Prior Review Thresholds I. Goods and Works and non-consulting services. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Procurement Method Prior Review Remarks Thresholds (Estimated Cost of the Contract/Package) Works (including turnkey, ICB, NCB, Direct >=US$ 10,000,000 supply & installation of Contract plant and equipment, and RFQ None PPP) Goods, information ICB, NCB, Direct >=US$ 2,000,000 technology and non- Contract consulting services RFQ None II. Selection of Consultants Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of Procurement Procurement Method Prior Review Remarks Thresholds (Estimated Cost of the Contract/Package) Consultants: firms QCBS, QBS, FBS, >=US$ 1,000,000 CQS, Single Source Selection Consultants: Individual IC (Open, 3CV, or SSS) >=US$ 300,000 III. Short list comprising entirely of national consultants Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Bangladesh : Bangladesh Urban Resilience Project PLAN General Information Country: Bangladesh Banks Approval Date of the Original Procurement Plan: 2017-02-23 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-08-07 Project ID: P149493 GPN Date: Project Name: Bangladesh Urban Resilience Project Loan / Credit No: IDA / 55990 Executing Agency(ies): Rajdhani Unnayan Kartripakhha, Department of Disaster Mangement, Dhaka North City Corporation, Project Coordination and Monitoring Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Reinforcing the URP/DDM/W-1 / Renovation of Countrys Emergency Request for Single Stage - One the facility that would house IDA / 55990 Prior Open - National 701,300.00 0.00 Canceled 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2018-03-19 Management Response Proposals Envelope ERCC Capacity Component A: Reinforcing the URP/DDM/W-2 / Renovation of Countrys Emergency Request for Single Stage - One the facility that would house IDA / 55990 Prior Open - National 467,530.00 0.00 Canceled 2017-06-07 2017-06-12 2017-07-24 2017-08-23 2017-09-27 2018-03-26 Management Response Proposals Envelope NDMRTI Capacity URP-DNCC/W-3-4 / Erection Component A: Reinforcing the and Fabrication of Signboard at Countrys Emergency Request for Single Stage - One Pending IDA / 55990 Post Open - National 8,750.00 0.00 2018-02-16 2018-04-30 2018-06-29 Emergency Warehouses of City Management Response Quotations Envelope Implementation Corporations Capacity URP-DNCC/W-3-5 / Erection Component A: Reinforcing the and Fabrication of Signboard at Countrys Emergency Request for Single Stage - One Pending IDA / 55990 Post Open - National 8,750.00 0.00 2018-04-04 2018-06-16 2018-08-15 Emergency Warehouses of Management Response Quotations Envelope Implementation FSCD Capacity URP-DNCC/W-1-2 / Component A: Reinforcing the Construction of FSCD Command Countrys Emergency Single Stage - One Pending & Control Center including IDA / 55990 Post Request for Bids Open - National 963,904.00 0.00 2018-01-30 2018-02-14 2018-03-16 2018-05-15 2018-06-19 2019-03-16 Management Response Envelope Implementation Warehouses at South Surma, Capacity Sylhet Component A: Reinforcing the BD-DDM-44875-CW-RFB / Countrys Emergency Single Stage - One Pending Renovation of the facility that IDA / 55990 Post Request for Bids Open - National 701,300.00 0.00 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Management Response Envelope Implementation would house ERCC Capacity Component A: Reinforcing the BD-DDM-44877-CW-RFB / Countrys Emergency Single Stage - One Pending Renovation of the facility that IDA / 55990 Post Request for Bids Open - National 467,530.00 0.00 2018-02-22 2018-02-27 2018-04-10 2018-05-10 2018-06-14 2018-12-11 Management Response Envelope Implementation would house NDMRTI Capacity Component B: Vulnerability URP/RAJUK/W-1A / Assessment of Critical and Construction of Shed ,Partition Essential Facilities Request for Single Stage - One Pending and supportive Accessories for IDA / 55990 Post Open - National 12,987.00 0.00 2018-03-15 2018-05-06 2018-06-05 Component C: Improved Quotations Envelope Implementation Accommodation of PIU Office Construction, Urban Planning, Security and Development Component B: Vulnerability Assessment of Critical and URP/RAJUK/W-1B / Renovation Essential Facilities Request for Single Stage - One Pending IDA / 55990 Post Open - National 12,990.00 0.00 2018-04-16 2018-06-11 2019-06-11 of office utility Space at Level 9 Component C: Improved Quotations Envelope Implementation Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and URP/RAJUK/G-W1C / Essential Facilities Request for Single Stage - One Pending Renovation of Wash room and IDA / 55990 Post Open - National 12,990.00 0.00 2018-05-18 2018-07-13 2019-07-13 Component C: Improved Quotations Envelope Implementation others Space at Level 9 Construction, Urban Planning, and Development URP-DNCC/W-1-1 / Build FSCD Command and Control Room, Component A: Reinforcing the Dhaka (Vertical extension of 1st Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 1,192,824.00 0.00 2018-03-20 2018-03-25 2018-05-06 2018-07-05 2018-08-09 2019-02-05 & 2nd floor of newly constructed Management Response Envelope Implementation warehouse at FSCD Compound, Capacity Mirpur-10, Dhaka) URP-DNCC/W-2-1 / Construction of Emergency Component A: Reinforcing the Operation Center (EOC), DRM Countrys Emergency Single Stage - One Pending Office and Urban Resilience Unit IDA / 55990 Post Request for Bids Open - National 362,500.00 0.00 2018-03-25 2018-03-30 2018-05-11 2018-07-10 2018-08-14 2018-12-12 Management Response Envelope Implementation at SCC Sylhet (Vertical Capacity extension of 5th floor of SCC Nagar Bhaban, Sylhet) URP-DNCC/W-2-2 / Building Component A: Reinforcing the Emergency Operating Centre Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 124,375.00 0.00 2018-04-25 2018-04-30 2018-05-30 2018-07-29 2018-09-02 2018-12-31 (EOC), DRM Office and Urban Management Response Envelope Implementation Resilience Unit at DSCC, Dhaka Capacity URP-DNCC/W-3-6 / Component A: Reinforcing the Construction of Security Fence Countrys Emergency Request for Single Stage - One Pending IDA / 55990 Post Open - National 11,900.00 0.00 2018-10-30 2019-01-20 2019-03-21 (Grill) inside and outside the Management Response Quotations Envelope Implementation Warehouses of DNCC Capacity URP-DNCC/W-3-7 / Component A: Reinforcing the Construction of Security Fence Countrys Emergency Request for Single Stage - One Pending IDA / 55990 Post Open - National 11,900.00 0.00 2018-11-02 2019-01-23 2019-03-24 (Grill) inside and outside the Management Response Quotations Envelope Implementation Warehouses of DSCC Capacity GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 URP-DNCC/G-1-1 / Procurement Component A: Reinforcing the of Specialized ICT Equipment Countrys Emergency Single Stage - One (VHF and HF Radio Terminals IDA / 55990 Prior Request for Bids Open - International 6,025,250.00 3,812,149.94 Signed 2017-05-14 2017-06-20 2017-05-19 2017-06-22 2017-07-18 2017-11-01 2018-04-16 2017-12-13 2018-05-30 2018-09-09 Management Response Envelope and Related Installations) for Capacity FSCD (Lot-1: VHF, Lot-2: HF) URP-DNCC/G-2-2 / Supply of Component A: Reinforcing the Specialized Search and Rescue Countrys Emergency Single Stage - One IDA / 55990 Prior Request for Bids Open - International 647,658.00 688,797.06 Signed 2017-05-14 2017-06-20 2017-05-19 2017-07-13 2017-08-02 2017-11-16 2017-11-20 2017-12-28 2017-12-18 2018-09-24 Equipment (Water Rescue) for Management Response Envelope FSCD Capacity URP-DNCC/G-2-6 / Supply of Component A: Reinforcing the Specialized Search and Rescue Countrys Emergency Single Stage - One IDA / 55990 Prior Request for Bids Open - International 1,741,366.00 1,528,000.00 Signed 2017-05-30 2017-06-15 2017-06-04 2017-06-20 2017-08-18 2017-12-02 2018-01-23 2018-01-13 2018-01-31 2018-10-10 Equipment (Lot-1: Ambulance, Management Response Envelope Lot-2: Mortuary Van) Capacity Component A: Reinforcing the BD-DDM-15188-GO-RFP / Countrys Emergency Request for Single Stage - One Procurement of Office Equipment IDA / 55990 Post Open - National 60,000.00 0.00 Canceled 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 Management Response Proposals Envelope for PIU, DDM Capacity BD-DDM-15189-GO-RFP / Component A: Reinforcing the Procurement of Computer and Countrys Emergency Request for Single Stage - One IDA / 55990 Post Open - National 26,000.00 0.00 Canceled 2017-06-22 2017-06-27 2017-08-08 2017-09-07 2017-10-12 2018-04-10 related Equipment's for PIU, Management Response Proposals Envelope DDM Capacity Component A: Reinforcing the BD-DDM-15190-GO-RFP / Countrys Emergency Request for Single Stage - One Procurement of Mobile Phone IDA / 55990 Post Limited 2,500.00 0.00 Canceled 2017-06-08 2017-06-13 2017-07-25 2017-08-24 2017-09-28 2018-03-27 Management Response Proposals Envelope etc. for PIU, DDM Capacity Component A: Reinforcing the BD-DDM-15191-GO-RFP / Countrys Emergency Request for Single Stage - One Procurement of Office Furniture IDA / 55990 Post Open - National 20,000.00 0.00 Canceled 2017-06-29 2017-07-04 2017-08-15 2017-09-14 2017-10-19 2018-04-17 Management Response Proposals Envelope for PIU, DDM Capacity BD-DDM-15192-GO-RFP / Component A: Reinforcing the Procurement of Telecom Countrys Emergency Request for Single Stage - One IDA / 55990 Post Limited 6,500.00 0.00 Canceled 2017-06-20 2017-06-25 2017-08-06 2017-09-05 2017-10-10 2018-04-08 Equipment's (Land Telephone, Management Response Proposals Envelope PABX system etc) for PIU, DDM. Capacity Component A: Reinforcing the URP-DNCC/G-4-3 / Procurement Countrys Emergency Single Stage - One IDA / 55990 Post Request for Bids Open - National 12,500.00 0.00 Canceled 2017-09-10 2017-09-25 2017-10-25 2017-12-09 2018-01-20 2018-04-20 of Motor Cycle Management Response Envelope Capacity Component A: Reinforcing the URP-DNCC/G-2-7 / Procurement Countrys Emergency Single Stage - One of Search and Rescue IDA / 55990 Post Request for Bids Open - National 148,600.00 0.00 Canceled 2017-09-20 2017-10-05 2017-11-19 2018-01-18 2018-03-08 2018-09-04 Management Response Envelope Equipment for City Corporations Capacity URP-DNCC/G-1-2 / Procurement of Specialized ICT Equipment Component A: Reinforcing the (VHF and HF Radio Terminals Countrys Emergency Single Stage - One IDA / 55990 Prior Request for Bids Open - International 2,401,700.00 0.00 Under Review 2017-07-16 2017-08-10 2017-07-31 2017-09-29 2018-01-27 2018-03-26 2018-09-22 and Related Installations) for City Management Response Envelope Corporation Capacity (Lot-1: VHF, Lot-2: HF) URP-DNCC/G-2-1 / Procurement Component A: Reinforcing the of Specialized Search and Countrys Emergency Single Stage - One IDA / 55990 Prior Request for Bids Open - International 12,000,000.00 6,856,362.37 Signed 2017-08-22 2017-08-25 2017-08-17 2017-10-06 2017-08-17 2017-10-09 2017-08-20 2017-10-15 2017-07-11 2018-12-09 Rescue Equipment (Emergency Management Response Envelope Tenders) for FSCD. Capacity URP-DNCC/G-3 / Procurement Component A: Reinforcing the of Heavy Equipment (Lot-1: Countrys Emergency Single Stage - One Crane, Lot-2: Wheel Type IDA / 55990 Prior Request for Bids Open - International 5,250,000.00 2,552,248.05 Signed 2017-08-24 2017-08-27 2017-10-08 2017-02-27 2017-12-07 2017-09-13 2018-02-03 2017-10-29 2018-10-01 Management Response Envelope Excavator, Lot-3: Chain Type Capacity Excavator, Lot-4: Dozer) Component A: Reinforcing the URP-DNCC/G-2-3 / Specialized Countrys Emergency Single Stage - One Search and Rescue Equipment IDA / 55990 Prior Request for Bids Open - International 2,053,488.00 1,942,500.00 Signed 2017-09-20 2017-09-20 2017-10-05 2018-05-21 2017-12-04 2017-12-20 2018-04-03 2018-05-27 2018-05-15 2018-07-05 2019-01-10 Management Response Envelope (Breathing Apparatus Tenders) Capacity Component A: Reinforcing the URP-DNCC/G-2-4 / Specialized Countrys Emergency Single Stage - One Search and Rescue Equipment IDA / 55990 Prior Request for Bids Open - International 2,818,100.00 1,127,810.50 Signed 2017-09-25 2017-10-09 2017-10-10 2017-12-21 2017-12-09 2018-01-08 2018-04-08 2018-04-11 2018-05-20 2018-06-04 2019-01-15 Management Response Envelope (Personal Protective Equipment) Capacity Component A: Reinforcing the URP-DNCC/G-2-8 / Rescuer Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 611,220.00 0.00 2017-10-01 2017-10-16 2017-11-27 2018-03-27 2018-05-08 2018-11-04 Carrying Vehicle (7.5 Ton Truck) Management Response Envelope Implementation Capacity Component D: Project BD-PCMU-32637-GO-RFB / Single Stage - One Pending IDA / 55990 Coordination, Monitoring, and Post Request for Bids Open - National 37,500.00 0.00 2018-01-31 2018-02-13 2018-02-28 2018-03-10 2018-03-29 2018-04-30 Computer and accessories Envelope Implementation Evaluation Component D: Project URP-PCMU/G-2A / Equipment/ Request for Single Stage - One Pending IDA / 55990 Coordination, Monitoring, and Post Open - National 6,250.00 0.00 2018-02-28 2018-04-30 2018-05-30 Machinery (Scanner, printer etc.) Quotations Envelope Implementation Evaluation Component D: Project URP-PCMU/G-5 / Office Single Stage - One Pending IDA / 55990 Coordination, Monitoring, and Post Request for Bids Open - National 50,000.00 0.00 2018-02-04 2018-02-25 2018-04-08 2018-05-08 2018-06-12 2018-07-12 Furniture and fixture Envelope Implementation Evaluation URP-DNCC/G-1-3 / Procurement Component A: Reinforcing the of Specialized ICT Equipment Countrys Emergency Single Stage - One Under IDA / 55990 Post Request for Bids Open - International 653,000.00 0.00 2017-12-24 2018-01-01 2018-01-08 2018-01-02 2018-03-19 2018-02-20 2018-07-03 2018-07-05 2018-08-14 2019-02-10 (UHF Radio Terminals and Management Response Envelope Implementation Related Installations) for DSCC Capacity Component A: Reinforcing the URP-DNCC/G-2-5 / Specialized Countrys Emergency Single Stage - One Pending Search and Rescue Equipment IDA / 55990 Post Request for Bids Open - National 27,450.00 0.00 2018-01-21 2018-02-05 2018-03-19 2018-06-02 2018-07-08 2019-01-04 Management Response Envelope Implementation (Rescuer Tools- Drone) for FSCD Capacity Page 2 URP/RAJUK/G-9 / Procurement of Earthquake & Seismic Component B: Vulnerability Single Stage - One Under Equipment for Vulnerability IDA / 55990 Assessment of Critical and Prior Request for Bids Open - International 3,545,450.00 0.00 2018-01-31 2018-02-25 2018-02-07 2018-04-26 2018-03-21 2018-04-26 2018-05-02 2018-06-06 2018-08-08 Envelope Implementation Assessment of Critical Assets Essential Facilities and etc. for URU URP/RAJUK/G-10 / Procurement of Earthquake & Component B: Vulnerability Single Stage - One Under Seismic Equipment for IDA / 55990 Assessment of Critical and Prior Request for Bids Open - International 3,389,610.00 0.00 2018-01-31 2018-02-07 2018-02-07 2018-04-26 2018-03-21 2018-04-26 2018-05-02 2018-06-06 2018-07-18 Envelope Implementation Developing Risk Sensitive Land Essential Facilities Use Planning and etc for URU. URP/RAJUK/G-11 / Procurement of Earthquake & Component B: Vulnerability Single Stage - One Seismic Equipment for IDA / 55990 Assessment of Critical and Prior Request for Bids Open - International 3,255,840.00 0.00 Canceled 2018-01-31 2018-02-25 2018-02-07 2018-04-26 2018-03-21 2018-05-08 2018-05-02 2018-06-30 2018-06-06 2018-12-03 Envelope Laboratory and field testing and Essential Facilities etc. for URU Component A: Reinforcing the URP/DDM/G-2 / Procurement of Countrys Emergency Request for Single Stage - One 4 units Micro-bus for NDMRTI IDA / 55990 Post Open - National 233,000.00 0.00 Canceled 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 Management Response Proposals Envelope and ERCC Capacity Component A: Reinforcing the BD-DDM-44873-GO-RFB / Countrys Emergency Single Stage - One Pending Procurement of 4 units Micro-bus IDA / 55990 Post Request for Bids Open - National 233,000.00 0.00 2018-01-28 2018-02-02 2018-03-16 2018-04-15 2018-05-20 2018-11-16 Management Response Envelope Implementation for NDMRTI and ERCC Capacity BD-DDM-44874-GO-RFQ / Component A: Reinforcing the Procurement of Telecom Countrys Emergency Request for Single Stage - One Under Equipment's (Land Telephone, IDA / 55990 Post Limited 9,000.00 0.00 2018-01-29 2018-03-01 2018-03-26 2018-09-22 Management Response Quotations Envelope Implementation PABX system, Mobile Phone Capacity etc. for PIU) Component A: Reinforcing the BD-DDM-44876-GO-RFB / Countrys Emergency Single Stage - One Pending Procurement of Office IDA / 55990 Post Request for Bids Open - National 60,000.00 0.00 2018-01-25 2018-01-30 2018-03-13 2018-04-12 2018-05-17 2018-11-13 Management Response Envelope Implementation Equipment's for PIU, DDM Capacity Component A: Reinforcing the BD-DDM-44878-GO-RFB / Countrys Emergency Single Stage - One Pending Procurement of Office Furniture IDA / 55990 Post Request for Bids Open - National 20,000.00 0.00 2018-01-28 2018-02-02 2018-03-16 2018-04-15 2018-05-20 2018-11-16 Management Response Envelope Implementation for PIU, DDM Capacity BD-DDM-44879-GO-RFB / Component A: Reinforcing the Procurement of Computer and Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 26,000.00 0.00 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2018-11-19 related Equipment's for PIU, Management Response Envelope Implementation DDM Capacity BD-DDM-45191-GO-RFB / Component A: Reinforcing the Procurement of Computer and Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - International 214,805.00 0.00 2018-02-04 2018-02-09 2018-03-23 2018-04-22 2018-05-27 2018-06-11 related Equipment for ERCC & Management Response Envelope Implementation NDMRTI Capacity Component A: Reinforcing the BD-DDM-45209-GO-RFB / Countrys Emergency Single Stage - One Pending Procurement of Office Equipment IDA / 55990 Post Request for Bids Open - International 155,130.00 0.00 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 2018-06-12 Management Response Envelope Implementation for ERCC & NDMRTI Capacity URP-DNCC/G-2-7N / Component A: Reinforcing the Procurement of Specialized Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 148,600.00 0.00 2018-03-01 2018-03-06 2018-04-17 2018-05-17 2018-06-21 2018-10-19 Search and Rescue Equipment Management Response Envelope Implementation for City Corporation Capacity Component A: Reinforcing the URP-DNCC/G-4-3N / Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 9,000.00 0.00 2018-02-25 2018-03-02 2018-04-13 2018-05-13 2018-06-17 2018-10-15 Procurement of Motorcycle Management Response Envelope Implementation Capacity Component B: Vulnerability Assessment of Critical and URP/RAJUK/G-4 / Supply of Essential Facilities Single Stage - One Under IDA / 55990 Post Request for Bids Open - National 389,610.00 0.00 2018-03-01 2018-05-21 2018-03-01 2018-03-31 2018-04-30 2018-06-04 2019-06-04 Furniture for PIU office Component C: Improved Envelope Implementation Construction, Urban Planning, and Development Component B: Vulnerability URP/RAJUK/G-1A / Mail domain Assessment of Critical and and its accessories purhase & Essential Facilities Request for Single Stage - One IDA / 55990 Post Open - National 6,490.00 0.00 Canceled 2017-09-21 2017-09-21 2017-09-21 installation for Emergecy Office Component C: Improved Quotations Envelope use of PIU, Construction, Urban Planning, and Development Component B: Vulnerability URP/RAJUK/G-14 / Variable Assessment of Critical and Refregerant Flow (VRF) Air Essential Facilities Single Stage - One Pending Conditioning system supply and IDA / 55990 Post Request for Bids Open - National 128,310.00 0.00 2018-04-01 2018-04-06 2018-05-06 2018-06-05 2018-07-10 2019-07-10 Component C: Improved Envelope Implementation installation for the renovation Construction, Urban Planning, work of URP, RAJUK and Development Component B: Vulnerability Assessment of Critical and URP/RAJUK/G-1-1 / Supply of Essential Facilities Single Stage - One Under Computer and Related IDA / 55990 Post Request for Bids Open - National 194,810.00 0.00 2018-05-01 2018-04-01 2018-05-06 2018-06-05 2018-04-19 2018-07-05 2018-06-05 2018-08-09 2019-08-09 Component C: Improved Envelope Implementation Equipment for PIU ,URP:RAJUK Construction, Urban Planning, and Development Component A: Reinforcing the URP-DNCC/G-2-9 / Procurement Countrys Emergency Single Stage - One Under of Turn Table Ladders Tender for IDA / 55990 Post Request for Bids Open - International 3,877,485.00 0.00 2018-03-15 2018-03-07 2018-03-30 2018-04-25 2018-05-29 2018-05-17 2018-09-12 2018-06-27 2018-10-24 2019-06-21 Management Response Envelope Implementation FSCD Capacity URP/RAJUK/G-3-1 / Component B: Vulnerability Procurement of Motor Vehicle for Assessment of Critical and PIU of URPRAJUK-Phase1 : Essential Facilities Single Stage - One Under IDA / 55990 Post Request for Bids Open - National 448,050.00 0.00 2018-03-11 2018-03-06 2018-03-14 2018-04-15 2018-04-09 2018-05-22 2018-04-25 2018-06-26 2019-06-26 i) 1no 4WD Sports Utility Vehicle Component C: Improved Envelope Implementation ii) 4 nos Double Cabin 4WD Pick- Construction, Urban Planning, up and iii) 1 no Microbus and Development Page 3 URP/RAJUK/G-3-2 / Component B: Vulnerability Procurement of Motor Vehicle for Assessment of Critical and PIU of URPRAJUK-Phase2 : Essential Facilities Single Stage - One Under IDA / 55990 Post Request for Bids Open - National 629,870.00 0.00 2018-04-08 2018-03-23 2018-04-08 2018-05-08 2018-04-16 2018-06-12 2018-04-25 2018-07-17 2019-07-17 i) 1no 4WD Sports Utility Vehicle Component C: Improved Envelope Implementation ii) 5 nos Double Cabin 4WD Pick- Construction, Urban Planning, up and iii) 3 no Microbus and Development Component A: Reinforcing the URP-DNCC/G-2-10 / Countrys Emergency Single Stage - One Pending Procurement of HazMat Tender IDA / 55990 Post Request for Bids Open - International 1,880,025.00 0.00 2018-07-15 2018-07-25 2018-09-28 2018-12-27 2019-02-07 2019-11-04 Management Response Envelope Implementation for FSCD Capacity Component D: Project BD-PCMU-60185-GO-RFB-A / Single Stage - One Pending IDA / 55990 Coordination, Monitoring, and Post Request for Bids Open - National 116,000.00 0.00 2018-08-23 2018-09-05 2018-09-20 2018-09-30 2018-10-19 2018-11-20 Procurement of Vehicles Envelope Implementation Evaluation URP-DNCC/G-2-11 / Component A: Reinforcing the Procurement of Search and Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - International 1,176,615.00 0.00 2018-08-20 2018-09-04 2018-11-03 2019-02-01 2019-03-16 2019-12-11 Rescue Equipment (Rescue Management Response Envelope Implementation Boat) Capacity Component A: Reinforcing the URP-DNCC/G-1-5 / Procurement Countrys Emergency Single Stage - One Pending of ICT Equipment for Emergency IDA / 55990 Post Request for Bids Open - International 3,000,000.00 0.00 2018-08-27 2018-09-11 2018-11-10 2019-02-08 2019-03-22 2019-12-17 Management Response Envelope Implementation Operation Center (EOC) at SCC Capacity URP-DNCC/G-1-6 / Procurement Component A: Reinforcing the of ICT Equipment for Command Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - International 3,000,000.00 0.00 2018-09-05 2018-09-20 2018-11-19 2019-02-17 2019-03-31 2019-12-26 and Control Room (CCR) at Management Response Envelope Implementation FSCD, Sylhet Capacity URP-DNCC/G-1-7 / Procurement Component A: Reinforcing the of ICT Equipment for Command Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - International 3,500,000.00 0.00 2018-09-10 2018-09-25 2018-11-24 2019-02-22 2019-04-05 2019-12-31 and Control Room (CCR) at Management Response Envelope Implementation FSCD, Dhaka Capacity URP-DNCC/G-1-11 / Component A: Reinforcing the Procurement of ICT Equipment Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 700,000.00 0.00 2018-10-01 2018-10-16 2018-11-30 2019-01-29 2019-03-12 2019-09-08 for Warehouses for DNCC and Management Response Envelope Implementation DSCC Capacity URP-DNCC/G-1-12 / Component A: Reinforcing the Procurement of ICT Equipment Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - International 3,250,000.00 0.00 2018-10-15 2018-10-30 2018-12-29 2019-03-29 2019-05-10 2020-02-04 for Emergency Operation Center Management Response Envelope Implementation (EOC) at DSCC Capacity NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Reinforcing the URP-DNCC/NS-1 / Selection of Countrys Emergency Single Stage - One IDA / 55990 Post Request for Bids Open - National 81,250.00 0.00 Canceled 2017-08-20 2017-09-04 2017-10-19 2017-12-03 2018-01-14 2020-12-29 Pre-Shipment Inspection Firm Management Response Envelope Capacity Component A: Reinforcing the URP-DNCC/NS-2 / Selection of Countrys Emergency Single Stage - One Clearing and Forwarding Agent IDA / 55990 Post Request for Bids Open - National 468,750.00 0.00 Canceled 2017-09-17 2017-10-02 2017-11-16 2017-12-31 2018-02-11 2020-12-27 Management Response Envelope (Firm) Capacity Component A: Reinforcing the URP-DNCC/NCS-1N / Selection Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 125,800.00 0.00 2018-03-01 2018-03-06 2018-04-17 2018-05-17 2018-06-21 2019-12-31 of Pre-Shipment Inspection Firm Management Response Envelope Implementation Capacity Component A: Reinforcing the URP-DNCC/NCS-2N / Selection Countrys Emergency Single Stage - One Pending of Clearing and Forwarding Agent IDA / 55990 Post Request for Bids Open - National 156,250.00 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2020-06-30 Management Response Envelope Implementation Firm Capacity BD-PCMU-60438-NC-RFP / Component D: Project Single Stage - Two Pending Supply of Manpower through IDA / 55990 Coordination, Monitoring, and Post Request for Bids Open - National 143,000.00 0.00 2018-06-30 2018-06-30 2018-06-30 2018-07-15 2018-07-22 2020-06-30 Envelope Implementation Outsourcing Evaluation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual URP/DDM/S-3 / Procurement of Consultancy Services for Training Exercises and Drills (TED) Program for the MoDMR, FSCD , Component E: Contingent Quality Based DNCC, DSCC & SCC and related IDA / 55990 Prior Open - International 10,000,000.00 0.00 Canceled 2017-05-14 2017-05-14 2017-06-28 2017-07-12 2017-07-26 2017-08-02 2017-09-06 2020-02-23 Emergency Response Selection institutions of the Government of Bangladesh involved in the Disaster Risk Management of Dhaka and Sylhet URP/RAJUK/S-6 / Consultancy Component C: Improved Quality And Cost- Under Services for Operationalizing the IDA / 55990 Construction, Urban Planning, Prior Open - International 3,522,730.00 0.00 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2018-02-09 2017-10-20 2018-04-15 2017-12-01 2018-05-22 2018-02-16 2018-06-30 2018-03-23 2020-06-30 Based Selection Implementation URU in RAJUK and Development URP/RAJUK/S-7 / Assessing the Current State and Deploying Component C: Improved a Web-based Integrated Quality And Cost- Under IDA / 55990 Construction, Urban Planning, Prior Open - International 1,998,260.00 0.00 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2018-02-09 2017-10-20 2017-12-01 2018-05-19 2018-02-16 2018-06-30 2018-03-23 2020-06-30 Information Management System Based Selection Implementation and Development for the Construction Permit System of RAJUK URP/RAJUK/S-8 / Consultancy Component C: Improved Quality And Cost- Under Services for Professional IDA / 55990 Construction, Urban Planning, Prior Open - International 3,542,210.00 0.00 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2018-02-09 2017-10-20 2017-11-19 2018-05-21 2018-03-04 2018-04-08 2020-06-30 Based Selection Implementation Accreditation Program in RAJUK and Development Page 4 BD-DDM-28928-CS-QBS / Selection of Consulting Services Component A: Reinforcing the Consultant on "Design and Supervision Countrys Emergency Under IDA / 55990 Post Qualification Open - National 37,500.00 0.00 2017-09-21 2017-10-04 2017-10-12 2017-11-25 2017-12-25 2018-01-29 2018-07-28 consultancy" for outfit NDMRTI & Management Response Implementation Selection ERCC Facilities in Dhaka and Capacity Sylhet URP/RAJUK/S-4 / Consultancy Services for Vulnerability Component B: Vulnerability Quality And Cost- Under Assessment and Prioritized IDA / 55990 Assessment of Critical and Prior Open - International 6,781,520.00 0.00 2017-09-21 2017-09-21 2017-10-05 2017-11-02 2017-11-09 2018-01-31 2018-06-10 2018-03-14 2018-04-18 2020-06-30 Based Selection Implementation Investment Plan for Critical Essential Facilities Assets in Dhaka for URU BD-DDM-29946-CS-QBS / Component A: Reinforcing the Consultancy Services for Training Countrys Emergency Quality And Cost- Under IDA / 55990 Prior Open - International 10,000,000.00 0.00 2017-09-25 2017-10-02 2017-10-16 2017-10-09 2017-11-29 2018-02-05 2017-12-27 2018-03-13 2018-01-26 2018-05-12 2018-03-02 2018-07-22 2018-04-06 2019-04-06 Exercises and Drills (TED) Management Response Based Selection Implementation Program Capacity URP/RAJUK/S-5 / Consultancy Component B: Vulnerability Services for Development of a Quality And Cost- Under IDA / 55990 Assessment of Critical and Prior Open - International 6,296,550.00 0.00 2017-10-04 2017-10-04 2017-10-18 2017-11-15 2017-11-07 2018-02-13 2018-04-12 2018-03-27 2018-05-01 2020-06-30 Risk-sensitive Land Use Planning Based Selection Implementation Essential Facilities Practice for URU URP-PCMU/S-1 / Monitoring Component D: Project Quality And Cost- and Evaluation Consultancy IDA / 55990 Coordination, Monitoring, and Prior Open - International 2,160,493.00 1,779,014.75 Signed 2017-05-21 2017-05-21 2017-05-21 2018-02-08 2017-06-04 2017-06-04 2017-10-16 2018-02-12 2018-01-28 2018-03-22 2018-03-15 2018-04-11 2020-06-30 Based Selection through a Firm Evaluation Component D: Project URP-PGMU/S-2 / Internal Audit Quality And Cost- Under IDA / 55990 Coordination, Monitoring, and Post Open - National 121,950.00 0.00 2017-05-21 2017-04-27 2017-05-21 2017-10-26 2017-11-30 2018-01-31 2018-02-18 2018-03-24 2020-06-30 through a Firm Based Selection Implementation Evaluation URP/RAJUK/S-11 / Consultancy Services for Design and Supervision of Urban Resilience Component B: Vulnerability Quality And Cost- Under Unit (URU) Building including IDA / 55990 Assessment of Critical and Prior Open - International 2,425,950.00 0.00 2017-10-04 2017-10-04 2018-02-11 2018-03-11 2018-06-09 2018-04-03 2018-07-21 2018-07-23 2018-08-25 2020-10-24 Based Selection Implementation Research, Training, and Testing Essential Facilities Laboratory facilities under RAJUK in Dhaka, Bangladesh URP/RAJUK/S-9 / Consultancy Component C: Improved Quality And Cost- Under Services for Building Code IDA / 55990 Construction, Urban Planning, Prior Open - International 3,240,260.00 0.00 2017-09-21 2017-09-21 2018-03-11 2018-02-09 2018-04-22 2018-07-21 2018-05-21 2018-09-08 2018-07-23 2018-10-13 2020-10-30 Based Selection Implementation Enforcement and Development URP-DNCC/S-7 / GIS- Phase 1: Component A: Reinforcing the Need Assessment for Consultant Countrys Emergency Pending Implementation of GIS IDA / 55990 Post Qualification Open - National 178,600.00 0.00 2018-10-30 2018-11-20 2019-02-03 2019-04-04 2019-05-16 2019-11-12 Management Response Implementation Infrastructure in the Urban Selection Capacity Resilience Project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response Component D: Project Individual Consultant S1 / Procurement Specialist IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 285,867.35 Signed 2016-04-28 2016-05-05 Selection Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response S2 / Senior Financial Component D: Project Individual Consultant Management & Planning IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 285,867.35 Signed 2016-04-28 2016-05-05 Selection Specialist Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response Component D: Project URP-DDM-1/ S1 / Procurement Individual Consultant IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 56,452.65 Signed 2016-05-24 2016-05-26 Specialist (Individual) Selection Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Page 5 Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response URP-DDM-1/ S2 / Financial Component D: Project Individual Consultant Management Specialist IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 54,164.03 Signed 2016-05-24 2016-05-26 Selection (Individual) Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response URP-DNCC/S-4 / International Component D: Project Consultant: Information & Individual Consultant IDA / 55990 Coordination, Monitoring, and Prior Open N 304,430.00 304,430.00 Signed 2016-05-05 2016-06-01 Communication Technology (ICT) Selection Evaluation Specialist Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response URP- DNCC/ S-1 / Individual Component D: Project Individual Consultant Consultant as Procurement IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 226,765.77 Signed 2016-08-01 2016-04-20 Selection Specialist (National) Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response Component D: Project URP-DNCC/S-3 / International Individual Consultant IDA / 55990 Coordination, Monitoring, and Prior Open N 383,300.00 383,300.00 Signed 2016-05-10 2016-06-01 Search and Rescue Expert Selection Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the URP-DNCC/S-5-3 / Procurement Countrys Emergency Individual Consultant Under IDA / 55990 Post Open 14,100.00 0.00 2017-05-14 2017-07-27 2017-08-17 2017-09-21 2018-03-20 of Junior Procurement Consultant Management Response Selection Implementation Capacity Component D: Project URP-PCMU/S-5 / Financial Individual Consultant Pending IDA / 55990 Coordination, Monitoring, and Prior Open 219,500.00 0.00 2017-05-21 2017-05-21 2017-05-28 2017-07-16 2018-07-15 Management Specialist Selection Implementation Evaluation Component D: Project URP-PCMU/S-10 / Procurement Individual Consultant Pending IDA / 55990 Coordination, Monitoring, and Prior Open 65,850.00 0.00 2017-05-21 2017-05-21 2017-05-21 2017-05-21 2017-10-29 Consultant (National) Selection Implementation Evaluation URP-DNCC/S-2 / Individual Component A: Reinforcing the Consultant as Financial Countrys Emergency Individual Consultant Under IDA / 55990 Prior Open 210,000.00 0.00 2017-08-15 2017-06-20 2017-11-28 2017-12-13 2018-01-18 2020-12-31 Management and Planning Management Response Selection Implementation Specialist (National) Capacity Component B: Vulnerability URP/RAJUK/S-13 / Assessment of Critical and Environmental Impact Essential Facilities Individual Consultant Pending Assessment of Proposed 30 IDA / 55990 Post Limited 15,580.00 0.00 2018-04-30 2018-05-05 2018-05-26 2018-06-30 2018-12-27 Component C: Improved Selection Implementation storied Urban Resilience Unit Construction, Urban Planning, Building and Development Component D: Project URP-PCMU/S8 / Training Need Individual Consultant Pending IDA / 55990 Coordination, Monitoring, and Post Open 17,650.00 0.00 2018-05-20 2018-07-08 2018-07-29 2018-09-02 2019-03-01 Assessment Specialist Selection Implementation Evaluation Component B: Vulnerability Assessment of Critical and URP/RAJUK/S-3 / Procurement Essential Facilities Individual Consultant IDA / 55990 Post Limited 162,337.66 110,481.66 Signed 2018-06-03 2018-05-31 2018-06-08 2018-05-31 2018-06-29 2018-06-04 2018-08-03 2018-07-01 2019-01-30 Specialist Component C: Improved Selection Construction, Urban Planning, and Development Component A: Reinforcing the URP-DNCC/S-1A / Selection of Countrys Emergency Individual Consultant Pending Procurement Specialist (Senior IDA / 55990 Post Open 140,000.00 0.00 2018-10-01 2019-01-14 2019-01-29 2019-03-13 2020-10-31 Management Response Selection Implementation National Consultant) Capacity Page 6