$6 million) Component 3: Coordination, F- PDIDAS-026-2017 / Impact Monitoring and Single Stage - One Acquisition d'outils de IDA / 53340 A posteriori Demande de prix Limited 6,000.00 0.00 Annulé 2017-09-11 2017-11-06 2018-05-05 Evaluation (GEF: US$0.5 Envelope collectes pour la DAPSA million; IDA: US$6 million) Component 3: Coordination, F- PDIDAS-027-2017 / Impact Monitoring and Single Stage - One Acquisition d'espace drop IDA / 53340 A posteriori Demande de prix Limited 6,000.00 0.00 Annulé 2017-08-25 2017-10-20 2018-04-18 Evaluation (GEF: US$0.5 Envelope box million; IDA: US$6 million) F-PDIDAS-029-2017 / Acquisition de petits matériels agricoles et de Component 2: Development laboratoire pour la of irrigation infrastructure Single Stage - One IDA / 53340 A posteriori Demande de prix Limited 8,000.00 0.00 Annulé 2017-08-23 2017-10-18 2018-04-16 multiplication in vitro de la and natural resources Envelope variété Beauregard et des management variétés Covington, Rubina et Bostok par l'ISRA Page 3 F-PDIDAS-030-2017 / Acquisition d'intrants,produits chimiques Component 2: Development et consommables pour la of irrigation infrastructure Single Stage - One IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2017-08-26 2017-10-21 2018-04-19 multiplication in vitro de la and natural resources Envelope variété Beauregard et des management variétés Covington, Rubina et Bostok par l'ISRA Component 2: Development F-PDIDAS-031-2017 / of irrigation infrastructure Single Stage - One Fournitures de bureau IDA / 53340 A posteriori Demande de prix Limited 8,000.00 0.00 Annulé 2017-08-27 2017-10-22 2018-04-20 and natural resources Envelope destinées à l'ISRA management F-PDIDAS-032-2017 / Component 2: Development Acquisition d'intrants pour of irrigation infrastructure Single Stage - One IDA / 53340 A posteriori Appel d'offres Open - National 243,619.00 0.00 Annulé 2017-08-24 2017-08-29 2017-10-10 2017-11-09 2017-12-14 2018-06-12 les 5 GIE du programme and natural resources Envelope pilote de Ngnith(200 ha) management F-PDIDAS-001-2018 / Component 1: Support to Single Stage - One En cours Fourniture et pose de IDA / 53340 A posteriori Demande de prix Limited 10,000.00 0.00 2018-04-02 2018-05-28 2018-11-24 sector actors Envelope d'exécution parcelle test F-PDIDAS-002-2018 / Fourniture et pose de Component 1: Support to Single Stage - One En cours IDA / 53340 A posteriori Appel d'offres Open - National 324,000.00 0.00 2018-04-10 2018-04-15 2018-05-27 2018-06-26 2018-07-31 2019-01-27 parcelles de démonstration sector actors Envelope d'exécution agro écologiques F-PDIDAS-003-2018 / Component 1: Support to Single Stage - One En cours Acquisition d'engrais IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2018-03-24 2018-05-19 2018-11-15 sector actors Envelope d'exécution biologiques F-PDIDAS-004-2018 / Component 1: Support to Single Stage - One En attente Acquisition d'échantillons de IDA / 53340 A posteriori Demande de prix Limited 2,000.00 0.00 2018-04-14 2018-06-09 2018-12-06 sector actors Envelope d'exécution foyers améliorés F-PDIDAS-005-2018 / Production de supports techniques (Présentations Component 1: Support to Single Stage - One En attente techniques, Brochures, IDA / 53340 A posteriori Demande de prix Limited 30,000.00 0.00 2018-03-25 2018-05-20 2018-11-16 sector actors Envelope d'exécution cahiers, fiches produits..) en diverses langues par l'UEP de l'APIX F-PDIDAS-006-2018 / Acquisition d'équipements Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 4,000.00 0.00 2018-03-26 2018-05-21 2018-11-17 et d'outils d'archivage pour sector actors Envelope d'exécution l'UCP et la DGID F-PDIDAS-007-2018 / Acquisition de onze (11) véhicules pick-up pour les Component 1: Support to Single Stage - One En cours IDA / 53340 A posteriori Appel d'offres Open - National 338,000.00 0.00 2018-03-30 2018-04-04 2018-05-16 2018-06-15 2018-07-20 2019-01-16 neuf bureaux fonciers et les sector actors Envelope d'exécution cadastres de st-louis et Louga F-PDIDAS-008-2018 / Acquisition de divers Component 2: Development matériels informatiques of irrigation infrastructure Single Stage - One En attente (ordinateurs, appareil photo IDA / 53340 A posteriori Demande de prix Limited 39,400.00 0.00 2018-03-28 2018-05-23 2018-11-19 and natural resources Envelope d'exécution etc...) et de consommables management informatiques pour l'UCP et de l'ANGMV F-PDIDAS-009-2018 / Component 1: Support to Single Stage - One En attente Impression de formulaires et IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 2018-03-18 2018-05-13 2018-11-09 sector actors Envelope d'exécution registres fonciers F-PDIDAS-010-2018 / Acquisition de carburant Component 1: Support to Single Stage - One En attente pour les véhicules des IDA / 53340 A posteriori Appel d'offres Open - National 110,000.00 0.00 2018-03-23 2018-03-28 2018-05-09 2018-06-08 2018-07-13 2019-01-09 sector actors Envelope d'exécution bureaux fonciers, de la DGID et de l'UCP F-PDIDAS-011-2018 / Acquisition de matériels informatiques et de communication Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2018-04-22 2018-06-17 2018-12-14 complémentaires selon le sector actors Envelope d'exécution modèle du Système d'Information Foncière(SIF) retenu F-PDIDAS-012-2018 / Acquisition Soft et Hardware Component 1: Support to Single Stage - One En attente selon le modèle SIF et IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2018-04-11 2018-04-16 2018-05-28 2018-06-27 2018-08-01 2019-01-28 sector actors Envelope d'exécution options technologiques retenues F-PDIDAS-013-2018 / Component 1: Support to Single Stage - One En cours Acquisition d'images IDA / 53340 A posteriori Appel d'offres Open - National 100,000.00 0.00 2018-04-16 2018-04-21 2018-06-02 2018-07-02 2018-08-06 2019-02-02 sector actors Envelope d'exécution satellitaires Page 4 F-PDIDAS-014-2018 / Acquisition de 02 stations GPS permanentes, de GPS Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 162,000.00 0.00 2018-03-30 2018-04-04 2018-05-16 2018-06-15 2018-07-20 2019-01-16 de levés parcellaires et de sector actors Envelope d'exécution tablettes pour la sécurisation foncière et bureaux fonciers F-PDIDAS-015-2018 / Acquisition de fournitures de Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 22,000.00 0.00 2018-04-14 2018-06-09 2018-12-06 bureau et de consommables sector actors Envelope d'exécution pour l'UCP et la DGID F-PDIDAS-016-2018 / Acquisition de matériels Component 1: Support to Single Stage - One En attente informatiques et de IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2018-04-16 2018-06-11 2018-12-08 sector actors Envelope d'exécution mobiliers de bureau pour la DGID F-PDIDAS-017-2018 / Component 2: Development Acquisition de supports de of irrigation infrastructure Single Stage - One En cours IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2018-04-17 2018-04-22 2018-06-03 2018-07-03 2018-08-07 2019-02-03 communication pour l'UCP and natural resources Envelope d'exécution et l'ANGMV management F-PDIDAS-018-2018 / Component 2: Development Acquisition de matériel of irrigation infrastructure Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2018-04-19 2018-04-24 2018-06-05 2018-07-05 2018-08-09 2019-02-05 d'inventaire et de géo and natural resources Envelope d'exécution référencement pour l'ANGMV management Component 2: Development F-PDIDAS-019-2018 / of irrigation infrastructure Single Stage - One En attente Acquisition de matériel IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 2018-04-17 2018-06-12 2018-12-09 and natural resources Envelope d'exécution bureautique pour l'ANGMV management Component 2: Development F-PDIDAS-020-2018 / of irrigation infrastructure Single Stage - One En attente Acquisition de matériels de IDA / 53340 A posteriori Demande de prix Limited 10,000.00 0.00 2018-04-23 2018-06-18 2018-12-15 and natural resources Envelope d'exécution jardin pour l'ANGMV management F-PDIDAS-021-2018 / Component 3: Coordination, Acquisition d'équipements de Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 30,000.00 0.00 2018-06-03 2018-07-29 2019-01-25 téléconférence et de Evaluation (GEF: US$0.5 Envelope d'exécution téléphonie million; IDA: US$6 million) Component 3: Coordination, F-PDIDAS-022-2018 / Impact Monitoring and Single Stage - One En attente Acquisition de licence IDA / 53340 A posteriori Demande de prix Limited 2,000.00 0.00 2018-04-18 2018-06-13 2018-12-10 Evaluation (GEF: US$0.5 Envelope d'exécution antivirus million; IDA: US$6 million) F- PDIDAS-009-2017 / Acquisition de supports de communication(plaquette,flyer Component 1: Support to Single Stage - One En cours IDA / 53340 A posteriori Demande de prix Limited 44,000.00 0.00 2017-08-20 2017-10-15 2018-04-13 s,kakémono,enseignes,vidéogr sector actors Envelope d'exécution amme ...) pour l'UCP et l'ANGMV F-PDIDAS-014-2017 / Component 3: Coordination, Acquisition de matériels Impact Monitoring and Single Stage - One En cours informatiques pour les IDA / 53340 A posteriori Demande de prix Limited 18,960.00 0.00 2017-10-10 2017-12-05 2018-06-03 Evaluation (GEF: US$0.5 Envelope d'exécution agents fonciers de l'UCP et million; IDA: US$6 million) la DHORT F-PDIDAS-017-2017 / Acquisition d'une station Component 1: Support to Single Stage - One En cours totale pour le cadastre de IDA / 53340 A posteriori Demande de prix Limited 30,000.00 0.00 2017-10-10 2017-12-05 2018-06-03 sector actors Envelope d'exécution Louga pour la sécurisation foncière F-PDIDAS-016-2017 / Acquisition de 15 GPS à levés parcellaires, d'un (01) Component 1: Support to Single Stage - One En cours IDA / 53340 A posteriori Appel d'offres Open - National 92,000.00 0.00 2017-09-04 2017-09-09 2017-10-21 2017-11-20 2017-12-25 2018-06-23 GPS différentiel pour le sector actors Envelope d'exécution Cadastre de Louga et de 15 tablettes pour les enquêteurs F-PDIDAS-010-2017 / Acquisition de véhicules et Component 1: Support to Single Stage - One En attente de motos pour la CFAHS, IDA / 53340 A posteriori Appel d'offres Open - National 199,600.00 0.00 2017-07-21 2017-07-26 2017-09-06 2017-10-06 2017-11-10 2018-05-09 sector actors Envelope d'exécution l'ANGMV, la DHORT et l'UCP F-PDIDAS-028-2017 / Acquisition de fournitures et de consommables Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 30,000.00 0.00 2017-03-25 2017-05-20 2017-11-16 informatiques pour l'UCP, sector actors Envelope d'exécution DHORT, cadastre st-louis et Louga Page 5 F- PDIDAS-012-2017 / Component 1: Support to Single Stage - One En attente Fourniture de formulaires et IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 2017-08-26 2017-10-21 2018-04-19 sector actors Envelope d'exécution de registres fonciers Component 3: Coordination, F-PDIDAS-023-2018 / Impact Monitoring and Single Stage - One Acquisition d'un(01) logiciel IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2018-04-15 2018-06-10 2018-12-07 Evaluation (GEF: US$0.5 Envelope MS-Project million; IDA: US$6 million) F-PDIDAS-001-2019 / Acquisition de matériels et Component 1: Support to Single Stage - One En attente d'intrants pour la mise en IDA / 53340 A posteriori Appel d'offres Open - National 110,000.00 0.00 2019-02-19 2019-02-24 2019-04-07 2019-05-07 2019-06-11 2019-12-08 sector actors Envelope d'exécution œuvre du système de qualité F-PDIDAS-002-2019 / Acquisition de matériels informatique et de Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 26,500.00 0.00 2019-03-17 2019-05-12 2019-11-08 communication sector actors Envelope d'exécution complémentaires pour l'UCP et les agents SIF F-PDIDAS-003-2019 / Acquisition d'équipements Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2019-02-18 2019-04-15 2019-10-12 et d'outils d'archivage pour sector actors Envelope d'exécution l'UCP et la DGID F-PDIDAS-005-2019 / Acquisition d'équipements Component 1: Support to Single Stage - One En cours des CTAF (matériels IDA / 53340 A posteriori Demande de prix Limited 10,000.00 0.00 2019-03-23 2019-05-18 2019-11-14 sector actors Envelope d'exécution informatiques, fournitures de bureau et consommables) F-PDIDAS-006-2019 / Acquisition de carburant Component 1: Support to Single Stage - One En attente pour les véhicules des IDA / 53340 A posteriori Appel d'offres Open - National 110,000.00 0.00 2019-02-14 2019-02-19 2019-04-02 2019-05-02 2019-06-06 2019-12-03 sector actors Envelope d'exécution bureaux fonciers, de la DGID et de l'UCP F-PDIDAS-007-2019 / Acquisition Soft et Hardware Component 1: Support to Single Stage - One En attente selon le modèle SIF et IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2019-03-05 2019-03-10 2019-04-21 2019-05-21 2019-06-25 2019-12-22 sector actors Envelope d'exécution options technologiques retenues F-PDIDAS-008-2019 / Acquisition de 02 stations Component 1: Support to Single Stage - One En cours IDA / 53340 A posteriori Appel d'offres Open - National 140,000.00 0.00 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 GPS permanentes pour la sector actors Envelope d'exécution DGID F-PDIDAS-009-2019 / Acquisition de fournitures de Component 1: Support to Single Stage - One En cours IDA / 53340 A posteriori Demande de prix Limited 16,000.00 0.00 2019-03-10 2019-05-05 2019-11-01 bureau et de consommables sector actors Envelope d'exécution pour l'UCP et la DGID F-PDIDAS-010-2019 / Acquisition de matériels Component 1: Support to Single Stage - One En cours informatiques et de IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2019-03-16 2019-05-11 2019-11-07 sector actors Envelope d'exécution mobiliers de bureau pour la DGID Component 2: Development F-PDIDAS-011-2019 / of irrigation infrastructure Single Stage - One En attente Fourniture et pose de IDA / 53340 A posteriori Appel d'offres Open - National 160,000.00 0.00 2019-03-27 2019-04-01 2019-05-13 2019-06-12 2019-07-17 2020-01-13 and natural resources Envelope d'exécution clôture management Component 2: Development F-PDIDAS-012-2019 / of irrigation infrastructure Single Stage - One En attente Acquisition de matériel IDA / 53340 A posteriori Demande de prix Limited 26,000.00 0.00 2019-03-11 2019-05-06 2019-11-02 and natural resources Envelope d'exécution bureautique pour l'ANGMV management F-PDIDAS-013-2019 / Component 3: Coordination, Acquisition d'équipements de Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 2019-03-25 2019-05-20 2019-11-16 téléconférence et de Evaluation (GEF: US$0.5 Envelope d'exécution téléphonie million; IDA: US$6 million) Component 3: Coordination, F-PDIDAS-014-2019 / Impact Monitoring and Single Stage - One En attente Acquisition de licence IDA / 53340 A posteriori Demande de prix Limited 2,000.00 0.00 2019-03-18 2019-05-13 2019-11-09 Evaluation (GEF: US$0.5 Envelope d'exécution antivirus million; IDA: US$6 million) F-PDIDAS-015-2019 / Component 3: Coordination, Acquisition d'un (01) logiciel Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 16,000.00 0.00 2019-03-11 2019-05-06 2019-11-02 Office 365 intégrant MS- Evaluation (GEF: US$0.5 Envelope d'exécution Project million; IDA: US$6 million) Page 6 F-PDIDAS-016-2019 / Acquisition de matériels Component 3: Coordination, bureautiques pour l'UCP et Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 17,000.00 0.00 2019-03-12 2019-05-07 2019-11-03 la DHORT (appareil photo Evaluation (GEF: US$0.5 Envelope d'exécution numérique, imprimante et million; IDA: US$6 million) photocopieuse) F-PDIDAS-017-2019 / Component 3: Coordination, Acquisition d'espace dans les Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2019-04-11 2019-04-16 2019-05-28 2019-06-27 2019-08-01 2020-01-28 médias nationaux et Evaluation (GEF: US$0.5 Envelope d'exécution internationaux million; IDA: US$6 million) F-PDIDAS-004-2019 / Component 3: Coordination, Acquisition de supports de Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2019-05-06 2019-07-01 2019-12-28 communication et de Evaluation (GEF: US$0.5 Envelope d'exécution documents de capitalisation million; IDA: US$6 million) Component 3: Coordination, F-PDIDAS-025-2018 / Passation de Impact Monitoring and En attente Acquisition d'un logiciel MS IDA / 53340 A posteriori marché de gré à Direct 20,000.00 0.00 2018-12-06 2018-12-06 2019-01-10 2019-07-09 Evaluation (GEF: US$0.5 d'exécution Project gré million; IDA: US$6 million) F-PDIDAS-0006-2019 / Acquisition de carburant Component 1: Support to Single Stage - One En cours pour les véhicules des IDA / 53340 A posteriori Demande de prix Limited 49,800.00 0.00 2019-06-01 2019-07-27 2020-01-23 sector actors Envelope d'exécution bureaux fonciers, de la DGID et de l'UCP F-PDIDAS-100-2019 / Acquisition d'un GPS Component 1: Support to Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 80,000.00 0.00 2019-09-21 2019-11-16 2020-05-14 différentiel pour le Cadastre sector actors Envelope d'exécution de Louga NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S-PDIDAS-001-2017 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente pour la couverture assurance IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2017-08-19 2017-10-14 2018-04-12 Evaluation (GEF: US$0.5 Envelope d'exécution maladie du personnel du million; IDA: US$6 million) PDIDAS S-PDIDAS-002-2017 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 10,800.00 0.00 2017-08-19 2017-10-14 2018-04-12 pour le gardiennage des Evaluation (GEF: US$0.5 Envelope d'exécution locaux du PDIDAS million; IDA: US$6 million) S-PDIDAS-003-2017 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 12,000.00 0.00 2017-08-19 2017-10-14 2018-04-12 pour le nettoiement des Evaluation (GEF: US$0.5 Envelope d'exécution locaux du PDIDAS million; IDA: US$6 million) S-PDIDAS-029-2018 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 40,000.00 0.00 2018-04-04 2018-05-30 2018-11-26 pour l'assurance maladie du Evaluation (GEF: US$0.5 Envelope d'exécution personnel du PDIDAS million; IDA: US$6 million) S-PDIDAS-030-2018 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente pour le gardiennage des IDA / 53340 A posteriori Demande de prix Limited 10,800.00 0.00 2018-04-02 2018-05-28 2018-11-24 Evaluation (GEF: US$0.5 Envelope d'exécution locaux PDIDAS à Saint- million; IDA: US$6 million) Louis et Dakar S-PDIDAS-031-2018 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 12,000.00 0.00 2018-03-31 2018-05-26 2018-11-22 pour le nettoiement des Evaluation (GEF: US$0.5 Envelope d'exécution locaux PDIDAS à Saint- million; IDA: US$6 million) Louis F-PDIDAS-011-2017 / Sélection d'un consultant Component 1: Support to Single Stage - One En attente individuel pour la conception IDA / 53340 A posteriori Demande de prix Limited 6,000.00 0.00 2017-04-08 2017-06-03 2017-11-30 sector actors Envelope d'exécution et le développement d'un site web pour la CFAHS S-PDIDAS-0005-2019 / Component 1: Support to Single Stage - One En attente Impression de formulaires et IDA / 53340 A posteriori Demande de prix Limited 20,000.00 0.00 2019-03-18 2019-05-13 2019-11-09 sector actors Envelope d'exécution registres fonciers S-PDIDAS-0001-2019 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2019-02-04 2019-02-09 2019-03-23 2019-04-22 2019-05-27 2019-11-23 pour l'entretien et réparation Evaluation (GEF: US$0.5 Envelope d'exécution des matériels roulants million; IDA: US$6 million) Page 7 S-PDIDAS-0002-2019 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Appel d'offres Open - National 50,000.00 0.00 2019-02-05 2019-02-10 2019-03-24 2019-04-23 2019-05-28 2019-11-24 pour l'assurance maladie du Evaluation (GEF: US$0.5 Envelope d'exécution personnel du PDIDAS million; IDA: US$6 million) S-PDIDAS-0003-2019 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente pour l'entretien et IDA / 53340 A posteriori Demande de prix Limited 12,000.00 0.00 2019-02-10 2019-04-07 2019-10-04 Evaluation (GEF: US$0.5 Envelope d'exécution nettoiement des locaux du million; IDA: US$6 million) PDIDAS S-PDIDAS-0004-2019 / Component 3: Coordination, Sélection d'un prestataire Impact Monitoring and Single Stage - One En attente IDA / 53340 A posteriori Demande de prix Limited 10,800.00 0.00 2019-02-12 2019-04-09 2019-10-06 pour le gardiennage des Evaluation (GEF: US$0.5 Envelope d'exécution locaux du PDIDAS million; IDA: US$6 million) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C-PDIDAS-001-2017 / Sélection d'un cabinet pour Sélection fondée Component 1: Support to En attente la préparation de IDA / 53340 A priori sur la qualité et Open - National 200,000.00 0.00 2017-08-21 2017-09-11 2017-10-25 2017-11-22 2017-12-22 2018-01-26 2018-03-02 2019-03-02 sector actors d'exécution l'évaluation sociale des 13 le coût 400 ha C-PDIDAS-012-2017 / Sélection d'un consultant pour l'étude diagnostique Sélection fondée technique des infra Component 1: Support to Open - IDA / 53340 A posteriori sur la qualité et 40,000.00 0.00 Annulé 2017-08-24 2017-09-14 2017-10-28 2017-11-25 2017-12-25 2018-01-29 2018-03-05 2019-03-05 existantes et élaboration sector actors International le coût d'un programme de développement de l'Agropole de Fassstructures C-PDIDAS-013-2017 / Sélection d'un consultant Sélection fondée Component 1: Support to Open - pour la réalisation de l'audit IDA / 53340 A posteriori sur la qualité et 40,000.00 0.00 Annulé 2017-08-17 2017-09-07 2017-10-21 2017-11-18 2017-12-18 2018-01-22 2018-02-26 2019-02-26 sector actors International environnemental de le coût l'Agropole de Mpal C-PDIDAS-016-2017 / Component 2: Development Sélection fondée Sélection d'un consultant of irrigation infrastructure sur les En attente pour l'évaluation sociale du IDA / 53340 A posteriori Open - National 40,000.00 0.00 2017-08-14 2017-09-04 2017-10-18 2017-11-17 2017-12-22 2018-06-20 and natural resources qualifications des d'exécution processus foncier des offres management consultants foncières C-PDIDAS-017-2017 / Sélection d'un cabinet de Component 2: Development Sélection fondée supervision et de contrôle of irrigation infrastructure Open - En attente IDA / 53340 A priori sur la qualité et 1,476,030.00 0.00 2017-08-24 2017-09-14 2017-10-28 2017-11-25 2017-12-25 2018-01-29 2018-03-05 2019-03-05 des travaux des and natural resources International d'exécution le coût infrastructures primaires du management Ngalam C-PDIDAS-018-2017 / Sélection d'un cabinet chargé de l'étude d'impact Component 2: Development Sélection fondée environnemental et social of irrigation infrastructure sur les En cours IDA / 53340 A posteriori Open - National 80,000.00 0.00 2017-08-16 2017-09-06 2017-10-20 2017-11-19 2017-12-24 2018-06-22 des infrastructures and natural resources qualifications des d'exécution d'irrigation primaires management consultants incluant les trois marigots et le Gandiolais C-PDIDAS-019-2017 / Sélection d'un cabinet de Component 2: Development Sélection fondée supervision et de contrôle of irrigation infrastructure Open - En attente IDA / 53340 A priori sur la qualité et 800,000.00 0.00 2017-08-23 2017-09-13 2017-10-27 2017-11-24 2017-12-24 2018-01-28 2018-03-04 2019-03-04 des travaux des and natural resources International d'exécution le coût infrastructures d'irrigation management secondaires C-PDIDAS-020-2017 / Sélection d'un consultant Component 2: Development Sélection fondée pour la réalisation de l'étude of irrigation infrastructure En attente IDA / 53340 A posteriori sur la qualité et Open - National 120,000.00 0.00 2017-08-25 2017-09-15 2017-10-29 2017-11-26 2017-12-26 2018-01-30 2018-03-06 2019-03-06 d'impact environnemental et and natural resources d'exécution le coût social des aménagements management secondaires et tertiaires C-PDIDAS-021-2017 / Component 2: Development Sélection d'un consultant Sélection fondée of irrigation infrastructure En attente pour la réalisation de l'audit IDA / 53340 A priori sur la qualité et Open - National 200,000.00 0.00 2017-08-22 2017-09-12 2017-10-26 2017-11-23 2017-12-23 2018-01-27 2018-03-03 2019-03-03 and natural resources d'exécution environnemental détaillé du le coût management Delta C-PDIDAS-022-2017 / Sélection d'un consultant Component 2: Development pour la réalisation de l'étude Sélection fondée of irrigation infrastructure En attente d'actualisation du plan IDA / 53340 A posteriori sur la qualité et Open - National 40,000.00 0.00 2017-08-28 2017-09-18 2017-11-01 2017-11-29 2017-12-29 2018-02-02 2018-03-09 2019-03-09 and natural resources d'exécution d'exploitation et d'entretien le coût management des barrages de Diama et de Manantali Page 8 C-PDIDAS-032-2018 / Sélection fondée Sélection d'un cabinet pour Component 1: Support to sur les En attente la préparation de IDA / 53340 A posteriori Open - National 154,000.00 0.00 2018-03-26 2018-04-16 2018-05-30 2018-06-29 2018-08-03 2019-01-30 sector actors qualifications des d'exécution l'évaluation sociale des 19 consultants 364 ha C-PDIDAS-039-2018 / Sélection d'un Consultant pour le diagnostic du Sélection fondée Component 1: Support to En attente Système d'Information sur le IDA / 53340 A posteriori sur la qualité et Open - National 160,000.00 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-25 2018-08-24 2018-09-28 2018-11-02 2019-11-02 sector actors d'exécution Foncier(SIF), études le coût architecturales et développement du SIF C-PDIDAS-043-2018 / Sélection d'un cabinet pour la réalisation de l'Étude Component 2: Development Sélection fondée d'impact environnemental et of irrigation infrastructure sur les En attente social et du Plan d'Action IDA / 53340 A posteriori Open - National 120,000.00 0.00 2018-04-17 2018-05-08 2018-06-21 2018-07-21 2018-08-25 2019-02-21 and natural resources qualifications des d'exécution de Réinstallation des management consultants infrastructures d'irrigation primaires incluant les trois marigots C-PDIDAS-044-2018 / Sélection d'un cabinet de Component 2: Development Sélection fondée supervision et de contrôle of irrigation infrastructure En cours IDA / 53340 A posteriori sur la qualité et Open - National 160,000.00 0.00 2018-04-02 2018-04-23 2018-06-06 2018-07-04 2018-08-03 2018-09-07 2018-10-12 2019-10-12 des travaux des and natural resources d'exécution le coût infrastructures d'irrigation management secondaires C-PDIDAS-045-2018 / Sélection d'un consultant pour la réalisation de l'étude Component 2: Development Sélection fondée d'impact Environnemental et of irrigation infrastructure sur les En attente Social et évaluation sociale IDA / 53340 A posteriori Open - National 120,000.00 0.00 2018-04-10 2018-05-01 2018-06-14 2018-07-14 2018-08-18 2019-02-14 and natural resources qualifications des d'exécution et du Plan d'Action de management consultants Réinstallation des aménagements secondaires et tertiaires C-PDIDAS-046-2018 / l'audit environnemental et l'élaboration du schéma Component 2: Development Sélection fondée d'aménagement et de gestion of irrigation infrastructure En cours IDA / 53340 A posteriori sur la qualité et Open - National 200,000.00 0.00 2018-04-19 2018-05-10 2018-06-23 2018-07-21 2018-08-20 2018-09-24 2018-10-29 2019-10-29 des ressources naturelles et and natural resources d'examen le coût de l'environnement dans le management delta et la moyenne vallée du fleuve Sénégal C-PDIDAS-047-2018 / Sélection d'un consultant pour la réalisation de l'Etude sur les risques Component 2: Development Sélection fondée d'inondation et le of irrigation infrastructure En attente IDA / 53340 A posteriori sur la qualité et Open - National 448,059.54 0.00 2018-04-05 2018-04-26 2018-06-09 2018-07-07 2018-08-06 2018-09-10 2018-10-15 2019-10-15 déversement non contrôlé and natural resources d'exécution le coût des barrages de Diama et management de Manantali et le Plan de Préparation aux situations d'urgence C-PDIDAS-048-2018 / Sélection d'un consultant Component 2: Development pour la réalisation de Sélection fondée of irrigation infrastructure En attente l'Etude d'actualisation du IDA / 53340 A posteriori sur la qualité et Open - National 40,000.00 0.00 2018-05-23 2018-06-13 2018-07-27 2018-08-24 2018-09-23 2018-10-28 2018-12-02 2019-12-02 and natural resources d'exécution Plan d'exploitation et le coût management d'entretien des Barrages de Diama et Manantali C-PDIDAS-055-2018 / Component 3: Coordination, Sélection d'un consultant Sélection fondée Impact Monitoring and En attente pour l'établissement de la IDA / 53340 A posteriori sur la qualité et Open - National 60,000.00 0.00 2018-04-06 2018-04-27 2018-06-10 2018-07-08 2018-08-07 2018-09-11 2018-10-16 2019-10-16 Evaluation (GEF: US$0.5 d'exécution situation de référence du le coût million; IDA: US$6 million) carbone C-PDIDAS-056-2018 / Component 3: Coordination, Sélection fondée Sélection d'un consultant Impact Monitoring and En attente IDA / 53340 A posteriori sur la qualité et Open - National 40,000.00 0.00 2018-04-09 2018-04-30 2018-06-13 2018-07-11 2018-08-10 2018-09-14 2018-10-19 2019-10-19 pour l'informatisation du Evaluation (GEF: US$0.5 d'exécution le coût système suivi-évaluation million; IDA: US$6 million) C-PDIDAS-042-2018 / Sélection d'un cabinet de Component 2: Development Sélection fondée supervision et de contrôle of irrigation infrastructure Open - En attente IDA / 53340 A priori sur la qualité et 1,520,000.00 0.00 2018-04-02 2018-04-23 2018-06-06 2018-07-04 2018-07-25 2018-08-29 2018-10-03 2019-10-03 des travaux des and natural resources International d'exécution le coût infrastructures primaires à management Ngalam C-PDIDAS-0001-2019 / Sélection d'un Consultant pour le diagnostic du Sélection fondée Component 1: Support to En attente Système d'Information sur le IDA / 53340 A posteriori sur la qualité et Open - National 160,000.00 0.00 2019-02-22 2019-03-15 2019-04-28 2019-05-26 2019-06-25 2019-07-30 2019-09-03 2020-09-02 sector actors d'exécution Foncier(SIF), études le coût architecturales et développement du SIF Page 9 C-PDIDAS-0002-2019 / Sélection d'un cabinet pour la réalisation de l'Étude Component 2: Development Sélection fondée d'Impact Environnemental et of irrigation infrastructure sur les En cours Social et du Plan d'Action IDA / 53340 A posteriori Open - National 97,000.00 0.00 2019-02-26 2019-03-19 2019-05-02 2019-06-01 2019-07-06 2020-01-02 and natural resources qualifications des d'examen de Réinstallation des management consultants aménagements secondaires et tertiaires de la zone du lac de Guiers C-PDIDAS-0003-2019 / Sélection d'un cabinet pour la réalisation de l'Étude Component 2: Development Sélection fondée d'Impact Environnemental et of irrigation infrastructure sur les En cours Social et du Plan d'Action IDA / 53340 A posteriori Open - National 60,000.00 0.00 2019-03-09 2019-03-30 2019-05-13 2019-06-12 2019-07-17 2020-01-13 and natural resources qualifications des d'examen de Réinstallation des management consultants aménagements secondaires et tertiaires de la zone du Ngalam C-PDIDAS-0005-2019 / Sélection d'un cabinet de Component 2: Development Sélection fondée supervision et de contrôle of irrigation infrastructure En attente IDA / 53340 A posteriori sur la qualité et Open - National 700,000.00 0.00 2019-03-11 2019-04-01 2019-05-15 2019-06-12 2019-07-12 2019-08-16 2019-09-20 2020-09-19 des travaux des and natural resources d'exécution le coût infrastructures d'irrigation management tertiaires C-PDIDAS-0006-2019 / Sélection d'un consultant pour la réalisation de l'audit environnemental et Component 2: Development Sélection fondée l'élaboration du schéma of irrigation infrastructure En attente IDA / 53340 A posteriori sur la qualité et Open - National 200,000.00 0.00 2019-02-11 2019-03-04 2019-04-17 2019-05-15 2019-06-14 2019-07-19 2019-08-23 2020-08-22 d'aménagement et de gestion and natural resources d'exécution le coût des ressources naturelles et management de l'environnement dans le delta et la moyenne vallée du fleuve Sénégal C-PDIDAS-0007-2019 / Sélection d'un consultant Component 2: Development pour la réalisation de Sélection fondée of irrigation infrastructure En attente l'Etude d'actualisation du IDA / 53340 A posteriori sur la qualité et Open - National 40,000.00 0.00 2019-03-26 2019-04-16 2019-05-30 2019-06-27 2019-07-27 2019-08-31 2019-10-05 2020-10-04 and natural resources d'exécution Plan d'exploitation et le coût management d'entretien des Barrages de Diama et Manantali C-PDIDAS-0008-2019 / Component 2: Development Sélection fondée Sélection d'un consultant of irrigation infrastructure sur les En cours IDA / 53340 A posteriori Open - National 20,000.00 0.00 2019-03-08 2019-03-29 2019-05-12 2019-06-11 2019-07-16 2020-01-12 pour le renforcement des and natural resources qualifications des d'exécution capacités sur le logiciel SIG management consultants C-PDIDAS-0009-2019 / Component 2: Development Sélection fondée Sélection d'un consultant of irrigation infrastructure sur les En cours pour la formation en IDA / 53340 A posteriori Open - National 20,000.00 0.00 2019-03-15 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 and natural resources qualifications des d'exécution hygiène Qualité Sécurité management consultants Environnement C-PDIDAS-0004-2019 / Sélection d'un cabinet de Component 2: Development Sélection fondée supervision et de contrôle of irrigation infrastructure En attente IDA / 53340 A priori sur la qualité et Open - National 1,000,000.00 0.00 2019-02-12 2019-03-05 2019-04-18 2019-05-16 2019-06-15 2019-07-20 2019-08-24 2020-08-23 des travaux des and natural resources d'exécution le coût infrastructures d'irrigation management secondaires INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C-PDIDAS-002-2017 / Sélection d'un consultant Component 1: Support to En attente individuel pour la formation IDA / 53340 A posteriori Individuel Limited 32,000.00 0.00 2017-08-16 2017-08-21 2017-09-11 2017-10-16 2018-04-14 sector actors d'exécution sur l'hygiène et la sécurité sanitaire des aliments C-PDIDAS-003-2017 / Sélection d'un consultant Component 1: Support to individuel pour la formation IDA / 53340 A posteriori Individuel Limited 6,000.00 0.00 Annulé 2017-08-17 2017-08-22 2017-09-12 2017-10-17 2018-04-15 sector actors sur l'usage sécurisé des pesticides C-PDIDAS-004-2017 / Sélection d'un consultant individuel pour la Component 1: Support to En attente sensibilisation sur les IDA / 53340 A posteriori Individuel Limited 6,000.00 0.00 2017-08-17 2017-08-22 2017-09-12 2017-10-17 2018-04-15 sector actors d'exécution normes privées volontaires(GLOBAL GAP,BIO, etc.) Page 10 C-PDIDAS-005-2017 / Sélection d'un consultant Component 1: Support to individuel sur la traçabilité IDA / 53340 A posteriori Individuel Limited 6,000.00 0.00 Annulé 2017-08-17 2017-08-22 2017-09-12 2017-10-17 2018-04-15 sector actors et la mise en place de système de traçabilité C-PDIDAS-006-2017 / Sélection d'un consultant Component 1: Support to En attente IDA / 53340 A posteriori Individuel Limited 10,000.00 0.00 2017-08-18 2017-08-23 2017-09-13 2017-10-18 2018-04-16 individuel en infographie sector actors d'exécution pour l'UEP APIX C-PDIDAS-007-2017 / Sélection d'un consultant Component 1: Support to En attente individuel pour l'analyse de IDA / 53340 A posteriori Individuel Limited 24,000.00 0.00 2017-08-18 2017-08-23 2017-09-13 2017-10-18 2018-04-16 sector actors d'exécution la chaîne de valeurs patate douce C-PDIDAS-008-2017 / Sélection d'un consultant Component 1: Support to IDA / 53340 A posteriori Individuel Limited 24,000.00 0.00 Annulé 2017-08-16 2017-08-21 2017-09-11 2017-10-16 2018-04-14 individuel pour l'analyse de sector actors la chaîne de valeurs oignon C-PDIDAS-009-2017 / Sélection d'un consultant individuel chargé de l'étude Component 1: Support to IDA / 53340 A posteriori Individuel Limited 14,000.00 0.00 Annulé 2017-08-22 2017-08-27 2017-09-17 2017-10-22 2018-04-20 de faisabilité pour la mise sector actors en place d'une plateforme de services aux membres C-PDIDAS-010-2017 / Sélection d'un consultant individuel pour le Component 1: Support to renforcement du cadre de IDA / 53340 A posteriori Individuel Limited 6,000.00 0.00 Annulé 2017-08-22 2017-08-27 2017-09-17 2017-10-22 2018-04-20 sector actors dialogue permanent public privé autour de la filière patate douce C-PDIDAS-011-2017 / Sélection d'un consultant Component 1: Support to En attente individuel pour la conception IDA / 53340 A posteriori Individuel Limited 6,000.00 0.00 2017-08-16 2017-08-21 2017-09-11 2017-10-16 2018-04-14 sector actors d'exécution et le développement d'un site web pour la CFAHS C-PDIDAS-014-2017 / Sélection d'un consultant Component 1: Support to En attente individuel pour IDA / 53340 A posteriori Individuel Limited 14,000.00 0.00 2017-08-24 2017-08-29 2017-09-19 2017-10-24 2018-04-22 sector actors d'exécution l'actualisation du système d'information sur le foncier C-PDIDAS-015-2017 / Sélection d'un consultant pour la conception interface Component 1: Support to En attente IDA / 53340 A posteriori Individuel Limited 10,000.00 0.00 2017-08-30 2017-09-04 2017-09-25 2017-10-30 2018-04-28 de l'observatoire sur le sector actors d'exécution foncier(PM 1.2 formation et recherche appliquée) C-PDIDAS-023-2017 / Sélection d'un consultant Component 2: Development individuel pour la of irrigation infrastructure IDA / 53340 A posteriori Individuel Limited 14,600.00 0.00 Annulé 2017-08-29 2017-09-03 2017-09-24 2017-10-29 2018-04-27 classification and natural resources environnementale des sous management projets(screening) C-PDIDAS-024-2017 / Component 2: Development Sélection d'un consultant of irrigation infrastructure En attente individuel pour les études IDA / 53340 A posteriori Individuel Limited 60,000.00 0.00 2017-08-24 2017-08-29 2017-09-19 2017-10-24 2018-04-22 and natural resources d'exécution APD-EPI et évaluation management environnementale et sociale C-PDIDAS-025-2017 / Component 2: Development Sélection d'un consultant of irrigation infrastructure IDA / 53340 A posteriori Individuel Limited 10,000.00 0.00 Annulé 2017-08-23 2017-08-28 2017-09-18 2017-10-23 2018-04-21 individuel en appui and natural resources technique en communication management Component 3: Coordination, C-PDIDAS-026-2017 / Impact Monitoring and En attente Sélection d'un auditeur IDA / 53340 A priori Individuel Limited 48,000.00 0.00 2017-08-14 2017-08-19 2017-09-09 2017-10-14 2018-04-12 Evaluation (GEF: US$0.5 d'exécution interne million; IDA: US$6 million) C-PDIDAS-027-2017 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and En attente IDA / 53340 A posteriori Individuel Limited 14,000.00 0.00 2017-08-16 2017-08-21 2017-09-11 2017-10-16 2018-04-14 pour l'évaluation du Evaluation (GEF: US$0.5 d'exécution personnel du PDIDAS million; IDA: US$6 million) C-PDIDAS-028-2017 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and En attente pour la culture IDA / 53340 A posteriori Individuel Limited 14,000.00 0.00 2017-08-28 2017-09-02 2017-09-23 2017-10-28 2018-04-26 Evaluation (GEF: US$0.5 d'exécution organisationnelle et le million; IDA: US$6 million) développement institutionnel Page 11 C-PDIDAS-029-2017 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2017-08-28 2017-09-02 2017-09-23 2017-10-28 2018-04-26 individuel formateur sur le Evaluation (GEF: US$0.5 Process de Communication million; IDA: US$6 million) C-PDIDAS-030-2017 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and En attente IDA / 53340 A posteriori Individuel Limited 30,000.00 0.00 2017-08-22 2017-08-27 2017-09-17 2017-10-22 2018-04-20 pour la formation en MS Evaluation (GEF: US$0.5 d'exécution Project million; IDA: US$6 million) C-PDIDAS-031-2017 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2017-08-28 2017-09-02 2017-09-23 2017-10-28 2018-04-26 pour l'appui à la revue à Evaluation (GEF: US$0.5 mi-parcours du projet million; IDA: US$6 million) C-PDIDAS-032-2017 / Sélection d'un consultant Component 3: Coordination, individuel pour l'élaboration Impact Monitoring and IDA / 53340 A posteriori Individuel Limited 16,000.00 0.00 Annulé 2017-08-29 2017-09-03 2017-09-24 2017-10-29 2018-04-27 de la situation de référence Evaluation (GEF: US$0.5 et base de données million; IDA: US$6 million) environnementales et sociales C-PDIDAS-033-2017 / Sélection d'un consultant Component 3: Coordination, pour les analyses Impact Monitoring and physicochimiques,biologiques, IDA / 53340 A posteriori Individuel Limited 10,000.00 0.00 Annulé 2017-08-31 2017-09-05 2017-09-26 2017-10-31 2018-04-29 Evaluation (GEF: US$0.5 bactériologiques et analyses million; IDA: US$6 million) toxicologiques et suivi épidémiologique et sanitaire C-PDIDAS-034-2017 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and pour l'élaboration du manuel IDA / 53340 A posteriori Individuel Limited 6,000.00 0.00 Annulé 2017-09-01 2017-09-06 2017-09-27 2017-11-01 2018-04-30 Evaluation (GEF: US$0.5 de bonnes pratiques million; IDA: US$6 million) agricoles C-PDIDAS-035-2017 / Sélection d'un consultant Component 3: Coordination, pour l'élaboration et Impact Monitoring and diffusion de supports de IDA / 53340 A posteriori Individuel Limited 12,000.00 0.00 Annulé 2017-09-05 2017-09-10 2017-10-01 2017-11-05 2018-05-04 Evaluation (GEF: US$0.5 communication pour la million; IDA: US$6 million) prévention des risques et dangers liés aux pesticides C-PDIDAS-036-2017 / Sélection d'un consultant Component 3: Coordination, pour la formation sur les Impact Monitoring and IDA / 53340 A posteriori Individuel Limited 10,000.00 0.00 Annulé 2017-09-06 2017-09-11 2017-10-02 2017-11-06 2018-05-05 bonnes pratiques Evaluation (GEF: US$0.5 agroécologiques et les million; IDA: US$6 million) normes environnementales C-PDIDAS-037-2017 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and pour la formation sur IDA / 53340 A posteriori Individuel Limited 10,000.00 0.00 Annulé 2017-09-07 2017-09-12 2017-10-03 2017-11-07 2018-05-06 Evaluation (GEF: US$0.5 l'utilisation et la gestion des million; IDA: US$6 million) pesticides et des OGM C-PDIDAS-038-2017 / Component 3: Coordination, Sélection d'un consultant en Impact Monitoring and En attente création et édition de IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 2017-08-24 2017-08-29 2017-09-19 2017-10-24 2018-04-22 Evaluation (GEF: US$0.5 d'exécution supports de communication( million; IDA: US$6 million) infographie) pour l'UCP C-PDIDAS-033-2018 / Sélection d'un consultant individuel pour la formation Component 1: Support to En cours technique (Champ Ecole IDA / 53340 A posteriori Individuel Limited 16,000.00 0.00 2018-04-13 2018-04-18 2018-05-09 2018-06-13 2018-12-10 sector actors d'exécution Producteur CEP/Gestion Intégrée e la Production et des Prédateurs GIPD) C-PDIDAS-034-2018 / Sélection d'un consultant Component 1: Support to En attente pour la formation en gestion IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 2018-03-27 2018-04-01 2018-04-22 2018-05-27 2018-11-23 sector actors d'exécution des conflits et en gestion de stress des communautés C-PDIDAS-035-2018 / Sélection d'un consultant individuel pour l'appui aux Component 1: Support to En attente IDA / 53340 A posteriori Individuel Limited 30,000.00 0.00 2018-04-11 2018-04-16 2018-05-07 2018-06-11 2018-12-08 communautés à la sector actors d'exécution production de foyers améliorés C-PDIDAS-036-2018 / Sélection d'un consultant individuel pour l'appui aux Component 1: Support to En cours IDA / 53340 A posteriori Individuel Limited 30,000.00 0.00 2018-04-16 2018-04-21 2018-05-12 2018-06-16 2018-12-13 communautés à la sector actors d'exécution production de cultures fourragères Page 12 C-PDIDAS-037-2018 / Sélection d'un consultant individuel chargé de la production de supports Component 1: Support to En attente IDA / 53340 A posteriori Individuel Limited 30,000.00 0.00 2018-04-13 2018-04-18 2018-05-09 2018-06-13 2018-12-10 techniques (présentations sector actors d'exécution techniques, brochures, cahiers, fiches produits...) en divers langues C-PDIDAS-038-2018 / Component 1: Support to En attente Sélection d'un consultant IDA / 53340 A posteriori Individuel Limited 10,000.00 0.00 2018-04-06 2018-04-11 2018-05-02 2018-06-06 2018-12-03 sector actors d'exécution individuel en infographie C-PDIDAS-040-2018 / Component 1: Support to En attente Sélection de trois (03) IDA / 53340 A posteriori Individuel Limited 36,000.00 0.00 2018-03-28 2018-04-02 2018-04-23 2018-05-28 2018-11-24 sector actors d'exécution géomaticiens pour la DGID C-PDIDAS-041-2018 / Sélection de trois (03) Component 1: Support to En attente IDA / 53340 A posteriori Individuel Limited 36,000.00 0.00 2018-03-29 2018-04-03 2018-04-24 2018-05-29 2018-11-25 techniciens pour le cadastre sector actors d'exécution de St louis et de Louga C-PDIDAS-049-2018 / Component 2: Development Sélection d'un assistant pour of irrigation infrastructure En attente IDA / 53340 A posteriori Individuel Limited 14,000.00 0.00 2018-04-16 2018-04-21 2018-05-12 2018-06-16 2018-12-13 le suivi de la mise en and natural resources d'exécution œuvre du FFP management C-PDIDAS-050-2018 / Component 2: Development Sélection d'un consultant of irrigation infrastructure En attente individuel pour les études IDA / 53340 A posteriori Individuel Limited 40,000.00 0.00 2018-03-28 2018-04-02 2018-04-23 2018-05-28 2018-11-24 and natural resources d'exécution APD-EPI des sous projets management restants C-PDIDAS-051-2018 / Component 2: Development Sélection d'un consultant of irrigation infrastructure En attente individuel pour les études IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 2018-03-26 2018-03-31 2018-04-21 2018-05-26 2018-11-22 and natural resources d'exécution EES des sous projets management restants C-PDIDAS-052-2018 / Sélection d'un consultant Component 2: Development individuel pour la mise en of irrigation infrastructure En attente place d'un dispositif IDA / 53340 A posteriori Individuel Limited 40,000.00 0.00 2018-04-12 2018-04-17 2018-05-08 2018-06-12 2018-12-09 and natural resources d'exécution cartographique pour les management agents forestiers et les communautés C-PDIDAS-053-2018 / Component 2: Development Sélection d'un consultant of irrigation infrastructure En cours individuel pour le suivi des IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 2018-03-23 2018-03-28 2018-04-18 2018-05-23 2018-11-19 and natural resources d'exécution travaux de bornage et management pancartage C-PDIDAS-054-2018 / Component 2: Development Sélection d'un consultant of irrigation infrastructure En cours individuel pour le suivi des IDA / 53340 A posteriori Individuel Limited 30,000.00 0.00 2018-03-22 2018-03-27 2018-04-17 2018-05-22 2018-11-18 and natural resources d'exécution travaux d'aménagement des management pépinières C-PDIDAS-057-2018 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and En attente pour l'élaboration d'une des IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 2018-04-18 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Evaluation (GEF: US$0.5 d'exécution PME spécialisées dans million; IDA: US$6 million) l'horticulture C-PDIDAS-058-2018 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and En attente pour la réalisation d'une IDA / 53340 A posteriori Individuel Limited 10,000.00 0.00 2018-04-09 2018-04-14 2018-05-05 2018-06-09 2018-12-06 Evaluation (GEF: US$0.5 d'exécution vidéo sur les bureaux million; IDA: US$6 million) fonciers C-PDIDAS-059-2018 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and En cours pour la mise en place d'un IDA / 53340 A posteriori Individuel Limited 12,000.00 0.00 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2018-12-07 Evaluation (GEF: US$0.5 d'examen système de capitalisation au million; IDA: US$6 million) fil de l'eau C-PDIDAS-0010-2018 / Component 2: Development Sélection d'un assistant pour of irrigation infrastructure En attente IDA / 53340 A posteriori Individuel Open 15,400.00 0.00 2019-03-20 2019-05-08 2019-05-29 2019-07-03 2019-12-30 le suivi de la mise en and natural resources d'exécution œuvre du FFP management C-PDIDAS-0011-2019 / Component 2: Development Sélection d'un consultant of irrigation infrastructure En cours individuel pour les études IDA / 53340 A posteriori Individuel Open 20,000.00 0.00 2019-03-26 2019-05-14 2019-06-04 2019-07-09 2020-01-05 and natural resources d'examen EIES des sous projets management restants Page 13 C-PDIDAS-0012-2019 / Sélection d'un consultant Component 3: Coordination, individuel pour la mise à Impact Monitoring and En attente IDA / 53340 A posteriori Individuel Open 5,100.00 0.00 2019-02-22 2019-04-12 2019-05-03 2019-06-07 2019-12-04 jour des logiciels de gestion Evaluation (GEF: US$0.5 d'exécution financière TOMPRO et million; IDA: US$6 million) TOMFIN C-PDIDAS-0013-2019 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and En attente IDA / 53340 A posteriori Individuel Limited 48,000.00 0.00 2019-04-09 2019-04-14 2019-05-05 2019-06-09 2019-12-06 pour la réalisation d'un Evaluation (GEF: US$0.5 d'exécution publi-reportage million; IDA: US$6 million) C-PDIDAS-0014-2019 / Component 3: Coordination, Sélection d'un consultant Impact Monitoring and En attente pour la mise en place d'un IDA / 53340 A posteriori Individuel Open 12,000.00 0.00 2019-03-08 2019-04-26 2019-05-17 2019-06-21 2019-12-18 Evaluation (GEF: US$0.5 d'exécution système de capitalisation au million; IDA: US$6 million) fil de l'eau Component 3: Coordination, C-PDIDAS-0015-2019 / Impact Monitoring and En attente Sélection d'une agence pour IDA / 53340 A posteriori Individuel Open 50,000.00 0.00 2019-03-14 2019-05-02 2019-05-23 2019-06-27 2019-12-24 Evaluation (GEF: US$0.5 d'exécution la production audiovisuelle million; IDA: US$6 million) C-PDIDAS-016-2019 / Sélection d'un consultant individuel pour la réalisation Component 2: Development des études of irrigation infrastructure En attente IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 2019-05-20 2019-05-25 2019-06-15 2019-07-20 2020-01-16 environnementales sommaires and natural resources d'exécution pour les sous projets des management petits producteurs de la région de Louga C-PDIDAS-00009-2019 / Component 2: Development Sélection d'un consultant of irrigation infrastructure En attente pour la formation en IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 2019-05-27 2019-06-01 2019-06-22 2019-07-27 2020-01-23 and natural resources d'exécution hygiène Qualité Sécurité management Environnement C-PDIDAS-00008-2019 / Component 2: Development Sélection d'un consultant of irrigation infrastructure En attente IDA / 53340 A posteriori Individuel Limited 20,000.00 0.00 2019-05-31 2019-06-05 2019-06-26 2019-07-31 2020-01-27 pour le renforcement des and natural resources d'exécution capacités sur le logiciel SIG management Component 3: Coordination, C-PDIDAS-018-2019 / Impact Monitoring and En cours Sélection d'un Spécialiste en IDA / 53340 A posteriori Individuel Open 60,000.00 0.00 2019-07-12 2019-08-30 2019-09-20 2019-10-25 2020-04-22 Evaluation (GEF: US$0.5 d'exécution Communication million; IDA: US$6 million) C-PDIDAS-019-2019 / Component 3: Coordination, Sélection d'un Spécialiste Impact Monitoring and En attente Mesures de Sauvegarde IDA / 53340 A posteriori Individuel Open 60,000.00 0.00 2019-01-30 2019-03-20 2019-04-10 2019-05-15 2019-11-11 Evaluation (GEF: US$0.5 d'exécution Sociale et Développement million; IDA: US$6 million) Communautaire C-PDIDAS-020-2019 / Sélection d'un consultant pour la réalisation du Plan Component 2: Development de Gestion Environnementale of irrigation infrastructure En attente IDA / 53340 A posteriori Individuel Open 50,000.00 0.00 2019-08-25 2019-10-13 2019-11-03 2019-12-08 2020-06-05 et Sociale des infrastructures and natural resources d'exécution de substitution dans les management communes de Ronkh, Fass Ngom et Ndiébène Gandiole C-PDIDAS-017-2019 / Component 3: Coordination, Sélection d'un Spécialiste Impact Monitoring and En attente IDA / 53340 A posteriori Individuel Direct 80,000.00 0.00 2019-09-09 2019-09-12 2019-09-12 2019-09-13 2020-12-31 Principal en Passation de Evaluation (GEF: US$0.5 d'exécution Marchés million; IDA: US$6 million) Page 14