Sample Procurement Plan I. General 1. Bank’s approval Date of the Procurement Plan: Original, October 2015. 2. Date of General Procurement Notice: June 26, 2017 3. Period covered by this procurement plan: From September 2017 to September 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB (Works) All All 2. ICB (Goods and Non- All All Consulting Services) 3. NCB (Works) From US$ 15 million All 4. NCB (Goods and Non- From US$ 4 million All Consulting Services) 5. Shopping (Works) None None 6. Shopping (Goods and Non- None None Consulting Services) 7. Direct Contracting (Works) From US$ 15 million All Direct Contracting (Goods and From US$ 4 million All Non-Consulting Services) 2. Prequalification. Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: Not applicable. 4. Reference to (if any) Project Operational/Procurement Manual: The Operations Manual issued by the SEPLAN (Project Implementation Unit) describes the methods and procedures applicable to all procurement of goods, works, non-consulting services and consulting services financed by the Loan Agreement # 8575-BR. 5. Any Other Special Procurement Arrangements: Eligible expenditures under Part 1 of the Project are not subject to the Procurement and Consultant Guidelines. July 9, 2010 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior/Post US$ ence ) million (yes/n o) 1 Summary 0.24 1 No Prior of the ICBs (Goods) 2 Summary 3.1 16 No Post of the NCBs (Goods) 3 Summary 0.96 11 No Post of the NCBs (Non- Consulting Services) 4 Summary 0.23 5 No Post of the Shoppings (Goods) 5 Summary 0.37 10 No Post of the Shoppings (Non- Consulting Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) From US$ 1 million All 2. Single Source Selection (Firms) From US$ 1 million All 3. Individual Consultant From US$ 300,000 All 4 Single Source Selection From US$ 300,000 All (Individuals) 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 1,500,000 equivalent per contract, may comprise entirely of national consultants in July 9, 2010 accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million 1 Summary 5.8 19 Prior of number of contracts that will be let under QCBS method 2 Summary 2.2 25 Post SCQ of number of contracts that will be let under methods other than QCBS 3 Summary 2.7 22 Post IC of number of contracts that will be let under Individual Consultant method July 9, 2010 PROCUREMENT Brazil : Piaui: Pillars of Growth and Social Inclusion Project PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2017-09-26 2021-02-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P129342 GPN Date: 2017-06-26 Project Name: Piaui: Pillars of Growth and Social Inclusion Project Loan / Credit No: IBRD / 85750 S Executing Agency(ies): ecretariat of Planning of the State of Piaui WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Provision of BR-SEPLAN- PI-30415-GO- Em fase de technical assistance to Solicitação de Single Stage - One RFB / Compra de veículos IBRD / 85750 Posterior Open - National 200,000.00 482,980.63 Implementaçã 2017-10-02 2017-07-11 2017-10-07 2017-11-18 2017-09-14 2017-12-18 2017-10-11 2018-01-22 2018-07-21 strengthen the Borrower’s Ofertas Envelope automotores para órgãos o public management. BR-SEPLAN-PI-4-NC-RFQ / Contratação de serviços de Component 2: Provision of hospedagem para os technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 58,812.50 0.00 Cancelado 2017-11-27 2018-01-22 2018-07-21 conselheiros da sociedade strengthen the Borrower’s Cotações Envelope civil participarem das public management. atividades nos 12 territórios BR-SEPLAN-PI-10-GO-RFQ / Component 2: Provision of Aquisição de 02 Kit de technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 51,200.00 0.00 Cancelado 2018-02-06 2018-04-28 2018-10-25 moderação para apoiar as strengthen the Borrower’s Cotações Envelope atividades do planejamento public management. BR-SEPLAN-PI-9-GO-RFB / Aquisição de 10 Component 2: Provision of computadores, 6 notebooks, technical assistance to Solicitação de Single Stage - One 5 tablets, 2 maquina IBRD / 85750 Posterior Open - National 18,750.00 0.00 Cancelado 2018-01-01 2018-01-06 2018-02-17 2018-04-23 2018-10-20 strengthen the Borrower’s Ofertas Envelope fotografica, 1 filmadora, 1 public management. impressora apara apoiar as atividades do SIMO BR-SEPLAN-PI-11-GO-RFB / Component 2: Provision of Aquisição de 2 equipamentos technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 125,000.00 0.00 Cancelado 2018-11-01 2018-11-06 2018-12-18 2019-03-19 2019-09-15 de video wal 2x30 para sala strengthen the Borrower’s Ofertas Envelope de situação public management. BR-SEPLAN- PI-39567-GO- RFQ / Aquisição de 10 Component 2: Provision of computadores, 6 notebooks, Em fase de technical assistance to Solicitação de Single Stage - One 5 tablets, 2 maquinas IBRD / 85750 Posterior Open - National 35,000.00 0.00 Implementaçã 2018-01-22 2018-03-19 2018-09-15 strengthen the Borrower’s Cotações Envelope fotografica, 1 filmadora, 1 o public management. impressora apara apoiar as atividades do SIMO BR-SEPLAN- PI-76150-GO- Component 2: Provision of RFB / Aquisição de 10 Em fase de technical assistance to Solicitação de Single Stage - One veículos para as atividades IBRD / 85750 Posterior Open - National 356,115.00 0.00 Implementaçã 2018-09-10 2017-07-11 2018-09-15 2018-10-27 2018-11-26 2018-12-31 2019-06-29 strengthen the Borrower’s Ofertas Envelope dos órgãos CEPM, SEMAR, o public management. Ouvidoria e SEDUC. BR-SEPLAN- PI-30829-GO- Component 2: Provision of RFQ / Aquisição e instalação technical assistance to Solicitação de Single Stage - One Implementaçã IBRD / 85750 Posterior Open - National 31,250.00 0.00 2019-03-16 2019-05-11 2019-11-07 de equipamentos para strengthen the Borrower’s Cotações Envelope o Pendente videoconferência public management. BR-SEPLAN- PI-39563-GO- Component 2: Provision of RFB / Aquisição de 02 technical assistance to Solicitação de Single Stage - One Implementaçã IBRD / 85750 Posterior Open - National 128,000.00 0.00 2019-04-22 2019-05-20 2019-07-01 2019-07-31 2019-09-04 2020-03-02 equipamentos de video wall strengthen the Borrower’s Ofertas Envelope o Pendente 2x30 para Sala de Situação public management. BR-SEPLAN- PI-133036-GO- Component 2: Provision of RFQ / Aquisição de mobiliário technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Limited 39,000.00 66,755.41 Assinado 2019-11-12 2020-01-27 2020-01-07 2020-03-06 2020-07-05 para suprir a necessidade strengthen the Borrower’s Cotações Envelope dessa SEPLAN. public management. BR-SEPLAN- PI-155164-GO- Component 2: Provision of RFQ / Aquisição de Centrais technical assistance to Solicitação de Single Stage - One de Ar condicionado para IBRD / 85750 Posterior Open - National 47,732.00 38,258.31 Assinado 2020-03-07 2020-05-02 2020-07-02 2020-10-29 strengthen the Borrower’s Cotações Envelope estruturação do prédio da public management. SEPLAN BR-SEPLAN- PI-155168-GO- RFQ / Aquisição de Component 2: Provision of equipamento de informática e technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 59,665.90 0.00 Cancelado 2020-03-30 2020-05-25 2020-11-21 cabeamento de redes para strengthen the Borrower’s Cotações Envelope prédio anexo pertencente à public management. SEPLAN BR-SEPLAN- PI-183733-GO- Component 2: Provision of RFQ / Aquisições de racks, Em fase de technical assistance to Solicitação de Single Stage - One switchs, solução de wireless e IBRD / 85750 Posterior Open - National 47,350.00 43,303.48 Implementaçã 2020-07-31 2020-09-25 2020-12-14 strengthen the Borrower’s Cotações Envelope serviços de infraestrutura de o public management. cabeamento de rede BR-SEPLAN- PI-185343-GO- RFQ / Aquisição de Component 2: Provision of equipamentos de informática technical assistance to Solicitação de Single Stage - One Implementaçã IBRD / 85750 Posterior Open - National 57,471.26 0.00 2020-08-15 2020-10-10 2021-04-08 (computadores, monitores, strengthen the Borrower’s Cotações Envelope o Pendente nobreaks, mouse, teclado e public management. tablets) para a SEPLAN Page 1 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEPLAN-PI-3-NC-RFQ / Component 2: Provision of Serviço de fornecimento de technical assistance to Solicitação de Single Stage - One alimentação e locação de IBRD / 85750 Posterior Open - National 68,562.50 52,126.39 Assinado 2017-07-06 2017-08-31 2017-09-15 2018-02-27 strengthen the Borrower’s Cotações Envelope auditório, sob demanda, para public management. evento (12 territorios) BR-SEPLAN-PI-5-NC-RFQ / Contratação de serviços de Component 2: Provision of Em fase de deslocamento para os technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Limited 41,875.00 0.00 Implementaçã 2017-10-07 2017-12-02 2018-05-31 conselheiros da sociedade strengthen the Borrower’s Cotações Envelope o civil participarem das public management. atividades nos 12 territorios BR-SEPLAN-PI-16-NC-RFB / Component 2: Provision of Contratação de serviços technical assistance to Solicitação de Single Stage - One gráficos para impressão das IBRD / 85750 Posterior Open - National 62,500.00 15,481.11 Assinado 2017-06-18 2017-08-13 2017-11-16 2018-02-09 strengthen the Borrower’s Cotações Envelope publicações do SIMO e public management. atividades territoriais BR-SEPLANUGP- PI-30311- Component 2: Provision of NC-RFQ / Serviço de Em fase de technical assistance to Solicitação de Single Stage - One alimentação e aluguel de IBRD / 85750 Posterior Limited 30,000.00 0.00 Implementaçã 2017-10-06 2017-12-01 2018-05-30 strengthen the Borrower’s Cotações Envelope espaço para treinamento em o public management. aquisições Component 2: Provision of BR-SEPLANUGP- PI-30310- technical assistance to Solicitação de Single Stage - One NC-RFB / Empresa de IBRD / 85750 Posterior Limited 80,000.00 0.00 Cancelado 2018-01-07 2018-03-04 2018-08-31 strengthen the Borrower’s Cotações Envelope auditoria de DLIs public management. BR-SEPLAN- PI-30824-NC- RFQ / Contratação de 01 consultor especializado para Component 2: Provision of serviço de diagramação e art Em fase de technical assistance to Solicitação de Single Stage - One design dos materiais IBRD / 85750 Posterior Open - National 9,000.00 0.00 Implementaçã 2018-01-07 2018-03-04 2019-03-29 strengthen the Borrower’s Cotações Envelope produzidos para o SIMO e o public management. ações territoriais que desenvolverá a identidade visual da ação BR-SEPLANUGP- PI-30304- Component 2: Provision of NC-RFB / Contratação de technical assistance to Solicitação de Single Stage - One firma independente de IBRD / 85750 Posterior Limited 22,500.00 0.00 Cancelado 2018-01-07 2017-05-30 2018-03-04 2018-08-31 strengthen the Borrower’s Cotações Envelope auditoria financeira para os public management. anos do Projeto BR-SEPLAN-PI-8-NC-RFQ / Aluguel de 2 veiculos, por Component 2: Provision of dois anos, para apoio ao technical assistance to Solicitação de Single Stage - One processo de monitoramento IBRD / 85750 Posterior Limited 53,000.00 1,657.02 Assinado 2017-07-06 2017-06-14 2017-08-31 2017-07-07 2019-12-31 strengthen the Borrower’s Cotações Envelope nos órgãos setoriais e nos public management. territórios de desenvolvimento. BR-SEPLANUGP-PI-03-CS- Component 2: Provision of INDV / Serviços de technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 115,385.00 0.00 Cancelado 2017-05-01 2017-05-06 2017-06-17 2017-07-17 2017-08-21 2018-02-17 fornecimento e aquisição de strengthen the Borrower’s Ofertas Envelope passagens aéreas public management. BR-SEPLAN- PI-39574-NC- Component 2: Provision of RFB / Serviço de fornecimento technical assistance to Solicitação de Single Stage - One Implementaçã de passagens aéreas para IBRD / 85750 Posterior Open - National 115,385.00 0.00 2018-01-08 2018-01-13 2018-02-24 2018-03-26 2018-04-30 2018-10-27 strengthen the Borrower’s Ofertas Envelope o Pendente deslocamentos relacionados public management. as atividades do projeto BR-SEPLAN- PI-72433-NC- Component 2: Provision of RFQ / Contratação de firma technical assistance to Solicitação de Single Stage - One independente de auditoria IBRD / 85750 Posterior Limited 9,300.00 5,582.09 Assinado 2018-08-06 2019-06-29 2018-08-31 2018-09-07 2018-12-07 strengthen the Borrower’s Cotações Envelope financeira para o exercício public management. 2017 BR-SEPLAN- PI-76151-NC- Component 2: Provision of RFQ / Contratação de firma Em fase de technical assistance to Solicitação de Single Stage - One independente de auditoria IBRD / 85750 Posterior Limited 9,000.00 0.00 Implementaçã 2019-04-15 2019-06-17 2019-09-23 strengthen the Borrower’s Cotações Envelope financeira para o exercício o public management. 2018 BR-SEPLAN- PI-76155-NC- RFQ / Serviço de Locação de Component 2: Provision of 02 veículos tipo Picape para technical assistance to Solicitação de Single Stage - One Implementaçã IBRD / 85750 Posterior Limited 41,612.00 0.00 2018-09-08 2018-11-03 2019-11-11 apoio ao processo de strengthen the Borrower’s Cotações Envelope o Pendente planejamento, monitoramento public management. e avaliação BR-SEPLAN- PI-94448-NC- Component 2: Provision of RFQ / Segunda contratação de technical assistance to Solicitação de Single Stage - One serviços gráficos para IBRD / 85750 Posterior Open - National 62,500.00 26,260.81 Assinado 2019-01-15 2019-03-12 2019-04-04 2019-09-08 strengthen the Borrower’s Cotações Envelope impressão das publicações do public management. SIMO e atividades territoriais BR-SEPLAN- PI-94451-NC- RFQ / Segunda contratação de Component 2: Provision of serviço de fornecimento de technical assistance to Solicitação de Single Stage - One IBRD / 85750 Posterior Open - National 68,562.50 47,137.09 Assinado 2019-01-15 2019-03-12 2019-03-21 2019-09-08 alimentação e locação de strengthen the Borrower’s Cotações Envelope auditório, sob demanda, para public management. evento (12 territorios) BR-SEPLAN- PI-114276-NC- Component 2: Provision of RFQ / Contratação de firma technical assistance to Solicitação de Single Stage - One independente de auditoria IBRD / 85750 Posterior Limited 10,000.00 0.00 Cancelado 2020-01-06 2020-03-09 2020-06-15 strengthen the Borrower’s Cotações Envelope financeira para o exercício public management. 2019 BR-SEPLAN- PI-127584-NC- Component 2: Provision of DIR / Contratação de firma technical assistance to independente de auditoria IBRD / 85750 Posterior Aquisição Direta Direct 6,500.00 4,564.42 Assinado 2019-09-02 2019-08-28 2019-09-09 2020-05-01 2019-12-22 2020-04-13 2020-06-19 strengthen the Borrower’s financeira para o exercício public management. 2019 Page 2 Component 2: Provision of BR-SEPLAN- PI-155508-NC- technical assistance to Solicitação de Single Stage - One Implementaçã RFQ / Serviços gráficos para a IBRD / 85750 Posterior Open - National 28,639.00 0.00 2020-03-13 2020-05-08 2020-11-04 strengthen the Borrower’s Cotações Envelope o Pendente SEPLAN public management. BR-SEPLAN- PI-157995-NC- RFQ / Serviço de digitalização Component 2: Provision of e higienização do acervo technical assistance to Solicitação de Single Stage - One Implementaçã bibliográfico de referência de IBRD / 85750 Posterior Open - National 81,967.00 0.00 2020-03-21 2020-05-16 2020-11-12 strengthen the Borrower’s Cotações Envelope o Pendente estudo socioeconômico e public management. administrativos sobre o Piauí, pertencente à SEPLAN-PI BR-SEPLAN- PI-173100-NC- DIR / Contratação OSs para intermediar fabricação por Component 2: Provision of associações de costureiras e technical assistance to IBRD / 85750 Posterior Aquisição Direta Direct 159,091.00 58,460.54 Assinado 2020-05-13 2020-05-22 2020-05-18 2020-10-01 2020-06-22 2020-10-20 2020-12-19 distribuição de máscaras strengthen the Borrower’s artesanais para entrega nos public management. territórios de desenvolvimento. BR-SEPLAN- PI-114277-NC- Component 2: Provision of RFQ / Contratação de firma technical assistance to Solicitação de Single Stage - One Implementaçã independente de auditoria IBRD / 85750 Posterior Limited 4,880.00 0.00 2021-04-19 2021-06-21 2021-09-27 strengthen the Borrower’s Cotações Envelope o Pendente financeira para o exercício public management. 2020 e Período de Graça CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEPLAN-PI-1-CS-QCBS / Contratação de consultoria Component 2: Provision of Seleção Baseada para reestruturação do technical assistance to Em fase de IBRD / 85750 Posterior na Qualidade e Open - National 281,250.00 0.00 2017-09-12 2017-11-24 2017-10-03 2017-11-16 2018-08-29 2017-12-14 2018-08-29 2018-01-13 2018-02-17 2018-04-18 2019-04-18 processo de planejamento, strengthen the Borrower’s Implementação Custo orçamento, monitoramento e public management. avaliação do Governo do Piaui. BR-SEPLAN- PI-133115-CS- CQS / Consultoria para apoiar Component 2: Provision of a remodelagem da Política de Seleção Baseada technical assistance to Implementação Desenvolvimento Territorial e IBRD / 85750 Posterior nas Qualificações Open - National 170,000.00 0.00 2019-10-31 2019-11-21 2020-01-04 2020-02-03 2020-03-09 2020-09-05 strengthen the Borrower’s Pendente elaboração do Plano de dos Consultores public management. Desenvolvimento Sustentável do Estado do Piauí INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEPLANUGP-PI-01-CS- Component 2: Provision of INDV / Contratação de technical assistance to IBRD / 85750 Posterior Individual Open 72,000.00 21,884.80 Assinado 2017-08-10 2017-11-24 2017-09-20 2018-04-25 2017-09-29 2018-05-03 2017-10-02 2018-09-26 2018-10-02 serviços de consultoria em strengthen the Borrower’s aquisições (UGP) public management. BR-SEPLAN-PI-6-CS-CI / Contratação de consultor especializados para realizar Component 2: Provision of ações de capacitação de technical assistance to Em fase de IBRD / 85750 Posterior Individual Open 6,750.00 0.00 2018-02-26 2019-09-19 2018-04-16 2018-05-07 2018-06-11 2018-12-08 conselheiros territoriais nas strengthen the Borrower’s Implementação áreas de planejamento, public management. controle social, agendas territoriais e monitoramento BR-SEPLAN- PI-30295-CS- INDV / Contratação de consultor especializados para Component 2: Provision of realizar ações de capacitação technical assistance to IBRD / 85750 Posterior Individual Open 6,750.00 0.00 Cancelado 2018-01-02 2018-02-20 2018-03-13 2018-04-17 2018-10-14 de conselheiros territoriais strengthen the Borrower’s nas áreas de planejamento, public management. controle social, agendas territoriais e monitoramento BR-SEPLAN- PI-30296-CS- INDV / Contratação de consultor especializados para Component 2: Provision of realizar ações de capacitação technical assistance to IBRD / 85750 Posterior Individual Open 6,750.00 0.00 Cancelado 2018-01-02 2018-02-20 2018-03-13 2018-04-17 2018-10-14 de conselheiros territoriais strengthen the Borrower’s nas áreas de planejamento, public management. controle social, agendas territoriais e monitoramento BR-SEPLAN- PI-30297-CS- INDV / Contratação de consultor especializados para Component 2: Provision of realizar ações de capacitação technical assistance to IBRD / 85750 Posterior Individual Open 6,750.00 0.00 Cancelado 2018-01-02 2018-02-20 2018-03-13 2018-04-17 2018-10-14 de conselheiros territoriais strengthen the Borrower’s nas áreas de planejamento, public management. controle social, agendas territoriais e monitoramento BR-SEPLANUGP- PI-30307- Component 2: Provision of CS-INDV / Consultor technical assistance to especializado em IBRD / 85750 Posterior Individual Open 51,000.00 0.00 Cancelado 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 strengthen the Borrower’s salvaguardas ambientais e public management. sociais BR-SEPLAN-PI-13-CS-INDV / Contratação, por tempo, de 01 consultor especializado Component 2: Provision of para serviço de elaboração de technical assistance to Em fase de procedimentos e IBRD / 85750 Posterior Individual Open 15,000.00 0.00 2018-01-30 2018-04-04 2018-04-25 2018-06-07 2018-12-04 strengthen the Borrower’s Implementação metodologias com aplicação public management. de estatísticas e tecnologias da informação para extrair e processar dados do SIMO Page 3 BR-SEPLAN- PI-72430-CS- INDV / Consultor individual especializado para realização de verificação técnica que Component 2: Provision of ateste o alcance das metas technical assistance to IBRD / 85750 Posterior Individual Open 12,728.14 0.00 Em Análise 2019-01-09 2020-04-03 2019-02-18 2019-02-23 2019-03-18 2019-05-19 dos Indicadores Vinculados ao strengthen the Borrower’s Desembolso (DLI) 01 a 09 public management. ligados ao segundo, terceiro, quarto e quinto desembolsos do Projeto BR-SEPLAN-PI-12-CS-INDV / Contratação de consultor Component 2: Provision of especializado para serviço de technical assistance to Implementação IBRD / 85750 Posterior Individual Open 18,750.00 0.00 2019-02-25 2019-05-13 2019-06-03 2019-07-08 2020-05-28 elaboração das agendas strengthen the Borrower’s Pendente territoriais e atlas dos public management. territórios BR-SEPLAN- PI-94264-CS- INDV / Consultor individual especializado para realização de verificação técnica que Component 2: Provision of ateste o alcance das metas technical assistance to Em fase de IBRD / 85750 Posterior Individual Open 12,727.13 0.00 2019-01-09 2018-11-08 2019-02-18 2019-02-23 2019-03-18 2019-05-19 dos Indicadores Vinculados ao strengthen the Borrower’s Implementação Desembolso (DLIs) 10 a 15 public management. ligados ao segundo, terceiro, quarto e quinto desembolsos do Projeto BR-SEPLAN-PI-15-CS-INDV / Contratação de consultor com o objetivo de assistir ao SIMO na reestruturação, Component 2: Provision of normatização e padronização technical assistance to Implementação de processos, rotinas IBRD / 85750 Posterior Individual Limited 31,250.00 0.00 2019-01-25 2019-01-30 2019-02-20 2019-03-27 2019-09-23 strengthen the Borrower’s Pendente organizacionais na public management. alimentação e utilização do sistema pelos diversos atores, identificando os problemas e sugerindo mudanças BR-SEPLAN- PI-114271-CS- INDV / CONSULTOR INDIVIDUAL ESPECIALISTA EM GESTÃO DE PROJETOS PARA Component 2: Provision of ASSESSORAR A technical assistance to Implementação IBRD / 85750 Posterior Individual Direct 70,000.00 0.00 2019-05-20 2019-05-25 2019-06-15 2019-07-20 2020-12-26 COORDENAÇÃO DA UNIDADE strengthen the Borrower’s Pendente DE GESTÃO DE PROJETOS DO public management. PROJETO PIAUÍ: PILARES DE CRESCIMENTO E INCLUSÃO SOCIAL. Duração de 19 meses BR-SEPLAN- PI-129101-CS- INDV / CONTRATAÇÃO DE CONSULTOR INDIVIDUAL Component 2: Provision of ESPECIALISTA EM AQUISIÇÕES technical assistance to E CONTRATAÇÕES REGIDAS IBRD / 85750 Posterior Individual Direct 33,000.00 1,911,290.60 Assinado 2019-08-30 2019-08-28 2019-09-04 2019-08-28 2019-09-08 2019-08-29 2019-09-29 2019-10-08 2020-12-17 strengthen the Borrower’s PELAS DIRETRIZES DE public management. AQUISIÇÕES E SELEÇÕES DE CONSULTORES DO BANCO MUNDIAL BR-SEPLAN- PI-129105-CS- INDV / CONTRATAÇÃO DE Component 2: Provision of CONSULTOR INDIVIDUAL technical assistance to IBRD / 85750 Posterior Individual Direct 23,500.00 13,105.06 Assinado 2019-09-09 2019-09-05 2019-09-15 2019-09-11 2019-09-27 2019-09-11 2019-10-27 2019-11-18 2021-01-17 ASSESSOR EM AQUISIÇÕES strengthen the Borrower’s PARA A UNIDADE DE public management. GERENCIAMENTO DO PROJETO BR-SEPLAN- PI-132885-CS- INDV / Consultor individual especializado para realização de segunda verificação técnica Component 2: Provision of que ateste o alcance das technical assistance to IBRD / 85750 Posterior Individual Open 12,700.00 0.00 Em Análise 2019-10-31 2020-04-01 2019-12-31 2020-01-05 2020-01-28 2020-03-30 metas dos Indicadores strengthen the Borrower’s Vinculados ao Desembolso public management. (DLIs) 10 a 15 do Projeto Piaui: Pilares de Crescimento e Inclusão Social BR-SEPLAN- PI-132883-CS- INDV / Consultor individual especializado para realização de segunda verificação técnica Component 2: Provision of que ateste o alcance das technical assistance to IBRD / 85750 Posterior Individual Limited 13,500.00 0.00 Em Análise 2020-02-02 2020-04-01 2020-02-07 2020-02-28 2020-04-03 2020-09-30 metas dos Indicadores strengthen the Borrower’s Vinculados ao Desembolso public management. (DLI) 01 a 09 do Projeto Piauí: Pilares de Crescimento e Inclusão Social. BR-SEPLAN- PI-155808-CS- INDV / Consultor individual especializado em engenharia civil para auxiliar a Unidade Component 2: Provision of Gestora do Projeto no technical assistance to monitoramento das ações, IBRD / 85750 Posterior Individual Direct 20,719.42 0.00 Em Análise 2020-02-09 2020-02-07 2020-02-19 2020-03-11 2020-04-15 2021-04-10 strengthen the Borrower’s principalmente a construção public management. dos Centros de Especialidades em doenças Crônicas e as reformas das Escolas de Tempo Integral. Page 4