2018 Procurement Plan Mineral Sector Support for Economic Diversification Project (MinDiver) I. General 1. Project information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Mineral Sector Support for Economic Diversification Project Credit No.: 59900 Project ID No: P159761 Project Implementing Agencies: Ministry of Mines and Steel Development (MMSD) 2. Bank’s approval Date of the Original Procurement Plan: 27th March 2017 3. Bank’s approval Date of the Revised Procurement Plan: 19th April, 2017 Date of General Procurement Notice: Online December 27, 2017 4. Period covered by this procurement plan: 1st January 2018 to 31st December 2018 II. Goods, Supply and Installation and Works and non-consulting services 5. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments 1. ICB and LIB (Goods) >=1,000,000 All Contracts 2. ICB (Works/Supply & Installation) >=10,000,000 All Contracts 3. ICB (Non-Consultant Services) >=500,000 All Contracts 4. Direct Contracting All Values All Contracts 5. NCB (Goods) <=1,000,000 All Contracts 6. NCB (Works) <=10,000,000 All Contracts 7. Shopping <=100,000 All Contracts (a) List of contract Packages which will be procured following ICB and Direct contracting. (b) ICB Contracts estimated to cost above US$500,000 equivalent or more per Contract and all Direct Contracting will be subject to prior review by the Bank. 6. Prequalification: Nil 7. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): NA Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: (including advance procurement and retroactive financing, if applicable): N/A. 8. Procurement Packages with Methods and Time Schedule. 9. Procurement Packages with Methods and Time Schedule for Goods and Works Procurement Reviews and Thresholds Table 2.4. Procurement of Goods and Works and Non-consulting Services Prior Review Threshold Procurement Method Comments (US$) 1 NCB (goods) packages Above 750,000 All 2 Non-consultant Services packages Above 750,000 All 3 Shopping (goods) Below 100,000 None 4 Shopping (works) Below 200,000 None Summary of the procurement packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement). 18-Month Procurement Plan for Goods and Works Contract Original Expected Activit Prior or Estimated y List of Type Time Procurement Estimate Proposal Contract Post Submissio Completion # s Based or Type (US$, Review n Dates Lump Sum thousands) Dates 1 Equipment Lump Sum Not 2,000.00 Prior July 1, 2017 September for Stated 29, 2017 vocational training 2 Office Lump Sum NS 200.00 Post June 1, 30 August, Equipment 2017 2017 for MinDiver and other agencies Solar 3 System Lump Sum NS 50.00 Post August 1, October 30, system for 2017 2017 NGSA 5 Motor Lump Sum NS 75.00 Prior June 1, August 30, vehicles - 2017 2017 Saloon Cars (6) 6 Motor Lump Sum NS 175.00 Prior May 1, July 30, vehicles - 4 2017 2017 × 4 (seven) Completio 7 n Bill of NS 70.00 Post of the Quantities dimension stone laboratory in Kaduna Selection of Consultants Prior review threshold. Selection decisions subject to prior review by the World Bank as stated in the Procurement Regulations. Selections Subject to Prior Review by the World Bank Selection Method Prior Review Threshold (US$) Comments 1. Competitive Methods (Firms) Above 300,000 2. Single Source (Firms) All 3. Individual Above 100,000 41. Short list consisting entirely of national consultants. A short list of consultants for services estimated to cost less than US$300,000 equivalent per contract may consist entirely of national consultants. Consultancy Assignments with Selection Methods and Time Schedule 18-Month Procurement Plan for Consultancy Contract Original Expected Procur Prior or Estimated Activity Type Time Estimate Proposal List of Contracts ement Post Completion # Based or (US$, Submission Type Review Dates Lump Sum thousands) Dates Consultancies A1-1.1 Functional analysis Lump Sum QCBS 1,000.00 Prior May 1, 2017 October 28, within the MMSD, its 2018 associated agencies, and other MDAs based on identifying and reviewing the workflows and information flows A1-1.2 Upgrading and Lump Sum SS 440.00 Prior November June 29, automation of the 1, 2017 2018 MCO A1-2.1 Review and update of Lump Sum QCBS 600.00 Prior May 6, 2017 May 1, 2019 the NMMA, 2007 A1-4.1 Assisting the GoN to Lump Sum QCBS 250.00 Post November October 27, build the required 1, 2017 2018 technical skills and managerial capabilities to service and develop the mining sector A1-7.1 Design and develop a Lump Sum IC 300.00 Prior May 1, 2017 March 27, mechanism for citizen 2018 engagement and social accountability in the MinDiver project and the mining sector Contract Original Expected Procur Prior or Estimated Activity Type Time Estimate Proposal List of Contracts ement Post Completion # Based or (US$, Submission Type Review Dates Lump Sum thousands) Dates A2-1-3.1 Geological mapping, Lump Sum QCBS 14,000.00 Prior May 1, 2017 December GIS geodata base, 22, 2018 mapping, and reinterpretation of data, and mineral prospectivity targeting A2-1.2 TA on exploration Lump Sum CQ 150.00 Post May 1, 2017 August 24, embedded within the 2018 NGSA A3-1.1 Scoping analysis and Lump Sum QCBS 400.00 Prior September November strategy development 1, 2017 25, 2018 to create the basis for reintroducing and/or providing vocational training to achieve excellence for the training of the Government's technical staff as well as private sector (national pole) A3-1.2 Analyze and design a Lump Sum CQ 180.00 Post November August 28, program to address 1, 2017 2018 the skill gap in the domestic mining industry Design and A3-1.3 implement Lump Sum IC 100.00 Post November April 30, partnership program 1, 2017 2018 between the MMSD, Nigerian universities, and the NGSA on selected topics A3-1.4 Assess and develop Lump Sum CQ 150.00 Post November November policy and strategy for 1, 2017 26, 2018 achieving local content in Nigerian mining sector A4-1.1 Update SESA and Lump Sum CQ 150.00 Post July 1, 2017 April 27, prepare action plan for 2018 implementation of recommendations A4-2.1 Phase 1: Address Lump Sum QCBS 250.00 Post May 1, 2017 October 28, potential medical 2018 geology issues arising from interaction between geological Contract Original Expected Procur Prior or Estimated Activity Type Time Estimate Proposal List of Contracts ement Post Completion # Based or (US$, Submission Type Review Dates Lump Sum thousands) Dates background and its influence on the plants, animals, and humans to explore general mining- related health impacts. A4-5.1 Support the creation Lump Sum CQ 250.00 Post June 1, 2017 January 27, of opportunities for 2018 women and gender mainstreaming in the mining sector B1-1-3.1 Providing ASM Lump Sum QCBS 2,800.00 Prior June 1, 2017 November inventory, 28, 2018 operations/activities to assess scale and extent B3-1.2 Analyze economic Lump Sum QCBS 200.00 Post January 1, December drivers linking supply 2017 27, 2017 of industrial minerals with demand for construction and industrial materials; analyzing benefit sharing aspects (different stages of the value chain) institutional and governance. Needs assessment B3-1.3 and Lump Sum QCBS 4,120.00 Prior May 1, 2017 April 26, evaluation for 2018 accrediting and certifying laboratories including operationalization geological research laboratories B3-1.4 Development of Lump Sum QCBS 500.00 Prior December 1, November support action to 2017 26, 2018 improve the metallurgical and steel Inspectorate including an initial baseline study B4-1.1 Analysis and Lump Sum QCBS 540.00 Prior November October 27, development of 1, 2017 2018 strategies for addressing access to Contract Original Expected Procur Prior or Estimated Activity Type Time Estimate Proposal List of Contracts ement Post Completion # Based or (US$, Submission Type Review Dates Lump Sum thousands) Dates finances constraints for local ASM, junior and medium scale companies Assess the SMDF B4-1.2 and Lump Sum QCBS 600.00 Prior March 1, November provide 2018 26, 2018 recommendations for its restructuring and operationalization, covering governance, structure, organization, strategies, and operations B4-1.3 Assist in building Lump Sum QCBS 600.00 Prior June 1, 2017 November capacity for financial 28, 2018 institutions, public and semipublic bodies through the Bankers Committee, in understanding of mining financing, preparation of bankable FS, business plans, and marketing B5-1.1 Initial review and Lump Sum QCBS 3,000.00 Prior June 1, 2017 November development of 28, 2018 potential assets in different mining cycle stages to select some Mineral Assets, and Mining Operators requiring Support, to bring those Assets to a higher Level or Advancing transactions on specific Assets. B5-1.2 Preliminary Lump Sum IC 40.00 Post November December identification of ‘proof 1, 2017 26, 2018 of concept’ investment B5-2.1 Preliminary Lump Sum CQ 180.00 Post May 1, 2017 February 25, assessment and 2018 transaction advisory services for State Own Enterprise NIOMCO A2-2.2 Consultancy services Lump Sum IC 150.00 Post May 1, 2017 January 26, Contract Original Expected Procur Prior or Estimated Activity Type Time Estimate Proposal List of Contracts ement Post Completion # Based or (US$, Submission Type Review Dates Lump Sum thousands) Dates for review of legal 2018 framework A1-5.1 Consultancy services Lump Sum IC 75.00 Post May 1, 2017 January 26, for identifying revenue 2018 leakages, strengthening the administrative system, and oversight of revenue assessment and collection Consultancy service B5-1.1 for Lump Sum IC 400.00 Prior May 1, 2017 January 26, identifying prospective 2018 mineral targets and mining assets to be analyzed as candidates for transaction processes and investment promotion. (Geological Analyst) C1-1 Technical expert for Lump Sum IC 600.00 Prior n.a. October 23, the project (1 and 2) 2018 Procurement C1-2 Specialist Time based IC 75.00 Post n.a. October 23, 2018 C1-3 M&E Specialist Time based IC 75.00 Post n.a. October 23, 2018 C1-4 Project Coordinator Time based IC 120.00 Post n.a. October 23, 2018 C1-5 PMO (for subsequent Lump Sum QCBS 1,500.00 Prior n.a. October 23, months) 2018 Note: IC = Individual Consultant; QCBS = Quality- and Cost-Based Selection; SS = Single-Source Selection. PROCUREMENT Nigeria : Nigeria: Mineral Sector Support for Economic Diversification Project (MinDiver) PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2018-02-13 2019-04-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159761 GPN Date: 2017-12-27 Project Name: Nigeria: Mineral Sector Support for Economic Diversification Project (MinDiver) Loan / Credit No: IDA / 59900, IDA / V0270 Executing Agency(ies): Mineral Sector Support for Economic Diversification WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/RFB/W-001/18 / Pending Single Stage - One Renovation of Labouratory IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 2018-10-20 Envelope (NGSA Kaduna) on MINDIVER/RFB/W-003/18 / Pending Single Stage - One Completion of the dimension IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 2018-10-20 Envelope stone labouratory in Kaduna on MINDIVER/RFB/W-004/18 / Pending Construction of feeder roads Single Stage - One IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2018-01-01 2018-01-06 2018-02-17 2018-03-19 2018-04-23 2018-10-20 and bridges under proof of Envelope on concept NG-MINDIVER-103111-CW- Pending RFB / Rehabilitation of Ladi Single Stage - One IDA / 59900 Post Request for Bids Limited 0.00 Implementati 2019-05-16 2019-05-21 2019-07-02 2019-08-01 2019-09-05 2020-03-03 Kwali Centre on Poetry Envelope on Works MINDIVER/RFB/W-002/17 / Pending Renovation of Nigerian Single Stage - One IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2019-05-29 2019-06-03 2019-07-15 2019-08-14 2019-09-18 2020-03-16 Institute of Mining and Envelope on Geosciences (NIMG), Jos NG-MINDIVER-107430-CW- RFQ / Refurbishment of Pending Request for Single Stage - One Building in JOS zones of IDA / 59900 Post Limited 0.00 Implementati 2019-05-14 2019-07-09 2020-01-05 Quotations Envelope the Mining Cadastre Office on for online application NG-MINDIVER-107432-CW- RFQ / MAIDUGURI, Refurbishment of Identified Pending Request for Single Stage - One Building in 6 Geopolitical IDA / 59900 Post Limited 0.00 Implementati 2019-04-29 2019-06-24 2019-12-21 Quotations Envelope zones of the Mining on Cadastre for Online application NG-MINDIVER-107433-CW- RFQ / IBADAN: Refurbishment of the Pending Request for Single Stage - One identified building in Ibadan IDA / 59900 Post Limited 0.00 Implementati 2019-04-29 2019-06-24 2019-12-21 Quotations Envelope Geopolitical area of the on Mining Cadastre office for online application. NG-MINDIVER-107434-CW- RFQ / KADUNA: Refurbishment of the Pending Request for Single Stage - One identified building in IDA / 59900 Post Limited 0.00 Implementati 2019-04-29 2019-06-24 2019-12-21 Quotations Envelope Kaduna Geopolitical area of on the Mining Cadastre office for online application. Page 1 NG-MINDIVER-107435-CW- RFQ / ENUGU: Refurbishment of the Pending Request for Single Stage - One identified building in Enugu IDA / 59900 Post Limited 0.00 Implementati 2019-04-29 2019-06-24 2019-12-21 Quotations Envelope Geopolitical area of the on Mining Cadastre office for online application. NG-MINDIVER-107436-CW- RFQ / BENIN: Refurbishment of the Pending Request for Single Stage - One identified building in Benin IDA / 59900 Post Limited 0.00 Implementati 2019-04-29 2019-06-24 2019-12-21 Quotations Envelope Geopolitical area of the on Mining Cadastre office for online application. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/GO/RFQ/001/18 / Procurement of Office Request for Single Stage - One IDA / 59900 Post Limited 67,232.55 Completed 2018-02-10 2018-04-07 2018-10-04 Equipment for MinDiver Quotations Envelope Project use MINDIVER/GO/RFQ/003/17 / Procurement of Motor Vehichles -Saloon Cars Pending Single Stage - One (20NOS), 4X4 (30Nos) MCO IDA / 59900 Prior Request for Bids Open - National 0.00 Implementati 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Envelope 6/NGSA 20/NSRMEA on 2/Mining Inspectorate 2/ MMSD 12/ MINdIver 6 MINDIVER/GO/RFQ/004/18 Pending / Project Management IDA / 59900 Post Direct Selection Direct 0.00 Implementati 2018-04-15 2018-04-20 2018-06-08 2018-12-05 Server, Softwares and on Hardwares MINDIVER/GO/RFQ/007/17 Under / Procurement of Office Request for Single Stage - One IDA / 59900 Post Limited 60,921.44 Implementati 2018-02-20 2018-04-24 2018-10-21 Furniture for MinDiver Quotations Envelope on Project MINDIVER/GO/RFB/008/18 / Procurement of Office Pending Single Stage - One Furniture for Mining IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2018-02-10 2018-02-15 2018-03-29 2018-04-28 2018-06-02 2018-11-29 Envelope Cadastre office (MCO) -6 on Geopolitical Zones MINDIVER/GO/RFQ/008/18 Pending / Supply and Installation of Request for Single Stage - One IDA / 59900 Post Limited 0.00 Implementati 2018-02-20 2018-04-17 2018-10-14 ICT equipment for MinDiver Quotations Envelope on Project Office MINDIVER/NCB/G-007/18 / Supply and Installation of Pending Single Stage - One ICT equipment for 6 IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2018-02-15 2018-03-01 2018-04-12 2018-05-12 2018-06-16 2018-12-13 Envelope Geopolitical Zones of the on MCO MINDIVER/GO/RFQ/005/18 Under / Procurement of Stationeries Request for Single Stage - One IDA / 59900 Post Limited 0.00 Implementati 2018-03-01 2018-04-26 2018-10-23 and Printing materials for Quotations Envelope on Mindiver Project office Page 2 MINDIVER/GO/RFB/006/18 / Procurement of Office Equipment, Stationeries and Single Stage - One IDA / 59900 Post Request for Bids Open - National 0.00 Canceled 2018-04-01 2018-04-15 2018-05-27 2018-06-26 2018-07-31 2019-01-27 Printing materials for 6 Envelope Geopolitical Zones of the Mining Cadastre Office MINDIVER/GO/RFB/011/17 / Pending Single Stage - One XRF Analyzer X-Ray IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2018-03-15 2018-03-29 2018-05-10 2018-06-09 2018-07-14 2019-01-10 Envelope machines for exit Ports (10) on MINDIVER/GO/RFB/012/18 / Pending Single Stage - One Equiping of the dimension IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2019-06-07 Envelope stone laboratory in Kaduna on MINDIVER/GO/RFB/013/18 / Pending Rapid Analytical equipment Single Stage - One IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2018-02-28 2018-03-14 2018-04-25 2018-05-25 2018-06-29 2018-12-26 (handheld XRF analyzers)- Envelope on (20) MINDIVER/GO/RFQ/014/18 Pending Request for Single Stage - One / Solar Panel system for IDA / 59900 Post Limited 0.00 Implementati 2018-03-15 2018-05-10 2018-11-06 Quotations Envelope NGSA, Kaduna on MINDIVER/GO/RFB/005/18 / Under Single Stage - One Laboratory Equipment for IDA / 59900 Prior Request for Bids Open - National 0.00 Implementati 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Envelope NGSA Kaduna on MINDIVER/RFQ/G-004/18 / Procurement of Motor Request for Single Stage - One Vehicles for Project office - IDA / 59900 Post Limited 471,052.40 Completed 2018-02-15 2018-04-19 2018-10-16 Quotations Envelope Saloon Cars (4NOS), 4X4 (1Nos) MINDIVER/RFQ/GD-016/18 / Procurement of Hardware Pending Request for Single Stage - One upgrade for Information IDA / 59900 Post Limited 0.00 Implementati 2018-02-20 2018-04-17 2018-10-14 Quotations Envelope Management System at the on NGSA (DSS, Exploration, IT) MINDIVER/RFQ/GD-078/18 / Procurement of Request for Single Stage - One IDA / 59900 Post Limited 48,377.13 Completed 2018-09-05 2018-10-31 2019-04-29 Topographical Maps covering Quotations Envelope the entire country, Nigeria MINDIVER/RFB/GO/021-18 / Procurement and installation of Laboratory Pending Open - Single Stage - One Equipment for Nigerian IDA / 59900 Prior Request for Bids 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 International Envelope Metallurgical and on Development Centre (NMDC),Jos MINDIVER/GO/RFQ/107/19 Pending Request for Single Stage - One / Procurement of Stationery IDA / 59900 Post Limited 0.00 Implementati 2019-08-06 2019-10-01 2020-03-29 Quotations Envelope for MinDiver Project on MINDIVER/GO/RFQ/108/19 Pending / Procurement of Office Request for Single Stage - One IDA / 59900 Post Limited 0.00 Implementati 2019-04-20 2019-06-15 2019-12-12 Furniture for PMO Quotations Envelope on (MindIVER) MINDIVER/GO/RFB/102/19 / Procurement and installation Pending of Manual Shelving/Rack Request for Single Stage - One IDA / 59900 Post Limited 0.00 Implementati 2019-03-20 2019-05-15 2019-11-11 system for safekeping of Quotations Envelope on documents for MinDiverProcurement unit) Page 3 MINDIVER/GO/RFQ/104/19 Pending / Printing of NGSA Request for Single Stage - One IDA / 59900 Post Limited 0.00 Implementati 2019-08-20 2019-10-15 2020-04-12 Technical Reports and Quotations Envelope on Manuals NG-MINDIVER-103110-GO- Pending RFQ / Procurement of office Request for Single Stage - One IDA / 59900 Post Limited 0.00 Implementati 2019-08-06 2019-10-01 2020-03-29 Equipment for Mindiver Quotations Envelope on project MINDIVER/GO/RFB/009/19 / Pending Procurement of efficient Open - Single Stage - Two IDA / 59900 Prior Request for Bids 0.00 Implementati 2019-06-05 2019-06-10 2019-07-22 2019-10-04 2019-11-08 2020-05-06 Technology Equipmemt for International Envelope on safer and Cleaner Mining MINDIVER/GO/RFB/306/18 / / Procurement of Office Equipment, Stationeries and Pending Printing materials for Single Stage - One IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2019-03-21 2019-03-26 2019-05-07 2019-06-06 2019-07-11 2020-01-07 Headquarters and 6 Envelope on Geopolitical Zones of the Mining Cadastre Office (MCO) MINDIVER/GO/RFB/106/19 / Procurement and installation Pending of Laboratory Equipment for Single Stage - One IDA / 59900 Prior Request for Bids Open - National 0.00 Implementati 2019-05-01 2019-05-06 2019-06-17 2019-07-17 2019-08-21 2020-02-17 Nigerian INSTITUTE of Envelope on MINING and Geosciences (NIMG) NG-MINDIVER-104557-GO- RFB / Procurement of Solar Pending Single Stage - One Panel System for 6 Zonal IDA / 59900 Post Request for Bids Open - National 0.00 Implementati 2019-05-01 2019-05-06 2019-06-17 2019-07-17 2019-08-21 2020-02-17 Envelope offices of the Mining on Cadastre Office (MCO) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/NC/RFP/105/19 / Airborne Geophysical Survey of selected areas under proof of concept programme- High Request for Open - Single Stage - Two IDA / 59900 Prior 0.00 Canceled 2019-05-23 2019-05-28 2019-07-09 2019-09-21 2019-10-26 2020-04-23 resolution magnetic & Proposals International Envelope Radiometric. Areas A-1, A-2 and c-1 (100 sheets (TLM50 (38-32 NG-MINDIVER-103087-NC- RFP / Production of Topographic Mapping (Geodata Base) using Request for Open - Single Stage - Two IDA / V0270 Prior 0.00 Canceled 2019-05-22 2019-05-27 2019-07-08 2019-09-20 2019-10-25 2020-04-22 international Standards Proposals International Envelope (MGCPOVmap2) for Areas A- 1 , A-2 and c-1 (100 sheets (TLM50 (38-32percent. NG-MINDIVER-107437-NC- RFB / Airborne Geophysical Survey of selected areas Pending under proof of concept Open - Single Stage - One IDA / 59900 Prior Request for Bids 0.00 Implementati 2019-04-21 2019-05-12 2019-06-23 2019-07-23 2019-08-27 2020-02-23 programme- High resolution International Envelope on magnetic & Radiometric. Areas A-1 , A-2 and c-1 (100 sheets (TLM50 ) Page 4 NG-MINDIVER-107438-NC- RFB / Production of Topographic Mapping Pending (Geodata Base) using Open - Single Stage - One IDA / 59900 Prior Request for Bids 0.00 Implementati 2019-04-21 2019-05-12 2019-06-23 2019-07-23 2019-08-27 2020-02-23 international Standards International Envelope on (MGCPOVmap2) for Areas A- 1 , A-2 and c-1 (100 sheets (TLM50 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MINDIVER/QCBS/CS/002-18 / Advisory Firm to Strengthen the Institutional Frameworks Governing the Quality And Cost- Mining Sector (Functional IDA / 59900 Prior Open - National 0.00 Under Review 2018-01-15 2018-02-05 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 Based Selection analysis and institutional restructuring) and Sector Administrative Capacity Building MINDIVER/QCBS/CS/003-17 / Consultancy for Geological Quality And Cost- Open - Under Advisory Services (TA IDA / 59900 Prior 0.00 2018-02-05 2018-02-26 2018-04-18 2018-05-16 2018-06-15 2018-07-20 2018-08-24 2021-08-23 Based Selection International Implementation embed) in the Mining and Steel sector MINDIVER/QCBS/CS/004-18 / Consultancy to provide Quality And Cost- Under skills building and education IDA / 59900 Prior Open - National 0.00 2018-02-01 2018-02-22 2018-04-07 2018-05-05 2018-06-04 2018-07-09 2018-08-13 2019-08-13 Based Selection Implementation support for mining sector development to MMSD MINDIVER/QCBS/CS/006-17 / Review of legal & regulatory frameworks for environmental mgt, the design of policy frameworks to apply WB safeguards Quality And Cost- Under IDA / 59900 Prior Open - National 0.00 2018-05-02 2018-05-23 2018-07-06 2018-08-03 2018-09-02 2018-10-07 2018-11-11 2019-11-11 policies & the devt of Based Selection Implementation mitigation measures & guidelines for addressing potential conflicts between ASM operators & other land users MINDIVER/QCBS/CS/007-18 / Consultancy for the development of a comprehensive action plan to Quality And Cost- Under create opportunities for IDA / 59900 Post Open - National 0.00 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 Based Selection Implementation women in the mining and steel sector and to mitigate risks that are unique to women MINDIVER/QCBS/CS/009-18 / Consultancy to design and implement safer and cleaner Quality And Cost- IDA / 59900 Prior Open - National 0.00 Canceled 2018-01-16 2018-02-06 2018-03-22 2018-04-19 2018-05-19 2018-06-23 2018-07-28 2019-07-28 mining programmes, efficient Based Selection technologies and practies in the mining and steel sector Page 5 MINDIVER/QCBS/CS/011-18 / Develop Mines Inspectorate for ASM field inspection and recommend how to equip the Quality And Cost- Under IDA / 59900 Prior Open - National 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-01 2018-07-31 2018-09-04 2018-10-09 2019-10-09 Mines Inspectorate with Based Selection Implementation appropriate and modern technical and logistics equipment and tools MINDIVER/QCBS/CS/013-18 / Consultancy to assist with identification of revenue Quality And Cost- Under leakages, strengthen revenue IDA / 59900 Post Open - National 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-01 2018-07-31 2018-09-04 2018-10-09 2019-10-09 Based Selection Implementation assessment and develop action plan to combat smuggling MINDIVER/IC/CS/015-17 / Consultancy to provide support to NGSA and MMSD for mineral Quality And Cost- Open - prospectivity testing, IDA / 59900 Prior 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 Based Selection International integration and packaging using satellite data-based foundation layers and collection of geodata MINDIVER/CQ/CS-018/18 / Conduct needs assessment of Consultant Under NIMG training infrastructure IDA / 59900 Post Qualification Open - National 0.00 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 Implementation and setup procurement Selection process for refurbishment MINDIVER/QCBS/CS/020-18 / Development of support action to improve the Quality And Cost- Under IDA / 59900 Post Open - National 0.00 2018-02-05 2018-02-26 2018-04-11 2018-05-09 2018-06-08 2018-07-13 2018-08-17 2019-08-17 Metallurgical and steel Based Selection Implementation Inspectorate including an initial baseline study MINDIVER/QCBS/CS/016-18 / Consultancy to provide advice in the dissemination of geological knowledge and Quality And Cost- Pending in particular by the IDA / 59900 Prior Open - National 0.00 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 Based Selection Implementation development of a web application portal and system architecture to support MMIS MINDIVER/QCBS/CS/019-18 / Design policy, regulatory framework & programmes to add value to mineral support centers, processing Quality And Cost- Open - Pending IDA / 59900 Prior 0.00 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 & fabricating activities Based Selection International Implementation together with the analysis of ecoN drivers to develop & impl a strategy to utilise domestic SS of minerals MINDIVER/QCBS/CS/022-18 / Consultancy to undertake needs assessment and evaluation addressing Quality And Cost- Open - Pending mineral value chain IDA / 59900 Prior 0.00 2018-08-03 2018-08-24 2018-10-07 2018-11-04 2018-12-04 2019-01-08 2019-02-12 2020-02-12 Based Selection International Implementation technical skills demand gap including analysis of extension benefits and opportunities. Page 6 MINDIVER/QCBS/CS/023-18 / Consultancy to assess and build capacity in mining Quality And Cost- Open - financing through design and IDA / 59900 Prior 0.00 Canceled 2018-01-04 2018-01-25 2018-03-10 2018-04-07 2018-05-07 2018-06-11 2018-07-16 2019-07-16 Based Selection International implementation of training programmes and support within financing institutions MINDIVER/QCBS/CS/025-18 / Institutional and Quality And Cost- IDA / 59900 Post Open - National 0.00 Canceled 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 Administrative restructuring Based Selection of the SMDF MINDIVER/QCBS/CS/026-18 / Design and implementation Quality And Cost- of a public/Private sector IDA / 59900 Prior Open - National 0.00 Canceled 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2019-08-27 Based Selection Investment funding framework for the SMDF MINDIVER/QCBS/CS/027-18 / Consultancy to advance selected 'proof of concept' Quality And Cost- Open - assets, assess their IDA / 59900 Prior 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-03 2018-04-02 2018-05-07 2018-06-11 2019-06-11 Based Selection International infrastructure needs and also assist with development of a tender strategy MINDIVER/QCBS/CS/029-18 / Design, develop and Quality And Cost- Open - Pending IDA / 59900 Prior 0.00 2018-01-12 2018-02-02 2018-03-18 2018-04-15 2018-05-15 2018-06-19 2018-07-24 2019-07-24 implement an integrated Based Selection International Implementation MMIS for the mining sector MINDIVER/QCBS/CS/030-18 / Advisory firm to prepare and implement a Road Map Quality And Cost- Under to catalyse the mineral IDA / 59900 Post Open - National 0.00 2018-03-31 2018-04-21 2018-06-04 2018-07-02 2018-08-01 2018-09-05 2018-10-10 2019-10-10 Based Selection Implementation Sector for Regional Development.(Economic corridor) MINDIVER/QCBS/CS/046-18 Quality And Cost- Open - IDA / 59900 Prior 748,247.59 Signed 2017-11-12 2017-12-03 2018-01-16 2018-02-13 2018-03-15 2018-04-19 2018-05-24 2019-05-24 / Project Management Office Based Selection International MINDIVER/CQ/CS/047-18 / International Consultant to Provide technical assistance on the geological and Consultant Open - Under mineralization IDA / 59900 Post Qualification 0.00 2017-09-19 2017-10-10 2017-11-23 2017-12-23 2018-01-27 2018-07-26 International Implementation characterisation of Selection pegmatites with potentials of Lithium, metals & REE in the Mining sector MINDIVER/CQ/CS/049-18 / Consultant Economic impact analysis Pending IDA / 59900 Post Qualification Limited 0.00 2017-03-12 2017-03-26 2017-04-25 2017-05-30 2017-11-26 (and Economic Linkages)in Implementation Selection the Mining Sector MINDIVER/QCBS/CS/053-18 / Design and implement a Quality And Cost- Open - Under strategy for developing IDA / 59900 Post 0.00 2018-01-31 2018-02-21 2018-04-06 2018-05-04 2018-06-03 2018-07-08 2018-08-12 2019-08-12 Based Selection International Implementation Nigeria’s gemstone and jewellery industry MINDIVER/CQ/CS/058-18 / Consultancy Service for Consultant design and Supervision of IDA / 59900 Post Qualification Open - National 0.00 Canceled 2018-05-21 2018-06-11 2018-07-25 2018-08-24 2018-09-28 2019-03-27 Road Construction under Selection 'proof of concept' . Page 7 MINDIVER/QCBS/CS-057/18 / Needs assessment and evaluation for accrediting Quality And Cost- Open - and certifying laboratories IDA / 59900 Prior 0.00 Under Review 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2021-08-26 Based Selection International including operationalization geological research laboratories MINDIVER/CQ/CS-059/18 / Consultant Consultancy Service for the IDA / 59900 Post Qualification Open - National 0.00 Canceled 2018-06-05 2018-06-26 2018-08-09 2018-09-08 2018-10-13 2019-04-11 Design and Supervision of Selection Renovation of NIMG,Jos MINDIVER/CQ/CS-054/18 / Consultancy Service for the Consultant Design and Supervision of IDA / 59900 Post Qualification Open - National 0.00 Canceled 2018-06-05 2018-06-26 2018-08-09 2018-09-08 2018-10-13 2019-04-11 Renovation of NGSA and Selection Dimension stone Laboratories in Kaduna MINDIVER/CQ/CS-034/18 / Consultant Consultancy Services for the Under IDA / 59900 Post Qualification Limited 0.00 2018-01-25 2018-02-08 2018-03-10 2018-04-14 2018-10-11 update of the Mineral and Implementation Selection Mining Act of 2007 MINDIVER/CQ/CS-028/18 / Consultancy services for the Consultant Under Development and IDA / 59900 Post Qualification Limited 0.00 2018-01-28 2018-02-11 2018-03-13 2018-04-17 2018-10-14 Implementation Implementation of Selection Communication Strategies MINDIVER/QCBS/CS/008-18 / Formalization of artisanal miners into cooperatives and small-scale miners into larget mineral and financial Quality And Cost- Open - IDA / 59900 Prior 0.00 Canceled 2018-03-15 2018-04-05 2018-05-19 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 enterprises together with the Based Selection International design and implememtation of an ASM remote sensing montoring system in the mining and steel sector MINDIVER/CQ/CS/0070-18 / ENGAGEMENT OF CONSULTING FIRM TO Consultant CARRY OUT NEEDS Under IDA / 59900 Post Qualification Limited 332,263.22 2018-07-16 2018-07-30 2018-08-29 2018-10-03 2019-04-01 ASSESSMENT AND Implementation Selection EVALUATION OF THE NIGERIAN GEOLOGICAL SURVEY AGENCY (NGSA) MINDIVER/CQ/CS-071/ -18 / Engagement of a Consulting firm to carry out Consultant Under a review of implemented IDA / 59900 Post Qualification Limited 0.00 2018-07-16 2018-08-15 2018-08-30 2018-10-04 2019-04-02 Implementation Nigeria Mineral Resources Selection Decision Support System (NMRDSS). MINDIVER/QCBS/CS/080/18 / Formalization of artisanal miners into cooperatives the Quality And Cost- Open - Under IDA / 59900 Prior 0.00 2018-07-30 2018-08-20 2018-09-10 2018-10-08 2018-11-07 2018-12-12 2019-01-16 2020-01-16 design and implememtation Based Selection International Implementation of an ASM remote sensing montoring system MINDIVER/QCBS/CS/081/18 / Institutional and Quality And Cost- Open - Under Administrative restructuring IDA / 59900 Prior 0.00 2018-08-10 2018-08-31 2018-10-14 2018-11-11 2018-12-11 2019-01-15 2019-02-19 2020-02-19 Based Selection International Implementation of the Solid Mineral Development Fund (SMDF) Page 8 MINDIVER/CQ/CS/088-18 / Engagement of Consultant to Consultant Support the MMSD in Under IDA / 59900 Post Qualification Open - National 0.00 2018-11-20 2018-12-11 2019-01-24 2019-02-23 2019-03-30 2019-09-26 developing and implementing Implementation Selection a strategy to revive the Tin Industry in Nigeria MINDIVER/CQ/CS/014-18 / Design and develop a mechanism for citizens Consultant Pending engagement and social IDA / 59900 Post Qualification Open - National 0.00 2019-03-31 2019-04-21 2019-06-04 2019-07-04 2019-08-08 2020-02-04 Implementation accountability in the Selection MinDiver Project and the Mining sector MINDIVER/CS/CQ/122-19 / Engagement of a Firm to Consultant prepare/update the Strategic Under IDA / 59900 Post Qualification Open - National 0.00 2019-02-05 2019-02-26 2019-04-11 2019-05-11 2019-06-15 2019-12-12 Environment and Social Implementation Selection Assesment (SESA) Report for Mindiver Project MINDIVER/CQ/CS/209-19 / Consultancy to design and Consultant implement safer and cleaner Pending IDA / 59900 Post Qualification Open - National 0.00 2019-05-01 2019-05-22 2019-07-05 2019-08-04 2019-09-08 2020-03-06 mining programmes, efficient Implementation Selection technologies and practices in the mining and steel sector MINDIVER/QCBS/CS/023B- 19 / Consultancy to assess and build capacity in mining Quality And Cost- Pending financing through design and IDA / 59900 Prior Open - National 0.00 2019-06-05 2019-06-26 2019-08-09 2019-09-06 2019-10-06 2019-11-10 2019-12-15 2020-12-14 Based Selection Implementation implementation of training programmes and support within financing institutions NG-MINDIVER-103077-CS- CQS / Engagement of Consulting Firm for Quality And Cost- Under preparation of BOQ and IDA / 59900 Post Open - National 0.00 2019-03-13 2019-04-03 2019-05-17 2019-06-14 2019-07-14 2019-08-18 2019-09-22 2020-09-21 Based Selection Implementation Supervision of ALL Works activities for the Mindiver Project. MINDIVER/CS/CQ/121/19 / Engagement of Firm for Quality And Cost- overall Quality Asurance of IDA / 59900 Post Open - National 0.00 Under Review 2019-06-19 2019-07-10 2019-08-23 2019-09-20 2019-10-20 2019-11-24 2019-12-29 2020-12-28 Based Selection the Production of Topographic Maps NG-MINDIVER-103090-CS- CQS / Engagement of Firm Quality And Cost- for overall Quality Assurance IDA / 59900 Post Open - National 0.00 Under Review 2019-04-20 2019-05-11 2019-06-24 2019-07-22 2019-08-21 2019-09-25 2019-10-30 2020-10-29 Based Selection of Airborne Geophysical Survey- 5percent MINDIVER/CQ/CS/082-19 / Engagement of Consultant to design and implement a Quality And Cost- IDA / 59900 Prior Open - National 0.00 Canceled 2019-04-26 2019-05-17 2019-06-30 2019-07-28 2019-08-27 2019-10-01 2019-11-05 2020-11-04 Framework to restructure Based Selection and reposition the Women in Mining in Nigeria MINDIVER/QCBS/CS/050-18 Quality And Cost- / Quality Assurance IDA / 59900 Prior Open - National 0.00 Canceled 2018-05-30 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2019-12-09 Based Selection Consultant Page 9 MINDIVER/QCBS/CS/012-18 / Design and implement an Quality And Cost- Open - Electronic Archiving IDA / 59900 Prior 0.00 Canceled 2018-02-28 2018-03-21 2018-05-04 2018-06-01 2018-07-01 2018-08-05 2018-09-09 2019-09-09 Based Selection International Management System for NGSA NG-MINDIVER-107441-CS- CQS / Engagement of Consultant to design and Consultant Pending implement a Framework to IDA / 59900 Post Qualification Limited 0.00 2019-05-14 2019-05-28 2019-06-27 2019-08-01 2020-01-28 Implementation restructure and reposition Selection the Women in Mining in Nigeria INDIVIDUAL CONSULTANTS Page 10