Pays: Guinée Bissau Projet: West Africa Regional Communication Infrastructure Program (WARCIP) Référence de l'Accord de financement: H GUB Plan de passation de marchés pour la période Décembre 2016 - Janvier 2018 Date d'approbation par la Banque Mondiale : 21 mars 2017 Fourniture et services 1 2 3 4 5 6 7 8 9 Prequalificati Domestic Revview by Expected Bid - Estimated Ref Procurement on Preference Bank Opening Contract (Description) Nº Commentair Cost in USD Method (yes / no) (yes / no) (Prior / Post) Date es Participation financière de la Paiement direct au 1 dans le Consortium pour 5 000 000 Consortium Non Non À priori Non applicable la connectivité de la Guinée Bissau 2 Achat de véhicule léger 40 000 Shopping Non Non À posteriori 15/12/2016 3 Achat de matériel de bureau 20 000 Shopping Non Non À posteriori 17/12/2016 4 Achat de matériel informatique 20 000 Shopping Non Non À posteriori 19/12/2016 Recrutement prestataire d'entretien 5 et nettoyage 20 000 Shopping Non Non À posteriori 21/12/2016 MTC - Acquisition du matériel du point 6 d'échange internet 50 000 Shopping Non Non À posteriori 30/01/2018 Pays: Guinée Bissau Projet: West Africa Regional Communication Infrastructure Program (WARCIP) Référence de l'Accord de financement: H GUB Plan de passation de marchés pour la période Décembre 2016 - Décembre 2017 Travaux: 1 2 3 4 5 6 7 8 9 Prequalificati Domestic Revview by Expected Bid - Estimated Ref Procurement on Preference Bank Opening Contract (Description) Nº Commentair Cost in USD Method (yes / no) (yes / no) (Prior / Post) Date es Connectivité internationale - parcipation de la Guinée Bissau au Consortium ACE qui détient le câble sous-marin ACE et 1 constrution de la station d'atterrissement du câble sous-marin à SURO (approx. 23 Km de la capitale) et de l'architecture de feston sous-marin reliant la station ACE de SURO à celle de Dakar Connectivité nationale - Tronçon fibre optique terrestre (approx. 28 km) compris entre la station 1 000 2 d’atterrissement à Suro et le point d’entrée du réseau 000 AOI Non Non À priori 15/12/2017 régional de transmission électrique Organisme de Mise en Valeur du fleuve Gambie (OMVG) autour de Bissau dans la zone d'Antula. Pays: Guinée Bissau Projet: West Africa Regional Communication Infrastructure Program (WARCIP) Référence de l'Accord de financement: H GUB Plan de passation de marchés pour la période Décembre 2016 - Décembre 2017 Consultants: 1 2 3 4 5 6 7 8 9 Prequalificati Domestic Revview by Expected Bid - Estimated Ref Procurement on Preference Bank Opening Contract (Description) Nº Commentair Cost in USD Method (yes / no) (yes / no) (Prior / Post) Date es Etudes, DAO Suivi et contrôle de travaux de Connectivité nationale - Tronçon fibre optique terrestre (approx. 28 km) compris entre la station d’atterrissement à Suro et le point d’entrée du réseau 150 1 régional de transmission électrique Organisme de Mise 000 SBQC Non Non À priori 01/07/2017 en Valeur du fleuve Gambie (OMVG) autour de Bissau dans la zone d'Antula. SPV - Assistance technique dans la finalisation du PPP 80 2 000 SBQC Non Non À priori 15/12/2016 MTC - Assistance technique dans la mise en place d’une stratégie nationale sectorielle de promotion de l’accès et de l’usage des TIC et de l’internet haut débit (y compris 130 3 promotion de l’innovation technologique et de l’e- 000 QC Non Non À posteriori 5/02/2017 gouvernement et usage du Fonds d’Accès Universel) MTC - Assistance technique dans la mise à niveau du cadre légal et réglementaire relatif aux communications électroniques et à la société de l'information, y compris 200 4 préparation des textes d'application 000 SBQC Non Non À priori 10/03/2017 Pays: Guinée Bissau Projet: West Africa Regional Communication Infrastructure Program (WARCIP) Référence de l'Accord de financement: H GUB Plan de passation de marchés pour la période Décembre 2016 - Décembre 2017 Consultants: 1 2 3 4 5 6 7 8 9 Prequalificati Domestic Revview by Expected Bid - Estimated Ref Procurement on Preference Bank Opening Contract (Description) Nº Commentair Cost in USD Method (yes / no) (yes / no) (Prior / Post) Date es MTC - Guinetelecom/Guinetel - Assistance technique pour la réalisation d’une étude stratégique sur les options relatives au possible repositionnement stratégique de Guinetelecom et Guinetel, y compris 280 5 diagnostic, recommendations, plan d'actions et 000 SBQC Non Non À priori 20/02/2017 accompagnement juridique et réglementaire. MTC - Assistance technique pour la réalisation d’une étude de faisabilité pour la mise en place d'un point 50 6 000 CI Non Non À posteriori 05/10/2017 d'échange internet MTC - Assistance technique pour la réalisation d’une étude sur la réglementation de l'occupation du domaine public et les synergies intersectorielles pour la coordination de travaux de génie civil entre projets 150 7 d'infrastructures publiques, y compris 000 SBQC Non Non À priori 10/07/2017 recommandations, plan d'actions et Préparation de textes réglementaires MTC - Étude sur la fiscalité relative au secteur des Technologies de l’Information et de la Communication 120 8 000 SBQC Non Non À priori 06/04/2017 (TIC) en Guinée Bissau Pays: Guinée Bissau Projet: West Africa Regional Communication Infrastructure Program (WARCIP) Référence de l'Accord de financement: H GUB Plan de passation de marchés pour la période Décembre 2016 - Décembre 2017 Consultants: 1 2 3 4 5 6 7 8 9 Prequalificati Domestic Revview by Expected Bid - Estimated Ref Procurement on Preference Bank Opening Contract (Description) Nº Commentair Cost in USD Method (yes / no) (yes / no) (Prior / Post) Date es ARN - Assistance technique pour le renforcement des capacités de la régulation des télécommunications sur : (i) l’attribution d’autorisations et licences (définition des procédures et préparation de décisions) ; (ii) le partage d’infrastructure passives (sites mobiles, génie civil et fibre noire) et l'itinérance nationale ; (iii) la régulation 600 9 000 SBQC Non Non À priori 16/02/2017 des marchés pertinents pour la prise de décision sur la dominance et l'élaboration des catalogues d'accès et d'interconnexion, y compris modèles de coûts. ARN - Assistance technique pour la réalisation d’une étude sur la mise en place d'un observatoire télécommunications et TIC et d'une étude de diagnostic 80 10 et de faisabilité pour la mise en place d'un système 000 SBQC Non Non À priori 02/09/2017 Audit & due diligence FSU et CEVATEGE 80 11 000 CI Non Non À posteriori 10/02/2017 Pays: Guinée Bissau Projet: West Africa Regional Communication Infrastructure Program (WARCIP) Référence de l'Accord de financement: H GUB Plan de passation de marchés pour la période Décembre 2016 - Décembre 2017 Consultants: 1 2 3 4 5 6 7 8 9 Prequalificati Domestic Revview by Expected Bid - Estimated Ref Procurement on Preference Bank Opening Contract (Description) Nº Commentair Cost in USD Method (yes / no) (yes / no) (Prior / Post) Date es Sauvegardes Plans - Etudes environnementales et sociales (Etude d’Impact Environnemental et Social (EIES), Plan de Gestion Environnementale et Sociale 60 12 (PGES), un Plan de Succinct de Réinstallation (PSR) ou 000 CI Non Non À posteriori 10/05/2017 un Plan d’Action de Réinstallation (PAR))) PROCUREMENT Africa : West Africa Regional Communications Infrastructure Project - SOP3 PLAN General Information Country: Africa Banks Approval Date of the Original Procurement Plan: 2017-05-09 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-07-19 Project ID: P155876 GPN Date: Project Name: West Africa Regional Communications Infrastructure Project - SOP3 Loan / Credit No: IDA / 59970, IDA / V0050 Executing Agency(ies): WARCIP GUINEA BISSAU WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TVX-2 / CONNECTIVITE nationale-trncon fibre optique compris entre la station d atrrisage a SURO et le point d Single Stage - One Pending entree du reseau regional de IDA / 59970 Supporting Connectivity Prior Request for Bids Open - International 0.00 2017-12-15 2017-12-20 2018-01-31 2018-03-02 2018-04-06 2019-04-06 Envelope Implementation transmission electrique Organisme de Mise en Valeur du Fleuve Gambie autour de Bissau dans la zone d ANTULA GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FOURN-4 / ACHAT DE Request for Single Stage - One Pending IDA / 59970 Implementation support Post Limited 0.00 2017-01-15 2017-05-08 2017-08-06 MATERIEL INFORMATIQUE Quotations Envelope Implementation FOURN-3 / ACHAT DE Request for Single Stage - One Pending IDA / 59970 Implementation support Post Limited 0.00 2017-01-13 2017-05-12 2017-08-10 MATERIEL DE BUREAU Quotations Envelope Implementation FOURN-2 / ACHAT DE Request for Single Stage - One Pending IDA / 59970 Implementation support Post Limited 0.00 2016-01-16 2016-05-17 2016-08-15 VEHICULES Quotations Envelope Implementation FOURN-6 / ACQUISITION DU Enabling environment for Request for Single Stage - One Pending MATERIEL DU POINT D IDA / 59970 Post Limited 0.00 2018-02-04 2018-04-01 2018-09-28 improved connectivity Quotations Envelope Implementation ECHANGE INTERNET NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CNS-1 / SUIVI ET CONTROLE Quality And Cost- Pending DES TRAVAUX DE IDA / 59970 Supporting Connectivity Prior Open - International 0.00 2017-07-03 2017-07-24 2017-09-06 2017-10-04 2017-11-03 2017-12-08 2018-01-12 2019-01-12 Based Selection Implementation CONNECTIVITE NATIONALE CNS-5 / GUINETELECOM/GUINETEL- ASSISTANCE TECHNIQUE POUR LA REALISATION D ETUDE STRATEGIQUE SUR LES OPTIONS RELATIVES AU National backbone and POSSIBLE Restructuring of Quality And Cost- Pending IDA / 59970 Prior Open - International 0.00 2017-05-30 2017-06-20 2017-08-03 2017-08-31 2017-09-30 2017-11-04 2017-12-09 2018-12-09 REPOSITIONNEMENT GuineTelecom/GuineTel (co- Based Selection Implementation STRATEGIQUE DE financing) GUINTELECOM/GUINETEL, Y COMPRIS LE DIAGNOSTIC, RECOMMENDATIONS, PLAN D ACTION ET ACCOMPAGNEMENT JURID CNS-9 / ASSISTANCE TECNHIQUE RENFORCEMENT CAPACITES SUR- - ATTRIBUTION DES LICENCES, Enabling environment for Quality And Cost- Pending PARTAGE D IDA / 59970 Prior Open - International 0.00 2017-05-31 2017-06-21 2017-08-04 2017-09-01 2017-10-01 2017-11-05 2017-12-10 2018-12-10 improved connectivity Based Selection Implementation INFRASTRUCTURES PASSIVES, ET ITINERAIRE NATIONAL ET REGULATION DES MARCHES Fixed Budget Pending 13 / SERVICE GARDINAGE IDA / V0050 Implementation support Post Open - National 0.00 2017-05-16 2017-06-06 2017-07-20 2017-08-17 2017-09-16 2017-10-21 2017-11-25 2018-11-25 Selection Implementation CNS-10 / ASSISTANCE TECNIQUE POUR LA REALISATION D UNE ETUDE LA MISE EN PLCE D UN Consultant Pending OBSERVATOIRE DES IDA / 59970 Supporting Connectivity Post Qualification Open - National 0.00 2017-07-06 2017-07-27 2017-09-09 2017-10-09 2017-11-13 2018-05-12 Implementation TELECOMMUNICATIONS ET TIC Selection ET UNE ETUDE DIAGNOSTIC FAISABILITE MISE EN PLACE D UN SYSTEME Page 1 CNS-3 / ASSISTANCE tecnhique dans la mise en place Consultant d une strategie nationale Pending IDA / 59970 Supporting Connectivity Post Qualification Open - National 0.00 2017-07-06 2017-07-27 2017-09-09 2017-10-09 2017-11-13 2018-05-12 sectoriellr de promotion de l Implementation Selection acces et de l usage des TIC et de l internet haut debut CNS-4 / ASSISTANCE TECHNIQUE DANS MISE A NIVEAU DU CADRE LEGAL ET Consultant REGLEMENTAIRE RELATIF Pending IDA / 59970 Supporting Connectivity Prior Qualification Open - International 0.00 2017-07-06 2017-07-27 2017-09-09 2017-10-09 2017-11-13 2018-05-12 AUX TELECOMMUNICATIONS Implementation Selection ELECTRONIQUES Y COMPRIS LA PREPARATION DES TEXTES D APPLICATION GW-WARCIP-19592-CS-QCBS / É ude pour le repositionnement t Enabling environment for Quality And Cost- Pending stratégique de Guiné Telecom et IDA / 59970 Prior Open - International 0.00 2017-07-06 2017-07-27 2017-09-09 2017-10-07 2017-11-06 2017-12-11 2018-01-15 2019-01-15 improved connectivity Based Selection Implementation Guinetel dans le marché national. INDIVIDUAL CONSULTANTS Page 2