REPUBLIC OF MOZAMBIQUE MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT Agriculture and Natural Resources Landscape Management Project (ANRLMP) Project No: P149620 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 2017] 2. Date of General Procurement Notice: July 26, 2016. 3. Period covered by this procurement plan: April 2017 to October 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) and (Non- Above US$ 1,500,000 All Consultant Services) 3. ICB (Works) Above US$ 5,000,000 All 4. NCB (Works) Above US$ 5,000,000 All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As per paragraphs 3.17 of the Guidelines and Project Procurement Manual. 4. Reference to (if any) Project Operational/Procurement Manual: Items to be financed under this Credit/Grants will be procured in line with rules in the Operational Manual, Credit/Grants Agreement and Project Procurement Manual. 5. Any Other Special Procurement Arrangements: Not Applicable. 1 Date: April 19, 2017 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Estimated Review Domestic Ref. Cost by Bank Description Packages Preference Comments No. US$ (Prior / (yes/no) thousands Post) Summary of the NCB 1 1,791,00 5 No Post (Works) Summary of NCB 2 1,822,60 7 No Post (Goods) Summary of the NCB 3 (Non-Consulting 775,00 1 No Prior Services) Summary of the 4 249,6 6 No Post Shopping (Goods) Summary of the 5 Shopping (Non- 20,00 1 No Post Consulting Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) ≥ 200,000 2. Individual ≥ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 2 Date: April 19, 2017 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Estimated Review Description of Ref. No. Cost by Bank Assignment Packages Comments US$ (Prior / thousands Post) Summary of number of 17.800,00 6 Prior 1 contracts that will be let under QCBS 2 Individuals 495.00 6 Prior 3 Individuals 2.210,8 32 Post 3 Date: April 19, 2017 PROCUREMENT Mozambique : Moz Agriculture and Natural Resources Landscape Management Project PLAN General Information Country: Mozambique Banks Approval Date of the Original Procurement Plan: 2016-07-13 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-06-01 Project ID: P149620 GPN Date: 2016-07-28 Project Name: Moz Agriculture and Natural Resources Landscape Management Project Loan / Credit No: IDA / D1190, IDA / 58550, IDA / Q9900 Executing Agency(ies): MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT - International Funds Management Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 04/W/ARLNMP/16 / IDA / D1190 Agriculture and Forest-Based Single Stage - One Pending Rehabilitation of existing Post Request for Bids Open - National 500,000.00 0.00 2017-10-30 2017-11-06 2017-12-18 2018-01-17 2018-02-21 2019-12-26 IDA / 58550 Value Chain Development Envelope Implementation Irrigation Schemes 03/W/ARLNMP/16 / IDA / D1190 Agriculture and Forest-Based Single Stage - One Pending Rehabilitation of existing Post Request for Bids Open - National 500,000.00 0.00 2017-10-30 2017-11-06 2017-12-18 2018-01-17 2018-02-21 2018-08-20 IDA / 58550 Value Chain Development Envelope Implementation Irrigation Schemes Securing Land Tenure Rights 64/W/ANRLMP/17 / Single Stage - One Pending IDA / 58550 and Increasing Natural Post Request for Bids Open - National 366,000.00 0.00 2017-06-30 2017-07-07 2017-08-18 2017-09-18 2017-10-23 2018-04-23 Rehabilitation of the data center Envelope Implementation Resources Resilience 01/ARLMP/W/16 / Rural Roads IDA / D1190 Agriculture and Forest-Based Single Stage - One Pending Post Request for Bids Open - National 270,000.00 0.00 2017-06-12 2017-06-19 2017-07-31 2017-08-30 2017-10-04 2018-04-02 Spot Improvements IDA / 58550 Value Chain Development Envelope Implementation 02/W/ARLNMP/16 / Rural IDA / D1190 Agriculture and Forest-Based Single Stage - One Pending Post Request for Bids Open - National 300,000.00 0.00 2017-06-15 2017-06-21 2017-08-02 2017-09-01 2017-10-06 2018-04-04 Roads Spot Improvement IDA / 58550 Value Chain Development Envelope Implementation GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 05/G/ARLNMP/16 / IT Project Coordination and Request for Single Stage - One Pending IDA / D1190 Post Open - National 5,000.00 0.00 2017-03-20 2017-05-15 2017-11-15 Equipament Management Quotations Envelope Implementation Project Coordination and Single Stage - One Under 01/G/ANRLMP/16 / Vehicles IDA / Q9900 Post Request for Bids Open - National 200,000.00 0.00 2016-08-29 2016-08-29 2016-09-03 2016-10-15 2016-11-14 2017-03-20 2017-09-16 Management Envelope Implementation Securing Land Tenure Rights 10/G/ANRLMP/16 / Satelite IDA / 58550 Single Stage - One and Increasing Natural Prior Request for Bids Open - National 775,000.00 0.00 Canceled 2016-11-01 2016-11-07 2016-12-20 2017-01-19 2017-02-23 2017-08-22 picture aquisition IDA / D1190 Envelope Resources Resilience 6/G/ARLNMP/16 / IT IDA / D1190 Project Coordination and Single Stage - One Pending Post Request for Bids Open - National 219,600.00 0.00 2017-03-30 2017-04-04 2017-05-16 2017-06-15 2017-10-19 2018-02-12 Equipament IDA / 58550 Management Envelope Implementation 09/G/ARLNMP/16 / Office Project Coordination and Request for Single Stage - One Pending IDA / D1190 Post Open - National 46,600.00 0.00 2017-04-04 2017-05-30 2017-11-26 Supplies Management Quotations Envelope Implementation 60/G/ANRLMP/2016 / Office Project Coordination and Request for Single Stage - One Pending IDA / Q9900 Post Limited 56,500.00 0.00 2016-12-14 2017-02-08 2017-08-07 Suplies Management Quotations Envelope Implementation 61/G/ANRLMP/17 / IT Securing Land Tenure Rights Equipment for revitalization of the Single Stage - One Pending IDA / 58550 and Increasing Natural Post Request for Bids Open - National 207,000.00 0.00 2017-08-30 2017-09-06 2017-10-18 2017-11-17 2017-12-22 2018-06-20 data center in the field of Envelope Implementation Resources Resilience institutional support Securing Land Tenure Rights 63/G/ANRLMP/17 / Equipment Single Stage - One Pending IDA / 58550 and Increasing Natural Post Request for Bids Open - National 243,000.00 0.00 2017-08-30 2017-09-05 2017-10-17 2017-11-16 2017-12-21 2018-06-19 for datacenter revitalization Envelope Implementation Resources Resilience 73/G/ANRLMP/17 / Aquisition for tractors and accessories for Agriculture and Forest-Based Single Stage - One Under IDA / D1190 Post Request for Bids Open - National 1,107,000.00 0.00 2017-05-19 2017-05-23 2017-05-24 2017-07-05 2017-08-04 2017-09-08 2018-03-07 Small Emerging Commercial Value Chain Development Envelope Implementation Farmers 71/G/ANRLMP/17 / IT Project Coordination and Request for Single Stage - One Pending Equipament for Matching Grant IDA / D1190 Post Limited 29,000.00 0.00 2017-06-08 2017-06-29 2017-12-26 Management Quotations Envelope Implementation Unit 72/G/ANRLMP/17 / IT Project Coordination and Request for Single Stage - One Pending Equipament for Agriculture IDA / D1190 Post Limited 52,500.00 0.00 2017-08-28 2017-10-23 2018-04-21 Management Quotations Envelope Implementation Hidraulic/Irrigation team IDA / D1190 Project Coordination and Single Stage - One Pending 08/ARLNMP/G/16 / Vehicles Post Request for Bids Open - National 100,000.00 0.00 2017-10-31 2017-11-07 2017-12-19 2018-01-18 2018-05-24 2018-11-20 IDA / 58550 Management Envelope Implementation 62/G/ANRLMP/17 / Office Securing Land Tenure Rights Request for Single Stage - One Pending furniture in the scope of IDA / 58550 and Increasing Natural Post Open - National 60,000.00 0.00 2017-09-11 2017-11-06 2018-05-05 Quotations Envelope Implementation institutional support Resources Resilience Securing Land Tenure Rights Single Stage - One Pending 07/G/ARLNMP/16 / Motorcycles IDA / D1190 and Increasing Natural Post Request for Bids Open - National 78,000.00 0.00 2017-10-02 2017-10-09 2017-11-21 2017-12-21 2018-01-25 2018-07-24 Envelope Implementation Resources Resilience NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Securing Land Tenure Rights 10/NC/ANRLMP/16 / Satelite IDA / D1190 Single Stage - One and Increasing Natural Prior Request for Bids Open - National 775,000.00 621,474.24 Signed 2016-11-01 2016-10-13 2016-11-04 2016-10-27 2016-12-16 2016-11-15 2017-01-16 2017-01-30 2017-02-20 2017-05-17 2017-08-19 Picture Aquisition IDA / 58550 Envelope Resources Resilience 21/NC/ANRLMP/16 / Hiring a Project Coordination and Request for Single Stage - One company to create the slogan, IDA / D1190 Post Open - National 20,000.00 0.00 Canceled 2016-10-16 2016-12-11 2017-06-09 Management Quotations Envelope website, logo. 20/NC/ANRLMP/16 / Hiring company to advertise material Project Coordination and Request for Single Stage - One Pending IDA / D1190 Post Open - National 20,000.00 0.00 2016-12-15 2017-02-09 2018-02-09 supply (Posters, Printing, Flyers Management Quotations Envelope Implementation and other placartes) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 18/ARLNMP/C/16 / Design and Securing Land Tenure Rights IDA / D1190 Quality And Cost- Under Supervision of Irrigation Schemes and Increasing Natural Prior Open - International 500,000.00 0.00 2016-08-08 2016-12-14 2016-08-29 2016-10-12 2016-11-09 2016-12-09 2017-01-13 2017-02-17 2018-02-17 IDA / 58550 Based Selection Implementation (Rehabilitation) Resources Resilience 11/CS/ANRLMP/16 / Service Agriculture and Forest-Based Quality And Cost- Under Provider for Value Chain IDA / D1190 Prior Open - International 6,000,000.00 0.00 2016-08-26 2016-08-31 2016-09-16 2016-10-30 2016-12-27 2016-11-27 2017-03-07 2016-12-27 2017-04-15 2017-01-31 2017-03-07 2018-03-07 Value Chain Development Based Selection Implementation development 12/CS/ANRLMP/16 / Service Agriculture and Forest-Based Quality And Cost- Pending Provider-Restauration of IDA / 58550 Prior Open - International 4,000,000.00 0.00 2017-01-16 2017-02-06 2017-03-22 2017-04-19 2017-05-19 2017-06-23 2017-07-28 2018-07-28 Value Chain Development Based Selection Implementation degraded land 19/CS/ANRLMP/16 / Service Securing Land Tenure Rights Quality And Cost- Under Provider for Sistematic IDA / 58550 and Increasing Natural Prior Open - International 6,000,000.00 0.00 2016-08-26 2016-09-30 2016-09-01 2016-09-27 2017-01-09 2016-10-25 2017-03-14 2016-11-24 2017-04-15 2016-12-29 2017-02-02 2018-02-02 Based Selection Implementation community land delimitation Resources Resilience Consultant 14-CS/ANRLMP/16 / River basin IDA / 58550 Agriculture and Forest-Based Prior Qualification Open - International 750,000.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-20 2016-11-19 2016-12-22 2017-10-30 Studies IDA / D1190 Value Chain Development Selection Consultant 15-CS/ANRLMP/16 / River basin IDA / 58550 Agriculture and Forest-Based Prior Qualification Open - International 750,000.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-20 2016-11-21 2016-12-26 2017-06-24 studies IDA / D1190 Value Chain Development Selection 14/CS/ANRLMP/16 / River Basin Agriculture and Forest-Based Quality And Cost- Under IDA / D1190 Prior Open - International 750,000.00 0.00 2016-08-29 2016-09-28 2016-09-19 2016-11-02 2016-12-07 2016-11-30 2017-02-16 2016-12-30 2017-04-06 2017-02-03 2017-03-10 2018-03-10 Studies Value Chain Development Based Selection Implementation 15/CS/ANRLMP/16 / River Basin Agriculture and Forest-Based Quality And Cost- Under IDA / D1190 Prior Open - International 750,000.00 0.00 2016-08-29 2016-09-29 2016-09-19 2016-11-02 2016-12-07 2016-11-30 2017-02-16 2016-12-30 2017-03-30 2017-02-03 2017-03-10 2018-03-10 Studies Value Chain Development Based Selection Implementation 18/CS/ANRLMP/16 / Service Securing Land Tenure Rights Consultant Provider for systematic IDA / 58550 and Increasing Natural Prior Qualification Open - International 2,993,980.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-22 2016-11-21 2016-12-26 2017-06-24 community land delimitation Resources Resilience Selection 32-CS/ANRLMP/16 / Baseline Project Coordination and Quality And Cost- IDA / Q9900 Post Open - National 127,000.00 0.00 Canceled 2016-08-30 2016-08-29 2016-09-20 2016-11-03 2016-12-01 2017-01-01 2017-02-05 2017-03-12 2018-03-12 Survey Management Based Selection 32/CS/ANRLMP/16 / Baseline Project Coordination and Quality And Cost- Under IDA / Q9900 Prior Open - International 200,000.00 0.00 2016-10-06 2016-09-30 2016-10-27 2016-10-06 2016-12-09 2017-03-20 2017-01-06 2017-04-21 2017-02-06 2017-03-13 2017-04-17 2018-04-17 Sutudy Management Based Selection Implementation 21/CS/ANRLMP/16 / Hiring a Consultant Project Coordination and company to create the slogan, IDA / D1190 Post Qualification Open - National 10,000.00 0.00 Canceled 2016-10-10 2016-10-31 2016-12-14 2017-01-14 2017-02-18 2017-08-17 Management website,logo Selection MZ-UGFI-4758-CS-QCBS / Hire Agriculture and Forest-Based Quality And Cost- Under service provider to administer the IDA / D1190 Prior Open - International 300,000.00 0.00 2017-01-16 2017-01-25 2017-02-06 2017-02-01 2017-03-22 2017-05-09 2017-04-19 2017-05-19 2017-06-26 2017-07-31 2018-07-31 Value Chain Development Based Selection Implementation partial credit guarantee scheme INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 34/IC/ANRLMP/16 / Finance Project Coordination and Individual Consultant Under IDA / Q9900 Prior Open 90,000.00 0.00 2017-03-18 2017-03-23 2017-05-08 2017-05-29 2017-07-03 2017-12-30 Manager Management Selection Implementation 38/IC/ANRLMP/16 / Matching IDA / D1190 Project Coordination and Individual Consultant Under Post Open 108,000.00 0.00 2016-10-19 2016-08-29 2016-12-07 2017-01-18 2016-12-28 2017-01-24 2017-02-01 2017-07-31 Grants Manager IDA / 58550 Management Selection Implementation 41/IC/ANRLMP/16 / Financial IDA / D1190 Project Coordination and Individual Consultant Pending Post Open 54,000.00 0.00 2016-10-19 2016-12-07 2016-12-28 2017-02-01 2017-07-31 and Admnistrative Officer IDA / 58550 Management Selection Implementation 53/IC/ANRLMP/16 / Project Coordination and Individual Consultant Pending Administrative and Financial IDA / Q9900 Post Open 10,800.00 0.00 2017-12-26 2018-02-13 2018-03-06 2018-04-10 2018-10-07 Management Selection Implementation Assistant 36/IC/ANRLMP/16 / Finance Project Coordination and Individual Consultant Under IDA / Q9900 Prior Open 72,000.00 0.00 2017-02-13 2017-04-03 2017-04-24 2017-05-29 2018-11-20 Assistant Management Selection Implementation 40/IC/ANRLMP/16 / Technical IDA / D1190 Project Coordination and Individual Consultant Pending Post Open 72,000.00 0.00 2017-02-14 2017-04-04 2017-04-25 2017-05-30 2018-11-21 Advisor for Matching Grant IDA / 58550 Management Selection Implementation 47/IC/ANRLMP/16 / Project Coordination and Individual Consultant Pending Administrative and Financial IDA / Q9900 Post Open 10,800.00 0.00 2018-02-14 2018-04-04 2018-04-25 2018-05-30 2019-11-21 Management Selection Implementation Assistant 39/IC/ANRLMP/16 / Technical IDA / D1190 Project Coordination and Individual Consultant Pending Post Open 72,000.00 0.00 2017-02-14 2017-04-04 2017-04-25 2017-05-30 2018-11-21 Advisor for Matching Grant IDA / 58550 Management Selection Implementation Project Coordination and Individual Consultant Under CS23 / Procurement Specialist IDA / Q9900 Prior Open - National 99,000.00 0.00 2016-07-13 2016-07-13 2016-08-31 2016-09-21 2016-10-26 2018-06-30 Management Selection Implementation Page 2 69/IC/ANRLMP/17 / Project Coordination and Individual Consultant Pending Environmental and Social IDA / D1190 Post Open 12,000.00 0.00 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Management Selection Implementation Safeguard Specialist 66/IC/ANRLMP/17 / Civil Project Coordination and Individual Consultant Pending IDA / D1190 Post Open 60,000.00 0.00 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Engineer Management Selection Implementation 68/IC/ANRLMP/17 / GIS Project Coordination and Individual Consultant Pending IDA / D1190 Post Open 16,000.00 0.00 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Specialist Management Selection Implementation 24/IC/ANRLMP/16 / Forest Project Coordination and Individual Consultant Pending IDA / Q9900 Post Open 108,000.00 0.00 2017-05-01 2017-06-19 2017-07-10 2017-08-14 2018-02-10 Specialist Management Selection Implementation 74/IC/ANRLMP/17 / Project Project Coordination and Individual Consultant Pending IDA / D1190 Post Open 82,500.00 0.00 2017-06-05 2017-06-19 2017-06-19 2017-07-10 2018-01-06 Coordinator for ANRLMP Management Selection Implementation 65/IC/ANRLMP/17 / Senior Project Coordination and Individual Consultant IDA / D1190 Post Open 84,000.00 0.00 Canceled 2017-04-05 2017-04-25 2017-05-01 2017-05-08 2017-06-05 2017-12-02 Agricultural Hidraulics Specialist Management Selection Project Coordination and Individual Consultant Pending 67/IC/ANRLMP/17 / Topographer IDA / D1190 Post Open 24,000.00 0.00 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 Management Selection Implementation 23/IC/ANRLMP/16 / National Project Coordination and Individual Consultant IDA / Q9900 Post Open 129,600.00 0.00 Canceled 2017-05-30 2017-07-18 2017-08-08 2017-09-12 2018-03-11 Coordinator Management Selection 29/IC/ANRLMP/16 / Project Coordination and Individual Consultant Environmental/Resilience IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Management Selection Specialist 26/IC/ANRLMP/16 / Rural Project Coordination and Individual Consultant IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Development Specialist Management Selection 31/IC/ANRLMP/16 / Project Coordination and Individual Consultant IDA / Q9900 Prior Open 90,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Procurement Manager Management Selection 27/IC/ANRLMP/16 / Land Project Coordination and Individual Consultant IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Administration Specialist Management Selection 52/IC/ANRLMP/16 / Natural Project Coordination and Individual Consultant Resaurce Specialist Field IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Selection Operator 35/IC/ANRLMP/16 / Project Coordination and Individual Consultant IDA / Q9900 Prior Open 72,000.00 0.00 Canceled 2017-12-29 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Procurement Assistant Management Selection 42/IC/ANRLMP/16 / Provincial Project Coordination and Individual Consultant IDA / Q9900 Post Open 90,000.00 0.00 Canceled 2017-08-02 2017-09-20 2017-10-11 2017-11-15 2018-05-14 Coordinator Management Selection 33/IC/ANRLMP/16 / Project Coordination and Individual Consultant IDA / Q9900 Prior Open 72,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Procurement Assistant Management Selection 37/IC/ANRLMP/16 / M&E Project Coordination and Individual Consultant IDA / Q9900 Post Open 90,000.00 0.00 Canceled 2017-05-02 2017-05-19 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Specialist Management Selection 37/IC/ANRLMP/16 / M&E Project Coordination and Individual Consultant IDA / Q9900 Post Open 90,000.00 0.00 Canceled 2017-05-02 2017-05-19 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Specialist Management Selection 25/IC/ANRLMP/16 / Value Chain Project Coordination and Individual Consultant IDA / Q9900 Post Open 111,600.00 0.00 Canceled 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 Specialist Management Selection 30/IC/ANRLMP/16 / GIS Project Coordination and Individual Consultant IDA / Q9900 Post Open 72,000.00 0.00 Canceled 2017-07-03 2017-08-21 2017-09-11 2017-10-16 2018-04-14 Specialist Management Selection 43/IC/ANRLMP/16 / Project Coordination and Individual Consultant Pending Infraestruture Specialist Field IDA / Q9900 Post Open 63,000.00 0.00 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Selection Implementation Operator 28/IC/ANRLMP/16 / Project Coordination and Individual Consultant IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-10-04 2017-11-22 2017-12-13 2018-01-17 2018-07-16 Communication Specialist Management Selection 51/IC/ANRLMP/16 / Land Project Coordination and Individual Consultant IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Specialist Field Operator Management Selection 50/IC/ANRLMP/16 / Value Chain Project Coordination and Individual Consultant IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Specialist Field Operator Management Selection 49/IC/ANRLMP/16 / Project Coordination and Individual Consultant Infraestruture Specialist Field IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Selection Operator 44/IC/ANRLMP/16 / Value Chain Project Coordination and Individual Consultant IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Specialist Field Operator Management Selection 48/IC/ANRLMP / Provincial Project Coordination and Individual Consultant IDA / Q9900 Post Open 90,000.00 0.00 Canceled 2017-08-02 2017-09-20 2017-10-11 2017-11-15 2018-05-14 Coordinator Management Selection 46/IC/ANRLMP/16 / Natural Project Coordination and Individual Consultant Resaurce Specialist Field IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Management Selection Operator 45/IC/ANRLMP/16 / Land Project Coordination and Individual Consultant IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 Specialist Field Operator Management Selection 35/SS/ANRLMP/17 / Project Coordination and Pending IDA / D1190 Prior Direct Selection Direct 96,000.00 0.00 2017-05-30 2017-06-09 2017-08-14 2019-08-04 Procurement Assistant Management Implementation 37/SS/ANRLMP/17 / M&E Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 120,000.00 0.00 2017-05-29 2017-06-08 2017-08-12 2019-08-02 Specialist Management Implementation Page 3 48/SS/ANRLMP/17 / Provincial Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 120,000.00 0.00 2017-06-30 2017-07-10 2017-09-13 2019-09-03 Coordinator Management Implementation 29/SS/ANRLMP/17 / Project Coordination and Pending Environment and Social IDA / D1190 Post Direct Selection Direct 144,000.00 0.00 2017-05-29 2017-06-12 2017-08-16 2019-08-06 Management Implementation Safeguards Specialist 42/SS/ANRLMP/17 / National Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 120,000.00 0.00 2017-06-30 2017-07-10 2017-09-13 2019-09-03 Coordinator Management Implementation 31/SS/ANRLMP/17 / Project Coordination and Pending IDA / D1190 Prior Direct Selection Direct 120,000.00 0.00 2017-05-29 2017-06-12 2017-08-16 2019-08-06 Procurement Manager Management Implementation 24/SS/ANRLMP/17 / Natural Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 144,000.00 0.00 2017-05-29 2017-06-12 2017-08-16 2019-08-06 resaurces and forestry Specialist Management Implementation 27/SS/ANRLMP/17 / Land Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 144,000.00 0.00 2017-05-29 2017-06-12 2017-08-16 2019-08-06 Administration Specialist Management Implementation 28/SS/ANRLMP/17 / Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 144,000.00 0.00 2017-07-05 2017-07-17 2017-09-20 2019-09-10 Communications Specialist Management Implementation 26/SS/ANRLMP/17 / Rural Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 144,000.00 0.00 2017-05-29 2017-06-12 2017-08-16 2019-08-06 Development Specialist Management Implementation 30/SS/ANRLMP/17 / GIS Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 96,000.00 0.00 2017-07-05 2017-07-17 2017-09-20 2019-09-10 Specialist Management Implementation 25/SS/ANRLMP/17 / Value Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 148,800.00 0.00 2017-11-01 2017-11-13 2018-01-17 2020-01-07 Chain Specialist Management Implementation 33/SS/ANRLMP/17 / Project Coordination and Pending IDA / D1190 Prior Direct Selection Direct 96,000.00 0.00 2017-11-15 2017-11-27 2018-01-31 2020-01-21 Procurement Assistant Management Implementation 51/SS/ANRLMP/17 / Land Project Coordination and Pending Administration Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 0.00 2018-08-15 2018-08-27 2018-10-31 2019-04-29 Management Implementation Operator 44/SS/ANRLMP/17 / Value Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 84,000.00 0.00 2018-08-15 2018-08-27 2018-10-31 2020-10-20 Chain Specialist Field Operator Management Implementation 49/SS/ANRLMP/17 / Project Coordination and Pending Infraestruture Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 0.00 2018-08-15 2018-08-27 2018-10-31 2020-10-20 Management Implementation Operator 52/SS/ANRLMP/17 / Natural Project Coordination and Pending Resaurces and Forestry IDA / D1190 Post Direct Selection Direct 84,000.00 0.00 2018-08-15 2018-08-27 2018-10-31 2020-10-20 Management Implementation Specialist Field Operator 45/SS/ANRLMP/17 / Land Project Coordination and Pending Administration Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 0.00 2018-08-15 2018-08-27 2018-10-31 2020-10-20 Management Implementation Operator 46/SS/ANRLMP/17 / Natural Project Coordination and Pending Resaurces and Forestry IDA / D1190 Post Direct Selection Direct 84,000.00 0.00 2018-08-15 2018-08-27 2018-10-31 2020-10-20 Management Implementation Specialist Field Operator 50/SS/ANRLMP/17 / Value Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 84,000.00 0.00 2018-08-15 2018-08-27 2018-10-31 2020-10-20 Chain Specialist Field Operator Management Implementation 43/SS/ANRLMP/17 / Project Coordination and Pending Infraestruture Specialist Field IDA / D1190 Post Direct Selection Direct 84,000.00 0.00 2018-08-15 2018-08-27 2018-10-31 2020-10-20 Management Implementation Operator Securing Land Tenure Rights 65/IC/ ANRLMP/17 / Senior Individual Consultant Pending IDA / D1190 and Increasing Natural Post Open 84,000.00 0.00 2017-06-13 2017-08-01 2017-08-22 2017-09-26 2018-09-26 Agricultural hidraulics Specialist Selection Implementation Resources Resilience 23/SS/ANRLMP/17 / National Project Coordination and Pending IDA / D1190 Post Direct Selection Direct 172,800.00 0.00 2017-05-29 2017-06-12 2017-08-16 2019-08-06 Coordinator Management Implementation 17/IC/ANRLMP/16 / Facilitation Securing Land Tenure Rights IDA / 58550 Individual Consultant of the development of a Common and Increasing Natural Post Open 30,000.00 0.00 Canceled 2017-03-10 2017-05-01 2017-05-22 2017-06-26 2017-09-24 IDA / D1190 Selection Landscape Vision Resources Resilience Page 4