PROCUREMENT PLAN (Textual Part) Project information: Kiribati Outer Islands Transport, Infrastructure Investment Project (P165838) Project Implementation agency: Ministry of Infrastructure and Sustainable Energy (MISE); Ministry of Information, Communications, Transport & Tourism Development (MICTTD) Date of the Procurement Plan: July 2019 Period covered by this Procurement Plan: July 1, 2019 – June 30, 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in 2002 Kiribati Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Kiribati : Kiribati Outer Islands Transport Infrastructure Investment Project PLAN General Information Country: Kiribati Bank’s Approval Date of the Original Procurement Plan: 2020-09-25 2021-07-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165838 GPN Date: 2020-10-02 Project Name: Kiribati Outer Islands Transport Infrastructure Investment Project Loan / Credit No: IDA / D5590 K Executing Agency(ies): iribati Fiduciary Service Unit WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KI-KFSU-194818-CS-INDV / Individual Component 3: Strengthening Safeguard Officer Social IDA / D5590 Post Consultant Open 30,950.00 Signed 2020-09-27 2021-02-06 2020-11-15 2021-03-22 2020-12-06 2021-03-22 2021-01-10 2021-04-08 2021-07-09 the Enabling Environment (national) Selection KI-KFSU-194815-CS-INDV / Individual Component 3: Strengthening Under Safeguards Specialist IDA / D5590 Prior Consultant Open 0.00 2020-09-27 2021-01-19 2020-11-15 2021-06-01 2020-12-06 2021-01-10 2021-07-09 the Enabling Environment Implementation (international) Selection KI-KFSU-194819-CS-INDV / Individual Component 3: Strengthening Safeguards Officer IDA / D5590 Post Consultant Open 0.00 Canceled 2020-09-27 2021-02-06 2020-11-15 2021-03-22 2020-12-06 2021-03-22 2021-01-10 2021-07-09 the Enabling Environment Environment Selection Individual KOITIIP-INDV 6 KFSU / Component 3: Strengthening IDA / D5590 Post Consultant Open 0.00 Under Review 2021-04-29 2021-07-23 2021-06-17 2021-07-08 2021-08-12 2022-02-08 Procurement Officer 2 the Enabling Environment Selection KI-KFSU-194820-CS-INDV1 Individual Component 3: Strengthening Pending / Accountant Consultant 1, IDA / D5590 Post Consultant Open 0.00 2021-07-23 2021-09-10 2021-10-01 2021-11-05 2022-05-04 the Enabling Environment Implementation KFSU Selection KI-KFSU-194821-CS-INDV 2 Individual Component 3: Strengthening Pending / Accountant Consultant 2, IDA / D5590 Post Consultant Open 0.00 2021-07-23 2021-09-10 2021-10-01 2021-11-05 2022-05-04 the Enabling Environment Implementation KFSU Selection Page 1