PROCUREMENT PLAN (Textual Part) Project information: [Afghanistan] [WEE-RDP] [P-164443] Project Implementation agency: [Ministry of Rural Rehabilitation and Development/ WEE- RDP] Date of the Procurement Plan: [31 August, 2018] Period covered by this Procurement Plan: [01 July, 2018 - 31 December, 2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in “Not Applicable”, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Not Applicable for WEE-RDP Goods Packages. Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] “Not Applicable” Other Relevant Procurement Information. The project will have main procurement as the facilitating partner to for the CDD. All those packages will be added to the STEP. The project will be having community procurement the manual for the community procurement is under revision once it is finalized it will be followed for all the community procurement. PROCUREMENT Afghanistan : Women's Economic Empowerment Rural Development Project PLAN General Information Country: Afghanistan Bank’s Approval Date of the Original Procurement Plan: 2018-09-09 2019-08-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164443 GPN Date: Project Name: Women's Economic Empowerment Rural Development Project Loan / Credit No: / , IDA / D3840, TF / A8443 Executing Agency(ies): MRRD_Women's Empowerment Rural Development Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-MRRD/WEE-RDP-82435- Pending CW-RFB / Extension of Single Stage - One TF / A8443 Project Management Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-02-01 2019-02-06 2020-04-16 2020-05-16 2020-06-20 2020-12-17 Building in Kabul Regional Envelope on Office AF-MRRD/WEE-RDP-93270- Pending CW-RFQ / Extension of Request for Single Stage - One TF / A8443 Project Management Post Open - National 50,000.00 0.00 Implementati 2019-02-20 2019-04-17 2019-10-14 Building in Kandahar Quotations Envelope on Regional Office AF-MRRD/WEE-RDP-93269- Pending CW-RFQ / Extension of Request for Single Stage - One TF / A8443 Project Management Post Open - National 50,000.00 0.00 Implementati 2019-02-20 2019-04-17 2019-10-14 Building in Khost Provincial Quotations Envelope on Office AF-MRRD/WEE-RDP-93271- Pending CW-RFQ / Extension of Request for Single Stage - One TF / A8443 Project Management Post Open - National 50,000.00 0.00 Implementati 2019-02-20 2019-04-17 2019-10-14 Building for Herat Regional Quotations Envelope on Office GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-MRRD/WEE-RDP-76549- Pending Community Mobilization and Request for Single Stage - One GO-RFQ / stationery for / Post Open - National 19,400.00 0.00 Implementati 2019-09-19 2019-11-14 2020-05-12 Institution Development Quotations Envelope VSLAs on AF-MRRD/WEE-RDP-76559- Pending Request for Single Stage - One GO-RFQ / procurement of / Project Management Post Open - National 20,000.00 0.00 Implementati 2019-04-08 2019-06-03 2019-11-30 Quotations Envelope furniture for WEERDP on AF-MRRD/WEE-RDP-76558- Request for Single Stage - One GO-RFQ / Purchasing of E- / Project Management Post Open - National 4,450.00 0.00 Canceled 2019-01-24 2019-03-21 2019-09-17 Quotations Envelope attendance AF-MRRD/WEE-RDP-76543- Pending GO-RFB / procurement of Community Mobilization and Single Stage - One TF / A8443 Post Request for Bids Open - National 110,000.00 0.00 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2019-10-08 stationery for SHGs for Institution Development Envelope on CMID unit AF-MRRD/WEE-RDP-89363- Pending GO-RFB / Procurement of Community Mobilization and Single Stage - One TF / A8443 Post Request for Bids Open - National 55,000.00 0.00 Implementati 2019-01-01 2019-01-06 2019-02-17 2019-03-19 2019-04-23 2019-10-20 Book of records for SHGs Institution Development Envelope on for CMID unit Page 1 AF-MRRD/WEE-RDP-76466- GO-RFQ / Product Enterprise Development and Request for Single Stage - One / Post Open - National 49,000.00 0.00 Canceled 2019-02-01 2019-03-29 2019-09-25 promotion, labeling and Market Linkages Quotations Envelope printing for EGs AF-MRRD/WEE-RDP-86497- GO-RFQ / Procurement of printing materials for Request for Single Stage - One IDA / D3840 Project Management Post Open - National 20,000.00 0.00 Canceled 2019-01-12 2019-03-09 2019-09-05 training unit (Brouchures, Quotations Envelope IMF Booklet, Posters and Manuals). AF-MRRD/WEE-RDP-77349- Request for Single Stage - One GO-RFQ / Printing and / Project Management Post Open - National 10,000.00 0.00 Canceled 2019-01-10 2019-03-07 2019-09-03 Quotations Envelope designing of posters for ESS AF-MRRD/WEE-RDP-76472- Enterprise Development and Request for Single Stage - One / Post Open - National 49,000.00 0.00 Canceled 2019-02-07 2019-04-04 2019-10-01 GO-RFQ / Product Packaging Market Linkages Quotations Envelope AF-MRRD/WEE-RDP-76554- Community Mobilization and Single Stage - One GO-RFB / Signs boards for / Post Request for Bids Open - National 77,600.00 0.00 Canceled 2019-01-25 2019-01-30 2019-03-13 2019-04-12 2019-05-17 2019-11-13 Institution Development Envelope VSLAs AF-MRRD/WEE-RDP-76546- Pending GO-RFB / Provision of Community Mobilization and Single Stage - One TF / A8443 Post Request for Bids Open - National 80,000.00 0.00 Implementati 2018-12-08 2018-12-13 2019-01-24 2019-02-23 2019-03-30 2019-09-26 saving boxes for SGs CMID Institution Development Envelope on unit AF-MRRD/WEE-RDP-76555- GO-RFB / Providing digital Community Mobilization and Single Stage - One / Post Request for Bids Open - National 135,000.00 0.00 Canceled 2019-01-31 2019-02-05 2019-03-19 2019-04-18 2019-05-23 2019-11-19 technology/smart phones for Institution Development Envelope and tablets for VSLAs AF-MRRD/WEE-RDP-76548- Pending Community Mobilization and Single Stage - One GO-RFB / Provision of safe TF / A8443 Post Request for Bids Open - National 50,000.00 0.00 Implementati 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 2020-04-04 Institution Development Envelope for VSLAs CMID unit on AF-MRRD/WEE-RDP-105234- Pending GO-RFB / Procurement of Single Stage - One IDA / D3840 Project Management Post Request for Bids Open - National 170,000.00 0.00 Implementati 2019-03-25 2019-03-30 2019-05-11 2019-06-10 2019-07-15 2019-09-15 Laptops, Desktop, Printer, Envelope on Scanner and HDD AF-MRRD/WEE-RDP-125679- Pending GO-RFB / Procurement of Community Mobilization and Single Stage - One TF / A8443 Post Request for Bids Open - National 110,000.00 0.00 Implementati 2019-07-31 2019-08-05 2019-09-16 2019-10-16 2019-11-20 2020-05-18 saving boxes for VSLAs Institution Development Envelope on CMID Unit AF-MRRD/WEE-RDP-126123- Pending GO-RFB / Procurement of Community Mobilization and Single Stage - One IDA / D3840 Post Request for Bids Open - National 65,000.00 0.00 Implementati 2019-08-03 2019-08-08 2019-09-19 2019-10-19 2019-11-23 2020-05-21 Book of Records for SHGs Institution Development Envelope on (2nd package) AF-MRRD/WEE-RDP-76547- Pending Community Mobilization and Request for Single Stage - One GO-RFQ / Provision of TF / A8443 Post Open - National 145,000.00 0.00 Implementati 2019-02-11 2019-04-08 2019-10-05 Institution Development Quotations Envelope stationary for SHGs on AF-MRRD/WEE-RDP-128601- Pending Request for Single Stage - One GO-RFQ / Procurement of TF / A8443 Project Management Post Open - National 600.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope Chairs for Balkh PO on AF-MRRD/WEE-RDP-128603- Pending Request for Single Stage - One GO-RFQ / Procurement of TF / A8443 Project Management Post Open - National 2,600.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope Furniture for Khost RO on Page 2 AF-MRRD/WEE-RDP-128604- Pending GO-RFQ / Procurement of Request for Single Stage - One TF / A8443 Project Management Post Open - National 2,750.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Furniture for Kanadahar Quotations Envelope on RO AF-MRRD/WEE-RDP-128606- Pending Request for Single Stage - One GO-RFQ / Furniture for TF / A8443 Project Management Post Open - National 6,700.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope Balk on AF-MRRD/WEE-RDP-128608- Pending Request for Single Stage - One GO-RFQ / Furniture for TF / A8443 Project Management Post Open - National 3,300.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope Kunduz RFQ on AF-MRRD/WEE-RDP-128610- Pending Request for Single Stage - One GO-RFQ / Furniture for TF / A8443 Project Management Post Open - National 3,400.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope central zone on AF-MRRD/WEE-RDP-128611- Pending Request for Single Stage - One GO-RFQ / Furniture for TF / A8443 Project Management Post Open - National 3,480.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope Balkh RO on AF-MRRD/WEE-RDP-128612- Pending Request for Single Stage - One GO-RFQ / Furniture for TF / A8443 Project Management Post Open - National 1,830.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope PMO on AF-MRRD/WEE-RDP-128616- Pending GO-RFQ / Procurement of Request for Single Stage - One TF / A8443 Project Management Post Open - National 3,250.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Power inverter for PMO IT Quotations Envelope on Unit AF-MRRD/WEE-RDP-128618- Pending Request for Single Stage - One GO-RFQ / Power Inventor TF / A8443 Project Management Post Open - National 4,650.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope for MIS Dept on AF-MRRD/WEE-RDP-128619- Pending Request for Single Stage - One GO-RFQ / Desktop Computer TF / A8443 Project Management Post Open - National 6,400.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope for central zone on AF-MRRD/WEE-RDP-128620- Pending Request for Single Stage - One GO-RFQ / Procurement of TF / A8443 Project Management Post Open - National 3,900.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope Laptop ,Scanner and copier on AF-MRRD/WEE-RDP-128622- Pending GO-RFQ / Desktop Request for Single Stage - One TF / A8443 Project Management Post Open - National 6,430.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 computers and printers for Quotations Envelope on Kandahar RO AF-MRRD/WEE-RDP-128623- Pending GO-RFQ / Desktop Request for Single Stage - One TF / A8443 Project Management Post Open - National 6,670.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 computers and printers for Quotations Envelope on Herat RO Pending AF-MRRD/WEE-RDP-128625- Request for Single Stage - One TF / A8443 Project Management Post Open - National 5,500.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 GO-RFQ / IT Equipment Quotations Envelope on AF-MRRD/WEE-RDP-128626- Pending Request for Single Stage - One GO-RFQ / Procurement of TF / A8443 Project Management Post Open - National 2,000.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope Container for HERAT PO on AF-MRRD/WEE-RDP-128628- Pending GO-RFQ / Procurement of Request for Single Stage - One TF / A8443 Project Management Post Open - National 4,850.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Conex for Bagrami District Quotations Envelope on office Page 3 AF-MRRD/WEE-RDP-128631- Pending Request for Single Stage - One GO-RFQ / Container for HR TF / A8443 Project Management Post Open - National 2,350.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Quotations Envelope dept on AF-MRRD/WEE-RDP-128659- Pending GO-RFQ / Procurement of Request for Single Stage - One TF / A8443 Project Management Post Open - National 1,040.00 0.00 Implementati 2019-08-27 2019-10-22 2020-04-19 Couch Chairs and Office Quotations Envelope on desk for central zone/PMO NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-MRRD/WEE-RDP-82439- NC-RFQ / Purchasing of Quick Book Software for Finance and Budget Unit Under Request for Single Stage - One staff, 13 users (5 PMO IDA / D3840 Project Management Post Open - National 6,500.00 0.00 Implementati 2018-10-28 2018-12-23 2019-02-15 Quotations Envelope and 8 for Regional staff), it on included relevant training as well based on the listed requirements. AF-MRRD/WEE-RDP-76435- NC-RFB / Facilitation Partner for South East Community Mobilization and Open - Single Stage - One / Post Request for Bids 682,500.00 0.00 Canceled 2018-09-15 2018-09-20 2018-11-01 2018-12-01 2019-01-05 2019-07-04 Region- Ghazni (Ghazni Institution Development International Envelope Town) - Paktika (Sharana) 195 CDCs AF-MRRD/WEE-RDP-76440- NC-RFB / Facilitation Partner for North West Region- Faryab (Bilcheragh Community Mobilization and Open - Single Stage - One & Maimana) -Sar-e-Pul (Sar- / Prior Request for Bids 2,005,500.00 0.00 Canceled 2018-09-17 2018-09-22 2018-11-03 2018-12-03 2019-01-07 2019-07-06 Institution Development International Envelope e-Pul & Gosfandi) - Jawzjan (Faryab & Shibirghan)- Samangan (Hazrat-e-Sultan & Aybak) 573 CDCs AF-MRRD/WEE-RDP-76433- NC-RFB / Facilitation Partner for Central Region- Community Mobilization and Open - Single Stage - One Wardak (Maydan Shar) - / Post Request for Bids 1,249,500.00 0.00 Canceled 2018-09-15 2018-09-20 2018-11-01 2018-12-01 2019-01-05 2019-07-04 Institution Development International Envelope Logar (khoshi and Pule Alam) and Daikundi (Kiti and Nilli) 357 CDCs AF-MRRD/WEE-RDP-76437- NC-RFB / Facilitation Partner for West Region - Community Mobilization and Open - Single Stage - One Badghis (Qala-e-Naw & / Prior Request for Bids 1,725,500.00 0.00 Canceled 2018-09-15 2018-09-20 2018-11-01 2018-12-01 2019-01-05 2019-07-04 Institution Development International Envelope Jawand) - Farah (Farah) - Ghoor (Chakhcharan) 493 CDCs AF-MRRD/WEE-RDP-76443- NC-RFB / Facilitation Partner for East Region - Laghman (Mihtarlam & Community Mobilization and Open - Single Stage - One / Post Request for Bids 1,477,000.00 0.00 Canceled 2018-09-15 2018-09-20 2018-11-01 2018-12-01 2019-01-05 2019-07-04 Qarghaee) - Kunar (Asad Institution Development International Envelope Abad & Narang wa badil) - Nuristan (Patun & Wama) 422 CDCs Page 4 AF-MRRD/WEE-RDP-76439- NC-RFB / Facilitation Partner for North East Region- Badakhshan (Faiz Abad & Daraim) - Takhar Community Mobilization and Open - Single Stage - One IDA / D3840 Prior Request for Bids 3,332,000.00 0.00 Canceled 2018-09-22 2018-09-27 2018-11-08 2018-12-08 2019-01-12 2019-07-11 (Baharak & Taloqan)- Institution Development International Envelope Kunduz (Kundoz and Ali Abad)- Baghlan (Pule Khumri and Baghlan Jadid) 952 CDCs AF-MRRD/WEE-RDP-76436- NC-RFB / Facilitation Partner for South West Region- Helmand (Nawae Community Mobilization and Open - Single Stage - One Barekzai and Lashkargah), / Prior Request for Bids 2,481,500.00 0.00 Canceled 2018-09-24 2018-09-29 2018-11-10 2018-12-10 2019-01-14 2019-07-13 Institution Development International Envelope Nimroz (Zaranj and Charburjak), Zabul (Qalat) and Urozgan (Trin Kot) 709 CDCs AF-MRRD/WEE-RDP-86496- NC-RFQ / Procurement of Request for Single Stage - One IMF (Islamic Micro Finance) IDA / D3840 Project Management Post Open - National 1,300.00 0.00 Canceled 2018-11-17 2019-01-12 2019-07-11 Quotations Envelope indroid application for training unit. AF-MRRD/WEE-RDP-86499- NC-RFQ / Procurement for Request for Single Stage - One translation of training IDA / D3840 Project Management Post Open - National 2,000.00 0.00 Canceled 2019-01-12 2019-03-09 2019-09-05 Quotations Envelope manual from Dari to English and Pashto for training unit. AF-MRRD/WEE-RDP-76474- NC-RFQ / Symposium for Enterprise Development and Request for Single Stage - One / Post Open - National 25,000.00 0.00 Canceled 2019-02-21 2019-04-18 2019-10-15 women economic Market Linkages Quotations Envelope empowerment AF-MRRD/WEE-RDP-93339- Pending Request for Single Stage - One NC-RFQ / Hiring of Support IDA / D3840 Project Management Post Open - National 50,000.00 0.00 Implementati 2019-08-20 2019-10-15 2020-10-15 Quotations Envelope Staff for 7 regions on AF-MRRD/WEE-RDP-125841- NC-RFB / Provision of Pending Community Mobilization and Single Stage - One Training Facilities (lunch, IDA / D3840 Post Request for Bids Open - National 197,500.00 0.00 Implementati 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2021-06-10 Institution Development Envelope Refreshment and Stationary) on for Herat Region AF-MRRD/WEE-RDP-125843- NC-RFB / Provision of Pending Community Mobilization and Single Stage - One Training Facilities (Lunch, IDA / D3840 Post Request for Bids Open - National 130,000.00 0.00 Implementati 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2021-06-10 Institution Development Envelope Refreshment and Stationary) on for Nangarhar Region AF-MRRD/WEE-RDP-125847- NC-RFB / Provision of Pending Community Mobilization and Single Stage - One Facilities for Training IDA / D3840 Post Request for Bids Open - National 260,000.00 0.00 Implementati 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2021-06-10 Institution Development Envelope (Lunch, Refreshment and on Stationary) Kabul Region AF-MRRD/WEE-RDP-125849- NC-RFB / Provision of Pending Facilities for Training Community Mobilization and Single Stage - One IDA / D3840 Post Request for Bids Open - National 80,000.00 0.00 Implementati 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2021-06-10 (Lunch, Refreshment and Institution Development Envelope on Stationary) for Kandahar region Page 5 AF-MRRD/WEE-RDP-125850- NC-RFB / Provision of Pending Community Mobilization and Single Stage - One Facilities for Training IDA / D3840 Post Request for Bids Open - National 71,000.00 0.00 Implementati 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2021-06-10 Institution Development Envelope (Lunch, Refreshment and on Stationary) for Balkh Region AF-MRRD/WEE-RDP-125852- NC-RFB / Provision of Pending Community Mobilization and Single Stage - One Facilities for Training IDA / D3840 Post Request for Bids Open - National 206,000.00 0.00 Implementati 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2021-06-10 Institution Development Envelope (Lunch, Refreshment and on Stationary) for Khost Region CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-MRRD/WEE-RDP-76482- Consultant Under CS-CQS / Impact assessment / Project Management Post Qualification Open - National 180,000.00 0.00 2018-09-01 2018-09-22 2018-11-05 2018-12-05 2019-01-09 2019-07-08 Implementation of AREDP Selection AF-MRRD/WEE-RDP-87599- CS-FBS / Hiring of FP for Central Region: Wardak Community Mobilization and Fixed Budget Open - Under (Maydan Shahr 36 CDCs) IDA / D3840 Prior 892,500.00 0.00 2018-11-25 2018-12-16 2019-01-29 2019-02-26 2019-03-28 2019-05-02 2019-06-06 2020-06-05 Institution Development Selection International Implementation Logar (Khoshi 54 and Pol-i- Alam 165 CDCs) Total CDCs 255 AF-MRRD/WEE-RDP-87600- CS-FBS / Hiring of FP for Community Mobilization and Fixed Budget Open - Under central region: Dai Kondi IDA / D3840 Post 360,500.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Institution Development Selection International Implementation (Nili 41 CDCs) and (Kiti 62 CDCs) Total CDCs 103 AF-MRRD/WEE-RDP-87602- CS-FBS / Hiring of FP for South West region: Helmand Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 931,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 province (Nawa-e-barakzai Institution Development Selection International Implementation 153 CDCs) and lashkargah 113 CDCs) Total CDCs 266 AF-MRRD/WEE-RDP-87603- CS-FBS / Hiring of FP for South West region: Province Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 581,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Nimroz (Zaranj 125 CDCs) Institution Development Selection International Implementation and (Chahar Burjak 41 CDCs) Total CDCs 166 AF-MRRD/WEE-RDP-87604- CS-FBS / Hiring of FP for South West region: Province Community Mobilization and Fixed Budget Open - Under Zabul (Qalat 137 CDCs) IDA / D3840 Prior 973,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Institution Development Selection International Implementation Province Uruzgan (Tarin Kowt 141 CDCs) Total CDCs 278 AF-MRRD/WEE-RDP-87605- CS-FBS / Hiring of FP for South East region: Province Community Mobilization and Fixed Budget Open - Under Ghazni (Ghazni Town 127 IDA / D3840 Prior 686,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Institution Development Selection International Implementation CDCs) Province Paktika (Sharana 69 CDCs) Total CDCs 196 Page 6 AF-MRRD/WEE-RDP-87606- CS-FBS / Hiring of FP for North East region: Province Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 686,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Badakhshan (Darayim 80 Institution Development Selection International Implementation CDCs and Fayazbad 116 CDCs) Total CDCs 196 AF-MRRD/WEE-RDP-87607- CS-FBS / Hiring of FP for North East region: Province Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 1,078,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Takhar (Baharak 77 CDCs Institution Development Selection International Implementation and Taluqan 231 CDCs) Total CDCs 308 AF-MRRD/WEE-RDP-87609- CS-FBS / Hiring of FP for FP for North East region: Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 745,500.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Province Kunduz ( Ali Abad Institution Development Selection International Implementation 52 CDCs and Kunduz 151 CDCs) Total CDCs 213 AF-MRRD/WEE-RDP-87610- CS-FBS / Hiring of FP for North East region: Province Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 822,500.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Baghlan ( Puli-e-Khumri 69 Institution Development Selection International Implementation CDCs and Baghlan-e-Jadid 166 CDCs) Total CDCs 235 AF-MRRD/WEE-RDP-87611- CS-FBS / Hiring of FP for North Wet region: Province Jawzjan (Fayzabad 50 CDCs Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 899,500.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 and Shibirghan 95 CDCs) Institution Development Selection International Implementation Province Faryab (Bilichiragh 48 CDCs and Maymana 64 CDCs) Total CDCs 257 AF-MRRD/WEE-RDP-87636- CS-FBS / Hiring of FP for North West region: Province Samangan (Hazrat-i-sultan Community Mobilization and Fixed Budget Open - Under 42 CDCs and Aybak 89 IDA / D3840 Prior 1,106,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Institution Development Selection International Implementation CDCs) Province Sar-e-Pul (Sarepul 124 CDCs and Gasfandi 61 CDCs) Total CDCs 316 AF-MRRD/WEE-RDP-87638- CS-FBS / Hiring of FP for East region: province Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 917,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Laghman (Mihtarlam 154 Institution Development Selection International Implementation CDCs and Qarghayi 108 CDCs) Total CDCs 262 AF-MRRD/WEE-RDP-87639- CS-FBS / Hiring of FP for East region: Province Konar (Asad Abad 37 CDCs and Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 560,000.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Narang wa badil 43 CDCs) Institution Development Selection International Implementation Province Nuristan (patun 39 and Wama 41 CDCs) Total CDCs 160 AF-MRRD/WEE-RDP-87640- CS-FBS / Hiring of FP for Community Mobilization and Fixed Budget Open - Under West region: Province Ghor IDA / D3840 Prior 822,500.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 Institution Development Selection International Implementation (Chakharan 235 CDCs) Total CDCs 235 Page 7 AF-MRRD/WEE-RDP-87641- CS-FBS / Hiring of FP for West region: Province Badghis (Qala-e-Naw 67 Community Mobilization and Fixed Budget Open - Under IDA / D3840 Prior 906,500.00 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 CDCs and Jawand 88 CDCs) Institution Development Selection International Implementation province Farah (Farah 104 CDCs) Total CDCs AF-MRRD/WEE-RDP-86488- CS-FBS / Facilitation Partner for South East Community Mobilization and Fixed Budget Open - IDA / D3840 Prior 682,500.00 0.00 Canceled 2018-10-22 2018-11-12 2018-12-26 2019-01-23 2019-02-22 2019-03-29 2019-05-03 2020-05-02 Region- Ghazni (Ghazni Institution Development Selection International Town) - Paktika (Sharana) 195 CDCs AF-MRRD/WEE-RDP-76452- CS-QCBS / Business Enterprise Development and Quality And Cost- / Post Open - National 25,000.00 0.00 Canceled 2019-01-06 2019-01-27 2019-03-12 2019-04-09 2019-05-09 2019-06-13 2019-07-18 2020-07-17 Development Training Market Linkages Based Selection Packages for EGs AF-MRRD/WEE-RDP-90147- Consultant CS-CQS / Business Enterprise Development and Pending TF / A8443 Post Qualification Open - National 6,000.00 0.00 2019-06-27 2019-07-18 2019-08-31 2019-09-30 2019-11-04 2020-05-02 development training Market Linkages Implementation Selection packages to EGs and PAs AF-MRRD/WEE-RDP-76450- CS-QCBS / Technical Enterprise Development and Quality And Cost- / Post Open - National 40,000.00 0.00 Canceled 2018-10-28 2018-11-18 2019-01-01 2019-01-29 2019-02-28 2019-04-04 2019-05-09 2020-05-08 Training to EGs on specific Market Linkages Based Selection value chain AF-MRRD/WEE-RDP-90173- Consultant CS-CQS / Technical training Enterprise Development and Pending TF / A8443 Post Qualification Open - National 25,000.00 0.00 2019-06-27 2019-07-18 2019-08-31 2019-09-30 2019-11-04 2020-05-02 to EGs and on specific value Market Linkages Implementation Selection chain EDML unit AF-MRRD/WEE-RDP-90162- Consultant CS-CQS / Business linkages Enterprise Development and Pending TF / A8443 Post Qualification Open - National 120,000.00 0.00 2019-07-30 2019-08-20 2019-10-03 2019-11-02 2019-12-07 2020-06-04 established for EGs EDML Market Linkages Implementation Selection unit AF-MRRD/WEE-RDP-76449- CS-QCBS / Hiring of Enterprise Development and Quality And Cost- Pending consultant for Value Chain TF / A8443 Post Open - National 350,000.00 0.00 2019-02-28 2019-03-21 2019-05-04 2019-06-01 2019-07-01 2019-08-05 2019-09-09 2020-09-08 Market Linkages Based Selection Implementation Studies and Market Assessment EDML unit AF-MRRD/WEE-RDP-90165- CS-CQS / Hiring of Consultant consultant for Independent Enterprise Development and Pending TF / A8443 Post Qualification Open - National 15,000.00 0.00 2019-08-14 2019-09-04 2019-10-18 2019-11-17 2019-12-22 2020-06-19 verification of EGs and PAs Market Linkages Implementation Selection for common assets support EDML unit AF-MRRD/WEE-RDP-76453- CS-QCBS / Business Enterprise Development and Quality And Cost- / Post Open - National 700,000.00 0.00 Canceled 2019-01-12 2019-02-02 2019-03-18 2019-04-15 2019-05-15 2019-06-19 2019-07-24 2020-07-23 Linkages Established for Market Linkages Based Selection EGs AF-MRRD/WEE-RDP-76488- Consultant CS-CQS / Developing of / Project Management Post Qualification Open - National 15,000.00 0.00 Canceled 2019-02-12 2019-03-05 2019-04-18 2019-05-18 2019-06-22 2019-12-19 training manual Selection AF-MRRD/WEE-RDP-76477- Quality And Cost- CS-QCBS / Process / Project Management Post Open - National 70,000.00 0.00 Canceled 2019-02-02 2019-02-23 2019-04-08 2019-05-06 2019-06-05 2019-07-10 2019-08-14 2020-08-13 Based Selection monitoring by third party Page 8 AF-MRRD/WEE-RDP-124516- CS-CQS / Qualitative Consultant Diagnostic of Rural Women’s Pending IDA / D3840 Project Management Post Qualification Open - National 50,000.00 0.00 2019-07-31 2019-08-21 2019-10-04 2019-11-03 2019-12-08 2020-03-07 Social and Economic Implementation Selection Empowerment in Afghanistan INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF-MRRD/WEE-RDP-86498- CS-INDV / Hiring of international individual Individual consultant (Management IDA / D3840 Project Management Post Consultant Open 108,000.00 0.00 Canceled 2018-12-03 2019-01-21 2019-02-11 2019-03-18 2019-09-14 Information System MIS Selection Consultant) for One (01) Year. AF-MRRD/WEE-RDP-76541- Individual CS-INDV / Developing / Project Management Post Consultant Open 6,000.00 0.00 Canceled 2019-03-03 2019-04-21 2019-05-12 2019-06-16 2019-12-13 Website for WEE-RDP for Selection 18 months AF-MRRD/WEE-RDP-CS-DS / Hiring of national Enterprise Development and Pending consultant for identification TF / A8443 Post Direct Selection Direct 6,000.00 0.00 2019-06-15 2019-06-25 2019-08-29 2019-10-29 Market Linkages Implementation of 18 SMEs in three regions EDML unit AF-MRRD/WEE-RDP-93835- Individual Under CS-INDV / Program Advisor IDA / D3840 Project Management Post Consultant Open 108,000.00 0.00 2019-01-05 2019-03-08 2019-03-29 2019-05-03 2020-05-03 Implementation (international) Selection Page 9