Ratings of First and Second Phase of Coastal Transmission Backbone Project and Power Pool Program Projects for Ghana and Benin were as follows: outcomes were unsatisfactory, risk to development outcome was high, Bank performance was moderately unsatisfactory...  See More +

Details

  • 2018/02/28 10:05:00
  • Implementation Completion and Results Report;
  • ICR4338
  • 1
  • 1
  • Western Africa
  • Africa
  • 2018/03/09 08:02:58
  • Disclosed
  • Ghana and Benin - First and Second Phase of Coastal Transmission Backbone Project and Power Pool Program Projects