Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan 26 May 2017 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: The procurement period of project covered from year May 2017 to March 2018 II. Goods and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. Shopping (Goods) Above US$ 100,000 First contract 2. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project LSO-Social Assistance Project (P151442) issued by MoSD of PIU>PIM for Lesotho 3. Any Other Special Procurement Arrangements: No packages will be financed under retroactive financing 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Review Comments No. Cost by Bank July 9, 2010 US$ Domestic (Prior / Preferenc Post) e (yes/no) Summary of the NIL NIL No NIL No major works ICB (Works) Summary of the NIL NIL No NIL ICB (Goods) Summary of the NIL NIL No NIL No major works NCB (Works) Summary of the NIL NIL No NIL NCB (Goods) Summary of the NIL NIL No NIL ICB (Non- Consultant Services) Summary of the 630,100.00 11 No Post SHOPPING (Goods) Summary of the NIL NIL No NIL DC (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 300,000 2. Single Source (Firms) All 3. Individual Above US$ 100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ million (Prior / Post) Summary of NIL NIL NIL number of contracts that will be let under LCS July 9, 2010 Summary of 1,135,000.00 1 Prior Consultants number of contracts Qualification Selection that will be let under CQS Summary of 2,217,000.00 13 Prior Individual Consultants number of contracts that will be let under IC July 9, 2010 PROCUREMENT Lesotho : Social Assistance Project PLAN General Information Country: Lesotho Bank’s Approval Date of the Original Procurement Plan: 2017-09-28 2020-02-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151442 GPN Date: 2018-06-29 Project Name: Social Assistance Project Loan / Credit No: IDA / 58340, IDA / 59320 Executing Agency(ies): Ministry of Social Development WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MOSD-26652-GO-RFQ / Procurement of 40 Anti Component 2: Request for Single Stage - One Viruses for Desktops and IDA / 58340 Post Limited 4,500.00 4,461.67 Completed 2017-09-13 2017-10-11 2017-11-01 Implementation Support Quotations Envelope Laptops for Social Assistance Project LS-MOSD-26655-GO-RFQ / Procurement of Mobile Component 2: Request for Single Stage - One Filling Cabinets (3 Bay IDA / 58340 Post Limited 40,000.00 22,106.43 Completed 2017-09-20 2017-10-16 2017-11-27 Implementation Support Quotations Envelope Zippel) for 10 bursaries units in the Districts. LS-MOSD-54631-GO-RFQ / Supply, deliver and fit office Component 2: Request for Single Stage - One IDA / 58340 Post Limited 3,737.30 3,741.59 Completed 2018-03-25 2018-05-20 2018-11-16 furniture at DPS office at Implementation Support Quotations Envelope Letsie Complex LS-MOSD-106546-GO-RFB / Development and Component 2: Open - Single Stage - Two implementation of GOL IDA / 58340 Post Request for Bids 1,600,000.00 0.00 Canceled 2019-03-22 2019-04-04 2019-05-16 2019-07-29 2019-08-20 2020-02-28 Implementation Support International Envelope Social Benefit System (OAP- MIS) LS-MOSD-119687-GO-RFQ / Pending Procurement of video camera Component 2: Request for IDA / 58340 Post 11,500.00 0.00 Implementati 2019-07-19 2019-09-13 2020-03-11 and accessories for Implementation Support Quotations on information office LS-MOSD-119785-GO-RFB / Procurement of 13 Vehicles Under Component 2: Single Stage - One (10 Vehicles for 10 Districts, IDA / 58340 Post Request for Bids Open - National 507,143.00 0.00 Implementati 2019-07-28 2019-08-02 2019-09-13 2019-10-13 2019-11-17 2020-05-15 Implementation Support Envelope 1 for Pensitions and 2 for on Civil Registry) LS-MOSD-119795-GO-RFQ / Procurement of 10 Under Component 2: Request for Single Stage - One Computers for MOF, 3 IDA / 58340 Post Open - National 85,714.00 0.00 Implementati 2019-07-27 2019-09-21 2020-03-19 Implementation Support Quotations Envelope Laptops for NICR and 13 on Printers Page 1 LS-MOSD-119799-GO-RFQ / Under Procurement of 2 Mobile Component 2: Request for Single Stage - One IDA / 58340 Post Open - National 35,714.00 0.00 Implementati 2019-07-27 2019-09-21 2020-03-19 Registration Units for Implementation Support Quotations Envelope on Ministry of Home Affairs LS-MOSD-125572-GO-RFB / Procurement of Hardware Component 2: Single Stage - Two IDA / 59320 Post Request for Bids Open - National 960,000.00 0.00 Canceled 2019-09-13 2019-09-18 2019-10-30 2020-01-12 2020-02-16 2020-08-14 Equipment of MOSD MIS to Implementation Support Envelope incorporate OAP Program LS-MOSD-138987-GO-RFB / Under Procurement of Hardware Component 2: Single Stage - Two IDA / 59320 Post Request for Bids Open - National 960,000.00 0.00 Implementati 2019-10-08 2019-10-13 2019-11-24 2020-02-06 2020-03-12 2020-09-08 Equipment of MOSD MIS to Implementation Support Envelope on incorporate OAP Program LS-MOSD-139007-GO-RFQ / Pending Component 2: Request for Single Stage - One Procurement of A5 Leaflets IDA / 58340 Post Open - National 5,000.00 0.00 Implementati 2019-10-16 2019-12-11 2020-06-08 Implementation Support Quotations Envelope and A1 Posters on LS-MOSD-139013-GO-RFQ / Under Procurement of IEC Material Component 2: Request for Single Stage - One IDA / 58340 Post Open - National 8,000.00 0.00 Implementati 2019-10-16 2019-12-11 2020-06-08 for OAP Verification Exercise Implementation Support Quotations Envelope on (RRI) LS-MOSD-119803-GO-RFQ / Pending Component 2: Request for Single Stage - One Installation of call centre for IDA / 58340 Post Open - National 66,000.00 0.00 Implementati 2019-11-27 2020-01-22 2020-07-20 Implementation Support Quotations Envelope MOSD on LS-MOSD-139017-GO-RFQ / Pending Supply and Delivery of 11 Component 2: Request for Single Stage - One IDA / 58340 Post Open - National 25,000.00 0.00 Implementati 2019-11-29 2020-01-24 2020-07-22 Desktops, 6 Laptops and 1 Implementation Support Quotations Envelope on Computer for MoSD LS-MOSD-144364-GO-RFQ / Pending Component 2: Request for Single Stage - One Procurement of Office IDA / 58340 Post Open - National 7,200.00 0.00 Implementati 2019-11-23 2020-01-18 2020-01-28 Implementation Support Quotations Envelope Furniture for MOSD Officers on LS-MOSD-144366-GO-RFQ / Procurement of 300 Bag Pending Component 2: Request for Single Stage - One Packs for Verification IDA / 58340 Post Open - National 6,000.00 0.00 Implementati 2019-11-16 2019-12-26 2019-12-31 Implementation Support Quotations Envelope Officers during OAP on verification exercise LS-MOSD-144371-GO-RFQ / Procurement of 300 Power Pending Component 2: Request for Single Stage - One Banks for verification officers IDA / 58340 Post Open - National 5,000.00 0.00 Implementati 2019-11-15 2019-12-30 2020-01-04 Implementation Support Quotations Envelope during OAP verification on exercise NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MOSD-43402-NC-DIR / South-South Learning Forum Component 2: IDA / 58340 Post Direct Selection Direct 10,662.00 3,051.42 Completed 2018-01-11 2018-01-16 2018-02-20 2018-08-19 to be held in Frankfurt Implementation Support Germany LS-MOSD-54626-NC-RFQ / Removal of MoSD Property Component 2: Request for Single Stage - One IDA / 58340 Post Limited 2,750.00 4,754.58 Completed 2018-03-25 2018-05-20 2018-11-16 from Moposo and Health Implementation Support Quotations Envelope Building to Letsie Complex Page 2 LS-MOSD-54632-NC-RFQ / Procurement of internet Component 2: Request for Single Stage - One IDA / 58340 Post Limited 27,326.39 22,387.99 Completed 2018-03-25 2018-05-20 2018-11-16 cabling services at Letsie Implementation Support Quotations Envelope Complex LS-MOSD-78634-NC-DIR / Component 2: Procure Financial IDA / 58340 Prior Direct Selection Direct 150,000.00 71,830.00 Signed 2018-10-16 2018-10-21 2018-11-25 2019-05-24 Implementation Support Management System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MOSD-78619-CS-QCBS / Recruitment of Component 2: Quality And Cost- IDA / 59320 Post Open - National 300,000.00 0.00 Canceled 2018-09-28 2018-10-19 2018-12-02 2018-12-30 2019-01-29 2019-03-05 2019-04-09 2020-04-08 Nutrition/Infant initiative for Implementation Support Based Selection first 1000 days pilot LS-MOSD-78621-CS-CQS / Consultant Recruitment of firm to Component 2: IDA / 58340 Post Qualification Open - National 150,000.00 0.00 Canceled 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2019-03-29 conduct survey for Social Implementation Support Selection Assistance citizen satisfaction LS-MOSD-87767-CS-INDV / Consultancy for Hiring an Implementing Partner Component 2: Quality And Cost- Open - IDA / 59320 Post 950,000.00 0.00 Canceled 2018-11-29 2018-12-13 2019-01-26 2019-02-23 2019-03-25 2019-04-29 2019-06-03 2020-06-02 Organization for Graduation Implementation Support Based Selection International Community Development Model Program in Lesotho LS-MOSD-119544-CS-CQS / Consultancy to carry out Consultant Component 2: Under Social Assistance Citizen and IDA / 58340 Post Qualification Open - National 400,000.00 0.00 2019-07-28 2019-08-18 2019-10-01 2019-10-31 2019-12-05 2020-06-02 Implementation Support Implementation Beneficiary Statisfaction Selection Survey LS-MOSD-119624-CS-CQS / Consultant Consultancy for the Component 2: Open - Under IDA / 58340 Post Qualification 110,000.00 0.00 2019-07-28 2019-08-18 2019-10-01 2019-10-31 2019-12-05 2020-06-02 improvement of the OAP Implementation Support International Implementation Selection Payment System LS-MOSD-119626-CS-CQS / Consultant Consultancy to conduct Component 2: Open - Pending IDA / 58340 Post Qualification 25,000.00 0.00 2019-09-05 2019-09-26 2019-11-09 2019-12-09 2020-01-13 2020-07-11 external Financial Audit of Implementation Support International Implementation Selection the OAP LS-MOSD-119628-CS-CQS / Consultancy to carry out Consultant feasibility on reforms of Component 2: IDA / 58340 Post Qualification Open - National 200,000.00 0.00 Canceled 2019-09-29 2019-10-20 2019-12-03 2020-01-02 2020-02-06 2020-08-04 CGP to cater for the 1000 Implementation Support Selection days and draw Operational Plan LS-MOSD-119629-CS-CQS / Consultant Consultancy for Impact Component 2: IDA / 58340 Post Qualification Open - National 250,000.00 0.00 Canceled 2019-10-21 2019-11-11 2019-12-25 2020-01-24 2020-02-28 2020-08-26 Evaluation of the CGP and Implementation Support Selection or Public Assistance Program LS-MOSD-119678-CS-CQS / Consultancy for inclusion of Consultant Component 2: SP module in two rounds on IDA / 58340 Post Qualification Open - National 100,000.00 0.00 Canceled 2019-09-15 2019-10-06 2019-11-19 2019-12-19 2020-01-23 2020-07-21 Implementation Support CMS data and analysis of Selection data Page 3 LS-MOSD-119681-CS-CQS / Facilitator for team building Consultant Component 2: Under and strategic direction IDA / 58340 Post Qualification Open - National 36,000.00 0.00 2019-09-30 2019-10-21 2019-12-04 2020-01-03 2020-02-07 2020-08-05 Implementation Support Implementation reflection for MOSD Selection Management LS-MOSD-119625-CS-CQS / Consultant Consultancy to carry out Component 2: Pending IDA / 58340 Post Qualification Open - National 100,000.00 0.00 2019-11-21 2019-12-12 2020-01-25 2020-02-24 2020-03-30 2020-09-26 process evaluation for the Implementation Support Implementation Selection OAP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MOSD-32417-CS-INDV / Individual Component 2: Recruitment of 10 Data IDA / 58340 Post Consultant Open 255,738.39 6,989.66 Signed 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2020-09-01 Implementation Support Clerks Selection LS-MOSD-28189-CS-INDV / Individual Component 2: Review and improve OAP IDA / 58340 Post Consultant Open 170,000.00 68,753.40 Completed 2017-09-12 2017-09-12 2017-10-03 2017-11-07 2018-05-06 Implementation Support MIS Selection LS-MOSD-27464-CS-INDV / Individual Component 2: Eliminate ineligible IDA / 58340 Post Consultant Open 170,000.00 115,621.00 Signed 2017-09-06 2017-09-11 2017-09-15 2017-09-22 2018-09-14 Implementation Support beneficiaries Selection Individual LS-MOSD-30774-CS-INDV / Component 2: IDA / 58340 Prior Consultant Open 288,000.00 190,443.00 Signed 2017-10-13 2017-11-16 2017-11-26 2017-12-18 2019-12-18 Project Coordinator Implementation Support Selection LS-MOSD-43396-CS-INDV / Individual Component 2: Position of Accounts and IDA / 58340 Prior Consultant Open 240,000.00 3,814.84 Signed 2018-01-18 2018-03-08 2018-03-29 2018-05-03 2019-08-02 Implementation Support Finance Manager Selection LS-MOSD-44300-CS-CDS / Component 2: IDA / 58340 Prior Direct Selection Direct 100,000.00 251,296.00 Signed 2018-02-15 2018-02-25 2018-05-01 2018-10-28 implementation of the BRAC Implementation Support LS-MOSD-51397-CS-INDV / Individual Component 2: Recruitment of IDA / 58340 Post Consultant Open 32,162.00 35,000.00 Signed 2018-03-16 2018-05-04 2018-05-25 2018-06-29 2020-06-28 Implementation Support Administrative Officer Selection Individual LS-MOSD-51398-CS-INDV / Component 2: Under IDA / 58340 Post Consultant Open 78,212.00 0.00 2018-03-16 2018-05-04 2018-05-25 2018-06-29 2020-06-28 Recruitment of 3 Drivers Implementation Support Implementation Selection LS-MOSD-53003-CS-INDV / Individual Component 2: Position of Project IDA / 58340 Prior Consultant Open 288,000.00 3,983.12 Completed 2018-03-09 2018-04-27 2018-05-18 2018-06-22 2019-02-28 Implementation Support Coordinator Selection LS-MOSD-53004-CS-INDV / Individual Component 2: Position of Procurement IDA / 58340 Prior Consultant Open 240,000.00 3,983.12 Signed 2018-03-09 2018-04-27 2018-05-18 2018-06-22 2019-02-28 Implementation Support Specialist Selection LS-MOSD-53006-CS-INDV / Position of Financial Individual Component 2: Management Specialist IDA / 58340 Prior Consultant Open 240,000.00 4,563.99 Terminated 2018-03-09 2018-04-27 2018-05-18 2018-06-22 2019-02-28 Implementation Support (Finance and Account Selection Manager) Page 4 LS-MOSD-59725-CS-CDS / Request to use single source Component 2: selection (SSS) for the IDA / 58340 Prior Direct Selection Direct 100,000.00 51,535.91 Signed 2018-05-24 2018-06-13 2018-08-17 2019-02-13 Implementation Support improvement of the OAP MIS System LS-MOSD-78624-CS-INDV / Individual Component 2: Hire consultant to develop IDA / 58340 Post Consultant Open 120,000.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2019-02-28 Implementation Support payment mechanism Selection LS-MOSD-78453-CS-CDS / CONSULTANCY SERVICES TO PREPARE AN Individual Component 2: ENVIRONMENTAL AND IDA / 59320 Post Consultant Limited 100,000.00 8,475.59 Signed 2018-10-25 2018-10-30 2018-11-20 2018-12-25 2019-06-23 Implementation Support SOCIAL MANAGEMENT Selection FRAMEWORK FOR THE LIVELIHOODS LS-MOSD-85765-CS-INDV / Individual Recruitment of Procurement Component 2: Under IDA / 58340 Post Consultant Open 58,000.00 0.00 2018-11-12 2018-12-31 2019-01-21 2019-02-25 2019-08-24 Specialist for Social Implementation Support Implementation Selection Assistance Project Individual LS-MOSD-87764-CS-INDV / Component 2: IDA / 59320 Post Consultant Open 25,000.00 0.00 Canceled 2018-11-29 2019-01-17 2019-02-07 2019-03-14 2019-09-10 Market Assessment Implementation Support Selection LS-MOSD-106533-CS-CDS / Consultancy to advise and Component 2: Under IDA / 58340 Post Direct Selection Direct 140,000.00 0.00 2019-04-26 2019-05-08 2019-06-26 2020-03-27 assess MOSD MIS for Implementation Support Implementation absorption of OAP. LS-MOSD-119406-CS-INDV Individual Component 2: / Technical Advisor for IDA / 58340 Post Consultant Limited 11,000.00 0.00 Canceled 2019-06-28 2019-07-03 2019-07-24 2019-08-28 2020-02-24 Implementation Support Social Protection Selection LS-MOSD-119574-CS-INDV / Technical Assistance for Individual Component 2: Under Rapid Results Initiative IDA / 58340 Post Consultant Limited 115,000.00 0.00 2019-08-04 2019-08-09 2019-08-30 2019-10-04 2020-04-01 Implementation Support Implementation around the OAP Proof of Selection Life LS-MOSD-119677-CS-INDV Individual Component 2: Under / Facilitator for the end of IDA / 58340 Post Consultant Open 50,000.00 0.00 2019-11-10 2019-12-29 2020-01-19 2020-02-23 2020-08-21 Implementation Support Implementation the Project Review Selection LS-MOSD-119683-CS-INDV / Facilitator for customer Individual Component 2: Pending care and stress Management IDA / 58340 Post Consultant Open 15,000.00 0.00 2019-10-07 2019-11-25 2019-12-16 2020-01-20 2020-07-18 Implementation Support Implementation for drivers and office Selection assistant LS-MOSD-119684-CS-INDV Individual / Facilitator for Institutional Component 2: Pending IDA / 58340 Post Consultant Open 17,000.00 0.00 2019-09-30 2019-11-18 2019-12-09 2020-01-13 2020-07-11 Strengthening for middle Implementation Support Implementation Selection Management LS-MOSD-125410-CS-CDS / Consultancy for Software Component 2: Under Development Services to IDA / 58340 Post Direct Selection Direct 240,000.00 0.00 2019-08-18 2019-08-28 2019-11-01 2020-04-29 Implementation Support Implementation MOSD MIS to incorporate OAP Program LS-MOSD-144744-CS-INDV / Consultancy services to undertake development of Individual Component 2: Pending Lesotho Tertiary Students IDA / 59320 Post Consultant Limited 50,000.00 0.00 2019-11-24 2019-11-29 2019-12-04 2019-12-19 2020-04-30 Implementation Support Implementation bursaries means testing Selection mechanism (Policy and Instruments) Page 5 LS-MOSD-144747-CS-CDS / SYSTEM DEVELOPER SERVICES TO UNDERTAKE DEVELOPMENT AND INTEGRATION OF LESOTHO TERTIARY Component 2: Pending IDA / 59320 Post Direct Selection Direct 22,000.00 0.00 2019-11-17 2019-11-27 2020-01-31 2020-04-30 STUDENT BURSARIES Implementation Support Implementation MEANS TESTING MODEL INTO THE STUDENT SPONSORSHIP MANAGEMENT AND ADMINISTRATION SYSTEM (SSMAS) LS-MOSD-144748-CS-INDV / CONSULTANCY SERVICES TO Individual Component 2: Pending UNDERTAKE IDA / 59320 Post Consultant Limited 28,000.00 0.00 2019-11-17 2019-11-22 2019-12-13 2020-01-17 2020-04-30 Implementation Support Implementation DEVELOPMENT OF Selection LESOTHO TERTIARY EDUCATION FINANCING STRATEGY LS-MOSD-152857-CS-CDS / Consultancy Services for Component 2: Pending Community Councils IDA / 59320 Post Direct Selection Direct 10,800.00 0.00 2020-01-16 2020-01-26 2020-02-17 2020-03-31 Implementation Support Implementation Emergency Enrolment for MOSD Beneficiaries LS-MOSD-156587-CS-CDS / Component 2: Pending Consultant for Emergency IDA / 58340 Post Direct Selection Direct 5,800.00 0.00 2020-02-07 2020-02-15 2020-03-06 2020-03-31 Implementation Support Implementation Top Up Payment Page 6