Poverty Alleviation and Agriculture Development Demonstration in Poor Areas Project sichuan Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: May 13, 2015: 1stRevision: May 11, 2018; 2nd Revision: November 27, 2018; 3rd Revision: March 22, 2019; 4th Revision: April 4, 2019; 5th Revision: April 29, 2019; 6th Revision: June 24, 2019; 7th Revision: May 26, 2020; 8th Revision: June 9, 2020] 2. Date of General Procurement Notice: November 23, 2015 3. Period covered by this procurement plan: 2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 10million All 2. NCB (Goods) Above US$ 2million All 3. ICB (Works) Above US$ 40 million All 4. NCB (Works) Above US$ 10 million All 5. (Non-Consultant Services) Above US$ 2million All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Yes, in procurement manual] 4. Reference to (if any) Project Operational/Procurement Manual: Yes 5. Any Other Special Procurement Arrangements: no 6. Summary of the Procurement Packages planned: [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. No. Description Estimated Packages Domestic Review Comments Preference Cost by Bank (yes/no) US$ million (Prior / Post) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of 0.5784 1 No Post the NCB (Works) Summary of the NCB (Goods) Summary of 2.7850 22 No Post the Shopping (Works) Summary of 0.0274 3 No Post the Shopping (Goods) Summary of the ICB (Non- Consultant Services) Summary of the NCB (Non- Consultant Services) Summary of 0.0393 2 No Post the Shopping (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 1 million 2. Single Source (Firms) Above US$ 1 million 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: No 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ million (Prior / Post) Summary of number of contracts that will be let under QCBS Summary of 0.2727 12 post number of contracts that will be let under CQS Summary of 0.1786 16 post number of contracts that will be let under IS PROCUREMENT China : Poverty Alleviation and Agriculture-based Industry Pilot and Demonstration in Poor Areas Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2019-02-22 2020-08-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133326 GPN Date: Project Name: Poverty Alleviation and Agriculture-based Industry Pilot and Demonstration in Poor Areas Project Loan / Credit No: IBRD / 85090 Executing Agency(ies): Guizhou PPMO WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GZCS-GC-07 / 2km Pending Public Infrastructure and Request for Single Stage - One production road for Fukang IBRD / 85090 Post Limited 49,200.00 0.00 Implementat 2019-04-07 2019-06-02 2019-10-30 Services Quotations Envelope Cooperative. ion GZCS-GC-08 / irrigation Pending facility for 300mu dendrobe Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 73,800.00 0.00 Implementat 2019-04-07 2019-06-02 2019-10-30 production base in Changqi Services Quotations Envelope ion Town Fukang Cooperative GZCS-GC-09 / 2 reservoirs Pending Public Infrastructure and Request for Single Stage - One for the production base of IBRD / 85090 Post Limited 24,600.00 0.00 Implementat 2019-04-08 2019-06-03 2019-10-31 Services Quotations Envelope Fukang Cooperative ion GZTZ-GC-04 / 259m Pending Public Infrastructure and Request for Single Stage - One production road consrtuction IBRD / 85090 Post Limited 49,200.00 0.00 Implementat 2019-03-09 2019-05-04 2019-07-03 Services Quotations Envelope in Huaqiu Town ion GZDF-GC-02-24 / 3.825KM Pending Public Infrastructure and Request for Single Stage - One production road construction IBRD / 85090 Post Limited 487,000.00 0.00 Implementat 2019-03-09 2019-05-04 2019-10-01 Services Quotations Envelope in Maochang Town ion GZDF-GC-02-26 / 5KM Pending Public Infrastructure and Request for Single Stage - One production road construction IBRD / 85090 Post Limited 491,800.00 0.00 Implementat 2019-03-09 2019-05-04 2019-10-01 Services Quotations Envelope in Lvtang Town ion GZDF-GC-04-02 / THE Pending second batch of water Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 245,900.00 0.00 Implementat 2019-03-09 2019-05-04 2019-08-02 resource project--constructing Services Quotations Envelope ion irrigation facilities GZDF-GC-04-03 / 1.7 KM Pending drainage ditch construction Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 409,800.00 0.00 Implementat 2019-03-09 2019-05-04 2019-08-02 in Legong Village, Niuchang Services Quotations Envelope ion Town GZDF-GC-03-03 / 11.79km Pending Public Infrastructure and Request for Single Stage - One production road in IBRD / 85090 Post Limited 226,200.00 0.00 Implementat 2019-08-10 2019-09-20 2020-03-18 Services Quotations Envelope Yangchang Town ion GZZJ-GC-01-05 / 2.22 KM Pending Public Infrastructure and Request for Single Stage - One tractor road construction in IBRD / 85090 Post Limited 97,900.00 0.00 Implementat 2019-03-09 2019-05-04 2019-09-01 Services Quotations Envelope Jianfu Village ion Pending GZZJ-GC-01-06 / 7.55KM Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 244,900.00 0.00 Implementat 2019-03-09 2019-05-04 2019-09-01 tractor road construction Services Quotations Envelope ion Page 1 GZZJ-GC-01-07 / 3.4 KM tractor road construction in Qianjin Village, Baini Town 2 KM tractor road Pending Public Infrastructure and Request for Single Stage - One construction in Xianfeng IBRD / 85090 Post Limited 326,500.00 0.00 Implementat 2019-03-05 2019-04-30 2019-10-27 Services Quotations Envelope Village, Baini Town ion 2 KM tractor road construction in Dashujiao Village, Baini Town GZZJ-GC-01-08 / 5 KM Pending Public Infrastructure and Request for Single Stage - One tractor road construction in IBRD / 85090 Post Limited 220,600.00 0.00 Implementat 2019-03-09 2019-05-04 2019-09-01 Services Quotations Envelope Dapotou Village ion GZZJ-GC-01-09 / 3.7 KM Pending Public Infrastructure and Request for Single Stage - One tractor road construction in IBRD / 85090 Post Limited 163,200.00 0.00 Implementat 2019-03-09 2019-05-04 2019-09-01 Services Quotations Envelope Yumin Village. ion GZZJ-GC-01-10 / 1.85 KM Pending Public Infrastructure and Request for Single Stage - One tractor road construction in IBRD / 85090 Post Limited 81,600.00 0.00 Implementat 2019-03-10 2019-05-05 2019-10-02 Services Quotations Envelope Babu street Town. ion GZZJ-GC-02-01 / Pending Public Infrastructure and Request for Single Stage - One Constructing production road IBRD / 85090 Post Limited 247,100.00 0.00 Implementat 2019-03-10 2019-05-05 2019-09-02 Services Quotations Envelope of 21 km in Baiyan Village ion GZZJ-GC-02-02 / Pending Public Infrastructure and Request for Single Stage - One Constructing production road IBRD / 85090 Post Limited 155,300.00 0.00 Implementat 2019-03-10 2019-05-05 2019-09-02 Services Quotations Envelope of 13.2 km in Baini Town ion GZZJ-GC-02-03 / Pending Constructing production road Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 61,800.00 0.00 Implementat 2019-03-10 2019-05-05 2019-09-02 of 5.25 km in Jinlong Services Quotations Envelope ion Village. GZZJ-GC-02-04 / Pending Constructing production road Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 155,300.00 0.00 Implementat 2019-03-10 2019-05-05 2019-09-02 of 13.2 km in Zhongzhai Services Quotations Envelope ion Town. GZZJ-GC-02-05 / Pending Constructing production road Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 92,900.00 0.00 Implementat 2019-03-10 2019-05-05 2019-09-02 of 7.9 km in Jichang Services Quotations Envelope ion Village. GZZJ-GC-02-06 / Pending Constructing 3.9km Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 45,900.00 0.00 Implementat 2019-03-10 2019-05-05 2019-10-02 production road in Sanjia Services Quotations Envelope ion Street. GZZJ-GC-02-07 / Pending Constructing production road Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 30,600.00 0.00 Implementat 2019-03-10 2019-05-05 2019-11-01 of 2.6 km for Yacai planting Services Quotations Envelope ion area in Babu Street. Pending GZZJ-GC-03 / 41 reservoirs Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 226,500.00 0.00 Implementat 2019-03-10 2019-05-05 2019-07-04 in5 towns Services Quotations Envelope ion Pending GZZJ-GC-04 / 21KM Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 92,600.00 0.00 Implementat 2019-03-10 2019-05-05 2019-08-03 irrigation facility in 3 towns Services Quotations Envelope ion Pending GZTZ-GC-03 / site leveling Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 82,000.00 0.00 Implementat 2019-03-10 2019-05-05 2019-07-04 of 8000 sq.m Services Quotations Envelope ion Page 2 GZDF-GC-03-03 / 11.79 KM Pending Public Infrastructure and Request for Single Stage - One industrial road in Yangchang IBRD / 85090 Post Limited 197,142.86 0.00 Implementat 2020-08-08 2020-09-08 2020-12-07 Services Quotations Envelope Town,Dafang County ion GZDF-GC-05 -05 / 2KM Pending cooperative power facilities Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 42,857.14 0.00 Implementat 2020-08-08 2020-08-30 2020-10-29 in Yingpan Village, LvTang Services Quotations Envelope ion Town, Dafang County GZDF-GC- 05-06 / 3KM Pending cooperative power facilities Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 64,285.71 0.00 Implementat 2020-08-10 2020-09-06 2020-09-12 in Bijiao Village, Maochang Services Quotations Envelope ion Town, Dafang County GZDF-GC- 05-07 / 1.5KM cooperative power facilities Pending Public Infrastructure and Request for Single Stage - One in Dalugou Group Jinkou IBRD / 85090 Post Limited 32,142.86 0.00 Implementat 2020-08-08 2020-09-03 2020-11-02 Services Quotations Envelope Village, Maochang Town, ion Dafang County GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Pending GZTZ-HW-01 / purchasing 4 Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 131,100.00 0.00 Implementati 2019-03-09 2019-04-06 2019-06-05 sets of transformers Services Quotations Envelope on Pending GZZJ-HW-03 / purchasing Public Infrastructure and Request for Single Stage - One IBRD / 85090 Post Limited 22,100.00 0.00 Implementati 2019-03-06 2019-05-01 2019-06-30 office equipment Services Quotations Envelope on GZTZ-HW- 03 / One Pending Public Infrastructure and 250KVA transformer for IBRD / 85090 Post Direct Selection Direct 21,400.00 0.00 Implementati 2020-08-03 2020-08-08 2020-08-29 2020-10-28 Services Tongzi County on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Pending GZXS-FZX-01 / cooperative Integrated Value Chain Request for Single Stage - One IBRD / 85090 Post Limited 163,900.00 0.00 Implementati 2019-03-10 2019-05-05 2019-12-31 farmer training Development Quotations Envelope on Pending GZCS-FZX-02 / cooperative Integrated Value Chain Request for Single Stage - One IBRD / 85090 Post Limited 49,200.00 0.00 Implementati 2019-03-09 2019-05-04 2020-04-28 production training Development Quotations Envelope on Pending GZCS-FZX-01 / cooperative Integrated Value Chain Request for Single Stage - One IBRD / 85090 Post Limited 49,200.00 0.00 Implementati 2019-03-09 2019-05-04 2020-04-28 managerial training Development Quotations Envelope on Pending GZCS-FZX-03 / cooperative Integrated Value Chain Request for Single Stage - One IBRD / 85090 Post Limited 49,200.00 0.00 Implementati 2019-03-09 2019-04-22 2020-04-16 technology training Development Quotations Envelope on Page 3 Pending GZDF-FZX-08-02 / Integrated Value Chain Request for Single Stage - One IBRD / 85090 Post Limited 111,500.00 0.00 Implementati 2019-05-20 2019-07-15 2020-07-09 cooperative farmer training Development Quotations Envelope on GZZJ-FZX-01 / employing a professional agency to train Pending cooperstive managerial staff Integrated Value Chain Request for Single Stage - One IBRD / 85090 Post Limited 16,800.00 0.00 Implementati 2019-03-06 2019-05-01 2020-04-25 in order to improve their Development Quotations Envelope on operation management and marketign abilities GZZJ-FZX-02 / employing a professional agency to carry out minority ethnics training Pending Integrated Value Chain Request for Single Stage - One including practical IBRD / 85090 Post Limited 264,700.00 0.00 Implementati 2019-03-06 2019-05-01 2020-04-25 Development Quotations Envelope technology, women on development and harmonious relations with neighbors. GZZJ-FZX-03 / employing a professional agency to Pending Integrated Value Chain Request for Single Stage - One improve practical technology IBRD / 85090 Post Limited 110,300.00 0.00 Implementati 2019-03-06 2019-05-01 2020-04-25 Development Quotations Envelope cooperative members and on farmers CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZSJ-ZX- 08 / Guizhou Province Project Office selects the third party service agency to analyze Consultant and study the way and Research, Training and Pending IBRD / 85090 Post Qualification Open - National 173,913.04 0.00 2020-08-03 2020-08-17 2020-08-27 2020-08-29 2020-08-31 2021-04-28 effect of the project Extension Implementation Selection implementation, summarize the experience and refine the mode and measures that can be promoted. GZXMB-ZX- 10 / Guizhou Province Project Office selects the third party Consultant service agency to provide Research, Training and Pending IBRD / 85090 Post Qualification Open - National 65,217.39 0.00 2020-08-03 2020-08-17 2020-08-27 2020-08-29 2020-08-31 2021-08-26 guidance in order to Extension Implementation Selection improve cooperatives' operation management and marketing abilities GZXMB -ZX-11 / Guizhou Province Project Office selects the third party service agency to sort out Consultant various documents and files Project Management, Pending IBRD / 85090 Post Qualification Open - National 5,797.10 0.00 2020-08-03 2020-08-17 2020-08-27 2020-08-29 2020-08-31 2020-12-29 in the project Monitoring and Evaluation Implementation Selection implementation management to form a standardized and standardized file management method. Page 4 GZXMB- ZX-12 / Guizhou Province Project Office selects the third party service agency to provide legal consulting services for Consultant Project Management, Pending project implementation and IBRD / 85090 Post Qualification Open - National 11,594.20 0.00 2020-08-04 2020-08-18 2020-08-28 2020-09-02 2020-09-04 2020-09-07 Monitoring and Evaluation Implementation management, review and Selection provide contract management technical guidance, and be entrusted to handle legal affairs INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZZJ-ZX-01-04 / employing Individual Public Infrastructure and Pending 6 facilitatorsfor Zhijin PMO, IBRD / 85090 Post Consultant Limited 39,300.00 0.00 2019-03-01 2019-03-15 2019-03-20 2019-03-30 2020-03-24 Services Implementation contract extension. Selection GZDF-ZX-02-02 / contract Individual extension for a cooperative Public Infrastructure and Pending IBRD / 85090 Post Consultant Limited 3,900.00 0.00 2019-03-01 2019-03-15 2019-03-20 2019-03-30 2020-03-24 financial expert in Dafang Services Implementation Selection County. GZDF-ZX-01-04 / contract Individual extension for one year of 6 Public Infrastructure and Pending IBRD / 85090 Post Consultant Limited 39,300.00 0.00 2019-03-01 2019-03-15 2019-03-20 2019-03-30 2020-03-24 facilitators in Dafang Services Implementation Selection County. GZTZ-ZX-04-04 / contract Individual Public Infrastructure and Pending extension of a faciitator in IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-03-01 2019-03-15 2019-03-20 2019-03-30 2020-03-24 Services Implementation Tongzi County. Selection GZTZ-ZX-05 / employing a Individual Public Infrastructure and Pending new facilitator in Tongzi IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-03-01 2019-03-15 2019-03-20 2019-03-30 2020-03-24 Services Implementation County. Selection GZTZ-ZX-06 / employing a Individual Public Infrastructure and Pending new facilitator in Tongzi IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-03-01 2019-03-15 2019-03-20 2019-03-30 2020-03-24 Services Implementation County Selection GZTZ-ZX-07 / employing a Individual Public Infrastructure and Pending new facilitator in Tongzi IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-03-01 2019-03-15 2019-03-20 2019-03-30 2020-03-24 Services Implementation County. Selection GZXS-ZX-01-04 / contract Individual Public Infrastructure and Pending extension of one year for IBRD / 85090 Post Consultant Limited 19,700.00 0.00 2019-11-01 2019-11-15 2019-11-22 2019-12-02 2020-11-26 Services Implementation facilitators. Selection GZCS-ZX-06-04 / recruiting Individual Public Infrastructure and Pending a facilitator named Hu IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-11-01 2019-11-15 2019-11-20 2019-11-30 2020-11-24 Services Implementation Yongfang for the 4th year. Selection GZCS-ZX-07-02 / recruiting Individual Public Infrastructure and Pending a facilitator named Du IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-11-01 2019-11-15 2019-11-18 2019-11-26 2020-11-20 Services Implementation Bingli for the second year. Selection GZCS-ZX-08-02 / recruiting Individual a facilitator named Ming Public Infrastructure and Pending IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-11-01 2019-11-15 2019-11-22 2019-12-04 2020-11-28 Hongyuan for the second Services Implementation Selection year Page 5 GZCS-ZX-09-02 / recruiting Individual Public Infrastructure and Pending a facilitator named Shi IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-11-04 2019-11-09 2019-11-16 2019-11-30 2020-11-24 Services Implementation Weitao for the second year Selection Individual GZXS-ZX-02 / recruiting a Project Management, Pending IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-03-04 2019-03-09 2019-03-30 2019-05-04 2019-12-30 financial technician Monitoring and Evaluation Implementation Selection Individual GZXS-ZX-03 / recruiting a Project Management, Pending IBRD / 85090 Post Consultant Limited 4,900.00 0.00 2019-03-04 2019-03-09 2019-03-30 2019-05-04 2019-12-30 legal advisor. Monitoring and Evaluation Implementation Selection GZCS-ZX-06-05 / Continue to employ Hu Yongfang as Individual Public Infrastructure and Pending the cooperative advisor for IBRD / 85090 Post Consultant Limited 4,285.71 0.00 2020-11-02 2020-11-07 2020-11-14 2020-11-28 2021-11-23 Services Implementation the 5th year in Chishui Selection City, Zunyi Manucipality GZCS-ZX-07- 03 / Continue to employ Du Bingli as the Individual Public Infrastructure and Pending cooperative advisor for the IBRD / 85090 Post Consultant Limited 4,285.71 0.00 2020-11-02 2020-11-07 2020-11-14 2020-11-28 2021-11-23 Services Implementation third year in Chishui City, Selection Zunyi Manucipality GZCS-ZX-08 -03 / Continue to employ Ming Hongyuan Individual as the cooperative advisor Public Infrastructure and Pending IBRD / 85090 Post Consultant Limited 4,285.71 0.00 2020-11-02 2020-11-07 2020-11-14 2020-11-28 2021-11-23 for the third year in Services Implementation Selection Chishui City, Zunyi Manucipality GZCS-ZX-09 -03 / Continue to employ Zhong Weitao as Individual Public Infrastructure and Pending the cooperative advisor for IBRD / 85090 Post Consultant Limited 4,285.71 0.00 2020-11-02 2020-11-07 2020-11-14 2020-11-28 2021-11-23 Services Implementation the third year in Chishui Selection City, Zunyi Manucipality Page 6