Updated Procurement Plan for Goods and Consulting Services Updated on: 15-Apr-10 Road Network Improvement Project WB/Credit No. 3843 - VN Bank's no RFP Technical evaluation Financial evaluation Draft Contract Advertising Short list RFP/ TOR objection to Issued to Proposals Contract Contract SL No. of Description of Estimated cost Method of Review for Short finalised prepared Shortlist and Shortlisted received Bank's no Bank's no Approved by Bank's no Signed Completion No. Packages Services (USD equiv.) selection* method listing ** Completed Completed (Date) (Date) RFP/ TOR Firms (Date) objection ** objection ** GOV. objection ** (Date) (Date) (Date) (Date) (Date) (Date) (Date) (Date) (Date) (Date) (Date) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 1 PP Procurement of Office equipment 15-Sep-05 15-May-05 15-Nov-05 24-Dec-05 28-Jan-06 31-Dec-05 7-Jan-06 10-Jan-06 11-Mar-06 1 45,000 NS Post review R for PMU2 20-Oct-09 25-Apr-10 4-May-10 11-May-10 16-May-10 16-May-10 25-May-10 26-May-10 9-Jun-10 A 2 PP 31-Dec-05 21-Feb-06 24-Feb-06 2-Mar-06 14-Mar-06 14-Apr-06 30-Apr-06 7-May-06 14-May-06 19-May-06 23-May-06 26-May-06 30-May-06 15-Jun-08 1 Technical Audit for RNIP 500,000 QCBS Prior review R 15-Jul-09 15-Sep-09 31-Oct-09 7-Nov-09 14-Nov-09 12-Dec-09 26-Dec-09 30-Apr-10 14-May-10 28-May-10 11-Jun-10 18-Jun-10 25-Jun-10 6-Dec-13 A 20-Jul-09 5-Oct-09 19-Oct-09 19-Nov-09 25-Nov-09 23-Dec-09 4-Mar-10 3 Upgrading and Maintenance of PP Directing 1 software for RNIP financial 6,020 Post review R Contract 25-Jun-09 2-Jul-09 30-Jun-09 31-Oct-09 management A 18-Apr-09 31-May-09 31-May-09 3-Aug-09 3-Aug-13 4 Long-term consultant service on PP 15-Sep-08 30-Oct-08 4-Nov-08 14-Nov-08 4-Dec-08 3-Jan-09 23-Jan-09 7-Feb-09 27-Feb-09 14-Mar-09 13-Apr-09 28-Apr-09 13-May-09 8-May-10 1 capacity strenthening for 600,000 QCBS Prior review R 12-Jun-09 19-Jun-09 9-Jul-09 8-Aug-09 5-Dec-09 20-Apr-10 20-May-10 4-Jun-10 19-Jun-10 4-Jul-10 19-Jul-10 14-Jul-11 maintenance contractors A 22-Oct-08 20-Dec-08 21-May-09 20-Jul-09 21-Aug-09 6-Sep-09 9-Feb-10 12-Apr-10 5 Long-term consultant service on PP 15-Aug-05 29-Sep-05 4-Oct-05 14-Oct-05 3-Nov-05 3-Dec-05 23-Dec-05 7-Jan-06 27-Jan-06 11-Feb-06 13-Mar-06 28-Mar-06 12-Apr-06 4-Oct-07 2 road network management system 2,100,000 QCBS Prior review R 31-May-10 30-Jun-10 20-Jul-10 4-Aug-10 24-Aug-10 8-Sep-10 8-Oct-10 23-Oct-10 7-Nov-10 30-Apr-12 building A 29-Sep-05 6 Long-term consultant service on PP 15-Aug-05 29-Sep-05 4-Oct-05 14-Oct-05 3-Nov-05 3-Dec-05 23-Dec-05 7-Jan-06 27-Jan-06 11-Feb-06 13-Mar-06 28-Mar-06 12-Apr-06 7-Apr-07 1 business planning and assets 1,100,000 QCBS Prior review R 15-Dec-08 30-Dec-08 31-May-10 30-Jun-10 20-May-09 12-Sep-09 2-Oct-09 17-Oct-09 16-Nov-09 1-Dec-09 16-Dec-09 11-Dec-10 managent for VRA A 8-Dec-08 30-Dec-08 9-Feb-09 29-Jul-09 21-Dec-09 7 PP Audit of Project Financial 1 5,000 LCS Post review R Statement for 2009 A 8 Audit of Project Financial PP 15-May-10 5-Jun-10 19-Jun-10 3-Jul-10 6-Jul-10 5-Aug-10 4-Sep-10 18-Sep-10 2-Oct-10 16-Oct-10 15-Nov-10 22-Nov-10 6-Dec-10 30-Jun-14 1 Statement for years 2010, 2011, 50,000 LCS Post review R 2012 and 2013 A PP Procurement Plan with target dates; R Revision (on the latest/final time); A Actual dates * For Column 5 - in case of firms, state QCBS/QBS/LC/FB/CQ etc as per DCA. in case of individual, state IC, and only fill in columns 1-5, 7, 14-19. ** Applicable only in case of contracts subject to 'Prior Review' by Bank as per DCA. Updated Procurement Plan for Goods and Consulting Services Road Network Improvement Project; WB/Credit No. 3843 - VN Updated on 15-Apr-10 Completed Contract Contract Component/ Contract value Contract Completion (Date) No. Contract name Review method value Signed Started Status Package No. (USD equiv)* (USD equiv)* (Date) (Date) Proposed Actual A NPP Design and supervision services of 1 DESU for NPP Prior review 6,584,378 07-Nov-05 07-Nov-05 30-Jun-10 On-going Periodic maintenance - BCEOM Advisory consulting services - 2 AS for NPP Prior review 2,555,515 1,890,687 25-Dec-05 25-Dec-05 15-Jan-09 Complete RENADET SA Financial Management Prepare the Financial 3 Post review 25,000 25,000 2-Jun-04 2-Jun-04 31/12/2005 Complete Manual Management Manual consultant SETA - 1st Social and environmental technical 3 Post review 44,268 20-Aug-04 20-Aug-04 31-Dec-10 On-going AWP assisstant - 1st AWP NPP SETA - 2nd & Social and environmental technical 4 Post review 103,125 24-Nov-08 24-Nov-08 31-Dec-11 On-going 3rd AWPs assisstant - 2nd & 3rd AWPs NPP Design and supervision services of 5 DESU for PBC Performance Based Contracts - Prior review 1,089,468 14-Feb-07 14-Feb-07 31-Dec-13 On-going WSP+KEI 6 Computer Purchasing computer Post review 41,078 41,078 26-Sep-05 26-Sep-05 14-Nov-05 Complete Official 7 Purchasing official equipments Post review 22,782 22,782 26-Sep-05 26-Sep-05 30-Dec-05 Complete equipment Electronic 8 Purchasing electronic equipments Post review 4,263 4,263 26-Sep-05 26-Sep-05 12-Feb-06 Complete equipment B NIP Detailed design and supervision 9 DESU for NIP Prior review 9,564,448 8-Mar-05 8-Mar-05 31-Dec-09 On-going consulting services SMEC Advisory consulting services - 10 AS for NIP Prior review 1,335,606 12-Apr-05 12-Apr-05 31-Dec-09 On-going Scott Wilson SETA - 1st Social and environmental technical 11 Post review 49,576 On-going AWP assisstant - 1st AWP NIP SETA - 2nd Social and environmental technical 12 Post review 76,563 2-Jan-09 2-Jan-09 30-Sep-12 On-going AWP assisstant - 2nd AWP NIP 13 SUN Sun system maintenance Post review 5,188 5,188 Complete MIS development consulting 14 MIS Post review 31,622 31,622 Complete services ANA accounting software 15 ANA software Post review 6,020 3-Aug-09 3-Aug-09 3-Aug-13 On-going development 16 Vehicle Purchasing the motorbike Post review 8,300 8,300 Complete Official 17 Purchasing official equipments Post review 13,973 13,973 Complete equipment 18 Vehicle Purchasing cars Prior review 147,087 147,087 Complete C RSMIBP 19 PPP PPP consulting services Prior review 935,575 935,575 Complete Financial Audit from beginning of 20 FA Prior review 21,314 21,314 13-Oct-06 13-Oct-06 30-Jun-09 Complete project to end of 2008 HDM4 data 21 Individual consultant Prior review 54,967 54,967 2-Nov-04 2-Nov-04 18-Sep-06 Complete collection 22 HDM4 Analysis Individual consultant Prior review 52,877 52,877 24-Nov-04 24-Nov-04 1-Sep-06 Complete Purchasing equipment for 23 IRI equipment Post review 53,000 53,000 10-Nov-04 10-Nov-04 27-Jan-05 Complete measuring the IRI 24 Computer Purchasing 06 computers Post review 6,766 6,766 2-Aug-05 2-Aug-05 12-Jun-06 Complete Note: * 1USD is equivalent 16,000VND ** Proposed Date Procurement Plan for Works For roads under Initial DCA - Network Improvement Program Road Network Improvement Project; WB/Credit No. 3843 - VN Updated on 15-Apr-10 Cost Contract Completed Contract Contract Contract Completion No. Package No. Contract name Review method Estimate value value Signed Started (Date) Status (USD equiv)* (USD equiv)* (USD equiv)* (Date) (Date) Proposed Actual Improvement NH48-1 Nghe An Old contract 1 NIP/CP-1 (Nam Cam-Cua Lo); Length: Prior review 426,259 426,259 18-Mar-05 5-May-05 Terminated Handed-over 8.0 km; Upgrade to class III. Improvement NH48-1 Nghe An New contract 2 NIP/CP-1/2 (Nam Cam-Cua Lo); Length: Prior review 1,862,043 1,760,438 1,578,562 18-Apr-08 9-May-08 4-Jan-09 26-Jul-09 Handed-over 8.0 km.; Upgrade to class III. Improvement NH47 Thanh Hoa (Thieu Bridge to Xuan Thang). 3 NIP/CP-2 Prior review 5,074,779 5,074,779 6-Jan-06 5-Apr-06 30-Oct-09 25-Mar-10 Handed-over Length: 20.5 km; Upgrade to class III. Improvement NH48-2 Nghe An 4 NIP/CP-3 (km0-km20). Length: 20.0 km. Prior review 4,533,097 4,533,097 6-Jan-06 16-Dec-06 30-Sep-09 25-Mar-10 Handed-over Upgrade to class III. Improvement NH48-3 Nghe An 5 NIP/CP-4 (km38-km64). Length: 25.3 km. Prior review 5,434,317 5,434,317 6-Jan-06 14-Feb-06 30-Nov-09 25-Mar-10 Handed-over Upgrade to class III. Improvement NH37 (Thai Under 6 NIP/CP-5 Nguyen - Bac Giang); Length: Prior review 14,022,407 13,353,813 28-Mar-07 14-Sep-07 30-Apr-10 construction 49.6 km. Upgrade to class IV. Improvement of NH21-2. Lac Under 7 NIP/CP-6 Quan - Thinh Long. Length: Prior review 16,477,266 15,541,125 10-Jul-08 16-Jul-08 31-Aug-10 construction 33.5Km. Upgrade to Class IV Cost Contract Completed Contract Contract Contract Completion No. Package No. Contract name Review method Estimate value value Signed Started (Date) Status (USD equiv)* (USD equiv)* (USD equiv)* (Date) (Date) Proposed Actual Improvement of NH38B, Hai Under 8 NIP/CP-7 Duong - Cau Trang; Length: Prior review 12,482,938 12,024,063 5-Mar-08 24-Mar-08 30-Sep-10 construction 22.9Km. Upgrade to Class III Improvement of NH38B, Cau Under 9 NIP/CP-8 Trang - Hung Yen; Length: Prior review 15,295,625 15,024,625 7-Mar-08 24-Mar-08 30-Sep-10 construction 19.3Km. Upgrade to Class III Improvement of NH18. Cua Under 10 NIP/CP-9 Ong - Mong Duong. Length: Prior review 10,906,479 10,879,500 16-Nov-09 22-Feb-10 30-Nov-11 construction 10Km. Upgrade to Class III Improvement of NH21-1. Nam Under 11 NIP/CP-11 Dinh - Lac Quan. Length: Prior review 18,634,759 18,460,938 3-Nov-08 1-Jan-09 31-Jan-11 construction 21Km. Upgrade to Class III Improvement of NH39-2. Trieu Duong - Diem Dien, 10.5Km Under 12 NIP/CP-14A Prior review 9,708,257 9,392,000 27-Nov-08 2-Jan-09 31-Dec-10 (Km64 - Km74.43). Upgrade to construction Class III Improvement of NH39-2. Trieu Duong - Diem Dien, 10Km Under 13 NIP/CP-14B Prior review 8,269,310 8,969,967 23-Dec-09 25-Feb-10 30-Nov-11 (Km81.6 - Km91). Upgrade to construction Class III Note: * 1USD is equivalent 16,000VND ** Proposed Date Procurement Plan for Works For roads under Initial DCA - Network Preservation Program Road Network Improvement Project; WB/Credit No. 3843 - VN Updated on : 15-Apr-10 Network Preservation Program Cost Contract Completed Contract Contract Contract Completion Completed value No. Package No. Contract name Review method Estimate value value Signed Started (Date) Note (VND) (USD equiv)* (USD equiv)* (USD equiv)* (Date) (Date) Proposed Actual Maintenance NH1 Ninh Binh - 1 NPP/CP-1.1 Prior review 1,582,369 1,422,778 8,183,591,000 511,474 20/Jul/05 11/Nov/05 11/Jul/06 13/Aug/07 Complete Thanh Hoa; Km 269 - Km 286 Maintenance NH1 Ninh Binh - 2 NPP/CP-1.2 Prior review 5,538 5,538 88,613,000 5,538 17/May/07 25/May/07 14/Jun/07 14/Jun/07 Complete Thanh Hoa; Km 269 - Km 286 Maintenance NH1 - Thanh Hoa; 3 NPP/CP-2 Prior review 1,173,508 1,139,805 18,113,841,636 1,132,115 28/Oct/05 11/Nov/05 27/Sep/07 27/Sep/07 Complete Km 286 - Km 295 Maintenance NH1 Nghe An; Km 4 NPP/CP-3 Prior review 2,362,158 1,886,858 29,549,658,182 1,846,854 08/May/06 08/Jun/06 14/Jan/08 21/Dec/07 Complete 383 - Km 405 Maintenance NH1 Nghe An; Km 5 NPP/CP-4 Prior review 2,412,061 2,185,070 33,280,146,364 2,080,009 08/May/06 08/Jun/06 23/Nov/07 10/Oct/07 Complete 405 - Km 428 Maintenance NH1 Nghe An; Km 6 NPP/CP-5 Prior review 2,391,115 1,830,158 27,694,593,955 1,730,912 07/Jun/06 07/Jul/06 07/Jun/08 18/Aug/08 Complete 428 - Km 442 Maintenance NH1 Nghe An; Km 7 NPP/CP-6 Prior review 2,488,422 2,485,221 39,326,053,000 2,457,878 24/Mar/06 28/Mar/06 28/Jan/07 28/Aug/07 Complete 442 - Km 460 Maintenance NH1 Ninh Thuan; 8 NPP/CP-7 Prior review 1,615,557 1,612,965 25,584,060,545 1,599,004 19/Sep/05 29/Nov/05 15/May/07 03/Oct/07 Complete Km 1541 - Km 1525 Maintenance NH1 Dong Nai; Km 9 NPP/CP-8 Prior review 1,196,083 1,149,872 16,725,417,273 1,045,339 17/Oct/05 29/Nov/05 29/Jul/06 03/Oct/07 Complete 1785 - Km 1800 Maintenance NH26 Khanh Hoa; 10 NPP/CP-9 Prior review 1,990,182 1,740,289 26,541,278,743 1,658,830 08/Feb/06 15/Mar/06 02/Mar/07 08/Oct/07 Complete Km 2 - Km 21 Maintenance NH26 Khanh Hoa- 11 NPP/CP-10 Prior review 2,120,439 2,004,269 24,778,314,000 1,548,645 07/Feb/06 15/Mar/06 15/Nov/06 Dak Lak; Km 21 - Km 39 Maintenance NH26 -Dak Lak; 12 NPP/CP-11 Prior review 2,053,609 1,924,605 20,747,870,000 1,296,742 24/Jan/06 10/Mar/06 10/Nov/06 Km 39 - Km 67 Maintenance NH26 -Dak Lak; 13 NPP/CP-12 Prior review 2,322,244 1,858,816 37,004,310,344 2,312,769 22/Dec/06 25/Jan/07 18/Nov/08 28/Feb/09 Complete Km 67 - Km 94 Maintenance NH26 -Dak Lak; 14 NPP/CP-13 Prior review 1,831,285 1,818,750 28,537,624,455 1,783,602 06/Jan/06 13/Jan/06 13/Nov/06 09/Oct/07 Complete Km 94 - Km 122 Maintenance NH15 Hai Duong; 15 NPP/CP-14 Prior review 1,051,104 891,644 13,047,033,182 815,440 13/Sep/05 09/Nov/05 09/Jul/06 05/Sep/06 Complete Km 0 - Km 12 Maintenance NH15 Hai Duong; 16 NPP/CP-15 Prior review 974,492 833,316 12,181,670,000 761,354 13/Sep/05 09/Nov/05 27/Aug/06 27/Aug/06 Complete Km 12 - Km 22 Maintenance NH1 - Thanh Hoa; 17 NPP/CP-1.3 Prior review 2,233,811 2,326,125 37,218,000,000 2,326,125 01/Oct/09 31/Oct/09 28/Jun/10 Km 286 - Km 295 Maintenance NH1 -Quang Ngai; 18 NPP/CP-16 Prior review 1,112,389 943,750 15,100,000,000 943,750 11/Aug/09 09/Sep/09 09/May/10 Km 1027 - Km 1034 Cost Contract Completed Contract Contract Contract Completion Completed value No. Package No. Contract name Review method Estimate value value Signed Started (Date) Note (VND) (USD equiv)* (USD equiv)* (USD equiv)* (Date) (Date) Proposed Actual Maintenance NH1 -Quang Ngai; 19 NPP/CP-17 Prior review 1,192,922 993,750 15,900,000,000 993,750 11/Aug/09 09/Sep/09 09/May/10 Km 1034 - Km 1045 Maintenance NH1 -Dong Nai; 20 NPP/CP-18 Prior review 1,618,758 1,638,688 26,219,000,000 1,638,688 23/Jan/09 22/Feb/09 22/Dec/09 03/Nov/09 Complete Km 1820 - Km 1824 Maintenance NH1 -Dong Nai; 21 NPP/CP-19 Prior review 1,736,742 1,736,438 27,783,000,000 1,736,438 18/Dec/08 17/Jan/09 17/Nov/09 14/Aug/09 Complete Km 1824 - Km 1829 Maintenance NH1 -Dong Nai; 22 NPP/CP-20 Prior review 1,710,323 1,701,803 27,228,842,000 1,701,803 18/Dec/09 17/Jan/09 17/Nov/09 03/Nov/09 Complete Km 1829 - Km 1834 Maintenance NH1 -Quang Nam; 23 NPP/CP-21 Prior review 1,410,032 1,250,994 20,015,900,000 1,250,994 21/Aug/09 21/Sep/09 21/Jun/10 Km 942 - Km 963 Maintenance NH1 -Quang Nam; 24 NPP/CP-22 Prior review 1,657,434 1,478,875 23,662,000,000 1,478,875 21/Aug/09 21/Sep/09 06/Jul/10 Km 963 - Km 971 Maintenance NH1 -Quang Nam; 25 NPP/CP-23 Prior review 1,371,524 1,166,325 18,661,200,000 1,166,325 21/Aug/09 21/Sep/09 06/Jun/10 Km 971 - Km 977 Maintenance NH1 -Quang Nam; 26 NPP/CP-24 Prior review 1,601,658 1,332,438 21,319,000,000 1,332,438 21/Aug/09 21/Sep/09 06/Jul/10 Km 977 - Km 990 Maintenance NH1 -Quang Nam; 27 NPP/CP-25 Prior review 1,551,095 1,547,788 24,764,600,000 1,547,788 22/Jul/09 22/Aug/09 22/May/10 Km 996 - Km 1005 Maintenance NH1 -Quang Nam; 28 NPP/CP-26 Prior review 1,283,927 1,266,750 20,268,000,000 1,266,750 21/Aug/09 14/Sep/09 14/May/10 Km 1005 - Km 1013 Maintenance NH1 -Quang Nam; 29 NPP/CP-27 Prior review 1,473,142 1,223,356 19,573,700,000 1,223,356 21/Aug/09 14/Sep/09 29/May/10 Km 1013 - Km 1020 Maintenance NH1 -Quang Nam; 30 NPP/CP-28 Prior review 1,526,544 1,269,038 20,304,600,000 1,269,038 21/Aug/09 14/Sep/09 29/Apr/10 Km 1020 - Km 1027 Maintenance NH5 -Hai Duong; 31 NPP/CP-29 Prior review 1,705,629 1,703,600 27,257,607,000 1,703,600 08/Oct/08 07/Nov/08 07/Sep/09 06/Sep/09 Complete Km 47 - Km 55 Maintenance NH5 -Hai Duong; 32 NPP/CP-30 Prior review 1,588,970 1,582,704 25,323,271,000 1,582,704 08/Oct/08 07/Nov/08 07/Sep/09 06/Sep/09 Complete Km 55 - Km 63 Maintenance NH5 -Hai Duong; 33 NPP/CP-31 Prior review 1,837,804 1,652,212 26,435,395,000 1,652,212 08/Oct/08 07/Nov/08 25/Aug/09 20/Aug/09 Complete Km 63 - Km 67 Maintenance NH5 -Hai Duong; 34 NPP/CP-32 Prior review 1,594,618 1,395,502 22,328,032,000 1,395,502 08/Oct/08 07/Nov/08 25/Aug/09 20/Aug/09 Complete Km 67 - Km 71 Maintenance NH5 -Hai Duong; 35 NPP/CP-33 Prior review 1,836,657 1,692,473 27,079,573,000 1,692,473 08/Oct/08 07/Nov/08 07/Aug/09 30/Jul/09 Complete Km 71 - Km 76 Maintenance NH1 -Dong Nai; 36 NPP/CP-34 Prior review 2,063,168 1,940,988 31,055,808,000 1,940,988 05/Jan/09 04/Feb/09 04/Dec/09 Km 1850 - Km 1858+500 Maintenance NH1 -Dong Nai; 37 NPP/CP-35 Prior review 1,922,526 1,808,688 28,939,000,000 1,808,688 05/Jan/09 04/Feb/09 04/Dec/09 07/Jan/10 Complete Km 1858+500 - Km 1867 Maintenance NH1 -Dong Nai; 38 NPP/CP-36 Prior review 1,643,373 1,606,586 25,705,373,000 1,606,586 05/Jan/09 04/Feb/09 04/Dec/09 03/Nov/09 Complete Km 1867 - Km 1873+50 Maintenance NH26 Khanh Hoa- 39 NPP/CP-10.2 Prior review 1,622,968 1,622,438 25,959,000,000 1,622,438 28/Apr/09 27/May/09 27/Oct/09 Dak Lak; Km 21 - Km 67 Maintenance NH1 -Binh Thuan; 01/Feb/10 03/Mar/10 40 NPP/CP-37 Prior review 1,481,576 28/Dec/10 Km 1688 - Km 1698 ** ** On bidding process Cost Contract Completed Contract Contract Contract Completion Completed value No. Package No. Contract name Review method Estimate value value Signed Started (Date) Note (VND) (USD equiv)* (USD equiv)* (USD equiv)* (Date) (Date) Proposed Actual On bidding Maintenance NH1 -Binh Thuan; 01/Feb/10 03/Mar/10 process 41 NPP/CP-38 Prior review 1,314,785 28/Dec/10 Km 1698 - Km 1712 ** ** Maintenance NH1 -Binh Thuan; 42 NPP/CP-39 Prior review 1,278,435 1,249,414 19,990,620,000 1,249,414 11/Aug/09 11/Sep/09 11/May/10 Km 1712 - Km 1721 Maintenance NH1 -Binh Thuan; 01/Feb/10 03/Mar/10 On bidding 43 NPP/CP-40 Prior review 1,392,008 28/Dec/10 Km 1721 - Km 1731 ** ** process Maintenance NH1 -Binh Thuan; 44 NPP/CP-41 Prior review 1,394,720 1,229,656 19,674,500,000 1,229,656 11/Aug/09 11/Sep/09 26/Jun/10 Km 1731 - Km 1741 Maintenance NH1 -Binh Thuan; 45 NPP/CP-42 Prior review 1,409,018 1,242,625 19,882,000,000 1,242,625 11/Aug/09 11/Sep/09 26/Jun/10 Km 1741 - Km 1751 Maintenance NH1 -Binh Thuan; 46 NPP/CP-43 Prior review 1,399,971 1,395,938 22,335,000,000 1,395,938 11/Aug/09 01/Sep/09 01/Jul/10 Km 1751 - Km 1761 Maintenance NH1 -Dong Nai; 47 NPP/CP-44 Prior review 1,609,518 1,437,500 23,000,000,000 1,437,500 11/Aug/09 11/Sep/09 11/Jul/10 Km 1800 - Km 1809 Maintenance NH1 -Dong Nai; 48 NPP/CP-45 Prior review 1,586,384 1,415,375 22,646,000,000 1,415,375 11/Aug/09 11/Sep/09 11/Jul/10 Km 1809 - Km 1815 Maintenance NH1 -Dong Nai; 49 NPP/CP-46 Prior review 1,780,753 1,721,344 27,541,500,000 1,721,344 11/Aug/09 11/Sep/09 11/Jul/10 Km 1815 - Km 1820 Maintenance NH5 -Hung Yen; 50 NPP/CP-47 Prior review 1,380,101 1,146,325 18,341,200,000 1,146,325 21/Aug/09 21/Sep/09 06/Jul/10 Km 11+135 - Km 15 Maintenance NH5 -Hung Yen; 51 NPP/CP-48 Prior review 1,266,546 1,153,981 18,463,700,000 1,153,981 21/Aug/09 21/Sep/09 21/Jul/10 Km 15 - Km 19 Maintenance NH5 -Hung Yen; 52 NPP/CP-49 Prior review 1,544,122 1,368,825 21,901,200,000 1,368,825 21/Aug/09 21/Sep/09 06/Jul/10 Km 19 - Km 24 Maintenance NH5 -Hung Yen; 53 NPP/CP-50 Prior review 1,521,123 1,250,375 20,006,000,000 1,250,375 11/Aug/09 11/Sep/09 11/Jul/10 Km 24 - Km 28 Maintenance NH5 -Hung Yen; 54 NPP/CP-51 Prior review 1,536,618 1,356,250 21,700,000,000 1,356,250 16/Jun/09 16/Jul/09 16/May/10 Km 28 - Km 33 Maintenance NH5 -Hung Yen; 55 NPP/CP-52 Prior review 1,288,113 1,050,125 16,802,000,000 1,050,125 22/Jul/09 22/Aug/09 22/Jun/10 14/Apr/10 Complete Km 33 - Km 37 Maintenance NH5 -Hai Duong; 56 NPP/CP-53 Prior review 1,443,503 1,248,113 19,969,800,000 1,248,113 07/Oct/09 06/Nov/09 02/Sep/10 Km 37 - Km 42 Maintenance NH5 -Hai Duong; 57 NPP/CP-54 Prior review 1,484,189 1,193,750 19,100,000,000 1,193,750 16/Jun/09 16/Jul/09 16/May/10 Km 42 - Km 47 Performance Based Contracts Section Km0-Km95, NH1-Lang 12/May/10 11/Jun/10 1 PBC 1 Prior Review 3,673,000 10/Jun/13 Son-Voi (Bac Giang) ** ** Section Km95-Km160,77, NH1- 12/May/10 11/Jun/10 On bidding 2 PBC 2 Prior Review 8,764,000 10/Jun/13 Voi (Bac Giang)-Ha Noi ** ** process Section Km0 -Km141,76, NH10- 12/May/10 11/Jun/10 3 PBC 3 Prior Review 17,596,000 10/Jun/13 Quang Ninh-Ninh Binh. ** ** Note: * 1USD is equivalent 16,000VND Cost Contract Completed Contract Contract Contract Completion Completed value No. Package No. Contract name Review method Estimate value value Signed Started (Date) Note (VND) (USD equiv)* (USD equiv)* (USD equiv)* (Date) (Date) Proposed Actual ** Proposed Date As these contracts have not completed yet the completed value is expected equivalent to the contract value Packages are under bidding process.