Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] July 9, 2010 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contract (Works) for Prior Review Summary 1.86 4 No Post 1st of the NCB contract (Goods) for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Sao Tome and Principe : STP Power Sector Recovery Project PLAN General Information Country: Sao Tome and Principe Bank’s Approval Date of the Original Procurement Plan: 2016-07-21 2021-03-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157096 GPN Date: 2016-09-29 Project Name: STP Power Sector Recovery Project Loan / Credit No: IDA / V0030, IDA / D1260, IDA / D5870 P Executing Agency(ies): roject Fiduciary and Administrative Agency WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 03/W/PSR/2016 / Investing in enhanced Reabilitation and expansion of reliability of electricity Single Stage - One 2018-03- access roads in Ponta Figo to IDA / D1260 Post Request for Bids Open - National 480,000.00 0.00 Canceled 2017-05-16 2017-05-21 2017-07-02 2017-08-01 2017-09-05 generation, transmission and Envelope 04 the water channels and load distribution chamber 19/W/PSR/2016 / Project Implementation Request for Single Stage - One 2017-10- Rehabilitation of a new AFAP's IDA / D1260 Post Limited 41,000.00 61,655.34 Signed 2017-02-28 2017-01-03 2017-04-25 2017-01-09 Support Quotations Envelope 22 office 32/W/PSR/2018 / Obstacle Strengthening operational Request for Single Stage - One 2018-11- clearance in the canal access IDA / D1260 performance and governance Post Open - National 320,000.00 430,602.88 Signed 2018-03-27 2018-05-22 2018-09-03 Quotations Envelope 18 to Contador of EMAE 01/W/PSR/2016 / Investing in enhanced Rehabilitation and expansion reliability of electricity Single Stage - One 14,600,000.0 2021-01- IDA / D1260 Prior Request for Bids Open - International 0.00 Canceled 2018-12-21 2018-12-10 2019-03-08 2019-06-12 2019-03-08 2018-12-26 2018-12-12 2019-05-17 2019-06-16 2019-07-21 of the Contador Hydropwer generation, transmission and Envelope 0 11 Plant and access road distribution 04/W/PSR/2016 / Investing in enhanced Rehabilitation of key Pending reliability of electricity Single Stage - One 2022-10- components of Contador IDA / D1260 Post Request for Bids Open - International 900,000.00 0.00 Implementat 2021-12-15 2021-12-20 2022-01-31 2022-03-02 2022-04-06 generation, transmission and Envelope 03 transmission line and ion distribution equipment 71/W/PSR/2020 / Investing in enhanced Rehabilitation and expansion reliability of electricity Request for Single Stage - One 18,000,000.0 2021-11- IDA / D5870 Prior Open - International 0.00 Canceled 2021-02-05 2021-02-10 2021-03-24 2021-04-23 2021-05-28 of the Contador Hydropwer generation, transmission and Proposals Envelope 0 24 Plant and access road distribution 76/W/PRSE/2021 / Design, Investing in enhanced Supply and Installation of the Pending reliability of electricity Single Stage - One 2022-02- Electromechanical Equipment IDA / D5870 Prior Request for Bids Open - International 3,000,000.00 0.00 Implementat 2021-04-19 2021-04-24 2021-06-05 2021-07-05 2021-08-09 generation, transmission and Envelope 05 for the Rehabilitation and ion distribution Extension of the Contador HPP GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/S/PSR/2016 / Purchase Strengthening operational Single Stage - One and installation of 3000 IDA / D1260 performance and governance Prior Request for Bids Open - International 1,200,000.00 0.00 Canceled 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 Envelope power meters for large of EMAE customers 04/S/PSR/2016 / Purchase and installation of 2000 3- Strengthening operational Single Stage - One phase power meters for large IDA / D1260 performance and governance Prior Request for Bids Open - International 3,700,000.00 0.00 Canceled 2018-03-18 2018-03-23 2018-05-04 2018-06-03 2018-07-08 2019-01-04 Envelope customers and 16000 single of EMAE phase power meters Investing in enhanced 01/G/PSR/2016 / Purchase Under reliability of electricity Request for Single Stage - One of three double cabin 4WD IDA / D1260 Post Limited 99,000.00 0.00 Implementati 2016-11-10 2017-02-02 2017-01-30 2017-07-29 generation, transmission and Quotations Envelope pickups on distribution 23/G/PSR/2016 / Purchase Pending Project Implementation Request for Single Stage - One of fourniture for the new IDA / D1260 Post Open - National 50,000.00 0.00 Implementati 2017-02-28 2017-04-25 2017-10-22 Support Quotations Envelope AFAP's office on 03/S/PSR/2016 / Purchase Strengthening operational Single Stage - One and installation of 170 IDA / D1260 performance and governance Post Request for Bids Open - International 300,000.00 0.00 Canceled 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 Envelope statistical meters of EMAE 65/G/PSR/2020 / Supply, Installation, Commissioning Investing in enhanced Under and Testing of Fuel reliability of electricity Single Stage - One IDA / D1260 Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2020-03-10 2020-03-16 2020-03-15 2020-04-26 2020-05-26 2020-06-15 2020-10-21 Monitoring System For The generation, transmission and Envelope on EMAE’s Diesel Thermal distribution Generation Plants 70/G/PRSE/2020 / Supply of Investing in enhanced Under Two hundred forty six reliability of electricity Single Stage - One IDA / D5870 Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2020-06-01 2020-07-20 2020-06-06 2020-07-20 2020-07-18 2020-09-18 2020-08-17 2020-11-13 2020-09-21 2021-03-20 thousand five hundred generation, transmission and Envelope on (246,500) LED lamps distribution Investing in enhanced 38/G/2018 / Purchase and Pending reliability of electricity Single Stage - One installation of turbines at the IDA / D1260 Prior Request for Bids Open - International 2,300,000.00 0.00 Implementati 2021-03-12 2021-03-17 2021-04-28 2021-05-28 2021-07-02 2021-12-29 generation, transmission and Envelope Contador Plant on distribution NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 05/S/PSR/2016 / Update of Under Project Implementation the AFAP's existing IDA / D1260 Prior Direct Selection Direct 30,000.00 0.00 Implementati 2016-11-18 2016-11-23 2016-12-28 2017-06-26 Support management software on 10/S/PSR/2016 / Technical Pending assistance for designer and Project Implementation Request for Single Stage - One IDA / D1260 Post Open - National 15,000.00 0.00 Implementati 2017-02-28 2017-04-25 2017-10-22 supervision of the new AFAP's Support Quotations Envelope on office Investing in enhanced Under 34/S/PSR/2018 / reliability of electricity Single Stage - One IDA / D1260 Post Request for Bids Limited 90,000.00 0.00 Implementati 2018-03-26 2018-02-21 2018-03-31 2018-01-16 2018-05-12 2018-06-11 2018-07-16 2019-01-12 Topographic surveying study generation, transmission and Envelope on distribution Investing in enhanced 35/S/PSR/2018 / Apoio a reliability of electricity realização do levantamento IDA / D1260 Post Direct Selection Direct 25,000.00 17,092.54 Signed 2018-08-27 2019-03-18 2018-09-01 2019-03-18 2018-10-06 2019-03-29 2019-04-04 generation, transmission and topográfico distribution 01/S/PSR/2016 / Acquisition, Strengthening operational Pending installation and configuration Single Stage - One IDA / D1260 performance and governance Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2021-06-18 2021-06-23 2021-08-04 2021-09-03 2021-10-08 2022-04-06 of the management Envelope of EMAE on Information System in EMAE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/C/EPPF/16 / Feasibility Investing in enhanced study for the rehabilitation of reliability of electricity Quality And Cost- IDA / V0030 Prior Open - International 275,000.00 1,250,725.57 Signed 2016-07-21 2016-07-27 2016-07-21 2016-09-09 2016-10-26 2016-10-07 2017-02-01 2016-11-06 2017-03-06 2016-12-11 2017-07-07 2017-01-15 2017-07-11 2018-01-15 the Contador Hydro Power generation, transmission and Based Selection Plant distribution Investing in enhanced 03/C/EPPF/16 / Technical Consultant reliability of electricity Assistance to elaborate the IDA / V0030 Prior Qualification Open - International 90,000.00 212,935.00 Signed 2016-10-07 2017-01-30 2016-10-28 2017-04-12 2016-12-11 2017-06-15 2017-01-10 2017-07-06 2017-02-14 2017-10-17 2017-08-13 generation, transmission and Environmental impact Study Selection distribution 01/C/PSR/2016 / Project Project Implementation Least Cost IDA / D1260 Post Open - International 80,000.00 41,160.00 Signed 2016-11-24 2016-09-28 2016-12-15 2017-01-28 2016-11-08 2017-02-25 2016-12-19 2017-03-27 2017-01-19 2017-05-01 2017-02-19 2017-06-05 2017-03-20 2017-12-02 audit Support Selection 02/C/PSR/2016 / Development of integrated Support to institutional Quality And Cost- Least Cost Power IDA / D1260 Prior Open - International 400,000.00 190,957.50 Completed 2017-01-27 2017-04-12 2017-02-17 2017-05-02 2017-04-02 2017-07-27 2017-04-30 2017-09-15 2017-05-30 2017-10-13 2017-07-04 2018-01-11 2017-08-08 2017-12-29 2018-08-08 2018-10-24 reform and sector planning Based Selection Development Plan for Sao Tome and Principe 03/C/PSR/2016 / Project Investing in enhanced planning and work Consultant reliability of electricity supervision for rehabilitation IDA / D1260 Post Qualification Open - National 80,000.00 0.00 Canceled 2017-01-08 2017-01-29 2017-03-14 2017-04-13 2017-05-18 2017-11-14 generation, transmission and work of access roads to Selection distribution Contador facility Strengthening operational Consultant 08/C/PSR/2016 / Tariff IDA / D1260 performance and governance Prior Qualification Open - International 200,000.00 0.00 Canceled 2017-12-07 2017-12-28 2018-02-10 2018-03-12 2018-04-16 2018-10-13 Study of EMAE Selection Investing in enhanced 09/C/PSR/2016 / Technical reliability of electricity Quality And Cost- Assistance to prepare the IDA / D1260 Prior Open - International 600,000.00 0.00 Canceled 2018-02-01 2017-07-06 2018-02-22 2018-04-07 2018-05-05 2018-06-04 2018-07-09 2018-08-13 2019-08-13 generation, transmission and Based Selection network protection distribution 04/C/PSR/2017 / Technical Assistance to modernize and Support to institutional Quality And Cost- harmonize legal and IDA / D1260 Post Open - International 250,000.00 283,345.90 Signed 2017-10-11 2017-07-06 2017-10-12 2017-10-30 2017-10-04 2017-11-27 2017-12-27 2018-01-26 2018-01-31 2018-02-23 2018-03-07 2018-04-09 2019-03-07 reform and sector planning Based Selection regulatory framework of the energy sector 04/C/PSR/2016 / Technical Assistance to modernize and Support to institutional Quality And Cost- harmonize legal and IDA / D1260 Prior Open - International 250,000.00 0.00 Canceled 2017-02-06 2017-07-06 2017-02-27 2017-08-07 2017-04-12 2017-05-10 2017-06-09 2017-07-14 2017-08-18 2018-08-18 reform and sector planning Based Selection regulatory framework of the energy sector 06/C/PSR/2016 / Strengthening operational Consultation and Quality And Cost- IDA / D1260 performance and governance Prior Open - National 400,000.00 0.00 Canceled 2017-09-28 2017-10-19 2017-12-02 2017-12-30 2018-01-29 2018-03-05 2018-04-09 2019-04-09 communication Strategy to Based Selection of EMAE end users 05/C/PSR/2016 / Preparation Strengthening operational Quality And Cost- of management Improvement IDA / D1260 performance and governance Prior Open - International 400,000.00 0.00 Canceled 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-12-25 Based Selection Plan for EMAE of EMAE Strengthening operational Consultant 33/C/PSR/2018 / Inventory IDA / D1260 performance and governance Post Qualification Open - National 100,000.00 231,900.00 Signed 2018-03-01 2018-05-03 2018-03-22 2018-07-18 2018-05-05 2018-08-24 2018-06-04 2018-12-07 2018-07-09 2018-12-07 2019-01-05 of EMAE's Assets of EMAE Selection 30/C/PSR/2018 / Strengthening operational Consultant Consultation and IDA / D1260 performance and governance Post Qualification Open - National 150,000.00 239,213.72 Signed 2018-02-23 2017-10-27 2018-03-16 2018-04-29 2018-01-08 2018-05-29 2018-04-03 2018-07-03 2018-04-03 2018-12-30 Comunication Startegy to end of EMAE Selection users 41/C/PRS/2019 / Recruitment of a Human Strengthening operational Consultant resource consultant to IDA / D1260 performance and governance Post Qualification Open - International 170,000.00 162,491.19 Signed 2019-08-18 2019-07-16 2019-09-08 2019-07-31 2019-10-22 2019-10-09 2019-11-21 2019-11-27 2019-12-26 2019-11-27 2020-06-23 support the selection of EMAE of EMAE Selection Top Level Executive Officers 60/C/PSR/2019 / Project Project Implementation Least Cost Under IDA / D1260 Post Open - International 30,000.00 0.00 2019-11-25 2019-12-10 2019-12-16 2020-01-29 2020-02-26 2020-03-27 2020-05-01 2020-06-05 2020-12-02 Audit for the years Support Selection Implementation 2019/2021 75/C/PRSE/2020 / Consultant Facilitating the Selection of an Support to institutional IDA / D5870 Post Qualification Open - International 100,000.00 0.00 Under Review 2021-03-15 2021-03-24 2021-04-05 2021-05-19 2021-06-18 2021-07-23 2022-01-19 Expert for Pre-shipment reform and sector planning Selection Inspection of LED Lamps Page 2 67/C/PRSE/2020 / T.A. for Investing in enhanced Consultant EMAE on the Preparation of reliability of electricity IDA / D1260 Post Qualification Open - National 250,000.00 0.00 Canceled 2020-04-30 2020-05-21 2020-07-04 2020-08-03 2020-09-07 2021-03-06 Awareness Campaign for LED generation, transmission and Selection Bulb Deployment distribution INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 06/C/EPPF/16 / Technical assistance to elaborate the Project Implementation IDA / V0030 Prior Direct Selection Direct 29,000.00 0.00 Canceled 2016-08-17 2016-09-06 2016-08-27 2016-09-28 2016-09-21 2017-03-20 operating, administrative and Support financial procedure manuals 05/C/EPPF/16 / Upgrade of Investing in enhanced Individual the study on the water reliability of electricity IDA / V0030 Post Consultant Limited 50,500.00 0.00 Canceled 2016-09-26 2016-10-01 2016-10-22 2016-11-26 2017-05-25 potential of Sao Tome and generation, transmission and Selection Principe distribution Investing in enhanced Individual 25/C/PSR/2016 / reliability of electricity IDA / D1260 Post Consultant Limited 25,000.00 76,154.87 Signed 2017-02-28 2017-02-13 2017-03-05 2017-03-26 2017-07-10 2017-04-30 2017-07-24 2017-10-27 Topographic surveying study generation, transmission and Selection distribution Investing in enhanced Individual 26/C/PSR/2016 / Preparation reliability of electricity IDA / D1260 Post Consultant Limited 30,000.00 32,706.01 Signed 2017-02-26 2017-02-13 2017-03-03 2017-03-24 2017-07-31 2017-04-28 2017-07-31 2017-10-25 of Geological surface mapping generation, transmission and Selection distribution 27/C/PSR/2016 / Investing in enhanced Individual Assessment of the water reliability of electricity IDA / D1260 Post Consultant Limited 40,000.00 19,058.54 Signed 2017-02-27 2017-02-13 2017-03-04 2017-03-25 2017-05-26 2017-04-29 2017-05-26 2017-10-26 resources available for energy generation, transmission and Selection production at Contador SHP distribution 12/C/PSR/2016 / Project Implementation Recruitment of Financial IDA / D1260 Post Direct Selection Direct 66,000.00 2,750.00 Signed 2016-11-30 2017-01-02 2016-12-10 2017-02-13 2017-01-02 2017-08-12 Support manager 18/C/PSR/2016 / Project Implementation Recruitment of Administrative IDA / D1260 Post Direct Selection Direct 24,000.00 1,000.00 Signed 2016-11-30 2017-01-02 2016-12-10 2017-02-13 2017-01-02 2017-08-12 Support Assistant 24/C/PSR/2016 / Preparation of TOR's for: Topographic Investing in enhanced surveying, geological surface reliability of electricity mapping and assessment of IDA / D1260 Post Direct Selection Direct 17,400.00 17,400.00 Signed 2016-12-16 2016-12-01 2016-12-26 2016-11-17 2017-03-01 2016-12-06 2017-08-28 generation, transmission and the watert resources available distribution for energy production at Contador SHP 11/C/PSR/2016 / Project Implementation Recruitment of AFAP IDA / D1260 Post Direct Selection Direct 98,400.00 0.00 Canceled 2016-11-30 2016-12-01 2016-12-10 2017-02-13 2017-08-12 Support Coordinator 13/C/PSR/2016 / Project Implementation IDA / D1260 Post Direct Selection Direct 66,000.00 3,206.50 Signed 2016-11-30 2016-12-30 2016-12-10 2017-02-13 2017-01-02 2017-08-12 Recruitment of Procurement Support 16/C/PSR/2016 / Project Implementation IDA / D1260 Post Direct Selection Direct 36,000.00 2,750.00 Signed 2016-11-30 2016-12-30 2016-12-10 2017-02-13 2017-01-02 2017-08-12 Recruitment of Accountant Support 15/C/PSR/2016 / Individual Recruitment of Monitoring, Project Implementation IDA / D1260 Post Consultant Open 55,200.00 6,900.00 Signed 2017-02-28 2017-01-31 2017-04-18 2017-04-06 2017-05-09 2017-04-06 2017-06-13 2017-04-10 2017-12-10 environmental safeguards and Support Selection indicators technician Strengthening operational Individual 07/C/PSR/2016 / Demand IDA / D1260 performance and governance Post Consultant Open 95,000.00 0.00 Canceled 2017-01-13 2017-02-01 2017-03-03 2017-03-24 2017-04-28 2017-10-25 Forecast Study of EMAE Selection 28/C/PSR/2017 / Individual Project Implementation Recruitment of Procurement IDA / D1260 Prior Consultant Direct 55,200.00 13,800.00 Signed 2017-03-22 2017-04-05 2017-04-01 2017-04-22 2017-07-27 2017-05-27 2018-03-09 2017-11-23 Support Assistant Selection 10/C/PSR/2016 / Technical Individual Support to institutional Assistance to structure the IDA / D1260 Post Consultant Limited 70,000.00 0.00 Canceled 2018-01-24 2018-01-29 2018-02-19 2018-03-26 2018-09-22 reform and sector planning PPP strategy for AGER Selection Investing in enhanced 09/C/PSR/2017 / Technical Individual reliability of electricity Assistance to prepare the IDA / D1260 Post Consultant Open 60,000.00 74,000.00 Signed 2017-08-18 2017-06-15 2017-10-06 2017-12-27 2017-10-27 2018-03-02 2017-12-01 2018-03-01 2018-05-30 generation, transmission and network protection Selection distribution 14/C/PSR/2016 / Individual Project Implementation Recruitment of Technical IDA / D1260 Post Consultant Open 66,000.00 2,320.00 Signed 2017-10-11 2015-05-04 2017-11-29 2017-12-20 2016-12-05 2018-01-24 2016-07-28 2018-07-23 Support Advisor Selection 14/C/PRS/2016 / Project Implementation Recruitment of Technical IDA / D1260 Post Direct Selection Direct 66,000.00 0.00 Canceled 2016-11-30 2015-04-05 2016-12-10 2017-02-13 2017-08-12 Support Advisor 29/C/PSR/2018 / Preparation Strengthening operational Individual of Management Improvement IDA / D1260 performance and governance Post Consultant Limited 60,000.00 34,100.00 Completed 2018-03-30 2018-03-08 2018-04-04 2018-03-14 2018-04-25 2018-05-15 2018-05-30 2018-06-07 2018-11-26 2018-12-13 Plan for EMAE of EMAE Selection 31/C/PSR/2018 / Individual Independent legal opinion on Support to institutional IDA / D1260 Post Consultant Limited 60,000.00 0.00 Canceled 2018-03-14 2018-03-19 2018-04-09 2018-05-14 2018-11-10 the concession of Catchment- reform and sector planning Selection basin Investing in enhanced 36/C/PSR/2018 / Supervision Individual reliability of electricity of Obstacle clearance in the IDA / D1260 Post Consultant Limited 12,500.00 0.00 Canceled 2018-09-13 2018-09-18 2018-10-09 2018-11-13 2019-05-12 generation, transmission and canal access to Contador Selection distribution Page 3 ST-AFAP-87635-CS-CDS / Strengthening operational Alternatives for urgent IDA / D1260 performance and governance Post Direct Selection Direct 50,000.00 76,000.00 Completed 2018-12-14 2018-12-11 2018-12-24 2019-01-16 2019-02-27 2019-02-20 2019-08-26 2019-06-14 solution of the power deficit of EMAE in Sao Tome 39/C/PSR/16 / Technical assistance to elaborate the Project Implementation IDA / V0030 Post Direct Selection Direct 29,000.00 0.00 Canceled 2016-09-06 2016-09-05 2016-09-16 2016-11-20 2017-05-19 operating, administrative and Support financial procedure manuals 40/C/PSR/2019 / Consultancy Service for Fuel Investing in enhanced Individual Control and Monitoring reliability of electricity IDA / D1260 Post Consultant Limited 40,000.00 32,760.00 Signed 2019-06-17 2019-06-03 2019-06-22 2019-08-12 2019-07-13 2019-10-10 2019-08-17 2019-10-10 2020-02-13 Improvement Plan of EMAE's generation, transmission and Selection Diesel Thermal Generation distribution Plants 50/C/PRS/2019 / Temporary Project Implementation IDA / D1260 Post Direct Selection Direct 6,000.00 0.00 Canceled 2019-10-04 2019-10-14 2019-12-18 2020-06-15 Procurement Assistant Support 51/C/PRS/2019 / Accountant Project Implementation IDA / D1260 Post Direct Selection Direct 13,992.00 0.00 Canceled 2019-10-08 2019-10-18 2019-12-22 2020-06-19 Assistant Support 53/C/PRSE/2019 / Project Implementation Administrative Assistant of IDA / D1260 Post Direct Selection Direct 13,992.00 0.00 Canceled 2019-10-08 2017-05-01 2019-10-18 2019-12-22 2020-06-19 Support AFAP 54/C/PRSE/2019 / Project Implementation IDA / D1260 Post Direct Selection Direct 20,988.00 0.00 Canceled 2019-10-08 2019-10-18 2019-12-22 2020-06-19 Accountant Support 58/C/PSR/2018 / Project Implementation Under Recruitment of a Procurement IDA / D1260 Prior Direct Selection Direct 32,181.60 0.00 2018-12-03 2018-12-13 2019-01-07 2020-01-07 Support Implementation Officer Project Implementation 56/C/PSR/2018 / Accountant IDA / D1260 Post Direct Selection Direct 20,988.00 20,988.00 Signed 2018-12-03 2018-12-31 2018-12-13 2019-01-02 2019-01-07 2019-01-03 2019-02-12 Support 50/C/PSRE/2019 / Project Implementation Pending IDA / D1260 Post Direct Selection Direct 6,000.00 0.00 2018-06-03 2018-06-13 2018-07-14 2018-10-12 Temporary Procurement Support Implementation Assistant 59/C/PSR/2018 / Project Implementation Administrative Assistant of IDA / D1260 Post Direct Selection Direct 13,992.00 13,992.00 Signed 2018-12-03 2018-12-28 2018-12-13 2019-01-02 2019-01-07 2019-01-03 2020-01-07 Support AFAP 13/C/EPPF/2016 / Technical assistance to elaborate the Project Implementation Pending IDA / D1260 Post Direct Selection Direct 29,000.00 0.00 2016-07-05 2016-07-15 2016-08-19 2017-02-15 operating, administrative and Support Implementation financial procedure manuals 57/C/PSR/2018 / Accountant Project Implementation Pending IDA / D1260 Post Direct Selection Direct 13,992.00 0.00 2018-12-03 2018-12-13 2019-01-07 2020-01-07 Assistant Support Implementation 42/C/PRSE/2019 / T.A. FOR Strengthening operational Individual LED BULB DEPLOYMENT IDA / D1260 performance and governance Post Consultant Open 100,000.00 0.00 Canceled 2019-11-07 2019-11-19 2019-12-26 2020-01-16 2020-02-20 2020-08-18 PROGRAMING SAO TOME AND of EMAE Selection PRINCIPE 61/C/PRSE/2019 / T.A. FOR Strengthening operational Individual LED BULB DEPLOYMENT IDA / D1260 performance and governance Post Consultant Limited 100,000.00 63,040.00 Signed 2019-12-05 2019-12-02 2019-12-10 2019-12-19 2019-12-31 2020-01-14 2020-02-04 2020-01-14 2020-08-02 PROGRAMING SAO TOME AND of EMAE Selection PRINCIPE Individual 63/C/PRS/2020 / Social Project Implementation Under IDA / D1260 Post Consultant Open 30,000.00 0.00 2020-03-02 2020-07-23 2020-04-20 2020-05-11 2020-06-15 2020-12-12 safeguards Support Implementation Selection 66/C/PRSE/2020 / Support Strengthening operational to EMAE executives in the IDA / D1260 performance and governance Post Direct Selection Direct 10,000.00 9,580.00 Signed 2020-03-02 2020-03-10 2020-03-12 2020-05-21 2020-05-16 2020-05-22 2020-11-12 implementation of MIP of EMAE Investing in enhanced 68/C/PRSE/2020 / T.A. on reliability of electricity the Implementation of IDA / D1260 Post Direct Selection Direct 70,000.00 60,000.00 Signed 2020-03-23 2020-04-24 2020-04-02 2020-05-07 2020-06-06 2020-06-05 2020-12-03 generation, transmission and Network Protection distribution 64/C/PRS/2020 / Support to Project Implementation Pending IDA / D1260 Post Direct Selection Direct 10,000.00 0.00 2020-03-23 2020-04-02 2020-06-06 2020-12-03 Safeguard department Support Implementation 69/C/PSRP/2020 / Technical assistance to Updating the Project Implementation operating, administrative and IDA / D1260 Post Direct Selection Direct 10,000.00 12,384.00 Signed 2020-03-20 2020-03-24 2020-03-30 2020-04-01 2020-06-03 2020-04-03 2020-11-30 Support financial procedure manuals with the AF 55/C/PSR/2018 / Project Implementation Recruitment of AFAP General IDA / D1260 Post Direct Selection Direct 57,367.20 114,734.40 Signed 2018-12-03 2018-12-20 2018-12-13 2019-01-02 2019-01-12 2019-01-03 2020-01-12 Support Director 72/C/PSR/2020 / Technical Assistance on Procurement for Individual Project Implementation Pending the implementation of the IDA / D1260 Prior Consultant Limited 40,000.00 0.00 2021-01-19 2021-01-24 2021-02-14 2021-03-21 2021-09-17 Support Implementation Contador Hydropower Plant Selection Rehabilitation Project 74/C/PRSE/2021 / Consultant to develop and Investing in enhanced Individual implement a Consumer reliability of electricity IDA / D5870 Prior Consultant Open 230,000.00 0.00 Under Review 2021-03-07 2021-04-25 2021-05-16 2021-06-20 2021-12-17 Awareness and generation, transmission and Selection Communication program for distribution LED Program 73/C/PRSE/2021 / Expert in Monitoring and Evaluation Strengthening operational Individual (M&E) of Impacts of the LED IDA / D5870 performance and governance Prior Consultant Open 250,000.00 0.00 Under Review 2021-04-26 2021-06-14 2021-07-05 2021-08-09 2022-02-05 BULBS AND LED TUBELIGHTS of EMAE Selection DEPLOYMENT PROGRAM IN SAO TOME AND PRINCIPE Page 4 78/C/PRSE/2021 / T.A. to EMAE on the Incorporation of Individual Support to institutional Pending an Information System for IDA / D5870 Post Consultant Limited 65,000.00 0.00 2021-04-30 2021-05-05 2021-05-26 2021-06-30 2021-12-27 reform and sector planning Implementation Management of Corporate Selection Resources 79/C/PRSE/21 / T.A. Individual Support to institutional Pending TRANSACTION ADVISOR TO IDA / D5870 Post Consultant Open 100,000.00 0.00 2021-04-12 2021-05-31 2021-06-21 2021-07-26 2022-01-22 reform and sector planning Implementation ORGANIZE BIDDING PROCESS Selection Page 5