12 MONTHS PROCUREMENT PLAN Project information: P163782 - Integrated Water Management and Development Project Project Implementation agency: National Water And Sewerage Corporation AND Ministry of Water and Environment Date of the Procurement Plan: July 2018 Period covered by this Procurement Plan: One year Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, recvised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Paragraph 5.3 of the Procurement Regulations will not apply. When approaching the national market, the country’s own procurement procedures shall not be used due to restrictions on eligibility of otherwise eligible firms to participate in NCB. The Regulations will apply. However, the Borrower may use its own procurement arrangements as set forth in the Public Procurement and Disposal Act, 2003 Request for Quotation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods : Applicable for those contracts identified in the Procurement Plan tables Works: applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information:- (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the IWMDP ): Thresholds*, Procurement Methods, and Prior Review Contract (C) Expenditure Value Procurement Contracts Subject to No Category Threshold* Method Prior Review /[eq. US$] [eq. USD] All contracts at or above USD 10 million are Open Competition subject to international advertising and the International Market use of the Bank’s SPDs (or other C ≥ 10,000,000 Approach and Direct documents agreed with the Bank), as well Contracting as the first contract under Open Competition 1 Works Open Competition 200,000 < C < National Market None except if it is the first contract under 10,000,000 Approach Open Competition. C ≤ 200,000 RfQ None All contracts at or above USD 2 million are Open Competition subject to international advertising and the Goods, IT and International Market use of the Bank’s SPDs (or other 2 non-consulting C ≥ 2,000,000 Approach and Direct documents agreed with the Bank), as well services as the first contract under Open Contracting Competition. Contract (C) Expenditure Value Procurement Contracts Subject to No Category Threshold* Method Prior Review /[eq. US$] [eq. USD] Open Competition : National Market None except if it is the first contract under 100,000 < C < Approach Open Competition. 2,000,000 C ≤ 100,000 RfQ None All contracts at or above USD 300,000 are for subject to international advertising and the C < 300,000 Consulting Services use of the Bank’s SPDs (or other selection of documents agreed with the Bank). 3 consultant firms All contracts at or above USD 300,000 are For Engineering and subject to international advertising and the C ≤ 300,000 Construction Supervision use of the Bank’s SPDs (or other documents agreed with the Bank). Selection of ≥ 300,000 ≥ 300,000 4 Individual All Approaches consultants Training, Workshops, Based on approved This line activity is not subject to 5 Study Tours All Values Annual Work Plan & procurement Review. Budgets (AWPB) by TTL * All contracts not subject to prior review will be post-reviewed. ** Short lists of consultants for services estimated to cost less US$300,000 equivalent per contract may be composed entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. However, if foreign firms have expressed interest, they will not be excluded from consideration. Prior review Thresholds High Substantial Procurement Type Risk Risk Works 5.0 10.0 Goods, It & Non-Consulting 1.5 2.0 Services Consultants (Firms) 0.5 1.0 Individual Consultants 0.2 0.3 Prequalification. Not expected for any works or goods packages in the procurement plan. Proposed Procedures for CDD Components: Applicable Reference to (if any) Project Operational/Procurement Manual: the IWMDP team will prepare a Procurement manuals, which will also be part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Uganda : Integrated Water Management and Development Project PLAN General Information Country: Uganda Bank’s Approval Date of the Original Procurement Plan: 2018-07-10 2021-09-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163782 GPN Date: 2018-05-31 Project Name: Integrated Water Management and Development Project Loan / Credit No: IDA / 62760, / M Executing Agency(ies): inistry of Water and Environment WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned UG-MWE-65387-CW-RFB / Works for Construction of Busia Municipality Water Component 1: WSS in Small Supply and Single Stage - One 10,366,641.0 9,605,671.7 2021-04- IDA / 62760 Towns and RGCs and Support Prior Request for Bids Open - International Signed 2018-10-15 2020-02-29 2018-11-15 2020-07-10 2018-12-27 2020-09-07 2019-02-15 2021-01-04 2019-04-30 2021-02-09 Sanitation/Facilities System, Envelope 0 7 30 to Districts Hosting Refugees Source Protection Measures and Sanitation Facilities in Kumi-Nyero-Ngora UG-MWE-107851-CW-RFB / Construction of 12 monitoring Under Component 3: Water Single Stage - One 2019-11- stations (5No. Ground Water, IDA / 62760 Post Request for Bids Open - National 391,000.00 0.00 Implementat 2019-04-12 2020-10-12 2019-04-24 2020-10-12 2019-06-05 2019-07-05 2019-08-09 Resource Management Envelope 08 5No. Surface water, 2No. ion automatic weather stations). UG-MWE-107829-CW-RFB / Works for Construction of: Lot 1 : Namasale Water Supply and Sanitation System and Sanitation and Koboko Component 1: WSS in Small Under Single Stage - One 2022-01- Sanitation works IDA / 62760 Towns and RGCs and Support Prior Request for Bids Open - International 7,543,256.00 0.00 Implementat 2019-07-31 2021-07-23 2019-08-24 2021-07-28 2019-10-05 2019-11-17 2020-01-25 Envelope 25 Lot 2: Kaliro - Namungalwe to Districts Hosting Refugees ion Water Supply and Sanitation System Lot 3: Sanitation works for Rukungiri Municipality UG-MWE-162979-CW-DIR / Component 1: WSS in Small Under 2020-10- Works for drilling and Testing IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 186,285.00 0.00 Implementat 2020-03-10 2020-03-09 2020-03-15 2020-04-30 27 of 17No. wells in RGCs to Districts Hosting Refugees ion UG-MWE-173602-CW-RFB / Works for drilling and test pumping of production Component 1: WSS in Small Pending boreholes for 20 sites in the Single Stage - One 2021-03- IDA / 62760 Towns and RGCs and Support Post Request for Bids Open - National 438,947.00 0.00 Implementat 2020-05-25 2020-06-11 2020-07-02 2020-08-03 2020-09-07 refugees settlements and host Envelope 06 to Districts Hosting Refugees ion communities in the districts of Kiryandongo, Arua, Moyo, Adjumani, Lamwo and Yumbe UG-MWE-211703-CW-RFB / Contract for Dredging and Component 3: Water Single Stage - One 2021-04- Flood Protection Works in IDA / 62760 Post Request for Bids Limited 4,008,000.00 0.00 Canceled 2021-01-07 2021-01-12 2021-02-05 2021-02-26 2021-04-02 Resource Management Envelope 12 upper mid stream River Nyamwamba UG-MWE-211704-CW-RFB / Contract for Dredging and Component 3: Water Single Stage - One 2021-07- IDA / 62760 Post Request for Bids Limited 3,592,500.00 0.00 Canceled 2021-01-07 2021-01-12 2021-02-05 2021-02-26 2021-04-02 Flood Protection Works in Resource Management Envelope 31 lower River Nyamwamba UG-MWE-244336-CW-RFB / Emergency Maintenance of Request for Bids - River Nyamwamba for Flood Pending Component 3: Water Single Stage - One Small Works SPD 2022-08- Mitigation against Damage of IDA / 62760 Post Request for Bids Limited 4,400,000.00 0.00 Implementat 2021-08-23 2021-08-27 2021-10-08 2021-11-07 2021-12-12 Resource Management Envelope (1 envelope 09 Critical Infrastructure and ion process) Loss of Livelihoods in Kasese District GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-65595-GO-RFB / Supply and Installation under the Umbrella Authorities of: Component 1: WSS in Small Pending Single Stage - One Lot 1: Pipes and Fittings / Towns and RGCs and Support Post Request for Bids Open - International 1,869,000.00 0.00 Implementati 2018-12-31 2019-02-01 2019-03-15 2019-04-28 2019-06-02 2019-11-29 Envelope (150,000m) to Districts Hosting Refugees on Lot 2: 500 Bulk and 30,000 domestic meters UG-MWE-65550-GO-RFB / Supply and Installation of: Lot 1: hydrometric equipment namely (5No. Ground Water, Under 5No. Surface water, 2No. Component 3: Water Single Stage - One IDA / 62760 Post Request for Bids Open - International 1,345,000.00 0.00 Implementati 2019-04-15 2020-07-16 2019-05-02 2020-07-28 2019-06-13 2019-07-19 2019-09-06 2020-09-04 automatic weather stations). Resource Management Envelope on Lot 2: Establishment of 3no. automatic precipitation and 2no. dry deposition monitoring stations UG-MWE-107838-GO-RFB / Component 4: Project Under Procurement of Project Request for Single Stage - One IDA / 62760 Implementation and Post Limited 624,000.00 387,480.33 Implementati 2019-04-30 2019-07-04 2019-07-09 2020-01-05 Vehicles- 13N0. - 4WD pickup Quotations Envelope Institutional Strengthening on trucks Page 1 UG-MWE-107841-GO-RFQ / Procurement of IT equipment for Project Implementation : Component 4: Project Pending 20No.Laptops, 2No.Printers, Request for Single Stage - One IDA / 62760 Implementation and Post Limited 98,000.00 0.00 Implementati 2019-04-25 2019-07-12 2019-10-11 2No.Projectors, 1No. Quotations Envelope Institutional Strengthening on Photocopier, 4No. still cameras and 25No. GPS machines UG-MWE-130166-GO-RFB / Supply of 25,000 micro and Component 1: WSS in Small Under Bulk Water Meters for Single Stage - One IDA / 62760 Towns and RGCs and Support Post Request for Bids Open - National 551,000.00 0.00 Implementati 2019-09-13 2020-07-15 2019-09-23 2020-07-20 2019-10-16 2019-11-15 2019-12-20 2022-12-19 Umbrellas of Water and Envelope to Districts Hosting Refugees on Sanitation under Framework Agreement UG-MWE-113671-GO-RFQ / Supply and Installation of 60 Component 1: WSS in Small units of Electro-Mechanical Single Stage - One IDA / 62760 Towns and RGCs and Support Post Request for Bids Open - National 496,000.00 0.00 Canceled 2019-05-20 2019-05-31 2019-07-01 2019-07-24 2019-08-28 2022-08-26 equipment for Umbrella Water Envelope to Districts Hosting Refugees and Sanitation Authority under Framework Agreement UG-MWE-113661-GO-RFB / Supply of 200,000m Pipes and Component 1: WSS in Small Single Stage - One Fittings for Umbrellas of Water IDA / 62760 Towns and RGCs and Support Prior Request for Bids Open - National 1,700,000.00 0.00 Canceled 2020-02-24 2020-04-24 2020-03-09 2020-07-24 2020-04-09 2020-08-26 2020-05-09 2020-06-13 2023-06-13 Envelope and Sanitation under Frame to Districts Hosting Refugees Work Agreement. UG-MWE-113654-GO-DIR / Supply of 25,000 Micro and Component 1: WSS in Small Bulk Water Meters for IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 551,000.00 0.00 Canceled 2019-05-20 2019-05-31 2019-08-09 2022-08-08 Umbrellas of Water and to Districts Hosting Refugees Sanitation under Framework Agreement UG-MWE-164748-GO-RFB / Supply of Technical Equipment for Regional Laboratories: Lot 1:Assorted Laboratory Analytical Equipment Under Component 3: Water Single Stage - One Lot 2:Assorted Laboratory IDA / 62760 Post Request for Bids Open - International 800,000.00 0.00 Implementati 2020-04-09 2020-07-19 2021-01-15 Resource Management Envelope Processing,Containment on &Storage Equipment Lot 3:Assorted Field Equipment Lot 4:Assorted Laboratory Apparatus & Glassware UG-MWE-183001-GO-RFB / Supply, Installation, Upgrading, Commissioning Under Component 3: Water and Maintaining the Water IDA / 62760 Prior Direct Selection Direct 2,900,000.00 3,189,374.00 Implementati 2020-07-13 2020-08-31 2020-08-03 2020-11-23 2020-10-15 2024-03-28 Resource Management Information System phase II on for the Government of the Republic of Uganda. UG-MWE-186158-GO-RFQ / Component 4: Project Pending Request for Single Stage - One Procurement of Video IDA / 62760 Implementation and Post Limited 60,000.00 0.00 Implementati 2020-08-12 2020-09-21 2020-12-20 Quotations Envelope Conferencing equipment Institutional Strengthening on UG-MWE-211705-GO-DIR / Pending Supply and Installation of Component 3: Water IDA / 62760 Post Direct Selection Direct 60,000.00 0.00 Implementati 2021-01-07 2021-01-12 2021-02-16 2021-06-16 flood early warning systems Resource Management on on River Nyamwamba UG-MWE-228573-GO-RFB / Supply of Pipes and Fittings for Umbrella Authorities under: Lot 1(498,000m of pipes for Component 1: WSS in Small Under Single Stage - One Wakiso & Kyenjojo) , Lot IDA / 62760 Towns and RGCs and Support Prior Request for Bids Open - International 2,400,000.00 0.00 Implementati 2021-04-16 2021-06-01 2021-04-28 2021-06-11 2021-06-09 2021-07-15 2021-07-09 2021-08-13 2024-08-12 Envelope 2(498,000m of pipe for Lira & to Districts Hosting Refugees on Mbale), Lot 3 (249,000m of pipes for Kabale) and Lot 4 (Supply of fittings for the five Umbrella Authorities) UG-MWE-241168-GO-RFB / Supply and Installation of: Lot 1: hydrometric equipment(5No. Ground Pending Component 3: Water Single Stage - One Water, 5No. Surface water, IDA / 62760 Post Request for Bids Open - International 735,000.00 0.00 Implementati 2021-08-06 2021-08-11 2021-09-08 2021-10-01 2021-11-05 2022-11-05 Resource Management Envelope 2No. automatic weather on stations). Lot 2: Hydromet Modeling Unit and Security Equipment(Assorted) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-65819-NC-RFB / Implementation of priority WRM measures in: Lot 1: Lwakhakha sub- Under Component 3: Water Single Stage - One catchment IDA / 62760 Prior Request for Bids Open - International 9,094,000.00 0.00 Implementati 2019-01-15 2020-09-30 2019-02-15 2020-10-08 2019-03-29 2020-11-23 2019-05-10 2021-09-29 2019-07-05 2020-12-31 Resource Management Envelope Lot 2: Aswa II sub-catchment on Lot 3: Kochi sub-catchment Lot 4: Middle Awoja sub- catchment UG-MWE-130162-NC-RFP / Non Consultancy Services for Component 1: WSS in Small Pending Request for Single Stage - Two Development of an Online IDA / 62760 Towns and RGCs and Support Post Limited 50,000.00 0.00 Implementati 2019-09-13 2019-09-18 2019-10-10 2019-12-09 2020-01-13 2020-05-12 Proposals Envelope M&E Progress Reporting to Districts Hosting Refugees on System Page 2 UG-MWE-113664-NC-RFB / Labor requirement for the installation of pipes, fittings and water meters for Umbrella Component 1: WSS in Small Pending Water & Sanitation Authorities Single Stage - One IDA / 62760 Towns and RGCs and Support Post Request for Bids Open - National 619,000.00 0.00 Implementati 2019-05-31 2019-06-12 2019-07-17 2019-08-16 2019-09-20 2022-09-19 under Framework Agreements Envelope to Districts Hosting Refugees on in : Lo1: Central, Lot 2: Eastern, Lot 3: South Western, Lot 4: Mid-Western and Lot 5: Northern UG-MWE-162982-NC-RFQ / Non Consulting services to Component 1: WSS in Small Pending under take the printing and Request for Single Stage - One IDA / 62760 Towns and RGCs and Support Post Limited 30,000.00 0.00 Implementati 2020-03-14 2020-04-14 2020-10-11 binding of the bidding and Quotations Envelope to Districts Hosting Refugees on other related documents under IWMDP. UG-MWE-211654-NC-RFB / Implementation of priority Under Component 3: Water Single Stage - One catchment management IDA / 62760 Post Request for Bids Limited 1,300,000.00 0.00 Implementati 2021-01-07 2021-02-25 2021-01-12 2021-02-25 2021-02-04 2021-02-25 2021-04-01 2021-10-28 Resource Management Envelope measures in upstream on Nyamwamba UG-MWE-211697-NC-RFB / Implementation of priority Under Component 3: Water Single Stage - One catchment management IDA / 62760 Post Request for Bids Limited 1,500,000.00 0.00 Implementati 2021-01-07 2021-02-25 2021-01-12 2021-02-25 2021-02-04 2021-02-25 2021-04-01 2021-10-28 Resource Management Envelope measures in Midstream on Nyamwamba UG-MWE-211698-NC-RFB / Implementation of priority Under Component 3: Water Single Stage - One catchment management IDA / 62760 Post Request for Bids Limited 1,200,000.00 0.00 Implementati 2021-01-07 2021-02-25 2021-01-12 2021-02-25 2021-02-04 2021-02-25 2021-04-01 2021-10-28 Resource Management Envelope measures in downstream on Nyamwamba CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-65575-CS-QCBS / Preparation of Albert WMZ Component 3: Water Quality And Cost- Under / Prior Open - International 1,500,000.00 0.00 2018-09-28 2019-06-11 2018-10-26 2019-08-02 2018-12-21 2020-04-03 2019-01-18 2020-06-29 2019-02-17 2021-02-22 2019-03-28 2019-05-08 2020-05-07 Water Resources Strategy and Resource Management Based Selection Implementation Action Plan UG-MWE-65391-CS-QCBS / Consultancy Services for Component 1: WSS in Small Quality And Cost- Under Construction Supervision of IDA / 62760 Towns and RGCs and Support Prior Open - National 490,000.00 0.00 2018-10-25 2018-08-25 2018-11-22 2018-10-29 2019-01-05 2019-05-16 2019-02-06 2019-09-05 2019-03-08 2020-08-06 2019-04-12 2021-06-09 2019-06-07 2020-12-07 Based Selection Implementation Water Supply and Sanitation to Districts Hosting Refugees Systems in Busia UG-MWE-107835-CS-QCBS / Consultancy Services for Feasibility, Detailed Component 1: WSS in Small Engineering Design and Quality And Cost- Under IDA / 62760 Towns and RGCs and Support Prior Open - International 650,000.00 0.00 2019-05-17 2019-07-21 2019-06-14 2019-08-14 2019-07-28 2021-03-14 2019-08-25 2020-08-06 2019-09-24 2021-03-15 2019-10-29 2021-08-26 2019-12-03 2021-12-02 Construction Supervision of Based Selection Implementation to Districts Hosting Refugees Water Supply and Sanitation System in Kyegegwa-Mpara- Ruyonza UG-MWE-65546-CS-QCBS / LOT 1: Preparation of 2 Component 3: Water Quality And Cost- Under Catchment Management Plans IDA / 62760 Prior Open - International 2,850,000.00 0.00 2019-05-17 2019-06-11 2019-06-14 2019-08-02 2019-08-09 2020-04-27 2019-09-06 2020-06-29 2019-10-06 2021-02-15 2019-11-14 2021-08-18 2019-12-25 2020-12-24 Resource Management Based Selection Implementation for Nyamugasani & Kafu in Albert WMZ. UG-MWE-113265-CS-QCBS / LOT 2: Preparation of 2 Component 3: Water Quality And Cost- Under Catchment Management Plans IDA / 62760 Prior Open - International 2,850,000.00 0.00 2019-05-17 2019-06-11 2019-06-14 2019-08-04 2019-07-28 2020-06-18 2019-08-25 2020-06-29 2019-09-24 2021-02-15 2019-10-29 2019-12-03 2020-12-02 Resource Management Based Selection Implementation for Sezibwa and Okweng in Kyoga WMZ UG-MWE-113859-CS-CQS / Lot 1: Feasibility Study, Detailed Engineering Design and Construction Supervision Component 1: WSS in Small Quality And Cost- Under of Solar Powered Piped Water IDA / 62760 Towns and RGCs and Support Prior Open - International 642,000.00 0.00 2019-05-13 2019-05-22 2019-05-27 2019-08-14 2019-07-10 2020-07-26 2019-07-31 2020-09-03 2019-08-30 2021-06-10 2019-10-04 2019-11-08 2022-02-07 Based Selection Implementation Supply Systems and Sanitation to Districts Hosting Refugees Facilities in Refugee Settlements and Host Districts Arua and Moyo UG-MWE-113876-CS-QCBS / Lot 2: Feasibility Study, Detailed Engineering Design and Construction Supervision Component 1: WSS in Small Quality And Cost- Under of Solar Powered Piped Water IDA / 62760 Towns and RGCs and Support Prior Open - International 735,000.00 0.00 2019-05-13 2019-05-22 2019-05-27 2019-08-14 2019-07-10 2020-07-26 2019-07-31 2020-09-03 2019-08-30 2021-06-10 2019-10-04 2019-11-08 2022-02-07 Based Selection Implementation Supply Systems and Sanitation to Districts Hosting Refugees Facilities in Refugee Settlements and Host District of Yumbe UG-MWE-113877-CS-QCBS / Lot 3: Feasibility Study, Detailed Engineering Design and Construction Supervision Component 1: WSS in Small Quality And Cost- Under of Solar Powered Piped Water IDA / 62760 Towns and RGCs and Support Prior Open - International 730,000.00 0.00 2019-05-13 2019-05-22 2019-05-27 2020-01-31 2019-07-10 2020-07-26 2019-07-31 2020-09-03 2019-08-30 2021-06-11 2019-10-04 2019-11-08 2022-02-07 Based Selection Implementation Supply Systems and Sanitation to Districts Hosting Refugees Facilities in Refugee Settlements and Host Districts of Adjumani and Lamwo UG-MWE-107833-CS-QCBS / Consultancy Services for Construction Supervision of Water Supply and Sanitation Component 1: WSS in Small Quality And Cost- Systems in (a) Namasale and IDA / 62760 Towns and RGCs and Support Prior Open - International 500,000.00 0.00 Under Review 2019-05-24 2019-06-19 2019-06-21 2019-08-02 2019-08-04 2020-12-22 2019-09-01 2021-01-28 2019-10-01 2019-11-05 2019-12-10 2021-12-09 Based Selection Sanitation Facilities in koboko to Districts Hosting Refugees (b)Kaliro-Namungalwe and (c) Sanitation Facilities in Rukungiri Page 3 UG-MWE-115609-CS-CQS / Consultancy Services for Component 1: WSS in Small Consultant Design Review and Under IDA / 62760 Towns and RGCs and Support Post Qualification Open - International 314,000.00 0.00 2019-05-27 2019-06-05 2019-06-10 2019-06-24 2019-07-24 2020-01-23 2019-08-23 2019-09-27 2021-09-26 construction services for Implementation to Districts Hosting Refugees Selection Bitsya Water Supply and Sanitation system UG-MWE-65450-CS-QCBS / LOT 1: Consultancy Services Component 1: WSS in Small Quality And Cost- for design review and IDA / 62760 Towns and RGCs and Support Prior Open - International 730,000.00 0.00 Canceled 2019-05-10 2019-05-26 2019-07-09 2019-08-11 2019-09-12 2019-10-17 2019-11-21 2021-11-20 Based Selection Construction Supervision for to Districts Hosting Refugees Nyamugasani GFS UG-MWE-117147-CS-QCBS / Consultancy Services for Component 1: WSS in Small Quality And Cost- Under design review and IDA / 62760 Towns and RGCs and Support Prior Open - International 730,000.00 0.00 2019-06-04 2019-06-05 2019-06-11 2019-06-28 2019-07-25 2020-07-26 2019-08-26 2020-09-01 2019-09-25 2021-04-15 2019-10-23 2021-08-19 2019-11-27 2021-11-26 Based Selection Implementation Construction Supervision for to Districts Hosting Refugees Nyamugasani GFS UG-MWE-113032-CS-CQS / LOT 2: Consultancy Services Component 1: WSS in Small Consultant for Design Review and IDA / 62760 Towns and RGCs and Support Post Qualification Open - International 314,000.00 0.00 Canceled 2019-05-09 2019-05-07 2019-05-30 2019-07-13 2019-08-12 2019-09-16 2021-09-15 construction services for to Districts Hosting Refugees Selection Bitsya Water Supply and Sanitation system UG-MWE-113883-CS-QCBS / Lot 4: Feasibility Study, Detailed Engineering Design and Construction Supervision Component 1: WSS in Small Consultant of Solar Powered Piped Water IDA / 62760 Towns and RGCs and Support Post Qualification Open - International 345,000.00 0.00 Canceled 2019-05-13 2019-05-21 2019-05-27 2019-07-10 2019-07-31 2019-09-04 2022-02-07 Supply Systems and Sanitation to Districts Hosting Refugees Selection Facilities in Refugee Settlements and Host Districts of Kiryandongo UG-MWE-117157-CS-CQS / Consultancy services for Feasibility Study, Detailed Engineering Design and Component 1: WSS in Small Consultant Construction Supervision of Under IDA / 62760 Towns and RGCs and Support Post Qualification Open - International 345,000.00 0.00 2019-06-04 2019-06-05 2019-06-11 2019-08-14 2019-07-25 2020-01-24 2019-08-24 2019-09-28 2021-09-27 Solar Powered Piped Water Implementation to Districts Hosting Refugees Selection Supply Systems and Sanitation Facilities in Refugee Settlements and Host Districts of Kiryandongo UG-MWE-117161-CS-QCBS / Consultancy Services for quantification of the available Component 3: Water Quality And Cost- Under IDA / 62760 Prior Open - International 2,000,000.00 0.00 2019-06-17 2019-08-01 2019-07-01 2019-10-29 2019-08-14 2020-06-09 2019-09-11 2020-08-04 2019-10-04 2020-12-17 2019-11-01 2021-07-12 2019-12-06 2020-12-05 groundwater and assessment Resource Management Based Selection Implementation of sustainability of groundwater development UG-MWE-113950-CS-CQS / Consultancy Services to conduct Sanitation & giene Promotion/Training on O & M of Sanitation Facilities in Component 1: WSS in Small Consultant Busia, Kumi-Ngora-Nyero, IDA / 62760 Towns and RGCs and Support Post Qualification Open - National 250,000.00 0.00 Canceled 2019-05-14 2019-05-20 2019-05-28 2019-07-04 2019-07-29 2019-09-02 2020-09-02 Rukungiri, Koboko, to Districts Hosting Refugees Selection Namungalwe-Kaliro, Namasale, Kyegegwa-Mpara- Ruyonza &Towns of Busolwe- Kadama-Tirinyi-Kibuku- Butaleja UG-MWE-127198-CS-QCBS / Consultancy Services to conduct community Component 1: WSS in Small engagement, Sanitation & Quality And Cost- IDA / 62760 Towns and RGCs and Support Prior Open - National 600,000.00 0.00 Canceled 2019-08-19 2019-09-02 2019-11-15 2019-12-13 2020-01-12 2020-02-16 2020-03-22 2022-12-12 hygiene Promotion/Training Based Selection to Districts Hosting Refugees on O & M of Sanitation Facilities in small towns under IWMDP UG-MWE-127207-CS-CQS / Consultancy services for Component 1: WSS in Small Consultant preparation of Towns IDA / 62760 Towns and RGCs and Support Post Qualification Open - National 450,000.00 0.00 Canceled 2019-08-20 2019-09-04 2019-09-03 2019-10-17 2019-11-16 2019-12-21 2020-06-18 Sanitation plans for Small to Districts Hosting Refugees Selection towns(18 No) under IWMDP UG-MWE-127221-CS-QCBS / Consultancy Services for Component 1: WSS in Small Construction Supervision of Quality And Cost- IDA / 62760 Towns and RGCs and Support Prior Open - International 1,500,000.00 0.00 Under Review 2019-08-19 2019-09-27 2019-09-09 2020-08-30 2019-11-06 2019-12-04 2020-01-03 2020-02-07 2020-03-13 2021-03-08 Large Solar Powered Water Based Selection to Districts Hosting Refugees Supply and Sanitation Systems in 32 RGCS UG-MWE-118949-CS-CQS / Consultancy Services for Component 1: WSS in Small Consultant Development of an Online IDA / 62760 Towns and RGCs and Support Post Qualification Open - National 50,000.00 0.00 Canceled 2019-07-22 2019-08-05 2019-09-18 2019-10-18 2019-11-22 2020-05-20 M&E Progress Reporting to Districts Hosting Refugees Selection System UG-MWE-121827-CS-CQS / Consultancy Services for the Component 1: WSS in Small Consultant Professionalization of IDA / 62760 Towns and RGCs and Support Prior Qualification Open - International 750,000.00 0.00 Canceled 2019-07-31 2019-08-21 2019-10-04 2019-11-03 2019-12-08 2020-12-07 Umbrellas of Water and to Districts Hosting Refugees Selection Sanitation UG-MWE-130406-CS-CQS / Consultancy Services for Stakeholder Engagement, Component 1: WSS in Small Quality And Cost- Under Environment and Social Risk IDA / 62760 Towns and RGCs and Support Prior Open - National 1,150,000.00 0.00 2019-09-16 2020-07-13 2019-10-07 2020-11-25 2019-11-20 2019-12-18 2020-01-17 2020-02-21 2020-03-27 2022-03-27 Based Selection Implementation Management for Nyamugasani to Districts Hosting Refugees and Bistya Gravity Flow Schemes UG-MWE-130593-CS-CQS / Consultancy Services for Consultant Development and Component 3: Water IDA / 62760 Post Qualification Open - National 240,000.00 0.00 Canceled 2019-09-12 2019-10-03 2019-11-16 2019-12-16 2020-01-20 2020-07-18 Implementation of Micro- Resource Management Selection Catchment Management Plans for Refugee Settlements Page 4 UG-MWE-145127-CS-CQS / LOT 1: Preparation of 2 Micro Catchment Management Plans Component 3: Water Quality And Cost- Under IDA / 62760 Post Open - International 335,000.00 0.00 2019-11-15 2019-11-19 2019-12-06 2020-02-20 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2020-11-22 for Selected Micro Catchment Resource Management Based Selection Implementation around Water Sources in Ora and Anyau Sub Catchments UG-MWE-145128-CS-CQS / LOT 2: Preparation of 2 Micro Catchment Management Plans Component 3: Water Quality And Cost- Under for Selected Micro Catchment IDA / 62760 Post Open - International 335,000.00 0.00 2019-11-15 2019-11-19 2019-12-06 2020-02-20 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2020-11-22 Resource Management Based Selection Implementation around Water Sources in Laropi and Ayugi Sub Catchments UG-MWE-145129-CS-CQS / LOT 3: Preparation of 2 Micro Catchment Management Plans Component 3: Water Quality And Cost- Under for Selected Micro Catchment IDA / 62760 Post Open - International 335,000.00 0.00 2019-11-15 2019-11-19 2019-12-06 2020-02-20 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2020-11-22 Resource Management Based Selection Implementation around Water Sources in Nyimur and Mutunda Sub Catchments UG-MWE-146154-CS-FBS / Lot 1: Consultancy Services to Conduct Community Engagement, Town Sanitation Planning, Sanitation and Component 1: WSS in Small Quality And Cost- Under Hygiene Promotion, Training IDA / 62760 Towns and RGCs and Support Post Open - International 350,000.00 0.00 2019-11-22 2020-07-30 2019-12-13 2020-10-14 2020-01-26 2020-02-23 2020-03-24 2020-04-28 2020-06-02 2022-06-02 Based Selection Implementation on Operation and to Districts Hosting Refugees Maintenance of Sanitation Facilities in Small Towns of: Koboko, Namasale, and cluster of Kumi-Ngora-Nyero. UG-MWE-146193-CS-QCBS / Lot 2: Consultancy Services to Conduct Community Engagement, Town Sanitation Planning, Sanitation and Component 1: WSS in Small Quality And Cost- Under Hygiene Promotion, Training IDA / 62760 Towns and RGCs and Support Post Open - International 350,000.00 0.00 2019-11-22 2020-07-30 2019-12-13 2020-10-14 2020-01-26 2020-02-23 2020-03-24 2020-04-28 2020-06-02 2022-05-23 Based Selection Implementation on Operation and to Districts Hosting Refugees Maintenance of Sanitation Facilities in Small Towns of: Rukungiri and the cluster of Kyegegwa-Mpara-Ruyonza UG-MWE-146194-CS-QCBS / Lot 3: Conduct Community Engagement, Town Sanitation Planning, Sanitation and Hygiene Promotion, Training Component 1: WSS in Small Quality And Cost- Under on Operation and IDA / 62760 Towns and RGCs and Support Post Open - International 350,000.00 0.00 2019-11-22 2020-07-30 2019-12-13 2020-10-14 2020-01-26 2020-02-23 2020-03-24 2020-04-28 2020-06-02 2022-05-23 Based Selection Implementation Maintenance of Sanitation to Districts Hosting Refugees Facilities in Small Towns of: Busia, Namungalwe-Kaliro, Busolwe, Butaleja, Kadama- Tirinyi-Kibuku- Budaka UG-MWE-160277-CS-CQS / LOT 1: Consultancy Services Consultant for Technical Supervision of Component 3: Water Under IDA / 62760 Post Qualification Open - National 218,500.00 0.00 2020-02-24 2020-09-28 2020-03-09 2020-10-19 2020-04-22 2020-05-22 2020-06-26 2020-12-23 Implementation of Catchment Resource Management Implementation Selection Management Measures in Lwakhakha Sub Catchment UG-MWE-160279-CS-CQS / LOT 2: Consultancy Services Consultant for Technical Supervision of Component 3: Water Under IDA / 62760 Post Qualification Open - National 293,254.00 0.00 2020-02-24 2020-09-28 2020-03-09 2020-10-19 2020-04-22 2020-05-22 2020-06-26 2020-12-23 Implementation of Catchment Resource Management Implementation Selection Management Measures in Aswa II Sub Catchment UG-MWE-160280-CS-CQS / LOT 3: Consultancy Services Consultant for Technical Supervision of Component 3: Water Under IDA / 62760 Post Qualification Open - National 297,254.00 0.00 2020-02-24 2020-09-28 2020-03-09 2020-10-19 2020-04-22 2020-05-22 2020-06-26 2020-12-23 Implementation of Catchment Resource Management Implementation Selection Management Measures in Kochi Sub Catchment UG-MWE-160281-CS-CQS / LOT 4: Consultancy Services for Technical Supervision of Consultant Component 3: Water Under Implementation of Catchment IDA / 62760 Post Qualification Open - National 296,378.00 0.00 2020-02-24 2020-09-28 2020-03-09 2020-10-19 2020-04-22 2020-05-22 2020-06-26 2020-12-23 Resource Management Implementation Management Measures in Selection Middle/lower Awoja Sub Catchment UG-MWE-182398-CS-CQS / Consultancy Services for Component 4: Project Consultant Under strengthening and capacity IDA / 62760 Implementation and Post Qualification Open - National 160,000.00 0.00 2020-07-13 2020-07-16 2020-07-27 2020-09-09 2020-10-09 2020-11-13 2021-05-12 Implementation building for the Regional Institutional Strengthening Selection Water Utility Regulation Units UG-MWE-130191-CS-QCBS / Component 1: WSS in Small Consultancy Services for Quality And Cost- IDA / 62760 Towns and RGCs and Support Prior Open - International 2,225,000.00 0.00 Canceled 2019-09-16 2019-12-13 2019-10-07 2019-11-20 2019-12-18 2020-01-17 2020-02-21 2020-03-27 2024-03-26 Professionalization of Based Selection to Districts Hosting Refugees Umbrella Authorities UG-MWE-193868-CS-QCBS / Component 1: WSS in Small Consultancy Services for Quality And Cost- Under IDA / 62760 Towns and RGCs and Support Prior Open - International 2,225,000.00 0.00 2020-09-30 2020-09-28 2020-10-02 2020-09-30 2020-11-15 2021-07-27 2020-12-13 2021-01-12 2021-02-16 2021-03-23 2023-03-23 Professionalization of Based Selection Implementation to Districts Hosting Refugees Umbrella Authorities UG-MWE-196155-CS-CQS / LOT 1: Consultancy Services for Stakeholder Engagement, Environment and Social Risk Component 1: WSS in Small Consultant Management for Large Solar IDA / 62760 Towns and RGCs and Support Post Qualification Open - National 342,000.00 0.00 Canceled 2020-09-30 2020-10-27 2020-10-21 2020-12-04 2021-01-03 2021-02-07 2023-02-07 Powered Water Supply and to Districts Hosting Refugees Selection Sanitation Systems in Rural Growth Centres - Western region (12 solar powered water supply systems) Page 5 UG-MWE-196157-CS-CQS / Lot 2: Consultancy Services for Stakeholder Engagement, Environment and Social Risk Component 1: WSS in Small Consultant Management for Large Solar IDA / 62760 Towns and RGCs and Support Post Qualification Open - National 313,000.00 0.00 Canceled 2020-09-30 2020-10-27 2020-10-21 2020-12-04 2021-01-03 2021-02-07 2023-02-07 Powered Water Supply and to Districts Hosting Refugees Selection Sanitation Systems in Rural Growth Centres -Central region (11 solar powered water supply systems) UG-MWE-196161-CS-CQS / Lot 3: Consultancy Services for Stakeholder Engagement, Environment and Social Risk Component 1: WSS in Small Consultant Management for Large Solar IDA / 62760 Towns and RGCs and Support Post Qualification Open - National 255,000.00 0.00 Canceled 2020-09-30 2020-10-27 2020-10-21 2020-12-04 2021-01-03 2021-02-07 2023-02-07 Powered Water Supply and to Districts Hosting Refugees Selection Sanitation Systems in Rural Growth Centres - Eastern region (9 solar powered water supply systems) UG-MWE-223396-CS-CQS / Consultancy Services to undertake the Stakeholder Component 1: WSS in Small Consultant engagement , Environment Under IDA / 62760 Towns and RGCs and Support Post Qualification Limited 241,211.00 0.00 2021-03-12 2021-08-18 2021-03-26 2021-04-25 2021-05-30 2021-11-26 and Risk for Solar Powered Implementation to Districts Hosting Refugees Selection water supply and sanitation systems in Refugee Hosting District of Kiryandongo. UG-MWE-228559-CS-QCBS / LOT 1: Consultancy Services for Stakeholder Engagement, Environment and Social Risk Component 1: WSS in Small Management for Large Solar Quality And Cost- Under IDA / 62760 Towns and RGCs and Support Prior Open - National 964,845.00 0.00 2021-04-16 2021-09-29 2021-05-07 2021-06-20 2021-07-18 2021-08-17 2021-09-21 2021-10-26 2023-10-26 Powered Water Supply and Based Selection Implementation to Districts Hosting Refugees Sanitation Systems in Rural Growth Centers - Western region (12 solar powered water supply systems) UG-MWE-228562-CS-QCBS / Lot 2: Consultancy Services for Stakeholder Engagement, Environment and Social Risk Component 1: WSS in Small Management for Large Solar Quality And Cost- Under IDA / 62760 Towns and RGCs and Support Prior Open - National 884,442.00 0.00 2021-04-16 2021-09-29 2021-05-07 2021-06-20 2021-07-18 2021-08-17 2021-09-21 2021-10-26 2023-10-26 Powered Water Supply and Based Selection Implementation to Districts Hosting Refugees Sanitation Systems in Rural Growth Centers -Central region (11 solar powered water supply systems) UG-MWE-228563-CS-QCBS / Lot 3: Consultancy Services for Stakeholder Engagement, Environment and Social Risk Component 1: WSS in Small Management for Large Solar Quality And Cost- Under IDA / 62760 Towns and RGCs and Support Prior Open - National 723,634.00 0.00 2021-04-16 2021-09-29 2021-05-07 2021-06-20 2021-07-18 2021-08-17 2021-09-21 2021-10-26 2023-10-26 Powered Water Supply and Based Selection Implementation to Districts Hosting Refugees Sanitation Systems in Rural Growth Centers - Eastern region (9 solar powered water supply systems) UG-MWE-228575-CS-CQS / Consultancy Services for Update of Environmental and Social Impact Assessment Component 1: WSS in Small Consultant (ESIA), Source Protection Plan Under IDA / 62760 Towns and RGCs and Support Post Qualification Limited 300,000.00 0.00 2021-04-16 2021-05-18 2021-04-30 2021-05-30 2021-07-04 2021-12-31 (SPP), and Resettlement Action Implementation to Districts Hosting Refugees Selection Plan (RAP) for the Bitsya and Nyamugasani Water Systems in Buhweju and Kasese Districts Respectively UG-MWE-233662-CS-QCBS / Consultancy Services for Stakeholder Engagement, Component 1: WSS in Small Quality And Cost- Pending Environment and Social Risk IDA / 62760 Towns and RGCs and Support Prior Open - International 1,050,000.00 0.00 2021-05-14 2021-06-04 2021-07-18 2021-08-15 2021-09-14 2021-10-19 2021-11-23 2022-11-23 Based Selection Implementation Management for Ora-Enyau to Districts Hosting Refugees Water Supply and Sanitation System UG-MWE-233666-CS-CQS / Consultancy Services for Environmental and Social Component 1: WSS in Small Consultant Impact Assessment (ESIA), IDA / 62760 Towns and RGCs and Support Post Qualification Limited 300,000.00 0.00 Under Review 2021-05-14 2021-09-30 2021-05-28 2021-06-27 2021-08-01 2022-08-01 Source Protection Plan (SPP), to Districts Hosting Refugees Selection and Resettlement Action Plan (RAP) for Ora-Enyau Water Supply and Sanitation System UG-MWE-233081-CS-CQS / Consultancy Services for Component 1: WSS in Small Consultant Pending Construction Supervision of IDA / 62760 Towns and RGCs and Support Post Qualification Limited 300,000.00 0.00 2021-05-17 2021-05-31 2021-06-30 2021-08-04 2022-08-04 Implementation Bwera Water Supply System in to Districts Hosting Refugees Selection Kasese District. UG-MWE-233085-CS-CQS / Consultancy Services for Component 1: WSS in Small Consultant Pending Construction Supervision of IDA / 62760 Towns and RGCs and Support Post Qualification Limited 300,000.00 0.00 2021-05-17 2021-05-31 2021-06-30 2021-08-04 2022-08-04 Implementation Dunguluha Water Supply to Districts Hosting Refugees Selection System in Kasese District UG-MWE-223390-CS-QCBS / LOT 1: Stakeholder engagement, Environment and Component 1: WSS in Small Social Risk Management for Quality And Cost- Pending IDA / 62760 Towns and RGCs and Support Post Open - National 615,041.00 0.00 2021-03-12 2021-04-02 2021-05-16 2021-06-13 2021-07-13 2021-08-17 2021-09-21 2022-09-21 Solar Powered water supply Based Selection Implementation to Districts Hosting Refugees and sanitation systems in Refugee Hosting Districts of Arua & Moyo Page 6 UG-MWE-223391-CS-QCBS / Lot 2: Consultancy Services to undertake Stakeholder engagement, Environment and Component 1: WSS in Small Quality And Cost- Pending Social Risk Management for IDA / 62760 Towns and RGCs and Support Post Open - National 404,757.00 0.00 2021-03-12 2021-04-02 2021-05-16 2021-06-13 2021-07-13 2021-08-17 2021-09-21 2022-09-21 Based Selection Implementation Solar Powered water supply to Districts Hosting Refugees and sanitation systems in Refugee Hosting Districts of Yumbe UG-MWE-253406-CS-QCBS / Lot 3: Consultancy Services to undertake Stakeholder engagement, Environment and Component 1: WSS in Small Quality And Cost- Pending Social Risk Management for IDA / 62760 Towns and RGCs and Support Post Open - National 575,770.00 0.00 2021-09-20 2021-10-11 2021-11-24 2021-12-22 2022-01-21 2022-02-25 2022-04-01 2023-04-01 Based Selection Implementation Solar Powered water supply to Districts Hosting Refugees and sanitation systems in Refugee Hosting Districts of Adjumani and Lamwo INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-71843-CS-INDV / Component 4: Project Individual Procurement of an individual Under IDA / 62760 Implementation and Post Consultant Open 405,000.00 0.00 2019-03-22 2019-03-20 2019-04-29 2019-05-13 2019-05-31 2025-05-30 consultant for the position of Implementation Institutional Strengthening Selection Project Technical Officer UG-MWE-71833-CS-INDV / Component 4: Project Individual Procurement of an individual Under IDA / 62760 Implementation and Post Consultant Open 405,000.00 0.00 2019-03-22 2019-03-20 2019-04-29 2019-05-13 2019-05-31 2025-05-30 consultant for the position of Implementation Institutional Strengthening Selection Environment Specialist UG-MWE-72025-CS-INDV / Component 4: Project Individual Procurement of an individual IDA / 62760 Implementation and Prior Consultant Open 405,000.00 0.00 Canceled 2019-02-15 2019-03-15 2019-03-25 2019-04-08 2019-04-26 2025-04-25 consultant for the position of Institutional Strengthening Selection Social Safeguards Specialist UG-MWE-113006-CS-INDV / Component 4: Project Individual Procurement of an individual Under IDA / 62760 Implementation and Post Consultant Open 405,000.00 0.00 2019-05-17 2019-05-20 2019-07-03 2019-07-24 2019-08-28 2020-02-24 consultant for the position of Implementation Institutional Strengthening Selection Social Safeguards Specialist UG-MWE-71827-CS-INDV / Procurement of an Individual Component 4: Project Individual consultant for the position of IDA / 62760 Implementation and Prior Consultant Direct 270,000.00 0.00 Canceled 2018-11-23 2018-12-14 2018-12-28 2019-01-18 2025-01-17 Assistant Procurement Institutional Strengthening Selection Specialist - Mr Vincent Okurut UG-MWE-113008-CS-INDV / Procurement of an Individual Component 4: Project Individual Under consultant for the position of IDA / 62760 Implementation and Post Consultant Direct 270,000.00 0.00 2019-05-07 2019-05-20 2019-05-17 2019-05-24 2019-06-28 2025-06-27 Implementation Assistant Procurement Institutional Strengthening Selection Specialist - Mr Vincent Okurut UG-MWE-71426-CS-INDV / Procurement of an Individual Component 4: Project Individual Consultant for the position of IDA / 62760 Implementation and Prior Consultant Direct 450,000.00 0.00 Canceled 2018-11-23 2018-12-14 2018-12-28 2019-01-18 2025-01-17 Financial Management Institutional Strengthening Selection Specialist - Mr Sufiyian Igwahabi UG-MWE-113011-CS-INDV / Procurement of an Individual Component 4: Project Individual Consultant for the position of IDA / 62760 Implementation and Post Consultant Direct 450,000.00 303,696.00 Signed 2019-05-07 2019-07-19 2019-05-17 2019-04-18 2019-05-31 2019-07-15 2019-06-28 2019-07-15 2025-06-27 Financial Management Institutional Strengthening Selection Specialist - Mr Sufiyian Igwahabi UG-MWE-87286-CS-INDV / Procurement of an Individual Individual Consultant for the position of Component 3: Water IDA / 62760 Prior Consultant Direct 135,000.00 0.00 Canceled 2018-11-23 2018-12-14 2018-12-28 2019-01-18 2021-01-15 Water Information System Resource Management Selection Specialist- Mr Kirunda Deusdedit UG-MWE-113012-CS-INDV / Procurement of an Individual Individual Consultant for the position of Component 3: Water IDA / 62760 Post Consultant Direct 135,000.00 230,134.80 Signed 2019-05-07 2019-05-20 2019-05-17 2019-04-18 2019-05-31 2019-07-15 2019-06-28 2019-07-15 2020-06-27 Water Information System Resource Management Selection Specialist- Mr Kirunda Deusdedit UG-MWE-71820-CS-INDV / Procurement of an Individual Component 4: Project Individual Consultant for the position of IDA / 62760 Implementation and Prior Consultant Direct 405,000.00 0.00 Canceled 2018-11-23 2018-12-14 2018-12-28 2019-01-18 2025-01-17 Monitoring and Evaluation Institutional Strengthening Selection Specialist - Mr. Tonny Emmy Ameny UG-MWE-113013-CS-INDV / Procurement of an Individual Component 4: Project Individual Consultant for the position of IDA / 62760 Implementation and Post Consultant Direct 360,000.00 230,134.80 Signed 2019-05-09 2019-05-20 2019-05-19 2019-04-18 2019-06-02 2019-06-30 2019-07-15 2025-06-29 Monitoring and Evaluation Institutional Strengthening Selection Specialist - Mr. Tonny Emmy Ameny UG-MWE-71810-CS-INDV / Component 4: Project Individual Procurement of an Individual Under IDA / 62760 Implementation and Prior Consultant Open 405,000.00 0.00 2019-02-15 2019-07-21 2019-03-25 2020-02-24 2019-04-08 2019-04-26 2025-04-25 Consultant for the Position of Implementation Institutional Strengthening Selection a Procurement Specialist UG-MWE-117193-CS-CDS / Preparation of Resettlement Component 1: WSS in Small Action Plans for the 16 large IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-07-22 2019-08-01 2019-10-05 2020-04-02 solar powered water supply to Districts Hosting Refugees systems Page 7 UG-MWE-130212-CS-CDS / Preparation of Resettlement Component 1: WSS in Small Under Action Plans for the 32 large IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 200,000.00 0.00 2019-09-10 2019-10-21 2019-09-27 2019-12-01 2020-05-29 Implementation solar powered water supply to Districts Hosting Refugees systems UG-MWE-162976-CS-CDS / Consultancy services to carry Component 1: WSS in Small out Geophysical Survey and Under IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 32,589.00 0.00 2020-03-10 2020-03-10 2020-03-20 2020-05-19 2020-11-15 Drilling Supervision of Implementation to Districts Hosting Refugees Production Wells In RGCs under IWMDP UG-MWE-180334-CS-INDV / Procurement of individual consultant for the position of Component 4: Project Individual Under Project Advisor/Project IDA / 62760 Implementation and Post Consultant Direct 365,000.00 0.00 2020-06-22 2020-10-14 2020-06-29 2020-07-13 2020-07-27 2024-12-31 Implementation Management Specialist for the Institutional Strengthening Selection Integrated Water Management & Development Project. UG-MWE-117178-CS-CDS / Consultancy Services for Quality Assurance of the roll Component 3: Water Under IDA / 62760 Post Direct Selection Direct 300,000.00 0.00 2019-06-17 2020-10-07 2019-06-27 2019-08-31 2021-08-30 out of Water Information Resource Management Implementation System in Victoria, Upper Nile, Albertine and Kyoga WMZs UG-MWE-187888-CS-CDS / Consultancy Services for Environmental and Social Impact Assessment (ESIA), Component 1: WSS in Small RAP & Source Protection Plans Under IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 60,000.00 0.00 2020-08-11 2021-01-22 2020-08-21 2020-10-25 2021-04-23 (SSP) for Large Solar Powered Implementation to Districts Hosting Refugees Piped Water Supply Systems and Sanitation Facilities in Refugee Settlement and Host Communities in Kiryandongo UG-MWE-211700-CS-CDS / Consultancy for undertaking Social and Environment Component 3: Water IDA / 62760 Post Direct Selection Direct 60,000.00 0.00 Under Review 2021-01-07 2021-02-19 2021-01-17 2021-03-08 2021-03-14 Assessment for River Resource Management Nyamwamba flood risk management activities UG-MWE-211701-CS-CDS / Consultancy for Design and Component 3: Water Under Construction Supervision of IDA / 62760 Post Direct Selection Direct 450,000.00 0.00 2021-01-07 2021-02-03 2021-01-17 2021-03-09 2021-07-07 Resource Management Implementation Dredging and Flood Protection Works for River Nyamwamba UG-MWE-215916-CS-CDS / Consultancy for Environmental and Social Impact Assessment (ESIA), RAP & Source Protection Plans Component 1: WSS in Small Under (SSP) for Large Solar Powered IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 100,000.00 0.00 2021-02-08 2021-06-18 2021-02-18 2021-04-24 2021-10-21 Implementation Piped Water Supply Systems to Districts Hosting Refugees and Sanitation in 5 RGCS of Bugomolwa, Kikonge- Nakasero, Lubaali ,Damba- Kalyambuzi and Kikooge UG-MWE-173608-CS-CQS / Environmental and Social Impact Assessment (ESIA), RAP & Source Protection Plans Component 1: WSS in Small (SSP) for Large Solar Powered Under IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 120,000.00 0.00 2021-02-08 2021-06-18 2021-02-22 2021-04-16 2021-10-13 Piped Water Supply Systems Implementation to Districts Hosting Refugees and Sanitation Facilities in 6 RGCS of Bugwara, Kabamba, Kikoora, Mwitanzige, Kasese and Lwentulege. UG-MWE-215886-CS-CDS / Consultancy for Environmental and Social Impact Assessment (ESIA), Component 1: WSS in Small RAP & Source Protection Plans Under IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 100,000.00 0.00 2021-02-05 2021-06-18 2021-02-15 2021-04-21 2021-10-18 (SSP) for Large Solar Powered Implementation to Districts Hosting Refugees Piped Water Supply Systems and Sanitation Facilities in 5 RGCS of Igwaya, Kidera, Kitenga, Lugala and Bukizibu UG-MWE-223407-CS-INDV / Procurement of an Individual Component 4: Project Individual Under consultant for the position of IDA / 62760 Implementation and Post Consultant Open 147,000.00 0.00 2021-03-12 2021-04-27 2021-05-10 2021-05-31 2021-07-05 2024-12-16 Implementation Assistant Procurement Institutional Strengthening Selection Specialist for IWMDP UG-MWE-255501-CS-CDS / Consultancy Services for carrying out Engineering re- Component 1: WSS in Small Pending design of Bwera and IDA / 62760 Towns and RGCs and Support Post Direct Selection Direct 298,000.00 0.00 2021-10-05 2021-10-15 2021-12-19 2022-06-17 Implementation Dunguluha water supplys for to Districts Hosting Refugees emergency reconstruction and rehabilitation Page 8