The World Bank Report No: ISR14973 Implementation Status & Results Lebanon LB: Mobile Internet Ecosystem Project (MIEP) (P131202) Public Disclosure Copy Operation Name: LB: Mobile Internet Ecosystem Project (MIEP) (P131202) Project Stage: Implementation Seq.No: 2 Status: ARCHIVED Archive Date: 20-Jun-2014 Country: Lebanon Approval FY: 2014 Product Line: IBRD/IDA Region: MIDDLE EAST AND NORTH AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Ministry of Telecommunications Key Dates Board Approval Date 31-Jul-2013 Original Closing Date 31-Dec-2017 Planned Mid Term Review Date Last Archived ISR Date 24-Dec-2013 Effectiveness Date Revised Closing Date 31-Dec-2017 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to strengthen innovation and entrepreneurship in the Lebanese Mobile Internet Ecosystem. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Component 1: Skills development and attraction of talent. 1.75 Component 2: Strengthening and growth of mobile internet industry. 2.90 Component 3: Enhancement of mobile internet enabling environment 0.50 Component 4: Project management 0.75 Contingency 0.50 Contingency 0.50 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Unsatisfactory Unsatisfactory Overall Risk Rating High High Implementation Status Overview Project is still pending approval by Council of Ministers and ratification by Parliament; it will need to be approved by the Council of Ministers and be ratified by Parliament to become effective before December 31, 2014. These are pre-requisites for signing the Loan Agreement. Page 1 of 4 The World Bank Report No: ISR14973 Locations Country First Administrative Division Location Planned Actual Lebanon Beyrouth Beirut ✔ Public Disclosure Copy Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Increased number of startup projects in the ICT Number Value 0.00 60.00 sector (particularly mobile internet) Date 17-Sep-2012 30-Jun-2017 Comments Number of graduates participating in the Number Value 0.00 500.00 program who work in domestic ICT industry Date 17-Sep-2012 30-Jun-2017 Comments Percentage of project beneficiaries satisfied Percentage Value 0.00 85.00 with MiHub services Date 17-Sep-2012 30-Jun-2017 Comments Impact on IT/ITES Sector of World Bank Number Value 1.00 3.00 Technical Assistance (composite score: 1 # low Date 17-Sep-2012 30-Jun-2017 impact to 5 # high impact) Comments Direct project beneficiaries Number Value 0.00 50000.00 Date 17-Sep-2012 30-Jun-2017 Comments Female beneficiaries Percentage Value 0.00 35.00 Sub Type Supplemental Public Disclosure Copy Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of mobile applications competitions Number Value 0.00 9.00 hosted Date 17-Sep-2012 30-Jun-2017 Comments Page 2 of 4 The World Bank Report No: ISR14973 Number of graduates participating in Number Value 0.00 500.00 internships Date 17-Sep-2012 30-Jun-2017 Comments Public Disclosure Copy Number of project beneficiaries participating in Number Value 0.00 80.00 ICT start-up projects Date 17-Sep-2012 30-Jun-2017 Comments Number of Industry Hub beneficiaries Number Value 0.00 500.00 Date 17-Sep-2012 30-Jun-2017 Comments Number of vertical industries participating in Number Value 0.00 20.00 clusters Date 17-Sep-2012 30-Jun-2017 Comments Manpower trained /mentored under component Number Value 0.00 3200.00 2 Date 17-Sep-2012 30-Jun-2017 Comments Number of recommendations regarding the Number Value 0.00 5.00 legal and regulatory environment that are Date 17-Sep-2012 30-Jun-2017 implemented by the Government Comments Data on Financial Performance (as of 01-Aug-2013) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P131202 IBRD-82650 Not Effective 31-Jul-2013 31-Dec-2017 31-Dec-2017 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Public Disclosure Copy P131202 IBRD-82650 Not Effective USD 6.40 6.40 0.00 0.00 6.40 0.00 Disbursement Graph Page 3 of 4 The World Bank Report No: ISR14973 Public Disclosure Copy Key Decisions Regarding Implementation N/A Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Public Disclosure Copy Page 4 of 4