P128534 Safety Nets Project Procurement Plan June 1st 2017 I. General 1. Bank’s approval Date of the procurement Plan: February 5, 2013 (initial): Revision 12 of Updated Procurement Plan, April 20, 2017 2. Date of General Procurement Notice: Nov 24, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year November 2016 to March 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. NCB (Goods) Above or equal US$ 10 million 2. NCB (Works) Above or equal US$ 10 million 3. NCB (Non-Consultant Services) Above or equal US$ 2 million 4. Individual (Goods) Above or equal Justification to be included US$ 10 million in the PP 5. Individual (Non Consultant Above or equal Justification to be included Services) US$ 2 million in the PP 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for the Safety Nets Project issued on January 2014 by Project Coordination Unit. 5. Any Other Special Procurement Arrangements: Not Applicable 1 6. Summary of the Procurement Packages planned during the 18 months of the current Procurement Plan-November 2016 to March 2018 (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) 1 Summary of 0 0 No No the ICB (Works) 2 Summary of 0 0 No No the ICB (Goods) 3 Summary of 0 0 No No the NCB (Works) 4 Summary of 1.5 18 No Post the NCB (Goods) 5 Summary of 0.74 2 No Prior the NCB (Non- Consultant Services) 6 Summary of 0.51 16 No Post the NCB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above or equal US$ 1 million 2 Competitive Methods (Individual) Above or equal US$ 0.3 million 3 Single Source (Firms) Above or equal Justification to be US$ 1 million included in the PP 4 Single Source (Individual) Above or equal Justification to be US$ 0.3 million included in the PP 2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 1.7 8 Prior LCS; SSS; number of CQS; contracts that Individual; will be let under other methods 2 Summary of 2 72 Post SSS; CQS; number of Individual contracts that will be let under other methods 3 PROCUREMENT Cameroon : Cameroon Social Safety Nets PLAN General Information Country: Cameroon Bank’s Approval Date of the Original Procurement Plan: 2017-02-14 2020-08-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128534 GPN Date: Project Name: Cameroon Social Safety Nets Loan / Credit No: IDA / 52240, IDA / 62230, IDA / D2980 Executing Agency(ies): UNITE DE GESTION DU PROJET FILETS SOCIAUX WORKS Procurem Bid Evaluation Activity Reference No. Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificatio High ent Process Prequalification Bidding Documents Report and Contract / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process n (Y/N) SEA/SH Risk Documen Status Evaluation Report as Issued Recommendation for Completion (US$) Documents Justification / Invitation Opening / Minutes t Type Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne Actu d al CM-UGP-PFS-26069-CW- Laying the Foundations of RFQ / Aménagement des a Safety Net System and Demande de Single Stage - 2018-04- 2018-08- 2018-04- 2018-10- 2018-05- 2018- IDA / 52240 A posteriori Limited 7,209.40 Achevé bureaux de l'antenne Supporting Project prix One Envelope 01 29 24 05 15 12-17 régionale du Nord ouest Management GOODS Bid Evaluation Activity Reference No. Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificatio Process Prequalification Bidding Documents Report and Contract / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process n (Y/N) Status Evaluation Report as Issued Recommendation for Completion (US$) Documents Justification / Invitation Opening / Minutes Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-5831-GO- Laying the Foundations of RFB / fourniture du a Safety Net System and Single Stage - 2017-01- 2017-02- 2017-01- 2017-03- 2017-01- 2017-04- 2017-02- 2017-05- 2017-04- 2017-11- 2017-05- matériel informatique, de IDA / 52240 A posteriori Appel d'offres Open - National 243,616.43 Achevé Supporting Project One Envelope 24 01 29 12 24 11 10 16 17 12 08 téléphonie, et d'équipement Management de bureau (en 3 lots distincts) CM-UGP-PFS-6172-GO- RFQ / Fourniture du matériel de la phase 3 Public Works Program Demande de Single Stage - 2017-02- 2017-02- 2017-04- 2017-03- 2017-05- 2017-04- des THIMO dans 2 IDA / 52240 A posteriori Limited 159,198.65 Achevé Pilot prix One Envelope 18 10 15 10 15 14 communes de la région de l'Extrême Nord et 2 communes de la région de l'EST CM-UGP-PFS-6231-GO- RFQ / Fourniture des boîtes à pharmacie de la phase 3 des THIMO pour Public Works Program Demande de Single Stage - 2017-02- 2017-03- 2017-04- 2017-04- 2017-05- 2017-04- IDA / 52240 A posteriori Limited 31,172.51 Achevé 2 communes de la région Pilot prix One Envelope 20 03 17 07 01 14 de l'Extrême Nord et 2 communes de la région de l'Est CM-UGP-PFS-6307-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-03- 2017-05- 2018-05- IDA / 52240 A posteriori Limited 0.00 Annulé fournitures de bureau au Supporting Project prix One Envelope 20 15 10 Projet Filets Sociaux Management CM-UGP-PFS-7392-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - 2017-05- 2016-12- 2017-06- 2017-07- 2017-08- 2017-09- 2017-10- IDA / 52240 A posteriori Appel d'offres Open - National 0.00 Annulé consommables Supporting Project One Envelope 31 12 05 17 16 20 20 informatiques Management CM-UGP-PFS-16931-GO- Laying the Foundations of RFQ / fourniture des a Safety Net System and Demande de Single Stage - 2017-06- 2017-08- 2017-07- 2017-08- 2017-08- pièces de rechange pour IDA / 52240 A posteriori Open - National 32,502.70 Achevé Supporting Project prix One Envelope 19 14 17 28 17 véhicules et motos du Management Projet Filets Sociaux CM-UGP-PFS-23000-GO- RFQ / fourniture des boites à pharmacie pour Public Works Program Demande de Single Stage - 2017-08- 2017-09- 2017-10- 2017-10- 2018-04- 2017-10- la phase 4 des THIMO IDA / 52240 A posteriori Limited 21,014.35 Achevé Pilot prix One Envelope 15 04 13 16 11 24 dans 2 communes de la région de l'Adamaoua et 1 commune de la région du Nord CM-UGP-PFS-25708-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - 2017-11- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- IDA / 52240 A posteriori Limited 6,813.69 Achevé mobilier de bureau de Supporting Project prix One Envelope 09 22 12 06 02 12 l'antenne du Nord-Ouest Management CM-UGP-PFS-25990-GO- RFQ / Fourniture des boites à pharmacie de la Public Works Program Demande de Single Stage - 2017-10- 2018-03- 2017-11- 2018-04- 2017-12- 2018-04- phase 5 des THIMO pour IDA / 52240 A posteriori Limited 20,966.02 Achevé Pilot prix One Envelope 12 01 10 03 01 13 2 communes de la région de l'Est et 2 communes de la région du Nord ouest CM-UGP-PFS-26037-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-09- 2018-06- 2017-10- 2018-07- 2017-10- 2018-07- autocollants pour voitures IDA / 52240 A posteriori Limited 2,081.57 Achevé Supporting Project prix One Envelope 27 11 16 05 30 19 et motos au Projet Filets Management Sociaux CM-UGP-PFS-23003-GO- RFQ / Fourniture du matériel et des matériaux Public Works Program Demande de Single Stage - 2017-09- 2017-09- 2017-10- 2017-10- 2017-10- 2017-11- IDA / 52240 A posteriori Limited 90,128.08 Achevé de travail pour la phase 4 Pilot prix One Envelope 11 04 03 16 24 22 des THIMO dans 2 communes de la région de l'Adamaoua CM-UGP-PFS-25561-GO- Laying the Foundations of RFB / Fourniture du a Safety Net System and Single Stage - 2017-09- 2017-04- 2017-09- 2017-09- 2017-06- 2017-09- 2017-07- 2017-09- 2017-08- 2017-10- matériel roulant autos et IDA / 52240 A posteriori Appel d'offres Open - National 143,614.65 Signé Supporting Project One Envelope 01 28 01 01 29 01 07 08 31 08 motos au projet Filets Management Sociaux en deux lots distincts CM-UGP-PFS-25477-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - 2017-10- 2017-11- 2017-11- 2017-12- 2017-11- 2018-01- IDA / 52240 A posteriori Limited 26,101.20 Achevé seaux au Projet Filets Measures to Boost prix One Envelope 09 13 06 20 27 24 Sociaux Household Productivity CM-UGP-PFS-25475-GO- RFQ / Fourniture du matériel et des matériaux Public Works Program Demande de Single Stage - 2017-09- 2017-09- 2017-09- 2017-11- 2017-10- 2017-11- IDA / 52240 A posteriori Limited 50,255.93 Achevé de travail pour la phase 4 Pilot prix One Envelope 02 04 24 14 15 23 des THIMO dans la région du nord , commune de Touboro CM-UGP-PFS-47595-GO- RFQ / Fourniture du matériel de la phase 6 Public Works Program Demande de Single Stage - 2018-06- 2018-08- 2018-07- 2018-09- 2018-08- 2018-10- IDA / 52240 A posteriori Limited 65,428.39 Achevé des THIMO du Projet Pilot prix One Envelope 18 31 30 27 29 18 Filets Sociaux dans les communes de Dembo et Bashéo, région du Nord CM-UGP-PFS-47606-GO- RFB / Fourniture et paramétrage d'un progiciel Cash Transfer Program de gestion intégré pour la with Accompanying Single Stage - 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- planification, la IDA / 52240 A posteriori Appel d'offres Open - National 0.00 Annulé Measures to Boost One Envelope 21 26 27 17 14 13 programmation, la Household Productivity budgétisation, le suivi évaluation et la production des rapports et indicateurs CM-UGP-PFS-47608-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - 2018-03- 2018-05- 2018-05- IDA / 52240 A posteriori Limited 0.00 Annulé logiciels informatiques au Measures to Boost prix One Envelope 27 08 29 projet Filets Sociaux Household Productivity CM-UGP-PFS-16933-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - 2017-06- 2017-08- 2017-09- seaux, Tee shirt, IDA / 52240 A posteriori Open - National 0.00 Annulé Measures to Boost prix One Envelope 20 15 14 casquettes autocollants Household Productivity pour véhicules estampillés Projet Filets Sociaux CM-UGP-PFS-25989-GO- RFQ / Fourniture du matériel et des matériaux Public Works Program Demande de Single Stage - 2018-04- 2018-03- 2018-05- 2018-04- 2018-06- 2018-04- de travail pour la phase 5 IDA / 52240 A posteriori Limited 72,952.92 Achevé Pilot prix One Envelope 06 01 05 03 04 20 des THIMO dans 2 communes de la région du Nord ouest (Oku et Ako) CM-UGP-PFS-25987-GO- RFQ / Fourniture du matériel et des matériaux Public Works Program Demande de Single Stage - 2018-04- 2018-03- 2018-05- 2018-04- 2018-06- 2018-04- de travail pour la phase 5 IDA / 52240 A posteriori Limited 65,815.47 Achevé Pilot prix One Envelope 06 01 05 03 04 24 des THIMO dans 2 communes de la région de l'EST (Bétaré OYA et Batouri) CM-UGP-PFS-25491-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - 2018-04- 2018-05- 2019-05- IDA / 52240 A posteriori Limited 0.00 Annulé matériel de pause café au Supporting Project prix One Envelope 19 24 24 Projet Filets Sociaux Management CM-UGP-PFS-47578-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - 2018-06- 2019-01- 2018-07- 2019-03- 2018-08- 2019-03- IDA / 52240 A posteriori Limited 24,340.71 Achevé pneus de recharge pour Measures to Boost prix One Envelope 04 24 16 04 06 28 des autos et motos du Household Productivity Projet CM-UGP-PFS-25476-GO- Cash Transfer Program RFQ / Fourniture des tee- with Accompanying Demande de Single Stage - 2017-12- 2018-01- 2017-12- 2018-03- 2018-01- 2018-03- IDA / 52240 A posteriori Limited 68,943.69 Achevé shirts et casquettes Measures to Boost prix One Envelope 02 24 26 01 16 29 estampillés au Projet Household Productivity Filets Sociaux Page 1 CM-UGP-PFS-25488-GO- Laying the Foundations of RFQ / fourniture des a Safety Net System and Demande de Single Stage - 2018-01- 2018-03- 2018-02- 2018-05- 2019-02- 2018-12- IDA / 52240 A posteriori Limited 83,622.13 Achevé encres pour imprimantes Supporting Project prix One Envelope 03 29 10 22 10 20 et photocopieurs Management CM-UGP-PFS-25487-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-09- 2017-10- 2018-10- IDA / 52240 A posteriori Limited 0.00 Annulé fournitures de bureau au Supporting Project prix One Envelope 16 11 11 Projet Filets sociaux Management CM-UGP-PFS-67485-GO- RFQ / Fourniture du Laying the Foundations of matériel informatique et a Safety Net System and Demande de Single Stage - 2018-07- 2018-07- 2018-08- 2018-07- 2018-09- 2018-08- IDA / 52240 A posteriori Limited 6,993.13 Achevé de bureautique de Supporting Project prix One Envelope 15 05 19 30 02 06 l'antenne régionale du Management projet du Nord Ouest CM-UGP-PFS-67490-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2018-07- 2018-07- 2018-08- 2018-07- 2019-08- 2018-08- IDA / 52240 A posteriori Limited 3,525.35 Achevé polices d'assurance aux 40 Supporting Project prix One Envelope 10 02 14 25 14 29 premières motos du projet Management CM-UGP-PFS-47597-GO- RFQ / Fourniture des Public Works Program Demande de Single Stage - 2018-09- 2018-08- 2018-09- 2018-09- 2018-10- 2018-09- boîtes à pharmacie de la IDA / 52240 A posteriori Limited 7,383.31 Achevé Pilot prix One Envelope 09 29 30 14 07 19 phase 6 des THIMO du Projet Filets Sociaux CM-UGP-PFS-75801-GO- Cash Transfer Program RFQ / Fourniture du with Accompanying Demande de Single Stage - 2018-09- 2018-10- 2018-10- 2018-10- 2018-10- 2018-10- IDA / 52240 A posteriori Limited 7,144.10 Achevé matériel pour les crèches Measures to Boost prix One Envelope 15 01 10 24 17 31 temporaires au PFS Household Productivity CM-UGP-PFS-130190-GO- RFQ / Fourniture des licences pour la plateforme Laying the Foundations of tomate ( Licence a Safety Net System and Demande de Single Stage - 2019-10- 2019-09- 2019-12- 2019-11- 2020-06- IDA / 62230 A posteriori Limited 29,607.05 Signé Multiprojet, Monosite et Supporting Project prix One Envelope 10 30 13 18 10 Multiposte Tom2pro, Management Tom2monitoring, Tom2paie et Tom2marché) CM-UGP-PFS-121205-GO- Laying the Foundations of RFB / Fourniture des a Safety Net System and Demande de Single Stage - 2019-10- 2019-09- 2019-11- 2019-11- 2020-03- IDA / 52240 A posteriori Limited 62,547.39 Signé consommables Supporting Project prix One Envelope 05 30 23 18 22 informatiques au Projet Management Filets Sociaux CM-UGP-PFS-121383-GO- RFQ / Acquisition des Laying the Foundations of fournitures de bureaux et a Safety Net System and Demande de Single Stage - 2019-10- 2019-09- 2019-12- 2019-11- 2020-04- IDA / 62230 A posteriori Limited 26,447.17 Signé des produits d'entretien de Supporting Project prix One Envelope 14 30 16 18 14 bureau en deux lots Management distincts CM-UGP-PFS-120445-GO- UN / FOURNITURE DE 756 TABLETTES BIOMETRIQUES Laying the Foundations of Passation de MOBILES et 756 a Safety Net System and marchés auprès 2019-11- 2019-07- 2019-12- 2019-06- 2020-02- 2019-11- 2020-08- IDA / 62230 A posteriori Direct 660,808.00 Signé BATTERIE EXTERNES Supporting Project des agences de 30 31 14 07 02 13 20 TYPES POWERBANK ET Management l'ONU 756 SACS PHOTOVOLTAÏQUES en deux tranches de 400 et 356 chacune CM-UGP-PFS-171977-GO- RFB / Fourniture du matériel THIMO de la Public Works Program Single Stage - En attente 2020-06- 2020-07- 2020-08- 2020-09- 2020-10- 2020-11- IDA / D2980 A posteriori Appel d'offres Open - National 0.00 phase 7 des Travaux à Pilot One Envelope d'exécution 30 05 16 15 20 10 Haute Intensité de Main d'œuvre en 4 lots distincts CM-UGP-PFS-172000-GO- RFQ / Fourniture des Public Works Program Demande de Single Stage - En attente 2020-06- 2020-08- 2020-09- boîtes à pharmacie de la IDA / D2980 A posteriori Limited 0.00 Pilot prix One Envelope d'exécution 20 26 09 phase 7 des THIMO en 3 lots distincts CM-UGP-PFS-172008-GO- RFQ / Fourniture et Public Works Program Demande de Single Stage - En attente 2020-05- 2020-07- 2020-08- équipement du matériel de IDA / D2980 A posteriori Limited 0.00 Pilot prix One Envelope d'exécution 20 26 09 crèche de la Phase 7 des THIMO en 3 lots CM-UGP-PFS-172043-GO- RFB / Fourniture du matériel productif pour les Cash Transfer Program sanctions positives with Accompanying Single Stage - En attente 2020-12- 2020-12- 2021-02- 2021-03- 2021-04- 2022-04- (machettes et limes, IDA / 62230 A posteriori Appel d'offres Open - National 0.00 Measures to Boost One Envelope d'exécution 15 25 05 07 11 11 machines à écraser avec Household Productivity bancs, brouettes) au Projet Filets Sociaux en trois lots distincts CM-UGP-PFS-172069-GO- RFQ / Fourniture du Laying the Foundations of mobilier de bureau et d’un a Safety Net System and Demande de Single Stage - En attente 2020-09- 2020-10- 2020-10- IDA / 62230 A posteriori Limited 0.00 coffre-fort pour l’Unité de Supporting Project prix One Envelope d'exécution 05 15 29 Gestion du Projet Filets Management Sociaux CM-UGP-PFS-172065-GO- Laying the Foundations of RFB / Fourniture des a Safety Net System and Single Stage - En attente 2020-07- 2020-07- 2020-09- 2020-10- 2020-11- 2021-11- consommables IDA / 52240 A posteriori Appel d'offres Open - National 0.00 Supporting Project One Envelope d'exécution 15 25 05 05 09 09 informatiques à l'unité de Management Gestion du Projet Filets Sociaux CM-UGP-PFS-172070-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - En attente 2020-11- 2021-01- 2021-01- Pneus et pièces de IDA / 62230 A posteriori Limited 0.00 Supporting Project prix One Envelope d'exécution 22 10 24 rechange des véhicules du Management Projet Filets Sociaux CM-UGP-PFS-172036-GO- Laying the Foundations of RFQ / Fourniture de 50 a Safety Net System and Demande de Single Stage - En attente 2020-06- 2020-08- 2020-09- IDA / 62230 A posteriori Limited 0.00 mini groupes électrogènes Supporting Project prix One Envelope d'exécution 20 19 02 au Projet Filets Sociaux Management CM-UGP-PFS-170601-GO- RFB / Fourniture du Laying the Foundations of matériel informatique, du a Safety Net System and Single Stage - En attente 2020-07- 2020-08- 2020-09- 2020-10- 2020-12- 2021-01- matériel de téléphonie et IDA / 62230 A posteriori Appel d'offres Open - National 0.00 Supporting Project One Envelope d'exécution 30 13 27 27 07 21 des logiciels informatiques Management au Projet Filets Sociaux en 3 lots distincts CM-UGP-PFS-172042-GO- Laying the Foundations of RFB / Fourniture de 4 a Safety Net System and Demande de Single Stage - En attente 2020-08- 2020-10- 2020-11- véhicules pick up double IDA / 62230 A posteriori Open - National 0.00 Supporting Project prix One Envelope d'exécution 14 16 15 cabine au Projet Filets Management Sociaux NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificatio Process Prequalification Bidding Documents Report and Contract / Description Component Review Type Method Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process n (Y/N) Status Evaluation Report as Issued Recommendation for Completion (US$) Documents Justification / Invitation Opening / Minutes Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6232-NC- RFQ / Recrutement des Public Works Program Demande de Single Stage - 2017-02- 2017-02- 2017-04- 2017-04- 2017-12- agences de paiement pour IDA / 52240 A posteriori Limited 61,263.97 Signé Pilot prix One Envelope 15 10 12 24 08 les phases 3 et 4 des THIMO en lots CM-UGP-PFS-6233-NC- RFQ / Recrutement des agences de paiement pour le paiement de 19500 ménages bénéficiaires du Cash Transfer Program cycle 2 des transferts with Accompanying Demande de Single Stage - 2017-03- 2017-05- 2019-04- IDA / 52240 A priori Limited 0.00 Annulé monétaires dont 7500 dans Measures to Boost prix One Envelope 07 05 25 la région de l'Extrême Household Productivity Nord, 5500 dans les régions du Nord et de l'Adamaoua, et 6500 dans les régions de l'Est, du Nord Cash Transfer Program CM-UGP-PFS-6315-NC- with Accompanying Demande de Single Stage - 2017-02- 2017-04- 2017-04- 2017-05- 2017-05- 2017-06- RFQ / Impression des IDA / 52240 A posteriori Limited 22,001.63 Achevé Measures to Boost prix One Envelope 25 21 22 26 06 19 documents du Projet Household Productivity Laying the Foundations of CM-UGP-PFS-6306-NC- a Safety Net System and Demande de Single Stage - 2017-03- 2017-03- 2017-04- 2017-06- 2018-04- 2018-06- RFQ / fourniture des IDA / 52240 A posteriori Limited 58,410.90 Achevé Supporting Project prix One Envelope 03 06 28 07 23 08 polices d'assurance maladie Management CM-UGP-PFS-7385-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-03- 2017-03- 2017-04- 2017-06- 2018-04- 2018-06- IDA / 52240 A posteriori Limited 18,329.45 Achevé polices d'assurance Supporting Project prix One Envelope 03 06 28 15 23 14 automobile Management CM-UGP-PFS-14464-NC- Laying the Foundations of RFQ / Renouvellement du a Safety Net System and Demande de Single Stage - 2017-06- 2018-07- 2017-06- 2018-07- 2018-06- IDA / 52240 A posteriori Limited 3,553.09 Signé contrat d'assurance des 40 Supporting Project prix One Envelope 13 17 19 25 14 motos en circulation Management Page 2 Laying the Foundations of CM-UGP-PFS-25608-NC- a Safety Net System and Demande de Single Stage - 2017-10- 2017-10- 2018-10- RFQ / Maintenance Autos IDA / 52240 A posteriori Limited 0.00 Annulé Supporting Project prix One Envelope 04 31 31 UGP pour 1 an Management CM-UGP-PFS-25616-NC- Laying the Foundations of RFQ / Maintenance a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 0.00 Annulé matériel bureautique et Supporting Project prix One Envelope 07 07 07 informatique UGP pour 1 Management an CM-UGP-PFS-25623-NC- Laying the Foundations of RFQ / Maintenance froid a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 0.00 Annulé et climatisation UGP Supporting Project prix One Envelope 11 09 09 pour 1 an Management CM-UGP-PFS-25711-NC- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - 2017-12- 2018-04- 2018-01- 2018-07- 2019-01- IDA / 52240 A posteriori Limited 8,986.03 Signé service de gardiennage Supporting Project prix One Envelope 09 20 09 10 09 pour l'antenne régionale Management du Nord Ouest CM-UGP-PFS-25729-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-10- 2018-02- 2017-11- 2018-03- 2017-12- 2018-07- systèmes de sécurité et de IDA / 52240 A posteriori Limited 1,315.18 Achevé Supporting Project prix One Envelope 15 20 15 12 15 02 GPS et du service de Management tracking pour les autos CM-UGP-PFS-25892-NC- Laying the Foundations of RFQ / Confection et la a Safety Net System and Demande de Single Stage - 2017-09- 2017-11- 2018-02- 2017-12- 2018-04- pose des plaques IDA / 52240 A posteriori Open - National 7,636.09 Achevé Supporting Project prix One Envelope 30 10 08 01 09 signalétiques (7 plaques Management directionnelles + 3 panneaux) CM-UGP-PFS-25980-NC- Laying the Foundations of RFQ / Avenant au contrat a Safety Net System and Demande de Single Stage - 2017-09- 2016-09- 2017-09- 2016-10- 2018-09- IDA / 52240 A posteriori Limited 14,850.36 Signé de l'agence de gardiennage Supporting Project prix One Envelope 11 26 23 31 23 de l'antenne régionale du Management Nord CM-UGP-PFS-25981-NC- Laying the Foundations of RFQ / Avenant au contrat a Safety Net System and Demande de Single Stage - 2017-09- 2016-06- 2017-09- 2016-07- 2018-09- de l'agence de gardiennage IDA / 52240 A posteriori Limited 16,374.35 Signé Supporting Project prix One Envelope 11 24 23 28 23 de l'antenne régionale de Management l'Extrême Nord CM-UGP-PFS-25983-NC- RFQ / Avenant au contrat Laying the Foundations of d'assurance du personnel a Safety Net System and Demande de Single Stage - 2017-09- 2017-10- 2017-10- 2017-12- 2018-08- 2018-06- IDA / 52240 A posteriori Limited 24,386.04 Achevé en vu de la prise en Supporting Project prix One Envelope 15 19 16 20 12 08 compte du personnel Management nouvellement recruté CM-UGP-PFS-30748-NC- DIR / recrutement d'une agence de paiement Cash Transfer Program chargée d'assurer les Passation de with Accompanying 2017-10- 2018-01- 2017-10- 2017-11- 2017-11- 2018-02- 2018-11- transferts monétaires des IDA / 52240 A posteriori marché de gré Direct 30,643.76 Signé Measures to Boost 04 04 09 27 16 13 16 bénéficiaires de la phase 2 à gré Household Productivity des transferts monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-37510-NC- RFQ / avenant Lettre de Marché N°009/LM/MINEPAT/CTS/P Passation de FS/UGP/CAPM/2017 du 26 Public Works Program 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- 2018-05- IDA / 52240 A posteriori marché de gré Direct 22,354.79 Signé mai 2017 de l'agence de Pilot 18 04 25 08 15 13 15 à gré paiement pour la réalisation des paiements des 6000 bénéficiaires des THIMO 5 dont 3000 dans le Nord-Ouest et 3000 dans l'Est CM-UGP-PFS-37511-NC- RFQ / Avenant au contrat Laying the Foundations of d'assurance véhicule Passation de a Safety Net System and 2017-12- 2017-12- 2017-12- 2017-12- 2018-01- 2018-02- 2018-07- LETTRE DE MARCHE IDA / 52240 A posteriori marché de gré Direct 1,207.48 Signé Supporting Project 18 22 23 22 09 13 08 N°011/LM/MINEPAT/CTS/P à gré Management FS/UGP/CAPM/2017 DU 08 JUIN 2017 CM-UGP-PFS-25853-NC- DIR / Avenant au contrat de l'agence de paiement chargée des transferts monetaires du cycle 2 à Public Works Program Demande de Single Stage - 2017-09- 2018-01- 2017-11- 2018-02- 2018-05- l'Est, le Nord ouest, IDA / 52240 A posteriori Limited 22,232.85 Signé Pilot prix One Envelope 25 08 20 13 19 Douala et Yaoundé pour la phase 5 des THIMO dont 3000 dans la région de l'Est et 3000 dans la région du Nord Ouest CM-UGP-PFS-47580-NC- Cash Transfer Program RFQ / Fourniture de with Accompanying Demande de Single Stage - 2018-03- 2018-06- 2018-05- 2018-08- 2019-05- IDA / 52240 A posteriori Limited 14,785.79 Signé polices d'assurance autos Measures to Boost prix One Envelope 31 11 26 22 26 au projet Filets Sociaux Household Productivity CM-UGP-PFS-47582-NC- Cash Transfer Program RFQ / Confection et pause with Accompanying Demande de Single Stage - 2018-04- 2018-08- 2018-06- 2018-09- 2018-07- 2018-11- des plaques signalétiques IDA / 52240 A posteriori Limited 7,009.83 Achevé Measures to Boost prix One Envelope 30 23 11 12 11 23 des réalisations du Projet Household Productivity Filets Sociaux dans les communes CM-UGP-PFS-47593-NC- RFQ / Agence de paiement chargée d'assurer Cash Transfer Program le paiement des 3000 with Accompanying Demande de Single Stage - 2018-05- 2018-07- 2019-07- bénéficiaires de la phase 3 IDA / 52240 A posteriori Limited 0.00 Annulé Measures to Boost prix One Envelope 23 18 18 des transferts monétaires Household Productivity d'urgence du du Projet Filets Sociaux dans le Nord Ouest CM-UGP-PFS-47602-NC- DIR / Avenant au contrat de l'agence de paiement chargée d'assurer les paiement des transfert Passation de monétaires du cycle 2 Public Works Program 2018-06- 2018-06- 2018-07- 2018-07- 2018-09- 2019-01- 2019-02- IDA / 52240 A posteriori marché de gré Direct 10,227.50 Achevé dans le Nord et Pilot 21 26 20 31 12 27 26 à gré l'Adamaoua pour les paiements de 3000 bénéficiaire de la phase 6 des THIMO dans la région du Nord, communes de Dembo et Bashéo CM-UGP-PFS-25707-NC- Laying the Foundations of RFQ / Maintenance froid a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 0.00 Annulé et climatisation EN et Supporting Project prix One Envelope 09 07 07 NO pour 1 an Management CM-UGP-PFS-25610-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - 2017-10- 2017-10- 2018-10- IDA / 52240 A posteriori Limited 0.00 Annulé Autos et Motos de Supporting Project prix One Envelope 04 31 31 l'Extrême-Nord Management CM-UGP-PFS-25612-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - 2017-09- 2017-09- 2018-09- IDA / 52240 A posteriori Limited 0.00 Annulé Autos et Motos du Projet Supporting Project prix One Envelope 03 30 30 du Nord Management CM-UGP-PFS-25618-NC- Laying the Foundations of RFQ / Maintenance a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 0.00 Annulé matériel bureautique et Supporting Project prix One Envelope 07 03 03 informatique EN et NO Management pour 1 an CM-UGP-PFS-47255-NC- Cash Transfer Program RFQ / Production et with Accompanying Demande de Single Stage - 2018-03- 2018-02- 2018-04- 2018-03- 2018-04- 2018-03- multiplication des IDA / 52240 A posteriori Limited 7,132.71 Achevé Measures to Boost prix One Envelope 16 23 10 08 24 12 documents des Pratiques Household Productivity familiales essentielles CM-UGP-PFS-26101-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 0.00 Annulé Autos et Motos du Nord- Supporting Project prix One Envelope 11 13 13 Ouest Management CM-UGP-PFS-6311-NC- Laying the Foundations of RFQ / Fourniture de a Safety Net System and Demande de Single Stage - 2018-04- 2018-03- 2018-05- 2018-03- 2019-05- 2018-08- IDA / 52240 A posteriori Limited 3,228.19 Achevé police d'assurance pour 20 Supporting Project prix One Envelope 06 02 11 26 06 28 motos Management CM-UGP-PFS-26060-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2018-05- 2018-03- 2018-06- 2018-03- 2018-06- 2018-03- IDA / 52240 A posteriori Limited 1,867.92 Achevé Systèmes de sécurité pour Supporting Project prix One Envelope 01 05 01 26 22 29 les motos du projet (20) Management CM-UGP-PFS-37512-NC- RFQ / Avenant N°2 au contrat d'assurance du Cash Transfer Program personnel pour la prise en Passation de with Accompanying 2018-03- 2018-03- 2018-04- 2018-03- 2018-05- 2018-04- 2018-10- compte des relais IDA / 52240 A posteriori marché de gré Direct 34,099.31 Signé Measures to Boost 30 19 06 22 04 24 31 communautaires recrutés à gré Household Productivity dans le cadre de la sensibilisation sur les pratiques familiales essentielles CM-UGP-PFS-47572-NC- Cash Transfer Program RFB / Fourniture des with Accompanying Demande de Single Stage - 2018-05- 2018-06- 2018-07- 2018-10- 2019-07- IDA / 52240 A posteriori Limited 127,074.00 Signé polices d'assurance au Measures to Boost prix One Envelope 07 11 02 05 02 personnel du Projet Filets Household Productivity Sociaux Page 3 CM-UGP-PFS-72576-NC- RFQ / Multiplication de certains documents pour la collecte des données sur Laying the Foundations of les PFE de la phase pilote a Safety Net System and Demande de Single Stage - 2018-09- 2018-09- 2018-10- 2018-09- 2018-11- 2018-10- pour une période de 6 IDA / 52240 A posteriori Limited 7,116.25 Achevé Supporting Project prix One Envelope 16 05 28 27 11 01 mois et des questionnaires Management et autres documents pour la collecte des données dans le cadre de la première évaluation interne du Projet CM-UGP-PFS-92192-NC- RFQ / Multiplication de Cash Transfer Program certains documents de with Accompanying Demande de Single Stage - 2019-01- 2019-01- 2019-02- 2019-02- 2020-02- IDA / 52240 A posteriori Limited 5,551.26 Signé collecte de données des Measures to Boost prix One Envelope 15 17 26 04 26 PFE pour une période Household Productivity d'un an MOF-CM-UGP-PFS-6233- NC-RFQ / Recrutement Cash Transfer Program des agences de paiement with Accompanying Demande de Single Stage - 2017-02- 2017-03- 2017-05- 2017-05- 2019-10- pour le paiement de 19500 IDA / 52240 A posteriori Limited 142,058.17 Signé Measures to Boost prix One Envelope 27 08 01 26 28 menages beneficiaires du Household Productivity cycle 2 des transferts monetaires en 3 lots CM-UGP-PFS-121194-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2019-09- 2019-09- 2019-11- 2020-11- polices d'assurance pour IDA / 62230 A posteriori Limited 0.00 Annulé Supporting Project prix One Envelope 10 06 05 04 les autos du Projet Filets Management Sociaux CM-UGP-PFS-121367-NC- RFB / FOURNITURE D’UNE POLICE Laying the Foundations of D'ASSURANCE MALADIE a Safety Net System and Single Stage - 2019-08- 2019-10- 2019-09- 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2020-12- POUR UN AN EN IDA / 62230 A posteriori Appel d'offres Open - National 0.00 Annulé Supporting Project One Envelope 30 09 14 26 13 25 27 23 22 FAVEUR DU Management PERSONNEL DU PROJET FILETS SOCIAUX ET LEURS FAMILLES (2019- 2020) CM-UGP-PFS-152342-NC- RFQ / FOURNITURE DES Laying the Foundations of POLICES D'ASSURANCE a Safety Net System and Demande de Single Stage - En attente 2020-02- 2020-04- 2021-04- IDA / 62230 A posteriori Open - National 0.00 POUR SIX (06) Supporting Project prix One Envelope d'exécution 10 14 14 VEHICULES DU PROJET Management FILETS SOCIAUX CM-UGP-PFS-143142-NC- RFQ / Recrutement d'une agence de paiement pour le paiement des bénéficiaires de la phase Public Works Program Demande de Single Stage - En attente 2020-07- 2020-09- 2021-03- 7 des Travaux à Haute IDA / D2980 A posteriori Limited 0.00 Pilot prix One Envelope d'exécution 10 20 19 Intensité de Main d'œuvre du PFS dans la région de l'Est dont 1000 dans la commune de Ngoura, et 1000 dans la commune de Mandjou CM-UGP-PFS-143130-NC- RFQ / Recrutement d'une agence de paiement pour le transfert des paiements Public Works Program Demande de Single Stage - En attente 2020-07- 2020-09- 2021-03- aux 3000 bénéficiaires IDA / D2980 A posteriori Limited 0.00 Pilot prix One Envelope d'exécution 10 20 19 de la phase 7 des Travaux à Haute Intensité de Main d'œuvre dans la commune de Mokolo CM-UGP-PFS-143140-NC- RFQ / Recrutement d'une agence de paiement pour le paiement des bénéficiaires de la phase Public Works Program Demande de Single Stage - En attente 2020-07- 2020-09- 2021-03- 7 des Travaux à Haute IDA / D2980 A posteriori Limited 0.00 Pilot prix One Envelope d'exécution 10 26 25 Intensité de Main d'œuvre du PFS dont 1000 dans la commune de Dir région de l'Adamaoua et 4000 dans la commune deTouboro, région du Nord CM-UGP-PFS-172015-NC- RFQ / Recrutement des Public Works Program Demande de Single Stage - En attente 2020-07- 2020-09- 2021-09- agences de paiement pour IDA / D2980 A posteriori Limited 0.00 Pilot prix One Envelope d'exécution 05 09 09 la phase 7 des THIMO en 3 lots distincts CM-UGP-PFS-172057-NC- Laying the Foundations of RFQ / Confection et pause a Safety Net System and Demande de Single Stage - En attente 2021-01- 2021-02- 2021-08- IDA / 62230 A posteriori Limited 0.00 des plaques signalitiques Supporting Project prix One Envelope d'exécution 09 27 26 du Projet Filets Sociaux Management CM-UGP-PFS-172111-NC- RFB / Fourniture d'une Laying the Foundations of police d'assurance maladie a Safety Net System and Single Stage - En attente 2020-06- 2020-06- 2020-07- 2020-08- 2020-10- 2021-10- IDA / 62230 A posteriori Appel d'offres Open - National 0.00 pour un an en faveur du Supporting Project One Envelope d'exécution 01 16 28 27 01 01 personnel du Projet Filets Management Sociaux et leur famille CM-UGP-PFS-172112-NC- Laying the Foundations of RFQ / Fourniture d'une a Safety Net System and Demande de Single Stage - En attente 2020-07- 2020-09- 2021-09- police d'assurance pour 60 IDA / 62230 A posteriori Limited 0.00 Supporting Project prix One Envelope d'exécution 05 05 05 motos du Projet Filets Management Sociaux CM-UGP-PFS-175637-NC- DIR / Agence de paiement des 6000 bénéficiaires du Cycle 3 des transferts Monétaires Ordinaires, des Cash Transfer Program Passation de 2000 de la phase 3 des with Accompanying En attente 2020-06- 2020-07- 2020-08- 2022-09- IDA / D2980 A posteriori marché de gré Direct 0.00 Transferts Monétaires Measures to Boost d'exécution 30 05 23 02 à gré d’Urgence et des 3000 Household Productivity de la phase 7 des THIMO dans les Régions de l’Adamaoua et de l’Est en 3 lots distinct CM-UGP-PFS-175721-NC- DIR / Agence de paiement des bénéficiaires du Cycle 3 des transferts Cash Transfer Program Monétaires Ordinaires, de Passation de with Accompanying En attente 2020-06- 2020-07- 2020-08- 2022-09- la phase 3 des Transferts IDA / 62230 A posteriori marché de gré Direct 0.00 Measures to Boost d'exécution 30 05 23 02 Monétaires d’Urgence, de à gré Household Productivity la phase 7 des Travaux à Haute Intensité de Main d'œuvre, Régions de l’Extrême Nord et du Nord CM-UGP-PFS-175722-NC- DIR / Agence de Paiement des bénéficiaires du cycle 3 des Transferts Monétaires Ordinaires Cash Transfer Program Passation de dans la Région du Sud, with Accompanying En attente 2020-06- 2020-07- 2020-08- 2022-09- IDA / 62230 A posteriori marché de gré Direct 0.00 Communes d'Ebolawa 2 Measures to Boost d'exécution 30 05 23 02 à gré (1000), Meyomessala (1000) Household Productivity Ma’an (1000) et dans les ville de Douala et yaoundé communes de Douala 5 (1500),Yaoundé 3 (1500), CM-UGP-PFS-175723-NC- DIR / Agence de Paiement des bénéficiaires de la Cash Transfer Program Passation de phase 3 des Transferts with Accompanying 2020-06- 2020-07- 2020-08- 2022-09- IDA / 62230 A posteriori marché de gré Direct 0.00 Annulé Monétaires d’Urgence dans Measures to Boost 30 05 23 02 à gré la Région du Sud-Ouest, Household Productivity Communes de Limbe1 (500), Limbe 2 (500) Limbe 3 (500) CM-UGP-PFS-175725-NC- DIR / Agence de Paiement des bénéficiaires de la Cash Transfer Program phase 3 des Transferts Passation de with Accompanying 2020-06- 2020-07- 2020-08- 2022-09- Monétaires d’Urgence dans IDA / 62230 A posteriori marché de gré Direct 0.00 Annulé Measures to Boost 30 05 23 02 la Région du Nord-Ouest, à gré Household Productivity Communes de Bamenda 1 (500), Bamenda 2 (500) Bamenda 3 (1000) CM-UGP-PFS-172073-NC- Laying the Foundations of RFB / Impression et a Safety Net System and Single Stage - En attente 2020-07- 2020-08- 2020-09- 2020-10- 2020-11- 2021-11- reprographie des IDA / 62230 A posteriori Appel d'offres Open - National 0.00 Supporting Project One Envelope d'exécution 30 04 15 15 19 19 documents pour le Projet Management Filets Sociaux CONSULTING FIRMS Activity Reference No. Short List and Opening of Combined Loan / Market Contract Type Actual Process Expression of Request for Evaluation of Contract / Description Component Review Type Method Terms of Reference Draft Request for Technical Proposals Evaluation Report Signed Contract Credit No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal Completion Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual CM-UGP-PFS-6358-CS- CQS / ONG pour THIMO: 7000 bénéficiaires dans 2 communes de l'Extrême Sélection fondée Nord, 2 communes de Public Works Program sur les 2016-10- 2017-02- 2017-04- 2017-02- 2017-05- 2017-03- 2017-06- 2018-03- 2017-12- 2018-04- IDA / 52240 A posteriori Open - National 367,605.09 Achevé 2017-02-07 l'Est pour la phase 3 et Pilot qualifications 07 28 13 22 13 03 17 23 14 10 6000 bénéficiaires: 2 des consultants communes Adamaoua, 1 commune Nord pour la phase 4 en 2017 (1 ONG par région) Page 4 CM-UGP-PFS-54735-CS- CQS / Consultant pour le Cash Transfer Program Sélection fondée développement d'un with Accompanying sur les 2018-06- 2018-06- 2018-10- 2018-08- 2019-01- 2018-09- 2019-03- 2018-10- 2019-04- 2019-04- IDA / 52240 A posteriori Open - National 135,528.54 Signé 2018-05-30 progiciel de gestion intégré Measures to Boost qualifications 11 20 26 03 23 02 22 07 15 05 pour le système Household Productivity des consultants d'information du Projet Filets Sociaux CM-UGP-PFS-172238-CS- QCBS / Recrutement d'un Laying the Foundations of cabinet pour l'audit Sélection fondée a Safety Net System and En attente 2020-09- 2020-11- 2020-11- 2020-12- 2021-02- 2021-03- 2022-03- externe du Projet Filets IDA / 62230 A posteriori sur la qualité Open - National 0.00 2020-08-28 Supporting Project d'exécution 18 01 29 29 05 12 12 Sociaux, financement et le coût Management additionnel , exercices 2019-2020 (18 mois) , 2021 CM-UGP-PFS-175920-CS- CQS / Recrutement d'une ONG pour la mise en œuvre des activités de la Sélection fondée Phase 8 des THIMO Public Works Program sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- dans les régions du Nord IDA / 62230 A posteriori Open - National 0.00 2020-12-30 Pilot qualifications d'exécution 20 05 04 09 05 Ouest, Commune de Santa des consultants (2000 bénéficiaires) et du Sud-Ouest, Communes de Buéa (1000 bénéficiaires) et de Limbé II (1500 bénéficiaires) INDIVIDUAL CONSULTANTS Activity Reference No. Invitation to Loan / Market Actual Process Draft Negotiated Contract / Description Component Review Type Method Contract Type Teams of Reference Identified/Selected Signed Contract Credit No. Approach Amount (US$) Status Contract Completion Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6328-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2016-12- 2017-03- 2017-04- 2017-05- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 10,372.40 Signé 2017-02-06 Measures to Boost 20 27 17 19 22 19 16 à Blangoua du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6334-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-03- 2017-04- 2017-01- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 10,368.36 Signé 2017-02-06 Measures to Boost 15 27 17 13 22 19 16 à Goulfey du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6337-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-03- 2017-04- 2017-06- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 12,422.62 Signé 2017-02-06 Measures to Boost 15 27 17 13 22 19 21 à Makari du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6339-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-03- 2017-04- 2017-05- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 10,372.40 Signé 2017-02-06 Measures to Boost 17 27 17 19 22 19 16 à GOBO du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6340-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-03- 2017-04- 2017-05- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 10,379.07 Signé 2017-02-06 Measures to Boost 15 27 17 16 22 19 16 à BOURRHA du cycle 2 Household Productivity des transferts monetaires CM-UGP-PFS-6341-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-03- 2017-04- 2017-05- 2017-05- 2017-01- 2017-06- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 10,379.07 Signé 2017-02-06 Measures to Boost 15 27 17 16 22 19 16 à Koza du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6342-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-05- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 10,372.40 Signé 2017-02-06 Measures to Boost 16 13 14 18 24 19 21 à Mogodé du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6344-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-05- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 11,613.54 Signé 2017-02-06 Measures to Boost 15 13 14 17 24 26 26 à Banyo du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6346-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-06- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 10,381.76 Signé 2017-02-06 Measures to Boost 29 13 14 28 24 19 21 à Tcheboa du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6347-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 9,829.76 Signé 2017-02-06 Measures to Boost 15 13 14 24 26 21 à Mayo Oulo du cycle 2 Household Productivity des transferts monetaires CM-UGP-PFS-6348-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-05- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 9,707.50 Signé 2017-02-06 Measures to Boost 16 24 26 24 28 26 25 à Rey Bouba du cycle 2 Household Productivity des transferts monetaires CM-UGP-PFS-6349-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-05- 2017-02- 2017-01- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 9,716.26 Signé 2017-02-06 Measures to Boost 22 09 10 26 12 26 09 à Touboro du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6350-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2016-12- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 11,772.77 Signé 2017-02-06 Measures to Boost 20 18 28 04 14 29 à Kette du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6351-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-05- 2017-03- 2017-03- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 9,713.75 Signé 2017-02-06 Measures to Boost 15 18 28 17 04 14 29 à Belo du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6352-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-05- 2017-03- 2017-03- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 9,703.73 Signé 2017-02-06 Measures to Boost 15 18 28 16 04 14 29 à Menchum Valley du Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6353-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2016-12- 2017-02- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- 2017-08- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 9,020.07 Achevé 2017-02-06 Measures to Boost 20 18 23 28 10 04 14 29 01 à Douala 3 du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6354-CS- Cash Transfer Program INDV / Consultant pour le with Accompanying 2017-05- 2017-02- 2017-02- 2017-05- 2017-03- 2017-03- 2017-03- ciblage et l'enregistrement IDA / 52240 A posteriori Individuel Open 9,264.24 Signé 2017-02-06 Measures to Boost 17 18 28 24 04 14 29 à Yaoundé du cycle 2 des Household Productivity transferts monetaires CM-UGP-PFS-6355-CS- INDV / Consultant chargé d'améliorer les modules du volet économique notamment formation en Cash Transfer Program AGR ( agriculture, petit with Accompanying 2016-12- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- 2017-04- 2018-09- IDA / 52240 A posteriori Individuel Open 22,361.04 Achevé 2017-02-10 commerce, gestion de Measures to Boost 15 25 09 02 21 12 21 17 24 l'argent, élevage) et former Household Productivity les bénéficiaires dans ces modules à l'Extrême Nord dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6356-CS- INDV / Consultant chargé d'améliorer les modules du volet économique : Cash Transfer Program formation en AGR ( with Accompanying 2016-12- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- 2017-04- 2018-09- agriculture,petit commerce, IDA / 52240 A posteriori Individuel Open 24,278.93 Achevé 2017-02-10 Measures to Boost 15 25 09 02 21 12 21 17 21 gestion de l'argent, Household Productivity élevage) et former les bénéficiaires dans ces modules dans le Nord et l'Adamaoua dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6357-CS- INDV / Consultant chargé d'améliorer les modules du volet économique : formation en AGR ( Cash Transfer Program agriculture,petit commerce, with Accompanying 2016-12- 2017-02- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- 2017-04- 2018-10- IDA / 52240 A posteriori Individuel Open 26,919.25 Achevé 2017-02-10 gestion de l'argent, Measures to Boost 15 25 09 02 21 12 21 17 25 élevage) et former les Household Productivity bénéficiaires dans ces modules dans le Nord O, Est, Dla, Ydé dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6421-CS- Public Works Program 2017-07- 2017-04- 2017-03- 2017-04- 2017-06- 2017-11- INDV / Expert IDA / 52240 A priori Individuel Open 0.00 Annulé 2017-02-17 Pilot 13 07 29 28 02 29 environnemental et social du PFS Laying the Foundations of CM-UGP-PFS-6423-CS- a Safety Net System and 2017-07- 2017-03- 2017-05- 2017-04- 2017-05- 2017-06- INDV / Assistant IDA / 52240 A priori Individuel Open 0.00 Annulé 2017-02-07 Supporting Project 13 28 09 18 23 28 Comptable Management Page 5 Laying the Foundations of CM-UGP-PFS-6424-CS- a Safety Net System and 2017-07- 2017-03- 2017-03- 2017-04- 2017-05- 2017-06- IDA / 52240 A priori Individuel Open 0.00 Annulé 2017-02-07 INDV / Assistant SPM Supporting Project 13 28 21 18 23 28 Management CM-UGP-PFS-6327-CS- Cash Transfer Program Sélection de CDS / protocole d'accord with Accompanying 2017-02- 2017-03- 2017-09- IDA / 52240 A priori consultants par Direct 0.00 Annulé 2017-02-06 avec l'INS pour le Measures to Boost 16 03 29 entente directe dénombrement et l'enquête Household Productivity PMT du cycle 2 CM-UGP-PFS-14406-CS- INDV / Opérateur Terrain Cash Transfer Program commune Mayo Moskota with Accompanying 2017-06- 2017-06- 2017-10- 2017-06- 2017-10- 2017-06- 2017-10- 2019-06- IDA / 52240 A posteriori Individuel Open 7,006.15 Signé 2017-05-19 (Extrême Nord) pour les Measures to Boost 26 04 23 11 27 21 31 21 transferts monetaires Household Productivity d'urgence CM-UGP-PFS-14407-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2015-01- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2019-05- IDA / 52240 A posteriori Individuel Open 55,333.37 Signé 2017-05-08 contrat de l'Assistante du Supporting Project 09 09 05 10 13 10 09 10 Coordonnateur du Projet Management CM-UGP-PFS-14409-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2015-01- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2019-05- contrat de la Secrétaire IDA / 52240 A posteriori Individuel Open 44,266.70 Signé 2017-05-05 Supporting Project 09 06 05 07 14 07 09 07 de l'Unité de Gestion du Management Projet CM-UGP-PFS-14410-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2015-01- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2019-05- contrat Chauffeur 1 de IDA / 52240 A posteriori Individuel Open 38,438.87 Signé 2017-05-05 Supporting Project 09 06 05 07 09 07 09 07 l'Unité de Gestion du Management Projet CM-UGP-PFS-14411-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2015-06- 2017-05- 2015-05- 2017-05- 2017-06- 2017-05- 2017-06- 2019-05- IDA / 52240 A posteriori Individuel Open 38,438.87 Signé 2017-05-05 contrat Chauffeur 2 Supporting Project 09 06 05 07 09 07 09 07 Unité de Gestion du Management Projet CM-UGP-PFS-14412-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2015-01- 2017-05- 2017-05- 2017-05- 2017-05- 2017-05- 2017-06- 2019-05- contrat de l'Agent de IDA / 52240 A posteriori Individuel Open 32,191.68 Signé 2017-05-05 Supporting Project 09 06 05 07 31 07 09 07 liaison de l'Unité de Management Gestion du Projet CM-UGP-PFS-14463-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 0.00 Annulé 2017-06-09 contrat de l'operateur de Supporting Project 12 13 15 15 terrain de Yaoundé 7 Management CM-UGP-PFS-14460-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-12- IDA / 52240 A posteriori Individuel Open 0.00 Annulé 2017-06-09 contrat de l'opératrice de Supporting Project 12 13 15 12 terrain de la commune de Management Douala 2 CM-UGP-PFS-14490-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 0.00 Annulé 2017-06-15 contrat de Technicienne de Supporting Project 23 25 29 29 surface de l'UGP Management CM-UGP-PFS-14454-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-10- 2017-06- 2017-06- 2015-06- 2017-06- 2015-06- 2019-06- IDA / 52240 A posteriori Individuel Open 34,575.36 Résilié 2017-06-09 contrat du point focal de Supporting Project 27 12 13 15 15 17 15 la ville de Douala Management CM-UGP-PFS-16811-CS- Laying the Foundations of INDV / renouvellement de a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- contrat opérateur de IDA / 52240 A posteriori Individuel Direct 25,629.07 Signé 2017-06-09 Supporting Project 11 07 12 09 13 09 03 terrain 1 commune de Management MOKOLO CM-UGP-PFS-16814-CS- Laying the Foundations of INDV / renouvellement a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- contrat opérateur de IDA / 52240 A posteriori Individuel Direct 23,513.04 Signé 2017-06-09 Supporting Project 12 07 13 09 14 09 04 terrain 2 commune de Management MOKOLO CM-UGP-PFS-16821-CS- Laying the Foundations of INDV / Renouvellement de a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- contrat de l'opérateur de IDA / 52240 A posteriori Individuel Direct 23,513.04 Signé 2017-06-09 Supporting Project 12 07 13 09 15 09 05 terrain de la commune de Management MAGA CM-UGP-PFS-16823-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-12- contrat de l'opérateur de IDA / 52240 A posteriori Individuel Direct 22,483.20 Signé 2017-06-09 Supporting Project 10 07 11 09 12 09 09 terrain de la commune de Management Kar Hay Laying the Foundations of CM-UGP-PFS-16925-CS- a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- INDV / Avenant au IDA / 52240 A priori Individuel Open 0.00 Annulé 2017-06-12 Supporting Project 15 19 21 11 contrat du SPM du Projet Management Laying the Foundations of CM-UGP-PFS-14451-CS- a Safety Net System and 2017-07- 2017-06- 2017-06- 2017-06- 2019-06- INDV / Renouvellement du IDA / 52240 A priori Individuel Open 0.00 Annulé 2017-06-09 Supporting Project 19 10 14 15 15 contrat Comptable Management CM-UGP-PFS-14446-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-07- 2017-06- 2017-06- 2017-06- 2019-06- contrat de l'Expert IDA / 52240 A priori Individuel Open 0.00 Annulé 2017-06-09 Supporting Project 19 09 10 15 15 Informatique et Management Responsable SIG du Projet CM-UGP-PFS-14452-CS- Laying the Foundations of INDV / Renouvellement du a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A priori Individuel Direct 0.00 Annulé 2017-06-09 contrat du Responsable Supporting Project 12 13 13 15 15 Régional Extrême Nord Management CM-UGP-PFS-25501-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and 2017-08- 2017-09- 2017-10- 2017-10- 2017-11- 2017-10- 2017-11- 2018-10- responsable régional du IDA / 52240 A posteriori Individuel Open 46,457.14 Signé 2017-08-31 Supporting Project 17 26 25 03 06 13 03 13 Nord ouest du projet Management Filets Sociaux CM-UGP-PFS-25504-CS- Laying the Foundations of INDV / Consultant chargé a Safety Net System and 2017-09- 2017-09- 2017-10- 2017-10- 2017-11- 2017-10- 2017-11- 2018-04- de la Conception et l' IDA / 52240 A posteriori Individuel Open 80,692.20 Signé 2017-09-01 Supporting Project 06 29 02 06 03 16 03 19 appui à la mise en œuvre Management du plan de communication CM-UGP-PFS-25520-CS- INDV / Recrutement de 4 consultants pour le ciblage des bénéficiaires de la phase 2 des transferts Laying the Foundations of monetaires d'urgence dans a Safety Net System and 2017-10- 2017-10- 2017-12- 2017-10- 2017-12- 2017-10- 2017-12- 2017-11- 2018-09- IDA / 52240 A posteriori Individuel Open 30,128.36 Achevé 2017-09-07 les département du Logone Supporting Project 05 12 05 19 11 27 12 16 17 et Chari (Communes de Management Blangoua, Goulfey, Makari) et dans le département du Mayo Tsanaga(commune de Mayo Moskota CM-UGP-PFS-25782-CS- Laying the Foundations of INDV / Avenant N°01 au a Safety Net System and 2014-10- 2017-09- 2017-06- 2017-09- 2017-06- 2017-09- 2017-08- 2018-09- contrat de l'Expert IDA / 52240 A posteriori Individuel Open 157,236.52 Signé 2017-09-06 Supporting Project 10 09 13 10 15 11 17 11 informatique et Management responsable SIG UGP CM-UGP-PFS-25786-CS- Laying the Foundations of INDV / Avenant N°02 au a Safety Net System and 2013-05- 2017-09- 2017-06- 2017-09- 2017-06- 2017-09- 2017-08- 2018-09- contrat du Spécialiste en IDA / 52240 A posteriori Individuel Open 71,473.92 Signé 2017-09-06 Supporting Project 29 09 19 10 22 11 17 11 passation des Marchés de Management l'UGP CM-UGP-PFS-25787-CS- Laying the Foundations of INDV / Avenant N°1 au a Safety Net System and 2014-10- 2017-09- 2017-06- 2017-09- 2017-06- 2017-09- 2017-08- 2018-09- IDA / 52240 A posteriori Individuel Open 134,620.67 Signé 2017-09-06 contrat du Comptable de Supporting Project 14 09 13 10 15 11 17 11 l'UGP Management CM-UGP-PFS-25794-CS- INDV / Avenant N°1 au Laying the Foundations of contrat du Responsable a Safety Net System and 2015-04- 2017-09- 2017-06- 2017-09- 2017-06- 2017-09- 2017-08- 2018-09- IDA / 52240 A posteriori Individuel Open 86,985.26 Signé 2017-09-06 régional du Projet Filets Supporting Project 14 09 13 10 16 11 17 11 Sociaux dans l'Extrême Management Nord CM-UGP-PFS-25517-CS- INDV / Consultant chargé de la sensibilisation des Cash Transfer Program bénéficiaires du Cycle 2 with Accompanying 2017-09- 2017-10- 2017-10- 2017-10- 2017-11- 2017-10- 2017-11- 2018-02- IDA / 52240 A posteriori Individuel Open 43,182.70 Signé 2017-09-07 (i) à l'Extrême Nord, (ii) Measures to Boost 06 12 25 19 01 27 01 24 au Nord et à l'Adamaoua, Household Productivity (iii) à l'Est, au Nord-ouest, à Douala et à Yaoundé CM-UGP-PFS-6326-CS- Cash Transfer Program Sélection de CDS / Protocole d'accord with Accompanying 2017-09- 2017-08- 2017-09- 2017-09- 2018-05- IDA / 52240 A priori consultants par Direct 391,776.36 Signé 2017-08-31 avec l'INS pour la Measures to Boost 05 31 16 28 14 entente directe réalisation de l'enquête de Household Productivity base CM-UGP-PFS-25509-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2017-10- 2017-12- 2017-11- 2018-01- 2017-11- 2018-01- 2017-12- 2019-01- dans la commune de IDA / 52240 A posteriori Individuel Open 49,307.71 Signé 2017-11-30 Measures to Boost 13 30 20 06 24 14 07 14 Koza, département du Household Productivity Mayo Tsanaga, Région de l'Extrême Nord Page 6 CM-UGP-PFS-25508-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2017-10- 2018-01- 2017-11- 2018-02- 2017-11- 2018-02- 2017-12- 2019-02- dans la commune de IDA / 52240 A posteriori Individuel Open 46,287.84 Signé 2017-12-30 Measures to Boost 13 29 24 03 27 11 05 11 Bourrha, département du Household Productivity Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25512-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2017-10- 2017-12- 2017-11- 2018-01- 2017-11- 2018-01- 2017-12- 2019-01- dans la commune de IDA / 52240 A posteriori Individuel Open 69,189.81 Signé 2017-11-30 Measures to Boost 13 30 08 06 22 14 05 14 Mogode, département du Household Productivity Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25515-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2017-10- 2018-01- 2017-11- 2018-01- 2017-11- 2018-01- 2017-12- 2019-01- IDA / 52240 A posteriori Individuel Open 50,528.89 Signé 2017-11-30 dans la commune de Mayo- Measures to Boost 13 02 24 09 28 17 05 17 Oulo, département du Household Productivity Mayo Louti, Région du Nord CM-UGP-PFS-25516-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2017-10- 2018-01- 2017-12- 2018-01- 2017-12- 2018-01- 2017-12- 2019-01- IDA / 52240 A posteriori Individuel Open 68,555.87 Signé 2017-11-30 dans la commune de Measures to Boost 13 04 04 11 04 19 05 19 Tcheboa, département de Household Productivity la Bénoué, Région du Nord CM-UGP-PFS-37431-CS- Laying the Foundations of INDV / Chauffeur de a Safety Net System and 2018-01- 2018-01- 2018-02- 2018-01- 2018-03- 2018-01- 2018-03- 2019-01- IDA / 52240 A posteriori Individuel Open 10,274.36 Signé 2017-12-27 l'antenne régionale du Supporting Project 11 20 28 22 06 29 06 29 Projet du Nord- Ouest Management CM-UGP-PFS-37432-CS- Laying the Foundations of INDV / Secrétaire de a Safety Net System and 2018-01- 2018-01- 2018-02- 2018-01- 2018-03- 2018-02- 2018-03- 2019-02- IDA / 52240 A posteriori Individuel Open 15,722.34 Signé 2017-12-28 l'antenne régionale du Supporting Project 11 23 28 28 06 04 06 04 Projet du Nord Ouest Management CM-UGP-PFS-37434-CS- Laying the Foundations of INDV / Point focal du a Safety Net System and 2018-01- 2017-12- 2018-02- 2017-12- 2018-03- 2017-12- 2018-03- 2018-12- IDA / 52240 A posteriori Individuel Open 14,584.42 Signé 2017-11-30 Projet de la ville de Supporting Project 11 22 28 26 29 28 29 28 Douala Management CM-UGP-PFS-25972-CS- CQS / Avenant au contrat N°001/MINEPAT/CTS/PFS/ CAPM/2017 du 23 mars 2017 de l'ONG chargée de Sélection de la mise en œuvre des Public Works Program 2017-12- 2017-12- 2017-12- 2018-01- 2018-02- 2018-07- IDA / 52240 A posteriori consultants par Direct 93,748.34 Signé 2017-12-18 THIMO 3 dans l'Extrême Pilot 21 25 22 18 13 17 entente directe Nord avec 4000 bénéficiaires pour la mise en œuvre des THIMO 5 avec 3000 bénéficiaires dans la région du Nord- ouest CM-UGP-PFS-25907-CS- CQS / Avenant au contrat N°002/MINEPAT/CTS/PFS/ CAPM/2017 du 23 mars 2017 de l'ONG chargée de Sélection de la mise en œuvre des Public Works Program 2017-12- 2017-12- 2017-12- 2018-01- 2018-02- 2018-07- 2018-07- IDA / 52240 A posteriori consultants par Direct 92,937.44 Achevé 2017-12-18 THIMO 3 dans la région Pilot 21 25 22 18 13 17 27 entente directe de l'Est avec 3000 bénéficiaires pour la mise en œuvre des THIMO 5 avec 3000 bénéficiaires dans la région de l'Est CM-UGP-PFS-47367-CS- INDV / Consultant individuel chargé Public Works Program 2018-04- 2018-04- 2018-04- 2018-05- IDA / 52240 A posteriori Individuel Limited 0.00 Annulé 2018-03-30 d'actualiser la carte des Pilot 04 18 28 28 THIMO du Projet Filets Sociaux CM-UGP-PFS-47368-CS- INDV / Consultants Cash Transfer Program individuels (3) chargés du with Accompanying 2018-05- 2018-05- 2018-06- 2018-07- ciblage des bénéficiaires de IDA / 52240 A posteriori Individuel Open 0.00 Annulé 2018-04-06 Measures to Boost 09 23 02 17 la phase 3 des transferts Household Productivity monétaires d'urgence dans la région du Nord Ouest CM-UGP-PFS-47363-CS- INDV / Consultants individuels (03) chargés de Cash Transfer Program compléter et d'améliorer with Accompanying 2018-02- 2018-04- 2018-04- 2018-04- 2018-04- 2018-05- 2018-04- 2019-05- les manuels de formation IDA / 52240 A posteriori Individuel Open 87,765.09 Signé 2018-03-09 Measures to Boost 02 14 06 28 13 12 18 12 et de former les Household Productivity bénéficiaires sur les AGR pour le cycle 2 des transferts monétaires du Projet Filets CM-UGP-PFS-47362-CS- Cash Transfer Program INDV / Consultant with Accompanying 2018-05- 2018-04- 2018-05- 2018-04- 2018-06- 2018-04- 2018-06- 2019-04- individuel chargé de la IDA / 52240 A posteriori Individuel Open 7,158.24 Signé 2018-03-15 Measures to Boost 15 17 23 24 01 30 01 30 traduction des documents Household Productivity du projet en anglais CM-UGP-PFS-25526-CS- INDV / Consultant chargé Laying the Foundations of de l'accompagnement en a Safety Net System and 2018-10- 2017-10- 2017-10- 2017-10- 2018-10- IDA / 52240 A posteriori Individuel Open 0.00 Annulé 2017-09-15 TOM2PRO, TOM2PAIE, Supporting Project 30 11 16 24 24 TOM2MONITORING et Management TOM2MARCHE CM-UGP-PFS-25881-CS- Laying the Foundations of INDV / Consultant chargé a Safety Net System and 2018-08- 2018-05- 2018-09- 2018-05- 2018-09- 2018-06- 2018-09- 2018-12- 2019-02- IDA / 52240 A posteriori Individuel Open 7,201.62 Achevé 2018-04-17 du développement du site Supporting Project 08 13 10 20 12 17 13 14 15 WEB Management CM-UGP-PFS-16899-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2014-10- 2017-10- 2017-10- 2017-09- 2017-10- 2017-11- 2019-10- IDA / 52240 A posteriori Individuel Open 71.57 Signé 2017-10-02 contrat de l'auditeur Supporting Project 14 13 18 08 23 01 13 interne Management Cash Transfer Program CM-UGP-PFS-47928-CS- with Accompanying 2018-06- 2018-05- 2018-11- 2018-06- 2018-11- 2018-07- 2019-01- 2019-07- INDV / Assistant au suivi IDA / 52240 A posteriori Individuel Open 10,966.15 Signé 2018-04-20 Measures to Boost 22 30 12 13 20 04 03 04 évaluation Household Productivity CM-UGP-PFS-47923-CS- Cash Transfer Program INDV / Recrutement d'un with Accompanying 2018-03- 2018-05- 2018-10- 2018-05- 2018-10- 2018-06- 2018-10- 2019-06- IDA / 52240 A posteriori Individuel Open 26,092.28 Signé 2018-04-04 Spécialiste en Passation Measures to Boost 26 07 01 21 10 18 11 18 des Marché Assistant Household Productivity CM-UGP-PFS-54610-CS- INDV / consultant Cash Transfer Program individuel pour l'assistance with Accompanying 2018-03- 2018-04- 2018-05- 2018-06- 2018-12- à la migration comptable IDA / 52240 A posteriori Individuel Limited 0.00 Annulé 2018-04-16 Measures to Boost 26 21 12 16 13 vers le nouveau référentiel Household Productivity comptable SYSCOHADA révisé CM-UGP-PFS-54615-CS- INDV / consultant pour Cash Transfer Program assister l'UGP à with Accompanying 2018-10- 2018-04- 2018-11- 2018-05- 2018-12- 2018-06- 2018-12- 2019-06- IDA / 52240 A posteriori Individuel Limited 10,408.76 Signé 2018-04-20 l'utilisation optimale des Measures to Boost 30 25 19 16 06 20 07 20 logiciels TOM2PRO, Household Productivity TOM2PAIE et TOM2MARCHE CM-UGP-PFS-54616-CS- INDV / Consultant pour la conception du masque Cash Transfer Program de saisie, la supervision with Accompanying 2018-08- 2018-04- 2018-08- 2018-05- 2018-09- 2018-06- 2018-09- 2018-12- IDA / 52240 A posteriori Individuel Limited 7,097.50 Signé 2018-04-25 de la saisie et l'analyse Measures to Boost 07 30 14 21 10 25 11 22 des données de la Household Productivity première évaluation interne du Projet IDA CM-UGP-PFS-47366-CS- INDV / Consultant Cash Transfer Program individuel chargé with Accompanying 2018-05- 2018-05- 2018-05- 2018-06- d'actualiser la carte de IDA / 52240 A posteriori Individuel Limited 0.00 Annulé 2018-04-30 Measures to Boost 05 19 29 28 pauvreté pour les Household Productivity transferts monétaires du Projet Filets Sociaux CM-UGP-PFS-47370-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat du point focal du with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 3,181.63 Signé 2018-04-20 Projet dans le Measures to Boost 11 27 28 03 28 30 entente directe Département du Mberé, Household Productivity région de l'Adamaoua CM-UGP-PFS-25974-CS- CQS / Contrat ONG pour Sélection de la phase 6 des THIMO Public Works Program 2018-07- 2018-06- 2018-07- 2018-07- 2018-09- 2019-01- 2019-02- IDA / 52240 A posteriori consultants par Direct 85,366.88 Achevé 2018-05-30 pour 3000 bénéficiaires Pilot 02 09 20 30 19 26 09 entente directe dans 2 communes de la région du Nord CM-UGP-PFS-47376-CS- INDV / Avenant au contrat de l'opérateur de Cash Transfer Program Sélection de terrain de la commune de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,169.08 Signé 2018-04-24 la commune de la Measures to Boost 11 28 28 04 28 31 entente directe commune de kai kai Household Productivity département du Mayo Danay, région de l'extrême Nord Page 7 CM-UGP-PFS-47377-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat de l'opérateur de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 terrain de la commune de Measures to Boost 11 28 28 04 28 31 entente directe Méri, département du Household Productivity Diamaré, région de l'Extrême Nord CM-UGP-PFS-47378-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- terrain de la commune de IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 Measures to Boost 11 28 28 04 28 31 Ndoukoula, département entente directe Household Productivity du Diamaré, région de l'Extrême Nord CM-UGP-PFS-47379-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat de l'opérateur de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,169.08 Signé 2018-04-24 terrain de la commune de Measures to Boost 11 28 28 04 28 31 entente directe Guider, département du Household Productivity Mayo Louti, région du Nord CM-UGP-PFS-47430-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat de l'opérateur de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 terrain de la commune de Measures to Boost 11 28 28 04 28 31 entente directe Lagdo, département de la Household Productivity Bénoué, région du Nord CM-UGP-PFS-47431-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- terrain N° 1 de la IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 Measures to Boost 11 28 28 04 28 31 commune de Bibemi entente directe Household Productivity (ADAMOU Bienvenu), département de la Bénoué, région du Nord CM-UGP-PFS-47432-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- terrain N° 2 de la IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 Measures to Boost 11 28 28 04 28 31 commune de Bibemi entente directe Household Productivity (GOUDOUM GRANA Dieunedort), département de la Bénoué, région du Nord CM-UGP-PFS-47433-CS- INDV / Avenant au contrat de l'opérateur de Cash Transfer Program terrain de la commune de Sélection de with Accompanying 2018-02- 2018-04- 2018-01- 2018-04- 2018-02- 2019-04- Kar Hay pour la commune IDA / 52240 A posteriori consultants par Direct 8,495.18 Signé 2018-04-18 Measures to Boost 23 22 23 28 28 28 de Makary dans le entente directe Household Productivity département du Logone et Chari, région de l'Extrême Nord CM-UGP-PFS-47434-CS- Cash Transfer Program INDV / Avenant au Sélection de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2019-12- contrat de la secrétaire de IDA / 52240 A posteriori consultants par Direct 15,497.59 Signé 2018-04-24 Measures to Boost 11 28 28 04 28 30 l'antenne régionale de entente directe Household Productivity l'Extrême Nord CM-UGP-PFS-47435-CS- Cash Transfer Program INDV / Avenant au with Accompanying 2018-03- 2018-07- 2018-03- 2018-07- 2018-03- 2018-07- 2019-12- IDA / 52240 A posteriori Individuel Direct 7,980.91 Signé 2018-03-05 contrat du chauffeur de Measures to Boost 12 02 17 04 25 04 15 l'antenne régionale du Household Productivity Nord CM-UGP-PFS-47369-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat du point focal du with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-11- IDA / 52240 A posteriori consultants par Direct 3,188.07 Signé 2018-04-25 département du Diamaré Measures to Boost 11 29 28 05 28 01 entente directe dans la région de Household Productivity l'Extrême Nord CM-UGP-PFS-47371-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- terrain N°1 de la IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 Measures to Boost 11 28 28 04 28 31 commune de DIR entente directe Household Productivity (HEBGASSO Jean Baptiste) département du Mbéré, région de l'Adamaoua CM-UGP-PFS-47372-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- terrain N° 2 de la IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 Measures to Boost 11 28 28 04 28 31 Commune de Dir entente directe Household Productivity (HOULAO Pierre) département du Mbéré, région de l'Adamoua CM-UGP-PFS-47375-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2018-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- terrain N°2 de la IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 Measures to Boost 11 28 28 04 28 31 commune de BOGO( entente directe Household Productivity Wanie Bernard) département du Diamaré, région de l'Extrême Nord CM-UGP-PFS-47373-CS- INDV / Avenant au Cash Transfer Program contrat de l'opératrice de Sélection de with Accompanying 2016-01- 2018-04- 2018-02- 2018-05- 2018-02- 2018-10- terrain N°1 de la IDA / 52240 A posteriori consultants par Direct 2,147.60 Signé 2018-04-24 Measures to Boost 11 28 28 04 28 31 commune de BOGO, entente directe Household Productivity département du Diamaré, région de l'Extrême Nord CM-UGP-PFS-59671-CS- Cash Transfer Program Sélection de CDS / Opérateur de with Accompanying 2016-01- 2018-05- 2018-05- 2018-05- 2018-05- 2018-11- IDA / 52240 A posteriori consultants par Direct 2,391.05 Signé 2018-04-30 terrain de la commune de Measures to Boost 11 10 30 19 31 15 entente directe Douala 4 Household Productivity CM-UGP-PFS-59673-CS- Cash Transfer Program INDV / Recrutement du with Accompanying 2018-06- 2018-06- 2018-10- 2018-06- 2018-11- 2018-06- 2018-12- 2019-06- Responsable régional de IDA / 52240 A posteriori Individuel Open 16,630.56 Signé 2018-05-04 Measures to Boost 12 06 10 13 16 22 03 22 l'antenne du Nord du Household Productivity Projet Filets Sociaux CM-UGP-PFS-59789-CS- CDS / Audit financier et comptable des comptes du Projet de Remise à niveau Cash Transfer Program des Réseaux de Transport Sélection de with Accompanying 2018-04- 2018-04- 2018-03- 2018-05- 2018-07- 2020-05- d'Electricité et Réforme du IDA / 52240 A posteriori consultants par Direct 46,581.42 Signé 2018-04-26 Measures to Boost 20 30 23 14 31 13 Secteur (PRRTERS): entente directe Household Productivity exercices 2017-2018 - 2019 et du Projet Filets Sociaux (PFS) : exercices 2017-2018 CM-UGP-PFS-67474-CS- CDS / Avenant au contrat Laying the Foundations of Sélection de de l'opérateur de terrain a Safety Net System and 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2019-01- IDA / 52240 A posteriori consultants par Direct 2,831.73 Signé 2018-06-29 de la commune de Supporting Project 30 03 02 09 08 05 entente directe Yaoundé 1er NGO SICK Management ELEANOR RHOLY épouse KAM CM-UGP-PFS-67475-CS- CDS / Avenant au contrat Laying the Foundations of de l'opérateur de terrain Sélection de a Safety Net System and 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2019-01- de la commune de IDA / 52240 A posteriori consultants par Direct 2,831.73 Signé 2018-06-29 Supporting Project 30 03 02 09 08 05 Funfong, département du entente directe Management Boyo région du Nord Ouest AGHA-AH EVARISTUS ALANJI CM-UGP-PFS-67477-CS- CDS / Avenant au contrat de l'opérateur de terrain Laying the Foundations of Sélection de de la commune de a Safety Net System and 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2019-01- IDA / 52240 A posteriori consultants par Direct 2,831.73 Signé 2018-06-29 Balikumbat département Supporting Project 30 03 02 09 08 05 entente directe du Ngo Ketungja région Management du Nord Ouest TAJIPUKU ALPHONSE TAMIGHANG CM-UGP-PFS-67478-CS- CDS / avenant au contrat de l'opérateur de terrain Laying the Foundations of Sélection de N1 de la commune de a Safety Net System and 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2019-01- IDA / 52240 A posteriori consultants par Direct 2,831.73 Signé 2018-06-29 Messamena département Supporting Project 30 03 02 09 08 05 entente directe du Haut Nyong région de Management l'Est TSALA MVOGO BERNARD JEAN CM-UGP-PFS-67479-CS- Laying the Foundations of CDS / Avenant au contrat Sélection de a Safety Net System and 2015-12- 2018-07- 2015-05- 2018-07- 2018-05- 2019-01- du point focal du IDA / 52240 A posteriori consultants par Direct 4,195.15 Signé 2018-06-29 Supporting Project 30 03 04 09 08 05 département du Haut entente directe Management Nyong région de l'Est MBILLA Pierre Valery CM-UGP-PFS-67481-CS- CDS / avenant au contrat Laying the Foundations of de l'opérateur de terrain Sélection de a Safety Net System and 2015-12- 2018-07- 2018-06- 2018-07- 2018-06- 2018-11- N°2 de la commune de IDA / 52240 A posteriori consultants par Direct 1,887.82 Signé 2018-07-02 Supporting Project 30 06 25 12 29 09 Messamena ESSOMBA entente directe Management YANNICK ALBERT NGUEM CM-UGP-PFS-67482-CS- CDS / Avenant au contrat Laying the Foundations of de l'opérateur de terrain Sélection de a Safety Net System and 2015-12- 2018-07- 2018-05- 2018-07- 2018-05- 2018-08- 2018-06- N°2 de la commune de IDA / 52240 A posteriori consultants par Direct 471.95 Achevé 2018-06-29 Supporting Project 30 03 10 08 15 07 30 Lagdo, département de la entente directe Management Bénoué, région du Nord SIRINA ELVIS Page 8 CM-UGP-PFS-67517-CS- Laying the Foundations of Sélection de INDV / Responsable a Safety Net System and 2018-07- 2018-07- 2019-07- IDA / 52240 A posteriori consultants par Direct 0.00 Annulé 2018-06-29 Administratif et Financier Supporting Project 04 11 11 entente directe du Projet Management CM-UGP-PFS-72586-CS- Laying the Foundations of INDV / Recrutement d'un a Safety Net System and 2018-09- 2018-09- 2018-09- 2018-09- 2018-09- 2018-10- 2018-09- 2019-10- IDA / 52240 A posteriori Individuel Direct 5,136.94 Signé 2018-08-23 opérateur de terrain pour Supporting Project 13 02 14 23 17 28 17 28 la commune de Koza Management CM-UGP-PFS-81429-CS- INDV / consultants national sénior chargé Laying the Foundations of d'appuyer la Banque a Safety Net System and 2018-10- 2018-10- 2018-11- 2018-11- 2018-11- 2018-12- 2018-11- 2019-03- 2019-09- mondiale et le Projet IDA / 52240 A posteriori Individuel Limited 21,307.91 Achevé 2018-10-18 Supporting Project 05 25 26 15 28 20 30 20 04 Filets Sociaux dans la Management préparation d'une évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-83718-CS- Laying the Foundations of INDV / Responsable a Safety Net System and 2018-10- 2018-12- 2019-03- 2019-01- 2019-03- 2019-02- 2019-04- 2021-02- IDA / 52240 A posteriori Individuel Open 32,568.58 Signé 2018-11-11 Administratif et Financier Supporting Project 22 30 13 20 18 24 01 23 du Projet Filets Sociaux Management CM-UGP-PFS-83719-CS- Laying the Foundations of INDV / Expert en a Safety Net System and 2018-10- 2018-12- 2019-02- 2019-01- 2019-03- 2019-02- 2019-03- 2020-02- IDA / 52240 A posteriori Individuel Open 25,544.73 Signé 2018-11-11 sauvegardes sociales du Supporting Project 24 30 19 20 04 24 15 24 Projet Filets Sociaux Management CM-UGP-PFS-83720-CS- Laying the Foundations of INDV / coach du a Safety Net System and 2018-11- 2019-01- 2019-03- 2019-01- 2019-03- 2019-03- 2019-04- 2019-08- responsable des activités IDA / 52240 A posteriori Individuel Open 19,480.26 Résilié 2018-11-18 Supporting Project 01 06 07 27 11 03 17 30 d'accompagnement du Management Projet Filets Sociaux CM-UGP-PFS-83722-CS- Laying the Foundations of INDV / Assistant en a Safety Net System and 2018-11- 2019-01- 2019-02- 2019-01- 2019-02- 2019-03- 2019-02- 2020-03- IDA / 52240 A posteriori Individuel Open 10,329.66 Signé 2018-11-18 Gestion des Ressources Supporting Project 01 06 18 27 20 03 20 02 Humaines et du matériel Management CM-UGP-PFS-83723-CS- Laying the Foundations of INDV / Assistant au a Safety Net System and 2018-11- 2019-01- 2019-03- 2019-01- 2019-03- 2019-03- 2019-03- 2020-03- Responsable du Systeme IDA / 52240 A posteriori Individuel Open 9,119.51 Signé 2018-11-18 Supporting Project 13 06 01 27 06 03 06 02 d'Information Management du Projet Filets Sociaux MOF-CM-UGP-PFS-14460- Laying the Foundations of Sélection de CS-CDS / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2017-12- IDA / 52240 A posteriori consultants par Direct 2,785.30 Signé 2017-06-09 contrat de l'opératrice de Supporting Project 13 09 16 17 13 entente directe terrain de la commune de Management Douala 2 MOF-UGP-PFS-14463-CS- Laying the Foundations of Sélection de CDS / Avenant au contrat a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori consultants par Direct 25,147.34 Signé 2017-01-12 de l'operateur de terrain Supporting Project 12 09 23 15 23 entente directe de Yaoundé 7 Management MOF-UGP-PFS-14490-CS- Laying the Foundations of Sélection de CDS / Avenant au contrat a Safety Net System and 2015-01- 2017-06- 2017-06- 2017-07- 2017-07- 2019-07- IDA / 52240 A posteriori consultants par Direct 14,442.29 Signé 2017-06-15 de Technicienne de surface Supporting Project 13 23 23 02 03 02 entente directe de l'UGP Management MOF-CM-UGP-PFS-6421- Laying the Foundations of CS-INDV / Expert a Safety Net System and 2017-02- 2017-04- 2017-05- 2017-04- 2017-05- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 81,486.50 Signé 2017-02-17 environnemental et social Supporting Project 10 07 17 28 18 02 09 02 du PFS Management Laying the Foundations of MOF-CM-UGP-PFS-6423- a Safety Net System and 2017-01- 2017-03- 2017-05- 2017-04- 2017-05- 2017-05- 2017-06- 2018-05- 2018-06- CS-INDV / Assistant IDA / 52240 A posteriori Individuel Open 27,305.89 Signé 2017-02-07 Supporting Project 11 28 17 18 17 23 13 23 13 Comptable Management Laying the Foundations of MOF-CM-UGP-PFS-6424- a Safety Net System and 2017-01- 2017-03- 2017-04- 2017-04- 2017-04- 2017-05- 2017-05- 2018-05- IDA / 52240 A posteriori Individuel Open 6,156.07 Résilié 2017-02-07 CS-INDV / Assistant SPM Supporting Project 11 28 12 18 21 23 10 23 Management Laying the Foundations of CM-UGP-PFS-108883-CS- a Safety Net System and 2019-03- 2019-06- 2019-08- 2019-07- 2019-08- 2019-08- 2019-09- 2020-08- INDV / Auditeur interne IDA / 52240 A posteriori Individuel Open 29,878.57 Signé 2019-04-19 Supporting Project 24 16 08 07 13 04 09 03 du Projet Filets Sociaux Management CM-UGP-PFS-111619-CS- CDS / Avenant N°01 au Cash Transfer Program contrat de l'Opérateur de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- Terrain 1 de la Commune IDA / 52240 A posteriori consultants par Direct 1,832.99 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 05 de Banyo, Département du entente directe Household Productivity Mayo Banyo, Région de l'Adamaoua CM-UGP-PFS-111629-CS- CDS / Avenant Contrat de Cash Transfer Program l'Opérateur de Terrain 2 Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- de la Commune de Banyo, IDA / 52240 A posteriori consultants par Direct 1,845.59 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 05 Département du Mayo entente directe Household Productivity Banyo, Région de l'Adamaoua CM-UGP-PFS-111638-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 2,459.26 Signé 2019-05-22 la Commune de Bélo, Measures to Boost 12 01 14 05 18 16 entente directe Département du Boyo, Household Productivity Région du Nord-Ouest CM-UGP-PFS-111640-CS- Cash Transfer Program CDS / Avenant au contrat Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- de l'Opérateur de Terrain IDA / 52240 A posteriori consultants par Direct 15,181.83 Signé 2019-05-22 Measures to Boost 12 01 14 05 18 16 1 de Douala IIIe, Ville de entente directe Household Productivity Douala CM-UGP-PFS-111642-CS- Cash Transfer Program CDS / Avenant de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- l'Opérateur de Terrain 2 IDA / 52240 A posteriori consultants par Direct 15,181.83 Signé 2019-05-22 Measures to Boost 12 01 14 05 18 16 de la Commune de Douala entente directe Household Productivity IIIe, Ville de Douala CM-UGP-PFS-111643-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain 1 with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 15,181.83 Signé 2019-05-22 de la Commune de Ketté, Measures to Boost 12 01 14 05 18 16 entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111658-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain 2 with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 15,181.83 Signé 2019-05-22 de la Commune de Ketté, Measures to Boost 12 01 14 05 18 16 entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111662-CS- Cash Transfer Program CDS / Avenant contrat de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- l'Opératrice de Terrain 1 IDA / 52240 A posteriori consultants par Direct 15,181.83 Signé 2019-05-22 Measures to Boost 12 01 14 05 18 16 de la Commune de entente directe Household Productivity Yaoundé IIe, Ville de Yaoundé CM-UGP-PFS-111664-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- la Commune de Blangoua, IDA / 52240 A posteriori consultants par Direct 1,374.74 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 04 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111670-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- la Commune de Bourha, IDA / 52240 A posteriori consultants par Direct 1,374.74 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 04 Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111678-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- la Commune de Gobo, IDA / 52240 A posteriori consultants par Direct 1,374.74 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 04 Département du Mayo entente directe Household Productivity Danay, Région de l'Extrême-Nord CM-UGP-PFS-111681-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- la Commune de Goulfey, IDA / 52240 A posteriori consultants par Direct 1,374.74 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 04 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111685-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- la Commune de Koza, IDA / 52240 A posteriori consultants par Direct 1,374.74 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 04 Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord Page 9 CM-UGP-PFS-111688-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- la Commune de Makari, IDA / 52240 A posteriori consultants par Direct 4,124.22 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 06 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111691-CS- CDS / Avenant de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- la Commune de Mogodé, IDA / 52240 A posteriori consultants par Direct 4,124.22 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 06 Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111692-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- IDA / 52240 A posteriori consultants par Direct 1,832.99 Signé 2019-05-22 la Commune de Mayo Measures to Boost 12 01 14 05 20 05 entente directe Oulo, Département du Household Productivity Mayo Louti, Région du Nord CM-UGP-PFS-111696-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- IDA / 52240 A posteriori consultants par Direct 4,124.22 Signé 2019-05-22 la Commune de Rey Measures to Boost 12 01 14 05 20 06 entente directe Bouba, Département du Household Productivity Mayo Rey, Région du Nord CM-UGP-PFS-111698-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- IDA / 52240 A posteriori consultants par Direct 4,124.22 Signé 2019-05-22 la Commune de Tchéboa, Measures to Boost 12 01 14 05 20 06 entente directe Département de la Household Productivity Bénoué, Région du Nord CM-UGP-PFS-111699-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain 1 with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- IDA / 52240 A posteriori consultants par Direct 1,832.99 Signé 2019-05-22 de la Commune de Measures to Boost 12 01 14 05 20 05 entente directe Touboro, Département du Household Productivity Mayo Rey, Région du Nord CM-UGP-PFS-111725-CS- CDS / Avenant contrat Cash Transfer Program Sélection de Point Focal du Projet with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- IDA / 52240 A posteriori consultants par Direct 22,491.60 Signé 2019-05-22 Filets Sociaux dans le Measures to Boost 12 01 14 05 18 16 entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111726-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- Filets Sociaux dans le IDA / 52240 A posteriori consultants par Direct 6,109.96 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 06 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême- Nord CM-UGP-PFS-111727-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-12- Filets Sociaux dans le IDA / 52240 A posteriori consultants par Direct 2,715.54 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 05 Département du Mayo entente directe Household Productivity Banyo, Région de l'Adamaoua CM-UGP-PFS-111735-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2019-11- Filets Sociaux dans le IDA / 52240 A posteriori consultants par Direct 2,036.65 Signé 2019-05-22 Measures to Boost 12 01 14 05 20 04 Département du Mayo entente directe Household Productivity Danay, Région de l'Extrême-Nord CM-UGP-PFS-111737-CS- CDS / Avenant contrat Cash Transfer Program Sélection de Point Focal du Projet with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-05- IDA / 52240 A posteriori consultants par Direct 6,109.96 Signé 2019-05-22 Filets Sociaux dans le Measures to Boost 12 01 14 05 20 06 entente directe Département Mayo Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111739-CS- Cash Transfer Program CDS / Avenant contrat Sélection de with Accompanying 2017-01- 2019-06- 2019-03- 2019-08- 2019-03- 2020-01- Point Focal du Projet IDA / 52240 A posteriori consultants par Direct 22,491.60 Signé 2019-05-22 Measures to Boost 12 01 14 05 18 16 Filets Sociaux dans la entente directe Household Productivity Ville de Yaoundé CM-UGP-PFS-121795-CS- CDS / Consultant chargé de l'élaboration de la Laying the Foundations of Sélection de méthodologie de choix et a Safety Net System and En cours 2019-07- 2019-12- 2019-10- 2020-02- 2020-03- IDA / 62230 A posteriori consultants par Direct 0.00 2019-11-30 d’opérationnalisation du Supporting Project d'exécution 12 19 29 13 14 entente directe choix des communes Management bénéficiaires du Projet Filets Sociaux CM-UGP-PFS-141188-CS- INDV / Recrutement d'un Laying the Foundations of point Focal dans la a Safety Net System and 2020-02- 2020-02- 2020-03- 2022-03- ville de Douala, région du IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2019-12-10 Supporting Project 04 25 31 31 littoral pour la phase 3 Management des Transferts Monétaires ordinaires CM-UGP-PFS-141191-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans la ville a Safety Net System and 2020-02- 2020-02- 2020-03- 2022-03- IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2019-12-10 de Yaoundé pour la Supporting Project 04 25 31 31 cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141758-CS- INDV / Recrutement d'un Consultant pour le ciblage des 1000 bénéficiaires de Laying the Foundations of la Phase 3 des TMU du a Safety Net System and En cours 2020-01- 2020-01- 2020-02- 2020-03- 2020-10- IDA / D2980 A posteriori Individuel Open 0.00 2019-11-29 Projet Filets Sociaux dans Supporting Project d'exécution 03 24 14 20 16 la commune de Waza, Management département du Logone et Chari, région de l'Extrême- Nord CM-UGP-PFS-143558-CS- INDV / Recrutement de l'enquêteur Chercheur Laying the Foundations of N°1 de l'équipe a Safety Net System and 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-11- 2020-06- septentrionale dans le IDA / 62230 A posteriori Individuel Limited 4,942.86 Signé 2019-11-29 Supporting Project 27 20 25 03 26 07 27 06 cadre de la préparation Management d'une évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143560-CS- INDV / Recrutement de l'enquêteur Chercheur N°2 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,942.86 Signé 2019-11-29 Supporting Project 27 20 26 03 26 07 06 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143562-CS- INDV / Recrutement de l'enquêteur Chercheur N°3 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,942.86 Signé 2019-11-29 Supporting Project 27 20 26 03 26 07 16 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143563-CS- INDV / Recrutement de l'enquêteur Chercheur N°4 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-11- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 7,719.29 Signé 2019-11-29 Supporting Project 27 20 26 03 26 07 27 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143564-CS- INDV / Recrutement de l'enquêteur Chercheur N°1 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,529.24 Signé 2019-11-29 Supporting Project 27 20 25 03 26 07 06 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143565-CS- INDV / Recrutement de l'enquêteur Chercheur N°2 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,529.24 Signé 2019-11-29 Supporting Project 27 20 25 03 26 07 06 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun Page 10 CM-UGP-PFS-143567-CS- INDV / Recrutement de l'enquêteur Chercheur N°3 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,529.24 Signé 2019-11-29 Supporting Project 27 20 25 03 26 07 13 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143568-CS- INDV / Recrutement de l'enquêteur Chercheur N°4 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-09- 2019-12- 2019-11- 2020-01- 2019-11- 2020-02- 2019-12- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,529.24 Signé 2019-11-29 Supporting Project 27 20 25 03 26 07 06 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-152346-CS- INDV / RECRUTEMENT DU CONSULTANT CHARGE D’INSTALLER Laying the Foundations of ET DE PARAMETRER a Safety Net System and En cours 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- 2020-04- 2020-07- LES LOGICIELS IDA / 62230 A posteriori Individuel Limited 0.00 2020-01-31 Supporting Project d'exécution 22 07 22 28 05 04 03 TOM2PRO, Management TOM2MARCHE ET TOM2PAIE D’UNE PART ET D’AUTRE PART DE RENFORCER LES CAPACITES DE L’UGP CM-UGP-PFS-142945-CS- CDS / Recrutement d'une ONG pour la mise en Sélection de Public Works Program En attente 2020-02- 2020-05- 2020-12- œuvre des activités de la IDA / D2980 A posteriori consultants par Direct 0.00 2020-02-10 Pilot d'exécution 29 04 30 Phase 7 des THIMO dans entente directe la région de l'Extrême Nord, commune de Mokolo CM-UGP-PFS-142946-CS- CDS / Recrutement d'une ONG pour la mise en Sélection de Public Works Program En attente 2020-02- 2020-05- 2020-12- œuvre des activités de la IDA / D2980 A posteriori consultants par Direct 0.00 2020-02-10 Pilot d'exécution 29 04 30 Phase 7 des THIMO dans entente directe la région du Nord , commune de Touboro CM-UGP-PFS-142944-CS- CDS / Recrutement d'une ONG pour la mise en œuvre des activités de la Sélection de Public Works Program En attente 2020-02- 2020-05- 2020-12- Phase 7 des THIMO IDA / D2980 A posteriori consultants par Direct 0.00 2020-02-10 Pilot d'exécution 29 04 30 dans les régions de entente directe l'Adamaoua (commune de Dir) et de l'Est (Communes de Ngoura et de Mandjou) CM-UGP-PFS-141791-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-04- cycle 3 des TMO du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Garoua Boulaï , département du Lom et Djérem, région de l'Est CM-UGP-PFS-141143-CS- INDV / Recrutement de l' Opérateur de Terrain N°1 du Projet Filets Laying the Foundations of Sociaux de la Commune a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 de Logone Birni, Supporting Project d'exécution 25 15 20 20 département du Logone et Management Chari, région de l'Extrême Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141107-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- la Région du SUD-OUEST IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141192-CS- INDV / Recrutement d'un Consultant pour le ciblage des 1000 bénéficiaires de Laying the Foundations of la Phase 3 des TMU du a Safety Net System and En cours 2019-10- 2020-08- 2020-04- 2020-09- 2020-10- 2021-05- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Projet Filets Sociaux dans Supporting Project d'exécution 16 25 11 15 20 18 la commune de Fotokol, Management département du Logone et Chari, région de l'Extrême- Nord CM-UGP-PFS-141091-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 la Région de l'Est pour la Supporting Project d'exécution 25 15 20 20 cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141718-CS- INDV / Recrutement de l'Opérateur de Terrain I Laying the Foundations of de la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Meiganga, département du Supporting Project d'exécution 25 15 20 20 Mbéré, région de Management l'Adamaoua pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141717-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of de la Commune de Logone a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- Birni, département du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 Logone et Chari, région de Management l'Extrême Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141793-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 3000 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- cycle 3 des TMO du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 Projet Filets Sociaux dans Management la commune de Touboro, département du Mayo-Rey, région du Nord CM-UGP-PFS-141162-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- Meyomessala, Département IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 du Dja et Lobo, région du Management Sud pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141731-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 du Projet Filets Sociaux Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Moulvoudaye , Supporting Project d'exécution 25 15 20 20 département du Mayo Management Kani, région de l'Extrême- Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141171-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-10- Fotokol, département du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 Logone et Chari, région de Management l'Extrême Nord pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141780-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En cours 2019-10- 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 16 25 15 20 18 Projet Filets Sociaux dans Management la commune de Meiganga , département du Mbéré, région de l'Adamaoua CM-UGP-PFS-141196-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Madringrin , département du Mayo-Rey, région du Nord Page 11 CM-UGP-PFS-141170-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-10- Waza, département du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 Logone et Chari, région de Management l'Extrême Nord pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141801-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Ma'an , département de la Valée du Ntem, région du Sud CM-UGP-PFS-141167-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En cours 2019-10- 2020-08- 2020-05- 2020-09- 2020-10- 2021-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Meiganga, département du Supporting Project d'exécution 10 25 26 15 20 20 Mbéré, région de Management l'Adamaoua pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141168-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Ngaoui, département du Supporting Project d'exécution 25 15 20 20 Mbéré, région de Management l'Adamaoua pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141160-CS- INDV / Recrutement de l'Opérateur de Terrain Laying the Foundations of N°1 de la la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- Madingring , département IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 du Mayo Rey, région du Management Nord pour le cycle 3 des Transferts Monetaires Ordinaires CM-UGP-PFS-141755-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- la Phase 3 des TMU du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Ngaoui, département du Mbéré, région de l'Adamaoua CM-UGP-PFS-141794-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune d' Ebolowa II, département de la Mvila, région du Sud CM-UGP-PFS-141184-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans le a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- département du Mayo Rey, IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 région du Nord pour la Management cycle 3 des Transferts Monétaires ordinaires CM-UGP-PFS-141145-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 du Projet Filets Sociaux Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Bétaré Oya, département Supporting Project d'exécution 25 15 20 20 du Lom et Djérem, région Management de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141787-CS- INDV / Recrutement d'un Consultant pour le ciblage des 1500 bénéficiaires du Laying the Foundations of cycle 3 des TMO du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Projet Filets Sociaux dans Supporting Project d'exécution 25 15 20 18 la commune de Logone Management Birni, département du Logone et Chari, région de l'Extrême-Nord CM-UGP-PFS-141812-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1500 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 cycle 3 des TMO du Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Yaoundé III , Ville de Yaoundé CM-UGP-PFS-141727-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 du Projet Filets Sociaux Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Bétaré Oya, département Supporting Project d'exécution 25 15 20 20 du Lom et Djérem, région Management de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141164-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- Ma'am, Département de la IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 Vallée du Ntem, région Management du Sud pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141800-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Meyomessala, département du Dja et Lobo, région du Sud CM-UGP-PFS-141159-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 du Projet Filets Sociaux Laying the Foundations of dans la Commune de a Safety Net System and En cours 2019-10- 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Moulvoudaye , Supporting Project d'exécution 10 25 15 20 20 département du Mayo Management Kani, région de l'Extrême- Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141097-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 la Région du SUD pour la Supporting Project d'exécution 25 15 20 20 cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141163-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 d'Ebolowa II, département Supporting Project d'exécution 25 15 20 20 de la Mvila, région du Management Sud pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141141-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 Laying the Foundations of du Projet Filets Sociaux a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- de la Commune de IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 Meiganga, département du Management Mbéré, région de l'Adamaoua pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141161-CS- INDV / Recrutement de 3 Opérateurs de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- Touboro, département du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 Mayo-Rey, région du Nord Management pour le cycle 3 des Transferts Monétaires Ordinaires Page 12 CM-UGP-PFS-141735-CS- INDV / Recrutement de l'Opérateur de Terrain Laying the Foundations of N°2 de la la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- Madingring , département IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 du Mayo Rey, région du Management Nord pour le cycle 3 des Transferts Monetaires Ordinaires CM-UGP-PFS-141155-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 du Projet filets sociaux Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Garoua-Boulaï, Supporting Project d'exécution 25 15 20 20 département du Lom et Management Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141785-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Moulvoudaye , département du Mayo Kani, région de l'Extrême- Nord CM-UGP-PFS-141183-CS- INDV / Recrutement d'un Point Focal dans le Laying the Foundations of département du Logone et a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Chari, région de l'Extrême Supporting Project d'exécution 25 15 20 20 Nord pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141804-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des1500 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 cycle 3 des TMO du Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Douala V , Ville de Douala CM-UGP-PFS-141187-CS- INDV / Recrutement d'un Point Focal dans le Laying the Foundations of département du Mayo a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / 62230 A posteriori Individuel Open 0.00 2020-06-30 Kani, région de l'Extrême Supporting Project d'exécution 25 15 20 20 Nord pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141084-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- la Région de l'Adamaoua IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141729-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 du Projet filets sociaux Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Garoua-Boulaï, Supporting Project d'exécution 25 15 20 20 département du Lom et Management Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141725-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 Laying the Foundations of du Projet Filets Sociaux a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2022-10- de la Commune de IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 20 Meiganga, département du Management Mbéré, région de l'Adamaoua pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141193-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- cycle 3 des TMO du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Bétaré Oya , département du Lom et Djérem, région de l'Est Laying the Foundations of CM-UGP-PFS-172114-CS- a Safety Net System and En cours 2020-06- 2020-07- 2020-08- 2020-09- 2021-09- INDV / Recrutement d'un IDA / 62230 A posteriori Individuel Open 0.00 2020-05-25 Supporting Project d'examen 29 16 06 10 10 Assistant SPM Management CM-UGP-PFS-172253-CS- INDV / Recrutement d’un Consultant pour une Laying the Foundations of évaluation sociale et une a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-04- consultation des IDA / 62230 A posteriori Individuel Limited 0.00 2020-08-13 Supporting Project d'exécution 18 08 13 11 populations '4B' en vue de Management l'élaboration d'un Plan d'action Peuple Autochtone (PPA) (IDA National) CM-UGP-PFS-141123-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-09- 2020-10- 2020-11- 2022-11- Chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 0.00 2020-07-30 Supporting Project d'exécution 24 15 19 19 régionale du Sud-Ouest du Management Projet Filets Sociaux CM-UGP-PFS-172280-CS- Laying the Foundations of INDV / Consultant pour a Safety Net System and En attente 2021-02- 2021-03- 2021-04- 2021-10- la production des séries IDA / 62230 A posteriori Individuel Open 0.00 2020-12-21 Supporting Project d'exécution 11 04 08 05 radiophoniques pour la Management prévention des VBG CM-UGP-PFS-172210-CS- INDV / Recrutement d'un Laying the Foundations of consultant pour la a Safety Net System and En cours 2020-06- 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 0.00 2020-06-22 traduction des documents Supporting Project d'exécution 29 13 03 08 08 du Projet Filets Sociaux Management en Anglais/ Français CM-UGP-PFS-141752-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2021-05- la Phase 3 des TMU du IDA / D2980 A posteriori Individuel Open 0.00 2020-06-30 Supporting Project d'exécution 25 15 20 18 Projet Filets Sociaux dans Management la commune de Meiganga, département du Mbéré, région de l'Adamaoua CM-UGP-PFS-176264-CS- INDV / Recrutement par Entente Directe d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En cours 2020-06- 2020-06- 2020-07- 2020-08- 2021-02- IDA / D2980 A posteriori Individuel Direct 0.00 2020-06-10 cycle 3 des TMO du Supporting Project d'exécution 30 20 11 15 11 Projet Filets Sociaux dans Management la commune de Meiganga , département du Mbéré, Région de l'Adamaoua CM-UGP-PFS-172276-CS- Laying the Foundations of INDV / Consultant pour a Safety Net System and En attente 2020-08- 2020-09- 2020-10- 2020-11- la conception d'une IDA / 62230 A posteriori Individuel Limited 0.00 2020-08-20 Supporting Project d'exécution 25 15 20 19 affiche de communication Management et de sensibilisation sur le MGP CM-UGP-PFS-141118-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente 2020-11- 2020-12- 2021-01- 2023-01- Secrétaire de l'antenne IDA / 62230 A posteriori Individuel Open 0.00 2020-09-30 Supporting Project d'exécution 25 16 20 20 régionale du Sud-Ouest du Management Projet Filets Sociaux CM-UGP-PFS-141130-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente 2020-11- 2020-12- 2021-01- 2023-01- Secrétaire de l'antenne IDA / D2980 A posteriori Individuel Open 0.00 2020-09-30 Supporting Project d'exécution 25 16 20 20 régionale de l'Est du Management Projet Filets Sociaux CM-UGP-PFS-141124-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente 2020-11- 2020-12- 2021-01- 2023-01- Secrétaire de l'antenne IDA / 62230 A posteriori Individuel Open 0.00 2020-09-30 Supporting Project d'exécution 25 16 20 20 régionale Sud du Projet Management Filets Sociaux CM-UGP-PFS-141134-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-11- 2020-12- 2021-01- 2023-01- Chauffeur de l'antenne IDA / D2980 A posteriori Individuel Open 0.00 2020-09-30 Supporting Project d'exécution 25 16 20 20 régionale de l'Adamaoua Management du Projet Filets Sociaux CM-UGP-PFS-141131-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-11- 2020-12- 2021-01- 2023-01- Chauffeur de l'antenne IDA / D2980 A posteriori Individuel Open 0.00 2020-09-30 Supporting Project d'exécution 25 16 20 20 régionale de l'Est du Management Projet Filets Sociaux Page 13 CM-UGP-PFS-141129-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-11- 2020-12- 2021-01- 2023-01- Chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 0.00 2020-09-30 Supporting Project d'exécution 25 16 20 20 régionale Sud du Projet Management Filets Sociaux CM-UGP-PFS-141133-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente 2020-11- 2020-12- 2021-01- 2023-01- Secrétaire de l'antenne IDA / D2980 A posteriori Individuel Open 0.00 2020-09-30 Supporting Project d'exécution 25 16 20 20 régionale de l'Adamaoua Management du Projet Filets Sociaux CM-UGP-PFS-187235-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-11- 2020-12- 2021-01- 2023-01- chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 0.00 2020-09-30 Supporting Project d'exécution 25 16 20 20 régionale du Sud ouest du Management Projet Filets Sociaux CM-UGP-PFS-141174-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Bamenda II, département Supporting Project 25 15 20 20 de MEZAM, région du Management Nord-Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141763-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-05- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Supporting Project 25 15 20 18 Projet Filets Sociaux dans Management la commune de Bamenda II , département de la Mezam, région du Nord- Ouest CM-UGP-PFS-141771-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-05- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Supporting Project 25 15 20 18 Projet Filets Sociaux dans Management la commune de Limbé III, département du Fako, région du Sud-Ouest CM-UGP-PFS-141765-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-05- la Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Supporting Project 25 15 20 18 Projet Filets Sociaux dans Management la commune de Bamenda III , département de la Mezam, région du Nord- Ouest CM-UGP-PFS-141178-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Limbé I, département de Supporting Project 25 15 20 20 Fako, région du Sud- Management Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141179-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Limbé II, département de Supporting Project 25 15 20 20 Fako, région du Sud- Management Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141769-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-05- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Supporting Project 25 15 20 18 Projet Filets Sociaux dans Management la commune de Limbé II, département du Fako, région du Sud-Ouest CM-UGP-PFS-141197-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-05- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Supporting Project 25 15 20 18 Projet Filets Sociaux dans Management la commune de Bamenda I, département de la Mezam, région du Nord- Ouest CM-UGP-PFS-141173-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Bamenda I, département Supporting Project 25 15 20 20 de MEZAM, région du Management Nord-Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141180-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-10- IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Limbé III, département de Supporting Project 25 15 20 20 Fako, région du Sud- Management Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141176-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-10- Bamenda III, département IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Supporting Project 25 15 20 20 de MEZAM, région du Management Nord-Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141767-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and 2020-08- 2020-09- 2020-10- 2021-05- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 0.00 Annulé 2020-06-30 Supporting Project 25 15 20 18 Projet Filets Sociaux dans Management la commune de Limbé I , département du Fako, région du Sud-Ouest Page 14