Page 1 Procurement Plan-Goods Country/Organisation: NIGERIA/ EBONYI STATE HIV/AIDS PROGRAMME DEVELOPMENT PROJECT Project/Programme: EBOSACA ABAKALIKI If Post-Review, No-objection Dates are not needed Loan #: Spec Proc Notice Contract Implementation Description* Package Number Lot Number Estimated Amount in US $ Procurement Method Pre-or Post Qualification Prior or Post Review Plan vs. Actual Prep & Submission by Ex Agency No-objection Date On-line UNDB Gateway Nat Press Bid Invitation Date Bid Closing- Opening Submission Bid Eval Rpt No-objection Date Plan vs. Actual Contract Amount in US$'000 Date Contract Award Date Contract Signature Opening of Let of Credit Arrival of Goods Inspection Final Acceptance If Prequalification Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks 1 - 1.5 wks Plan 1 wk 1.5-3 wks add 7-13 wks Actual Actual List of Contracts EB/HIV/01/07 1 15.00 N/Shopping N/A Post Plan 02/04/07 02/04/07 N/A 16/04/07 30/04/07 10/05/07 N/A Plan 15.00 30/05/07 30/05/07 N/A 30/06/07 30/06/07 Actual Actual date EB/HIV02/07 1 15.00 N/Shopping N/A Post Plan 02/04/07 02/04/07 N/A 16/04/07 30/04/07 10/05/07 N/A Plan 15.00 S 30/05/07 N/A 30/06/07 30/06/07 Actual Actual EB/HIV/03/07 1 42.00 N/Shopping N/A Post Plan 02/04/07 02/04/07 N/A 16/04/07 30/04/07 10/05/07 N/A Plan 42.00 30/05/07 30/05/07 N/A 30/06/07 30/06/07 Actual Actual EB/HIV/04/07 1 46.00 N/Shopping N/A Post Plan 01/05/07 14/05/07 N/A 15/05/07 29/05/07 08/05/07 N/A Plan 46.00 04/06/07 11/06/07 N/A 29/06/07 05/07/07 Actual Actual EB/HIV/05/07 1 38.00 Shopping N/A Post Plan 01/05/07 14/05/07 N/A 15/05/07 29/05/07 08/05/07 N/A Plan 38.00 04/06/07 11/06/07 N/A 29/06/07 05/07/07 Actual Actual EB/HIV/06/07 1 46.00 N/Shopping N/A Post Plan 01/05/07 14/05/07 N/A 15/05/07 29/05/07 08/05/07 N/A Plan 46.00 04/06/07 11/06/07 N/A 29/06/07 05/07/07 Actual Actual EB/HIV/07/07 1 23.00 N/Shopping N/A Post Plan 01/05/07 14/05/07 N/A 15/05/07 29/05/07 08/05/07 N/A Plan 23.00 04/06/07 11/06/07 N/A 29/06/07 05/07/07 Actual Actual EB/HIV/08/07 1 4.00 N/SHOPPING NA POST Plan 01/05/07 14/05/07 NA 15/05/07 29/05/07 08/05/07 NA Plan 4.00 04/06/07 11/06/07 NA 29/06/07 05/07/07 Actual Actual EB/HIV/09/07 1 61.00 N/SHOPPING NA POST Plan 2/05/07 15/05/07 NA 16/05/07 30/05/07 01/06/07 NA Plan 61.00 10/06/07 15/06/07 NA 20/06/07 30/06/07 Actual Actual Total Cost 290.00 Plan Plan 290.00 0.00 Actual Actual 0.00 Fill gray cells only! Bid Evaluation Contract Finalization BASIC DATA Bidding Period Draft Bid Documents, including specs and quantities, draft SPN Norm Duration of Proc Steps Procurement of 1 No. 4Wheel Drive vehicle Furnishing and equiping of new Saca office Renovation of new SACA Secretariat Production of additional bulletins,periodicals Establishment of five youth friendly viewing centres SACA Agency bill Procurement of male and female condoms Mass Production of SSF Production of bill boards, bulletins etc 4208700PROP0P01rocurement0Plan02007.xls 1 of 17 01/16/2008 3:00 AM Page 2 Procurement Plan-Approvals-Goods Initial Approval Update Dates of Bank Approval of Procurement Plan For Goods 4208700PROP0P01rocurement0Plan02007.xls 2 of 17 01/16/2008 3:00 AM Page 3 Procurement Plan-Works Country/Organisation: Project/Programme: Loan #: Description* Package Number Lot Number Lumpsum or Bill of Quantities Procurement Method Estimated Amount in US $ Pre-or Post Qualification Prior or Post Review If Prequalification add 7-13 wks List of Contracts Total Cost 0.00 0.00 Fill gray cells only! Basic Data Norm Duration of Proc Steps 4208700PROP0P01rocurement0Plan02007.xls 3 of 17 01/16/2008 3:00 AM Page 4 Procurement Plan-Works Country/Organisation: Project/Programme: Loan #: Description* List of Contracts Total Cost Fill gray cells only! Norm Duration of Proc Steps If Post-Review, No-objection Dates are not needed Spec Proc Notice Advert Plan vs. Actual Prep & Submission by Ex Agency No-objection Date On-line UNDB Gateway Nat Press Bid Invitation Date Bid Closing- Opening Submission Bid Eval Rpt No-objection Date Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Bid Evaluation Bidding Period Draft Bid Documents, including specs and quantities, draft SPN 4208700PROP0P01rocurement0Plan02007.xls 4 of 17 01/16/2008 3:00 AM Page 5 Procurement Plan-Works Country/Organisation: Project/Programme: Loan #: Description* List of Contracts Total Cost Fill gray cells only! Norm Duration of Proc Steps Plan vs. Actual Contract Amount in US$ '000 Date Contract Award Date Contract Signature Mobilization Advance Payment Substantial Completion Final Acceptance Final Cost Plan 1 wk 1.5-3 wks Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan 0.00 0.00 Actual 0.00 0.00 Contract Finalization Contract Implementation 4208700PROP0P01rocurement0Plan02007.xls 5 of 17 01/16/2008 3:00 AM Page 6 Procurement Plan-Approvals-Works Initial Approval Update Dates of Bank Approval of Procurement Plan For Works 4208700PROP0P01rocurement0Plan02007.xls 6 of 17 01/16/2008 3:00 AM Page 7 Procurement Plan-Consultants Country/Organisation: NIGERIA/EBONYI STATE HIV/AID PROGRAMME DEVELOPMENT PROJECT, ABAKALIKI Project/Programme: EBONYI STATE HIV/AIDS PROGRAMME DEVELOPMENT PROJECT If Post-Review, No-objection Dates are not needed Loan #: Contract Type Description* Selection Method Lumpsum or Time- Estimated Amount in US$ Prior/Post Review Plan vs. Actual Prep & Submission by Ex Ag No- objection Date On-line UNDB Gateway Lead-time before shortlist Submission Date No- objection Date Plan vs. Actual Invitation Date Submission/ Opening Date Submission Evaluation Report (T) No-objection Evaluation Report (T) Opening Financial Proposals Submission Eval Report (T) (F) No-objection Eval Report (T) (F) Plan vs. Actual Negotiations Submission Draft Contract No-objection Negotiations Contract Amount in US$ '000 Contract ward Contract Signature Plan vs. Actual Mobilization Advance Payment Draft Report Final Report Final Cost Plan 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 1 - 2 wks Plan 4 to 12 wks 2 - 3 wks 0.5 - 2 wks 2 wks 1 - 2 wks 1 - 1,5 wks Plan 2 wks 1 - 2 wks 1 - 2 wks 1 wk 1 - 3 wks Plan Actual Actual Actual Actual List of Contracts CQ Lump Sum 846,615.00 Post Plan 02/04/07 16/04/07 N/A N/A NA NA Plan 30/04/07 07/05/07 14/05/07 28/05/07 01/06/07 10/06/07 18/06/07 Plan 30/06/07 07/07/07 14/07/07 846,615.00 01/08/07 07/08/07 Plan 14/08/07 14/09/07 30/09/07 Actual Actual Actual Actual QCBS Lump Sum 919.00 Post Plan 02/04/07 16/04/07 N/A N/A N/A NA Plan 30/04/07 07/05/07 14/05/07 28/05/07 01/06/07 10/06/07 18/06/07 Plan 30/06/07 07/07/07 14/07/07 919.00 01/08/07 07/08/07 Plan NA 14/09/07 30/09/07 Actual Actual Actual Actual IC Lump Sum 111.00 Post Plan 10/04/07 24/04/07 N/A N/A N/A N/A Plan 05/05/07 14/05/07 21/05/07 07/06/07 21/06/07 28/06/07 05/07/07 Plan 20/07/07 28/07/07 10/08/07 111.00 17/08/07 25/08/07 Plan NA 30/08/07 20/09/07 Actual Actual Actual Actual IC Lump Sum 84.00 Post Plan 10/04/07 24/04/07 N/A N/A N/A N/A Plan 05/05/07 14/05/07 21/05/07 07/06/07 21/06/07 28/06/07 05/07/07 Plan 20/07/07 28/07/07 10/08/07 84.00 17/08/07 25/08/07 Plan NA 30/08/07 20/09/07 Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Total Cost 847,729.00 Plan Plan Plan 847,729.00 Plan 0.00 0.00 Actual Actual Actual 0.00 Actual 0.00 Fill gray cells only! Grants to LGAs Contract Finalization Short List Consultant Proposals Preparation Request for Proposal Evaluation Technical (T) & Financial (F) for projects approved before May Negotiations Request for Expression of Interest Contract Implementation Support to line ministries Norm Duration of Proc Steps State Strategic framework Funding of HAF 4208700PROP0P01rocurement0Plan02007.xls 7 of 17 01/16/2008 3:00 AM Page 8 Procurement Plan-Approvals-Consultants Initial Approval Update Dates of Bank Approval of Procurement Plan For Consultants 4208700PROP0P01rocurement0Plan02007.xls 8 of 17 01/16/2008 3:00 AM Page 9 Procurement Plan-Consultants 2 Country/Organisation: For Contracts under projects approved before the May 2002 Guidelines Project/Programme: If Post-Review, No-objection Dates are not needed Loan #: Contract Type Description* Selection Method Lumpsum or Time-Based Estimated Amount in US$ '000 Prior/Post Review Plan vs. Actual Prep & Submission by Ex Ag No-objection Date On-line UNDB Gateway Nat Press Lead-time before shortlist Submission Date No-objection Date Plan 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 1 - 2 wks Actual List of Contracts Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Total Cost 0.00 Plan 0.00 Actual Fill gray cells only! Request for EOI (where required) Short List Preparation Request for Proposals Norm Duration of Proc Steps 4208700PROP0P01rocurement0Plan02007.xls 9 of 17 01/16/2008 3:00 AM Page 10 Procurement Plan-Consultants 2 Country/Organisation: Project/Programme: Loan #: Description* List of Contracts Total Cost Fill gray cells only! Norm Duration of Proc Steps Plan vs. Actual Invitation Date Submission/ Opening Date Submission Evaluation Report (T) No-objection Evaluation Report (T) Opening Financial Proposals Preparation Eval Report (T) (F) Negotiations (N) Plan 4 to 12 wks 2 - 3 wks 0.5 - 2 wks 2 wks 1 - 2 wks 2 wks Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Consultant Proposals Proposal Evaluation and Negotiation for Projects after May 2002 Technical (T) & Financial (F) and Negotions (N) 4208700PROP0P01rocurement0Plan02007.xls 10 of 17 01/16/2008 3:00 AM Page 11 Procurement Plan-Consultants 2 Country/Organisation: Project/Programme: Loan #: Description* List of Contracts Total Cost Fill gray cells only! Norm Duration of Proc Steps Plan vs. Actual Submission Date No-objection Date Contract Amount in US$ '000 Contract Award Contract Signature Plan 1 - 2 wks 1 - 2 wks 1 wk 1 - 3 wks Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan 0.00 Actual 0.00 Draft Contract Contract Finalization 4208700PROP0P01rocurement0Plan02007.xls 11 of 17 01/16/2008 3:00 AM Page 12 Procurement Plan-Consultants 2 Country/Organisation: Project/Programme: Loan #: Description* List of Contracts Total Cost Fill gray cells only! Norm Duration of Proc Steps Plan vs. Actual Mobilization Advance Payment Draft Report Final Report Final Cost Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual Plan 0.00 Actual 0.00 Contract Implementation 4208700PROP0P01rocurement0Plan02007.xls 12 of 17 01/16/2008 3:00 AM Page 13 EBONYI STATE HIV/AIDS PROGRAMME DEVELOPMENT PROJECT PROCUREMENT PLAN 2007 TRAININGS & CAPACITY BUILDING PLAN & STUDY TOUR Transport 0.4 2 Workplan Finalizati on Clinic for Lacas and Line Ministries Lacas & Line Ministries Desk Officers, Critical Mass of each HIV unit Ai 3days NA 9 Nominate d members, plwas, etc Local capacity 5 SACA staff Saca managem Ai Naca accr. Inst. Na 15 4 State participati on in 2007 Aids summit Delegates Abuja 5 days NA 9 Na 9 3 SACA periodic & emmerge ncy meetings Saca members & staff SACA Ai Periodic 1 Saca Training of SACA/ project and health workers on relevant emerging issues/ne eds 29 line mins & 13 Lacas SACA officers & senior personel Abakaliki 3 Weeks NA 28 Designati on Venue Period Tuition fee S/N Dept Descripti on of Training Participa nts Page 14 Buildings on hiv/aids program ming Invited public, saca, cso etc 7 Skills acquisitio n workshop for PLWHAs PLWHA EBONET MEMBER S Ai 1 Week Na 12 9 Start up workshop s for HAF process Beneficia ries NGOs,CB Os Ai 1 week NA 9 25 General AI 1 week NA 8 2007 World Aids Day Celebrati on The General Public 9 6 Stakehold ers meeting to review SSF Stakehold ers Ai 2 Weeks NA ent staff Page 15 EBONYI STATE HIV/AIDS PROGRAMME DEVELOPMENT PROJECT DSA Total in 0.6 US$ 14 23 23 38 23 14 14 23 41 69 Remarks Page 16 19 31 14 23 37 62 14 23 Page 17 Procurement Plan-Approvals-Consultants 2 Initial Approval Update Dates of Bank Approval of Procurement Plan For Consultants 2 4208700PROP0P01rocurement0Plan02007.xls 17 of 17 01/16/2008 3:00 AM