DAM REHABILITATION AND IMPROVEMENT PROJECT (DRIP) II (Funded by World Bank) SOM KAMLA AMBA DAM ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT February 2020 (Draft Report) Office of Additional Chief Engineer Water Resources Department Government of Rajasthan Water Resources Zone, Jaipur-302001 Tel: 0141-2702353, e-mail: acejpr.wr@gmail.com CONTENTS Page No. CHAPTER 1: INTRODUCTION 1.1 PROJECT OVERVIEW 1 1.2 SUB-PROJECT DESCRIPTION – SOM KAMLA AMBA DAM 2 1.3 PURPOSE OF ESIA 7 1.4 APPROACH AND METHODOLOGY OF ESIA 7 CHAPTER 2: LEGAL, REGULATORY AND INSTITUTIONAL FRAMEWORK 2.1 APPLICABILITY ANALYSIS OF INDIAN REGULATION 8 2.2 APPLICABILITY ANALYSIS OF WB ENVIRONMENT AND SOCIAL FRAMEWORK 19 2.3 INSTITUTIONAL FRAMEWORK 22 CHAPTER 3: OVERVIEW OF ENVIRONMENTAL AND SOCIAL CONDITIONS 3.1 PHYSICAL ENVIRONMENT 23 3.2 BIOLOGICAL ENVIRONMENT 25 3.3 PROTECTED AREA 26 3.4 SOCIAL ENVIRONMENT 26 3.5 CULTURAL ENVIRONMENT 27 CHAPTER 4: STAKEHOLDERS CONSULTATION 4.1 STAKEHOLDERS CONSULTATION 28 CHAPTER 5: ENVIRONMENTAL & SOCIAL RISKS AND IMPACTS 5.1 ASSESSMENT AND MANAGEMENT OF E&S RISK AND IMPACT (ESS 1) 30 5.2 LABOUR AND WORKING CONDITIONS (ESS 2) 31 5.3 RESOURCE EFFICIENCY AND POLLUTION PREVENTION AND MANAGEMENT (ESS 3) 32 5.4 COMMUNITY HEALTH AND SAFETY (ESS 4) 35 5.5 INDIGENEOUS PEOPLE/SUB-SAHARAN AFRICAN HISTORICALLY UNDERSERVED TRADITIONAL LOCAL COMMUNITIES (ESS 7) 36 CHAPTER 6: ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN 6.1 ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN 37 6.2 MONITORING REPORTING AND BUDGETING 41 6.3 ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) AND OTHER REQUIREMENTS 41 List of Tables Table 2.1: Applicability Analysis 9 Table 2.2: Relevance and requirements ESF Policy, Standards and Directives 19 Table 3.1: Water Quality of Som Kamla Amba Reservoir 24 List of Figures Figure 1.1: Selected Photographs of Improvement/Intervention area 5 Figure 1.2: Project Area showing major intervention locations 6 Figure 3.1: Land Use and Land Cover Map of 5 Km radius around Dam site 23 Figure 3.2: Map showing location of Protected Areas wrt Som Kamla Amba Dam 26 List of Annexures Annexure I: Socio-economic Profile of Proximity villages (Study Area) 42-50 ABBREVIATIONS AND ACRONYMS AIBP : Accelerated Irrigation Benefit Program AIDS : Acquired Immunodeficiency Syndrome ASHA : Accredited Social Health Activist ASI : Archaeological Survey of India AWS : Automatic Weather Station BOCWW : Building and Other Construction Workers Welfare CCA : Culturable Command Area CPCB : Central Pollution Control Board CRZ : Coastal Regulation Zone CWC : Central Water Commission DEIAA : District Environment Impact Assessment Authority DRIP : Dam Rehabilitation and Improvement Project EAP : Emergency Action Plan ERP : Emergency Response Procedure ESCP : Environmental and Social Commitment Plan ESF : Environmental and Social Framework ESIA : Environmental and Social Impact Assessment ESS : Environmental and Social Standards FI : Financial Intermediaries FSI : Forest Survey of India GBV : Gender Based Violence GCA : Gross Command Area GIS : Geographic Information System GRM : Grievance Redressal Mechanism HIV : Human Immunodeficiency Virus ICDS : Integrated Child Development Services ID&R : Investigation Design & Research IGND : Indira Gandhi Nahar Division IPF : Investment Project Financing IS : Indian Standards JICA : Japan International Cooperation Agency JTU : Jackson Turbidity Unit LMC : Left Main Canal LMP : Labour Management Procedure MCM : Million Cubic Meters MDDL : Minimum Draw Down Level MJSA : Mukhyamantri Jal Swavlamban Abhiyan MOEF&CC : Ministry of Environment, Forest & Climate Change MSDS : Material Safety Data Sheets MSIHC : Manufacture Storage & Imports of Hazardous Chemicals MWL : Maximum Water Level NAAQS : National Ambient Air Quality Standards NH : National Highway NTU : Nephelometric Turbidity Unit O&M : Operation & Maintenance OBC : Other Backward Class OHS : Occupational Health & Safety PESO : Petroleum and Explosives Safety Organization PMKSY : Pradhan Mantri Krishi Sinchayee Yojana PMU : Project Management Unit PPE : Personal Protective Equipment PST : Project Screening Template PUC : Pollution Under Control PWD : Public Work Department RCC : Reinforced Cement Concrete RMC : Right Main Canal SC : Scheduled Castes SCADA : Supervisory Control and Data Acquisition SEF : Stakeholder Engagement Framework SEIAA : State Environment Impact Assessment Authority SH : State Highway SHG : Self-Help Group SPCB : State Pollution Control Board SPMU : State Project Management Unit ST : Scheduled Tribe TMC : Thousand Million Cubic Feet WLS : Wildlife Sanctuary WRD : Water Resources Department Chapter INTRODUCTION 1 1.1 PROJECT OVERVIEW The proposed Dam Rehabilitation and Improvement Project (DRIP-2) would complement the suite of ongoing and pipeline operations supporting India’s dam safety program. The project would continue to finance structural improvements but would break with the prevailing build-neglect-rebuild approach by giving greater emphasis to establishing sustainable mechanisms for financing regular O&M and dam rehabilitation, enhancing State capabilities to manage these critical assets through institutional strengthening, and introducing risk- informed dam safety management. The project development objective (PDO) is to increase the safety of selected dams and to strengthen institutional capacity for dam safety in participating States. Project Components include: Component 1: Institutional Strengthening (US$ 40 million): This component supports further strengthening of dam safety management in the country through institutional modernization. A major focus of activities under this component will be increasing the oversight of dam safety by developing dam safety guidelines and by strengthening the capacity of various dam safety actors to carry out the regulatory functions defined in the proposed Dam Safety Bill, which has been passed by the Lok Sabha. Component 2: Risk-informed Asset Management and Sustainable Financing (US$ 25 million): This component supports identifying long-term funding needs for dam safety based on asset management and risk assessment financing for dam safety. This component would focus on: (i) improving the efficiency of public financing; (ii) generating alternative revenue streams Alternative revenue streams that could be developed include tourism and water recreational activities, fisheries, and other innovative schemes such as floating solar panels; and (iii) establishing financing arrangements for dam safety (e.g., dedicated budget lines). Component 3: Rehabilitation of Dams and Appurtenant Structures (US$ 200 million): This component supports improving the safety of dams through structural and non-structural interventions. Structural measures could include measures for seepage reduction (e.g., grouting, geomembranes), hydrological and structural safety measures (e.g., additional spillways, fuse plugs), enhancing the reliability of operational facilities (e.g., gates), rehabilitating foundation deficiencies, strengthening dam concrete/embankment structures, and improving basic dam facilities (e.g., access roads). Non-structural measures could include standardized dam safety instrumentation, monitoring, assessment and reporting protocols for dam health; flood forecasting and early warning systems; integrated reservoir operations including streamflow forecasting for climate resilient dam management; preparation and implementation of EAPs; preparation and implementation of sediment management plans; and revised operational rule curves to account for climate change. 1 Component 4: Project Management (US$ 15 million): This component will ensure effective implementation of project activities and monitoring and evaluating project implementation progress, outputs and outcomes. The component will support: (i) establishment of the Central Project Management Unit (CPMU), which will oversee and coordinate activities of the implementing agencies of the project, supported by a Engineering and Management Consultant (EMC), which is currently being procured; (ii) establishment and operations of State level Project Management Units (SPMUs) within State implementing agencies, which can hire experts in various fields as and when needed on a contractual basis; (iii) setting up of a monitoring and evaluation system; and (iv) establishment of a Quality Assurance and Quality Control system. This component will also finance consultancies, as well as related material, office equipment and incremental operating costs. The project will provide investment and technical support for the establishment of a Management Information System and Information and Communication Technology systems. 1.2 SUB-PROJECT DESCRIPTION – SOM KAMLA AMBA DAM The construction of Som Kamla Amba Project across Som river, a tributary of Mahi river was completed in the year 1992. The dam is located in Ashpur Tehsil of Dungarpur District, Rajasthan to provide the Irrigation cum drinking water facilities. The dam supplies drinking water to the tune of 8.1 MCM., besides irrigation supply to 26998.6 ha of Gross Command Area (GCA) and 19155.42 ha of Culturable Command Area (CCA). Salient features of the project area as reported below: Project Som Kamla Amba Project River Som river, a tributary of Mahi Lat/Long 230 58' 00''/ 740 02' 00'' GCA 26998.60 ha CCA 19155.42 ha Annual water supply 8.01 MCM Catchment Area 5376 sq km Main Dam Type Earthen Dam Length 620 m Top elevation 217.50 m Height of dam above lowest river 27 m bed level Lowest river bed level 190.5 m Spillway Type Ogee spillway Length 244 m Location of spillway Central spillway Crest level 335.40 m Number of bays 13 Discharge capacity at MWL 20045 cumec Size of spillway gate 15 m wide and 12.885 m high Reservoir Maximum water level 215.50 m Full Reservoir Level 33.50 m MDDL 200.50 m Live storage 160.30 MCM Gross storage 172.80 MCM Reservoir spread area 36.18 sq km Year of start of construction 1977 Date of completion 1992 Year of first impoundment 2004 2 View of the Dam Proposed Interventions/ Activities at Som Kamla Amba Dam The following rehabilitation proposals have been formulated and same are described in PST. Present ESIA report has been prepared for these proposals/interventions: Structural Rehabilitation Works Civil Work including Paint 1. Resetting of disturbed upstream (U/S) Rip Rap 2. Cleaning/Reaming of drainage holes in dam gallery 3. Repairs to parapet walls of dam 4. Extension of downstream (D/S) guide walls right side ( R/S) of dam & repair of left side ( L/S) ,downstream( D/S) guide wall 5. General maintenance and upkeep of 13 No’s radial gates and hoist bridge of dam 6. Construction of toe drain for seepage control at saddle no 2 & 3 7. Repair and renovation of gallery 8. Construction of control room for new DG set 9. Repair of Damages to piers of spillway Electro-mechanical Work 10. Repair /replacement of canal sluice gate of LMC, RMC & Bhabhrana 11. General maintenance and up keeping of 13 No’s radial gates and hoist bridge 12. Supply and installation of one 180 KVA DG Set 3 13. Providing Lighting over Dam and surrounding area 14. Lighting arrangement of foundation gallery 15. Repairs of Gantry Crane 16. Supply and fixing of new steel wire rope of 09 nos. radial gates 17. Renovation of centralized control system for operating of 13 Nos. radial crest gates Basic facilities improvement 18. Renovation of Approach Road to dam upto Karakala Dam Site Entry Gate 19. Renovation of existing rest house and surrounding area of dam 20. Providing and installing of lightning arrester at dam 21. Renovation of control room tower of dam Instrumentation, SCADA, Surveillance system, etc 22. Installation of instrumentation on Dam Figures 1.1 and 1.2 provide photographs of key infrastructure proposed for rehabilitation works and also major interventions locations. Implementation Schedule Timelines for implementing above proposals has been proposed as 36 months. Broken wire rope of Gate no 4,5,6,7,8 & 10 Damaged D/S left side guide wall Damaged bridge parapet wall Non-functional driving units of gantry crane 4 Damaged magnetic breaks of Dam radial gate Leaching in dam foundation gallery Damaged rubber seal of dam radial gate Damaged Dam approach road Damaged pathways for Rusting of radial gates and hoist bridge gallery approach from rest house arrangement of Dam Disturbed Rip Rap of U/S face of Dam Seepage on D/S from saddle 2 & 3 due to damaged toe drain Figure 1.1: Selected Photographs of Improvement/Intervention area 5 Figure 1.2: Project Area showing major intervention locations 6 1.3 PURPOSE OF ESIA The overall project (DRIP II) was categorized as High Risk as per the internal Environment and Social Risk Classification of the Bank. Hence, a separate agency was contracted to conduct the Environment and Social Impact Assessment to use it as a tool for decision- making on the sub-project. Specifically, the objectives of the ESIA are: i. To identify, evaluate and manage the environment and social risks and impacts of the project in a manner consistent with the ESSs; ii. To adopt a mitigation hierarchy approach to the project’s E&S risks i.e. a) anticipate and avoid risks and impacts; b) minimize or reduce risks and impacts to acceptable levels, if not avoidable; c) once risks and impacts have been minimized or reduced, mitigate; and (d) where significant residual impacts remain, compensate for or offset them, where technically and financially feasible; iii. To help identify differentiated impacts on the disadvantaged or vulnerable and to identify differentiated measures to mitigate such impacts, wherever applicable; iv. To assess the relevance and applicability of environmental and social institutions, systems, laws, regulations and procedures in the assessment, development and implementation of projects, whenever appropriate; identify gaps, if any exist, and v. To assess borrower’s existing capacity, gaps therein, and identify a reas for enhanced capacity towards management of E&S risks. 1.4 APPROACH AND METHODOLOGY OF ESIA The following approach has been adopted for ESIA: i. Study sub-project information, proposed interventions, their magnitude and locations and carry out assessment of each proposed intervention to identify the magnitude of E&S risk and impacts; ii. Conduct site visit to understand baseline environment and social settings, proposed activities under the sub-project, their location and sensitivity, if any. iii. Conduct stakeholder consultations to help identify potential stakeholders; to provide information on the proposed interventions; to identify issues and concerns; and finally ascertain appropriate mechanisms for continued engagement iv. Prepare baseline data essential for impact assessment in immediate vicinity area of proposed interventions from secondary sources, such as land-use, protected areas in vicinity, habitation, access roads, ascertain presence of indigenous (schedule tribe)/vulnerable people, etc. v. Review relevance and applicability of national and state legal requirements and Bank’s ESF policy, standards and directives and preliminary assessment of impacts as per ESS framework (2-8), suggest mitigation measures in accordance with the requirements of each applicable standard vi. Undertake institutional assessment to identify existing capacities & relevant gaps to manage E&S risks and impacts All formats used for collection of the above information, checklists used for consultations and photographs towards preparation of the Draft ESIA report are available in the project files. 7 Chapter LEGAL, REGULATORY, AND 2 INSTITUTIONAL FRAMEWORK India has well defined environmental and social regulatory framework. The regulation applicability depends on nature of work and location of work. Broadly legislation can be divided into four categories viz environmental, social, wildlife protection, and forests conservation. The applicability of environmental laws to dam are mostly at setting up new dams compared to rehabilitation stage. The applicability analysis of regulations pertaining to all the above four categories is carried out and summarized at section 2.1. Central Water Commission, Ministry of Jal Shakti, Government of India has also prepared “Operational Procedures for Assessing and Managing Environmental Impacts in Existing Dam Projects� as a guiding document for the dam owners to systematically address in advance the environmental safeguard requirements and have discussed in detail all applicable legal requirement. Reference has been drawn from this document as well while carrying out applicability analysis. The World Bank ESF comprises 10 ESSs (ESS1 to ESS10) and 2 Directives. The applicability of each standard to the proposed rehabilitation proposals and standard specific requirements is analysed and presented at Section 2.2. 2.1 APPLICABILITY ANALYSIS OF INDIAN REGULATION The regulatory applicability analysis to the proposed rehabilitation work has been carried out considering nature of improvements, methodology of construction/improvement, material requirement, sourcing and transportation mode, and waste generation. The regulatory applicability analysis is summarised at Table 2.1 below. 8 Table 2.1: Applicability Analysis S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability 1 Environment Protection To protect and improve overall Yes Applicable to all None MoEF&CC Act/Rules-1986 environment activities in general 2 The Forest (Conservation) To help conserve the country's forests. No No diversion of forest None Forest Department Act, 1980 and amendments It strictly restricts and regulates the de- land involved and The Forest reservation of forests or use of forest (conservation) Rules 1981 land for non-forest purposes without and amendments the prior approval of the Government. To this end the Act lays down the pre- requisites for the diversion of forest land for non-forest purposes 3 Rajasthan Forest Act, 1953 Conservation of forest and control No No tree will be felled None Forest Department felling of trees for proposed intervention 4 Coastal Regulation Zone To regulate development activities No Project is not located None SCZMA, (CRZ) notification 2011 and within the 500 m of high tide line in in coastal area amendment till date coastal zone and 100 m of tidal influence rivers. 5 Air (Prevention and Control An act to prevent and control Air Yes Air pollution from Consent to SPCB of Pollution) Act, 1981, 1987 pollution proposed activities establish and During construction operate by stage contractor for operation of DG sets and any other air pollution system like ready mix plant etc. 6 Water Prevention and An Act to prevent and control water Yes Water pollution from Consent to SPCB Control of Pollution) Act, pollution. proposed activities establish and 1974, 1988 during construction operate by stage contractor for setting up construction camp/labour camp 9 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability 7 Noise Pollution (Regulation Ambient Noise Standards for different Yes Noise emission from None CPCB & SPCB and Control Act) 2000 and areas and zones proposed activities amendment till date during construction stage like operation of DG sets 8 Hazardous & Other Waste ( Protection to general public against Yes Hazardous waste Authorisation for SPCB Management and Trans- improper handling storage and disposal generation from handling of boundary Movement) of hazardous waste. The rules prescribe proposed activities hazardous wastes Rules, 2016 the management requirement of like generation of hazardous wastes from its generation paints waste, used to final disposal. oil/waste oil. 9 Manufacture Storage, & Usage and storage of hazardous Yes Painting is proposed Arrange MSDS and Chief Inspector of imports of Hazardous substances which will require use store quantity of Factories Chemicals (MSIHC) Rules, of solvents/thinners hazardous 1989 as amended till date which will falls under chemicals below hazardous chemicals threshold quantity category 10 The Batteries (Management To regulate the disposal and recycling No Batteries will not be None SPCB and Handling) Rules 2001 of lead acid batteries used for proposed activities 11 Construction and Demolition To manage the demolition and Yes Construction and Contractor needs Local bodies of the Waste Management Rules , construction waste and prevent demolition waste will to submit plan for area 2016 environmental degradation be generated from reuse or safe proposed activities disposal 12 Solid Waste Management To manage solid waste or semi-solid Yes Solid Waste will be Contractor needs Local bodies of the Rules, 2016 domestic waste, sanitary waste, generated from to submit plants area proposed activities for its safe due to influx of disposal/burial labour 13 Motor Vehicle Act 1988 and To minimize the road accidents, Yes Transportation of None Motor Vehicle amendment till date penalizing the guilty, provision of manpower and Department compensation to victim and family and material (Licensing authority, check vehicular air and noise pollution. registration authority &State Transport Authorities) 10 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability 14 The Gas Cylinder Rules 2016 To regulate the storage of gas / Yes gas cylinders will be None PESO possession of gas cylinder more than used during welding the exempted quantity. and other electromechanical work. Storage within threshold quantity and as per capability analysis. Handling with define safe practices 15 Ancient Monuments and Conservation of cultural and historical Yes Presence of historical None Archaeological Archaeological Sites and remains found in India. sites of archaeological Dept. Gol Remains Act, 1958 importance 16 Building and Other To regulate the employment and Yes Involvement of None Labour Construction Workers conditions of service of buildings and workforce/labour Commissioner (Regulation of Employment other construction workers and to and Conditions of Service) provide for their safety, health and Act, 1996 welfare measures and for other matters connected therewith or incidental thereto. 17 Plastic waste management To manage the plastic waste generated Yes Plastic waste None Local bodies of the Rules, 2016 so as it does not affect the water generation from area pipeline, animals and other proposed activities. environmental components Safe disposal as per Rules 18 E-Waste Management Rules, Protection of environment against Yes E-waste generation None CPCB &SPCB 2016 improper handling storage and disposal from replacement of of hazardous waste. instrumentation. Safe disposal as per rules 19 Rajasthan Minor, Mineral Control of extraction, collection and Yes requirement of None Mines Department/ Concession Rules, 2017 removal of minor minerals construction material DEIAA/SEIAA from quarries and borrow areas 20 The Right to Fair Regulates land acquisition and lays No Land Acquisition is None Revenue Compensation and down the procedure and rules for not involved Department/District Transparency in Land granting compensation, rehabilitation Administration 11 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability Acquisition, Rehabilitation and resettlement to the affected and Resettlement Act, 2013 persons 21 Rights of Persons with Ensures that the Persons with Disability Yes Persons with None Disabilities Act, 2016 (PWD) enjoy the right to equality, life disability with dignity, and respect for his or her own integrity equally with others. 22 Right To Information Act, Mandates timely response to citizen Yes Borrower is None Any Government 2005 requests for government information government Department organization 23 Article 366 (25) of the Defines following essential Yes Dam is located in None Government of Constitution of India characteristics, for a community to be Scheduled Area India Article 244(1) of Constitution identified as Scheduled Tribes are; of India - The Fifth Schedule • Indications of primitive traits; under Article 244(1) of a • Distinctive culture; subsequent Act of • Shyness of contact with the Constitution community at large; “Scheduled Areas� as such • Geographical isolation; and areas as the President may • Backwardness. by order declare to be Scheduled Areas after The criteria for declaring any area as a consultation with Governor “Scheduled Area� under the Fifth of that State. Schedule are; (a) preponderance of tribal population, (b) compactness and reasonable size of the area, (c) a viable administrative entity such as a district, block or Taluka, and (d) economic backwardness of the area as compared to the neighbouring areas. 24 Scheduled Tribes and Other To recognize and vest the forest rights No No such activities None Ministry of Tribal Traditional Forest Dwellers and occupation in forest land in forest impacting tribes and Affairs (Recognition of Forest dwelling STs and other traditional their rights are Rights) Act, 2006 forest dwellers who are residing in such proposed forests for generations but whose 12 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability rights could not be recorded. Its objective is to facilitate the overall development and welfare of the tribal people by empowering them socially, economically, politically without any impact on their culture, habitation and tradition and in terms of their age old rights and privileges. 25 Panchayats (Extension to the The Gram Sabha or the Panchayats at No As no structural None Concerned State Scheduled Areas) Act, 1996 the appropriate level shall be consulted intervention is Government and before making the acquisition of land in planned. Only Tribal Welfare the Scheduled Areas for development awareness generation Department projects and before re-settling or on EAP preparation rehabilitating persons affected by such and implementation projects in the Scheduled Areas. shall take place in these areas. 26 Major Labour Laws Applicable To Establishments Engaged In Building And Other Construction Work 1 Employees Compensation The Act provides for compensation in Yes Contractor/Labour None Commissioner for Act 1923 case of injury, disease or death arising engagement Workmen’s out of and during the course of Compensation employment. 2 Payment of Gratuity Act 1972 Gratuity is payable to an employee Yes Contractor/Labour None Chief Labour under the Act on satisfaction of certain engagement Commissioner conditions on separation if an employee has completed 5 years’ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees. 3 Employees P.F. and The Act provides for monthly Yes Contractor/Labour None Ministry of Labour Miscellaneous Provision Act contribution by the employer plus engagement 1952 (since amended) workers @ 10% or 8.33%. The benefits payable under the Act are: 13 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability 4 Maternity Benefit Act 1961 The Act provides for leave and some Yes Contractor/Labour None Chief Labour other benefits to women employees in engagement Commissioner case of confinement or miscarriage etc. 5 Sexual Harassment of This Act defines sexual harassment in Yes Contractor/Labour None District Officer Women at the Workplace the workplace, provides for an enquiry engagement (District Magistrate (Prevention, Prohibition and procedure in case of complaints and or Additional Redressal) Act, 2013 mandates the setting up of an Internal District Magistrate Complaints Committee or a Local or the Collector or Complaints Committee Deputy Collector) 6 Contract Labour (Regulation The Act provides for certain welfare Yes Contractor/Labour None Chief labour & Abolition) Act 1970 measures to be provided by the engagement Commissioner Contractor to contract labour and in case the Contractor fails to provide, the same are required to be provided, by the Principal Employer by law. The Principal Employer is required to take Certificate of Registration and the Contractor is required to take license from the designated Officer. The Act is applicable to the establishments or Contractor of Principal Employer if they employ 20 or more contract labour. 7 Minimum Wages Act 1948 The Employer is supposed to pay not Yes Contractor/Labour None Chief labour less than the Minimum Wages fixed by engagement Commissioner appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employments. 8 Payment of Wages Act 1936 It lays down the mode, manner and by Yes Contractor/Labour None Chief labour what date the wages are to be paid, engagement Commissioner what deductions can be made from the wages of the workers. 9 Equal Remuneration Act The Act provides for payment of equal Yes Contractor/Labour None Chief labour 1976 wages for work of equal nature to male engagement Commissioner and female workers and for not making discrimination against Female 14 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability employees in the matters of transfers, training and promotions etc. 10 Payment of Bonus Act 1965 The Act is applicable to all Yes Contractor/Labour Chief labour establishments employing 20 or more engagement Commissioner employees. Some of the State Governments have reduced this requirement from 20 to 10. The Act provides for payments of annual bonus subject to a minimum of 8.33% of the wages drawn in the relevant year. It applies to skilled or unskilled manual, supervisory, managerial, administrative, technical or clerical work for hire or reward to employees who draw a salary of Rs. 10,000/- per month or less. To be eligible for bonus, the employee should have worked in the establishment for not less than 30 working days in the relevant year. The Act does not apply to certain establishments. 11 Industrial Disputes Act 1947 the Act lays down the machinery and Yes Contractor/Labour None Ministry of Labour procedure for resolution of Industrial engagement and Employment disputes, in what situations, a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment. 12 Trade Unions Act 1926 The Act lays down the procedure for Yes Contractor/Labour None Ministry of Labour registration of trade unions of workmen engagement and Employment and employers. The Trade Unions registered under the Act have been given certain immunities from civil and criminal liabilities. 13 Child Labour (Prohibition & The Act prohibits employment of Yes Contractor/Labour None Chief labour Regulation) Act 1986 children below 14 years of age in certain engagement Commissioner occupations and processes and provides 15 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability for regulation of employment of children in all other occupations and processes. Employment of Child Labour is prohibited in the Building and Construction Industry. 14 Inter-State Migrant The Act is applicable to an Yes Contractor/Labour None Chief labour workmen’s (Regulation of establishment which employs 5 or more engagement Commissioner Employment & Conditions of inter-state migrant workmen through Service) Act 1979 an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The Inter-State migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc. 15 The Building and Other All the establishments who carry on any Yes Contractor/Labour None Chief labour Construction Workers building or other construction work and engagement Commissioner (Regulation of Employment employ 10 or more workers are covered and Conditions of Service) under these Acts. All such Act 1996 and the Building establishments are required to pay cess and Other Construction at the rate not exceeding 2% of the cost Workers Welfare Cess Act, of construction as may be notified by 1996 (BOCWW Cess Act) the Government. The Employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as Canteens, First – Aid facilities, Ambulance, Housing accommodations for workers near the work place etc. The Employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government. 16 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability 16 Factories Act 1948 the Act lays down the procedure for Yes Contractor/Labour None Chief Inspector of approval of plans before setting up a engagement Factories factory engaged in manufacturing processes, health and safety provisions, welfare provisions, working hours, annual earned leave and rendering information regarding accidents or dangerous occurrences to designated authorities. It is applicable to premises employing 10 persons or more with aid of power or 20 or more persons without the aid of power. 17 Bonded Labour System The Act provides for the abolition of Yes Contractor/Labour None Chief labour (Abolition) Act, 1976 bonded labour system with a view to engagement Commissioner preventing the economic and physical exploitation of weaker sections of society. Bonded labour covers all forms of forced labour, including that arising out of a loan, debt or advance. 18 Employer’s Liability Act, 1938 This Act protects workmen who bring Yes Contractor/Labour None Chief labour suits for damages against employers in engagement Commissioner case of injuries endured in the course of employment. Such injuries could be on account of negligence on the part of the employer or persons employed by them in maintenance of all machinery, equipment etc. in healthy and sound condition. 19 Employees State Insurance The Act provides for certain benefits to Yes Contractor/Labour None Chief labour Act 1948 insured employees and their families in engagement Commissioner case of sickness, maternity and disablement arising out of an employment injury. The Act applies to all employees in factories (as defined) or establishments which may be so notified by the appropriate Government. The Act provides for the 17 S. No. Legislation Purpose Applicability Reason Type of Administrative permit/specific Authority action and stage of applicability setting up of an Employees’ State Insurance Fund, which is to be administered by the Employees State Insurance Corporation. Contributions to the Fund are paid by the employer and the employee at rates as prescribed by the Central Government. The Act also provides for benefits to dependents of insured persons in case of death as a result of an employment injury. 20 The Personal Injuries This Act provides for the employer’s Yes Contractor/Labour None Chief labour (Compensation Insurance) liability and responsibility to pay engagement Commissioner Act, 1963 compensation to employees where workmen sustain personal injuries in the course of employment. 21 Industrial Employment It is applicable to all establishments Yes Contractor/Labour None Chief labour (Standing Order) Act 1946 employing 100 or more workmen engagement Commissioner (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the Employer on matters provided in the Act and get the same certified by the designated Authority. 18 2.2 APPLICABILITY ANALYSIS OF WB ENVIRONMENTAL AND SOCIAL FRAMEWORK STANDARDS The World Bank Environmental and Social Framework comprises Policy, 10 standards and 2 Directives. The applicability of these standard vary depending on nature of activities. This applicability analysis is presented at Table 2.2 below. Table 2.2: Relevance and requirements ESF Policy, Standards and Directives ESF Policy, Standards Applicable Activities Applicability / Requirements and Directives & Guidelines ESS1: Assessment and All projects, sub-projects and associated facilities Applicable Management of (a) Conduct an environmental and social assessment of the proposed project, Environmental and including stake- holder engagement; Social Risks and (b) Undertake stakeholder engagement and disclose appropriate information in Impacts accordance with ESS10; (c) Develop an ESCP, and implement all measures and actions set out in the legal agreement including the ESCP; and (d) Conduct monitoring and reporting on the environmental and social performance of the project against the ESSs ESS2: Labour and Engagement of labour for various civil, paint and Applicable Working Conditions electro-mechanical or any other activities as part of a) Preparation of Labour Management Procedures applicable to the project. rehabilitation proposal. It applies to project workers b) Preparation of Grievance Mechanism and sharing with all the workers including full- time, part-time, temporary, seasonal c) Design and Implement OHS measures and migrant workers. It covers working conditions, protecting workforce, Grievance Mechanism and Occupational Health and Safety (OHS). ESS3: Resource Resource consumption and pollution generation from Applicable Efficiency, Pollution proposed activities (civil, electromechanical and paint a) To assess the resource requirement and implement technically and financially Prevention and work). This includes both hazardous and non- feasible measures for improving efficient consumption of energy, water and raw Management hazardous chemical pollutants in the solid, liquid, or materials, as well as other resources. gaseous phases b) Preparation of Resource Efficiency and Pollution Prevention Plan to assess and minimize/control the concentration of release of pollutants to air, water and land due to routine, non-routine, and accidental circumstances, and with the potential for local, regional, and transboundary impacts. ESS 4: Community Applies to potential risks and impacts on Applicable Health and Safety communities that may be affected by project a) Pollution from project activities and labour colony and increased traffic causing activities such as transportation of material to pollution and road safety risks on village roads during transportation of project site through village roads, labour colony material. 19 ESF Policy, Standards Applicable Activities Applicability / Requirements and Directives & Guidelines housing migrant workers near the project site, b) Preparation of Emergency Response Procedure (ERP) to prevent injuries to pollution generation from civil and electro- health and safety of the community during an emergency event arising from mechanical work. both natural and man-made hazards, typically in the form of fire, explosions, leaks or spills, flooding, etc. ESS 5: Land Acquisition, Applies to permanent or temporary physical and Not Applicable Restrictions on Land economic displacement resulting from land Proposed interventions are limited to the existing dam and will take place on the use and Involuntary acquisition or restrictions on land use undertaken or existing dam structure and within its premises. Any of the proposed Resettlement imposed in connection with project implementation. activities/interventions, does not involve acquisition of private land and/or private assets. These activities in no way cause restriction on access to land or use of resources by local communities and there is no economic displacement envisaged due to the sub-project. ESS 6: Biodiversity Applies to all projects that potentially affect Not Applicable Conservation and biodiversity or habitats, either positively or The present interventions do not involve any tree cutting or impacting any forest Sustainable negatively, directly or indirectly, or that depend upon area in any way. Activities remain limited to the dam premises only. Impacts on Management of Living biodiversity for their success. wildlife including that on fish fauna in the reservoir and river are negligible due the Natural resources nature and location of activities proposed under this sub-project. There is no national park/wildlife sanctuary/Conservation Reserve within 10 Km of the project. No direct or indirect impacts on biodiversity are envisaged due to proposed interventions. ESS 7: Indigenous Applies to traditional communities or schedule Applicable Peoples/Sub-Saharan tribes, if they are present or have collective The whole district is a Schedule V area, even though the project interventions do African Historically attachment to a proposed project area, as not directly or indirectly impact schedule tribe. Though there are scheduled tribe Underserved Tradition determined during the environmental and social population in the downstream, they will be involved in non-structural interventions Local Communities assessment. This ESS applies regardless of whether such as in the preparation of the Emergency Action Plans. such Communities are affected positively or negatively, and regardless of the significance of any such impacts. ESS 8: Cultural Heritage Applies to all projects that are likely to have Not Applicable – risks/impacts on cultural heritage Project is not directly or indirectly impacting any cultural heritage as no such sites are in proximity to the project site. Access to temples/religious places in surrounding villages will not be blocked/hampered dur to any of the proposed interventions as such activities are limited to dam premises only. ESS 9: Financial Applies to Financial Intermediaries (FIs) that receive Not Applicable - Project does not have any FIs Intermediaries financial support from the Bank. FIs include public 20 ESF Policy, Standards Applicable Activities Applicability / Requirements and Directives & Guidelines and private financial services providers, including national and regional development banks, which channel financial resources to a range of economic activities across industry sectors. ESS 10: Stakeholder Applies to all projects supported by the Bank through Applicable for the dam as a whole and in particular in relation to the non-structural Engagement and Investment Project Financing. The Borrower will interventions involving Early flood Warning system having siren systems, Information Disclosure engage with stakeholders as an integral part of the broadcasting facilities, etc. project’s environmental and social assessment and Preparation of Stakeholder Engagement Plan project design and implementation Establishment of a project level GRM Environmental and This Directive applies to the Bank and sets out the Applies to Bank in addressing E&S aspects of this project Social Directive for mandatory requirements for the implementation of Investment Project the Environmental and Social Policy for Investment Financing Project Financing (IPF). Bank Directive This Directive establishes directions for Bank staff Applies to Bank in addressing E&S risks and impacts on disadvantaged and Addressing Risks and regarding due diligence obligations relating to the vulnerable persons or groups that are identified in this project Impacts on identification of, and mitigation of risks and impacts Disadvantaged or on, individuals or groups who, because of their Vulnerable Individuals particular circumstances, may be disadvantaged or or Groups vulnerable World Bank’s Guidance The document provides guidelines to address Not applicable as even though influx of skilled migrant labour in construction note on managing the issues and risks arising from influx of migrant labour works is likely, these labor will operate within the dam premises which is a risks of adverse leading to gender-based violence, forced labour etc. restricted access zone and distant from habitations. However, GBV related clauses impacts on would be included in the bid documents and sensitization/awareness trainings communities from would be provided to all dam personnel, contractors, etc. during implementation temporary project induced labor influx, 2016 21 2.3 INSTITUTIONAL FRAMEWORK The sub-project will be implemented by Water Resources Department (WRD, Rajasthan. The department has two distinct divisions – IGND (Indira Gandhi Nahar Division) and Water Resources Division. Water Resources Division who will be responsible for implementing the project and is headed by Principal Secretary. The mandate of WRD is: • Construction of major, medium and minor irrigation projects, • Operation and maintenance of existing tanks, canals and other irrigation structures are the prime function of the Irrigation Department. • Flood control measures and floods related remedial measures are also assigned to the Irrigation Department. • Construction of irrigation structures under various special schemes like PMKSY, MJSA, AIBP, JICA etc. are entrusted to the Irrigation department. • Collection of revenue pertaining to sale of water from tanks irrigating more than 1000 ha. of land is done by the Irrigation Department. However, collection of irrigation charges in respect of tanks Engineering irrigating less than 1000 ha. is assigned to the Patwaris of the Revenue Department. • Construction and maintenance of the rest houses of irrigation department, office buildings, residential buildings of the staff, gardens, parks, roads etc. Specifically, in respect of capacity to address E&S issues, WRD Rajasthan do not have inhouse expertise. Chief Engineer at SPMU and Executive Engineer at dam level look after all the aspects. Presently, no formal system is established for dealing with external complaints. 22 Chapter OVERVIEW OF ENVIRONMENTAL AND 3 SOCIAL CONDITIONS The baseline conditions are analysed based on secondary information and site observations and are presented in following order Physical, Biological, Protected area and Socio- economic profile. 3.1 PHYSICAL ENVIRONMENT Land Use/ Land Cover The project surrounding area’s land use and environmental sensitivity was analysed using GIS techniques. Landuse/land cover map for 5 Km radius around dam site is presented at Figure 3.1. As can be seen from the map, present land use upstream of dam is largely waterbody (reservoir), remaining land is agriculture and some part is scrub land. On downstream side, right bank is mainly agriculture land and left bank is mix of agriculture and scrub land. However, as discussed under chapter 2 on project description the project activities will be confined to dam body only and no activities are proposed beyond existing dam boundaries. Villages in close proximity to dam body are Kamla Amba and Karkoli on left bank, Salawata and Karkala on right bank. The dam is also approachable from left flank by covering a distance of 7 km from Jatana village. The distance of Dam from Dungarpur district HQ is 57 km and 6 km from Dungarpur to Aspur State Highway 54 (RJ SH 54). Nearest village from dam is Kamla Amba. Figure 3.1: Land Use and Land Cover Map of 5 Km radius around Dam 23 Ambient Air Quality and Noise Site-specific data of ambient air quality and sound levels at project site is not available. However, general observation is made during site visit that area is free from air and noise pollution. This is substantiated by the fact that the dam is away from habitation, traffic and industries and that there are no anthropogenic sources of air/noise pollution in the vicinity. Therefore, ambient air is clean and sound levels are observed low. They are expected to be well within the prescribed limits. Water Quality Water quality data of Som Kamla Amba reservoir was taken from “Ecology and Fisheries of selected Reservoirs of Southern Rajasthan�, a study by Sharma, V. K. and Kushal, D. K. of Central Inland Fisheries Research Institute (ICAR) Kolkata. Bull No. 138. Water in Som Kamla Amba reservoir remains clear imparting a greenish tinge. The water temperature varied from 17 in winter to 28°C in post-monsoon. The alkaline water (PH 7.4) is favorable for fish growth. Dissolved oxygen varied from 6.0 to 8.4 mg/l. Assessment of the productivity based on total alkalinity (122 mg/l) reflected the water body fairly productive. Calcium content of water ranged between 27 and 30 mg/l. Magnesium concentration was of high range (8.4- 21.6 mg/l). Chloride values fluctuated from 10.0 to 18.0 mg/l. Higher values of specific conductance (601 µMho/cm) supported the eutrophic character of the reservoir. Table 3.1 give water quality data. Table 3.1: Water Quality of Som Kamla Amba Reservoir Depth (in m) Surface 2 4 6 8 Water Summer 25.5 - - - - Temperature Post Monsoon 28 27.5 27 26.3 26 (deg C) Winter 17 16.5 16.4 16 - Summer 8.12 - - - - pH Post Monsoon 7.69 830 735 7.94 7.95 Winter 6.49 6.52 6.59 6.61 - Summer 8 - - - - DO (ppm) Post Monsoon 8.4 8 6 5.6 5.2 Winter 6 5.6 5.6 52 - Summer 205.8 - - - - Total alkalinity Post Monsoon 86 90 90 92 96 (ppm) Winter 95 1032 117.6 133.8 - Conductivity Summer 881 - - - - (micro- Post Monsoon 429 414 412 411 402 mhos/cm) Winter 494 495 502 505 - Natural Hazards Potential of natural hazards such as flooding and earthquake is not significant. Project is designed for a design flood value of 20500 cumec, revised design flood has been worked as 21767 cumec by CWC i.e. a nominal 6.18% increase. Project falls in earthquake zone II, there is no revision and dam design has taken care of this aspect as well. Bureau of Indian Standards [IS 1893 (Part I):2002], has grouped the country into four seismic zones, viz. Zone II, III, IV and V. Zone II is the least active and Zone V is the most active. 24 3.2 BIOLOGICAL ENVIRONMENT Flora and Fauna The natural vegetation of North Dry Deciduous and Northern Tropical Thorn Forest (Champion and Seth 1968) occurs in the area. Forest in the area is categorised as Teak (Tectona grandis) Forest, Salar (Boswellia serrate) Forest and Miscelleaneous Forest. Common tree species reported from these forest are Anogeissus pendula, Azadriachta indicaAnogeissus latifolia, Terminalis tomentosa, Terminalis arjuna, Terminalia chembula, Albizia lebbeck, Butea monosperma, Capparis sepiaria, Cassia auriculata, Lannea coromandelica, Moringa concanensis, Prosopis cineraria,Cassia fistula,etc. Shrubs in the area were mainly represented by Leptadenida pyrotechnica, Calligonum polygonoides, Calotropis procera, Acacia jacquemontti, Ziziphus nummularia, etc. Bamboo is commonly found in the depresions and on moderate slopes. The hillock forests, scrub forest, streams provide habitat for wildlife in the area. Rhesus Monkey, Wild boar, Blue Bull, Indian Fox, and Indian Palm Squirrel were sighted frequently species in the study area. Indian leopard, Tiger, striped hyena, golden jackal, Bengal fox, jungle cat, porcupine and sloth bear are also reported from the area. The availability of water, safe habitat and food sources for both common and migratory birds around the water bodies of district’s are important for the occurrence and abundance of aquatic bird populations. Around 85 species of aquatic birds belonging to 13 families were recorded in the study area which has its own importance. The resident aquatic species of the globally importance include Saras Crane, Storks (Painted and Blacknecked), Darter, Black-Headed Ibis are found here at many wetland sites. Whereas migratory aquatic birds of global importance include Dalmatian Pelican, Lesser Flamingo, Ferruginous Pochard, Black-tailed Godwit, Eurasian Curlew, Black tailed Tern etc. are identified here in winter season spatially (Patidar 2014). Proposed activities remain limited to dam premises and therefore no risk is envisaged on flora and fauna in the surrounding areas. Fish & Fisheries Fishing in the reservoir is being done by fishermen engaged by the contractor to whom the fishing rights are leased out for a period of three years through an open auction. The common species thriving in the reservoir are Catla catla, Labeo rohita, Cirrhinus mrigala, Aorichthys seenghala, Labeo gonius, Labeo calbasu, Labeo bata, Puntuis sarana and Wallago attu. (Sharma & Kaushal, 2004). None of the proposed activities under the sub-project will impact water quality of river/reservoir and therefore, there is no risk/impact on fish fauna. 25 3.3 PROTECTED AREA Nearest Protected Area Jaisamand Wildlife Sanctuary is the nearest at about 24.7 km from the dam. Other protected areas are Sitamata WLS at 44.6 Km and Phulwari Ki Nal WLS at 70.80 Km. The location of protected areas in relation to dam is shown below at Figure 3.2. Figure 3.2: Map showing location of Protected Areas wrt Som Kamla Amba Dam 3.4 SOCIAL ENVIRONMENT The district Dungarpur is one of the six districts, those comes under Udaipur division. The district has four sub-divisions and four tehsil headquarters. The brief demographic characteristic of the district is given in the table below: No. of Households 2,82,029 Household Size 5 Total Population 13,88,552 Population (0-6 age) 2,42,239 Male 6,96,532 Boys (0-6 age) 1,26,008 Female 6,92,020 Girls (0-6 age) 1,16,231 Sex Ratio 994 Sex Ratio (0-6) 922 Population (SC) 52,267 Population (ST) 9,83,437 Male 26,543 Male 4,91,631 Female 25,724 Female 4,91,806 Literates 6,81,591 Literacy Rate 59.5 Male 4,15,820 Male 72.9 Female 2,65,771 Female 46.2 No. of Workers 6,41,515 Cultivators 2,27,849 (35.5%) Male 3,46,624 Agricultural Labours 1,84,330 (28.7%) Female 2,94,891 Household Industrial Workers 12,514 (2.0%) No. of Main Workers 2,16,411 Other Workers 2,16,822 (33.8%) No. of Marginal Workers 4,25,104 Source: Census of India, 2011 (District Handbook) 26 The project district i.e. Dungarpur is fully tribal district as declared under the Schedule V 1 areas. There is significant tribal population at 70.8%. There are Schedule Tribe households in the downstream areas, however, there will be no physical interventions outside the dam boundary. However, these areas and households will be covered during the preparation of overall Emergency Action Plan for Som Kamla Amba Dam. Study area is defined as proximity villages i.e. villages which fall within 5 km distance from dam on downstream side. According to Census 2011, total population of the study area has been worked out to 16,797. The gender wise distribution of the above population is 8,536 (50.82%) male and 8,261 (49.18%) female. The overall sex ratio of the study area has been worked out to 968 females per 1,000 males. Total population of the study area is distributed into different social groups like Scheduled Caste (SC), Scheduled Tribe (ST) and General Category (including OBC). The share of these social groups’ population to the total population of the study area is 7.10%, 42.48% and 50.42% respectively. In the study area, 57.12% of the population is literate in which male literates are 61.91% and that of females are 38.09%. The overall literacy rate in the study area has been worked out to 67.20%. The male literacy rate is 82.01% and female literacy rate is 51.56%, creating a gender gap in literacy rate of 30.05%. The economic classification of workers as per Census 2011 is saying that total number of workers in the study area is 7,798 which constitute 46.42% of the total population. Of the total workers, 59.07% are males and remaining 40.93% are females. In absolute term, total number of male workers is 4,606 and that of female is 3,192. The gender gap in work participation rate is only 18.14%. Agriculture and allied activities are the main occupation & sources of livelihood and income for most of the local people in the study area. Rabi and Kharif, both are the main crops. Wheat, gram, bajra, barley, jowar, guar, moong, moth, methi, isabgol are the main crops from production point of view in the study area. Vegetable and fruits are also being produced in the study area. Canals and Tube wells are main sources of irrigation followed by wells. Apart from this, other people are engaged in household industries and ancillary works. Basic amenities like water supply for drinking and other uses is available with various sources such as Tap (Treated & Un-treated), Well (Covered & Un-covered), Hand Pump, Tube wells, River/Canal and Tank etc. Electricity is available for domestic, agriculture and commercial or industrial uses in almost all over the study area. The study area having approach roads as Black Topped (Paved), Gravel and Footpath. Data on population, occupation and amenities of vicinity villages haven been compiled from Census of India and is given at Annexure I. 3.5 CULTURAL ENVIRONMENT List of National Monuments in Rajasthan and list of State Protected monuments in Rajasthan have been reviewed. There are no protected monuments in the entire district. 1 Scheduled Areas are areas in India with a preponderance of tribal population subject to a special governance mechanism wherein the central government plays a direct role in safeguarding cultural and economic interests of scheduled tribes in the area. 27 Chapter 4 STAKEHOLDERS CONSULTATION 4.1 STAKEHOLDERS CONSULTATION Stakeholder consultations was conducted as part of environmental and social impact assessments. The purpose was to: a. provide initial information to the communities on the proposed project interventions and particularly the non-structural interventions; b. help identify potential stakeholders who are involved at this stage and will be involved a later stage. c. ascertain if there are any legacy issues relating to displacement, resettlement, etc. d. elicit their responses in relation to key non-structural interventions such as early warning systems, emergency action plans e. identify mechanisms that would be deployed to engage with different stakeholders and particularly communities living downstream A stakeholder consultation meeting was conducted at dam on 19/01/2020. The meeting was attended by permanent staff of the borrower (WRD) working at dam, contract workers from nearby villages; and locals. Following is the outcome of the stakeholder consultation meeting: 1. The participants expressed concern about the infrastructure of the dam and sought speedy implementation, before the onset of monsoon. 2. During the last season the district administration and dam authorities coordinated cautiously to avoid damage. Early warning and alarm set up are noted as important measures. 3. The counterpart highlighted the scarcity of staff but are fully aware of the interventions proposed in the PST and the execution plan. It is however requested that 28 awareness/operational training on ESF and related compliances prior to procurement process is imparted. 4. The participants informed that the prosperity around the dam and downstream is because of the dam and proposed works are required to be taken up soon. 5. It is learnt that around 150-200 boats operate in the dam for fishing on a multi-year contract through contractor. The contract is engaged with fisheries department and no revenue is shared with WRD. The participants opined that a portion of revenue is shared for dam maintenance. The proposed interventions in no way interfere with the fishing activity and the same is clarified during the discussions. 6. The participants also suggested to increase security staff during the tourist season of monsoon to address potential safety issues of the tourists and dam site. 7. Approach road works to the dam from the main entrance as well as saddle dam as well as strengthening the rip rap of the saddle dam are highlighted during the discussions. The right of way required for works is the property of WRD and is in the possession of WRD. Based on these findings relating to both structural and non-structural interventions, potential stakeholders were categorized as follows: Affected, Other interested stakeholders, and disadvantaged and vulnerable stakeholders Affected parties: There are no affected persons who shall be directly or indirectly adversely affected by the proposed interventions Other interested stakeholders: In relation to structural interventions, these would be potential contractors, Project Management consultants, either regulatory bodies/institutional stakeholders such as Revenue, Environmental Authorities, etc. In relation to non-structural interventions, these would include: communities living downstream including farmers; village heads (Sarpanchs), community leaders; district administration; police, state disaster management authority, revenue department; electronic and print media, etc. These communities would be key stakeholders requiring to be involved in the preparation and implementation of EAP. Disadvantaged and vulnerable persons and groups: Illiterate persons, physically challenged, women and elderly would be key stakeholders – requiring special focus and outreach to ensure that they are well informed about the provisions of the EAP. Communities welcomed such interactions and indicated that they would prefer Dam authorities conduct one such face -to- face meeting once a month at a convenient location to inform of developments/interventions relevant to them. They welcomed other means of information such as advertisements in the local papers etc, but preferred to have face to face interactions at least once a month. 29 Chapter ENVIRONMENTAL & SOCIAL 5 RISKS AND IMPACTS Based on the relevance of each Standard, as identified in the chapter on Legal, Regulatory and Institutional Framework, ensuing sections summarize the environmental and social risks and impacts likely due to the proposed interventions followed by the mitigation measures considered, for each relevant Standard. Table below, presents the Risk and impacts grouped in respect of the applicable ESS identified in chapter 3 earlier: Applicable ESS Risk and Impacts area assessed ESS1- Assessment and Management of The risks and Impacts is carried out as per Environmental and Social Risks and requirement of this standard Impacts ESS2- Labour and Working Conditions Types of Workers/labour and working conditions ESS3- Resource Efficiency, Pollution Impact on Physiography/land use/Geology/Soil Prevention and Management Impacts on water resources/Water Quality Impact on Air quality/Noise levels Impact due waste generation/disposal ESS4- Community Health and Safety Impacts on Community Health and safety ESS7 - Indigenous Peoples/Sub-Saharan Impacts and risks on such indigenous/tribal groups in African Historically Underserved this Schedule V area. Tradition Local Communities 5.1 ASSESSMENT AND MANAGEMENT OF E&S RISK AND IMPACT (ESS 1) Proposed intervention are categorised as civil, electromechanical and painting work requiring labour involvement for works and their stay at site for a period of about 3 years, use of resources such as water and power during construction, pollution generation from storage and handling of material, generation of waste, use of paints and other chemicals for construction activities, transportation of raw material, etc. In addition, labour intensive work always involves risks of accidents such as working at heights, working on upstream body of dam, underground activities, etc. As all the proposed structural interventions are within the dam premises, no adverse impacts are envisaged on communities including that on the disadvantaged or vulnerable people. On the contrary, all communities including disadvantaged and vulnerable persons and groups will indirectly benefit from these proposed interventions that shall enhance dam safety. However, in case of non-structural interventions relating to early flood warning systems having siren systems, broadcasting facilities and Emergency Action Plans, project will need to make extra efforts to reach out to the disadvantaged and vulnerable persons and groups to involve them in both preparation and implementation. 30 5.2 LABOUR AND WORKING CONDITIONS (ESS 2) Water Resources Department, Rajasthan shall contract agencies to undertake civil works, agencies/firms to support core-functions; primary suppliers of material/equipment and other implementation support partners, and these could be from anywhere in the country. Construction works will require labour force and associated goods and services. Based on the construction package sizes and the project implementation schedule, the peak construction workforce/manpower has been estimated as 40-50. These will be skilled and semi-skilled workforce of contractors and expected to stay on site for a period of 3 years. In addition, there will be floating population of suppliers, transporters of material and their labour who will keep on moving in and out of the site during the work period of 3 years. Construction contractors are expected to stay at/near dam, set up construction equipment and machinery near work location at pre-determined /approved sites. Project shall comprise the following types of workers: 1. Direct workers: Direct workers will include the project managers and supervisors, who are employees of WRD. The estimated number of direct workers is not likely to exceed 30 as per existing institutional arrangements and practices of WRD. 2. Contracted workers: All the work force deployed by the Contractors will be deemed to be contracted workers. The Contractor(s) might further engage multiple subcontractors. All work force of all such sub-contractors will be also deemed to be contracted workers. These will also include Migrant workers as all the required labour will not be fully supplied locally for a number of reasons, such as worker unavailability and lack of technical skills and capacity. Migrant Workers: The migrant workers are that, who are employed for the Project but does not belong to the Project region and are not normally expected to return to their places of residence after work shift hours. The number of migrant workers in any contract package, would depend on decisions made by contractors, based on the locally available workforce and their skills for Project construction requirements. The migrant workers could be at all levels and include unskilled and semiskilled construction labour and could even comprise combination of male and women labour force. The migrant workers are either directly engaged by the contractor or through labour contractors, who supply the work force as per the needs of the contractors. 3. Primary Supply Workers: No primary supplier or primary supply workers are anticipated as all goods and services essential to the core functions of the project shall be provided by the contractor – through a contract by Rajasthan WRD. 4. Community Workers: Community workers are envisaged under the Emergency Action Plans, who will be mostly volunteers for implementing parts of the EAP. Potential Labour risks: Following are the potential risks associated with workers/labours engaged in execution of planned intervention works. 31 Impact/Risks on Community 1. Waste generation from labour colony can pollute drinking water sources of community Impacts/Risks for Workforce 2. Safety issues while at work like injuries/accidents/ fatalities leading to even death, while at work; 3. Short terms effects due to exposure to dust and noise levels, while at work 4. Long term effects on life due to exposure to chemical /hazardous wastes 5. Inadequate accommodation facilities at work force camps, including inadequate sanitation and health facilities 6. Non-payment of wages 7. Discrimination in Employment (e.g. abrupt termination of the employment, working conditions, wages or benefits etc.) 8. Sexual harassment at work 9. Absence or inadequate or inaccessible emergency response system for rescue of labour/workforce in situations of natural calamities. 10. Health risks of labour relating to HIV/AIDS and other sexually transmitted diseases In addition, other risks that would be applicable for all types of workers would be as follows: 1. Unclear terms and conditions of employment 2. Discrimination and denial of equal opportunity in hiring and promotions/incentives/training opportunities 3. Denial for workers’ rights to form worker’s organizations, etc. 4. Absence of a grievance mechanism for labour to seek redressal of their grievances/issues 5.3 RESOURCE EFFICIENCY AND POLLUTION PREVENTION AND MANAGEMENT (ESS 3) Impact on Physiography The dam is operational for over 15 years now and the present interventions involve only civil and electromechanical works to improve dam operation and safety. All the work will be carried out at one location i.e. at dam, therefore, physiography will not change due to any of the proposed interventions. There will be no significant impact on physiography of the region due to the proposed interventions. Impact on Land/Geology All project components are proposed to happen within existing dam with no land acquisition. Therefore, impact on land and geology will be limited to sourcing of construction material or disposal of construction waste related only. The civil works will require different construction materials such as earth, aggregate, boulders, and sand. The requirement of such material is not large and will be sourced from already operational and approved mines/quarries. The construction waste generation is also likely to be minimal and will be 32 either reused or disposal for land filling or levelling purposes. However, requisite mitigation measures will be taken to minimise impact further. The various ‘resource efficacy’ options during design include optimize usage of material generated from excavation for wall foundation and generation of construction waste from repair activities and thereby reduce potential impact due to dumping etc., are considered to achieve minimum construction footprint. Impact on Soil The land where construction activities will take place will be directly impacted due to excavation, removal of topsoil, temporary storage of excavated material, etc. Other repair sites will also impact soil due to repair and demolition works such as removal and fresh laying of rip-raps, repair to steps, spillage during painting, operation of construction equipment and machinery and waste generation thereof, etc. There is also possibility of contamination of soil from leakage and spillage during handling and storage of fuels and chemicals. Muck Disposal The activities that generate construction debris and/or spoil are excavation, removal of damaged rip-raps, other repair and renovation activities as discussed above. This being largely repair work, quantities have not been estimated and they are not expected to be significant to create disposal problem. Nevertheless, all the construction debris/muck generated needs to be disposed off in a planned manner to avoid adverse impacts on soil. Impacts on Water Resources The proposed intervention activities are not expected to impact water resources in any way as the proposed interventions are neither crossing, altering or disturbing drainages nor impacting ground water resource in any form. Use of resources such as water and power will be optimised before start of work through Resource Efficiency and Pollution Prevention Plan. Impacts on Water Quality Construction related impacts and risks for water quality include: a) accidental release of fuel or chemicals and contamination from poor waste practices can affect surface and groundwater b) contamination from construction machinery working near water bodies c) discharges and disturbance of soil and sediment that drain into surface waters d) construction of d/s protection wall e) Generation of sanitary wastes from camp site and construction sites finding way to water bodies Impact on Ambient Air Quality As discussed in baseline, ambient air quality in the area is pristine and without any significant anthropogenic sources of pollution. Construction activities can give rise to dust emissions if not effectively managed and have the potential to affect receptors near to the main construction sites due to dust generated from demolition, excavation, operation of construction equipment and machinery, increased movement of vehicles, onto the local 33 road network. Earth works will result in exposed areas of soil which will potentially generate dust when it is windy, with dust potentially being generated when winds blow at all times of day or night, not just during active periods of construction. The level and distribution of dust emissions will vary according to the duration and location of activity, weather conditions, and the effectiveness of suppression measures. Gaseous emission during construction will be from machinery, equipment and vehicles used for material transportation. The operation of vehicles and equipment will result in emissions of carbon monoxide, sulphur dioxide, and oxides of nitrogen. In particular, all commercial vehicle driven with diesel fuel is often used in India. The greatest impact on air quality due to emissions from vehicles and plant will be in the areas immediately adjacent to work area. Generally, additional vehicle movements generated during the construction phase will have the potential to influence local air quality at sensitive receptors located at close proximity to road and pollutant concentration is likely to reduce with increase distance from road. The impacts will therefore apply mostly to the villages on route to dam. As the project is presently operational and the interventions are not going to alter the project operation in any manner, no operational phase impacts are envisaged on ambient air quality. Impact of Noise and Vibration Sources of noise will be the vehicles and equipment for construction at the project site. Due to construction activity in the area, noise levels will increase during the period of construction, however, they will remain limited to the work area mainly where construction activity will progress. Additionally, noise levels will increase on approach roads due to increased traffic. Impact of noise generation due to operation of construction machines and equipment is the exposure of workers operating these machines and other who are working in the surrounding. Such impacts can become significant if they are exposed to high noise for long hours continuously. Impact of Waste Generation Migratory population is expected to reside in the area during peak construction period. Proper sanitary and solid waste management facilities would be provided at the labour colonies. In the absence of proper solid waste management plan, there can be serious impacts of land and water pollution due to indiscriminate disposal. In addition, there will be odour issues and health impacts. There will be an influx of labourers and other service providers into the project area. Sewage and solid waste will be generated from the colonies. It is essential that from the planning stage, sewage management and solid waste disposal facilities should be conceptualized to maintain the health of the people and the environment. Solid waste generated from the colonies during construction phase will be disposed off as per Solid Wastes Management Rules, 2016. As most of the proposed activities involve repair and renovation, it is expected that construction and demolition waste in the form of debris will be generated. This being largely 34 repair work, quantities have not been estimated and they are not expected to be significant to create disposal problem. Nevertheless, all the construction debris/muck generated needs to be disposed off in a planned manner to avoid adverse impacts on soil/land. All such wastes will be handled in compliance with Construction and Demolition Waste Rules, 2016. Project interventions include substantial amount of electro-mechanical work such as repair/replacement of hoists and gates, repair of gantry crane, installing lights in gallery and over dam body, renovation of centralised control room, etc. These activities will generate significant amount of waste in terms of replaced parts, packaging material, empty containers, use and disposal of oil & grease, iron scrap, etc. There will be a mix of hazardous and non-hazardous wastes. It is important to have a plan ready for disposal of such wastes before start of the activity. Contractor is obliged to provide first-aid/basic medical facilities to labour at site especially during accident/emergency which is likely to generate bio-medical waste, although quantity is not expected to be significant, this needs to be managed to avoid indiscriminate dumping as impacts could be serious. WRD along with contractor will prepare project specific muck / debris/Solid Waste disposal plan and provide sufficient site for such disposals. 5.4 COMMUNITY HEALTH AND SAFETY (ESS 4) Heath safety and security risks and impacts on project affected communities especially on vulnerable people are not considered significant as communities are not directly involved or getting impacted. However, the project construction would involve engagement of labour, transportation and handling of material, civil construction and electromechanical works and such activities may impact the community and increase the risks. Engagement of labour for project work and their stay at site for about 3 years’ time, will increase the risks of crimes including gender based violence. Waste generation from labour colony if not handled properly, will pollute the water resources used by community for drinking leading to health impacts. Migratory workforce may be bringing in new and infectious diseases not known to area. Transportation of material will increase the traffic on village roads. Increased movement of traffic will impact the community by way of increased noise and air pollution. In addition, this will also increase the risk of accidents. Similarly, civil construction and electromechanical works will lead to pollution generation in the form of air emissions and noise generation, which will remain local and are not expected to impact the community. Construction waste and electromechanical work waste, especially the hazardous waste if not disposed off, properly have the potential of impacting the surrounding community. 35 5.5 INDIGENOUS PEOPLES/SUB-SAHARAN AFRICAN HISTORICALLY UNDERSERVED TRADITIONAL LOCAL COMMUNITIES (ESS 7) The standard will apply as the project dam is located in a Schedule V area with preponderance of tribal population. Proposed structural interventions resulting in improved dam safety will not lead to any direct or indirect adverse impacts on the population. On the contrary, these will benefit all the beneficiary population including the scheduled tribes in the area. Non-structural interventions such as Early warning system and Emergency Action Plans too will benefit these groups. These tribal groups will comprise Disadvantaged and Vulnerable groups under the Stakeholder Engagement efforts. More efforts will be made to reach out to these groups during EAP preparation and implementation, particularly using culturally appropriate communication and IEC material. 36 Chapter ENVIRONMENTAL AND SOCIAL 6 MANAGEMENT PLAN As can be seen from the above discussion, the interventions proposed under Som kamla Amba sub-project are of the nature of civil and electromechanical work, besides Non- structural interventions such as early flood warning systems, Emergency action plans. In case of structural interventions, there is no additional land requirement – neither forest nor private, as all the interventions remain within the close proximity to dam body itself. Impacts/risks as assessed under ESIA study will remain limited to dam area except for procurement and transportation of material and labour habitation in the area, which have the potential of impacting community around the dam site. 6.1 ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN E&S impacts/risks for this sub-project Dam is Low risk, as identified in the previous chapter. These risks and impacts can be mitigated by appropriately implementing management measures. Based on the ESIA following plans/procedures have been identified to effectively mitigate the environment and social impacts and risks of the proposed interventions: • Labour Management Procedure including GRM The Procedure will set out the way in which project workers will be managed, in accordance with the requirements of national law and the bank’s ESS Standards and will address the way in which this ESS will apply to different categories of project workers. It covers the terms and conditions of employment, non-discrimination and equal opportunity, worker’s organization and welfare. Protecting the workforce, establishing minimum age for labour to prevent child labour will be defined in the procedure. The responsibility to manage any adverse impacts would be clearly reflected in the contractual obligations of the Contractor with appropriate mechanisms for addressing non-compliance. A grievance mechanism will be provided for all direct workers and contracted to raise workplace concerns and workers will be informed of the grievance mechanism at the time of recruitment along with the measures put in place to protect them against any reprisal for its use. Mechanism should be easily accessible to all project workers. It should be designed to address concerns promptly, using an understandable and transparent process that provides timely feedback to those concerned in a language they understand, without any retribution, and will operate in an independent and objective manner. The document shall be prepared by Rajasthan WRD with support from the E&S staff and shall be applicable for all dams taken under DRIP 2 in the state. It will be disclosed by Rajasthan WRD one month before mobilization of the Contractor. • OHS Measures Measures relating to occupational health and safety applies to the project as it involves engagement of workers. The OHS measures will take into account the General Environment 37 Health and Safety Guidelines and applicable legal requirements. The OHS measures will be designed and implemented to address: i. identification of potential hazards to project workers, particularly those that may be life threatening; ii. provision of preventive and protective measures, including modification, substitution, or elimination of hazardous conditions or substances; iii. training on occupational safety and health, and maintenance of training records iv. Provision of personal protective equipment without expense to the project workers. v. documentation and reporting of occupational accidents, diseases and incidents; vi. emergency prevention and preparedness and response arrangements to emergency situations; vii. remedies for adverse impacts such as occupational injuries, deaths, disability and disease viii. accident reporting and analysis procedure ix. system for regular review of OHS performance The document shall be prepared by Rajasthan WRD with support from E&S Staff and shall be applicable for all dams taken under DRIP 2 in the state. It shall be disclosed by Rajasthan WRD one month before mobilization of the Contractor. • GBV Risk Mitigation Guidelines The proposed structural interventions are extremely localized in nature and will be carried out in areas of restricted access – as normally all dams are. These structural interventions will not result in any project interface with local communities, the overall GBV rating for this dam intervention as per the Risk Assessment Tool is low. Hence, in accordance with the overall GBV Risk Mitigation Framework for the project, guidelines will be developed commensurate to the low risk category to address Gender Based Violence Risk before invitation of bids. The Plan will provide a set of measures such as orientation to all categories of labour including department staff/dam site personnel. The document shall be prepared by Rajasthan WRD with support from the E&S Staff of Rajasthan WRD. • Resource Efficiency and Pollution Prevention Measures Keeping in view the risks and impacts of the proposed activities, WRD will prepare a set of measures to be implemented by the Contractors to ensure efficient use of resources and avoid/minimize the pollution from proposed interventions. The measures should address all possible impacts identified above, with respect to resource use and pollution generation from civil works including road repair, electromechanical and painting work and also from labour camps and colonies. It should focus on reuse/recycling; energy efficiency such as solar lights and cookers for colony/community kitchen for workers, where possible. The project’s demand for major raw material such as boulders, aggregate and sand for construction will be sourced through pre-existing authorized quarries, with valid environment clearance. To mitigate air and noise pollution from transportation, material storage and handling and construction activities, following measures should be included: • To ensure trucks are loaded only up to permitted capacities to prevent high emission 38 • The ensure trucks used for transportation of material is covered by tarpaulin and provided tail board, so that en-route spillage and generation of fugitive dust are prevented. • Vehicles in good condition with valid PUC (Pollution Under Control) certificate shall be deployed during construction • Regular sprinkling of the water will be done on construction sites for dust suppression. • Mobile DG sets shall be used for lighting only during construction phase and they should meet emission and noise standards as per guidelines/standards issued by CPCB. • All the construction workers and other staff, who get directly exposed to dust, should necessarily be provided with dust masks. Workers in high noise area, will be provided with ear muffs and their use will be monitored. Workers exposure (time duration) to high noise will also be controlled. • Minimize the use of noise producing equipment during night hours to avoid the disturbance to locals and wild animals of surrounding area. To mitigate the risk of wastewater from construction site and colony finding its way to fresh water source without treatment, the following measures should be included: • All toilets and wash areas in worker’s colony have functional septic tanks and soak pit arrangements, of adequate capacity. • No discharge from oil/lube storage areas shall be directly discharged in to any open surface water channel/ streams. • Construction along the river bank/reservoir shall be done when surface water level is receded and clear construction area is available. • Storage of material and construction equipment should be kept away from the drainages to avoid any spillage and pollution of surface water. For solid and hazardous waste management, sites should be identified for disposal of construction waste, surplus excavated material, and other solid wastes; and appropriate permissions taken for dumping with restoration plan covering engineering and biological measures as appropriate. No dump site shall be located in forest area. WRD will share identified locations of muck or debris disposal sites with the contractor. The contractor will develop a muck and debris disposal plan after incorporating longitudinal and cross section references to assess volume or capacity of the disposal site and will submit muck/ debris disposal plan before commencement of the work at site. This action needs to be included in the Bid Document as one of the key requirements. WRD needs to prepare a plan to identify and quantify all the waste generated from electro- mechanical work include replaced parts with estimated quantities and categorisation as hazardous and non-hazardous waste. The plan should also identify the temporary secured and covered storage location till the time it is removed, contractors/vendors who will pick these parts/wastes; authorisation status of contractors for hazardous wastes. Measures should also cover cleanliness of the labour colony, provision of basic sold waste collection facilities and restrict dumping of solid waste on land or in water body. Contractor should provide bins for dumping of domestic waste from colony and ensure timely pick up and dumping at authorised location. 39 The document shall be prepared by Rajasthan WRD with support from the E&S staff and shall be applicable for all dams taken under DRIP 2 in the state. It shall be disclosed by Rajasthan WRD one month before mobilization of the Contractor. • Emergency Response Plan The plan will identify and implement measures to address emergency events, arising from both natural and man-made hazards, typically in the form of fire, explosions, leaks or spills or flooding of downstream area in case of dam break. The measures will be designed to address the emergency event in a coordinated and expeditious manner, to prevent it from injuring the health and safety of the community, and to minimize, mitigate and compensate for any impacts that may occur. ERP will cover emergency preparedness and response activities, resources, and responsibilities, and will disclose appropriate information to affected communities, relevant government agencies, or other relevant parties. The Borrower will assist and collaborate with affected communities, relevant government agencies and other relevant parties in their preparations to respond effectively to an emergency. The plan so prepared should be dovetailed with district disaster management plan and state disaster management plan. The plan shall be prepared by Rajasthan WRD by engaging expert consultants; it should be ready before the invitation of bids. • Procedures for Stakeholder Engagement The Stakeholder Engagement Framework (SEF) will describe the timing, methods of engagement with stakeholders and range of information, distinguishing between project- affected parties and other interested parties, as well as the type of information to be sought from them. The procedures developed based on SEF will set out how stakeholders will be engaged throughout project preparation and implementation and describe the measures that will be used to remove obstacles to participation, and how the views of differently affected groups will be captured. Where applicable, the procedures will include differentiated measures to allow the effective participation of those identified as disadvantaged or vulnerable. The draft Framework will be prepared by CWC in discussion with Rajasthan WRD and will be disclosed. The Stakeholder Engagement Procedures will be developed specific to the proposed interventions at the site, prior to invitation of bids. • Institutional Arrangement As part of institutional strengthening for implementation of sub-projects, Environmental and Social staff will be engaged by the department to enable preparation of management plans as well subsequent implementation of mitigation measures during implementation. IA will hire experts from outside department or seek deputation of staff with relevant experience. • Grievance Mechanism WRD shall establish and implement a grievance mechanism to receive and facilitate resolution of concerns and grievances, from the communities and other stakeholders including implementation partners. It shall be proportionate to the potential risks and 40 impacts of the project and be accessible and inclusive. The department will establish three levels of Grievance Mechanism: 1. A cell at each of the dam site headed by respective Executive Engineer 2. A cell at the SPMU headed by CE/PD 3. A committee at the state government level headed by Secretary to Government Details on the processes and procedures for the GRM will be provided in the Stakeholder Engagement Framework. 6.2 MONITORING REPORTING AND BUDGETING SPMU will prepare a monitoring, reporting and budgeting requirement to implement above plans and measures, which will be approved by CPMU - CWC. SPMU will prepare a quarterly monitoring report and submit to CPMU - CWC. 6.3 ENVIRONMENTAL AND SOCIAL COMMITMENT PLAN (ESCP) AND OTHER REQUIREMENTS WRD, Rajasthan will agree on an Environmental and Social Commitment Plan (ESCP) with the Bank covering the material measures and actions that are required for the project to achieve compliance with the ESSs over a specified timeframe. It will take into account the findings of the environmental and social assessment, the Bank’s environmental and social due diligence and the results of engagement with stakeholders. ESCP will clearly spell out the plans to be prepared with time frame and responsibility. 41 Annexure I Socio-economic Profile of Proximity villages (Study Area) Study area is defined as proximity villages i.e. villages which fall within 5 km distance from dam on downstream side. These are Naya Gaon, Baran, Gamri, Aspur, Tonkwasa, Karkoli, Vara Kundli, Varaghoriya, Amartiya, Fatehpura and Kamla Amba. A. Demography of Study Area S. No. Description Number Percentage to Respective Total 1 Total Population 16797 100.0 Male 8536 50.82 Female 8261 49.18 Sex Ratio 968 2 Population (0-6 age group) 2521 100.0 Male 1293 51.29 Female 1228 48.71 Child Sex Ratio 950 3 Scheduled Caste (SC) Population 1192 100.0 Male 607 50.92 Female 585 49.08 Sex Ratio 964 4 Scheduled Tribe (ST) Population 7136 100.0 Male 3573 50.07 Female 3563 49.93 Sex Ratio 997 5 General Category (Including OBC) 8469 100.0 Male 4356 51.43 Female 4113 48.57 Sex Ratio 944 6 Total No. of Households 3405 Average Household Size 5 7 Total Literates 9594 100.0 Male 5940 61.91 Female 3654 38.09 Overall Literacy Rate 67.20 Male Literacy Rate 82.01 Female Literacy Rate 51.96 Gender Gap in Literacy Rate 30.05 8 Total Workers 7798 100.0 Male 4606 59.07 Female 3192 40.93 Gender Gap in Work Participation Rate 18.14 9 Main Workers 3794 100.0 Male 3153 83.10 Female 641 16.90 Gender Gap in Work Participation Rate 66.20 10 Marginal Workers 4004 100.0 Male 1453 36.29 Female 2551 63.71 Gender Gap in Work Participation Rate -27.42 11 Household Industrial Workers 129 100.0 Male 77 59.69 Female 52 40.31 12 Cultivators 2841 100.0 Male 1552 54.98 42 Female 1279 45.02 13 Agricultural Labour 1706 100.0 Male 625 36.64 Female 1081 63.36 14 ‘Other Workers’ 3122 100.0 Male 2342 75.02 Female 780 24.98 Source: Census of India, 2011 B. Population Composition According to Census 2011, total population of the study area has been worked out to 16,797. The gender wise distribution of the above population is 8,536 (50.82%) male and 8,261 (49.18%) female. The overall sex ratio of the study area has been worked out to 968 females per 1,000 males. The entire population of the study area is distributed into approx. 3,405 households and the average household size is five. Population Distribution Share of Population 16797 Female 8536 8261 Male 49.18% 50.82% Total Population Male Female Village wise population distribution of the study area is given in the table below: Village wise Population Distribution with Sex Ratio S. No. Village No. of HH Population Sex Total Male Female Ratio 01 Naya Gaon 145 694 350 344 983 02 Baran 742 4062 2054 2008 978 03 Gamri 108 513 257 256 996 04 Aspur 778 3754 1919 1835 956 05 Tonkwasa 411 2003 1033 970 939 06 Karkoli 126 648 299 349 1167 07 Vara Kundli 129 556 294 262 891 08 Varaghoriya 457 2152 1111 1041 937 09 Amartiya 262 1211 607 604 995 10 Fatehpura 118 579 296 283 956 11 Kamla Amba 129 625 316 309 978 TOTAL 3405 16797 8536 8261 968 Source: Census of India, 2011 C. Child Population Distribution In the study area, the total child population of 0-6 age group has been worked out to 2,521 which represent 15.01% of the total population. Of the total child population, 51.29 % are boys and remaining 48.71% are girl child. The child sex ratio in this age group is 950 girls per 1,000 boys. 43 Share of Child Population Child Population Distribution 2521 Girls Boys 1293 1228 48.71% 51.29% Child Population Boys Girls Village wise child population distribution of the study area is given in the table below: S. No. Village Child Population (0-6) Age Group Sex Total Boys Girls Ratio 01 Naya Gaon 98 50 48 960 02 Baran 823 399 424 1063 03 Gamri 83 42 41 976 04 Aspur 473 261 212 812 05 Tonkwasa 273 144 129 896 06 Karkoli 95 39 56 1436 07 Vara Kundli 47 29 18 621 08 Varaghoriya 286 152 134 882 09 Amartiya 181 98 83 847 10 Fatehpura 57 31 26 839 11 Kamla Amba 105 48 57 1188 TOTAL 2521 1293 1228 950 Source: Census of India, 2011 D. Social Group Population Distribution Total population of the study area is distributed into different social groups like Scheduled Caste (SC), Scheduled Tribe (ST) and General Category (including OBC). The share of these social groups’ population to the total population of the study area is 7.10%, 42.48% and 50.42% respectively. Population Distribution Share of Social Groups Population SC 16797 7.10% 8469 Gen (+ 7136 OBC) ST 50.42% 42.48% 1192 Total SC ST Gen (+ Population OBC) • Scheduled Caste (SC) Population: In the study area, Scheduled Caste population has been worked out to 1192 which constitute about 7.10% of the total population. Of this, 50.92% is male and remaining 49.08% is female. The sex ratio among Scheduled Caste population has been worked out to 964 females per 1,000 males. 44 Share of SC Population SC Population 1192 Female Male 607 585 49.08% 50.92% SC Population Male Female Village wise SC population distribution of the study area is given in the table below: S. No. Village SC Population Sex Ratio Total Male Female 01 Naya Gaon 9 5 4 800 02 Baran 25 13 12 923 03 Gamri 0 0 0 000 04 Aspur 604 303 301 993 05 Tonkwasa 125 62 63 1016 06 Karkoli 41 19 22 1158 07 Vara Kundli 20 10 10 1000 08 Varaghoriya 233 127 106 835 09 Amartiya 113 58 55 948 10 Fatehpura 19 9 10 1111 11 Kamla Amba 3 1 2 2000 TOTAL 1192 607 585 964 Source: Census of India, 2011 • Scheduled Tribe Population: The Scheduled Tribe population in the study area has been worked out to 7,136 which represent 42.48% of the total population. Of the total Scheduled Tribe population, 50.07% is male and 49.93% is female. The sex ratio among the Scheduled Tribe population has been worked out to 997 females per 1,000 males. ST Population Share of ST Population 7136 3573 3563 Female Male 49.93% 50.07% ST Population Male Female Village wise ST population distribution of the study area is given in the table below: S. No. Village ST Population Sex Ratio Total Male Female 01 Naya Gaon 349 168 181 1077 02 Baran 3912 1968 1944 988 03 Gamri 192 94 98 1043 45 04 Aspur 462 233 229 983 05 Tonkwasa 656 344 312 907 06 Karkoli 353 168 185 1101 07 Vara Kundli 33 16 17 1063 08 Varaghoriya 560 284 276 972 09 Amartiya 163 74 89 1203 10 Fatehpura 60 30 30 1000 11 Kamla Amba 396 194 202 1041 TOTAL 7136 3573 3563 997 Source: Census of India, 2011 • General Category (including OBC) Population: The population of this group has been worked out to 8,469 which is 50.42% of the total population of the study area. Of the total population of this group, 51.43% is male and 48.57% is female. The sex ratio among this group of population has been worked out to 944 females per 1,000 males. Gen. (including OBC) Population Share of Gen Population 8469 4356 4113 Female Male 48.57% 51.43% Gen Population Male Female Village wise General Category (including OBC) population distribution of the study area is given in the table below: S. No. Village GEN (including ‘OBC’) Population Sex Ratio Total Male Female 01 Naya Gaon 336 177 159 898 02 Baran 125 73 52 712 03 Gamri 321 163 158 969 04 Aspur 2688 1383 1305 944 05 Tonkwasa 1222 627 595 949 06 Karkoli 254 112 142 1268 07 Vara Kundli 503 268 235 877 08 Varaghoriya 1359 700 659 941 09 Amartiya 935 475 460 968 10 Fatehpura 500 257 243 946 11 Kamla Amba 226 121 105 868 TOTAL 8469 4356 4113 944 Source: Census of India, 2011 E. Literates, Literacy Rate and Gender Gap in Literacy Rate In the study area, 57.12% of the population is literate in which male literates are 61.91% and that of females are 38.09%. The overall literacy rate in the study area has been worked out to 67.20%. The male literacy rate is 82.01% and female literacy rate is 51.56%, creating a gender gap in literacy rate of 30.05%. 46 Literate Population Share of Literates 9594 Female Literates 5940 38.09% 3654 Male Literates 61.91% Total Literates Male Literates Female Literates Village wise literate population and literacy rate is given in the table below: S. Village Literate Population Literacy Rate (%) No. Total Male Female Total Male Female 01 Naya Gaon 368 221 147 61.74 73.67 49.66 02 Baran 2067 1333 734 63.82 80.54 46.34 03 Gamri 211 143 68 49.07 66.51 31.63 04 Aspur 2590 1469 1121 78.94 88.60 69.07 05 Tonkwasa 1043 671 372 60.29 75.48 44.23 06 Karkoli 296 172 124 53.53 66.15 42.32 07 Vara Kundli 315 221 94 61.89 83.40 38.52 08 Varaghoriya 1256 798 458 67.31 83.21 50.50 09 Amartiya 723 448 275 70.19 88.02 52.78 10 Fatehpura 384 251 133 73.56 94.72 51.75 11 Kamla Amba 341 213 128 65.58 79.48 50.79 TOTAL 9594 5940 3654 67.20 82.01 51.96 Source: Census of India, 2011 F. Workers and Work Participation Rate The economic classification of workers as per Census 2011 is saying that total number of workers in the study area is 7,798 which constitute 46.42% of the total population. Of the total workers, 59.07% are males and remaining 40.93% are females. In absolute term, total number of male workers is 4,606 and that of female is 3,192. The gender gap in work participation rate is only 18.14%. Working Population Share of Working Population 7798 Female 4606 Workers 3192 40.93% Male Workers 59.07% Total Workers Male Workers Female Workers Further of the total workers, 48.65% are main workers and remaining 51.35% are marginal workers. Of the total main workers, 83.10% are male and remaining 16.90% are female which creates a gender gap in work participation rate of 66.20%. In case of marginal workers, 47 36.29% are male and 63.71% are female that creates a gender gap of minus (-) 27.42% in this segment of work participation. Distribution of Workers Share of Workers (Main Vs Marginal) (Main Vs Marginal) 7798 4004 Main 3794 Marginal Workers Workers 48.65% 51.35% Total Workers Main Workers Marginal Workers Village wise working population of the study area is given in the table below: Village Name Total Worker Main Worker Marginal Worker T M F T M F T M F Naya Gaon 175 159 16 140 137 3 35 22 13 Baran 1532 946 586 662 578 84 870 368 502 Gamri 307 160 147 112 96 16 195 64 131 Aspur 1406 1032 374 1073 908 165 333 124 209 Tonkwasa 1087 606 481 672 511 161 415 95 320 Karkoli 366 197 169 44 39 5 322 158 164 Vara Kundli 316 154 162 148 144 4 168 10 158 Varaghoriya 1239 641 598 439 407 32 800 234 566 Amartiya 667 347 320 137 121 16 530 226 304 Fatehpura 331 175 156 327 174 153 4 1 3 Kamla Amba 372 189 183 40 38 2 332 151 181 TOTAL 7798 4606 3192 3794 3153 641 4004 1453 2551 Source: Census of India, 2011 The workers are further divided into Cultivators, Agricultural Labours, Household Industrial Workers and ‘Other Workers’. Their shares in the total workers are 36.43%, 21.88%, 1.65% and 40.04% respectively. Distribution of Workers withVarious Share of various occupational population Occupations 7798 2841 3122 Other 1706 Workers Cultivators 129 40.04% 36.43% Agri HH Labours Industrial 21.88% 1.65% Distribution of working population with various occupations is given in table below: 48 S. Village Total Cultivators Agricultural Household Industrial Other No. Workers Labour Workers Workers 01 Naya Gaon 175 94 10 5 66 02 Baran 1532 664 549 11 308 03 Gamri 307 86 173 2 46 04 Aspur 1406 182 58 35 1131 05 Tonkwasa 1087 394 241 29 423 06 Karkoli 366 103 6 0 257 07 Vara Kundli 316 230 2 1 83 08 Varaghoriya 1239 699 33 17 490 09 Amartiya 667 113 402 21 131 10 Fatehpura 331 192 37 2 100 11 Kamla Amba 372 84 195 6 87 TOTAL 7798 2841 1706 129 3122 Source: Census of India, 2011 Agriculture and allied activities are the main occupation & sources of livelihood and income for most of the local people in the study area. Rabi and Kharif, both are the main crops. Wheat, gram, bajra, barley, jowar, guar, moong, moth, methi, isabgol are the main crops from production point of view in the study area. Vegetable and fruits are also being produced in the study area. Canals and Tube wells are main sources of irrigation in most of the part of the study area whereas most of the farmers belonging from the district Ajmer are mostly dependent on rain crops/kharif crops. In this part of the study area, most of the land is being irrigated by wells. Apart from this, other people are engaged in household industries and ancillary works. G. Basic Amenities The basic amenities like education, health, drinking water, electricity, approach road, transportation and other facilities available in the study area are given in the following table: Basic Amenities Available in the Study Area EDUCATION Type of Institutes Number Pre-primary School (Pvt.) 05 Primary School (Govt.) 14 Primary School (Pvt.) 05 Middle School (Govt.) 09 Educational Institutions Middle School (Pvt.) 05 Secondary School (Govt.) 04 Secondary School (Pvt.) 04 Senior Secondary School (Govt.) 02 HEALTH Type of Facilities Number Primary Health Centre 01 Primary Health Sub-Centre 06 Community Health Centre 01 Maternity and Child Welfare Centre 02 Health Facilities Hospital (Alternative Medicine) 02 Dispensary 01 Family Welfare Centre 01 Non-Govt. Medical Facilities (For Out Patient) 06 Non-Govt. Medical Facilities (For In & Out Patient) 01 49 ASHA 11 Anganwadi Centre (Nutritional Centre) 11 Nutritional Centre- ICDS 11 WATER Means of Drinking Water No. of Villages Tap (Treated & Un-treated) 10 Well (Covered & Un-covered) 07 Drinking Water Hand Pump 10 Tube wells 09 River/Canal 01 Tank 01 ELECTRICITY Types of Electricity Available No. of Villages Electricity Supply Power for Domestic Uses 11 Power for Agriculture Uses 11 Power for Commercial or Industrial Uses 08 ROAD Types of Approach Roads No. of Villages Approach Road Black Topped (Paved/Pucca) Road 05 Gravel (Mud/Kachcha) Road 11 Footpath Road 11 TRANSPORTATION Types of Road Transportation Available No. of Villages Public Bus Services 07 Road Transportation Private Bus Services 08 Auto/Modified Autos 05 Taxi Services 05 OTHER AMENITIES Agricultural Credit Society 02 Public Distribution System Shop 06 Post Office 01 Other Amenities Sub-post Office 06 Open Drainage 08 Closed Drainage 06 Source: Census of India, 2011 Basic amenities like water supply for drinking and other uses is available with various sources such as Tap (Treated & Un-treated), Well (Covered & Un-covered), Hand Pump, Tube wells, River/Canal and Tank etc. Electricity is available for domestic, agriculture and commercial or industrial uses in almost all over the study area. The study area having approach roads as Black Topped (Paved), Gravel and Footpath. 50