Report No. PIC5452 Project Name Brazil-Central Bank Modernization ... Technical Assistance Loan Region Latin America and the Caribbean Sector Public Sector Management/ Private Sector Development Project ID BRPE48357 Borrower Federative Republic of Brazil Implementing Agency Central Bank of Brazil Date this PID Prepared July 21, 1997 Projected Board Date September/October 1997 1. Country Background. Brazil underwent a major change in economic regime with the introduction of the Real Plan in mid-1994. The Plan introduced an exchange rate anchor with flexibility to move within a band, deindexed the economy, and implemented tight credit and monetary policies. Brazil has clearly embraced a new vision of development -- embodying reforms for stable and sustainable growth with poverty reduction and improving equity -- which is being strongly translated into its policy agenda by an administration that has achieved some of the best economic results in a generation. Much economic and social progress has been achieved, including an increase in the growth rate from virtual stagnation through 1992 to an average of about four percent during 1993 -1996, a reduction in annual inflation from 2,668 percent in 1994 to about 10 percent in 1996, a strong balance of payments, and a reduction in both relative and absolute poverty indices during the same period. However, fiscal adjustment has been more difficult than originally anticipated. 2. Sector Background. As a consequence of the sharp fall of inflation following the introduction of the Real Plan, bank revenues have shifted dramatically. Whereas in 1994, Brazil's banks earned about half of their revenues by reinvesting their non- interest earning deposits in high-yielding financial instruments, this percentage had dropped sharply to a few percentage points by the fourth quarter of 1995. Numerous private and public banks, burdened by high cost structures, non-performing loans and few earnings alternatives, could not adjust and failed. Among the private banks, the major failures included Banco Economico and Banco Nacional. The restructured assets and liabilities of both of these institutions were merged into other banks. In 1996, Bamerindus, the fifth largest bank in the country, also encountered problems and its acquisition by a major international bank was completed in early 1997. Among the major public banks, both the state banks in Rio de Janeiro and Sao Paulo were intervened by the Central Bank. The state bank of Rio was subsequently privatized in mid-1997. The state bank of Sao Paulo is currently being restructured and is expected to be privatized in 1998. Banco do Brasil, the country's largest bank which has also suffered from structural deficiencies, has been recapitalized (about US$8 billion) and is now engaged in a major restructuring effort. 3. Project Objectives. The macroeconomic and financial sector difficulties have exposed some need to improve the institutional capacity of the Central Bank, particularly of its banking supervision function. The Central Bank has thus embarked on a long-term modernization effort to both help it anticipate/prevent major bank failures and to allow it to manage failures more expertly. 4. The Project's development objective is to complement the Central Bank's long-term effort by supporting a first-phase action plan with the goal of strengthening banking supervision, and by assisting in the identification of international best practices. The primary vehicle, to achieve better banking supervision, is the increased professionalization of its banking supervision staff via training in enhanced supervision and enforcement tools, upgrading of the information flow to the Central Bank and utilization of advanced information technology equipment. 5. Other Project components include laying the groundwork (legal and financial feasibility studies) for the possible creation of an entity, separate from the Central Bank, to manage the disposal of failed banking assets. The surge of bank failures added significantly to the Central Bank's inventory of assets of failed banks, and has burdened its capacity to manage timely asset liquidation and disposal. 6. The Project will also assist in the evaluation of the financial sector structure and consider changes in public policies and instruments to foster a growing and profitable private banking system. Finally, the Project will allow the Central Bank to continue to expand its training programs rapidly in a few key areas outside banking supervision. 7. Project Components and Financing. To achieve its objectives, the Project has been designed around broad and indicative project components such as training, upgrading of data bases, improvement of the quality of information flows from banks, information technology equipment, selected studies and high level advisory services to delineate the future directions of the financial sector as well as banking supervision. The Bank is proposing to provide a US$20 million loan to finance all project components other than the Central Bank's Project Coordination. Total project cost are estimated at US$22 million. 8. Institutional and Implementation Arrangements. Implementation Period: Three years, with the objective of disbursing most of the Bank loan during the first two years. This is to respond to the Central Bank's need for urgency. Executing agencies: The Central Bank of Brazil would be the sole executing agency for all Project components. Project coordination. The Central Bank has established a Project Coordinating Unit (PCU) headed by a manager with a rank of at least Head of Department, or equivalent. This Unit would be staffed with - 2 - appropriate accounting, procurement and administrative personnel. The PCU would be supported by a Central Bank coordinating committee which would draw participants from all areas benefiting from this Project. 9. Project Sustainability. All project expenditures will be designed in such a manner that their outputs can be productively applied. For instance, staff trained abroad would be required to pass on such training upon their return. 10. Lessons learned and reflected in the project design. The principal lesson is that TA loans are only successful when their goals are fully shared by borrowers. The Central Bank of Brazil has demonstrated such full sharing. Other lessons applied include: -- limiting scope of work to a few defined areas (human resources, information & information technology); -- developing Terms of Reference for key project components as part of loan preparation; -- focusing on the core of Central Bank operations - Bank Supervision - and not trying to influence all aspects of the institution's mandate; -- having a clear need for the proposed technical assistance agenda (high staff turn-over and retirements increase need for training; changes in macroeconomic environment and banking industry structure require new supervisory tools; recent bank failures and costs of bail-outs for government have created a sense of urgency in the Central Bank to better foresee future bank failures, etc.). 11. Poverty Category and Environmental Aspects. Not applicable. 12. Program Objective Category. Economic Management (EM) Contact Point: Public Information Center The World Bank 1818 H Street N.W. Washington, D.C. 20433 Telephone No.: (202) 458-5454 Fax No.: (202) 522-1500 Note: This is information on an evolving project. Certain components may not necessarily be included in the final project. Processed by the Public Information Center week ending August 1, 1997. - 3 -