Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: December16, 2016; V8: Sept. 1, 2020] 2. Date of General Procurement Notice: Jan 24, 2017 3. Period covered by this procurement plan: 2020-2022 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 10million All 2. NCB (Goods) Above US$ 2million All 3. ICB (Works) Above US$ 40 million All 4. NCB (Works) Above US$ 10 million All 5. (Non-Consultant Services) Above US$ 2million All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Yes, in procurement manual] 4. Reference to (if any) Project Operational/Procurement Manual: Yes 5. Any Other Special Procurement Arrangements: no 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descriptio Estimated Package Domesti Review Comments No. n Cost s c by Bank US$ million Preferen (Prior / ce Post) (yes/no) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary 4.6093 34 No Post of the Shopping (Works) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 1 million 2. Single Source (Firms) Above US$ 1 million 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: No 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ million (Prior / Post) Summary of number of contracts that will be let under QCBS Summary of number of contracts that will be let under other methods PROCUREMENT China : Shaanxi Poor Rural Areas Community Development Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2017-03-20 2021-04-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153541 GPN Date: 2017-01-24 Project Name: Shaanxi Poor Rural Areas Community Development Project Loan / Credit No: IBRD / 86840 Executing Agency(ies):Shaanxi Poor Rural PMO WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component B: Economic W/YA/YCH/2017/01 / Road Request for Single Stage - One 2017-04- 2017-06- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 57,300.00 55,582.83 Completed construction Quotations Envelope 06 01 04 01 Support Component B: Economic W/YA/Y/G/2017/01 / Apple Single Stage - One 2017-06- 2017-06- 2017-07- 2017-08- 2017-09- 2018-03- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 828,000.00 0.00 Canceled cold storage civil (4000 tons) Envelope 01 06 18 17 21 20 Support W/YU/D/Y/2017/02 / Component B: Economic Single Stage - One 2017-07- 2017-09- 2018-03- Peasant household sheep IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 251,500.00 0.00 Canceled Envelope 25 19 18 shed Support W/YU/D/Y/2018/01 / Component B: Economic Request for Single Stage - One 2018-02- 2018-04- 2018-09- Peasant household sheep IBRD / 86840 Infrastructure and Services Post Open - National 205,800.00 0.00 Canceled Quotations Envelope 06 03 30 shed Support Component B: Economic W/W/B/J/2018/02 / Hail Single Stage - One 2018-01- 2018-03- 2018-08- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 257,100.00 0.00 Canceled net 225 mu Envelope 06 03 30 Support W/YU/D/Y/2018/02 / Component B: Economic Single Stage - One 2018-02- 2018-02- 2018-03- 2018-04- 2018-05- 2018-11- Peasant household sheep IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 425,300.00 0.00 Canceled Envelope 01 06 20 19 24 20 shed Support W/YU/D/Y/2018/03 / Component B: Economic Request for Single Stage - One 2018-02- 2018-04- 2018-09- Peasant household sheep IBRD / 86840 Infrastructure and Services Post Open - National 214,900.00 0.00 Canceled Quotations Envelope 06 03 30 shed Support Component B: Economic W/W/B/F/2018/01 / Hail Single Stage - One 2018-03- 2018-05- 2018-10- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 314,300.00 0.00 Canceled net 258 mu Envelope 06 01 28 Support W/B/LX/QQ/2017/02 / Component B: Economic Single Stage - One 2017-09- 2017-09- 2017-10- 2017-11- 2017-12- 2018-06- Pepper seedling greenhouse IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 780,200.00 0.00 Canceled Envelope 01 06 18 17 22 20 6 Support Component B: Economic W/W/H/2017/06 / Village Request for Single Stage - One 2017-06- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 61,700.00 0.00 Canceled road 0.85km Quotations Envelope 30 25 21 Support Component B: Economic W/YU/M/2017/07 / Road Request for Single Stage - One 2017-06- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 152,400.00 0.00 Canceled construction Quotations Envelope 06 01 01 Support Component B: Economic W/YU/M/2017/06 / Road Request for Single Stage - One 2017-06- 2017-08- 2018-01- IBRD / 86840 Infrastructure and Services Post Open - National 48,800.00 0.00 Canceled construction Quotations Envelope 06 01 28 Support Component B: Economic W/YA/YC/2017/08 / Road Request for Single Stage - One 2017-06- 2017-08- 2018-01- IBRD / 86840 Infrastructure and Services Post Open - National 207,800.00 0.00 Canceled hardening 2.9km Quotations Envelope 06 01 28 Support W/YA/YC/2017/03 / Yanchuan county. Component B: Economic Request for Single Stage - One 2018-07- 2018-09- 2019-03- Constructed 5 bridges IBRD / 86840 Infrastructure and Services Post Open - National 243,900.00 0.00 Canceled Quotations Envelope 15 09 08 cemented with M10 masonry Support and the wall is based on M12.5 fine stone materials. W/YA/YC/2017/04 / Yanchuan county. Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-01- Constructed 3 bridges IBRD / 86840 Infrastructure and Services Prior Open - National 146,300.00 0.00 Canceled Quotations Envelope 06 01 28 cemented with M10 masonry Support and the wall is based on M12.5 fine stone materials. W/YA/YC/2017/01 / Component B: Economic Yanchuan county. Gaojiageta Request for Single Stage - One 2018-07- 2018-08- 2018-11- IBRD / 86840 Infrastructure and Services Post Open - National 87,800.00 0.00 Canceled village, road hardening Quotations Envelope 25 29 29 Support 0.875km W/YA/YC/2017/02 / Component B: Economic Yanchuan county. Production Request for Single Stage - One 2018-08- 2018-09- 2019-03- IBRD / 86840 Infrastructure and Services Post Open - National 208,900.00 0.00 Canceled road 4.95km resurfacing Quotations Envelope 04 09 08 Support with sand. W/YA/YC/2017/05 / Component B: Economic Yanchuan county. 300 sets Request for Single Stage - One 2018-08- 2018-09- 2019-03- IBRD / 86840 Infrastructure and Services Post Open - National 237,800.00 0.00 Canceled of soft rainwater cellars. Quotations Envelope 04 29 28 Support Diameter: 3m and depth: 3m. W/YA/YC/2017/06 / Yanchuan county. Road Component B: Economic Request for Single Stage - One 2018-08- 2018-09- 2019-03- hardening 2.032km. Shiyao IBRD / 86840 Infrastructure and Services Post Open - National 157,700.00 0.00 Canceled Quotations Envelope 04 29 28 village 1.282km and Support Fanjiachuan village 0.75km W/YA/Y/2017/03 / Component B: Economic Yanchang County, rainwater Request for Single Stage - One 2017-06- 2017-08- 2018-01- IBRD / 86840 Infrastructure and Services Post Open - National 27,000.00 0.00 Canceled cellar construction in the Quotations Envelope 06 01 28 Support Farming Orchard, Leichi Town. W/YA/Y/2017/04 / Yanchang county: road construction in 5 Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-01- communities including IBRD / 86840 Infrastructure and Services Post Open - National 27,800.00 0.00 Canceled Quotations Envelope 06 01 28 Jing'gou, Xinglie, Jiechu, Support Zhongliang and Houlie of Leiduo village in Leichi township. W/YA/Y/2017/05 / Yangchang county, 3.448km road construction of Component B: Economic Niangeda and Caiziliang Request for Single Stage - One 2017-06- 2017-08- 2018-01- IBRD / 86840 Infrastructure and Services Post Open - National 18,800.00 0.00 Canceled communities of Xiadaya Quotations Envelope 06 01 28 Support village in Leichi township, and 0.285km road resurfacing and construction of Shiganliang community W/YA/Y/2017/06 / Yanchang county, 1.15km Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-01- road construction of IBRD / 86840 Infrastructure and Services Post Open - National 33,000.00 0.00 Canceled Quotations Envelope 06 01 28 Zhangtao and Shentou Support communities in Leichi township. W/YA/Y/2017/07 / Component B: Economic Request for Single Stage - One 2018-07- 2017-08- 2018-09- 2017-09- 2019-03- Yanchang county, 1.75km IBRD / 86840 Infrastructure and Services Post Limited 18,400.00 17,316.28 Completed Quotations Envelope 16 07 10 11 09 productive road for Leichi Support township. W/YA/Y/2017/02 / Component B: Economic Residential road hardening Request for Single Stage - One 2017-06- 2017-08- 2018-01- IBRD / 86840 Infrastructure and Services Post Open - National 152,500.00 0.00 Canceled from Leichi township to Quotations Envelope 06 01 28 Support Wapenyaozi village. W/W/F/2017/01 / Fuping County, asphalt road Component B: Economic Pending Single Stage - One 2017-04- 2017-04- 2017-05- 2017-06- 2017-07- 2018-01- construction with 3.3 IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 820,100.00 0.00 Implementa Envelope 01 06 18 17 22 22 kilometers in width and 6 Support tion meters in length W/W/F/2017/02 / Fuping county, 5.47km road Component B: Economic Pending Single Stage - One 2018-04- 2018-04- 2018-06- 2018-07- 2018-08- 2019-03- construction in which 3.5m IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 391,900.00 0.00 Implementa Envelope 19 24 05 05 09 31 width of road for out use Support tion and 3m width for residence use. W/W/F/2017/03 / Fuping Component B: Economic county, 11.1km length and Single Stage - One 2018-04- 2018-04- 2018-05- 2018-06- 2018-07- 2018-12- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 163,300.00 0.00 Canceled 3m width of road Envelope 01 06 18 17 22 31 Support construction. Page 1 W/W/F/D/2017/01 / Fuping county, construction of peeling factories of 1,000 square meters, cold storage Component B: Economic Pending building of 500 tons and Single Stage - One 2018-04- 2018-04- 2018-06- 2018-07- 2018-08- 2019-02- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 474,800.00 0.00 Implementa 500 square meters, peeling Envelope 19 24 05 05 09 28 Support tion factories of 2400 square meters , drying rooms of 400 square meters and 1500 square meters. W/W/B/2017/03 / Baishui county, 3.2km residential Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-01- road construction in Zhaoyao IBRD / 86840 Infrastructure and Services Post Open - National 204,900.00 0.00 Canceled Quotations Envelope 06 01 28 community in Lingao project Support area. W/W/B/2017/04 / Baishui county. One cement concrete road from Xiguojiashan Component B: Economic village to Xiyou village Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 247,600.00 0.00 Canceled 1.8km, another road from Quotations Envelope 06 31 27 Support Guojiashan village to Dongsunjiashan village 1.1km, together is 2.9km. W/W/B/2018/12 / Baishui Component B: Economic Pending Request for Single Stage - One 2018-07- 2018-09- 2019-03- county. 2.2km road IBRD / 86840 Infrastructure and Services Post Limited 167,700.00 0.00 Implementa Quotations Envelope 17 11 10 hardening for Lingao Support tion community. W/W/B/2018/14 / Baishui Component B: Economic Pending Request for Single Stage - One 2018-07- 2018-09- 2019-03- village. 1.27km road IBRD / 86840 Infrastructure and Services Post Limited 96,800.00 0.00 Implementa Quotations Envelope 17 11 10 hardening for Gaoxi village. Support tion W/W/B/2018/15 / Baishui Component B: Economic Pending Request for Single Stage - One 2018-07- 2018-09- 2019-03- county. 3.38km productive IBRD / 86840 Infrastructure and Services Post Limited 51,500.00 0.00 Implementa Quotations Envelope 17 11 10 road for Wuyao village. Support tion W/W/B/2018/17 / Baishui Component B: Economic Request for Single Stage - One 2018-07- 2018-09- 2019-03- county. 0.9km productive IBRD / 86840 Infrastructure and Services Post Limited 13,700.00 0.00 Canceled Quotations Envelope 17 11 10 road for Gaoxi village. Support W/W/B/2018/18 / Baishui county. Repair 1 well for Component B: Economic Pujun village and drill 3 well Request for Single Stage - One 2018-07- 2018-06- 2018-09- 2018-07- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 159,300.00 163,502.49 Completed for the following palces: Quotations Envelope 17 25 11 28 10 Support Lingao community, Wuyao village and Taowa village, 1 for each. W/W/B/2018/19 / Baishui county, 200 square meters Component B: Economic Request for Single Stage - One 2018-07- 2018-06- 2018-09- 2018-07- 2019-03- biological fermented IBRD / 86840 Infrastructure and Services Post Limited 18,300.00 21,370.72 Completed Quotations Envelope 17 25 11 26 10 fertilizer pits construction in Support Lingao project area. W/B/LX/2017/01 / Long county, construction of 4 wells in which 2 well constructed in Liujiazu Component B: Economic community, 1 well Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 88,300.00 0.00 Canceled constructed in Hujiazhuang Quotations Envelope 06 31 27 Support community and 1 well construction on Shangliang community with 150 meters depth respectively. W/B/LX/2017/02 / Long county, new construction of 8.123 km diversion canal, in which 3.523 km in the crossing of Liangfuhe Component B: Economic Request for Single Stage - One 2017-08- 2017-08- 2018-02- community in Shangliang IBRD / 86840 Infrastructure and Services Post Open - National 195,700.00 0.00 Canceled Quotations Envelope 01 22 18 village and Xialiang village, Support 1.1 km in Liujiazui village, and 3.5 km between tanyuanpo community in Liujiazui and railway. W/B/LX/2017/03 / Long county, construction of 3 bridges, in which 1 bridge between Hujiazhuang community and Liujiazui Component B: Economic Request for Single Stage - One 2017-09- 2017-11- 2018-04- community, 1 bridge in IBRD / 86840 Infrastructure and Services Post Open - National 54,900.00 0.00 Canceled Quotations Envelope 06 01 30 Yinqigou community in Support Sanjiaodian village, and 1 bridge in Duimianqiao community in Sanjiaodian village. W/YU/D/2017/03 / Dingbian county, construction of 1 300 meters- Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-04- deep water well for farming IBRD / 86840 Infrastructure and Services Post Open - National 45,700.00 0.00 Canceled Quotations Envelope 06 01 01 use (equipped with pump, Support high- and low voltage wire, transformer, water collection pool). W/YU/D/2017/01 / Dingbian county, 7 km Component B: Economic Pending residential concrete road Single Stage - One 2018-07- 2018-07- 2018-09- 2018-10- 2018-11- 2019-05- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 747,000.00 0.00 Implementa construction Road Envelope 24 29 09 09 13 16 Support tion construction from Shangendi village to No. 303 provincial road of Shaanxi. W/YU/D/2017/02 / Dingbian county, 5.4 km residential road from Xiaoqu community to Tuwozi community, which is divided Component B: Economic Pending Single Stage - One 2018-04- 2018-04- 2018-04- 2018-05- 2018-05- 2018-12- into 2 parts: the first part is IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 576,200.00 0.00 Implementa Envelope 19 24 29 04 30 28 1.9 km from Xiaoqu Support tion community to a triple path, and the second part is 3.5 km from Liwazi community to Tuwozi community. W/YU/D/Y/2017/01 / Dingbian county. 5700 Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-01- square meter of peasant IBRD / 86840 Infrastructure and Services Post Open - National 191,200.00 0.00 Canceled Quotations Envelope 06 01 28 household sheep shed for Support Yangwan village. W/YU/D/2017/04 / Dingbian county, Component B: Economic construction of sheep Request for Single Stage - One 2017-06- 2017-08- 2018-04- IBRD / 86840 Infrastructure and Services Post Open - National 109,800.00 0.00 Canceled trading market covering Quotations Envelope 06 01 01 Support 5,000 square meters, brick floor, 0.5 meter high wall on which welded 1 meter iron column. W/YU/M/2018/01 / Mizhi Component B: Economic Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- county. 1.4km road IBRD / 86840 Infrastructure and Services Post Limited 42,700.00 37,663.39 Completed Quotations Envelope 18 23 12 21 11 hardening for Aijiawa village. Support W/YU/M/2018/03 / Mizhi Component B: Economic county. Middle part of Long Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 38,100.00 56,047.63 Completed town. Management of land Quotations Envelope 18 23 12 21 11 Support and terrace for 125 Mu. W/B/LY/2017/03 / Linyou Component B: Economic county, 2.2km road Request for Single Stage - One 2017-06- 2017-08- 2018-01- IBRD / 86840 Infrastructure and Services Post Open - National 76,200.00 0.00 Canceled hardening in the first, Quotations Envelope 06 01 28 Support second and fourth group of Sujia village. W/YU/M/2018/02 / Mizhi County, land management Component B: Economic Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- and terracing in the front IBRD / 86840 Infrastructure and Services Post Limited 165,500.00 171,339.93 Signed Quotations Envelope 18 23 12 21 11 part of Long Township, with Support a total dimension of 543 mu. W/B/LY/2017/04 / Linyou Component B: Economic county, 2.3km road Request for Single Stage - One 2017-08- 2017-10- 2018-03- IBRD / 86840 Infrastructure and Services Post Open - National 162,300.00 0.00 Canceled hardening in Aoli community Quotations Envelope 06 01 30 Support in Changfeng village. W/B/LY/2017/05 / Linyou Component B: Economic county, 3km road hardening Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 245,400.00 0.00 Canceled from Guanzhuang village to Quotations Envelope 06 31 27 Support Zhujiayuan community. W/YU/M/2018/05 / Mizhi county. Water tower for Component B: Economic Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- orchard irrigation. 10 high IBRD / 86840 Infrastructure and Services Post Limited 99,100.00 93,719.52 Completed Quotations Envelope 18 23 12 21 11 water tower and 1 low water Support tower. W/YU/M/2018/04 / Mizhi County, land management Component B: Economic Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- and terracing at the rear of IBRD / 86840 Infrastructure and Services Post Limited 131,700.00 56,047.63 Signed Quotations Envelope 18 23 12 21 11 Long Town, with a total Support dimension of 432 mu. Page 2 W/B/LY/2017/06 / Linyou Component B: Economic county, 1.7km road Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 170,000.00 0.00 Canceled hardening from Shenjia Quotations Envelope 06 31 27 Support community to Xizhuang community. W/B/LY/2017/01 / Linyou county, 3.75km road Component B: Economic Single Stage - One 2017-04- 2018-07- 2017-04- 2017-05- 2018-08- 2017-06- 2018-08- 2017-07- 2018-09- 2018-02- hardening from Changfeng IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 387,500.00 402,955.92 Signed Envelope 01 13 06 18 15 17 28 22 01 21 township to Shenjia Support community. W/YU/M/2018/06 / Mizhi Component B: Economic Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- county. 10 well house for IBRD / 86840 Infrastructure and Services Post Limited 15,200.00 13,358.13 Completed Quotations Envelope 18 22 12 21 11 orchard irrigation. Support W/B/LY/2017/02 / Linyou Component B: Economic county, 4.9km road Single Stage - One 2017-05- 2018-05- 2017-05- 2017-06- 2018-06- 2017-07- 2018-06- 2017-08- 2018-07- 2018-03- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 451,900.00 452,335.87 Signed hardening from Changfeng Envelope 01 28 06 17 28 17 28 21 23 21 Support township to Wushen village. W/YU/M/2018/07 / Mizhi county. Water tower for Component B: Economic Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- orchard irrigation and IBRD / 86840 Infrastructure and Services Post Limited 218,800.00 139,324.08 Signed Quotations Envelope 18 22 12 21 11 ancillary facility engineering Support with a total number of 10. W/YU/M/2017/13 / Mizhi County, Irrigation pipeline Component A: Farmer Request for Single Stage - One 2017-06- 2017-08- 2018-08- construction in the orchard IBRD / 86840 Cooperative and Value Post Open - National 134,100.00 0.00 Canceled Quotations Envelope 06 01 01 garden with a total Chain Development. dimension of 550 mu. W/YU/M/2018/08 / Mizhi Component A: Farmer county. Pipeline for orchard Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- IBRD / 86840 Cooperative and Value Post Limited 134,100.00 125,734.94 Completed irrigation. The depth is 1m, Quotations Envelope 18 22 12 21 11 Chain Development. and the material is PE. W/YU/M/2017/14 / Mizhi County, irrigation and outlet Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-08- pile construction in the IBRD / 86840 Infrastructure and Services Post Open - National 88,900.00 0.00 Canceled Quotations Envelope 06 01 01 orchard garden with 1000 Support water piles. W/B/LY/2017/07 / Linyou county, 5.775km road Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-01- resurfaced with sand in the IBRD / 86840 Infrastructure and Services Post Open - National 88,000.00 0.00 Canceled Quotations Envelope 06 01 28 farmland of in Changfeng Support village and Changle village. W/B/LY/2017/08 / Linyou county, construction of Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-01- 4.5km water pipelines from IBRD / 86840 Infrastructure and Services Post Open - National 27,600.00 0.00 Canceled Quotations Envelope 06 01 28 the water factory in Support Changfeng village to Changle village. W/W/H/2017/01 / Heyang Component B: Economic Request for Single Stage - One 2017-07- 2017-09- 2018-03- County, 2 wells in Xiyang IBRD / 86840 Infrastructure and Services Post Open - National 233,300.00 0.00 Canceled Quotations Envelope 25 19 18 and Diantou Village. Support W/W/H/2017/03 / Heyang Component B: Economic County, 2 wells in Xiao Request for Single Stage - One 2017-06- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 233,300.00 0.00 Canceled Community and Meng Quotations Envelope 30 25 21 Support Community. W/W/H/2017/02 / Heyang Component B: Economic county. 1 well for Xiangong Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 233,300.00 0.00 Canceled village and another well for Quotations Envelope 05 30 26 Support Chengcun village. W/W/H/2017/07 / Heyang Component B: Economic County, production of 5 Request for Single Stage - One 2017-06- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 89,200.00 0.00 Canceled roads with a total length of Quotations Envelope 30 25 21 Support 6060 meters in Diantou Village. W/W/H/2017/08 / Heyang Component B: Economic county, 2.57km road Request for Single Stage - One 2017-06- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 38,000.00 0.00 Canceled construction in Xiaocun Quotations Envelope 30 25 21 Support community. W/W/H/2017/09 / Heyang Component B: Economic Request for Single Stage - One 2017-06- 2017-08- 2018-02- county, 4.97km in Xiangong IBRD / 86840 Infrastructure and Services Post Open - National 73,500.00 0.00 Canceled Quotations Envelope 30 25 21 village. Support W/X/C/2017/01 / Changwu county. Road hardening. The Component B: Economic Single Stage - One 2017-05- 2017-05- 2017-06- 2017-07- 2017-08- 2018-06- total length is 5298m: IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 80,800.00 0.00 Canceled Envelope 01 06 17 17 21 21 3919m for Santai village and Support 1379m for Fanluo village. W/X/C/2017/02 / Changwu county. Road hardening . Component B: Economic Single Stage - One 2017-05- 2017-05- 2017-06- 2017-07- 2017-08- 2018-02- The total length is 2562m: IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 195,300.00 0.00 Canceled Envelope 01 06 17 17 21 21 2111m for Santai village and Support 451m for Fanluo village. W/X/C/2017/03 / Changwu county. Associated drainage Component B: Economic channel of hardening road Request for Single Stage - One 2017-06- 2017-08- 2018-08- IBRD / 86840 Infrastructure and Services Post Open - National 70,100.00 0.00 Canceled for Santai village and Fanluo Quotations Envelope 06 01 01 Support village, the total length is 3678m. W/W/H/2017/05 / Heyang Component B: Economic Pending Single Stage - One 2019-01- 2019-01- 2019-02- 2019-03- 2019-04- 2019-10- county. 5.8km village road IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 457,100.00 0.00 Implementa Envelope 01 06 17 19 23 20 for Xiaocun community. Support tion W/W/H/2017/04 / Heyang Component B: Economic Under county, 6.7km road Single Stage - One 2019-01- 2018-09- 2019-01- 2019-02- 2019-03- 2019-04- 2019-10- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 528,400.00 0.00 Implementa construction in Diantou Envelope 01 17 06 17 19 23 20 Support tion village. W/X/C/L/2017/01 / Changwu county. Controlling office area of 5650sqm, Cold storage refrigeration to build 2000t, fence engineering Component B: Economic Under Single Stage - One 2019-01- 2019-03- 2019-01- 2019-02- 2019-03- 2019-04- 2019-10- 315m, refrigeration room IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 734,200.00 0.00 Implementa Envelope 01 04 06 17 19 23 20 door and controlling area, Support tion equipment room 400sqm, housing construction 300sqm, workshop 300sqm and 2 bathroom. W/W/F/2017/03A / Fuping Component B: Economic county, 11.1km length and Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 163,300.00 237,695.04 Signed 3m width of road Quotations Envelope 07 10 02 26 31 Support construction. W/X/C/2017/01A / Changwu county. Road Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- hardening. The total length IBRD / 86840 Infrastructure and Services Post Limited 80,800.00 0.00 Implementa Quotations Envelope 07 02 31 is 5298m: 3919m for Santai Support tion village and 1379m for Fanluo village. W/X/C/2017/02A / Changwu county. Road Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-03- hardening . The total length IBRD / 86840 Infrastructure and Services Post Limited 195,300.00 188,909.89 Signed Quotations Envelope 07 02 02 07 31 is 2562m: 2111m for Santai Support village and 451m for Fanluo village. Component B: Economic Pending W/YA/YCH/2017/06A / Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 35,800.00 0.00 Implementa Road hardening Quotations Envelope 07 02 31 Support tion W/YA/YCH/2017/15A / The Component B: Economic total length of production Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 55,900.00 45,644.98 Completed gravel road of Shuangquan Quotations Envelope 07 25 02 19 31 Support Villege in Macha is 3.9km W/B/LY/2017/03A / Linyou Component B: Economic county, 2.2km road Request for Single Stage - One 2018-08- 2017-12- 2018-10- 2018-03- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 76,200.00 59,292.77 Completed hardening in the first, Quotations Envelope 07 20 02 05 31 Support second and fourth group of Sujia village. W/YA/YCH/2017/14A / 1 hallucinogenic water stone Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- bridge and the total length IBRD / 86840 Infrastructure and Services Post Limited 38,400.00 0.00 Implementa Quotations Envelope 07 02 31 of hardening road of Support tion Shimengou is 0.2 km W/YU/D/2017/04A / Dingbian county, construction of sheep Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- trading market covering IBRD / 86840 Infrastructure and Services Post Limited 109,800.00 0.00 Implementa Quotations Envelope 07 02 31 5,000 square meters, brick Support tion floor, 0.5 meter high wall on which welded 1 meter iron column. Page 3 W/B/LX/QQ/2017/02A / Component B: Economic Pending Single Stage - One 2018-08- 2018-08- 2018-09- 2018-10- 2018-11- 2019-05- Pepper seedling greenhouse IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 780,200.00 0.00 Implementa Envelope 02 07 18 18 22 21 6 Support tion Component B: Economic W/W/B/2018/11A / Village Request for Single Stage - One 2018-08- 2018-06- 2018-10- 2018-07- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 192,000.00 50,423.54 Completed road 2.68km Quotations Envelope 07 25 02 26 31 Support Component B: Economic W/YA/YCH/2017/09A / Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 70,311.80 Completed Road hardening Quotations Envelope 07 25 02 20 31 Support Component B: Economic W/YU/M/2017/01A / Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-11- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 170,700.00 209,790.64 Completed Hardened Road Quotations Envelope 07 30 02 15 31 Support Component B: Economic Under W/W/B/2017/01A / Village Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 107,500.00 0.00 Implementa road 1.5km Quotations Envelope 07 23 02 31 Support tion Component B: Economic W/W/B/2017/07A / Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 77,200.00 80,666.96 Completed Production of road 5.25km Quotations Envelope 07 23 02 25 31 Support W/YA/YCH/2017/31A / Component B: Economic Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- Construction of revetment: IBRD / 86840 Infrastructure and Services Post Limited 47,100.00 44,681.05 Completed Quotations Envelope 07 06 02 10 31 800 m3 Support Component B: Economic Pending W/W/B/2018/10A / Village Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 70,900.00 0.00 Implementa road 0.99km Quotations Envelope 07 02 31 Support tion W/B/LY/2017/07A / Linyou county, 5.775km road Component B: Economic Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-03- resurfaced with sand in the IBRD / 86840 Infrastructure and Services Post Limited 88,000.00 70,186.90 Signed Quotations Envelope 07 09 02 09 31 farmland of in Changfeng Support village and Changle village. W/YA/Y/2017/06A / Yanchang county, 1.15km Component B: Economic Request for Single Stage - One 2018-08- 2017-08- 2018-10- 2017-09- 2019-03- road construction of IBRD / 86840 Infrastructure and Services Post Limited 33,000.00 31,133.30 Completed Quotations Envelope 07 07 02 11 31 Zhangtao and Shentou Support communities in Leichi township. W/YU/D/2017/03A / Dingbian county, construction of 1 300 meters- Component B: Economic Request for Single Stage - One 2018-08- 2018-10- 2018-10- 2018-10- 2019-03- deep water well for farming IBRD / 86840 Infrastructure and Services Post Limited 45,700.00 41,366.16 Completed Quotations Envelope 07 22 02 30 31 use (equipped with pump, Support high- and low voltage wire, transformer, water collection pool). W/YU/M/2017/13A / Mizhi County, Irrigation pipeline Component A: Farmer Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-06- 2019-03- construction in the orchard IBRD / 86840 Cooperative and Value Post Limited 134,100.00 125,648.03 Completed Quotations Envelope 07 22 02 21 31 garden with a total Chain Development. dimension of 550 mu. Component B: Economic W/YA/YCH/2017/03A / Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-06- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 77,328.58 Completed Road hardening Quotations Envelope 07 28 02 20 31 Support Component B: Economic Under W/W/B/2018/02A / Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 93,900.00 0.00 Implementa Production of road 6.38km Quotations Envelope 07 04 02 31 Support tion Component B: Economic Pending W/W/B/2018/04A / Village Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 186,300.00 0.00 Implementa road 3.2km Quotations Envelope 07 02 31 Support tion W/YA/Y/2017/03A / Component B: Economic Pending Yanchang County, rainwater Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 27,000.00 0.00 Implementa cellar construction in the Quotations Envelope 07 02 31 Support tion Farming Orchard, Leichi Town. W/YA/YC/2017/01A / Component B: Economic Yanchuan county. Gaojiageta Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-07- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 87,800.00 78,445.11 Completed village, road hardening Quotations Envelope 07 28 02 28 31 Support 0.875km Component B: Economic Pending W/W/B/2018/03A / Water Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 197,700.00 0.00 Implementa diversion canal 12 km Quotations Envelope 07 02 31 Support tion Component B: Economic Pending W/YA/YC/2017/07A / Road Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 31,800.00 0.00 Implementa hardening 2.9 km Quotations Envelope 07 02 31 Support tion W/YA/YCH/2017/19A / The Component B: Economic Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- total length of IBRD / 86840 Infrastructure and Services Post Limited 57,300.00 57,899.22 Completed Quotations Envelope 07 25 02 19 31 hardening0.81.0 km Support W/B/LY/2017/04A / Linyou Component B: Economic county, 2.3km road Request for Single Stage - One 2018-08- 2017-12- 2018-10- 2018-03- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 162,300.00 130,351.36 Completed hardening in Aoli community Quotations Envelope 07 20 02 05 31 Support in Changfeng village. W/W/H/2017/08A / Heyang Component B: Economic county, 2.57km road Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 38,000.00 30,407.37 Signed construction in Xiaocun Quotations Envelope 07 31 02 10 31 Support community. Component B: Economic Under W/W/B/2018/01A / Road Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 91,500.00 0.00 Implementa 1.2km Quotations Envelope 07 04 02 31 Support tion W/YA/YCH/2017/23A / The Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- total length of hardening IBRD / 86840 Infrastructure and Services Post Limited 21,500.00 0.00 Implementa Quotations Envelope 07 02 31 road of Machagou is 0.3 km Support tion W/YA/YC/2017/06A / Yanchuan county. Road Component B: Economic Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-07- 2019-03- hardening 2.032km. Shiyao IBRD / 86840 Infrastructure and Services Post Limited 157,700.00 146,301.25 Completed Quotations Envelope 07 28 02 29 31 village 1.282km and Support Fanjiachuan village 0.75km W/W/H/2017/02A / Heyang Component B: Economic county. 1 well for Xiangong Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 233,300.00 228,869.39 Signed village and another well for Quotations Envelope 07 24 02 15 31 Support Chengcun village. W/B/LY/2017/08A / Linyou county, construction of Component B: Economic Request for Single Stage - One 2018-08- 2018-11- 2018-10- 2018-12- 2019-03- 4.5km water pipelines from IBRD / 86840 Infrastructure and Services Post Limited 27,600.00 24,575.78 Completed Quotations Envelope 07 14 02 06 31 the water factory in Support Changfeng village to Changle village. W/W/H/2017/09A / Heyang Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-10- 2019-03- county, 4.97km in Xiangong IBRD / 86840 Infrastructure and Services Post Limited 73,500.00 75,506.50 Signed Quotations Envelope 07 31 02 10 31 village. Support W/X/C/2017/03A / Changwu county. Associated Component B: Economic Pending drainage channel of Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 70,100.00 0.00 Implementa hardening road for Santai Quotations Envelope 07 02 31 Support tion village and Fanluo village, the total length is 3678m. W/B/LX/2017/03A / Long county, construction of 3 bridges, in which 1 bridge between Hujiazhuang community and Liujiazui Component B: Economic Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-03- community, 1 bridge in IBRD / 86840 Infrastructure and Services Post Limited 54,900.00 79,080.34 Signed Quotations Envelope 07 06 02 20 31 Yinqigou community in Support Sanjiaodian village, and 1 bridge in Duimianqiao community in Sanjiaodian village. W/YA/YCH/2017/17A / 2 Component B: Economic Request for Single Stage - One 2018-08- 2018-06- 2018-10- 2018-07- 2019-03- hallucinogenic water stone IBRD / 86840 Infrastructure and Services Post Limited 48,200.00 54,253.42 Completed Quotations Envelope 07 18 02 12 31 bridges in Machagou Support W/YA/Y/2017/05A / Yanchang county, 3.448km road construction of Component B: Economic Niangeda and Caiziliang Request for Single Stage - One 2018-08- 2017-08- 2018-10- 2017-09- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 18,800.00 17,704.84 Completed communities of Xiadaya Quotations Envelope 07 07 02 11 31 Support village in Leichi township, and 0.285km road resurfacing and construction of Shiganliang community Page 4 W/W/H/2017/01A / Heyang Component B: Economic Request for Single Stage - One 2018-08- 2018-06- 2018-10- 2018-07- 2019-03- County, 2 wells in Xiyang IBRD / 86840 Infrastructure and Services Post Limited 233,300.00 221,564.15 Signed Quotations Envelope 07 27 02 21 31 and Diantou Village. Support Component B: Economic Pending W/W/B/2018/08A / Village Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 53,400.00 0.00 Implementa road 3.5km Quotations Envelope 07 02 31 Support tion W/YA/YCH/2017/18A / Component B: Economic Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-06- 2019-03- total length of hardening IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 107,512.53 Completed Quotations Envelope 07 28 02 20 31 road of Machagou is 1.0 km Support Component B: Economic W/YA/YCH/2017/07A / Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 63,000.00 41,451.19 Completed Gravel road construction Quotations Envelope 07 06 02 10 31 Support Component B: Economic Pending W/W/B/2018/05A / Village Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 119,700.00 0.00 Implementa road 1.57km Quotations Envelope 07 02 31 Support tion W/YA/YCH/2017/13A / The Component B: Economic total length of production Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-06- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 43,000.00 98,598.60 Completed gravel road of Shimengou is Quotations Envelope 07 29 02 21 31 Support 3.0 km Component B: Economic Pending W/W/B/2018/06A / Road Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 51,800.00 0.00 Implementa 0.68 Km Quotations Envelope 07 02 31 Support tion W/YA/YCH/2017/25A / The Component B: Economic Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- total length of hardening IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 46,661.44 Completed Quotations Envelope 07 25 02 19 31 road of Machagou is 1.0 km Support W/YA/YCH/2017/26A / The Component B: Economic total length of hardening Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 35,800.00 43,089.30 Completed road of Xinzhaigou Villege Quotations Envelope 07 07 02 10 31 Support is 0.5 km W/YA/YCH/2017/30A / The Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- total length of hardening IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 0.00 Implementa Quotations Envelope 07 02 31 road of Machagou is 1.0 km Support tion W/YA/YCH/2017/22A / 2 Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- hallucinogenic water stone IBRD / 86840 Infrastructure and Services Post Limited 48,200.00 0.00 Implementa Quotations Envelope 07 02 31 bridges in Shitaisi Support tion Component B: Economic Pending W/W/B/2018/09A / Village Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 53,400.00 0.00 Implementa road 3.5km Quotations Envelope 07 02 31 Support tion W/W/H/2017/03A / Heyang Component B: Economic County, 2 wells in Xiao Request for Single Stage - One 2018-08- 2018-06- 2018-10- 2018-07- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 233,300.00 217,076.38 Signed Community and Meng Quotations Envelope 07 27 02 21 31 Support Community. W/B/LY/2017/06A / Linyou Component B: Economic county, 1.7km road Request for Single Stage - One 2018-08- 2017-12- 2018-10- 2018-03- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 170,000.00 143,040.24 Signed hardening from Shenjia Quotations Envelope 07 20 02 05 31 Support community to Xizhuang community. W/YA/YCH/2017/10A / The Component B: Economic total length of production Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 44,182.06 Completed gravel road of Liuchagou is Quotations Envelope 07 06 02 09 31 Support 5.0 km W/YA/YCH/2017/24A / The Component B: Economic total length of hardening Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 38,700.00 40,739.23 Completed road of Xinzhaigou Villege Quotations Envelope 07 07 02 10 31 Support in Shike is 2.7 km W/YA/YCH/2017/20A / The Component B: Economic Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- total length of hardening IBRD / 86840 Infrastructure and Services Post Limited 43,000.00 49,809.56 Completed Quotations Envelope 07 25 02 19 31 road of Guanshang Villege Support is 0.6km W/YA/YCH/2017/28A / 2 Component B: Economic Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- hallucinogenic water stone IBRD / 86840 Infrastructure and Services Post Limited 48,200.00 46,812.92 Completed Quotations Envelope 07 08 02 10 31 bridge in Yadi Villeges Support W/B/LX/2017/01A / Long county, construction of 4 wells in which 2 well constructed in Liujiazu Component B: Economic community, 1 well Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-09- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 88,300.00 149,600.80 Signed constructed in Hujiazhuang Quotations Envelope 07 06 02 04 31 Support community and 1 well construction on Shangliang community with 150 meters depth respectively. W/YA/YC/2017/04A / Yanchuan county. Component B: Economic Request for Single Stage - One 2018-08- 2018-10- 2019-03- Constructed 3 bridges IBRD / 86840 Infrastructure and Services Prior Limited 146,300.00 0.00 Canceled Quotations Envelope 07 02 31 cemented with M10 masonry Support and the wall is based on M12.5 fine stone materials. W/B/LX/2017/02A / Long county, new construction of 8.123 km diversion canal, in which 3.523 km in the crossing of Liangfuhe Component B: Economic Request for Single Stage - One 2018-08- 2018-06- 2018-10- 2018-08- 2019-03- community in Shangliang IBRD / 86840 Infrastructure and Services Post Limited 195,700.00 143,637.93 Signed Quotations Envelope 07 19 02 06 31 village and Xialiang village, Support 1.1 km in Liujiazui village, and 3.5 km between tanyuanpo community in Liujiazui and railway. W/YU/D/Y/2017/01A / Dingbian county. 5700 Component B: Economic Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-11- 2019-03- square meter of peasant IBRD / 86840 Infrastructure and Services Post Limited 191,200.00 182,235.95 Completed Quotations Envelope 07 08 02 22 31 household sheep shed for Support Yangwan village. W/YA/YCH/2017/21A / The Component B: Economic Pending total length of production Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 73,100.00 0.00 Implementa gravel road road of Quotations Envelope 07 02 31 Support tion Machagou is 5.1 km W/YU/M/2017/14A / Mizhi County, irrigation and outlet Component B: Economic Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-06- 2019-03- pile construction in the IBRD / 86840 Infrastructure and Services Post Limited 88,900.00 25,417.62 Signed Quotations Envelope 07 22 02 21 31 orchard garden with 1000 Support water piles. W/W/B/2017/04A / Baishui county. One cement concrete road from Xiguojiashan Component B: Economic village to Xiyou village Request for Single Stage - One 2018-08- 2017-08- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 247,600.00 233,530.20 Completed 1.8km, another road from Quotations Envelope 07 04 02 08 31 Support Guojiashan village to Dongsunjiashan village 1.1km, together is 2.9km. W/YA/Y/2017/04A / Yanchang county: road construction in 5 Component B: Economic communities including Request for Single Stage - One 2018-08- 2017-08- 2018-10- 2017-09- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 27,800.00 26,228.81 Completed Jing'gou, Xinglie, Jiechu, Quotations Envelope 07 07 02 11 31 Support Zhongliang and Houlie of Leiduo village in Leichi township. W/YA/YCH/2017/16A / The Component B: Economic total length of production Request for Single Stage - One 2018-08- 2017-09- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 43,000.00 40,661.10 Completed gravel road of Nanwan Quotations Envelope 07 07 02 10 31 Support Village in Guanshang is 3.0 km W/YA/YC/2017/03A / Yanchuan county. Component B: Economic Request for Single Stage - One 2018-08- 2017-11- 2018-10- 2017-12- 2019-03- Constructed 5 bridges IBRD / 86840 Infrastructure and Services Post Limited 243,900.00 196,422.06 Signed Quotations Envelope 07 16 02 15 31 cemented with M10 masonry Support and the wall is based on M12.5 fine stone materials. W/YA/YC/2017/02A / Component B: Economic Yanchuan county. Production Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-08- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 208,900.00 139,365.60 Completed road 4.95km resurfacing Quotations Envelope 07 28 02 05 31 Support with sand. W/YA/YCH/2017/27A / The Component B: Economic Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-06- 2019-03- total length of hardening IBRD / 86840 Infrastructure and Services Post Limited 78,800.00 84,572.57 Completed Quotations Envelope 07 29 02 21 31 road of Machagou is 5.5 km Support W/B/LY/2017/05A / Linyou Component B: Economic county, 3km road hardening Request for Single Stage - One 2018-08- 2017-12- 2018-10- 2018-03- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 245,400.00 206,793.35 Signed from Guanzhuang village to Quotations Envelope 07 20 02 05 31 Support Zhujiayuan community. Page 5 W/YA/YCH/2017/29A / The Component B: Economic total length of production Request for Single Stage - One 2018-08- 2017-07- 2018-10- 2018-08- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 64,389.01 Completed gravel road of Yadi Village is Quotations Envelope 07 25 02 20 31 Support 1.0 km W/YA/YCH/2017/11A / 2 Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- hallucinogenic water stone IBRD / 86840 Infrastructure and Services Post Limited 48,200.00 0.00 Implementa Quotations Envelope 07 02 31 bridges in Liuchagou Support tion W/YA/YCH/2017/32A / Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- Construction of irrigation IBRD / 86840 Infrastructure and Services Post Limited 35,300.00 0.00 Implementa Quotations Envelope 07 02 31 canals:600m Support tion W/W/B/2017/03A / Baishui county, 3.2km residential Component B: Economic Request for Single Stage - One 2018-08- 2017-10- 2018-10- 2017-10- 2019-03- road construction in Zhaoyao IBRD / 86840 Infrastructure and Services Post Limited 204,900.00 185,525.62 Completed Quotations Envelope 07 18 02 26 31 community in Lingao project Support area. Component B: Economic Pending W/W/B/2018/07A / Village Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 45,700.00 0.00 Implementa road 3km Quotations Envelope 07 02 31 Support tion W/YA/Y/2017/02A / Component B: Economic Pending Residential road hardening Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 152,500.00 0.00 Implementa from Leichi township to Quotations Envelope 07 02 31 Support tion Wapenyaozi village. W/YA/YC/2017/05A / Component B: Economic Yanchuan county. 300 sets Request for Single Stage - One 2018-08- 2018-05- 2018-10- 2018-08- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 237,800.00 73,265.09 Completed of soft rainwater cellars. Quotations Envelope 07 28 02 25 31 Support Diameter: 3m and depth: 3m. W/W/H/2017/07A / Heyang Component B: Economic County, production of 5 Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 89,200.00 107,433.71 Signed roads with a total length of Quotations Envelope 07 31 02 10 31 Support 6060 meters in Diantou Village. Component B: Economic W/YA/YCH/2017/02A / Request for Single Stage - One 2018-08- 2018-09- 2018-10- 2017-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 51,600.00 44,435.72 Completed Road construction. Quotations Envelope 07 28 02 09 31 Support W/YA/YCH/2018/07 / Component B: Economic Yichuan county. The 2km Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 143,300.00 139,974.70 Completed harden road for Mashan Quotations Envelope 18 05 13 26 11 Support village and Lijialing village. W/YA/YCH/2018/08 / Component B: Economic Yichuan county. 2 bridges Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 65,900.00 66,809.77 Completed for Miaogoukou and Quotations Envelope 18 06 13 27 11 Support Yunwanggou. And 1 culvert. W/YA/YCH/2018/09 / Component B: Economic Yichuan county. 1.4km Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 149,000.00 152,418.37 Completed hardening road and 1.7km Quotations Envelope 18 12 13 03 11 Support new drainage ditch. W/YA/YCH/2018/10 / Component B: Economic Yichuan county. 10km Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 79,192.00 Completed productive road for Ruyi Quotations Envelope 18 09 13 01 11 Support village. W/YA/YCH/2018/11 / Yichuan county. 2.6km Component B: Economic Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-07- 2019-04- hardening road for IBRD / 86840 Infrastructure and Services Post Limited 206,300.00 213,039.37 Completed Quotations Envelope 18 05 13 26 11 Shijiazhuang village, as well Support as 0.7km new drainage ditch. W/YA/YCH/2018/12 / Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-04- Yichuan county. 1 water well IBRD / 86840 Infrastructure and Services Post Limited 57,300.00 0.00 Implementa Quotations Envelope 18 13 11 for Shijiazhuang village. Support tion W/YA/YCH/2018/13 / Component B: Economic Pending Yichuan county. 8.05km Request for Single Stage - One 2018-08- 2018-10- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 57,700.00 0.00 Implementa productive road for Quotations Envelope 18 13 11 Support tion Shijiazhuang village. W/YA/YCH/2018/14 / Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- Yichuan county. 10km gravel IBRD / 86840 Infrastructure and Services Post Limited 143,300.00 148,410.58 Completed Quotations Envelope 18 14 13 07 11 road for Shijiazhuang village. Support W/YA/YCH/2018/15 / Component B: Economic Yichuan county. 9.5km Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 136,100.00 137,645.14 Completed gravel road for Guantou and Quotations Envelope 18 23 13 15 11 Support Shijiazhuang village. W/YA/YCH/2018/16 / Component B: Economic Yichuan county. 4 bridges. 2 Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 114,600.00 118,335.44 Completed for Shishao village and other Quotations Envelope 18 10 13 03 11 Support 2 for Taiping village. W/YA/YCH/2018/17 / Component B: Economic Yichuan county. 9km Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 110,300.00 111,144.29 Completed productive road and 7 Quotations Envelope 18 09 13 01 11 Support culvert for Shishao village. W/YA/YCH/2018/18 / Yichuan county. 0.825km Component B: Economic Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- hardening road and 0.5km IBRD / 86840 Infrastructure and Services Post Limited 73,400.00 85,765.04 Completed Quotations Envelope 18 23 13 15 11 drainage ditch for Shishao Support village. W/YA/YCH/2018/19 / Component B: Economic Yichuan county. 1.8km Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 129,000.00 133,625.18 Completed hardening road for Quotations Envelope 18 06 13 27 11 Support Nanbutou village. W/YA/YCH/2018/20 / Yichuan county. 11km Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- productive road and 2 IBRD / 86840 Infrastructure and Services Post Limited 96,000.00 99,156.80 Completed Quotations Envelope 18 10 13 03 11 culvert for Nanbutou village Support and Yanqu village. W/YA/YCH/2018/21 / Yichuan county. 8km Component B: Economic productive road for Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 75,200.00 75,944.92 Completed Nanbutou village, 0.5km Quotations Envelope 18 09 13 01 11 Support road for Guanzhuan village and 2km road for Mayuan. W/YA/YCH/2018/22 / Yichuan county. 2 bridges Component B: Economic Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- for Zuishang and Yadi IBRD / 86840 Infrastructure and Services Post Limited 74,500.00 81,085.62 Completed Quotations Envelope 18 24 13 17 11 village, 2 culverts for Support Guanzhuang village. W/YA/YCH/2018/23 / Yichuan county. 5km Component B: Economic Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- productive road for Nantou IBRD / 86840 Infrastructure and Services Post Limited 60,900.00 59,685.66 Completed Quotations Envelope 18 09 13 01 11 village and 3km road for Support Dahumiao village. W/YA/YCH/2018/24 / Component B: Economic Yichuan county. 10km Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 71,600.00 72,424.47 Completed productive road for Nantou Quotations Envelope 18 06 13 13 11 Support village. W/YA/YCH/2018/25 / Yichuan county. 4 watering Component B: Economic place for 4 villages, Request for Single Stage - One 2018-08- 2018-07- 2018-10- 2018-08- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 70,200.00 68,606.54 Completed Zuishang, Taiping, Quotations Envelope 18 24 13 17 11 Support Shijiazhuang and Heling village. 1km drainage ditch for Lingshang village. W/YA/YCH/2018/26 / Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-04- Yichuan county. Gravel road IBRD / 86840 Infrastructure and Services Post Limited 14,300.00 0.00 Implementa Quotations Envelope 18 13 11 for Taiping village. Support tion W/YA/YCH/2018/27 / Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-04- Yichuan county. bridge for IBRD / 86840 Infrastructure and Services Post Limited 28,700.00 0.00 Implementa Quotations Envelope 18 13 11 Nanbutou village. Support tion W/YU/M/2018/09 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Road hardening for IBRD / 86840 Infrastructure and Services Post Limited 153,000.00 141,804.45 Completed Quotations Envelope 28 13 23 10 21 Yangjiagou village. Support W/YU/M/2018/10 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Hardened Road for IBRD / 86840 Infrastructure and Services Post Limited 171,000.00 155,034.40 Signed Quotations Envelope 28 13 23 10 21 Sigou village. Support W/YU/M/2018/11 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Hardened Road for IBRD / 86840 Infrastructure and Services Post Limited 166,000.00 149,236.86 Signed Quotations Envelope 28 13 23 10 21 Gongjiagou village. Support Page 6 W/YU/M/2018/12 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Hardened Road for IBRD / 86840 Infrastructure and Services Post Limited 142,000.00 139,888.43 Completed Quotations Envelope 28 13 23 10 21 Gongjiagou village. Support W/YU/M/2018/13 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Hardened Road for Li IBRD / 86840 Infrastructure and Services Post Limited 266,000.00 232,514.61 Completed Quotations Envelope 28 13 23 10 21 village. Support W/YU/M/2018/14 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Hardened road for IBRD / 86840 Infrastructure and Services Post Limited 270,000.00 243,566.55 Signed Quotations Envelope 28 14 23 10 21 Yuejiacha village. Support W/YU/M/2018/15 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Hardened road for IBRD / 86840 Infrastructure and Services Post Limited 263,000.00 228,317.30 Signed Quotations Envelope 28 14 23 10 21 Yuejiacha village. Support W/YU/M/2018/16 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Hardened road for IBRD / 86840 Infrastructure and Services Post Limited 213,000.00 194,405.69 Completed Quotations Envelope 28 14 23 10 21 Majiaxiaogou village. Support W/YU/M/2018/17 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-08- 2018-10- 2018-09- 2019-04- county. Hardened road for IBRD / 86840 Infrastructure and Services Post Limited 231,000.00 270,463.98 Signed Quotations Envelope 28 14 23 10 21 Houjiagou village. Support Component B: Economic W/YU/M/2018/18 / Mizhi Request for Single Stage - One 2018-08- 2018-09- 2018-10- 2018-10- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 266,000.00 187,710.00 Signed county. Land governance. Quotations Envelope 28 07 23 09 21 Support W/YU/M/2018/19 / Mizhi county. Well engineering for Component B: Economic Request for Single Stage - One 2018-08- 2018-09- 2018-10- 2018-10- 2019-04- Yangjiagou village, IBRD / 86840 Infrastructure and Services Post Limited 166,000.00 157,195.31 Signed Quotations Envelope 28 07 23 09 21 Gongjiagou village and Li Support village. Component B: Economic W/YU/M/2018/20 / Mizhi Request for Single Stage - One 2018-08- 2018-09- 2018-10- 2018-10- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 161,000.00 153,883.66 Signed county. Well engineering Quotations Envelope 28 07 23 09 21 Support W/YU/M/2018/21 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-09- 2018-10- 2018-10- 2019-04- county. Water storage IBRD / 86840 Infrastructure and Services Post Limited 118,000.00 125,126.94 Signed Quotations Envelope 28 07 23 09 21 engineering. Support W/YU/M/2018/22 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-09- 2018-10- 2018-10- 2019-04- county. Water supply IBRD / 86840 Infrastructure and Services Post Limited 200,000.00 149,051.21 Signed Quotations Envelope 28 07 23 09 21 irrigation. Support W/YU/M/2018/23 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-09- 2018-10- 2018-10- 2019-04- county. Water supply IBRD / 86840 Infrastructure and Services Post Limited 244,000.00 186,891.43 Signed Quotations Envelope 28 07 23 09 21 Engineering. Support W/YU/M/2018/24 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2018-09- 2018-10- 2018-10- 2019-04- county. Drainage system IBRD / 86840 Infrastructure and Services Post Limited 140,000.00 154,499.71 Signed Quotations Envelope 28 07 23 09 21 construction service. Support W/YU/M/2018/25 / Mizhi Component B: Economic Request for Single Stage - One 2018-08- 2019-10- 2018-10- 2019-11- 2019-04- county. Environmental IBRD / 86840 Infrastructure and Services Post Limited 197,000.00 192,394.35 Completed Quotations Envelope 28 08 23 14 21 engineering. Support Component B: Economic W/YU/M/2018/26 / Mizhi Request for Single Stage - One 2018-08- 2019-06- 2018-10- 2019-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 177,000.00 166,711.76 Completed county. Market construction. Quotations Envelope 28 14 23 15 21 Support W/YA/Y/2018/01A / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. Irrigation IBRD / 86840 Infrastructure and Services Post Limited 148,000.00 131,912.29 Signed Quotations Envelope 04 04 30 31 28 project. Support W/YA/Y/2018/02 / Component B: Economic Yanchang county. Repair the Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 57,000.00 43,236.31 Signed 4km productive road for Quotations Envelope 04 02 30 27 28 Support Donggou village. W/YA/Y/2018/03 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. Repair the IBRD / 86840 Infrastructure and Services Post Limited 43,000.00 24,144.77 Signed Quotations Envelope 04 02 30 27 28 productive road for Liku Support village. W/YA/Y/2018/04 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. Repair the IBRD / 86840 Infrastructure and Services Post Limited 57,000.00 28,252.87 Signed Quotations Envelope 04 04 30 31 28 productive road for Liku Support village. W/YA/Y/2018/05 / Component B: Economic Yanchang village. Repair Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 43,000.00 44,057.11 Signed road from Liku village to Quotations Envelope 04 02 30 27 28 Support Yanliujiaxigou village. W/YA/Y/2018/06 / Component B: Economic Yanchang county. Repair the Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 36,000.00 18,730.86 Signed 2.5km productive road for Quotations Envelope 04 02 30 27 28 Support Zhaojialiang village. W/YA/Y/2018/07 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. 2 IBRD / 86840 Infrastructure and Services Post Limited 50,000.00 38,625.65 Signed Quotations Envelope 04 02 30 27 28 productive road for Yanliujia Support village. W/YA/Y/2018/08 / Component B: Economic Pending Request for Single Stage - One 2018-09- 2018-10- 2019-04- Yanchang county. The IBRD / 86840 Infrastructure and Services Post Limited 21,000.00 0.00 Implementa Quotations Envelope 04 30 28 productive road for Luozizui Support tion village. W/YA/Y/2018/09 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. The IBRD / 86840 Infrastructure and Services Post Limited 29,000.00 24,134.28 Signed Quotations Envelope 04 04 30 31 28 productive road for Support Kushuizuiliang village. W/YA/Y/2018/10 / Component B: Economic Pending Request for Single Stage - One 2018-09- 2018-10- 2019-04- Yanchang county. 3 IBRD / 86840 Infrastructure and Services Post Limited 40,000.00 0.00 Implementa Quotations Envelope 04 30 28 productive roads for Support tion Shangjia village. W/YA/Y/2018/11 / Component B: Economic Pending Request for Single Stage - One 2018-09- 2018-10- 2019-04- Yanchang county. Repair 2 IBRD / 86840 Infrastructure and Services Post Limited 47,000.00 0.00 Implementa Quotations Envelope 04 30 28 productive roads for Support tion Shangpan village. W/YA/Y/2018/12 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. Repair 2 IBRD / 86840 Infrastructure and Services Post Limited 50,000.00 34,779.65 Signed Quotations Envelope 04 03 30 30 28 productive roads for Support Shangpan village. W/YA/Y/2018/13 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. 3 IBRD / 86840 Infrastructure and Services Post Limited 73,000.00 41,532.26 Signed Quotations Envelope 04 03 30 30 28 productive roads for Yangjia Support village. W/YA/Y/2018/14 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. The IBRD / 86840 Infrastructure and Services Post Limited 43,000.00 27,696.02 Signed Quotations Envelope 04 03 30 30 28 productive road for Support Dongjinggou village. W/YA/Y/2018/15 / Component B: Economic Yanchang county. The Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 29,000.00 16,926.88 Signed productive road from Quotations Envelope 04 03 30 30 28 Support Nanling village to Gadamao village. W/YA/Y/2018/16 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. 2 IBRD / 86840 Infrastructure and Services Post Limited 64,000.00 16,042.03 Signed Quotations Envelope 04 03 30 30 28 productive roads for Xiayuan Support village. W/YA/Y/2018/17 / Component B: Economic Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- Yanchang county. Hardening IBRD / 86840 Infrastructure and Services Post Limited 269,000.00 229,693.22 Signed Quotations Envelope 04 04 30 31 28 road for Anhe community. Support Component B: Economic W/YA/Y/2018/18 / Request for Single Stage - One 2018-09- 2018-07- 2018-10- 2018-07- 2019-04- IBRD / 86840 Infrastructure and Services Post Limited 109,000.00 94,524.01 Signed Yanchang county. New road. Quotations Envelope 04 04 30 31 28 Support Component B: Economic W/W/B/2018/20 / Baishui Request for Single Stage - One 2018-09- 2019-04- 2018-11- 2019-05- 2019-05- IBRD / 86840 Infrastructure and Services Post Limited 229,000.00 67,114.18 Completed county. Repairing new road. Quotations Envelope 10 30 05 20 04 Support Component B: Economic Pending W/W/B/2018/21 / Baishui Request for Single Stage - One 2018-09- 2018-11- 2019-05- IBRD / 86840 Infrastructure and Services Post Limited 182,000.00 0.00 Implementa county. Repair new road. Quotations Envelope 10 05 04 Support tion Component B: Economic W/B/LX/2018/01 / Long Request for Single Stage - One 2018-09- 2018-09- 2018-11- 2018-10- 2019-05- IBRD / 86840 Infrastructure and Services Post Limited 43,000.00 42,052.07 Signed county. Land reclamation. Quotations Envelope 10 21 05 25 04 Support W/B/LX/2018/02 / Long Component B: Economic Request for Single Stage - One 2018-09- 2018-09- 2018-11- 2018-11- 2019-05- county. Repair the gravel IBRD / 86840 Infrastructure and Services Post Limited 116,000.00 107,309.26 Completed Quotations Envelope 10 21 05 02 04 road. Support W/B/LX/2018/03 / Long Component B: Economic Request for Single Stage - One 2018-09- 2018-09- 2018-11- 2018-11- 2019-05- county. Repair the gravel IBRD / 86840 Infrastructure and Services Post Limited 125,000.00 112,494.82 Completed Quotations Envelope 10 21 05 09 04 road. Support Page 7 W/B/LX/2018/04 / Long Component B: Economic Request for Single Stage - One 2018-09- 2018-10- 2018-11- 2018-11- 2019-05- county. Repair the gravel IBRD / 86840 Infrastructure and Services Post Limited 64,000.00 57,768.16 Completed Quotations Envelope 10 17 05 16 04 road. Support Component B: Economic W/W/H/2018/01 / Heyang Request for Single Stage - One 2018-09- 2019-02- 2018-11- 2019-03- 2019-05- IBRD / 86840 Infrastructure and Services Post Limited 242,000.00 269,875.26 Completed county. Village road. Quotations Envelope 10 26 05 29 04 Support Component B: Economic W/W/H/2018/02 / Heyang Request for Single Stage - One 2018-09- 2019-02- 2018-11- 2019-03- 2019-05- IBRD / 86840 Infrastructure and Services Post Limited 191,000.00 187,397.55 Completed county. Production road. Quotations Envelope 10 27 05 25 04 Support Component B: Economic W/W/H/2018/03 / Heyang Request for Single Stage - One 2018-09- 2019-02- 2018-11- 2019-03- 2019-05- IBRD / 86840 Infrastructure and Services Post Limited 123,000.00 121,446.71 Completed county. Production road. Quotations Envelope 10 28 05 26 04 Support Component B: Economic W/W/H/2018/04 / Heyang Request for Single Stage - One 2018-09- 2019-02- 2018-11- 2019-03- 2019-05- IBRD / 86840 Infrastructure and Services Post Limited 108,000.00 142,192.34 Completed county. Production road. Quotations Envelope 10 28 05 16 04 Support W/W/H/2018/06 / Heyang county. 1 elevated tank of Component B: Economic Request for Single Stage - One 2018-09- 2019-03- 2018-11- 2019-04- 2019-05- 1000 cubic meters in Xiang IBRD / 86840 Infrastructure and Services Post Limited 151,000.00 191,652.46 Completed Quotations Envelope 10 10 05 08 04 village, expand 1 secondary Support pump station in lingao. W/W/H/2018/09 / Heyang Component B: Economic Under Request for Single Stage - One 2018-09- 2019-03- 2018-11- 2019-05- county. Irrigation pipe IBRD / 86840 Infrastructure and Services Post Limited 270,000.00 292,770.09 Implementa Quotations Envelope 10 10 05 04 network. Support tion W/W/H/2018/10 / Heyang Component B: Economic Request for Single Stage - One 2018-09- 2019-03- 2018-11- 2019-04- 2019-05- county. Irrigation pipe IBRD / 86840 Infrastructure and Services Post Limited 161,000.00 204,160.55 Completed Quotations Envelope 10 10 05 08 04 network. Support Component B: Economic Pending W/W/H/2018/05 / Heyang Single Stage - One 2018-09- 2018-09- 2018-10- 2018-11- 2018-12- 2019-06- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 528,000.00 0.00 Implementa county. New pump station. Envelope 05 10 22 21 26 24 Support tion W/W/H/2018/07 / Heyang Component B: Economic Pending Single Stage - One 2018-09- 2018-09- 2018-10- 2018-11- 2018-12- 2019-06- county. Irrigation pipe IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 436,000.00 0.00 Implementa Envelope 05 10 22 21 26 24 network Support tion W/W/H/2018/08 / Heyang Component B: Economic Pending Single Stage - One 2018-09- 2018-09- 2018-10- 2018-11- 2018-12- 2019-06- county. Irrigation pipe IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 302,000.00 0.00 Implementa Envelope 05 10 22 21 26 24 network. Support tion W/W/H/H/2018/01 / Component B: Economic Pending Single Stage - One 2018-09- 2018-09- 2018-10- 2018-11- 2018-12- 2019-06- Heyang county. Irrigation IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 344,000.00 0.00 Implementa Envelope 05 10 22 21 26 24 pipe network. Support tion W/YA/YC/2017/04B / Yanchuan county. Component B: Economic Request for Single Stage - One 2018-10- 2017-11- 2018-12- 2017-12- 2019-06- Constructed 3 bridges IBRD / 86840 Infrastructure and Services Post Limited 146,300.00 136,731.49 Completed Quotations Envelope 31 07 26 10 24 cemented with M10 masonry Support and the wall is based on M12.5 fine stone materials. W/YA/YCH/2017/12 / Component B: Economic Request for Single Stage - One 2018-12- 2017-09- 2019-02- 2017-10- 2019-08- Yichuan county, hardening IBRD / 86840 Infrastructure and Services Post Limited 68,330.00 69,666.45 Completed Quotations Envelope 09 06 03 05 02 road in Liuchagou village. Support Component B: Economic Pending W/B/LX/2019/01 / 20 new Single Stage - One 2019-04- 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 86840 Infrastructure and Services Post Request for Bids Limited 308,100.00 0.00 Implementa motor-pumped well Envelope 04 09 21 20 25 21 Support tion Component B: Economic Pending W/B/LX/2019/02 / Newly Single Stage - One 2019-04- 2019-04- 2019-05- 2019-06- 2019-07- 2020-01- IBRD / 86840 Infrastructure and Services Post Request for Bids Limited 487,800.00 0.00 Implementa making 40km canal Envelope 04 09 21 20 25 21 Support tion W/B/LX/2019/03 / Component B: Economic Pending Request for Single Stage - One 2019-04- 2019-06- 2019-12- Retaining works including 2 IBRD / 86840 Infrastructure and Services Post Limited 14,300.00 0.00 Implementa Quotations Envelope 09 04 01 elevated tank Support tion W/B/LX/2019/04 / 6km Component B: Economic Pending Request for Single Stage - One 2019-04- 2019-06- 2019-12- new water-works IBRD / 86840 Infrastructure and Services Post Limited 68,800.00 0.00 Implementa Quotations Envelope 09 04 01 engineering Support tion Component B: Economic Pending W/B/LX/2019/05 / 4.8km Request for Single Stage - One 2019-04- 2019-06- 2019-12- IBRD / 86840 Infrastructure and Services Post Limited 27,500.00 0.00 Implementa new drainage work Quotations Envelope 09 04 01 Support tion W/B/LX/2019/06 / 3.5km Component B: Economic Pending Request for Single Stage - One 2019-04- 2019-06- 2019-12- newly making road inside IBRD / 86840 Infrastructure and Services Post Limited 250,800.00 0.00 Implementa Quotations Envelope 09 04 01 village Support tion W/B/LX/2019/07 / 8km Component B: Economic Pending Request for Single Stage - One 2019-04- 2019-06- 2019-12- road maintenance inside the IBRD / 86840 Infrastructure and Services Post Limited 172,000.00 0.00 Implementa Quotations Envelope 09 04 01 village Support tion Component B: Economic W/W/B/2019/02 / 12km Request for Single Stage - One 2019-04- 2019-04- 2019-06- 2019-05- 2019-12- IBRD / 86840 Infrastructure and Services Post Limited 197,700.00 243,996.27 Completed new canal construction Quotations Envelope 09 25 04 21 01 Support W/W/B/2019/03 / 1.89km Component B: Economic Request for Single Stage - One 2019-04- 2019-04- 2019-06- 2019-05- 2019-12- road construction in Yanghe IBRD / 86840 Infrastructure and Services Post Limited 162,500.00 231,895.07 Completed Quotations Envelope 09 30 04 20 01 village Support W/W/B/2019/04 / 1.183km Component B: Economic Request for Single Stage - One 2019-04- 2019-04- 2019-06- 2019-05- 2019-12- road hardening in Yangxia IBRD / 86840 Infrastructure and Services Post Limited 101,700.00 118,344.97 Completed Quotations Envelope 09 30 04 21 01 village Support W/YU/M/2019/01 / Biogas Component B: Economic Request for Single Stage - One 2019-04- 2019-06- 2019-06- 2019-07- 2019-12- engineering in civil IBRD / 86840 Infrastructure and Services Post Limited 9,100.00 10,486.42 Completed Quotations Envelope 09 14 04 15 01 engineering Support Component B: Economic W/YA/YCH/2018/01 / Request for Single Stage - One 2019-05- 2018-05- 2019-07- 2018-06- 2020-01- IBRD / 86840 Infrastructure and Services Post Limited 35,100.00 57,521.52 Completed 2.3km gravel road Quotations Envelope 20 29 15 21 11 Support Component B: Economic W/YA/YCH/2018/02 / Request for Single Stage - One 2019-05- 2018-05- 2019-07- 2018-06- 2020-01- IBRD / 86840 Infrastructure and Services Post Limited 25,900.00 57,521.52 Completed Gravel road in Tasi village. Quotations Envelope 20 29 15 21 11 Support W/YA/YCH/2018/03 / Component B: Economic Request for Single Stage - One 2019-05- 2018-05- 2019-07- 2018-06- 2020-01- Productive road in Yadi IBRD / 86840 Infrastructure and Services Post Limited 53,400.00 95,634.58 Completed Quotations Envelope 20 29 15 21 11 village. Support W/YA/YCH/2018/04 / Small Component B: Economic Request for Single Stage - One 2019-05- 2018-05- 2019-07- 2018-06- 2020-01- bridge in Shuangquan IBRD / 86840 Infrastructure and Services Post Limited 25,600.00 104,693.88 Completed Quotations Envelope 20 28 15 20 11 village. Support W/YA/YCH/2018/05 / Component B: Economic Request for Single Stage - One 2019-05- 2018-07- 2019-07- 2018-07- 2020-01- Hardening road in Nanwan IBRD / 86840 Infrastructure and Services Post Limited 72,400.00 68,141.73 Completed Quotations Envelope 20 05 15 26 11 village. Support W/YA/YCH/2018/06 / Component B: Economic Request for Single Stage - One 2019-05- 2018-05- 2019-07- 2018-06- 2020-01- Hardening road in Matouling IBRD / 86840 Infrastructure and Services Post Limited 76,200.00 67,438.15 Completed Quotations Envelope 20 28 15 20 11 and Xingshu village. Support W/W/F/2019/01 / 7 1.655 km 3.5 m wide concrete roads from Ren Wanli to Component B: Economic Zhoubesen Gate, Jiangjia to Request for Single Stage - One 2020-03- 2019-05- 2020-05- 2020-06- 2020-10- IBRD / 86840 Infrastructure and Services Post Limited 250,600.00 244,362.42 Signed Huangfeng Road, and 635 M Quotations Envelope 09 07 04 08 31 Support 4 m wide concrete roads from village committee south to Shanggou Group. W/W/F/2019/02 / Three 750 m 3.5 m wide concrete Component B: Economic roads from Jixian Village, Request for Single Stage - One 2020-03- 2020-05- 2020-05- 2020-06- 2020-10- IBRD / 86840 Infrastructure and Services Post Limited 79,000.00 70,347.68 Signed Jixian Village, to Lianbian, Quotations Envelope 09 07 04 08 31 Support Yimen Village, Du Haimen to Sun Jianqiangmen. W/W/F/2019/03 / Six 1.092km3.5m wide concrete roads from the front of Wang Component B: Economic youru's gate of xiancunwang Request for Single Stage - One 2020-03- 2020-05- 2020-05- 2020-06- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 115,100.00 111,246.61 Signed group to Zhizhang Road, Quotations Envelope 11 07 06 08 02 Support genrui's gate of Xijie group to Xiyu line, Sien's gate of Miaoqian group, etc. W/W/F/2019/04 / Three 2.12 km 3.5 m wide concrete roads from Jidong Component B: Economic Group of Zhuangzhen Village Request for Single Stage - One 2020-03- 2020-05- 2020-05- 2020-06- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 223,400.00 200,071.63 Signed to Lianwu Village, Quotations Envelope 11 07 06 09 02 Support Huizengmen Gate of Jixi Group to Dongliu Crossing, Jixi Group to Zhaocun, etc. Page 8 W/W/F/2019/05 / In villages east to Xirencun, Component B: Economic Under Xian project area, 330 m 3.5 Request for 2020-03- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post 270,500.00 0.00 Implementa m wide concrete road to Quotations 06 06 02 Support tion vineyard and two 1.965 km 4 m wide concrete roads. W/W/F/2019/06 / There are 4 1.47 km 3.5 m wide concrete roads from Dongren Village Jiebei Group to the park, Zheng Baiwa Component B: Economic Request for Single Stage - One 2020-03- 2019-05- 2020-05- 2020-06- 2020-11- Gate to Beinian, Zhengqiang IBRD / 86840 Infrastructure and Services Post Limited 232,300.00 204,658.70 Signed Quotations Envelope 16 07 11 09 07 Gate to Tianshimen Gate, Support and 645 M 4 m wide concrete roads from Zhongnan Village to LiuCement Road North in Jiexi Group. W/W/F/2019/07 / Four sets of concrete roads 400 m 4 m wide from the base of Component B: Economic Request for Single Stage - One 2020-03- 2020-05- 2020-05- 2020-06- 2020-11- Wangcun Shanzhuang to IBRD / 86840 Infrastructure and Services Post Limited 48,000.00 45,549.08 Signed Quotations Envelope 16 07 11 08 07 Zhanbacun newly moved to Support Huidian Village, Xian Project Area. W/W/F/2019/08 / 1.49 km Component B: Economic of 10 groups of road in Request for Single Stage - One 2020-03- 2019-04- 2020-05- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 157,700.00 182,642.43 Signed Taibai Village, Cao Village Quotations Envelope 16 13 11 09 07 Support Project Area. W/YU/D/2020/01 / 1.4 km Component B: Economic Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- Residential district road 150 IBRD / 86840 Infrastructure and Services Post Limited 167,700.00 166,239.06 Completed Quotations Envelope 16 05 11 11 07 m Drainage Channel Support Component B: Economic Pending W/YU/M/S/2020/01 / Request for Single Stage - One 2020-03- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 417,500.00 0.00 Implementa Apple preservation project Quotations Envelope 16 11 07 Support tion W/X/C/2020/01 / Component B: Economic Request for Single Stage - One 2020-03- 2020-05- 2020-05- 2020-06- 2020-11- Residential road 1,753 IBRD / 86840 Infrastructure and Services Post Limited 224,600.00 239,966.48 Completed Quotations Envelope 16 14 11 22 07 meters. Support Component B: Economic Pending W/X/C/2020/02 / 7,310 m Request for Single Stage - One 2020-03- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 154,900.00 0.00 Implementa production road Quotations Envelope 16 11 07 Support tion Component B: Economic W/X/C/2020/03 / Water Request for Single Stage - One 2020-03- 2020-06- 2020-05- 2020-08- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 133,700.00 128,590.43 Signed well drilling Quotations Envelope 16 22 11 05 07 Support W/B/LX/2020/01 / Build three overflow river bridges Component B: Economic Pending among Tieyuan first group, Request for Single Stage - One 2020-03- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 172,000.00 0.00 Implementa Tieyuan second group, Quotations Envelope 16 11 07 Support tion Tieyuan third group and Tieyuan fourth group. W/B/LX/2020/02 / Build Component B: Economic Pending Request for Single Stage - One 2020-03- 2020-05- 2020-11- three new restrooms in the IBRD / 86840 Infrastructure and Services Post Limited 107,500.00 0.00 Implementa Quotations Envelope 16 11 07 Tieyuan project area. Support tion W/B/LX/2020/03 / Build 400 square meters food court, which is used for poor Component B: Economic Pending Request for Single Stage - One 2020-03- 2020-05- 2020-11- households to start IBRD / 86840 Infrastructure and Services Post Limited 129,000.00 0.00 Implementa Quotations Envelope 16 11 07 businesses. There will be 50 Support tion exhibition shops, and each of them is 10 square meters. Component B: Economic W/YA/YC/2020/01 / 144 Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 94,000.00 94,070.89 Completed sets of Soft water cellar Quotations Envelope 17 13 12 18 08 Support Component B: Economic W/YA/YC/2020/02 / Road Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 81,500.00 81,558.90 Completed hardening 0.707 km Quotations Envelope 17 13 12 18 08 Support Component B: Economic W/YA/YC/2020/03 / Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 216,000.00 216,341.79 Completed Production road 5.903 km Quotations Envelope 17 12 12 18 08 Support Component B: Economic W/YA/YC/2020/04 / Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 225,400.00 225,747.23 Completed Production road 6.16 km Quotations Envelope 17 12 12 18 08 Support Component B: Economic W/YA/YC/2020/05 / Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 96,500.00 99,349.82 Completed Production road 2.638 km Quotations Envelope 17 12 12 18 08 Support Component B: Economic W/YA/YC/2020/06 / Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 229,300.00 229,823.94 Completed Production road 6.266 km Quotations Envelope 17 12 12 18 08 Support Component B: Economic W/YA/YC/2020/07 / Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 110,200.00 110,006.22 Completed Production road 3.011 km Quotations Envelope 17 13 12 18 08 Support W/YA/YC/2020/08 / 6 Component B: Economic Request for Single Stage - One 2020-03- 2020-04- 2020-05- 2020-05- 2020-11- production bridges and IBRD / 86840 Infrastructure and Services Post Limited 266,700.00 267,136.23 Completed Quotations Envelope 17 13 12 18 08 culverts Support W/W/B/2019/05A / 11.8 km production road Component B: Economic Request for Single Stage - One 2020-04- 2019-04- 2020-06- 2019-05- 2020-11- construction project in IBRD / 86840 Infrastructure and Services Post Limited 265,400.00 239,250.35 Completed Quotations Envelope 06 30 01 21 28 Dayang village, Houwa Support village and Fengjiayuan village. W/W/B/2019/06A / 4 Component B: Economic pumping well construction Request for Single Stage - One 2020-04- 2019-04- 2020-06- 2019-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 229,100.00 202,599.57 Signed programs in Dayang village Quotations Envelope 06 25 01 21 28 Support and Fengjiayuan village. W/W/B/2019/07 / Road Component B: Economic hardening engineering in Request for Single Stage - One 2020-05- 2019-10- 2020-06- 2019-10- 2020-12- IBRD / 86840 Infrastructure and Services Post Limited 98,500.00 94,347.12 Completed Dukang project area 0.85km Quotations Envelope 04 12 29 31 26 Support (4m in width). W/B/LX/2020/04 / Build Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- 4393 cubic meters of river IBRD / 86840 Infrastructure and Services Post Limited 251,800.00 0.00 Implementa Quotations Envelope 09 04 02 levee Support tion W/B/LX/2020/05 / Build a Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- drainage network of 2,200 IBRD / 86840 Infrastructure and Services Post Limited 51,600.00 0.00 Implementa Quotations Envelope 09 04 02 meters. Support tion W/B/LX/2020/06 / Rebuild Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- machine brick road (2910 IBRD / 86840 Infrastructure and Services Post Limited 247,400.00 0.00 Implementa Quotations Envelope 09 04 02 meters, 10155 square Support tion meters) W/B/LX/2020/07 / Biogas Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- project (3 bio-composting IBRD / 86840 Infrastructure and Services Post Limited 26,300.00 0.00 Implementa Quotations Envelope 09 04 02 pits, 175 cubic meters) Support tion W/B/LX/2020/08 / Market construction civil engineering (2,200 square meters of food plaza; 400 Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- square meters of agricultural IBRD / 86840 Infrastructure and Services Post Limited 237,900.00 0.00 Implementa Quotations Envelope 09 04 02 products points of sale; 400 Support tion square meters of specialty catering points of sale; total 3000 square meters) W/W/F/2020/01 / Rebuild concrete road (length: 2246 Component B: Economic Pending meters, width: 4 meters) Request for Single Stage - One 2020-08- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 269,400.00 0.00 Implementa from Industrial Park, Quotations Envelope 09 04 02 Support tion Shuangsheng Village, Liuji Project Area to the north of Dongwang Group. W/W/F/2020/02 / Rebuild concrete road (length: 2091.1 meters, width: 4 meters) in total in Liuji Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- Project Area. IBRD / 86840 Infrastructure and Services Post Limited 246,000.00 0.00 Implementa Quotations Envelope 09 04 02 Respectively, rebuild 795.63 Support tion meters of concrete road in Shuangsheng Village; 390.21 meters in Shizi Village; 905.26 meters in Zhangbei Village. Page 9 W/W/F/2020/03 / Rebuild concrete road (length: 1071.04 meters, width: 4 meters) in total in Liuji Project Area. Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- Respectively, rebuild IBRD / 86840 Infrastructure and Services Post Limited 127,500.00 0.00 Implementa Quotations Envelope 09 04 02 856.912 meters of concrete Support tion road in Beifu Village; 214.123 meters from the gate of Liuhui Station in Dongliu Group to Zhang Road. W/W/F/2020/04 / Build concrete U40 irrigation canal 8130m in Liuji Project Area totally. Component B: Economic Pending Respectively, build 1346m in Request for Single Stage - One 2020-08- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 211,100.00 0.00 Implementa Huangyuan Village; build Quotations Envelope 09 04 02 Support tion 1193m in Chuanhe Village; build 3378 meters in Shizi village ; build 2213 meters in Caoguan Village. W/X/C/2020/04 / The total Component B: Economic Pending length of hardened roads in Request for Single Stage - One 2020-08- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 247,300.00 0.00 Implementa Jujia Town Project Area is Quotations Envelope 27 22 20 Support tion 1,991 meters. W/X/C/2020/05 / The total Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- length of gravel roads in IBRD / 86840 Infrastructure and Services Post Limited 277,700.00 0.00 Implementa Quotations Envelope 27 22 20 Jujia Town is 8,956 meters. Support tion W/X/C/2020/06 / The total length of hardened roads in Hongjia Town Project Area is Component B: Economic Pending 1,485 meters. One road's Request for Single Stage - One 2020-08- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 176,800.00 0.00 Implementa width is 3.5 meters, and it's Quotations Envelope 27 22 20 Support tion length is 1,002 meters; The other's width is 3 meters, and it's length is 483 meters. W/X/C/2020/07 / Build a 417-meter drainage ditch in Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- Anli Village, Hongjia Town, IBRD / 86840 Infrastructure and Services Post Limited 30,900.00 0.00 Implementa Quotations Envelope 27 22 20 with a single-sided Support tion installation and concrete lining. W/B/LY/2020/01 / Harden Component B: Economic Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- cement roads in Zhaoxian IBRD / 86840 Infrastructure and Services Post Limited 191,200.00 190,063.78 Signed Quotations Envelope 27 15 22 13 20 Village. Support W/B/LY/2020/02 / Component B: Economic Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- Construct roads in the fields IBRD / 86840 Infrastructure and Services Post Limited 135,900.00 82,102.31 Signed Quotations Envelope 27 15 22 11 20 in Banqiao Village. Support W/B/LY/2020/03 / Component B: Economic Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- Construct roads in the fields IBRD / 86840 Infrastructure and Services Post Limited 121,500.00 70,327.09 Signed Quotations Envelope 27 30 22 11 20 in Gaozhuang Village. Support W/B/LY/2020/04 / Component B: Economic Construct roads in the fields Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 108,300.00 65,419.16 Signed in Zhuangzigou and Quotations Envelope 27 30 22 12 20 Support Nangouzu, Zhaoxian Village. W/B/LY/2020/05 / Component B: Economic Construct roads in the fields Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 181,200.00 188,812.06 Signed in Chongwangdian, Banpo Quotations Envelope 27 15 22 12 20 Support and Baozizu, Zhaoxian Village. W/B/LY/2020/06 / Component B: Economic Construct roads in the fields Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 161,300.00 165,755.54 Signed in Panjiagou and Xiajizu, Quotations Envelope 27 15 22 12 20 Support Zhaoxian Village. W/B/LY/2020/07 / Build a Component B: Economic Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- production bridge in Yuyuan IBRD / 86840 Infrastructure and Services Post Limited 44,400.00 46,151.99 Signed Quotations Envelope 27 29 22 10 20 Hetan, Banqiao Village. Support W/B/LY/2020/08 / Build a Component B: Economic Request for Single Stage - One 2020-08- 2020-12- 2020-10- 2020-10- 2021-04- production bridge in IBRD / 86840 Infrastructure and Services Post Limited 18,300.00 21,328.84 Signed Quotations Envelope 27 15 22 10 20 Jiaojiagou, Banqiao Village. Support W/B/LY/2020/09 / Build a Component B: Economic Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- production bridge in IBRD / 86840 Infrastructure and Services Post Limited 44,400.00 39,180.57 Signed Quotations Envelope 27 15 22 12 20 Yuchibian, Banqiao Village. Support W/B/LY/2020/10 / Build a Component B: Economic Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- production bridge in IBRD / 86840 Infrastructure and Services Post Limited 69,400.00 51,707.36 Signed Quotations Envelope 27 15 22 13 20 Xigoukou, Banqiao Village. Support W/B/LY/2020/11 / Build a Component B: Economic Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- production bridge in IBRD / 86840 Infrastructure and Services Post Limited 89,200.00 51,422.87 Signed Quotations Envelope 27 15 22 11 20 Donggou, Banqiao Village. Support W/B/LY/2020/12 / Build a Component B: Economic production bridge in Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 27,700.00 39,179.39 Signed Xujiashan, Baozizu, Quotations Envelope 27 15 22 12 20 Support Zhaoxian Village. W/B/LY/2020/13 / Build a Component B: Economic production bridge in Juju Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 69,400.00 42,715.99 Signed Menshen, Nangouzu, Quotations Envelope 27 15 22 14 20 Support Zhaoxian Village. W/B/LY/2020/14 / Build a Component B: Economic production bridge in Request for Single Stage - One 2020-08- 2020-12- 2020-10- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 55,500.00 62,605.06 Signed Zhuangke, Nangouzu, Quotations Envelope 27 15 22 14 20 Support Zhaoxian Village. W/B/LY/2020/15 / Build a Component B: Economic Under production bridge in Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 69,400.00 0.00 Implementa Liangshuiquan, Anjiapozu, Quotations Envelope 27 15 22 20 Support tion Gaozhuang Village. W/B/LY/2020/16 / Build a Component B: Economic Pending production bridge in Request for Single Stage - One 2020-08- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 69,400.00 0.00 Implementa Zhangjiashan, Zhulinzu, Quotations Envelope 27 22 20 Support tion Gaozhuang Village. W/B/LY/2020/17 / Build a Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- production bridge in Apple IBRD / 86840 Infrastructure and Services Post Limited 55,500.00 0.00 Implementa Quotations Envelope 27 22 20 Grove, Gaozhuang Village. Support tion W/B/LY/2020/18 / Land Component B: Economic Pending Request for Single Stage - One 2020-08- 2020-10- 2021-04- levelling project in Banqiao IBRD / 86840 Infrastructure and Services Post Limited 20,400.00 0.00 Implementa Quotations Envelope 27 22 20 Villiage. Support tion W/W/H/2020/03 / Install irrigation pipe network with 1.66-square kilometre main pipeline among Xiyang Component B: Economic Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- Village, Xiao Village, Cheng IBRD / 86840 Infrastructure and Services Post Limited 212,700.00 227,515.23 Signed Quotations Envelope 27 17 22 10 20 Village and Diantou Village. Support Expecially, the area of drop irrigation is 0.497 square kilometres. W/YA/YC/2020/09 / Component B: Economic Construct 6.7-kilometres Request for Single Stage - One 2020-08- 2020-09- 2020-10- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 223,200.00 240,157.76 Signed gravel roads in Zhongyuan Quotations Envelope 27 22 22 25 20 Support Village. W/YA/YC/2020/10 / Component B: Economic Construct 5.768-kilometres Request for Single Stage - One 2020-08- 2020-10- 2020-10- 2020-10- 2021-04- IBRD / 86840 Infrastructure and Services Post Limited 239,500.00 223,619.64 Signed gravel roads in Lijiaqian Quotations Envelope 27 19 22 25 20 Support Village. W/X/C /TF/2020/01 / Civil Component B: Economic Pending Single Stage - One 1,469,000.0 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- engineering of 4500¡ tradin IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 0.00 Implementa Envelope 0 05 10 24 23 28 24 g center Support tion W/W/B/L/2021/01 / 2340¡ Component B: Economic Pending storage and logistics area, a Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 724,400.00 0.00 Implementa nd 1620¡ processing and pa Envelope 05 10 24 23 28 24 Support tion ckaging area W/W/B/L/2021/02 / Compr Component B: Economic Pending Request for Single Stage - One 2021-02- 2021-04- 2021-10- ehensive service building 64 IBRD / 86840 Infrastructure and Services Post Limited 175,600.00 0.00 Implementa Quotations Envelope 09 06 03 0¡ Support tion W/W/F/SF/2021/01 / Build Component B: Economic Pending Single Stage - One 1,166,900.0 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- a processing workshop IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 0.00 Implementa Envelope 0 05 10 24 23 28 24 (136.5m*36.5m*8-18m) Support tion Page 10 W/YA/YCH/S/2021/01 / Bui ld a 1800¡ steel structure fr Component B: Economic Pending uit sorting workshop with fru Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 663,100.00 0.00 Implementa it sorting carts; a 1500¡ war Envelope 05 10 24 23 28 24 Support tion ehouse with steel framed an d color steel tile structure. W/B/LY/TFY/2021/01 / Breeding Park Construction Project (Construction of 4 brooding chicken houses, 10 breeding sheds, 30 simple Component B: Economic Pending Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- chicken houses, 100 m² cool IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 348,600.00 0.00 Implementa Envelope 05 10 24 23 28 24 manure farm, 100 m³ Support tion sewage treatment tank, 1 water pond, 6000 m steel wire fence, 400 m² feed processing warehouse) W/X/C/L/2021/01 / Build a set of 293¡ fruit sorting wor Component B: Economic Pending kshop, 116¡ turnover works Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 478,700.00 0.00 Implementa hop, 705¡ civil engineering Envelope 05 10 24 23 28 24 Support tion and corollary equipments of controlled atmosphere cold s torage. W/W/H/2021/01 / 5671¡ r Component B: Economic Pending Request for Single Stage - One 2021-02- 2021-04- 2021-10- oad construction between M IBRD / 86840 Infrastructure and Services Post Limited 119,300.00 0.00 Implementa Quotations Envelope 10 07 04 azhuang Village and Xiwang Support tion Village GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G/YA/YCH/F/2017/04 / Component B: Economic Request for Single Stage - One 2017-07- 2017-09- 2017-08- 2017-08- 2018-02- Provide 1400 sheep(70 poor IBRD / 86840 Infrastructure and Services Post Open - National 128,000.00 216,070.23 Signed Quotations Envelope 06 28 31 04 27 Families) Support Component B: Economic G/YA/YC/C/2017/01 / 342 Request for Single Stage - One 2017-10- 2017-12- 2018-05- IBRD / 86840 Infrastructure and Services Post Open - National 130,300.00 0.00 Canceled heads of moggy Quotations Envelope 06 01 30 Support G/B/LY/CF/SYJ/2017/03 / associated equipment of Component B: Economic spawn production Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 172,900.00 0.00 Canceled baseautoclave equipment of Quotations Envelope 06 31 27 Support culture room sun shading facilities Component B: Economic G/YA/YC/C/2018/01 / 342 Request for Single Stage - One 2018-06- 2018-08- 2019-01- IBRD / 86840 Infrastructure and Services Post Open - National 130,300.00 0.00 Canceled heads of moggy Quotations Envelope 06 01 28 Support Component B: Economic G/YA/YC/C/2018/03 / 342 Request for Single Stage - One 2018-10- 2018-12- 2019-05- IBRD / 86840 Infrastructure and Services Post Open - National 130,300.00 0.00 Canceled heads of moggy Quotations Envelope 06 01 30 Support Component B: Economic G/YA/YC/C/2019/01 / 342 Request for Single Stage - One 2019-06- 2019-08- 2020-01- IBRD / 86840 Infrastructure and Services Post Open - National 130,300.00 0.00 Canceled heads of moggy Quotations Envelope 06 01 28 Support G/W/F/D/2018/02 / 1 set Component B: Economic Request for Single Stage - One 2018-04- 2018-04- 2018-10- of cold storage refrigeration IBRD / 86840 Infrastructure and Services Post Open - National 234,100.00 0.00 Canceled Quotations Envelope 01 22 19 equipment Support G/W/F/D/2017/05 / Component B: Economic Stainless steel workbench, Request for Single Stage - One 2017-09- 2017-09- 2018-03- IBRD / 86840 Infrastructure and Services Post Open - National 108,700.00 0.00 Canceled persimmons hang 30 square Quotations Envelope 01 22 21 Support meters, 2.189 million Component B: Economic G/YA/Y/Z/2017/02 / Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 83,800.00 0.00 Canceled Carrier (4) Quotations Envelope 06 31 27 Support Component B: Economic G/W/F/D/2017/03 / Drying Request for Single Stage - One 2017-08- 2017-10- 2018-03- IBRD / 86840 Infrastructure and Services Post Open - National 105,500.00 0.00 Canceled shed 6020 square meters Quotations Envelope 06 01 30 Support G/W/F/D/2017/01 / Component A: Farmer Automatic peeling machines, 2017-04- 2017-04- 2017-05- 2017-12- IBRD / 86840 Cooperative and Value Post Direct Selection Direct 588,800.00 0.00 Canceled drying machines, drying 01 06 11 11 Chain Development. trolleies Component B: Economic G/W/B/F/2018/01 / A cold Request for Single Stage - One 2018-03- 2018-03- 2018-09- IBRD / 86840 Infrastructure and Services Post Open - National 180,100.00 0.00 Canceled storage equipment Quotations Envelope 01 22 18 Support Component B: Economic G/YU/D/Y/2017/02 / little Request for Single Stage - One 2017-10- 2017-12- 2018-05- IBRD / 86840 Infrastructure and Services Post Open - National 127,100.00 0.00 Canceled ewes Quotations Envelope 06 01 30 Support Component B: Economic G/YU/D/Y/2018/01 / little Request for Single Stage - One 2018-09- 2018-11- 2019-04- IBRD / 86840 Infrastructure and Services Post Open - National 169,200.00 0.00 Canceled ewe Quotations Envelope 06 01 30 Support Component B: Economic G/YU/M/L/2018/01 / Request for Single Stage - One 2018-01- 2018-03- 2018-08- IBRD / 86840 Infrastructure and Services Post Open - National 213,400.00 0.00 Canceled donkeys Quotations Envelope 06 03 30 Support Component B: Economic G/YU/M/L/2017/01 / Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Infrastructure and Services Post Open - National 213,400.00 0.00 Canceled donkeys Quotations Envelope 06 31 27 Support G/YA/YC/2018/01 / Yanchuan county. laptop computer3, computer 5, Component D: Project Request for Single Stage - One 2018-07- 2018-09- 2019-03- printer 3, copier 1, camera IBRD / 86840 Management, Monitoring Prior Limited 19,100.00 0.00 Canceled Quotations Envelope 20 14 13 1, fax machine 1, video and Evaluation (M&E). camera 1, projector 1, scanner 1, office software 8 G/YA/Y/2018/01 / Yanchang County, 10 kinds of office suppliers including desktop computers 5, Component C: Technical notebook computers 3, laser Request for Single Stage - One 2018-07- 2018-05- 2018-09- 2018-06- 2019-03- 2018-07- IBRD / 86840 Assistance and Capacity Post Limited 19,100.00 17,706.07 Completed printers 3, photocopier 1, Quotations Envelope 16 21 10 15 09 23 Building Support laser fax machine 1, video projector 1, scanner 1, digital camera 1, video camera 1, and office suite software. G/W/B/2018/01 / Baishui county, 2 sets of equipment Component B: Economic Pending Request for Single Stage - One 2018-07- 2018-08- 2018-09- for biological fermented IBRD / 86840 Infrastructure and Services Post Limited 36,600.00 0.00 Implementat Quotations Envelope 19 06 06 fertilizer in Shiguan project Support ion area. G/W/B/2018/02 / Baishui Component B: Economic Pending county, 1 set of equipment Request for Single Stage - One 2018-07- 2018-09- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 30,500.00 0.00 Implementat for fermented fertilizer pits Quotations Envelope 17 11 10 Support ion in Lingao project area. G/B/LX/2017/01 / Long county, 3 laptop computers, 5 desktop computers, 3 Component B: Economic Pending laser printers, 1 Request for Single Stage - One 2018-07- 2018-09- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 19,100.00 0.00 Implementat photocopier, 1 digital Quotations Envelope 17 11 10 Support ion camera, 1 laser fax machine, 1 video camera, 1 video projector, 1 scanner, 8 suites of office software. G/YU/D/2017/01 / Component D: Project Dingbian county, 3 laptop Request for Single Stage - One 2017-07- 2017-08- 2018-02- IBRD / 86840 Management, Monitoring Post Open - National 6,300.00 0.00 Canceled computers,, 1 camera, 8 Quotations Envelope 06 31 27 and Evaluation (M&E). suites of office software. G/B/LY/2017/01 / Linyou county, 3 laptop computers, 5 desktop computers, 3 Component D: Project Request for Single Stage - One 2017-03- 2017-05- 2017-10- laser printers, 1 photocopier, IBRD / 86840 Management, Monitoring Post Open - National 19,100.00 0.00 Canceled Quotations Envelope 06 01 28 1 digital camera, 1 laser fax and Evaluation (M&E). machine, 1 video camera, 1 video projector, 1 scanner. G/W/H/2017/01 / Heyang County, Notebook computers 3, Desktop computers 5, Scanner 1, Component D: Project Request for Single Stage - One 2017-04- 2017-06- 2017-11- Office suite softwares 8, IBRD / 86840 Management, Monitoring Post Open - National 19,100.00 0.00 Canceled Quotations Envelope 06 01 28 Photocopiers 1, Digital and Evaluation (M&E). camera 1, Laser printer 3, Video projector 1, Digital voice recorder 1, Laser fax machine 1. Page 11 G/W/H/J/2018/01 / Heyang county. 1050mu of drip irrigation: 300mu for Component B: Economic Request for Single Stage - One 2018-01- 2018-03- 2018-09- Diantou village, 150mu for IBRD / 86840 Infrastructure and Services Post Open - National 197,200.00 0.00 Canceled Quotations Envelope 25 22 18 Chengcun village, 100mu for Support Xiaocun village and 500mu for Mengcun village. G/W/H/J/2018/02 / Heyang Component B: Economic Pending Single Stage - One 2018-12- 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- county. 557 acres of new IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 285,400.00 0.00 Implementat Envelope 01 06 17 16 23 19 varieties of apple tree. Support ion G/W/F/D/2017/01A / Component A: Farmer Pending Automatic peeling machines, 2018-08- 2018-08- 2018-09- 2019-04- IBRD / 86840 Cooperative and Value Post Direct Selection Direct 712,500.00 0.00 Implementat drying machines, drying 02 07 11 13 Chain Development. ion trolleies Component D: Project Pending G/SH/2018/01A / Office Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Management, Monitoring Post Limited 124,500.00 0.00 Implementat equipment 176 set Quotations Envelope 07 02 31 and Evaluation (M&E). ion G/W/H/2017/01A / Heyang County, Notebook computers 3, Desktop computers 5, Scanner 1, Component D: Project Request for Single Stage - One 2018-08- 2018-11- 2018-10- 2018-12- 2019-03- 2019-01- Office suite softwares 8, IBRD / 86840 Management, Monitoring Post Limited 19,100.00 17,795.52 Completed Quotations Envelope 07 29 02 21 31 02 Photocopiers 1, Digital and Evaluation (M&E). camera 1, Laser printer 3, Video projector 1, Digital voice recorder 1, Laser fax machine 1. G/W/H/J/2018/01A / Heyang county. 1050mu of drip irrigation: 300mu for Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- Diantou village, 150mu for IBRD / 86840 Infrastructure and Services Post Limited 197,200.00 0.00 Implementat Quotations Envelope 07 02 31 Chengcun village, 100mu for Support ion Xiaocun village and 500mu for Mengcun village. Component B: Economic Pending G/YA/YCH/F/2018/01A / Request for Single Stage - One 2018-08- 2018-10- 2019-03- IBRD / 86840 Infrastructure and Services Post Limited 194,800.00 0.00 Implementat Providing 2130 sheep Quotations Envelope 07 02 31 Support ion G/YU/D/2017/01A / Component D: Project Dingbian county, 3 laptop Request for Single Stage - One 2018-08- 2017-08- 2018-10- 2017-11- 2019-03- 2017-12- IBRD / 86840 Management, Monitoring Post Limited 6,300.00 4,799.03 Completed computers,, 1 camera, 8 Quotations Envelope 07 24 02 22 31 29 and Evaluation (M&E). suites of office software. G/YA/YCH/F/2017/02A / Component A: Farmer Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- Livestock breeding: 100 IBRD / 86840 Cooperative and Value Post Limited 152,400.00 0.00 Implementat Quotations Envelope 07 02 31 rams Chain Development. ion G/B/LY/2017/01A / Linyou county, 3 laptop computers, 5 desktop computers, 3 Component D: Project Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- laser printers, 1 photocopier, IBRD / 86840 Management, Monitoring Post Limited 19,100.00 0.00 Implementat Quotations Envelope 07 02 31 1 digital camera, 1 laser fax and Evaluation (M&E). ion machine, 1 video camera, 1 video projector, 1 scanner. G/W/B/2017/01A / Notebook computers, Desktop computers, Component D: Project Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- Scanners, Office suite IBRD / 86840 Management, Monitoring Post Limited 19,100.00 0.00 Implementat Quotations Envelope 07 02 31 software, Digital cameras, and Evaluation (M&E). ion Video projectors, Printers, Fax machines, Copiers G/YA/YCH/F/2017/06A / Component B: Economic Pending Request for Single Stage - One 2018-08- 2018-10- 2019-03- 100 rams (demonstration IBRD / 86840 Infrastructure and Services Post Limited 152,400.00 0.00 Implementat Quotations Envelope 07 02 31 farms) Support ion G/B/LX/2019/01 / Component B: Economic Pending Request for Single Stage - One 2019-04- 2019-06- 2019-12- Equipment Purchase of 100 IBRD / 86840 Infrastructure and Services Post Limited 36,600.00 0.00 Implementat Quotations Envelope 09 04 01 dustbin Support ion Component B: Economic G/YU/M/2019/01 / 2 HLJK Request for Single Stage - One 2019-04- 2019-06- 2019-06- 2019-07- 2019-12- 2019-08- IBRD / 86840 Infrastructure and Services Post Limited 32,000.00 34,228.57 Completed and 1 tank car equipment Quotations Envelope 09 14 04 15 01 15 Support Component B: Economic Pending G/B/LX/2020/01 / 60 sets Request for Single Stage - One 2020-03- 2020-05- 2020-11- IBRD / 86840 Infrastructure and Services Post Limited 20,100.00 0.00 Implementat of sales booths Quotations Envelope 16 11 07 Support ion G/YA/YC/2018/01A / Yanchuan county. laptop computer3, computer 5, Component D: Project Request for Single Stage - One 2020-04- 2018-05- 2020-06- 2018-08- 2020-11- printer 3, copier 1, camera IBRD / 86840 Management, Monitoring Post Limited 19,100.00 14,061.34 Signed Quotations Envelope 06 24 01 05 28 1, fax machine 1, video and Evaluation (M&E). camera 1, projector 1, scanner 1, office software 8 G/B/LX/SYGP/2021/01 / Refrigeration equipments, Component B: Economic Pending including 2 sets of screw Request for Single Stage - One 2021-02- 2021-04- 2021-10- IBRD / 86840 Infrastructure and Services Post Limited 122,200.00 0.00 Implementat compressor racks, 2 sets of Quotations Envelope 09 06 03 Support ion evaporative condensers, and 18 sets of ceiling coolers. G/B/LX/SYGP/2021/02 / Installation auxiliary Component B: Economic Pending materials, including valves, Request for Single Stage - One 2021-02- 2021-04- 2021-10- IBRD / 86840 Infrastructure and Services Post Limited 53,000.00 0.00 Implementat filters, solenoid valves, Quotations Envelope 09 06 03 Support ion thermal expansion valves, and pressure gauges. G/B/LX/SYGP/2021/03 / Fluorine system materials, including 900m red copper Component B: Economic Pending Request for Single Stage - One 2021-02- 2021-04- 2021-10- pipe, 4010m seamless steel IBRD / 86840 Infrastructure and Services Post Limited 149,300.00 0.00 Implementat Quotations Envelope 09 06 03 pipe, reducing tee, elbow, Support ion flare copper nuts, and 35m³ rubber insulation pipe. G/B/LX/SYGP/2021/04 / Defrosting system materials, Component B: Economic Pending Request for Single Stage - One 2021-02- 2021-04- 2021-10- including 1000m drain pipe, IBRD / 86840 Infrastructure and Services Post Limited 23,700.00 0.00 Implementat Quotations Envelope 09 06 03 144 elbows, tee, head, 300m Support ion electric heating cable, etc. Component B: Economic Pending G/B/LX/SYGP/2021/05 / 14 Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 289,800.00 0.00 Implementat 960¡ insulation board Envelope 05 10 24 23 28 24 Support ion G/B/LX/SYGP/2021/06 / Thermal insulation doors and thermal insulation auxiliary materials and Component B: Economic Pending accessories (14 air curtains Request for Single Stage - One 2021-02- 2021-04- 2021-10- IBRD / 86840 Infrastructure and Services Post Limited 147,700.00 0.00 Implementat and 14 sets of 0.8 double- Quotations Envelope 09 06 03 Support ion sided color steel, collision post, galvanized C-shaped steel, sealing silica gel, foam material, color steel edging, etc.) G/B/LX/SYGP/2021/07 / Electrical system equipments, including 145 sets of electric cabinets, Component B: Economic Pending Request for Single Stage - One 2021-02- 2021-04- 2021-10- power distribution cabinets, IBRD / 86840 Infrastructure and Services Post Limited 154,900.00 0.00 Implementat Quotations Envelope 09 06 03 heating electric controls, Support ion 34890m wire and cable, electrical auxiliary materials, 15 remote monitoring systems, etc. G/YA/YC/YAMYG/2021/01 Component B: Economic Pending / 1 set of 4.0-level Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 853,700.00 0.00 Implementat photoelectric intelligent fruit Envelope 05 10 24 23 28 24 Support ion selection line Component B: Economic Pending G/YA/YC/YAMYG/2021/02 Request for Single Stage - One 2021-02- 2021-04- 2021-10- IBRD / 86840 Infrastructure and Services Post Limited 45,700.00 0.00 Implementat / 4 forklifts Quotations Envelope 10 07 04 Support ion G/B/LY/YMQ/2021/01 / Feeding equipments (544 sets of cages, 5222 meters of automatic drinking water system, 1360 meters of Component B: Economic Pending Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- automatic feeding system, IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 374,600.00 0.00 Implementat Envelope 05 10 24 23 28 24 544 sets of belt-type Support ion manure removal system, 2 sets of lighting systems, 2 sets of ventilation and cooling systems, etc.) Component B: Economic Pending G/YU/D/H/2021/02 / 1324 Single Stage - One 2021-02- 2021-02- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 86840 Infrastructure and Services Post Request for Bids Open - National 403,700.00 0.00 Implementat breeding ewes Envelope 05 10 24 23 28 24 Support ion NON CONSULTING SERVICES Page 12 Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C/SH/2018/02 / studies on Component D: Project Consultant sustainable development Pending 2018-02- 2018-04- 2018-05- 2018-06- 2018-12- IBRD / 86840 Management, Monitoring Post Qualification Open - National 76,200.00 0.00 2018-02-01 under the background of Implementation 22 07 07 11 08 and Evaluation (M&E). Selection relative poverty Component C: Technical Consultant C/SH/2017/07 / Project Under 2017-11- 2017-12- 2018-01- 2018-03- 2018-03- IBRD / 86840 Assistance and Capacity Post Qualification Open - National 182,900.00 0.00 2017-10-20 purchasing agent Implementation 10 24 23 07 07 Building Support Selection C/SH/2017/05 / studies on Component D: Project Consultant Pending 2018-07- 2018-09- 2018-10- 2018-11- 2019-11- cooperatives and ways of IBRD / 86840 Management, Monitoring Post Qualification Open - National 91,500.00 0.00 2018-06-30 Implementation 21 03 03 07 07 poverty alleviation and Evaluation (M&E). Selection Component D: Project Consultant C/SH/2018/04 / Entrust 2018-06- 2018-08- 2018-09- 2018-10- 2019-10- IBRD / 86840 Management, Monitoring Post Qualification Open - National 45,400.00 0.00 Canceled 2018-05-31 training and investigation 21 04 03 08 08 and Evaluation (M&E). Selection C/SH/2017/06 / studies on Component D: Project Consultant ways for supporting 2017-09- 2017-11- 2017-12- 2018-01- 2018-07- IBRD / 86840 Management, Monitoring Post Qualification Open - National 45,700.00 0.00 Canceled 2017-09-01 inclusive finance (including 22 05 05 09 08 and Evaluation (M&E). Selection insurance) in poor areas C/SH/2018/01 / studies on Component D: Project Consultant 2018-02- 2018-04- 2018-05- 2018-06- 2018-12- city and countryside IBRD / 86840 Management, Monitoring Post Qualification Open - National 76,200.00 0.00 Canceled 2018-02-01 22 07 07 11 08 integration of poor areas and Evaluation (M&E). Selection C/SH/2018/03 / studies on Component D: Project Consultant value chain and 2018-02- 2018-04- 2018-05- 2018-06- 2018-12- IBRD / 86840 Management, Monitoring Post Qualification Open - National 45,700.00 0.00 Canceled 2018-02-01 industrialization poverty 22 07 07 11 08 and Evaluation (M&E). Selection alleviation in poor areas Component D: Project C/SH/2017/02 / project Quality And Cost- Under 2018-09- 2018-12- 2018-09- 2019-02- 2020-10- 2019-03- 2019-01- 2019-04- 2019-01- 2019-05- 2019-06- 2020-06- IBRD / 86840 Management, Monitoring Post Open - National 457,300.00 0.00 2018-12-01 monitoring and evaluation Based Selection Implementation 26 22 26 04 22 04 22 03 22 08 12 11 and Evaluation (M&E). C/SH/2020/01 / Research Component D: Project Consultant 2020-06- 2020-06- 2020-07- 2020-08- 2020-08- 2020-10- 2020-09- 2020-11- 2021-03- on Value Chain Construction IBRD / 86840 Management, Monitoring Post Qualification Open - National 18,300.00 21,108.66 Signed 2020-05-18 29 08 22 25 21 20 25 17 24 and Industrial Poverty and Evaluation (M&E). Selection Alleviation C/SH/2020/02A / Study on Component D: Project Consultant the mechanism of poverty 2020-07- 2020-06- 2020-07- 2020-08- 2020-09- 2021-03- IBRD / 86840 Management, Monitoring Post Qualification Open - National 18,300.00 0.00 Under Review 2020-05-18 reduction of farmers' 30 08 22 21 25 24 and Evaluation (M&E). Selection professional cooperatives C/SH/2020/03A / Research Component D: Project Consultant on the Improvement of the 2020-07- 2020-06- 2020-07- 2020-08- 2020-08- 2020-10- 2020-09- 2020-11- 2021-03- IBRD / 86840 Management, Monitoring Post Qualification Open - National 18,300.00 18,355.36 Signed 2020-05-18 Operation Ability of Farmers' 30 08 22 25 21 20 25 16 24 and Evaluation (M&E). Selection Professional Cooperatives C/SH/2020/04A / Research on the Effective Connection Component D: Project Consultant 2020-07- 2020-06- 2020-07- 2020-08- 2020-08- 2020-10- 2020-09- 2020-11- 2021-03- between Sustainable IBRD / 86840 Management, Monitoring Post Qualification Open - National 18,300.00 18,355.36 Signed 2020-05-18 30 08 22 25 21 20 25 13 24 Development and Rural and Evaluation (M&E). Selection Rejuvenation in Poor Areas C/SH/2020/05A / Research on the Development of Component D: Project Consultant 2020-07- 2020-06- 2020-07- 2020-08- 2020-08- 2020-10- 2020-09- 2020-11- 2021-03- Cooperatives in Poor Areas IBRD / 86840 Management, Monitoring Post Qualification Open - National 18,300.00 18,355.36 Signed 2020-05-18 30 08 22 25 21 20 25 13 24 and the Modernization of and Evaluation (M&E). Selection Community Governance Component D: Project Consultant C/SH/2020/06 / Under 2020-12- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 86840 Management, Monitoring Post Qualification Open - National 16,800.00 0.00 2020-11-18 Cooperative Annual Audit Implementation 09 22 21 28 24 and Evaluation (M&E). Selection C/S/2021/01 / Hire a consulting agency to guide the operation and management of cooperatives Component B: Economic Consultant Open - Pending 2021-05- 2021-06- 2021-07- 2021-08- 2022-02- in 3 cities and 6 counties in IBRD / 86840 Infrastructure and Services Post Qualification 266,800.00 0.00 2021-04-16 International Implementation 07 20 20 24 20 Xianyang, Weinan and Baoji, Support Selection and improve the operation and management capabilities of cooperatives C/S/2021/02 / Hire a consulting agency to guide the operation and management of cooperatives Component B: Economic Consultant Open - Pending 2021-05- 2021-06- 2021-07- 2021-08- 2022-02- in 2 cities and 5 counties in IBRD / 86840 Infrastructure and Services Post Qualification 167,700.00 0.00 2021-04-16 International Implementation 07 20 20 24 20 Yulin and Yan'an, and Support Selection improve the operation and management capabilities of cooperatives INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component C: Technical Individual C/YA/YCH/J/2017/01 / 2017-07- 2017-09- 2017-07- 2017-09- 2017-08- 2017-11- 2017-08- 2018-05- IBRD / 86840 Assistance and Capacity Post Consultant Open 9,100.00 1,812.48 Signed 2017-07-20 sheep breeding expert 1 04 07 04 28 04 02 04 01 Building Support Selection Component C: Technical Individual C/YU/D/2017/01 / Animal 2017-05- 2017-06- 2017-07- 2018-05- IBRD / 86840 Assistance and Capacity Post Consultant Open 4,600.00 0.00 Canceled 2017-04-01 husbandary expert 20 10 15 15 Building Support Selection Component C: Technical Individual C/W/H/2017/01 / Project 2017-09- 2017-09- 2017-11- 2018-05- IBRD / 86840 Assistance and Capacity Post Consultant Open 30,500.00 0.00 Canceled 2017-07-20 bidding consultants 2 07 28 02 01 Building Support Selection C/W/2017/01 / 1 Component C: Technical Individual 2017-09- 2017-09- 2017-11- 2018-05- procurement technical IBRD / 86840 Assistance and Capacity Post Consultant Open 4,600.00 0.00 Canceled 2017-07-20 07 28 02 01 expert Building Support Selection Component C: Technical Individual C/W/2017/03 / 1 project 2017-09- 2017-09- 2017-11- 2018-05- IBRD / 86840 Assistance and Capacity Post Consultant Open 4,600.00 0.00 Canceled 2017-07-20 consultant 07 28 02 01 Building Support Selection Component C: Technical Individual C/W/2017/02 / 1 financial 2017-09- 2017-09- 2017-11- 2018-05- IBRD / 86840 Assistance and Capacity Post Consultant Open 4,600.00 0.00 Canceled 2017-07-20 management expert 07 28 02 01 Building Support Selection C/W/H/2017/05 / Component C: Technical Individual 2019-01- 2019-02- 2019-03- 2019-09- Cooperative operation and IBRD / 86840 Assistance and Capacity Post Consultant Open 4,600.00 0.00 Canceled 2018-12-01 19 09 16 12 management 1 consultant Building Support Selection Component C: Technical Individual C/YU/D/2017/02 / animal 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 86840 Assistance and Capacity Post Consultant Open 13,700.00 0.00 Canceled 2018-12-01 husbandman 19 09 16 12 Building Support Selection Component C: Technical Individual C/W/H/2017/02 / Civil 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 86840 Assistance and Capacity Post Consultant Open 4,600.00 0.00 Canceled 2018-12-01 Engineering Consultant 1 19 09 16 12 Building Support Selection Component C: Technical Individual C/W/H/2017/03 / Hydraulic 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 86840 Assistance and Capacity Post Consultant Open 4,600.00 0.00 Canceled 2018-12-01 Engineering Consultant 1 19 09 16 12 Building Support Selection C/W/H/2017/06 / 1 the Component C: Technical Individual 2019-01- 2019-02- 2019-03- 2019-09- cooperative marketing IBRD / 86840 Assistance and Capacity Post Consultant Open 4,600.00 0.00 Canceled 2018-12-01 19 09 16 12 expert Building Support Selection C/B/LY/2017/03 / Component C: Technical Individual 2019-01- 2019-02- 2019-03- 2019-09- consultant expert of IBRD / 86840 Assistance and Capacity Post Consultant Open 7,600.00 0.00 Canceled 2018-12-01 19 09 16 12 cooperative operation Building Support Selection management: 1 Component C: Technical Individual C/YA/YCH/J/2017/04A / Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 9,100.00 0.00 2018-08-02 Project sourcing specialist 1 Implementation 07 28 02 31 Building Support Selection C/B/LY/2017/01A / Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- consultant expert of edible IBRD / 86840 Assistance and Capacity Post Consultant Limited 7,600.00 0.00 2018-08-02 Implementation 07 28 02 31 fungi planting technology: 2 Building Support Selection Component C: Technical Individual C/W/B/2017/02A / 1 Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 9,100.00 0.00 2018-08-02 financial management expert Implementation 07 28 02 31 Building Support Selection Page 13 C/W/H/2017/05A / Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- Cooperative operation and IBRD / 86840 Assistance and Capacity Post Consultant Limited 4,600.00 0.00 2018-08-02 Implementation 07 28 02 31 management 1 consultant Building Support Selection C/W/B/2017/01A / 1 Component C: Technical Individual cooperative consulting Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 8,200.00 0.00 2018-08-02 industry development Implementation 07 28 02 31 Building Support Selection specialist Component D: Project Individual C/SH/2017/04A / social Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Management, Monitoring Post Consultant Limited 76,200.00 0.00 2018-08-02 safety monitoring Implementation 07 28 02 31 and Evaluation (M&E). Selection C/SH/2017/03A / Component D: Project Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- environment safety IBRD / 86840 Management, Monitoring Post Consultant Limited 76,200.00 0.00 2018-08-02 Implementation 07 28 02 31 monitoring and Evaluation (M&E). Selection C/X/C/2017/01A / 1 Component C: Technical Individual cooperative operation Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 4,600.00 0.00 2018-08-02 management consulting Implementation 07 28 02 31 Building Support Selection expert Component C: Technical Individual C/YU/D/2017/02A / animal Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 13,700.00 0.00 2018-08-02 husbandman Implementation 07 28 02 31 Building Support Selection C/YU/D/2017/03A / Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- Cooperative construction IBRD / 86840 Assistance and Capacity Post Consultant Limited 3,000.00 0.00 2018-08-02 Implementation 07 28 02 31 specialist Building Support Selection Component C: Technical Individual C/X/C/2017/03A / 1 Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 3,000.00 0.00 2018-08-02 financial consultant Implementation 07 28 02 31 Building Support Selection C/YA/YCH/J/2017/03A / Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- cooperative management IBRD / 86840 Assistance and Capacity Post Consultant Limited 9,100.00 0.00 2018-08-02 Implementation 07 28 02 31 expert 1 person Building Support Selection C/YA/YCH/J/2017/05A / Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- community financial expert IBRD / 86840 Assistance and Capacity Post Consultant Limited 9,100.00 0.00 2018-08-02 Implementation 07 28 02 31 1 person Building Support Selection Component C: Technical Individual C/W/H/2017/02A / Civil Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 4,600.00 0.00 2018-08-02 Engineering Consultant 1 Implementation 07 28 02 31 Building Support Selection Component C: Technical Individual C/YA/YCH/J/2017/02A / Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 9,100.00 0.00 2018-08-02 apiarist 1 person Implementation 07 28 02 31 Building Support Selection Component C: Technical Individual C/YU/D/2017/04A / Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 1,500.00 0.00 2018-08-02 Financial expert Implementation 07 28 02 31 Building Support Selection C/X/C/2017/02A / 1 the Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- cooperative marketing IBRD / 86840 Assistance and Capacity Post Consultant Limited 7,600.00 0.00 2018-08-02 Implementation 07 28 02 31 expert Building Support Selection C/W/B/2017/03A / Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- engineering consulting IBRD / 86840 Assistance and Capacity Post Consultant Limited 12,200.00 0.00 2018-08-02 Implementation 07 28 02 31 experts 2 Building Support Selection C/W/H/2017/03A / Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- Hydraulic Engineering IBRD / 86840 Assistance and Capacity Post Consultant Limited 4,600.00 0.00 2018-08-02 Implementation 07 28 02 31 Consultant 1 Building Support Selection C/W/H/2017/06A / 1 the Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- cooperative marketing IBRD / 86840 Assistance and Capacity Post Consultant Limited 4,600.00 0.00 2018-08-02 Implementation 07 28 02 31 expert Building Support Selection Component C: Technical Individual C/B/LY/2017/04A / expert Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 7,600.00 0.00 2018-08-02 of cooperative marketing: 1 Implementation 07 28 02 31 Building Support Selection C/W/H/2017/07A / Apple Component C: Technical Individual Pending 2018-08- 2018-08- 2018-10- 2019-03- pest control 1 technical IBRD / 86840 Assistance and Capacity Post Consultant Limited 4,600.00 0.00 2018-08-02 Implementation 07 28 02 31 consulting experts Building Support Selection Component C: Technical Individual C/B/LY/2017/02A / finance Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 4,600.00 0.00 2018-08-02 consultant expert: 1 Implementation 07 28 02 31 Building Support Selection C/B/LY/2017/03A / Component C: Technical Individual consultant expert of Pending 2018-08- 2018-08- 2018-10- 2019-03- IBRD / 86840 Assistance and Capacity Post Consultant Limited 7,600.00 0.00 2018-08-02 cooperative operation Implementation 07 28 02 31 Building Support Selection management: 1 Page 14