Ayeyarwady Integrated River Basin Management (AIRBM) Project Procurement Plan I. GENERAL 1. Project information a. Country/Borrower: Myanmar b. Project Implementing Agency: Ministry of Transport (Directorate for Water Resources and Improvement of River Systems) 2. Bank’s approval Date of the procurement Plan a. Original Plan: October 24, 2014 b. Revised Plan September 7, 2015 c. Revised Plan: November 11, 2015 d. Revised Plan: February 26, 2016 e. Revised Plan: August 4, 2016 f. Revised Plan: November 28, 2016 g. Revised Plan: March 21, 2017 3. Date of General Procurement Notice: a. Date : 18 February 2015 II. Type of Procurement. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Market Approaches Thresholds Prior Review Procurement International National-Open National RFQ Comments Threshold (Shopping) Works (Including USD 3m and Less than US$3m Less than Recommended to US$ 2 mil. turnkey supply and above US$1m advertise for 7 days for installation of plant RFQ above USD and equipment) 50,000. Goods, information USD 1m and Less than US$1m Less than Recommended to US$ 1 mil. technology and above US$0.5m advertise for 7 days for non-consulting RFQ above USD services 50,000. Consultants USD 0.1m and Less than Not applicable CQS method may be US$ 0.3 mil. (Firms) above US$0.1m used up to USD 500,000. Use of full RFP mandatory for CQS above USD 300,000. Limits on market approaches do not apply to individual consultants. Consultant US$ 0.2 mil. (Individuals) 1 PROCUREMENT Myanmar : Ayeyarwady Integrated River Basin Management Project PLAN General Information Country: Myanmar Bank’s Approval Date of the Original Procurement Plan: 2016-08-24 2019-12-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146482 GPN Date: Project Name: Ayeyarwady Integrated River Basin Management Project Loan / Credit No: IDA / 55590 Executing Agency(ies): Directorate Of Water Resources and Improvement of River Systems WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2. Hydro- CW2-1 / Meeting Room meteorological Observation Request for Single Stage - One Upgrade, DMH Yangon IDA / 55590 Post Open - National 50,000.00 47,524.58 Completed 2017-03-05 2017-04-30 2017-10-27 and Information Systems Quotations Envelope Office Modernization Component 1: Water Resource Management CW1-1-2 / Demolition of Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 3,000.00 2,603.61 Completed 2016-01-05 2016-03-01 2016-08-28 DWIR Building Quotations Envelope Support Systems & Capacity Building Component 1: Water Resource Management CW1-1-3 / Renovation of Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 90,000.00 85,639.39 Completed 2016-02-05 2016-04-01 2016-09-28 DWIR Building Quotations Envelope Support Systems & Capacity Building Component 1: Water Resource Management CW1-3 / PMU Building IDA / 55590 Institutions, Decision Post Direct Selection Direct 3,000.00 2,667.14 Completed 2017-09-30 2017-09-30 2017-10-21 2017-11-30 Car Parking Support Systems & Capacity Building CW3-1-5A / DWIR Micro- Component 3. Navigation Project in Bagan, Nyaung U IDA / 55590 Enhancement on the Post Force Account Direct 116,016.00 114,265.00 Signed 2016-04-01 2016-04-01 2016-04-01 2016-04-01 Groynes Ayeyarwady River CW3-1-5B / DWIR Micro- Component 3. Navigation Project in Bagan, Nyaung U IDA / 55590 Enhancement on the Post Force Account Direct 39,136.00 246,000.00 Signed 2016-04-01 2016-04-01 2016-04-01 2016-04-01 Dredging Ayeyarwady River CW3-1-5C / DWIR Micro- Component 3. Navigation Project in Bagan, Nyaung U IDA / 55590 Enhancement on the Post Force Account Direct 47,510.00 264,000.00 Signed 2016-04-07 2016-04-07 2016-04-07 2016-04-07 Dredging Ayeyarwady River Component 3. Navigation CW3-1-5D / DWIR Micro- IDA / 55590 Enhancement on the Post Force Account Direct 98,863.00 246,000.00 Signed 2016-04-07 2016-04-07 2016-04-07 2016-04-07 Project, Pakkoku Dredging Ayeyarwady River Component 3. Navigation CW3-1-5E / DWIR Micro- IDA / 55590 Enhancement on the Post Force Account Direct 56,327.00 236,836.00 Signed 2016-05-30 2016-05-30 2016-05-30 2016-05-30 Project, Pakkoku Dredging Ayeyarwady River Component 3. Navigation Pending CW3-1-5F / DWIR Micro- IDA / 55590 Enhancement on the Post Force Account Direct 84,000.00 0.00 Implementati 2017-02-02 2017-02-02 2017-02-02 2017-02-02 Project, Mandalay Dredging Ayeyarwady River on Component 3. Navigation Pending CW3-1-5G / DWIR Micro- IDA / 55590 Enhancement on the Post Force Account Direct 117,791.00 0.00 Implementati 2017-06-02 2017-06-02 2017-06-02 2017-06-02 Project, Mandalay Dredging Ayeyarwady River on Component 1: Water Resource Management CW1-1-1REVISED / PMU Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 900,000.00 1,188,755.48 Completed 2017-09-30 2017-09-30 2017-09-30 Building Quotations Envelope Support Systems & Capacity Building Component 1: Water Resource Management Open - Single Stage - One CW1-1-1 / PMU Building IDA / 55590 Institutions, Decision Prior Request for Bids 600,000.00 0.00 Canceled 2017-12-31 2017-12-31 2017-12-31 2017-12-31 2018-01-21 2018-07-20 International Envelope Support Systems & Capacity Building Page 1 Component 3. Navigation CW3-2 / Renovation of Request for Single Stage - One IDA / 55590 Enhancement on the Post Open - National 25,000.00 26,346.44 Completed 2018-01-03 2018-02-28 2018-08-27 DWIR Mandalay Office Quotations Envelope Ayeyarwady River Component 3. Navigation CW3-1 / River Bank Request for Single Stage - One IDA / 55590 Enhancement on the Post Open - National 1,500,000.00 825,216.13 Completed 2018-02-15 2018-04-12 2018-10-09 Protection for Sub Project 1 Quotations Envelope Ayeyarwady River Component 3. Navigation Under CW3-1-5H / Micro Project IDA / 55590 Enhancement on the Post Force Account Direct 300,000.00 0.00 Implementati 2018-02-28 2018-02-28 2018-02-28 2018-02-28 in Nyaung Oo Ayeyarwady River on Component 3. Navigation Under CW3-1-5I / Micro Project IDA / 55590 Enhancement on the Post Force Account Direct 600,000.00 0.00 Implementati 2018-02-28 2018-02-28 2018-02-28 2018-02-28 in Pakkoku Ayeyarwady River on Component 3. Navigation CW3-3 / Hydraulic Single Stage - One IDA / 55590 Enhancement on the Prior Request for Bids Open - National 2,500,000.00 2,185,602.77 Signed 2018-04-12 2018-04-17 2018-05-17 2018-06-16 2018-07-21 2019-01-17 Structure for Sub Project 1 Envelope Ayeyarwady River Component 1: Water CW1-2 / Municipal Water Resource Management Supply Connection and IDA / 55590 Institutions, Decision Post Direct Selection Direct 7,000.00 2,672.59 Completed 2018-09-30 2018-10-05 2018-11-09 2019-05-08 Tank for PMU Building Support Systems & Capacity Building CW2-2 / Refurbishment/renovation of Component 2. Hydro- the 5 regional support Under meteorological Observation Request for Single Stage - One centers (in Kalewa, IDA / 55590 Post Open - National 50,000.00 0.00 Implementati 2018-12-20 2019-02-14 2019-08-13 and Information Systems Quotations Envelope Mandalay, Mawlamyaing, on Modernization Pathein, Myintkyina) and the MHEWC (in NPT) CW3-1-5 J / Microproject Component 3. Navigation Pending for Aung Pan Chaung to IDA / 55590 Enhancement on the Post Force Account Direct 800,000.00 0.00 Implementati 2018-01-30 2018-01-30 2018-01-30 2018-01-30 Sin Min Waterway (Balaba) Ayeyarwady River on Component 1: Water CW1-5 / Construction of Resource Management Under Open - Single Stage - One NWRC HQ and HIC IDA / 55590 Institutions, Decision Prior Request for Bids 8,000,000.00 0.00 Implementati 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 International Envelope Building Support Systems & on Capacity Building Component 1: Water CW1-4 / Electricity Resource Management application and installation Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 100,000.00 108,045.50 Signed 2019-10-06 2019-12-01 2020-05-29 of Transformer for PMU Quotations Envelope Support Systems & Building Capacity Building CW2-3 / DMH New Component 2. Hydro- Pending Building Construction in meteorological Observation Single Stage - One IDA / 55590 Post Request for Bids Open - National 1,700,000.00 0.00 Implementati 2020-01-10 2020-01-15 2020-02-26 2020-03-27 2020-05-01 2020-10-28 NPT and Renovation in and Information Systems Envelope on YGN Modernization GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Water Resource Management G1-4-2 / DWIR Office Request for Single Stage - One IDA / 55590 Institutions, Decision Post Limited 48,000.00 40,168.21 Completed 2016-02-06 2016-04-02 2016-09-29 Equipment ( Yangon Office) Quotations Envelope Support Systems & Capacity Building Component 1: Water G1-8 / Office Resource Management Request for Single Stage - One Upgrade/Maintenance : WiFi IDA / 55590 Institutions, Decision Post Limited 7,000.00 6,057.12 Completed 2016-07-06 2016-08-31 2017-02-27 Quotations Envelope Installation at DWIR Support Systems & Capacity Building Component 2. Hydro- G2-2 / ADCP Flow meters meteorological Observation Request for Single Stage - One IDA / 55590 Post Limited 130,000.00 175,000.00 Completed 2016-12-06 2017-01-31 2017-07-30 and associated equipment and Information Systems Quotations Envelope Modernization Page 2 Component 1: Water Resource Management Request for Single Stage - One G1-9 / Vehicles IDA / 55590 Institutions, Decision Prior Open - National 250,000.00 168,803.98 Completed 2016-11-07 2017-01-18 2017-07-17 Quotations Envelope Support Systems & Capacity Building G3-1 / Speed Component 3. Navigation Request for Open - Single Stage - One Boats/Hydrographic Survey IDA / 55590 Enhancement on the Prior 350,000.00 225,500.00 Completed 2016-12-06 2017-01-31 2017-07-30 Quotations International Envelope Boats Ayeyarwady River G3-2 / Topo-Hydrographic survey equipment, satellite Component 3. Navigation Request for Single Stage - One images and maps, including IDA / 55590 Enhancement on the Prior Open - National 480,000.00 789,237.00 Completed 2016-10-06 2016-12-19 2017-06-17 Quotations Envelope installation of equipment Ayeyarwady River and training in surveying Component 3. Navigation G3-3 / Supply and Delivery Open - Single Stage - One IDA / 55590 Enhancement on the Prior Request for Bids 3,400,000.00 1,716,855.12 Completed 2017-01-01 2017-01-06 2017-02-17 2017-03-19 2017-04-23 2017-10-20 of Aids to Navigation International Envelope Ayeyarwady River Component 3. Navigation G3-4 / Multifunctional and Open - Single Stage - One IDA / 55590 Enhancement on the Prior Request for Bids 1,200,000.00 2,100,000.00 Signed 2017-02-01 2017-02-06 2017-03-20 2017-04-19 2017-05-24 2017-11-20 Buoy Handling vessel International Envelope Ayeyarwady River Component 3. Navigation G3-5 / Amphibious multi- Open - Single Stage - One IDA / 55590 Enhancement on the Prior Request for Bids 1,500,000.00 1,551,999.00 Completed 2017-02-01 2017-02-06 2017-03-20 2017-04-19 2017-05-24 2017-11-20 purpose dredger International Envelope Ayeyarwady River Component 3. Navigation G3-6 / WiFi Connection to Request for Single Stage - One IDA / 55590 Enhancement on the Post Open - National 7,000.00 4,081.86 Completed 2017-04-05 2017-05-31 2017-11-27 DWIR Mandalay Office Quotations Envelope Ayeyarwady River Component 3. Navigation G3-7 / Office Furniture for Request for Single Stage - One IDA / 55590 Enhancement on the Post Open - National 3,500.00 4,681.14 Completed 2017-04-05 2017-05-31 2017-11-27 DWIR Mandalay Office Quotations Envelope Ayeyarwady River Component 1: Water G1-10 / PMU Data Resource Management Request for Single Stage - One Network Infrastructure - IDA / 55590 Institutions, Decision Post Open - National 100,000.00 75,587.62 Completed 2017-02-15 2017-04-12 2017-10-09 Quotations Envelope Hardware and Software Support Systems & Capacity Building Component 1: Water Resource Management G1-4-3 / DWIR Office Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 25,000.00 27,389.42 Completed 2016-02-28 2016-06-03 2016-07-31 Furniture for Yangon Office Quotations Envelope Support Systems & Capacity Building Component 1: Water Resource Management Request for Single Stage - One G1-6 / Accounting Software IDA / 55590 Institutions, Decision Post Open - National 15,000.00 16,871.81 Signed 2016-02-26 2016-06-06 2016-07-06 Quotations Envelope Support Systems & Capacity Building G1-7 / Fiber Cable Component 1: Water Installation and Resource Management Transmission for Data IDA / 55590 Institutions, Decision Post Direct Selection Direct 5,000.00 2,049.12 Completed 2016-06-01 2016-06-01 2016-06-16 2016-06-16 Network for PMU and Support Systems & DWIR Office Capacity Building Component 2. Hydro- G2-1-1 / DMH Office meteorological Observation Request for Single Stage - One Equipment for Nay Pyi Taw IDA / 55590 Post Open - National 48,000.00 20,143.35 Completed 2016-01-30 2016-03-31 2016-03-31 and Information Systems Quotations Envelope and Yangon Office Modernization Component 2. Hydro- G2-1-4 / DMH Office meteorological Observation Request for Single Stage - One Furniture for Nay Pyi Taw IDA / 55590 Post Open - National 35,000.00 14,876.87 Completed 2016-02-28 2016-06-03 2016-07-29 and Information Systems Quotations Envelope and Yangon Office Modernization Component 2. Hydro- meteorological Observation Request for Single Stage - One G2-1-3 / Generators IDA / 55590 Post Open - National 30,000.00 26,757.13 Completed 2016-06-07 2017-02-07 2017-03-31 and Information Systems Quotations Envelope Modernization Component 1: Water G1-11 / Server Desktop Resource Management Request for Single Stage - One and Accessories for PMU IDA / 55590 Institutions, Decision Post Open - National 25,000.00 16,086.97 Completed 2017-09-05 2017-10-31 2018-04-29 Quotations Envelope Office Support Systems & Capacity Building Page 3 G2-1 / Fiber Cable Component 2. Hydro- Installation and meteorological Observation Request for Single Stage - One Transmission for Data IDA / 55590 Post Open - National 20,000.00 18,339.34 Completed 2017-03-05 2017-04-30 2017-10-27 and Information Systems Quotations Envelope Network for DMH Office in Modernization NayPyiTaw Component 1: Water G1-12 / Office Furniture Resource Management Request for Single Stage - One for interim NWRC HQ/HIC IDA / 55590 Institutions, Decision Post Open - National 70,000.00 9,335.80 Signed 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Building Support Systems & Capacity Building Component 1: Water G1-13 / Office Equipment Resource Management Request for Single Stage - One for interim NWRC HQ/HIC IDA / 55590 Institutions, Decision Post Open - National 30,000.00 7,738.91 Completed 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Building Support Systems & Capacity Building Component 1: Water G1-14 / Data Network Resource Management Cabling, Sever, Desktop and Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 100,000.00 144,742.75 Completed 2018-02-06 2018-04-03 2018-09-30 Accessories for interim Quotations Envelope Support Systems & NWRC HQ/HIC Building Capacity Building Component 1: Water G1-15 / Internet Resource Management Connection for interim IDA / 55590 Institutions, Decision Post Direct Selection Direct 20,000.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-09-09 NWRC HQ/HIC Building Support Systems & Capacity Building Component 3. Navigation G3-9 / Hydraulic Single Stage - One IDA / 55590 Enhancement on the Prior Request for Bids Open - National 2,500,000.00 0.00 Canceled 2018-08-31 2018-09-05 2018-10-17 2018-11-16 2018-12-21 2019-06-19 Structures for Sub Project 1 Envelope Ayeyarwady River Component 1: Water Resource Management G1-16 / Furniture for PMU Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 150,000.00 91,351.46 Completed 2018-09-06 2018-11-01 2019-04-30 Building Quotations Envelope Support Systems & Capacity Building Component 1: Water Resource Management G1-17 / Equipment for Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 200,000.00 21,155.96 Signed 2018-09-06 2018-11-01 2019-04-30 PMU Building Quotations Envelope Support Systems & Capacity Building Component 2. Hydro- G2-3 / Upper-air Radio meteorological Observation Open - Single Stage - One IDA / 55590 Prior Request for Bids 800,000.00 0.00 Canceled 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 2019-05-20 Sounding Equipment and Information Systems International Envelope Modernization Component 2. Hydro- G2-4 / Automatic Weather meteorological Observation Open - Single Stage - One stations and associated IDA / 55590 Prior Request for Bids 1,400,000.00 1,984,616.17 Signed 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 2019-05-20 and Information Systems International Envelope equipment Modernization Component 2. Hydro- G2-5 / Calibration lab Under meteorological Observation Request for Single Stage - One equipment and Electronic IDA / 55590 Post Open - National 220,000.00 0.00 Implementati 2018-08-06 2018-10-01 2019-03-30 and Information Systems Quotations Envelope test equipment on Modernization Component 2. Hydro- G2-6 / River monitoring meteorological Observation Open - Single Stage - One IDA / 55590 Prior Request for Bids 580,000.00 0.00 Canceled 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 2019-05-20 equipment and Information Systems International Envelope Modernization Component 2. Hydro- G2-8 / Supply and meteorological Observation Request for Single Stage - One installation of river level IDA / 55590 Post Open - National 160,000.00 107,397.39 Completed 2018-08-06 2018-10-01 2019-03-30 and Information Systems Quotations Envelope monitoring stage boards Modernization G3-11 / Supply and Component 3. Navigation Open - Single Stage - One Delivery of 2 Fast Transit IDA / 55590 Enhancement on the Prior Request for Bids 1,200,000.00 0.00 Canceled 2018-10-01 2018-10-06 2018-11-17 2018-12-17 2019-01-21 2019-07-20 International Envelope Buoy Handling Vessel Ayeyarwady River G3-12 / Two Cutter Component 3. Navigation Under Open - Single Stage - One Suction Dredgers and IDA / 55590 Enhancement on the Prior Request for Bids 8,400,000.00 10,589,855.10 Implementati 2018-10-01 2018-10-06 2018-11-17 2018-12-17 2019-01-21 2019-07-20 International Envelope Ancillary Equipment Ayeyarwady River on Component 3. Navigation G3-14 / Three Aluminium Request for Open - Single Stage - One IDA / 55590 Enhancement on the Post 490,000.00 753,420.00 Signed 2018-09-05 2018-10-31 2019-04-29 Hydrographic Survey Boats Quotations International Envelope Ayeyarwady River Page 4 G3-10A / Supply and Component 3. Navigation Request for Single Stage - One Delivery of Acoustic Doppler IDA / 55590 Enhancement on the Post Open - National 281,000.00 175,000.00 Completed 2018-09-08 2018-11-03 2019-05-02 Quotations Envelope Current Profiler Ayeyarwady River G3-10REVISED / Supply and Delivery of Topo- Component 3. Navigation Hydrographic Survey Request for Open - Single Stage - One IDA / 55590 Enhancement on the Post 492,000.00 614,890.00 Signed 2018-09-08 2018-11-03 2019-05-02 Equipment for the Stretch Quotations International Envelope Ayeyarwady River Between Nyaung Oo and Yangon Component 2. Hydro- G2-3REVISED / Upper Air meteorological Observation Request for Open - Single Stage - One IDA / 55590 Post 800,000.00 0.00 Canceled 2018-09-08 2018-11-03 2019-05-02 Radio Sounding Equipment and Information Systems Quotations International Envelope Modernization Component 2. Hydro- G2-7 / River Survey Boats- meteorological Observation Request for Single Stage - One IDA / 55590 Post Open - National 360,000.00 476,726.00 Signed 2018-09-19 2018-11-14 2019-05-13 3 Units and Information Systems Quotations Envelope Modernization Component 2. Hydro- G2-3REVISED-FINAL / meteorological Observation Open - Single Stage - One Upper Air Radio Sounding IDA / 55590 Post Request for Bids 800,000.00 1,032,786.00 Signed 2018-09-30 2018-10-05 2018-11-16 2018-12-16 2019-01-20 2019-07-19 and Information Systems International Envelope Equipment Modernization Component 2. Hydro- G2-6REVISED / River meteorological Observation Request for Open - Single Stage - One IDA / 55590 Post 490,000.00 541,480.00 Signed 2018-10-10 2018-12-05 2019-06-03 Monitoring Equipment and Information Systems Quotations International Envelope Modernization Component 2. Hydro- G2-10 / Automatic water meteorological Observation Open - Single Stage - One IDA / 55590 Prior Request for Bids 800,000.00 0.00 Canceled 2018-11-30 2018-12-05 2019-01-16 2019-02-15 2019-03-22 2019-09-18 level recording Equipment and Information Systems International Envelope Modernization G2-11 / Forecaster Component 2. Hydro- Under Workstations, Printers and meteorological Observation Request for Single Stage - One IDA / 55590 Post Open - National 500,000.00 0.00 Implementati 2018-12-06 2019-01-31 2019-07-30 Automated Desktop and Information Systems Quotations Envelope on Deployment System Modernization G2-12 / Special furniture Component 2. Hydro- for the Forecast Operations meteorological Observation Request for Single Stage - One IDA / 55590 Post Open - National 150,000.00 11,831.72 Signed 2018-12-05 2019-01-30 2019-07-29 Centre and 5 regional and Information Systems Quotations Envelope support centers Modernization G2-15 / NPT Datacentre Component 2. Hydro- and Forecast Operations meteorological Observation Open - Single Stage - One IDA / 55590 Prior Request for Bids 2,200,000.00 0.00 Canceled 2018-12-01 2018-12-06 2019-01-17 2019-02-16 2019-03-23 2019-09-19 Centre renovation,equipment and Information Systems International Envelope and related-services Modernization Component 2. Hydro- G2-19 / Data Hub Server meteorological Observation IDA / 55590 Post Direct Selection Direct 9,440.00 5,866.46 Signed 2018-11-30 2018-12-05 2019-01-09 2019-07-08 with Harddrives and UPS and Information Systems Modernization Component 2. Hydro- G2-20 / NPT-MDY-YGN Under meteorological Observation Request for Single Stage - One Internet capacity Upgrade IDA / 55590 Post Open - National 444,000.00 0.00 Implementati 2018-12-06 2019-01-31 2019-07-30 and Information Systems Quotations Envelope with Redundancy on Modernization Component 2. Hydro- G2-9 / Vehicles, 4WD Pick- meteorological Observation Request for Single Stage - One IDA / 55590 Post Open - National 225,000.00 0.00 Canceled 2018-12-05 2019-01-30 2019-07-29 up, 3.nos and Information Systems Quotations Envelope Modernization Component 1: Water G1-18 / Internet Resource Management Bandwidth Upgrading in IDA / 55590 Institutions, Decision Post Direct Selection Direct 5,000.00 1,458.82 Completed 2018-12-17 2018-12-22 2019-01-26 2019-07-25 PMU Building Support Systems & Capacity Building G2-13 / NPT Data centre Component 2. Hydro- Under and Forecast Operations meteorological Observation Open - Single Stage - One IDA / 55590 Prior Request for Bids 4,600,000.00 0.00 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2019-10-08 Centre set up and backend and Information Systems International Envelope on ICT infrastructure Modernization G2-10REVISED / Component 2. Hydro- Under Automatic Water Level meteorological Observation Open - Single Stage - One IDA / 55590 Post Request for Bids 800,000.00 0.00 Implementati 2019-01-18 2019-01-23 2019-03-06 2019-04-05 2019-05-10 2019-11-06 Recording Equipment and Information Systems International Envelope on (AWLR) Modernization Page 5 G3-11REVISED / Supply Component 3. Navigation and Delivery of Fast Open - Single Stage - One IDA / 55590 Enhancement on the Prior Request for Bids 1,500,000.00 2,382,813.00 Signed 2019-05-28 2019-06-02 2019-07-14 2019-08-13 2019-09-17 2020-03-15 Transit Buoy Handling International Envelope Ayeyarwady River Vessels G3-15 / Supply and Component 3. Navigation Under Delivery of Aids to Open - Single Stage - One IDA / 55590 Enhancement on the Prior Request for Bids 5,900,000.00 0.00 Implementati 2019-11-17 2019-11-22 2020-01-03 2020-02-02 2020-03-08 2020-09-04 Navigation between Nyaung International Envelope Ayeyarwady River on Oo and Yangon G2-14 / Cloud computing Component 2. Hydro- and other equipment to meteorological Observation Request for Single Stage - One IDA / 55590 Post Open - National 310,000.00 0.00 Canceled 2018-12-06 2019-01-31 2019-07-30 provide resilience to DMH and Information Systems Quotations Envelope systems, Yangon Modernization Component 1: Water G1-19 / DSS Software for Resource Management Under River Basin Modeling and IDA / 55590 Institutions, Decision Post Direct Selection Direct 250,000.00 0.00 Implementati 2019-12-06 2019-12-11 2020-01-15 2020-07-13 Dash Board Support Systems & on Capacity Building G2-12REVISED / Special Component 2. Hydro- Furniture for the Forecast Pending meteorological Observation Request for Single Stage - One Operations Center set up IDA / 55590 Post Open - National 32,000.00 0.00 Implementati 2019-12-25 2020-02-19 2020-08-17 and Information Systems Quotations Envelope and backend ICT on Modernization infrastructure NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Water Resource Management S1-1 / PMU Website Request for Single Stage - One IDA / 55590 Institutions, Decision Post Open - National 5,000.00 714.55 Signed 2016-11-23 2016-12-07 2017-06-05 Developer Quotations Envelope Support Systems & Capacity Building Component 3. Navigation Under S3-1 / Hydrographic Survey IDA / 55590 Enhancement on the Post Force Account Direct 160,000.00 0.00 Implementati 2017-01-31 2017-01-31 2017-01-31 2017-01-31 Stretch 1 Ayeyarwady River on Component 2. Hydro- S2-1 / Flow Surveys and meteorological Observation IDA / 55590 Post Force Account Direct 60,000.00 59,700.00 Signed 2016-09-30 2016-09-30 2016-09-30 2016-09-30 Rating Review and Information Systems Modernization Component 2. Hydro- S2-2REVISED / meteorological Observation Request for Single Stage - One Topographic Survey Firm to IDA / 55590 Post Open - National 60,000.00 49,400.64 Signed 2017-05-30 2017-07-25 2018-01-21 and Information Systems Quotations Envelope Support Flow Survey Modernization Component 2. Hydro- S2-2 / Topographic Survey meteorological Observation Request for Single Stage - One Firm to Support Flow IDA / 55590 Post Open - National 20,000.00 0.00 Canceled 2017-03-05 2017-04-30 2017-10-27 and Information Systems Quotations Envelope Survey Modernization Component 3. Navigation S3-2 / Installation of Aids IDA / 55590 Enhancement on the Post Force Account Direct 100,000.00 132,510.08 Completed 2017-12-31 2017-12-31 2017-12-31 2017-12-31 to Navigation Ayeyarwady River S2-3 / River Surveys and Component 2. Hydro- Very High Resolution meteorological Observation Request for Single Stage - One Satellite Data for Central IDA / 55590 Post Open - National 310,000.00 131,334.71 Signed 2018-08-06 2018-10-01 2019-03-30 and Information Systems Quotations Envelope and Upper Myanmar (4 Modernization areas) S3-3 / Conducting the Component 3. Navigation Hydrographic Survey Request for Single Stage - One IDA / 55590 Enhancement on the Post Open - National 700,000.00 1,053,000.00 Signed 2018-08-06 2018-10-01 2019-03-30 between Nyaung U and Quotations Envelope Ayeyarwady River Yangon S3-5 / Installation of Component 3. Navigation Benchmarks from Nyaung U IDA / 55590 Enhancement on the Prior Force Account Direct 50,000.00 0.00 Canceled 2018-08-06 2018-08-06 2018-08-06 2018-08-06 to Yangon Ayeyarwady River S3-5REVISED / Installation Component 3. Navigation of Benchmarks from Nyaung IDA / 55590 Enhancement on the Post Force Account Direct 50,000.00 40,029.87 Signed 2018-09-14 2018-09-14 2018-09-14 2018-09-14 Oo to Yangon Ayeyarwady River Page 6 Component 2. Hydro- meteorological Observation S2-4 / WMO agreement IDA / 55590 Prior Direct Selection Direct 4,000,000.00 3,438,338.00 Signed 2018-12-15 2018-12-20 2019-01-24 2019-07-23 and Information Systems Modernization Component 1: Water S1-2 / Development of Resource Management Under Request for Single Stage - One Myanmar Official Water IDA / 55590 Institutions, Decision Post Open - National 32,500.00 0.00 Implementati 2019-08-20 2019-10-15 2019-12-14 Quotations Envelope Portal Support Systems & on Capacity Building S3-6 / Installation of Aids Component 3. Navigation Pending to Navigation (Nyaung Oo IDA / 55590 Enhancement on the Post Force Account Direct 300,000.00 0.00 Implementati 2020-03-30 2020-04-04 2020-05-09 2020-11-05 to Yangon) Ayeyarwady River on S3-4 / Additional surveys Component 3. Navigation Request for Single Stage - One under the Engineering IDA / 55590 Enhancement on the Post Open - National 300,000.00 0.00 Canceled 2018-09-06 2018-11-01 2019-04-30 Quotations Envelope Study for Stretch 1 Ayeyarwady River CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Water C1.4-21 / Design and Resource Management Consultant Open - Construction Supervision of IDA / 55590 Institutions, Decision Prior Qualification 90,000.00 78,170.00 Completed International DWIR Building Support Systems & Selection Capacity Building Component 1: Water C1-17 / Ayeyarwady Resource Management Quality And Cost- Open - Master Plan and Decision IDA / 55590 Institutions, Decision Prior 7,500,000.00 7,833,571.61 Signed 2016-10-24 2016-11-14 2016-12-28 2017-01-25 2017-02-24 2017-03-31 2017-05-05 2018-05-05 Based Selection International Support System Support Systems & Capacity Building Component 2. Hydro- C2-2 / DMH System meteorological Observation Quality And Cost- Open - IDA / 55590 Prior 5,000,000.00 4,888,863.43 Signed 2016-11-16 2016-12-07 2017-01-20 2017-02-17 2017-03-19 2017-04-23 2017-05-28 2018-05-28 Integrator and Information Systems Based Selection International Modernization C3-3 / ESIA/SEA/EMP Component 3. Navigation Consultant Open - Supervision for Subproject 1 IDA / 55590 Enhancement on the Prior Qualification 453,000.00 416,368.00 Signed 2016-04-27 2016-05-18 2016-08-24 2016-11-30 2017-01-04 2017-07-03 International and Stretch 1 Ayeyarwady River Selection Component 1: Water C1-12 / SOB Package 2: Resource Management Consultant Open - Groundwater and data IDA / 55590 Institutions, Decision Prior Qualification 230,000.00 227,553.00 Completed 2016-05-10 2016-06-21 2016-07-26 2016-11-25 2016-12-30 2017-06-28 International management Support Systems & Selection Capacity Building Component 1: Water Resource Management Consultant C1-13 / SOB Package 3: Open - IDA / 55590 Institutions, Decision Prior Qualification 200,000.00 237,567.45 Completed 2016-05-10 2016-06-21 2016-07-26 2016-11-25 2016-12-30 2017-06-28 Sediments & geomorphology International Support Systems & Selection Capacity Building Component 1: Water Resource Management Consultant C1-14 / SOB Package 4: Open - IDA / 55590 Institutions, Decision Prior Qualification 300,000.00 269,945.38 Completed 2016-05-10 2016-06-21 2016-10-14 2016-12-30 2017-02-03 2017-08-02 Biodiversity & Fisheries International Support Systems & Selection Capacity Building Component 1: Water C1-15 / SOB Package 5: Resource Management Consultant Open - Sectoral development and IDA / 55590 Institutions, Decision Prior Qualification 250,000.00 245,680.00 Completed 2016-05-10 2016-06-21 2016-07-26 2016-11-25 2016-12-30 2017-06-28 International macroeconomics Support Systems & Selection Capacity Building Component 1: Water C1-16 / SOB Package 6: Resource Management Consultant Open - 3D Mapping and local IDA / 55590 Institutions, Decision Prior Qualification 350,000.00 344,425.00 Completed 2016-05-10 2016-06-21 2016-07-26 2016-11-25 2016-12-30 2017-06-28 International consultations Support Systems & Selection Capacity Building Component 1: Water C1-19REVISED / Resource Management HIC/NWRC Building Design Quality And Cost- Open - IDA / 55590 Institutions, Decision Prior 1,000,000.00 1,533,487.90 Signed 2017-05-25 2017-06-15 2017-07-29 2017-08-26 2017-09-25 2017-10-30 2017-12-04 2018-12-04 and Construction Based Selection International Support Systems & Supervision Capacity Building Page 7 C3-13 / Feasibility Study, Component 3. Navigation Engineering design, Capacity Quality And Cost- Open - IDA / 55590 Enhancement on the Prior 2,000,000.00 2,874,019.84 Signed 2017-08-31 2017-09-21 2017-11-04 2017-12-02 2018-01-01 2018-02-05 2018-03-12 2019-03-12 Building and Construction Based Selection International Ayeyarwady River Supervision for Stretch1 C3-14 / ESIA,ESMP and Component 3. Navigation Quality And Cost- Open - ARAPs Implementation IDA / 55590 Enhancement on the Prior 1,000,000.00 817,075.00 Signed 2017-08-31 2017-09-21 2017-11-04 2017-12-02 2018-01-01 2018-02-05 2018-03-12 2019-03-12 Based Selection International Support for Stretch 1 Ayeyarwady River Component 1: Water C1-19 / Architectural and Resource Management Engineering Design and Quality And Cost- Open - IDA / 55590 Institutions, Decision Prior 600,000.00 0.00 Canceled 2017-03-31 2017-04-21 2017-06-04 2017-07-02 2017-08-01 2017-09-05 2017-10-10 2018-10-10 Construction Supervision of Based Selection International Support Systems & the NWRC HQ/HIC Capacity Building C2-8 / Design and Component 2. Hydro- Construction Supervision of Consultant meteorological Observation New Building in NPT and IDA / 55590 Post Qualification Open - National 100,000.00 183,573.00 Signed 2018-04-01 2018-04-22 2018-06-05 2018-07-05 2018-08-09 2019-02-05 and Information Systems Renovation of Buildings in Selection Modernization NPT and Yangon C2-9 / Impact Based Component 2. Hydro- Forecasting Pilots and Flood meteorological Observation Quality And Cost- Open - Under Hazard Mapping in the IDA / 55590 Prior 1,400,000.00 0.00 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 and Information Systems Based Selection International Implementation Chindwin and Central Modernization Ayeyarwady Basin, Myanmar Component 2. Hydro- C2-11 / ACAS Coordination Consultant meteorological Observation Open - and Development of Agro IDA / 55590 Prior Qualification 370,000.00 183,060.00 Signed 2018-08-20 2018-09-10 2018-10-24 2018-11-23 2018-12-28 2019-06-26 and Information Systems International Meteorological Products Selection Modernization C3-17 / Formulation of the Component 3. Navigation Navigation Strategy and Quality And Cost- Open - IDA / 55590 Enhancement on the Prior 1,100,000.00 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-02 2018-12-02 2019-01-06 2019-02-10 2020-02-10 Action Plan, including Fleet Based Selection International Ayeyarwady River Optimization C3-17REVISED / Formulation of the Resource Component 3. Navigation Consultant Open - Under Management and Operation IDA / 55590 Enhancement on the Post Qualification 490,000.00 0.00 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 International Implementation Plan for Ayeyarwady Ayeyarwady River Selection Navigation - RMOP C2-24 / Update of the Myanmar Climate Change Component 2. Hydro- Consultant Alliance documentation with meteorological Observation IDA / 55590 Post Qualification Open - National 100,000.00 0.00 Canceled 2018-12-01 2018-12-22 2019-02-04 2019-03-06 2019-04-10 2019-10-07 new outputs from DMH on and Information Systems Selection climate trends and Modernization projections C1-33 / ESIA and ESMP Component 1: Water Consultancy Service for Resource Management Consultant Open - Feasibility Study on IDA / 55590 Institutions, Decision Post Qualification 490,000.00 0.00 Canceled 2019-03-29 2019-04-19 2019-06-02 2019-07-02 2019-08-06 2020-02-02 International Navigation Enhancement Support Systems & Selection Work For Stretch 2 Capacity Building Component 1: Water C1-32 / Feasibility Study Resource Management Quality And Cost- Open - on Navigation Enhancement IDA / 55590 Institutions, Decision Post 800,000.00 0.00 Canceled 2019-03-29 2019-04-19 2019-06-02 2019-06-30 2019-07-30 2019-09-03 2019-10-08 2020-10-07 Based Selection International Work for Stretch 2 Support Systems & Capacity Building Component 1: Water C1-35 / Yangon Region Resource Management Quality And Cost- Open - IWRM Project Feasibility IDA / 55590 Institutions, Decision Post 800,000.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection International Study Support Systems & Capacity Building INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Water C1.4-12 / HIC Resource Management Individual INTERNATIONAL IDA / 55590 Institutions, Decision Prior Consultant Open 10,000.00 7,598.00 Completed CONSULTANT Support Systems & Selection Capacity Building Page 8 Component 1: Water Resource Management Individual C1.4.1 / Component-1 IDA / 55590 Institutions, Decision Prior Consultant Open 169,200.00 169,200.00 Signed Director Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1.4-4 / NATIONAL IDA / 55590 Institutions, Decision Prior Consultant Open 48,000.00 32,136.00 Signed PROCUREMENT OFFICER Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C2.1-10 / COMPONENT 2 IDA / 55590 Institutions, Decision Prior Consultant Open 288,000.00 317,155.15 Signed INTERNATIONAL ADVISOR Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1.4-4- b / NATIONAL IDA / 55590 Institutions, Decision Prior Consultant Open 24,000.00 34,380.00 Signed PROCUREMENT OFFICER2 Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1.4-15 / National IDA / 55590 Institutions, Decision Prior Consultant Open 24,000.00 15,120.00 Signed Financial Officer Support Systems & Selection Capacity Building C3-6 / Engineering design, Component 3. Navigation capacity building and IDA / 55590 Enhancement on the Prior Direct Selection Direct 300,000.00 377,336.92 Signed 2016-11-16 2016-11-26 2017-01-30 2017-07-29 construction supervision for Ayeyarwady River sub project1 Component 1: Water C1-4-2 / International Resource Management Individual Project Coordination Advisor IDA / 55590 Institutions, Decision Prior Consultant Open 200,000.00 91,900.00 Signed 2016-11-17 2017-01-05 2017-01-26 2017-03-02 2017-08-29 to Project Director Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-6 / National Project IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 12,600.00 Signed 2016-01-22 2016-02-08 2016-02-29 2016-05-17 2016-11-13 Accountant Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-1-14 / HIC/GIS & IDA / 55590 Institutions, Decision Post Consultant Open 40,000.00 30,000.00 Completed 2016-10-07 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Data Base Specialist Support Systems & Selection Capacity Building Component 1: Water C1-2-1A / Institutional Resource Management Individual Review and Development IDA / 55590 Institutions, Decision Post Consultant Open 55,000.00 41,700.00 Completed 2016-05-10 2016-08-08 2016-08-29 2016-10-11 2017-04-09 Planning - Team Leader Support Systems & Selection and Institutional Specialist Capacity Building Component 1: Water C1-2-1B / Institutional Resource Management Individual Review and Development IDA / 55590 Institutions, Decision Post Consultant Open 50,000.00 40,350.00 Completed 2016-06-01 2016-08-08 2016-08-26 2016-09-20 2017-03-19 Planning - Management Support Systems & Selection Specialist Capacity Building Component 1: Water C1-2-1C / Institutional Resource Management Individual Review and Development IDA / 55590 Institutions, Decision Post Consultant Open 50,000.00 42,750.00 Completed 2016-05-10 2016-08-08 2016-08-29 2016-09-20 2017-03-19 Planning - Governance Support Systems & Selection Specialist Capacity Building Component 1: Water Resource Management Individual C1-11A / HIC GIS IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 19,530.00 Signed 2016-05-10 2016-07-18 2016-08-08 2016-09-01 2017-02-28 Specialist Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-11B / HIC Water IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 13,860.00 Completed 2016-05-10 2016-07-19 2016-08-09 2016-08-29 2017-02-25 Resource Engineer Support Systems & Selection Capacity Building Page 9 Component 1: Water Resource Management Individual C1-11C / HIC Resource Under IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 20,160.00 2016-10-01 2016-11-24 2016-12-15 2017-01-19 2017-07-18 Economist Implementation Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-11D / HIC IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 20,160.00 Signed 2016-05-31 2016-07-14 2016-07-25 2016-08-17 2017-02-13 Environmental Scientist Support Systems & Selection Capacity Building Component 2. Hydro- Individual C2-1 / Component 2 meteorological Observation IDA / 55590 Post Consultant Open 24,000.00 25,200.00 Completed 2016-07-28 2016-09-15 2016-10-06 2016-11-10 2017-05-09 Project Officer and Information Systems Selection Modernization Component 2. Hydro- C2-3 / DMH International Individual meteorological Observation Institutional and Regulatory IDA / 55590 Post Consultant Open 50,000.00 52,530.00 Signed 2017-02-10 2017-03-31 2017-04-21 2017-05-26 2017-11-22 and Information Systems Review Consultant Selection Modernization Component 2. Hydro- C2-4 / DMH National Individual meteorological Observation Institutional and Regulatory IDA / 55590 Post Consultant Open 25,000.00 15,070.00 Completed 2017-02-10 2017-03-31 2017-04-21 2017-05-26 2017-11-22 and Information Systems Review Consultant Selection Modernization Component 1: Water Resource Management Individual C1-11-C-REVISED / HIC IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 18,900.00 Completed 2016-10-07 2016-11-25 2016-12-12 2016-12-12 2017-06-10 Resource Economist-Revised Support Systems & Selection Capacity Building C3-10 / Component 3 Component 3. Navigation Individual International Engineering IDA / 55590 Enhancement on the Post Consultant Open 100,000.00 96,850.00 Completed 2016-10-31 2016-12-19 2017-01-09 2017-01-17 2017-07-16 Specialist Ayeyarwady River Selection Component 3. Navigation Individual C3-11 / Project Officer 2 IDA / 55590 Enhancement on the Post Consultant Open 24,000.00 14,400.00 Signed 2017-02-17 2017-04-07 2017-04-28 2017-06-02 2017-11-29 for Component 3 Ayeyarwady River Selection Component 1: Water Resource Management Individual C1-4-8A / National IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 18,540.00 Completed 2016-01-29 2016-02-17 2016-02-17 2016-02-24 2018-02-23 Environmental Officer Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-8B / National Social IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 11,340.00 Completed 2016-11-18 2016-12-12 2016-12-19 2016-12-19 2017-12-18 Officer Support Systems & Selection Capacity Building Component 1: Water C 1-4-11B / Stakeholder Resource Management Individual Communication Officer 2 for IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 15,600.00 Signed 2017-01-17 2017-03-07 2017-03-28 2017-05-02 2017-10-29 Component 1 Support Systems & Selection Capacity Building C3-12 / International Component 3. Navigation Individual Hydraulic Modelling IDA / 55590 Enhancement on the Post Consultant Open 113,950.00 121,590.00 Signed 2017-05-30 2017-07-18 2017-08-08 2017-09-12 2018-03-11 Specialist Ayeyarwady River Selection Component 1: Water C1-18REVISED / Evaluator Resource Management Individual for Myanmar-Netherlands IDA / 55590 Institutions, Decision Post Consultant Direct 9,500.00 9,000.00 Completed 2017-05-30 2017-06-09 2017-06-30 2017-08-04 2018-01-31 MOU Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-3 / International IDA / 55590 Institutions, Decision Post Consultant Open 237,140.00 317,300.00 Completed 2015-08-31 2015-11-30 2015-11-30 2015-12-24 2017-12-23 Procurement Advisor Support Systems & Selection Capacity Building Component 1: Water C1-4-5 / International Resource Management Individual Financial Management IDA / 55590 Institutions, Decision Post Consultant Open 200,000.00 231,915.00 Completed 2015-08-31 2015-11-30 2015-11-30 2015-12-24 2017-12-23 Advisor Support Systems & Selection Capacity Building Page 10 Component 1: Water Resource Management Individual C1-4-7 / International IDA / 55590 Institutions, Decision Post Consultant Open 200,000.00 334,500.00 Terminated 2015-08-31 2015-12-01 2016-01-31 2016-02-15 2018-02-14 Safeguards Advisor Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-9 / Component 1 IDA / 55590 Institutions, Decision Post Consultant Open 200,000.00 231,915.00 Signed 2015-10-31 2015-12-31 2015-12-31 2016-01-07 2018-01-06 International Advisor Support Systems & Selection Capacity Building Component 1: Water C1-4-11A / Stakeholder Resource Management Individual Communication Officer 1 for IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 18,900.00 Completed 2016-02-29 2016-02-29 2016-02-29 2016-06-21 2017-06-20 Component 1 Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-18 / Project Director IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 21,420.00 Completed 2016-03-01 2016-03-01 2016-03-01 2016-03-17 2017-03-16 Executive Assistatn Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-20 / National IT IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 11,340.00 Signed 2016-07-31 2016-07-31 2016-07-31 2016-09-06 2017-09-05 Network Specialist Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-9A / Project Officer 1 IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 18,900.00 Signed 2016-02-01 2016-02-01 2016-02-01 2016-05-02 2017-05-01 for Component 1 Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-9B / Project Officer 2 IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 10,080.00 Signed 2016-02-29 2016-02-29 2016-02-29 2016-05-12 2018-05-11 for Component 1 Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-10A / HIC Junior IDA / 55590 Institutions, Decision Post Consultant Open 6,000.00 6,300.00 Completed 2016-02-29 2016-02-29 2016-03-31 2016-04-01 2018-04-01 Researcher Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-10C / HIC Junior IDA / 55590 Institutions, Decision Post Consultant Open 6,000.00 6,300.00 Completed 2016-02-29 2016-02-29 2016-02-29 2016-04-01 2018-04-01 Researcher Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-10D / HIC Junior IDA / 55590 Institutions, Decision Post Consultant Open 6,000.00 6,300.00 Signed 2016-02-29 2016-02-29 2016-02-29 2016-04-01 2018-04-01 Researcher Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-10E / HIC Junior IDA / 55590 Institutions, Decision Post Consultant Open 6,000.00 6,300.00 Completed 2016-02-29 2016-02-29 2016-02-29 2016-04-01 2018-04-01 Researcher Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-10F CBBW / HIC IDA / 55590 Institutions, Decision Post Consultant Open 6,000.00 6,300.00 Completed 2016-02-29 2016-02-29 2016-02-29 2016-04-01 2017-04-01 Junior Researcher Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-10F PEP / HIC Junior IDA / 55590 Institutions, Decision Post Consultant Open 6,000.00 6,300.00 Completed 2016-02-29 2016-02-29 2016-02-29 2016-04-01 2018-03-03 Researcher Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-10G / HIC Junior IDA / 55590 Institutions, Decision Post Consultant Open 6,000.00 6,300.00 Signed 2016-02-29 2016-02-29 2016-02-29 2016-04-01 2018-04-01 Researcher Support Systems & Selection Capacity Building Page 11 Component 3. Navigation Individual C3-4-11 / Component 3 IDA / 55590 Enhancement on the Post Consultant Open 231,915.00 231,915.00 Signed 2015-08-31 2015-10-31 2015-10-31 2015-12-22 2017-12-21 International Advisor Ayeyarwady River Selection Component 3. Navigation Individual C3-4-1 / Project Officer 1 IDA / 55590 Enhancement on the Post Consultant Open 24,000.00 16,380.00 Signed 2016-02-29 2016-05-31 2016-05-31 2016-07-04 2018-07-03 for Component 3 Ayeyarwady River Selection Component 1: Water Resource Management Individual C1-18 / Evaluator for IDA / 55590 Institutions, Decision Prior Consultant Direct 9,500.00 0.00 Canceled 2017-03-03 2017-03-13 2017-03-13 2017-04-03 2017-09-30 Myanmar-Netherlands MOU Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-1-13 / NWRC IDA / 55590 Institutions, Decision Post Consultant Open 6,000.00 0.00 Canceled 2017-12-31 2017-12-31 2017-12-31 2018-03-01 2019-03-01 Secretariat Support Officer Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-20 / English/Myanmar IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 8,400.00 Signed 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 Translator for PMU Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-21 / English/Myanmar IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 9,600.00 Completed 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 Translator for Component 1 Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-22 / HIC IT Network IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 9,600.00 Completed 2017-12-31 2018-02-18 2018-03-11 2018-04-15 2018-10-12 Specialist Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-23 / AG Secretariat IDA / 55590 Institutions, Decision Post Consultant Open 18,000.00 8,400.00 Signed 2017-12-31 2018-02-18 2018-03-11 2018-04-15 2018-10-12 Technical Officer Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-24 / NWRC Secretariat Under IDA / 55590 Institutions, Decision Post Consultant Open 18,000.00 0.00 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 Coordinating Officer Implementation Support Systems & Selection Capacity Building Component 1: Water C1-25 / Stakeholder Forum Resource Management Individual Coordinator for Component IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 18,000.00 Completed 2017-11-30 2018-01-18 2018-02-08 2018-03-15 2018-09-11 1 Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-26 / Senior Safeguard IDA / 55590 Institutions, Decision Post Consultant Direct 50,000.00 30,800.00 Completed 2017-11-21 2017-12-01 2017-12-22 2018-01-26 2018-07-25 Specialist (National) Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-27 / National Civil Under IDA / 55590 Institutions, Decision Post Consultant Open 30,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 Engineer,Structural Implementation Support Systems & Selection Capacity Building Component 1: Water C1-28 / C1 National Social Resource Management Specialist for Yangon Region IDA / 55590 Institutions, Decision Post Direct Selection Direct 5,000.00 3,000.00 Completed 2018-02-01 2018-02-11 2018-03-04 2018-03-24 IWRM Project Preparation Support Systems & Capacity Building Component 2. Hydro- C2-5 / Component 2 meteorological Observation IDA / 55590 Post Direct Selection Direct 190,000.00 157,463.00 Signed 2018-01-01 2018-01-11 2018-03-17 2018-09-13 International Advisor 2 and Information Systems Modernization Component 2. Hydro- C2-7 / Component 2 meteorological Observation International Hydrological IDA / 55590 Post Direct Selection Direct 190,000.00 163,568.00 Signed 2018-02-28 2018-03-10 2018-05-14 2018-11-10 and Information Systems Specialist Modernization Page 12 Component 3. Navigation Individual C3-15 / Senior River IDA / 55590 Enhancement on the Post Consultant Open 150,000.00 243,600.00 Completed 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2018-12-10 Engineer Ayeyarwady River Selection Component 3. Navigation Individual C3-16 / Project Officer 3 Under IDA / 55590 Enhancement on the Post Consultant Open 24,000.00 14,400.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-11-13 for Component 3 Implementation Ayeyarwady River Selection Component 2. Hydro- C2-1A / Project Officer 2 meteorological Observation IDA / 55590 Post Direct Selection Direct 24,000.00 24,000.00 Signed 2018-01-15 2018-01-25 2018-02-09 2018-08-08 for Component 2 and Information Systems Modernization Component 1: Water Resource Management C1-4-8C / National IDA / 55590 Institutions, Decision Post Direct Selection Direct 24,000.00 14,400.00 Completed 2017-11-30 2017-12-10 2017-12-25 2018-12-25 Safeguard Officer Support Systems & Capacity Building Component 1: Water Resource Management Individual C1-4-3A / International IDA / 55590 Institutions, Decision Prior Consultant Open 290,000.00 197,600.00 Signed 2018-04-12 2018-05-15 2018-05-29 2018-06-17 2018-12-14 Procurement Advisor Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-29 / PFI Coordinator IDA / 55590 Institutions, Decision Post Consultant Open 54,850.00 30,000.00 Signed 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-06-12 for YGN-IWRM Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-8 D / National IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 18,000.00 Signed 2018-07-31 2018-09-18 2018-10-09 2018-11-13 2019-05-12 Environmental Officer Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-8 E / National Social IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 18,000.00 Completed 2018-07-31 2018-09-18 2018-10-09 2018-11-13 2019-05-12 Officer Support Systems & Selection Capacity Building Component 2. Hydro- Individual C2-10 / National Legal meteorological Observation IDA / 55590 Post Consultant Open 10,000.00 12,590.00 Signed 2018-08-01 2018-09-19 2018-10-10 2018-11-14 2019-05-13 Consultant and Information Systems Selection Modernization Component 3. Navigation Individual C3-19 / National Specialist IDA / 55590 Enhancement on the Post Consultant Open 10,000.00 12,360.00 Signed 2018-07-16 2018-09-03 2018-09-24 2018-10-29 2019-04-27 for Aids to Navigation Ayeyarwady River Selection Component 2. Hydro- C2-6 / Component 2 meteorological Observation IDA / 55590 Post Direct Selection Direct 50,000.00 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 National Advisor and Information Systems Modernization C1-31REVISED / The New Yangon City (regional) fresh Component 1: Water water supply study- Resource Management Under Development of the vision IDA / 55590 Institutions, Decision Post Direct Selection Direct 100,000.00 0.00 2018-09-30 2018-10-10 2018-12-14 2019-06-12 Implementation and functional requirements Support Systems & of the Pan Hlaing River Capacity Building System Component 2. Hydro- Individual C2-12 / Component 2 meteorological Observation IDA / 55590 Post Consultant Open 42,000.00 688.98 Signed 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2019-09-11 Finance Assistant and Information Systems Selection Modernization Component 2. Hydro- C2-13 / Component 2 Individual meteorological Observation Project Officer cum. Asst. to IDA / 55590 Post Consultant Open 42,000.00 12,000.00 Signed 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2019-09-11 and Information Systems Procurement Selection Modernization C3-19A / National Component 3. Navigation Individual Specialist for Aids to IDA / 55590 Enhancement on the Post Consultant Direct 10,000.00 12,360.00 Signed 2018-12-15 2018-12-25 2019-01-15 2019-02-19 2019-08-18 Navigation Ayeyarwady River Selection C3-19B / National Component 3. Navigation Individual Specialist for Aids to IDA / 55590 Enhancement on the Post Consultant Direct 10,000.00 12,360.00 Signed 2018-12-15 2018-12-25 2019-01-15 2019-02-19 2019-08-18 Navigation Ayeyarwady River Selection Page 13 C3-18 / National River Component 3. Navigation Individual Under Engineer and Coordinator IDA / 55590 Enhancement on the Post Consultant Limited 24,000.00 0.00 2019-04-01 2019-04-06 2019-04-27 2019-06-01 2019-11-28 Implementation for Component 3 Ayeyarwady River Selection Component 1: Water C1-31 / The New Yangon Resource Management City (regional) fresh water IDA / 55590 Institutions, Decision Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-08-31 2018-09-10 2018-11-14 2019-05-13 supply study Support Systems & Capacity Building Component 1: Water Resource Management C1-30 / International IDA / 55590 Institutions, Decision Prior Direct Selection Direct 25,000.00 0.00 Canceled 2018-08-31 2018-09-10 2018-11-14 2019-05-13 Water Law Consultant Support Systems & Capacity Building Component 1: Water C1-4-11C / Stakeholder Resource Management Individual Communication Officer for IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 12,000.00 Completed 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Component 1 Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-21A / English-Myanmar Pending IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Translator for Component 1 Implementation Support Systems & Selection Capacity Building Component 1: Water C1-30REVISED / Resource Management Individual International Water Law IDA / 55590 Institutions, Decision Post Consultant Open 25,000.00 36,140.00 Signed 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Consultant Support Systems & Selection Capacity Building Component 1: Water C1-36 / International Resource Management Individual Strategic Advisor for the Pending IDA / 55590 Institutions, Decision Post Consultant Open 30,000.00 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 preparation of the Yangon Implementation Support Systems & Selection Region IWRM Project Capacity Building Component 1: Water C1-38 / Interim Resource Management Individual International Finance IDA / 55590 Institutions, Decision Post Consultant Open 40,000.00 22,360.00 Signed 2019-05-28 2019-05-31 2019-06-01 2019-06-03 2019-11-30 Management Advisor Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1.4-8F / National IDA / 55590 Institutions, Decision Post Consultant Open 24,000.00 15,600.00 Signed 2019-07-31 2019-09-02 2019-09-09 2019-09-11 2020-09-05 Safeguard Officer Support Systems & Selection Capacity Building Component 1: Water C1-4-5A / International Resource Management Individual Pending Financial Management IDA / 55590 Institutions, Decision Prior Consultant Direct 100,000.00 0.00 2019-12-31 2020-01-10 2020-01-31 2020-03-06 2020-09-02 Implementation Advisor Support Systems & Selection Capacity Building Component 1: Water Resource Management Individual C1-4-7A / International Pending IDA / 55590 Institutions, Decision Post Consultant Open 150,000.00 0.00 2019-12-31 2020-02-18 2020-03-10 2020-04-14 2020-10-11 Safeguards Advisor Implementation Support Systems & Selection Capacity Building Page 14