PROCUREMENT PLAN Project information: Zambia: Mining and Environment remediation and improvement Project [P154683] Project Implementation agency: Ministry of Mines and Mineral Development Date of the Procurement Plan: February 14, 2017 Period covered by this Procurement Plan: [December 1, 2015- July 30, 2017] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. – Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). For Goods is applicable for those contracts identified in the Procurement Plan tables]; For Works is applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information: Not applicable PROCUREMENT Zambia : Zambia - Mining and Environmental Remediation and Improvement Project PLAN General Information Country: Zambia Bank’s Approval Date of the Original Procurement Plan: 2017-01-04 2019-11-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154683 GPN Date: Project Name: Zambia - Mining and Environmental Remediation and Improvement Project Loan / Credit No: IDA / Q9880, IDA / 59370 Executing Agency(ies): Ministry of Mines, Energy and Water Development WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Enhancing Institutional MMMD/MP/W/02/2018 / capacity to strengthen Request for Single Stage - One IDA / Q9880 Post Limited 27,000.00 44,601.70 Signed 2018-03-10 2018-05-05 2018-11-01 Rehabilitation-Kitwe SubPIU environmental governance Quotations Envelope and compliance Enhancing Institutional MMMD/MP/W/03/2018 / capacity to strengthen Request for Single Stage - One Office Rehabilitation-Mufulira IDA / Q9880 Post Limited 30,000.00 22,860.15 Signed 2018-03-10 2018-05-05 2018-11-01 environmental governance Quotations Envelope SubPIU and compliance Enhancing Institutional MMMD/MP/W/04/2018 / capacity to strengthen Request for Single Stage - One Office Rehabilitation-Chingola IDA / Q9880 Post Limited 16,000.00 13,901.69 Signed 2018-03-10 2018-05-05 2018-11-01 environmental governance Quotations Envelope SubPIU and compliance ZM-MMEWD-88199-CW-RFQ Project Management, Request for Single Stage - One / Net Work Installation at IDA / Q9880 Post Limited 20,000.00 0.00 Canceled 2019-07-05 2019-08-30 2020-02-26 Monitoring and Evaluation Quotations Envelope Mine Safety Department Enhancing Institutional MMMD/MP/W/01/2018 / capacity to strengthen Request for Single Stage - One Office Rehabilitation for IDA / Q9880 Post Limited 30,000.00 14,416.01 Signed 2019-06-05 2019-07-31 2020-01-27 environmental governance Quotations Envelope Mines Safety Department and compliance ZM-MMEWD-141605-CW- RFB / Procurement for Civil Reducing environmental Pending Single Stage - One and Engineering Works for IDA / Q9880 health risks through Post Request for Bids Open - National 1,300,000.00 0.00 Implementati 2020-05-20 2020-05-25 2020-07-06 2020-08-05 2020-09-09 2021-03-08 Envelope Rehabilitation and Closure localized interventions on of of OB 54 ZM-MMEWD-141790-CW- RFQ / Rehabilitation and Reducing environmental Pending Request for Single Stage - One disposal of expired IDA / Q9880 health risks through Post Limited 300,000.00 0.00 Implementati 2020-01-05 2020-03-01 2020-08-28 Quotations Envelope Chemicals for MSD localized interventions on laboratory in Kitwe ZM-MMEWD-141608-CW- RFB / Procurement of Civil Reducing environmental Pending Open - Single Stage - One and Engineering Works for IDA / Q9880 health risks through Post Request for Bids 6,000,000.00 0.00 Implementati 2020-05-20 2020-05-25 2020-07-06 2020-08-05 2020-09-09 2021-03-08 International Envelope Closure of Additional TD localized interventions on and OBs ZM-MMEWD-141596-CW- Reducing environmental Pending RFB / Procurement of Civil Open - Single Stage - One IDA / Q9880 health risks through Post Request for Bids 6,000,000.00 0.00 Implementati 2020-05-20 2020-05-25 2020-07-06 2020-08-05 2020-09-09 2021-03-08 and Engineering works for International Envelope localized interventions on Closure of TD 10 ZM-MMEWD-144997-CW- Reducing environmental Pending DIR / Emergency Works for IDA / Q9880 health risks through Prior Direct Selection Direct 15,000.00 0.00 Implementati 2019-11-19 2019-11-24 2019-12-29 2020-06-26 the Maintenance of Tailing localized interventions on Dam No. 10 in Mufulira Page 1 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Enhancing Institutional ZM-MMEWD-10605-GO-RFQ capacity to strengthen Request for Single Stage - One IDA / Q9880 Prior Open - National 40,000.00 0.00 Canceled 2017-03-26 2017-05-21 2017-11-17 / Purchase of motor vehicle environmental governance Quotations Envelope and compliance MMMD/MP/G/02/2018 / Enhancing Institutional Procurement of office capacity to strengthen Single Stage - One IDA / Q9880 Post Request for Bids Open - National 150,000.00 0.00 Canceled 2018-01-30 2018-02-04 2018-03-18 2018-04-17 2018-05-22 2018-11-18 equipment, internet server environmental governance Envelope and website services and compliance MMMD/MP/G/04/2018 / Procurement of remote Enhancing Institutional sensing and field equipment capacity to strengthen Single Stage - One for RPA,MSD,KCC.MMC and IDA / Q9880 Prior Request for Bids Open - National 400,000.00 0.00 Canceled 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2019-01-05 environmental governance Envelope CMC( hand held GPS,GIS and compliance and remote sensing equipment) MMMD/MP/G/03/2018 / Enhancing Institutional Procurement of office Under capacity to strengthen Single Stage - One equipment and furniture for IDA / Q9880 Post Request for Bids Open - National 220,000.00 0.00 Implementati 2018-03-12 2018-03-17 2018-04-28 2018-05-28 2018-07-02 2018-12-29 environmental governance Envelope MSD,KCC,MMC,CMC and on and compliance RPA(MSD furniture only) Enhancing Institutional MMMD/MP/G/05/2018 / capacity to strengthen Request for Single Stage - One Procurement of No.2 Project IDA / Q9880 Post Limited 120,000.00 80,941.25 Signed 2018-03-10 2018-05-05 2018-11-01 environmental governance Quotations Envelope Vehicles and compliance MMMD/MP/G/01/2018 / Enhancing Institutional Procurement of Laboratory capacity to strengthen UN Agencies IDA / Q9880 Prior Direct 450,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-05-26 2018-11-22 Equipment( Gas samplers, environmental governance (Direct) AAS and XRFs and compliance ZM-MMEWD-92351-GO-RFB Reducing environmental / procurement of Laboratory Single Stage - One IDA / Q9880 health risks through Post Request for Bids Open - National 450,000.00 227,883.00 Signed 2018-12-26 2018-12-31 2019-02-11 2019-03-13 2019-04-17 2019-10-14 Equipment (Gas sampler, Envelope localized interventions AAS and XRF's) ZM-MMEWD-94580-GO-RFB / procurement of remote sensing and field equipment Project Management, Single Stage - One for RPA, MSD,KCC,MMC, IDA / Q9880 Post Request for Bids Open - National 400,000.00 438,159.50 Signed 2019-01-18 2019-01-23 2019-03-06 2019-04-05 2019-05-10 2019-11-06 Monitoring and Evaluation Envelope and CMC (hand held GPS,GIS AND remote sensing equipment) ZM-MMEWD-104751-GO- Project Management, Request for Single Stage - One RFQ / Financial IDA / Q9880 Post Limited 40,000.00 0.00 Canceled 2019-04-10 2019-06-05 2019-12-02 Monitoring and Evaluation Quotations Envelope Management Software ZM - MMEWD - 104646 - Pending Project Management, UN Agencies GO - RFQ / Procurement of IDA / Q9880 Post Direct 280,000.00 0.00 Implementati 2019-04-30 2019-05-05 2019-06-09 2019-12-06 Monitoring and Evaluation (Direct) Project Vehicles on ZM-MMEWD-88190-GO-RFQ / procurement of IT Project Management, Request for Single Stage - One IDA / Q9880 Post Limited 28,484.55 49,222.90 Signed 2018-12-08 2019-02-02 2019-08-01 equipment for Mine Safety Monitoring and Evaluation Quotations Envelope Department Page 2 ZM-MMEWD-135597-GO- Pending RFQ / procurement of office Project Management, Request for Single Stage - One IDA / 59370 Post Limited 35,000.00 0.00 Implementati 2019-11-05 2019-12-31 2020-06-28 equipment for sub PIUs and Monitoring and Evaluation Quotations Envelope on MSD ZM-MMEWD-141796-GO- Enhancing Institutional Pending RFB / procurement of capacity to strengthen Single Stage - One IDA / Q9880 Post Request for Bids Open - National 1,000,000.00 0.00 Implementati 2019-11-29 2019-12-04 2020-01-15 2020-02-14 2020-03-20 2020-09-16 laboratory equipment for environmental governance Envelope on Kabwe, RPA and MSD and compliance ZM-MMEWD-141803-GO- Enhancing Institutional RFB / Procurement of Pending capacity to strengthen Single Stage - One Network Infrastructure and IDA / Q9880 Post Request for Bids Open - National 125,000.00 0.00 Implementati 2019-11-29 2019-12-04 2020-01-15 2020-02-14 2020-03-20 2020-09-16 environmental governance Envelope Installation of Data on and compliance Management ZM-MMEWD-141815-GO- Pending RFB / Procurement of Media Project Management, Single Stage - One IDA / Q9880 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2019-11-28 2019-12-03 2020-01-14 2020-02-13 2020-03-19 2020-09-15 Service and Production of Monitoring and Evaluation Envelope on Communications Metrials ZM-MMEWD-141810-GO- Enhancing Institutional Pending RFB / Procurement of capacity to strengthen Request for Single Stage - One IDA / Q9880 Post Limited 50,000.00 0.00 Implementati 2020-04-05 2020-05-31 2020-11-27 Laboratory Materials ( environmental governance Quotations Envelope on Consumables) and compliance NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MMMD/MP/S/01/2018 / Soil Remediation of Fertility and Agriculture Contaminated Hotspots and Request for Single Stage - One IDA / Q9880 Post Limited 50,000.00 15,544.97 Signed 2018-08-19 2018-10-14 2019-04-12 Extension Programmein Improvement of Quotations Envelope Kankoyo,Mufulira Environmental Infrastructure ZM-MMEWD-88217-NC-RFQ Project Management, Request for Single Stage - One IDA / Q9880 Post Limited 10,000.00 0.00 Canceled 2019-03-05 2019-04-30 2019-10-27 / Website Services Monitoring and Evaluation Quotations Envelope ZM-MMEWD-109462-NC- Project Management, Request for Single Stage - One RFQ / Website Design for IDA / Q9880 Post Limited 12,000.00 0.00 Canceled 2019-05-20 2019-07-15 2020-01-11 Monitoring and Evaluation Quotations Envelope the Project ZM-MMEWD-111316-NC- Enhancing Institutional RFB / Communication and capacity to strengthen Single Stage - One IDA / Q9880 Post Request for Bids Open - National 750,000.00 0.00 Canceled 2019-05-31 2019-06-05 2019-07-17 2019-08-16 2019-09-20 2020-03-18 Citizen Engagement Service environmental governance Envelope Provider and compliance Pending ZM-MMEWD-141820-NC- Project Management, Request for Single Stage - One IDA / Q9880 Post Limited 20,000.00 0.00 Implementati 2019-12-04 2020-01-29 2020-07-27 RFQ / Web site Hosting fees Monitoring and Evaluation Quotations Envelope on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual P154683/2/2016 / Enhancing Institutional Procurement of Consultancy capacity to strengthen Quality And Cost- Open - Under Services for Envirnomental IDA / Q9880 Prior 290,000.00 410,882.60 2015-12-05 2015-12-26 2016-02-08 2016-03-07 2016-04-06 2016-05-11 2016-08-01 2017-08-01 environmental governance Based Selection International Implementation and Social Management and compliance Framework Page 3 MMMD/MP/CS/06/2018 / Enhancing Institutional Development of procedures Consultant capacity to strengthen and Training for Honorary IDA / Q9880 Post Qualification Open - National 150,000.00 201,733.17 Signed 2018-01-30 2018-02-20 2018-04-05 2018-05-05 2018-06-09 2018-12-06 environmental governance Inspectors of Mines Safety Selection and compliance Department MMMD/MP/CS/07/2018 / Remediation of Identification of highly Contaminated Hotspots and Quality And Cost- Open - Under radioactively contaminated IDA / Q9880 Prior 250,000.00 0.00 2018-01-15 2018-02-05 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 Improvement of Based Selection International Implementation sites (Radiation Hotpots) in Environmental Infrastructure the Copperbelt Province MMMD/MP/CS/10/2018 / Conducting a feasibility Reducing environmental Consultant study for integrated solid IDA / Q9880 health risks through Post Qualification Open - National 50,000.00 0.00 Canceled 2018-01-30 2018-02-20 2018-04-05 2018-05-05 2018-06-09 2018-12-06 waste management in the localized interventions Selection city of Kitwe MMMD/MP/CS/08/2018 / Remediation of Consultant Bamboo feasibility and value Contaminated Hotspots and IDA / Q9880 Post Qualification Open - National 150,000.00 195,079.16 Signed 2018-03-12 2018-04-02 2018-05-16 2018-06-15 2018-07-20 2019-01-16 chain study for specific Improvement of Selection areas in Chingol a Environmental Infrastructure MMMD/MP/CS/09/2018 / Remediation of Consultant Soil fertility and agriculture Contaminated Hotspots and IDA / Q9880 Post Qualification Open - National 50,000.00 0.00 Canceled 2018-03-12 2018-04-02 2018-05-12 2018-06-11 2018-07-16 2019-01-12 extension program in Improvement of Selection Kankoyo,Mufulira Environmental Infrastructure MMMD/MP/CS/14/2018 / Enhancing Institutional Review of mining liabilities capacity to strengthen Quality And Cost- Open - IDA / Q9880 Prior 1,000,000.00 0.00 Canceled 2018-07-16 2018-08-06 2018-09-19 2018-10-17 2018-11-16 2018-12-21 2019-01-25 2019-07-05 and Environmental environmental governance Based Selection International Protection Fund(EPF) and compliance MMMD/MP/CS/12/2018 / Engineering Design, Preparation of Bidding Remediation of Documents and Contaminated Hotspots and Quality And Cost- Open - IDA / Q9880 Prior 350,000.00 0.00 Canceled 2018-06-06 2018-06-27 2018-08-10 2018-09-07 2018-10-07 2018-11-11 2018-12-16 2019-12-16 Supervision,BOQ and cost Improvement of Based Selection International estimates for TD10 in Environmental Infrastructure Mufulira and OB54 in Kitwe MMMD/MP/CS/13/2018 / Remediation of National Plan for Contaminated Hotspots and Quality And Cost- Open - IDA / Q9880 Prior 400,000.00 0.00 Canceled 2018-05-22 2018-06-12 2018-07-26 2018-08-23 2018-09-22 2018-10-27 2018-12-01 2019-06-01 Prioritisation and Improvement of Based Selection International Rehabilitation of TDs Environmental Infrastructure ZM-MMEWD-103033-CS- QCBS / Engineering Design, Preparation of BOQ, Reducing environmental Contract Management and Quality And Cost- Open - IDA / 59370 health risks through Post 350,000.00 0.00 Canceled 2019-03-28 2019-04-18 2019-06-01 2019-06-29 2019-07-29 2019-09-02 2019-10-07 2020-10-06 Supervision of works of the Based Selection International localized interventions Rehabilitation of OB 54, TD 10 and additional Tailing Dam (TD0 ZM-MMEWD-103043-CS- Remediation of QCBS / National Plan for Contaminated Hotspots and Quality And Cost- Open - Prioritization and IDA / 59370 Post 400,000.00 0.00 Canceled 2019-03-28 2019-04-18 2019-06-01 2019-06-29 2019-07-29 2019-09-02 2019-10-07 2020-10-06 Improvement of Based Selection International Rehabilitation of Mines Environmental Infrastructure Waste Facilities Remediation of MMMD/MP/CS/11/2018 / Consultant Contaminated Hotspots and Under EIA for closure of TD8,TD10 IDA / Q9880 Post Qualification Open - National 200,000.00 0.00 2019-09-27 2019-10-18 2019-12-01 2019-12-31 2020-02-04 2020-08-02 Improvement of Implementation and OB53 and OB54 Selection Environmental Infrastructure Page 4 ZM-MMEWD-106563-CS- QCBS / National Plan for Reducing environmental Quality And Cost- Open - Under Prioritization and IDA / Q9880 health risks through Post 600,000.00 0.00 2019-04-05 2019-04-26 2019-06-09 2019-07-07 2019-08-06 2019-09-10 2019-10-15 2020-10-14 Based Selection International Implementation Rehabilitation of Mines localized interventions Waste Facilities ZM-MMEWD-107854-CS- QCBS / Review and Development of Technical Remediation of and Financial Instruments Contaminated Hotspots and Quality And Cost- Open - Under IDA / Q9880 Post 850,000.00 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 for Environmental and Social Improvement of Based Selection International Implementation sustainability of Mine Sites Environmental Infrastructure and Mine Closure Guidelines for Zambia ZM-MMEWD-107856-CS- QCBS / Engineering Design, Preparation of BOQ, Contract Management and Project Management, Quality And Cost- Open - Under IDA / Q9880 Post 800,000.00 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 Supervision of Works of the Monitoring and Evaluation Based Selection International Implementation Rehabilitation of OB 54, TD 10, and Additional Tailing Dam (TD) ZM-MMEWD-108508-CS- Enhancing Institutional QCBS / Communication and capacity to strengthen Quality And Cost- Open - IDA / Q9880 Prior 1,500,000.00 0.00 Canceled 2019-05-31 2019-06-21 2019-08-04 2019-09-01 2019-10-01 2019-11-05 2019-12-10 2020-12-09 Citizen Engagement environmental governance Based Selection International Consultancy and compliance ZM-MMEWD-122362-CS- Consultant Project Management, Under CQS / Data Management IDA / 59370 Post Qualification Open - National 65,000.00 0.00 2019-07-26 2019-08-16 2019-09-29 2019-10-29 2019-12-03 2020-05-31 Monitoring and Evaluation Implementation Strategy Selection ZM-MMEWD-134924-CS- Enhancing Institutional Consultant CQS / Consultancy for capacity to strengthen Under IDA / Q9880 Post Qualification Open - National 65,000.00 0.00 2019-10-31 2019-11-21 2020-01-04 2020-02-03 2020-03-09 2020-09-05 Training of Honorary environmental governance Implementation Selection Inspectors and compliance ZM-MMEWD-141822-CS- Reducing environmental QCBS / Consultancy for Quality And Cost- Pending IDA / Q9880 health risks through Post Open - National 400,000.00 0.00 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2021-06-09 Developing Occupation Based Selection Implementation localized interventions Health Safety (OHS) ZM-MMEWD-142214-CS- Consultant Project Management, Pending CQS / Communication IDA / Q9880 Post Qualification Open - National 50,000.00 0.00 2019-12-31 2020-01-21 2020-03-05 2020-04-04 2020-05-09 2020-11-05 Monitoring and Evaluation Implementation Consultant for Citizen Selection Engagement Remediation of ZM-MMEWD-142216-CS- Consultant Contaminated Hotspots and Pending CQS / Operations Support IDA / Q9880 Post Qualification Open - National 60,000.00 0.00 2019-12-31 2020-01-21 2020-03-05 2020-04-04 2020-05-09 2020-11-05 Improvement of Implementation Consultant Selection Environmental Infrastructure ZM-MMEWD-142218-CS- Reducing environmental Consultant CQS / Engineering Design Open - Pending IDA / Q9880 health risks through Post Qualification 200,000.00 0.00 2020-01-15 2020-02-05 2020-03-20 2020-04-19 2020-05-24 2020-11-20 and Environmental Impact International Implementation localized interventions Selection Mining Legacy Site INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MMMD/MP/CS/01/2018 / Project Management, Under Engagement of Project IDA / Q9880 Prior Direct Selection Direct 300,000.00 0.00 2018-05-30 2018-06-09 2018-08-13 2019-08-13 Monitoring and Evaluation Implementation Management Consultant Page 5 ZM-MMEWD-108506-CS- Individual Project Management, INDV / Short term media IDA / Q9880 Post Consultant Limited 15,000.00 14,500.00 Signed 2019-05-31 2019-06-05 2019-06-26 2019-07-31 2020-01-27 Monitoring and Evaluation consultancy Selection Page 6