PROCUREMENT PLAN Project information: Ethiopia Lowland Livelihood Resilient Project, P146336 Project Implementation agency: Ministry of Peace Date of the Procurement Plan: May 2019 Period covered by this Procurement Plan: May 2019 to December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Sections 33(1)(a) and 35-48 of the Proclamation No. 649/2009, The Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets: “Not Applicable” Procurement of Second Hand Goods : “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. The project envisages procurement activities that will be implemented through CDD arrangement following the CDD Procurement manual that is under preparation and will be agreed with the Bank PROCUREMENT Ethiopia : Lowlands Livelihood Resilience Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2020-11-23 2020-12-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164336 GPN Date: 2019-10-17 Project Name: Lowlands Livelihood Resilience Project Loan / Credit No: IDA / 64120 G Executing Agency(ies): ambella Region - Lowlands Livelihood Resilience Project WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-GAMBELLA, LLRP-211335- Integrated Rangeland Pending CW-RFB / Itang Town-Pole Single Stage - One 2021-05- IDA / 64120 Development and Post Request for Bids Open - National 276,550.00 0.00 Implementat 2020-12-25 2020-12-30 2021-01-31 2021-02-05 2021-02-15 Kebele Rural Road Envelope 31 Management ion Construction Project (DC-2) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-GAMBELLA, LLRP-205495- Under GO-RFQ / Procurement of Project Management, Request for Single Stage - One IDA / 64120 Post Limited 69,500.00 0.00 Implementati 2020-12-07 2020-12-20 2021-01-11 2021-02-26 furnitures and office Monitoring and Evaluation Quotations Envelope on equipment for the 8 woredas ET-GAMBELLA, LLRP-205562- Integrated Rangeland Under GO-RFQ / procurement of Request for Single Stage - One IDA / 64120 Development and Post Limited 5,890.00 0.00 Implementati 2020-12-06 2020-12-11 2021-01-15 2021-02-25 10pcs of GPS for Region and Quotations Envelope Management on woredas offices ET-GAMBELLA, LLRP-205566- Under Project Management, Request for Single Stage - One GO-RFQ / Procurement of IDA / 64120 Post Limited 1,180.00 0.00 Implementati 2020-12-01 2020-12-07 2021-01-05 2021-02-15 Monitoring and Evaluation Quotations Envelope photo Camera on ET-GAMBELLA, LLRP-210345- GO-RFB / procurement of Integrated Rangeland Pending Single Stage - One spare parts for Existing water IDA / 64120 Development and Post Request for Bids Open - National 248,000.00 0.00 Implementati 2020-12-18 2020-12-23 2021-01-25 2021-01-29 2021-02-10 2021-02-28 Envelope points for 60 shallow and Management on hand dug wells NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1