SUPPLEMENTARY PROCUREMENT PLAN OF PHASE 2 USING COST SAVING AFTER BIDDING - WB FUND Mekong Delta Region Urban Upgrading Project My Tho city Sub-project A. Package proposed for expansion of contract: 139.573 USD Exchange rate: 1USD = 22.695 VND 1. Supervision consultant: First Expansion Number Consultant contracted First Second Contract value after value time/val time/val % expansion (USD) (USD) ue (USD) Ue (USD) MT-CS-4.9a Apave Asia Pacific 189.657 42.454 139.573 95,98 371.684 Total of expanded value: 139.573 B. New packages proposed this time: 4.639.788 USD Contract Procure Contractor impleme Estimate Bank's Contract utatn Number Description (U ) ment . selection ntation (USD) review tp method starts from period (month) iod Component 2: Supporting Primary and Secondary Infrastructure 4.639.788 USD , Upgrade District road 92C Quarter III- Fixed unit MT-PW-2.2.a (From Thanh Tri bridge to 506.720 NCB Post IV/2017 price5 Nguyen Minh Duong street). Upgrade Lo Me road extension (From Nguyen Quarter III- Fixed unit (From374.532 NCB Post 5V21 rc MT-PW- Trung True street to National IV/2017 price 2.2.b road 50) Upgrade Doe Binh Kieu street (From Hoang Hoa Tham to Nguyen An Ninh street); Phan Boi Chau (From Hoang Hoa Tham to Hoc Lac street); Hoc MT-PW- Lac street (from Phan Thanh Quarter III- Fixed unit 2.2.c Gian to Thai Sanh Hanh 449.438 NCB Post IV/2017 price4 street); Hoang Hoa Tham street (From Phan Thanh Gian to Nguyen Huynh Due street). Nguyen An Ninh street (From Nguyen Huynh Due to Hoc Lac street. 1 M'I-PW- Upgrade lanes connecting Quarter III- Fixed unit 2.2.d LIA 5, 6 and Bach Nha ditch 991.408 NCB Post IV/2017 price5 with surrounding areas Upgrade lanes of quarter 1-- Ward 6 (From Lc Thi Hong Gam to Xang Cut canal - ward Quarter 111- Fixed unit MT-PW-2.4a 6) lanes connecting quarter 12- 381344 NCR Post 4 IV/20 17 price ward 6. - Treatment of erosion at the end of lane 6 - LIA 14 _ MT-PW - Build impressive point on Quarter III- Fixed unit 2.4b Tien river embankment - 489.095 NCB Post IV/2017 price5 Ward 2. MT-PW-2-4. Artistic street lighting on Tien 934.126 NCR Post Quarter ITT- Fixed unit river embankment - Ward 1, IV/2017 price Ward 2, Ward 4 and Ward 6 MT-PW- Upgrade trees in streets of the 11.126 NCB Post Quarter III- Fixed unit 2.4d city. IV/2017 price C. Total of fund IDA: A + B 4.779.361 USD 2