Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) Indonesia National Slum Upgrading Project (P154782) EAST ASIA AND PACIFIC | Indonesia | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 4 | ARCHIVED on 04-Apr-2018 | ISR31855 | Implementing Agencies: Ministry of Public Works and Housing, Ministry of Finance Key Dates Key Project Dates Bank Approval Date:12-Jul-2016 Effectiveness Date:11-Oct-2016 Planned Mid Term Review Date:04-Mar-2019 Actual Mid-Term Review Date:-- Original Closing Date:31-Mar-2022 Revised Closing Date:31-Mar-2022 Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve access to urban infrastructure and services in targeted slums in Indonesia. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Institutional and Policy Development:(Cost $7.00 M) Integrated Planning Support and Capacity Building for Local Government and Communities:(Cost $84.00 M) Urban Infrastructure and Services Investment Support:(Cost $1578.00 M) Implementation Support and Technical Assistance:(Cost $74.00 M) Contingency for Disaster Response Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Satisfactory  Moderately Satisfactory Overall Risk Rating  Moderate  Moderate 4/4/2018 Page 1 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) Implementation Status and Key Decisions Overall progress towards achieving the PDO is still on track, despite slight implementation delays. Six out of eight targets set for 31 December 2017 have been met, such as: LG task forces established, SIAPs and CSPs completed for 2018 implementation, complaints resolved, and independent audit of Board of Trustee completed. The program has conducted training for local governments, city level teams and kelurahan (urban ward) facilitator teams, and has prepared detailed Slum Improvement Action Plans (SIAPs) in 44 priority cities and Community Settlement Plans (CSPs) in 3640 kelurahans. By the end of December 2017, the project had financed the implementation of tertiary infrastructure in 706 kelurahans, resulting in 918,000 beneficiaries to-date. The quality of the completed works visited is generally good, however the quality of planning and selection of primary/secondary infrastructure varies significantly from one location to another. Now that the National Management Consultants have come aboard, the completion and issuance of project technical manuals early in 2018 should be completed immediately to address these issues. Overall, it is still relatively early in implementation. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Moderate  Moderate  Moderate Macroeconomic  Moderate  Moderate  Moderate Sector Strategies and Policies  Low  Low  Low Technical Design of Project or Program  Moderate  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  Substantial  Substantial  Substantial Fiduciary  Moderate  Moderate  Moderate Environment and Social  Moderate  Moderate  Moderate Stakeholders  Moderate  Moderate  Moderate Other  --  --  -- Overall  Moderate  Moderate  Moderate Results Project Development Objective Indicators PHINDPDOTBL  People provided with improved infrastructure under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 9,500,000.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 4/4/2018 Page 2 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) Comments The first target is set for December 2018. Intervention and construction for 2017 has been completed, a calculation of the interim outcome will be available by the end of April 2018. PHINDPDOTBL  People provided with "improved water sources" under the project (of which women) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 800,000.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 PHINDPDOTBL  People provided with "improved sanitation" under the project (of which women) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,200,000.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 PHINDPDOTBL  People provided with access to all-season roads within 500 meter range under the project (of which women) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3,700,000.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 PHINDPDOTBL  People provided with regular solid waste collection under the project (of which women) (Number, Custom Breakdown) 4/4/2018 Page 3 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,500,000.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 PHINDPDOTBL  People provided with "improved drainage" under the project (of which women) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3,600,000.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 PHINDPDOTBL  Slum Area Alleviated (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7,800.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments The first target is set for December 2018. A calculation of the slum area reduced will be available by end of April 2018 following the completion of data updating of slum profile and investments of various funding. PHINDPDOTBL  Percentage of slum dwellers who are satisfied with the quality of urban infrastructure and services (of which women, of which bottom 40%, of which poor) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments The result will be produced through household survey scheduled to be carried out in the fourth quarter of 2018. 4/4/2018 Page 4 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) PHINDPDOTBL  Percentage of complaints resolved (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 99.56 99.90 90.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments NSUP has received 924 complaints, including request of information or clarification, channeled through various means. Out of 924 cases, 923 cases have been resolved. (Source of data: National Management Consultant (NMC) of NSUP through offline record). PHINDPDOTBL  Establishment of functional task forces for slum alleviation at local level (%Local Governments) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 76.00 79.00 90.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments Of the 154 participating cities, 121 cities (79%) have established the local task forces, however only 28.8% of local task forces are functioning effectively. In terms of functionality, it often happens that in the first quarter of a new fiscal year local governments are not yet fully active in implementation of the program. (Source: Secretariat of National Task Force and NMC of NSUP) PHINDPDOTBL  Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 917,690.00 9,700,000.00 4/4/2018 Page 5 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments The target by December 2018 is set at 3,000,000 people. Up to now, number of beneficiaries from investment of tertiary infrastructure and services across 701 kelurahans is 917,690 persons. The total recorded number of beneficiaries of improved infrastructure in slum areas under the umbrella program is 1,739,418, (national and local governments, community self-funded, etc). It is expected that in 2018, there will be investments due to loans in about 1,600 kelurahans. (Source: NMC of NSUP, data recorded offline). PHINDPDOTBL  Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 51.30 4,850,000.00 Overall Comments Intermediate Results Indicators PHINDIRITBL  Indicator 1.1. Establishment of functional task force for slum alleviation at national level (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N Y Y Y Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments The National Task Force was established in 2017, and the implementing team was formally assigned in January 2018. The implementing team will lead the program through Central Collaboration Management Unit (CCMU). 4/4/2018 Page 6 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) PHINDIRITBL  Indicator 1.2. Establishment of slum inventory database/profiling (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Done & Value No yes updated updated Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments Annual updating of the slum database is nearly completed, and currently under validation review before it is used to calculate outcomes indicators. The updated profile is expected to be available on the project website by April 2018. (Source: NMC of NSUP, data updated and submitted through online application). PHINDIRITBL  Percentage of local governments that have completed Slum Improvement Action Plans (SIAPs) which have been approved by Bupati/Walikota (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 56.21 56.21 90.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments The target for December 2018 is 60%. The status is still the same as the previous ISR sequence because [JSN1] the Bank has been focusing assistance to 45 select cities to improve the quality of the SIAPs, including area development plans and a 5-year investment list as requested before moving ahead to remaining cities. (source: NMC monitoring data) PHINDIRITBL  Indicator 2.2. Percentage of kelurahans which have Community Settlement Plans (CSPs) that have been consolidated with SIAPs (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 58.59 23.00 90.00 Date 01-Apr-2016 30-Sep-2017 05-Mar-2018 31-Dec-2021 Comments The target by December 2018 is set for 70%. The current status is very low due to difficulties in synchronizing CSPs with existing regulations and cities plans (some of which are not always available), incorporating relevant safeguard mitigation measures as well as the low number of urban planners (source: NMC monitoring data) 4/4/2018 Page 7 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) PHINDIRITBL  Indicator 3.1. Number of cities which have completed 80% of primary and secondary infrastructure works and services connected to slum areas (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments Expected target by December 2018 was set for 20 cities. No construction is expected until March 2018. A review of Detailed Engineering Design for primary and secondary infrastructure is still underway in 2 cities. It is expected that the number will increase by end of June 2018. PHINDIRITBL  Indicator 3.2. Number of kelurahans that have completed 90% of tertiary infrastructure and services implemented in slum areas (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 701.00 2,500.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments The target for December 2017 is set for 1400 kelurahans, and for December 2018, 1,600 kelurahans. PMU has disbursed the investment in 706 kelurahans, across 143 cities. Until now, 701 have completed the construction. 4/4/2018 Page 8 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) PHINDIRITBL  Indicator 3.3. Percentage of good quality of infrastructure and services (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 97.70 90.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments From 6,217 subprojects completed, 97.7% are reported to have good quality of infrastructure, based on indicators that are set by the NMC. (Source: NMC monitoring data) PHINDIRITBL  Indicator 3.4. Percentage of infrastructure built that is fully functioning (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments NMC will develop the indicators of functionality for monitoring. No target is set for 2018. PHINDIRITBL  Indicator 4.1. Percentage of local governments that have project monitoring structure and provide regular information on project implementation (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 01-Apr-2016 30-Sep-2017 07-Mar-2018 31-Dec-2021 Comments MIS development is still underway and experiencing delays and expected to be running by end of March 2018. The MIS will be used by the Local Governments to monitor implementation progress and update information. 4/4/2018 Page 9 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) PHINDIRITBL  Indicator 4.2. Percentage of kelurahans with completed annual financial audits (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 84.19 98.70 90.00 Date 01-Apr-2016 30-Sep-2017 14-Feb-2018 31-Dec-2021 Comments Not all kelurahans received grants for 2016-2017. Thus, financial audits were only done by those who received the grants. From 6,143 kelurahans that received the grants, 6,066 (98.7%) kelurahans have completed annual financial audits. Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P154782 IBRD-86360 Effective USD 216.50 216.50 0.00 45.20 171.30 21% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P154782 IBRD-86360 Effective 12-Jul-2016 22-Aug-2016 11-Oct-2016 31-Mar-2022 31-Mar-2022 Cumulative Disbursements 4/4/2018 Page 10 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Indonesia National Slum Upgrading Project (P154782) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 4/4/2018 Page 11 of 11 Public Disclosure Copy