Public Disclosure Copy The World Bank Implementation Status & Results Report E-Health Project (P131290) E-Health Project (P131290) EAST ASIA AND PACIFIC | Mongolia | Health, Nutrition & Population Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 3 | ARCHIVED on 15-Dec-2015 | ISR19803 | Implementing Agencies: Ministry of Health Key Dates Key Project Dates Bank Approval Date:06-Jun-2014 Effectiveness Date:17-Aug-2015 Planned Mid Term Review Date:06-Feb-2017 Actual Mid-Term Review Date:-- Original Closing Date:30-Sep-2019 Revised Closing Date:30-Sep-2020 Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve integration and utilization of health information and e-health solutions for better health service delivery in selected pilot sites. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name eHealth Foundational Activities:(Cost $2.85 M) Clinical Data Collection, Access and Sharing:(Cost $16.06 M) National Health Information Center:(Cost $2.44 M) Institutional Strengthening and Capacity Building:(Cost $1.20 M) Project Management:(Cost $1.20 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Moderately Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Unsatisfactory Overall Risk Rating  --  Substantial 12/15/2015 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report E-Health Project (P131290) Implementation Status and Key Decisions The PIU has not been established yet, which has made it impossible to begin project implementation. We hope that the recruitment of the PIU will be speeded up in the coming weeks. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  --  High Macroeconomic  --  --  Substantial Sector Strategies and Policies  --  --  Substantial Technical Design of Project or Program  --  --  Substantial Institutional Capacity for Implementation and Sustainability  --  --  Substantial Fiduciary  --  --  Substantial Environment and Social  --  --  Low 12/15/2015 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report E-Health Project (P131290) Stakeholders  --  --  Substantial Other  --  --  Substantial Overall  --  --  Substantial Results Project Development Objective Indicators PHINDPDOTBL  (1) Percentage of patient episodes for which information, including medical image information is available for secure viewing at pil ot facilities (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 60.00 Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 PHINDPDOTBL  (2) Percentage of statistical reports out of total reports produced by pilot facilities that are transmitted electronically throughH IEP to the National Centre for Health Development (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 75.00 Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 PHINDPDOTBL  (3) Percentage of electronic referrals out of total referrals at pilot facilities (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 Overall Comments Project implementation has not begun. There is no progress on the results as a result. Intermediate Results Indicators 12/15/2015 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report E-Health Project (P131290) PHINDIRITBL  Component 1: Health Data Standards are developed, validated and promulgated by MOH (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value no No No Yes Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2016 PHINDIRITBL  Component 1: Percentage of agencies which adopt and utilize the EA and HDS in the construction of software modules and communication layers. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 PHINDIRITBL  Component 2: Percentage of pilot facilities which design, develop, and implement successful piloting of eHealth Portal, Viewer and HIEP. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 PHINDIRITBL  Component 2: Percentage of digital images generated in pilot facilities which are transmitted to the central PACS. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 12/15/2015 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report E-Health Project (P131290) PHINDIRITBL  Component 3: Training Center has been designed, implemented and is ready for use. (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 PHINDIRITBL  Component 4: Improvements in IT literacy and health information management capacity among health professionals (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 200.00 Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 PHINDIRITBL  Health personnel receiving training (number) (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 200.00 Date 31-Dec-2013 12-May-2015 08-Dec-2015 31-Dec-2019 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P131290 IDA-54890 Effective XDR 12.70 12.70 0.00 0.00 12.70 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P131290 IDA-54890 Effective 06-Jun-2014 18-Jun-2015 17-Aug-2015 30-Sep-2019 30-Sep-2020 12/15/2015 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report E-Health Project (P131290) Cumulative Disbursements Restructuring History Level 2 Approved on 11-Jun-2015 Related Project(s) There are no related projects. 12/15/2015 Page 6 of 6 Public Disclosure Copy