GAMA PCU – GPOBA Procurement Plan I. General 1. Bank’s approval Date of the Procurement Plan [Original: December 2015]: Revision 4 of Updated Procurement Plan, August 2017] 2. Date of General Procurement Notice: [Original: December 2015; August 2017: 3. Period covered by this procurement plan: The procurement period of project covered from year January 2018 to June 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Above US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines.: NOT APPLICABLE 3. Reference to (if any) Project Operational/Procurement Manual: NOT APPLICABLE 4. Any Other Special Procurement Arrangements: NOT APPLICABLE 5. Summary of the Procurement Packages planned (during the year 2018) during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Re Description Estimated Packag Domestic Review f. Cost es Preferenc by Bank Comme No US$ million e (Prior / Post) nts . (yes/no) 1 Summary of the ICB (Works) July 9, 2010 2 Summary of the ICB (Goods) 3 Summary of the NCB (Works) 4 Summary of the NCB (Works) 5 Summary of the RFQ (Works) 6 Summary of the RFQ (Goods) 7 Summary of the ICB (Non-Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packa Review Comment No. Assignment Cost ges by Bank s US$ (Prior / million Post) 1 Summary of number of contracts that will be let under QCBS 2 Summary of 0.10 2 Post 2Nr. IC number of each contracts that 0.05M July 9, 2010 will be let under other methods July 9, 2010 PROCUREMENT Ghana : GH-GAMA Sanitation and Water Project PLAN General Information Country: Ghana Bank’s Approval Date of the Original Procurement Plan: 2018-03-05 2021-10-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P119063 GPN Date: Project Name: GH-GAMA Sanitation and Water Project Loan / Credit No: IDA / H8540, IDA / 67810 GAMA Sanitation and Water Project Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Document Amount Amount Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion Type (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MLGRD/GSWP/WK/005 - LOT 12 / Component 1 - Provision of Provision/Construction of a Single Stage - One 2018-10- 2018-08- 2018-10- 2018-11- 2018-10- 2018-12- 2019-02- 2019-01- 2019-05- 2020-01- IDA / H8540 environmental sanitation and Post Request for Bids Open - National 420,000.00 375,000.00 Signed minimum of 600 Household Envelope 09 23 16 20 25 20 21 24 29 19 water supply services Toilet Units in targetd LIUCs in Okaikoi North & Ablekuma North MLGRD/GSWP/WK/005 - LOT 13 / Component 1 - Provision of Provision/Construction of a Single Stage - One 2018-10- 2018-08- 2018-10- 2018-11- 2018-10- 2018-12- 2019-02- 2019-01- 2019-05- 2020-01- IDA / H8540 environmental sanitation and Post Request for Bids Open - National 420,000.00 323,076.92 Signed minimum of 600 Household Envelope 09 23 16 20 25 11 21 15 29 10 water supply services Toilet Units in targetd LIUCs in Ayawaso East & North MLGRD/GSWP/WK/005 - LOT 14 / Component 1 - Provision of Single Stage - One 2018-10- 2018-08- 2018-10- 2018-11- 2018-10- 2018-12- 2019-02- 2019-01- 2019-05- 2020-01- Provision/Construction of a IDA / H8540 environmental sanitation and Post Request for Bids Open - National 700,000.00 576,923.08 Signed Envelope 09 23 16 20 25 11 21 15 29 10 minimum of 1000 Household water supply services Toilet Units in targetd LIUCs in GCMA MLGRD/GSWP/WK/005 - LOT 15 / Component 1 - Provision of Provision/Construction of a Single Stage - One 2018-10- 2018-08- 2018-10- 2018-11- 2018-10- 2018-12- 2019-02- 2019-01- 2019-05- 2020-01- IDA / H8540 environmental sanitation and Post Request for Bids Open - National 700,000.00 606,067.31 Signed minimum of 1000 Household Envelope 09 23 16 20 25 11 21 15 29 10 water supply services Toilet Units in targetd LIUCs in Kpone Katamanso MLGRD/GSWP/WK/005 - LOT 16 / Component 1 - Provision of Provision/Construction of a Single Stage - One 2018-10- 2018-08- 2018-10- 2018-11- 2018-10- 2018-12- 2019-02- 2019-01- 2019-05- 2020-01- IDA / H8540 environmental sanitation and Post Request for Bids Open - National 700,000.00 500,000.00 Signed minimum of 1000 Household Envelope 09 23 16 20 25 11 21 15 29 10 water supply services Toilet Units in targetd LIUCs in Weija Gbawe Assembly MSWR/GSWP/WK/012 / Construction Opened U-Drain (348m by 0.60m by 0.60m, Component 3 – Planning, Construction of rectangular improvement & expansion of Single Stage - One 2018-10- 2018-10- 2018-12- 2018-07- 2018-12- 2018-07- 2018-12- 2018-11- 2019-06- IDA / H8540 Post Request for Bids Open - National 550,000.00 294,385.32 Signed closed drain 308m by 1.2m Environmental Sanitation Envelope 24 29 03 12 17 26 31 02 29 by 1.2m, Construction of sub- Services surface drain - 537m - ACCRA ACADEMY DARINS MSWR/GSWP/WK/013 / Reconstruction of 3.0 by 1.8m reinforced concrete Component 3 – Planning, drains, Construction of 1.2m improvement & expansion of Single Stage - One 2018-10- 2018-10- 2018-12- 2018-07- 2018-12- 2018-07- 2018-12- 2018-11- 2019-06- by 1.2m reinforced concrete IDA / H8540 Post Request for Bids Open - National 850,000.00 483,785.23 Signed Environmental Sanitation Envelope 24 29 03 12 17 26 31 02 29 drain (250m), Construction of Services 0.8m by 0.6m U-Drain at various locations (2920m) - OKAIKOI CENTRAL DRAINS MSWR/GSWP/WK/014 / Construction of 4Nr 12- Seater improved toilet Component 1 - Provision of Single Stage - One 2018-10- 2018-10- 2018-12- 2018-07- 2018-12- 2018-07- 2018-12- 2018-11- 2019-06- facilities, water supply, IDA / H8540 environmental sanitation and Post Request for Bids Open - National 350,000.00 191,297.02 Signed Envelope 24 29 03 12 17 26 31 02 29 provision of bin-bay and water supply services compost bins in selected schools within the Accra Metropolitan Assembly MSWR/GSWP/WK/015 / Construction of 2.0 by 2.0 Double Box Culvert (10m), Component 3 – Planning, 2.0 by 2.0m Double Box improvement & expansion of Single Stage - One 2018-10- 2018-11- 2018-12- 2018-07- 2018-12- 2018-08- 2019-01- 2018-12- 2019-07- Culvert (10m), 2.0 by 1.5m IDA / H8540 Post Request for Bids Open - National 650,000.00 339,235.46 Signed Environmental Sanitation Envelope 31 05 10 12 24 01 07 10 06 Double Box Culvert (10m), Services 2.5 by 2.5m Single Box Culvert (10m) - TABORA MORINGA DOWN, ETC. MSWR/GSWP/WK/016 / Construction of 0.60m U- Component 3 – Planning, Drain (1320m), Construction improvement & expansion of Single Stage - One 2018-10- 2018-11- 2018-12- 2018-07- 2018-12- 2018-08- 2019-01- 2018-12- 2019-07- IDA / H8540 Post Request for Bids Open - National 600,000.00 332,883.01 Signed of 0.90m U-Drain (700m), Environmental Sanitation Envelope 31 05 10 12 24 01 07 10 06 Construction of 1.2m U-Drain Services (100m) - TABORA AYIKUSHIE MSWR/GSWP/WK/006 / Expansion of Office Space at Component 4 – Institutional Request for Single Stage - One 2018-06- 2018-07- 2018-09- IDA / H8540 Post Limited 50,000.00 0.00 Canceled the Project Coordinating Unit Strengthening Quotations Envelope 04 30 28 Office to accommodate staff MSWR/GSWP/WK/32210/1 / Dredging of the following drains: South Kaneshie, Sukura-Mampon, Mateheko Component 3 – Planning, Highway, Kaneshie Highway, improvement & expansion of Request for Single Stage - One 2019-04- 2019-03- 2019-05- 2019-05- 2019-07- IDA / H8540 Post Limited 100,000.00 133,076.92 Signed Awudume and St Mary) within Environmental Sanitation Quotations Envelope 03 11 15 16 14 GAMA to alleviate flooding in Services support of National Flood Control Programe prior to the peak of rainy season - LOT 1 MSWR/GSWP/WK/32210/2 / Dredging of the following drains: Achimota-Apenkwa, Component 3 – Planning, Kwashie Bu, Bale Down improvement & expansion of Request for Single Stage - One 2019-04- 2019-03- 2019-05- 2019-05- 2019-07- Stream, Castle & Klottey IDA / H8540 Post Limited 100,000.00 133,817.31 Signed Environmental Sanitation Quotations Envelope 03 11 18 16 17 Lagoon, Alogbloshie within Services GAMA to alleviate flooding in support of National Flood Control Programme - LOT 2 MSWR/GSWP/WK/32210/3 / Dredging of the following drains: Dansoman (A), Sakaman, Opete Kwei- Component 3 – Planning, Pambros, Chemu Stream, improvement & expansion of Request for Single Stage - One 2019-04- 2019-03- 2019-05- 2019-05- 2019-07- Tetegu Stream, SCC Drain, IDA / H8540 Post Limited 100,000.00 129,807.69 Signed Environmental Sanitation Quotations Envelope 03 11 18 16 17 Shaibu Glefe, Bortinao- Services Amanfrom within GAMA to alleviate flooding in support of National Flood Control Programme - LOT 3 MSWR/GSWP/WK/008 / Construct of simplified Component 1 - Provision of Single Stage - One 2018-05- 2018-08- 2018-05- 2018-10- 2018-06- 2018-07- 2018-07- 2018-11- sewerage networks in IDA / H8540 environmental sanitation and Post Request for Bids Open - National 850,000.00 0.00 Canceled Envelope 01 22 08 15 07 05 26 22 BANKUMA Community to water supply services serve 800 households Page 1 MSWR/GSWP/WKS/1426 / Component 1 - Provision of Construct simplified Single Stage - One 1,300,000.0 2019-06- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2019-09- 2020-03- 2020-03- IDA / H8540 environmental sanitation and Post Request for Bids Open - National 988,070.35 Signed sewerage networks in Envelope 0 10 10 15 15 01 14 16 18 12 16 water supply services Bankuman to serve 3,000 households MSWR/GSWP/WKS/1436 / Construction of simpliefied sewerage networks in Component 1 - Provision of Single Stage - One 4,000,000.0 3,562,264.4 2019-06- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2019-09- 2020-03- 2020-03- ASHIAMAN NEW TOWN IDA / H8540 environmental sanitation and Post Request for Bids Open - National Signed Envelope 0 5 11 02 21 26 01 25 16 29 11 27 Community to serve water supply services approximately 4700 households MSWR/GSWP/WK/3228/4 / Component 3 – Planning, Priority MMA Local Drains to Under improvement & expansion of Single Stage - One 2019-06- 2019-07- 2019-07- 2019-08- 2019-08- 2019-08- 2019-08- 2019-09- 2020-03- alleviate flood risks at Tema IDA / H8540 Post Request for Bids Open - National 400,000.00 325,876.04 Implementa Environmental Sanitation Envelope 27 03 02 01 08 31 12 21 19 West Municipal Assembly - tion Services Lot 4 MSWR/GSWP/WK/3228/5 / Component 3 – Planning, Priority MMA Local Drains to improvement & expansion of Single Stage - One 2019-06- 2019-07- 2019-07- 2019-08- 2019-08- 2019-08- 2019-08- 2019-09- 2019-12- 2020-03- IDA / H8540 Post Request for Bids Open - National 400,000.00 239,721.41 Signed alleviate flood risks at GA Environmental Sanitation Envelope 27 03 02 01 08 31 12 21 09 19 East Municipal Assembly - Services Lot 5 MSWR/GSWP/WK/3228/1 / Component 3 – Planning, Priority MMA Local Drain Under improvement & expansion of Single Stage - One 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-08- 2019-08- 2019-09- 2020-03- works to alleviate flood risks IDA / H8540 Post Request for Bids Open - National 600,000.00 0.00 Implementa Environmental Sanitation Envelope 27 03 02 01 08 31 12 21 19 at Okaikoi Central Assembly - tion Services LOT 1 MSWR/GSWP/WK/3228/2 / Component 3 – Planning, Priority MMA Local Drain improvement & expansion of Single Stage - One 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2019-08- 2019-10- 2019-12- 2020-04- works to alleviate flood risks IDA / H8540 Post Request for Bids Open - National 600,000.00 482,593.05 Signed Environmental Sanitation Envelope 27 19 02 13 08 12 12 17 09 14 at Weija Gbawe Municipal Services Assembly - LOT 2 MSWR/GSWP/WK/3228/3 / Component 3 – Planning, Priority MMA Local Drain improvement & expansion of Single Stage - One 2019-04- 2019-06- 2019-05- 2019-06- 2019-08- 2019-07- 2019-08- 2019-07- 2019-11- 2020-01- IDA / H8540 Post Request for Bids Open - National 400,000.00 247,006.01 Signed works to alleviate flood risks Environmental Sanitation Envelope 30 19 05 04 08 04 12 25 20 21 at GA North Assembly - LOT Services 3 MSWR/GSWP/WK/1213/1/1 / Construct/rehabilitate Improved Instituttional Component 1 - Provision of Sanitation and Water Supply Single Stage - One 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2020-03- IDA / H8540 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Facilities in Selected Schools Envelope 30 04 04 03 07 05 water supply services in the Kpone Katamanso Municipal Assembly in GAMA - LOT 1 MSWR/GSWP/WK/1213/2/1 / Construct/rehabilitate Improved Instituttional Component 1 - Provision of Pending Single Stage - One 2019-06- 2019-07- 2019-08- 2019-08- 2019-10- 2020-04- Sanitation and Water Supply IDA / H8540 environmental sanitation and Post Request for Bids Open - National 400,000.00 0.00 Implementa Envelope 27 02 01 31 05 02 Facilities in Selected Schools water supply services tion in the Weija Gbawe Municipal Assembly in GAMA - LOT 1 MSWR/GSWP/WK/1213/3/1 / Construct/rehabilitate Improved Instituttional Component 1 - Provision of Single Stage - One 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2020-03- Sanitation and Water Supply IDA / H8540 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Envelope 30 04 04 03 07 05 Facilities in Selected Schools water supply services in the Ayawaso East Municipal Assembly in GAMA - LOT 1 MSWR/GSWP/WK/1213/5/8 / Construct/rehabilitate Improved Instituttional Component 1 - Provision of Single Stage - One 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2020-03- Sanitation and Water Supply IDA / H8540 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Envelope 30 04 04 03 07 05 Facilities in Selected Schools water supply services in the Ashiaman Municipal Assembly in GAMA - LOT 8 MSWR/GSWP/WK/1213/4/9 / Construct/rehabilitate Improved Instituttional Component 1 - Provision of Single Stage - One 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2020-03- Sanitation and Water Supply IDA / H8540 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Envelope 30 04 04 03 07 05 Facilities in Selected Schools water supply services in the Ga East Municipal Assembly in GAMA - LOT 9 MSWR/GSWP/WK/3229 / Component 3 – Planning, Priority drainage improvement & expansion of Single Stage - One 2019-06- 2019-07- 2019-08- 2019-09- 2019-10- 2020-04- IDA / H8540 Post Request for Bids Open - National 600,000.00 0.00 Canceled improvement works within Environmental Sanitation Envelope 27 02 13 12 17 14 the Agblobloshie Market Services MSWR/GSWP/WK/3228/6 / Component 3 – Planning, Pending Priority drainage improvement & expansion of Single Stage - One 2019-07- 2019-07- 2019-08- 2019-09- 2019-10- 2020-04- IDA / H8540 Post Request for Bids Open - National 450,000.00 0.00 Implementa improvement works to Environmental Sanitation Envelope 21 26 25 24 15 12 tion alleviate flood risks in the Services Gbawe Community. MSWR/GSWP/WK/3228/7 / Drainage improvement works Component 3 – Planning, Pending at selected locations within improvement & expansion of Single Stage - One 2019-10- 2019-11- 2019-12- 2020-01- 2020-01- 2020-05- IDA / H8540 Post Request for Bids Open - National 450,000.00 0.00 Implementa GAMA to alleviate flood risks Environmental Sanitation Envelope 30 04 04 03 24 23 tion - Weija-Gbawe Municipal Services Assembly - Lot 7 MSWR/GSWP/WK/3228/8 / Drainage improvement works Component 3 – Planning, Pending at selected locations within improvement & expansion of Single Stage - One 2019-10- 2019-11- 2019-12- 2020-01- 2020-01- 2020-05- IDA / H8540 Post Request for Bids Open - National 450,000.00 0.00 Implementa GAMA to alleviate flood risks Environmental Sanitation Envelope 31 05 05 04 25 24 tion - Ablekuma North Municipal Services Assembly - Lot 8 MSWR/GSWP/WK/3228/9 / Drainage improvement works Component 3 – Planning, at selected locations within improvement & expansion of Single Stage - One 2019-10- 2019-10- 2019-11- 2019-12- 2019-11- 2020-01- 2019-11- 2020-01- 2020-02- 2020-05- IDA / H8540 Post Request for Bids Open - National 450,000.00 604,797.06 Signed GAMA to alleviate flood risks Environmental Sanitation Envelope 31 04 05 05 05 04 12 25 25 24 - GA West Municipal Services Assembly - Lot 9 MSWR/GSWP/WK/3228/12 / Drainage improvement works Component 3 – Planning, at selected locations within improvement & expansion of Single Stage - One 2019-10- 2019-10- 2019-11- 2019-12- 2019-11- 2020-01- 2019-12- 2020-01- 2020-01- 2020-05- IDA / H8540 Post Request for Bids Open - National 450,000.00 408,769.29 Signed GAMA to alleviate flood risks Environmental Sanitation Envelope 31 29 05 05 29 04 03 25 16 24 - Adentan Municipal Services Assembly (SSNIT Flat) - Lot 12 MSWR/GSWP/WK/3228/13 / Drainage improvement works Component 3 – Planning, at selected locations within improvement & expansion of Single Stage - One 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-05- IDA / H8540 Post Request for Bids Open - National 500,000.00 467,197.29 Signed GAMA to alleviate flood risks Environmental Sanitation Envelope 31 12 05 05 13 04 13 25 10 24 - Adentan Municipal Services Assembly (SSNIT Flat) - Lot 7 MSWR/GSWP/WK/3228/10 / Drainage improvement works Component 3 – Planning, Pending at selected locations within improvement & expansion of Request for Single Stage - One 2019-11- 2019-12- 2020-04- IDA / H8540 Post Limited 70,000.00 0.00 Implementa GAMA to alleviate flood risks Environmental Sanitation Quotations Envelope 05 17 15 tion - LeKMA Municipal Assembly Services (Cocoa Str.) - Lot 10 Page 2 MSWR/GSWP/WK/3228/11 / Drainage improvement works Component 3 – Planning, Pending at selected locations within improvement & expansion of Request for Single Stage - One 2019-11- 2019-12- 2020-04- IDA / H8540 Post Limited 100,000.00 0.00 Implementa GAMA to alleviate flood risks Environmental Sanitation Quotations Envelope 05 17 15 tion - Adentan Municipal Services Assembly (Park Avenue) - Lot 11 MSWR/GSWP/WK/3221/15/2 Component 3 – Planning, 0 / Priority Drainage improvement & expansion of Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- 2020-04- 2020-03- 2020-05- 2020-04- 2020-07- 2020-07- Improvement Works in the IDA / H8540 Post Request for Bids Open - National 400,000.00 345,401.18 Signed Environmental Sanitation Envelope 04 28 09 10 16 24 12 07 14 06 Kpone Katamanso Municpal Services Assembly MSWR/GSWP/WK/007 / Construction of simplified Component 1 - Provision of Single Stage - One 2018-06- 2018-08- 2018-07- 2018-08- 2018-09- 2018-10- 2019-02- sewerage network in LAKPAN IDA / H8540 environmental sanitation and Post Request for Bids Open - National 850,000.00 0.00 Canceled Envelope 28 01 05 04 15 06 03 Community to serve 850 water supply services households MSWR/GSWP/WK/3227 / Priority MMA Local Drain Component 3 – Planning, works to alleviate flood risks improvement & expansion of Single Stage - One 2019-04- 2019-05- 2019-06- 2019-06- 2019-07- 2020-01- IDA / H8540 Post Request for Bids Open - National 250,000.00 0.00 Canceled at Agboga and stabilising of Environmental Sanitation Envelope 30 05 04 25 16 12 downstream channel to Services improve flow MSWR/GSWP/WK/011 / Component 3 – Planning, Construction of proposed improvement & expansion of Single Stage - One 13,000,000. 2019-04- 2019-05- 2019-06- 2019-07- 2019-08- 2020-05- faecal/septage sludge IDA / H8540 Prior Request for Bids Open - National 0.00 Canceled Environmental Sanitation Envelope 00 30 15 15 13 03 29 treatment plant in at Nungua Services Farms in GAMA GH- MSWR/GSWP/AF/GA/WKS/ C3/312/LOT1 / Design and Construct a specialized Component 1 - Provision of Pending treatment facility for Request for 2021-12- 2021-12- 2022-03- 2022-06- 2022-07- 2024-01- IDA / 67810 environmental sanitation and Post Open - National Multi Stage 500,000.00 0.00 Implementa receiving and processing Proposals 16 21 01 13 18 09 water supply services tion digested sludge from household bio-digester toilets into reusable products (2 Packages for 2 selected MMAs in GAMA) Lot1 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/KUMA/LOT1 / Provision of 1,000 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 500,000.00 0.00 Implementa Envelope 30 14 04 16 16 15 15 19 18 benefiting 8,000 low income water supply services tion beneficiaries in Kumasi Metropolitan Assembly within the GKMA Lot1 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/KUMA/LOT2 / Provision of 500 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 250,000.00 0.00 Implementa Envelope 30 14 04 16 16 15 15 19 18 benefiting 4,000 low income water supply services tion beneficiaries in Kumasi Metropolitan Assembly within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/ASMA/LOT1 / Provision of 1,000 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 500,000.00 0.00 Implementa Envelope 30 14 04 16 16 15 15 19 18 benefiting 8,000 low income water supply services tion beneficiaries in Asokwa Municipal Assembly within the GKMA Lot1 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/ASMA/LOT2 / Provision of 500 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 250,000.00 0.00 Implementa Envelope 30 14 04 16 16 15 15 19 18 benefiting 4,000 low income water supply services tion beneficiaries in Asokwa Municipal Assembly within the GKMA LOT 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/AMMA/LOT1 / Provision of 1,000 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 500,000.00 526,674.77 Implementa Envelope 30 14 04 16 16 29 15 19 19 18 benefiting 8,000 low income water supply services tion beneficiaries in Asokore Manpong Municipal Assembly within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/AMMA/LOT2 / Provision of 500 on-site Component 1 - Provision of Under household toilet facilities Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-08- 2021-09- 2022-03- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 250,000.00 266,882.30 Implementa benefiting 4,000 low income Envelope 30 14 04 16 16 29 15 19 19 18 water supply services tion beneficiaries in Asokore Mampong Menucipal Assembly within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/EJMA/LOT1 / Provision of 1,000 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 500,000.00 0.00 Implementa Envelope 30 14 04 16 16 16 15 19 18 benefiting 8,000 low income water supply services tion beneficiaries in Ejisu Menucipal Assembly within the GKMA Lot 1 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/EJMA/LOT2 / Provision of 500 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 250,000.00 0.00 Implementa Envelope 30 14 04 16 16 16 15 19 18 benefiting 4,000 low income water supply services tion beneficiaries in Ejisu Menucipal Assembly within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/OFMA/LOT1 / Provision of 1,000 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 500,000.00 0.00 Implementa Envelope 30 14 04 16 16 16 15 19 18 benefiting 8,000 low income water supply services tion beneficiaries in Oforikrom Municipal Assembly within the GKMA Lot1 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/OFMA/LOT2 / Provision of 500 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 250,000.00 0.00 Implementa Envelope 30 14 04 16 16 16 15 19 18 benefiting 4,000 low income water supply services tion beneficiaries in Oforikrom Municipal Assembly within the GKMA Lot 2 Page 3 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/TAMA/LOT1 / Provision of 1,000 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 500,000.00 0.00 Implementa Envelope 30 14 04 16 16 29 15 19 18 benefiting 8,000 low income water supply services tion beneficiaries in Tafo municipal Assembly within the GKMA Lot 1 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/TAMA/LOT2 / Provision of 500 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 250,000.00 0.00 Implementa Envelope 30 14 04 16 16 29 15 19 18 benefiting 4,000 low income water supply services tion beneficiaries in Tafo municipal Assembly within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/KWMA/LOT1 / Provision of 1,000 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 500,000.00 0.00 Implementa Envelope 30 14 04 16 16 15 19 18 benefiting 8,000 low income water supply services tion beneficiaries in Kwadaso Municipal Assembly within the GKMA Lot1 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/KWMA/LOT2 / Provision of 500 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 250,000.00 0.00 Implementa Envelope 30 14 04 16 16 15 19 18 benefiting 4,000 low income water supply services tion beneficiaries in Kwadaso Municipal Assembly within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/SUMA/LOT1 / Provision of 1,000 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 500,000.00 537,704.93 Implementa Envelope 30 14 04 16 16 28 15 17 19 18 benefiting 8,000 low income water supply services tion beneficiaries in Suame municipal Assembly within the GKMA Lot1 GH- MSWR/GSWP/AF/GK/WKS/ C1/113/SUMA/LOT2 / Provision of 500 on-site Component 1 - Provision of Under Single Stage - One 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 250,000.00 268,852.47 Implementa Envelope 30 14 04 16 16 28 15 17 19 18 benefiting 4,000 low income water supply services tion beneficiaries in Suame Municipal Assembly within the GKMA Lot2 GH- MSWR/GSWP/AF/GA/WKS/ C1/126/LOT 1 / Construction Component 1 - Provision of of additional 2 Gender Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Friendly Institutional Toilets Envelope 03 08 19 19 23 20 water supply services facilities in one MMAs, including water connection – GAMA Lot 1 GH- MSWR/GSWP/AF/GA/WKS/ C1/126/LOT2 / Construction Component 1 - Provision of of additional 2 Gender Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Friendly Institutional Toilets Envelope 03 08 19 19 23 20 water supply services facilities in one MMAs, including water connection – GAMA Lot 2 GH- MSWR/GSWP/AF/GA/WKS/ C1/126/LOT 3 / Construction Component 1 - Provision of of additional 2 Gender Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Friendly Institutional Toilets Envelope 03 08 19 19 23 20 water supply services facilities in one MMAs, including water connection – GAMA Lot 3 GH- MSWR/GSWP/AF/GA/WKS/ C1/126/LOTS 4 / Component 1 - Provision of Construction of additional 2 Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Gender Friendly Institutional Envelope 03 08 19 19 23 20 water supply services Toilets facilities in one MMAs, including water connection – GAMA Lot 4 GH- MSWR/GSWP/AF/GA/WKS/ C1/126/LOT 5 / Construction Component 1 - Provision of of additional 2 Gender Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Friendly Institutional Toilets Envelope 03 08 19 19 23 20 water supply services facilities in one MMAs, including water connection – GAMA Lot 5 GH- MSWR/GSWP/AF/GA/WKS/ C1/126/LOTS 6 / Component 1 - Provision of Construction of additional 2 Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 200,000.00 0.00 Canceled Gender Friendly Institutional Envelope 03 08 19 19 23 20 water supply services Toilets facilities in one MMAs, including water connection – GAMA Lot 6 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/ASMA/LOT3 / Construction of 2 Component 1 - Provision of Pending 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids 175,000.00 0.00 Implementa 01 06 18 17 22 20 including water connections, water supply services tion for selected needy schools in Asokwa municipal Assembly, within the GKMA lot 3 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/SUMA/LOT3 / Construction of 2 Component 1 - Provision of Pending Single Stage - One 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope 01 06 18 17 22 20 including water connections, water supply services tion for selected needy schools in Suame municipal Assembly, within the GKMA Lot3 GH- MSWR/GASWP/AF/GK/WKS/ Component 1 - Provision of Pending C3/3101/LOT1 / Single Stage - One 4,500,000.0 2021-12- 2022-01- 2022-02- 2022-03- 2022-04- 2022-10- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 0.00 Implementa Construction of Simplified Envelope 0 30 04 15 17 21 18 water supply services tion Sewerage Systems within Selected Communities in GKMA Lot1 Page 4 GH- MSWR/GASWP/AF/GK/WKS/ C3/3101/ LOT2 / Component 1 - Provision of Pending Single Stage - One 4,500,000.0 2021-12- 2022-01- 2022-02- 2022-03- 2022-04- 2022-10- Construction of Simplified IDA / 67810 environmental sanitation and Post Request for Bids Open - National 0.00 Implementa Envelope 0 30 04 15 17 21 18 Sewerage Systems within water supply services tion Selected Communities in GKMA Lot2 GH- MSWR/GSWP/AF/GA/WKS/ C3/312/ LOT2 / Design and Construct a specialized Component 1 - Provision of Pending treatment facility for Request for 2021-12- 2021-12- 2022-03- 2022-06- 2022-07- 2024-01- IDA / 67810 environmental sanitation and Post Open - National Multi Stage 500,000.00 0.00 Implementa receiving and processing Proposals 16 21 01 13 18 09 water supply services tion digested sludge from household bio-digester toilets into reusable products (2 Packages for 2 selected MMAs in GAMA) Lot2 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/TAMA/LOT1 / Construction of 2 Component 1 - Provision of Pending Request for Single Stage - One 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Open - National 175,000.00 0.00 Implementa Proposals Envelope 01 06 06 05 10 08 including water connections, water supply services tion for selected needy schools in Tafo municipal Assembly, within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/KUMA/LOT3 / Request for Bids - Provision of 50 on-site Component 1 - Provision of Pending Single Stage - One Works (without 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 25,000.00 0.00 Implementa Envelope prequalification) 30 04 16 15 19 18 benefiting an estimated 300 water supply services tion SPD low income beneficiaries in Kumasi Metropolitan Assembly within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/ASMA/LOT3 / Request for Bids - Provision of 50 on-site Component 1 - Provision of Pending Single Stage - One Works (without 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 25,000.00 0.00 Implementa Envelope prequalification) 30 04 16 15 19 18 benefiting an estimated 300 water supply services tion SPD low income beneficiaries in Asokwa Municipal Assembly within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/AMMA/LOT3 / Request for Bids - Provision of 50 on-site Component 1 - Provision of Pending Single Stage - One Works (without 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 25,000.00 0.00 Implementa Envelope prequalification) 30 04 16 15 19 18 benefiting an estimated 300 water supply services tion SPD low income beneficiaries in Asokore Mampong Municipal Assembly within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/EJMA/LOT3 / Request for Bids - Provision of 50 on-site Component 1 - Provision of Pending Single Stage - One Works (without 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 25,000.00 0.00 Implementa Envelope prequalification) 30 04 16 15 19 18 benefiting an estimated 300 water supply services tion SPD low income beneficiaries in Ejisu Municipal Assembly within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/OFMA/LOT3 / Request for Bids - Provision of 50 on-site Component 1 - Provision of Pending Single Stage - One Works (without 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 25,000.00 0.00 Implementa Envelope prequalification) 30 04 16 15 19 18 benefiting an estimated 300 water supply services tion SPD low income beneficiaries in Oforikrom Municipal Assembly within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/TAMA/LOT3 / Request for Bids - Provision of 50 on-site Component 1 - Provision of Pending Single Stage - One Works (without 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 25,000.00 0.00 Implementa Envelope prequalification) 30 04 16 15 19 18 benefiting an estimated 300 water supply services tion SPD low income beneficiaries in Tafo Municipal Assembly within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/KWMA/LOT3 / Request for Bids - Provision of 50 on-site Component 1 - Provision of Pending Single Stage - One Works (without 2021-05- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 25,000.00 0.00 Implementa Envelope prequalification) 30 04 16 15 19 18 benefiting an estimated 300 water supply services tion SPD low income beneficiaries in Kwadaso Municipal Assembly within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/113/SUMA/LOT3 / Request for Bids - Provision of 50 on-site Component 1 - Provision of Under Single Stage - One Works (without 2021-05- 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Open - National 25,000.00 0.00 Implementa Envelope prequalification) 30 14 04 16 15 19 18 benefiting an estimated 300 water supply services tion SPD low income beneficiaries in Suame Municipal Assembly within the GKMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 1 / Construction Request for Bids - of additional 4 Gender Component 1 - Provision of Pending Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- Friendly Institutional Toilets IDA / 67810 environmental sanitation and Post Request for Bids Limited 450,000.00 0.00 Implementa Envelope prequalification) 20 25 06 05 10 08 facilities including water water supply services tion SPD connection (2Nr 8Seater at AME Zion 1; 1Nr 10-Seater, 1 Nr 8 Seater in AME Zion 2) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT2 / Construction Request for Bids - Component 1 - Provision of Pending of additional 2 Gender Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 330,000.00 0.00 Implementa Friendly Institutional Toilets Envelope prequalification) 20 25 06 05 10 08 water supply services tion facilities including water SPD connection (1Nr 12Seater at NiiOtto; 1NR 12Seater at PokuaseMA) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT3 / Construction Request for Bids - Component 1 - Provision of Pending of additional 2 Gender Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 330,000.00 0.00 Implementa Friendly Institutional Toilets Envelope prequalification) 20 25 06 05 10 08 water supply services tion facilities including water SPD connection (2Nr 12 Seater at OurLady of Assumption Basic 1&2) – GAMA Page 5 GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 4 / Construction Request for Bids - Component 1 - Provision of Pending of additional 2 Gender Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 450,000.00 0.00 Implementa Friendly Institutional Toilets Envelope prequalification) 20 25 06 05 10 08 water supply services tion facilities including water SPD connection (2Nr 16Seater at Ashalaja MA Basic 1&2) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 5 / Construction Request for Bids - Component 1 - Provision of Pending of additional 3 Gender Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 280,000.00 0.00 Implementa Friendly Institutional Toilets Envelope prequalification) 20 25 06 05 10 08 water supply services tion facilities including water SPD connection (1Nr 20Seater at Christian Methodist SHS) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 6 / Construction Request for Bids - Component 1 - Provision of Pending of additional 2 Gender Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 280,000.00 0.00 Implementa Friendly Institutional Toilets Envelope prequalification) 20 25 06 05 10 08 water supply services tion facilities including water SPD connection (1Nr 8Seater at KojoAshung; 1Nr 12Seater at Sacred Heart) – GAMA GH- MSWR/GSWP/AF/GA/WK/ Request for Bids - C1/126/LOT 7 / Construction Component 1 - Provision of Pending Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- of additional 2 Gender IDA / 67810 environmental sanitation and Post Request for Bids Limited 450,000.00 0.00 Implementa Envelope prequalification) 20 25 06 05 10 08 Friendly Institutional Toilets water supply services tion SPD facilities including water connection (2Nr 16Seater at Opa MA JHS) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 8 / Construction Request for Bids - Component 1 - Provision of Pending of additional 2 Gender Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 330,000.00 0.00 Implementa Friendly Institutional Toilets Envelope prequalification) 20 25 06 05 10 08 water supply services tion facilities including water SPD connection (2Nr 12Seater at Weija Methodists 1&2) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 9 / Construction Request for Bids - of additional 2 Gender Component 1 - Provision of Pending Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- Friendly Institutional Toilets IDA / 67810 environmental sanitation and Post Request for Bids Limited 400,000.00 0.00 Implementa Envelope prequalification) 20 25 06 05 10 08 facilities including water water supply services tion SPD connection (1Nr 16Seater at Akporman Basic School; 1Nr 12Seater at Papao Community Presby) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 10 / Construction of additional 3 Request for Bids - Component 1 - Provision of Pending Gender Friendly Institutional Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 280,000.00 0.00 Implementa Toilets facilities including Envelope prequalification) 20 25 06 05 10 08 water supply services tion water connection (1Nr SPD 8Seater at Kwabenya Atomic MA5; 1Nr 8Seater at Adenkrebi MA Basic and 1Nr 4Seater at Taifa Polyclinic) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 11 / Request for Bids - Construction of additional 3 Component 1 - Provision of Pending Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- Gender Friendly Institutional IDA / 67810 environmental sanitation and Post Request for Bids Limited 500,000.00 0.00 Implementa Envelope prequalification) 20 25 06 05 10 08 Toilets facilities including water supply services tion SPD water connection (2Nr 16Seater at Kpon Methodist A&B and 1Nr 4Seater at Kpone Health Centre) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 12 / Construction of additional 2 Request for Bids - Component 1 - Provision of Pending Gender Friendly Institutional Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 550,000.00 0.00 Implementa Toilets facilities including Envelope prequalification) 20 25 06 05 10 08 water supply services tion water connection (1Nr SPD 20Seater at Zanu Cluster of Schools and 1Nr 4Seater at Bawaleshie Health Centre) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 13 / Request for Bids - Component 1 - Provision of Pending Construction of additional 1 Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 280,000.00 0.00 Implementa Gender Friendly Institutional Envelope prequalification) 20 25 06 05 10 08 water supply services tion Toilets facilities including SPD water connection (1Nr 20Seater at Zanu Cluster of Schools) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 14 / Request for Bids - Construction of additional 3 Component 1 - Provision of Pending Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- Gender Friendly Institutional IDA / 67810 environmental sanitation and Post Request for Bids Limited 280,000.00 0.00 Implementa Envelope prequalification) 20 25 06 05 10 08 Toilets facilities including water supply services tion SPD water connection (2Nr 16Seater at Katamanso Cluster of Schools and 1Nr 3Seater at Nima Clinic) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 15 / Construction of additional 3 Request for Bids - Component 1 - Provision of Pending Gender Friendly Institutional Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 220,000.00 0.00 Implementa Toilets facilities including Envelope prequalification) 20 25 06 05 10 08 water supply services tion water connection (1Nr SPD 8Seater at Foster Home School; 1Nr 4Seater at Pantang Hospital and 1Nr 4Seater Danfa Health Centre) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 16 / Construction of additional 3 Request for Bids - Gender Friendly Institutional Component 1 - Provision of Pending Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- Toilets facilities including IDA / 67810 environmental sanitation and Post Request for Bids Limited 280,000.00 0.00 Implementa Envelope prequalification) 20 25 06 05 10 08 water connection (1Nr water supply services tion SPD 12Seater at Klangon TMA School; 1Nr 4Seater at Community 2 Health Facility and 1Nr 4Seater Tema Polyclinic) – GAMA GH- MSWR/GSWP/AF/GA/WK/ C1/126/LOT 17 / Request for Bids - Construction of additional 2 Component 1 - Provision of Pending Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- Gender Friendly Institutional IDA / 67810 environmental sanitation and Post Request for Bids Limited 340,000.00 0.00 Implementa Envelope prequalification) 20 25 06 05 10 08 Toilets facilities including water supply services tion SPD water connection (1Nr 16Seater and 1Nr 8Seater at AgyeiKojo TWMA Schools) – GAMA Page 6 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/KUMA/LOT1 / Construction of 2 Request for Bids - Component 1 - Provision of Pending Institutional Toilets facilities, Works (without 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids 175,000.00 0.00 Implementa including water connections, prequalification) 01 06 18 17 22 20 water supply services tion for selected needy schools in SPD Kumasi Metropolitan Assembly, within the GKMA Lo 1 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/KUMA/LOT2 / Construction of 2 Request for Bids - Component 1 - Provision of Pending Institutional Toilets facilities, Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa including water connections, Envelope prequalification) 30 04 18 17 22 18 water supply services tion for selected needy schools in SPD Kumasi Metropolitan Assembly, within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/KUMA/LOT3 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Kumasi Metropolitan Assembly, within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/124/KUMA/LOT4 / Construction of 2 Request for Bids - Component 1 - Provision of Pending Institutional Toilets facilities, Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 67810 environmental sanitation and Post Request for Bids 175,000.00 0.00 Implementa including water connections, prequalification) 30 04 18 17 22 18 water supply services tion for selected needy schools in SPD Kumasi Metropolitan Assembly, within the GKMA Lot 4 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/ASMA/LOT1 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 01 06 18 17 22 20 including water connections, water supply services tion SPD for selected needy schools in Asokwa municipal Assembly, within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/124/ASMA/LOT2 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Asokwa municipal Assembly, within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/AMMA/LOT1 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Asokore Mampong municipal Assembly, within the GKMA GH- MSWR/GSWP/AF/GK/WK/ C1/124/ASMA/LOT3 / Request for Bids - Component 1 - Provision of Pending Construction of 2 Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Institutional Toilets facilities, Envelope prequalification) 30 04 18 17 22 18 water supply services tion including water connections, SPD for selected needy schools in Asokwa Municipal Assembly, within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/124/AMMA/LOT2 / Construction of 2 Request for Bids - Component 1 - Provision of Pending Institutional Toilets facilities, Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa including water connections, Envelope prequalification) 30 04 18 17 22 18 water supply services tion for selected needy schools in SPD Asokore Mampong municipal Assembly, within the GKMA Lot2 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/AMMA/LOT3 / Construction of 2 Request for Bids - Component 1 - Provision of Pending Institutional Toilets facilities, Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa including water connections, Envelope prequalification) 30 04 18 17 22 18 water supply services tion for selected needy schools in SPD Asokore Mampong municipal Assembly, within the GKMA Lot 3 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/EJMA/LOT1 / Request for Bids - Construction of 2 Component 1 - Provision of Under Single Stage - One Works (without 2022-01- 2021-06- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 14 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Ejisu municipal Assembly, within the GKMA Lot1 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/EJMA/LOT2 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Ejisu municipal Assembly, within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/EJMA/LOT3 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Ejisu municipal Assembly, within the GKMA Lot 3 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/OFMA/LOT1 / Construction of 2 Request for Bids - Component 1 - Provision of Pending Institutional Toilets facilities, Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 67810 environmental sanitation and Post Request for Bids 175,000.00 0.00 Implementa including water connections, prequalification) 30 04 18 17 22 18 water supply services tion for selected needy schools in SPD Oforikrom municipal Assembly, within the GKMA Lot1 Page 7 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/OFMA/LOT2 / Construction of 2 Request for Bids - Component 1 - Provision of Pending Institutional Toilets facilities, Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa including water connections, Envelope prequalification) 30 04 18 17 22 18 water supply services tion for selected needy schools in SPD Oforikrom municipal Assembly, within the GKMA Lot2 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/OFMA/LOT3 / Construction of 2 Request for Bids - Component 1 - Provision of Pending Institutional Toilets facilities, Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa including water connections, Envelope prequalification) 30 04 18 17 22 18 water supply services tion for selected needy schools in SPD Oforikrom municipal Assembly, within the GKMA Lot3 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/TAMA/LOT2 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Tafo municipal Assembly, within the GKMA Lot2 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/TAMA/LOT3 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Tafo municipal Assembly, within the GKMA Lot 3 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/KWMA/LOT1 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Kwadaso municipal Assembly, within the GKMA Lot1 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/KWMA/LOT2 / National Construction of 2 Component 1 - Provision of Procurement Pending Single Stage - One 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National Document - 1 175,000.00 0.00 Implementa Envelope 01 06 18 17 22 20 including water connections, water supply services Envelope process tion for selected needy schools in (Non Bank-SPD) Kwadaso municipal Assembly, within the GKMA Lot 2 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/KWMA/LOT3 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 01 06 18 17 22 20 including water connections, water supply services tion SPD for selected needy schools in Kwadaso municipal Assembly, within the GKMA LOt3 GH- MSWR/GSWP/AF/GK/WKS/ C1/124/SUMA/LOT2 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-11- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 30 04 18 17 22 18 including water connections, water supply services tion SPD for selected needy schools in Suame municipal Assembly, within the GKMA GH- MSWR/GSWP/AF/GK/WKS/ C1/124/SUMA/LOT1 / Request for Bids - Construction of 2 Component 1 - Provision of Pending Single Stage - One Works (without 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Institutional Toilets facilities, IDA / 67810 environmental sanitation and Post Request for Bids Open - National 175,000.00 0.00 Implementa Envelope prequalification) 01 06 18 17 22 20 including water connections, water supply services tion SPD for selected needy schools in Suame municipal Assembly, within the GKMA Lot 1 GH- MSWR/GSWP/AF/GK/WKS/C3 /311/LOT1 / Design and Construct a Specialized Request for Component 1 - Provision of Pending Treatment facility for Request for Single Stage - One Proposal Design 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Open - National 600,000.00 0.00 Implementa receiving and processing Proposals Envelope and Build - Works 08 13 25 24 29 27 water supply services tion digested sludge from SPD (Single-stage) household bio-digester toilets into reusable products in a selected MMA in GAMA GH- MSWR/GSWP/AF/GK/WKS/C1 /113/KUMA/LOT4 / Provision Request for Bids - of 500 on-site household Component 1 - Provision of Under Single Stage - One Works (without 2021-09- 2021-06- 2021-09- 2021-06- 2021-10- 2021-07- 2021-11- 2021-12- 2022-06- toilet facilities benefiting IDA / 67810 environmental sanitation and Post Request for Bids Limited 250,000.00 0.00 Implementa Envelope prequalification) 02 14 07 18 19 15 18 23 21 4,000 low income water supply services tion SPD beneficiaries in Kumasi Metropolitan Assembly within the GKMA LOT 4 GH- MSWR/GSWP/AF/GK/WKS/C1 /113/ASMA/LOT4 / Provision Request for Bids - of 500 on-site household Component 1 - Provision of Under Single Stage - One Works (without 2021-09- 2021-06- 2021-09- 2021-06- 2021-10- 2021-07- 2021-11- 2021-12- 2022-06- toilet facilities benefiting IDA / 67810 environmental sanitation and Post Request for Bids Limited 250,000.00 0.00 Implementa Envelope prequalification) 02 14 07 18 19 15 18 23 21 4,000 low income water supply services tion SPD beneficiaries in Asokwa Municipal Assembly within the GKMA LOT 4 GH- MSWR/GSWP/AF/GK/WKS/C1 /113/EJMA/LOT4 / Provision Request for Bids - Component 1 - Provision of Under of 500 on-site household Single Stage - One Works (without 2021-09- 2021-06- 2021-09- 2021-06- 2021-10- 2021-07- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 250,000.00 0.00 Implementa toilet facilities benefiting Envelope prequalification) 02 14 07 18 19 16 18 23 21 water supply services tion 4,000 low income SPD beneficiaries in Ejisu Municipal Assembly within the GKMA LOT 4 GH- MSWR/GSWP/AF/GK/WKS/C1 /113/SUMA/LOT 4 / Request for Bids - Provision of 500 on-site Component 1 - Provision of Under Single Stage - One Works (without 2021-09- 2021-06- 2021-09- 2021-06- 2021-10- 2021-07- 2021-11- 2021-12- 2022-06- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Limited 250,000.00 0.00 Implementa Envelope prequalification) 02 14 07 14 19 28 18 23 21 benefiting 4,000 low income water supply services tion SPD beneficiaries in Suame Municipal Assembly within the GKMA LOT 4 Page 8 GH- MSWR/GSWP/AF/GK/WKS/C1 /113/AMMA/LOT 4 / Request for Bids - Provision of 500 on-site Component 1 - Provision of Under Single Stage - One Works (without 2021-09- 2021-06- 2021-09- 2021-06- 2021-10- 2021-07- 2021-11- 2021-08- 2021-12- 2022-06- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Limited 250,000.00 268,852.47 Implementa Envelope prequalification) 02 14 07 18 19 29 18 19 23 21 benefiting 4,000 low income water supply services tion SPD beneficiaries in Asokore Mampong Municipal Assembly within the GKMA LOT 4 GH- MSWR/GSWP/AF/GK/WKS/C1 /113/OFMA/LOT4 / Provision Request for Bids - of 500 on-site household Component 1 - Provision of Under Single Stage - One Works (without 2021-09- 2021-06- 2021-09- 2021-06- 2021-10- 2021-07- 2021-11- 2021-12- 2022-06- toilet facilities benefiting IDA / 67810 environmental sanitation and Post Request for Bids Limited 250,000.00 0.00 Implementa Envelope prequalification) 02 14 07 18 19 16 18 23 21 4,000 low income water supply services tion SPD beneficiaries in Oforikrom Municipal Assembly within the GKMA LOT 4 GH- MSWR/GSWP/AF/GK/WKS/C1 /113/KWMA/LOT 4 / Request for Bids - Provision of 500 on-site Component 1 - Provision of Pending Single Stage - One Works (without 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- household toilet facilities IDA / 67810 environmental sanitation and Post Request for Bids Limited 250,000.00 0.00 Implementa Envelope prequalification) 02 07 19 18 23 21 benefiting 4,000 low income water supply services tion SPD beneficiaries in Kwadaso Municipal Assembly within the GKMA LOT 4 GH- MSWR/GSWP/AF/GK/WKS/C1 /113/TAMA/LOT4 / Provision Request for Bids - of 500 on-site household Component 1 - Provision of Under Single Stage - One Works (without 2021-09- 2021-06- 2021-09- 2020-06- 2021-10- 2021-07- 2021-11- 2021-12- 2022-06- toilet facilities benefiting IDA / 67810 environmental sanitation and Post Request for Bids Limited 250,000.00 0.00 Implementa Envelope prequalification) 02 14 07 18 19 29 18 23 21 4,000 low income water supply services tion SPD beneficiaries in Old Tafo Municipal Assembly within the GKMA LOT 4 GH- MSWR/GSWP/AF/GA/WK/C1/ 126/LOT 18 / Construction Request for Bids - Component 1 - Provision of Pending of additional 3 Gender Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 280,000.00 0.00 Implementa Friendly Institutional Toilets Envelope prequalification) 26 31 12 11 16 14 water supply services tion and WASH Facilities including SPD water connection (1Nr 12Seater at Ajin Kotoku Market) – GAMA GH- MSWR/GSWP/AF/GA/WK/C1/ 126/LOT19 / Construction of Request for Bids - additional 3 Gender Friendly Component 1 - Provision of Pending Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- Institutional Toilets and IDA / 67810 environmental sanitation and Post Request for Bids Limited 300,000.00 0.00 Implementa Envelope prequalification) 26 31 12 11 16 14 WASH Facilities including water supply services tion SPD water connection (1Nr 12Seater at Ajin Kotoku Markert) – GAMA- LOT 19 GH- MSWR/GSWP/AF/GA/WK/C1/ 126/LOT 20 / Construction Request for Bids - Component 1 - Provision of Pending of additional 3 Gender Single Stage - One Works (without 2021-08- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 67810 environmental sanitation and Post Request for Bids Limited 280,000.00 0.00 Implementa Friendly Institutional Toilets Envelope prequalification) 26 31 12 11 16 14 water supply services tion and WASH Facilities including SPD water connection (1Nr 12Seater at Ajin Kotoku Markert) – GAMA GH- MSWR/GSWP/AF/GA/WKS/ C1/126/LOT21 / Request for Bids - Construction of additional 3 Component 1 - Provision of Pending Single Stage - One Works (without 2021-09- 2021-09- 2021-09- 2021-09- 2021-11- 2022-05- Gender Friendly Institutional IDA / 67810 environmental sanitation and Post Request for Bids Limited 300,000.00 0.00 Implementa Envelope prequalification) 22 27 28 29 03 02 Toilets and WASH Facilities water supply services tion SPD including water connection (3Nr 12Seater within GWMA – GAMA GH- MSWR/GSWP/AF/GA/WKS/ C1/126/LOT22 / Request for Bids - Construction of additional 3 Component 1 - Provision of Pending Single Stage - One Works (without 2021-10- 2021-10- 2021-10- 2021-11- 2021-12- 2022-06- Gender Friendly Institutional IDA / 67810 environmental sanitation and Post Request for Bids Limited 350,000.00 0.00 Implementa Envelope prequalification) 04 09 23 13 18 16 Toilets and WASH Facilities water supply services tion SPD including Water connection (2Nr 20Seater plus 1Nr 24Seater within AMA) – GAMA GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSWR/GSWP/GD/018 / Supply of Office Furniture, Component 4 – Institutional Request for Single Stage - One 2018-11- 2019-01- 2018-12- 2019-01- Laptops, Desktop Computers, IDA / H8540 Post Limited 80,000.00 0.00 Canceled Strengthening Quotations Envelope 05 10 17 16 UPs for the new staff at the Project Coordinating Unit MSWR/GSWP/GD/41116/1 / Supply of Office Stationery and Consumables, Office Furniture, Laptops, UPs and Component 4 – Institutional Request for Single Stage - One 2019-04- 2019-03- 2019-05- 2019-05- 2020-01- IDA / H8540 Post Limited 60,000.00 8,051.80 Signed other Office Euipments as Strengthening Quotations Envelope 01 15 16 16 03 detailed below for project implemting units for PCU - LOT 1 MSWR/GSWP/GD/41116/2 / Supply of a set of Lorry Tyres - Ream 18, 12No. Ream 17 - Component 4 – Institutional Request for Single Stage - One 2019-04- 2019-03- 2019-05- 2019-05- 2019-06- 36No, for the following IDA / H8540 Post Limited 20,000.00 4,557.69 Signed Strengthening Quotations Envelope 02 11 14 16 13 project vehicles: - 2No Pajero, 3No Ford Explorer, 9 Double Cabin Pick Ups - LOT 2 MSWR/CBT/GSWP/GD/1111 / Design, pring and supply of marketing, promotional Component 1 - Provision of Under Request for Single Stage - One 2019-04- 2019-03- 2019-05- 2019-12- materials (flyers, posters, IDA / H8540 environmental sanitation and Post Limited 15,000.00 0.00 Implementati Quotations Envelope 03 15 15 31 banners, etc, ) for marketing water supply services on of toilet facilities and behaviour change education MSWR/CBT/GSWP/GD/1112 / Design, print and supply of marketing, promotional Component 1 - Provision of Request for Single Stage - One 2019-04- 2019-03- 2019-05- 2019-05- 2019-12- materials (T-Shirts, Caps, IDA / H8540 environmental sanitation and Post Limited 15,000.00 62,365.38 Signed Quotations Envelope 03 15 15 29 31 etc.) for marketing of toilet water supply services facilities and behaviour change education MSWR/CBT/GSWP/GD/4411 / Supply of additional 100No. Mobile Data Collection Component 4 – Institutional Request for Single Stage - One 2019-04- 2019-03- 2019-06- 2019-05- 2019-08- IDA / H8540 Post Limited 40,000.00 32,352.12 Signed Devices for ESICApps for the Strengthening Quotations Envelope 23 15 04 16 03 10 Newly Created MMAs in GAMA Page 9 MSWR/GSWP/GD/4821/1 / Supply of Office Equipment Pending and Consumables for the Component 4 – Institutional Request for Single Stage - One 2019-06- 2019-07- 2019-08- IDA / H8540 Post Limited 20,000.00 0.00 Implementati Social Accountability Unit of Strengthening Quotations Envelope 04 30 29 on the Ministry of Sanitation and Water Resources MSWR/GSWP/GD/4821/2 / Supply of Office Vehicle for the Office of the Social Component 4 – Institutional Request for Single Stage - One 2019-07- 2019-08- 2019-09- IDA / H8540 Post Limited 30,000.00 0.00 Canceled Accountability Unit of the Strengthening Quotations Envelope 01 26 25 Ministry of Sanitation and Water Resources GH- MSWR/GSWP/AF/GK/GDS/ C4/4201 - LOT 1 / Project Component 1 - Provision of Single Stage - One 2021-02- 2021-03- 2021-03- 2021-03- 2021-04- 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2021-12- Vehicles for 8MMAs for IDA / 67810 environmental sanitation and Prior Request for Bids Open - National 350,000.00 345,362.55 Signed Envelope 26 12 03 22 14 29 14 10 18 12 15 Project Implementation and water supply services Monitoring – One for each MMA (8Nr Pickups) GH- MSWR/GSWP/AF/GK/GDS/ Component 1 - Provision of C4/4201 - LOT 2 / Project Single Stage - One 2021-02- 2021-03- 2021-03- 2021-03- 2021-04- 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2021-12- IDA / 67810 environmental sanitation and Prior Request for Bids Open - National 600,000.00 604,317.02 Signed Vehicles for PCU team for Envelope 26 12 03 18 14 29 14 09 18 12 15 water supply services Project Implementation and Monitoring – (10Nr Pickups) GH- MSWR/GSWP/AF/GK/GDS/ C4/4201 - LOT 3 / Project Component 1 - Provision of Single Stage - One 2021-02- 2021-03- 2021-03- 2021-03- 2021-04- 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2021-12- Vehicles for the Project IDA / 67810 environmental sanitation and Prior Request for Bids Open - National 400,000.00 414,165.25 Signed Envelope 26 12 03 18 14 29 14 10 18 12 15 Implementation and water supply services monitoring team (3Nr Cross Country Vehicles) GH- MSWR/GSWP/AF/GK/GDS/ Component 1 - Provision of C4/4201 - LOT 4 / Project Single Stage - One 2021-02- 2021-03- 2021-03- 2021-03- 2021-04- 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2021-12- IDA / 67810 environmental sanitation and Prior Request for Bids Open - National 250,000.00 255,413.15 Signed Vehicles for the Project Envelope 26 12 03 18 14 29 14 10 18 12 15 water supply services Implementation and monitoring team (3Nr SUVs) GH-MSWR/GSWP/AF/GAK /GDS/ C4/4202 / Supply and Installation of Office Component 4 – Institutional Request for Single Stage - One 2021-02- 2021-01- 2021-04- 2021-03- 2021-10- IDA / 67810 Post Limited 50,000.00 44,671.16 Signed Furniture (Desks, Chairs, Strengthening Quotations Envelope 19 12 16 30 13 Conference Tables, etc) for the PCU-Sub Office in GKMA GH-MSWR/GSWP/AF/GAK/ GDS/ C4/4209 / Supply and Component 1 - Provision of Pending Request for Single Stage - One 2021-05- 2021-07- 2022-01- Installation of Office Curtains IDA / 67810 environmental sanitation and Post Limited 20,000.00 0.00 Implementati Quotations Envelope 19 14 10 and blinds in the PCU-Sub water supply services on Office in GKMA (12 Windows) GH-MSWR/GSWP/AF/GAK/ GDS/ C4/4210 / Supply and Component 1 - Provision of Request for Single Stage - One 2021-05- 2021-01- 2021-07- 2021-07- 2022-01- Installation 30KVA Generator IDA / 67810 environmental sanitation and Post Limited 50,000.00 29,371.21 Signed Quotations Envelope 19 12 14 22 10 Plant in the PCU-Sub Office in water supply services GKMA GH-MSWR/GSWP/AF/GAK /GDS/ C4/4211 / Office Equipment (20 Laptop Component 1 - Provision of Under Request for Single Stage - One 2021-02- 2021-01- 2021-03- 2021-09- Computers, 2 Photocopiers, IDA / 67810 environmental sanitation and Post Limited 80,000.00 0.00 Implementati Quotations Envelope 03 12 31 27 Printers, c) for the 8 MMAs, water supply services on PCU-Sub Office in GKMA & GAMA GH- MSWR/GSWP/AF/GK/GDS/ Component 1 - Provision of Under C1/1201 / Motor Bikes Request for Single Stage - One 2021-04- 2021-09- 2021-05- 2021-08- IDA / 67810 environmental sanitation and Post Limited 100,000.00 0.00 Implementati (16Nr) and Accessories for Quotations Envelope 04 29 30 28 water supply services on Household Toilet Monitoring Team for the 8MMA in GKMA GH-MSWR/GSWP/AF/GAK/ GDS/ C4/4203 / Stationery & Component 1 - Provision of Request for Single Stage - One 2021-06- 2021-04- 2021-08- 2021-07- 2022-01- Consumables for 8MMAs and IDA / 67810 environmental sanitation and Post Limited 75,000.00 24,971.85 Signed Quotations Envelope 06 29 01 22 28 PCU-Sub Office in GKMA & water supply services GAMA – Framework GH-MSWR/GSWP/AF/GAK/ GDS/ C4/4206 - LOT1 / Lorry Tyres for Project Component 1 - Provision of Under Request for Single Stage - One 2021-06- 2021-09- 2021-07- 2022-01- Vehicles for 8MMAs and PCU IDA / 67810 environmental sanitation and Post Limited 20,000.00 0.00 Implementati Quotations Envelope 03 28 29 25 Sub-Office – GKMA and PCU water supply services on & 25 MMAs in GAMA – Framework Agreement GH-MSWR/GSWP/AF/GAK/ GDS/ C4/4206 - LOT2 / Lorry Tyres for Project Component 1 - Provision of Under Request for Single Stage - One 2021-06- 2021-09- 2021-07- 2022-01- Vehicles for 8MMAs and PCU IDA / 67810 environmental sanitation and Post Limited 20,000.00 0.00 Implementati Quotations Envelope 03 23 29 25 Sub-Office – GKMA and PCU water supply services on & 25 MMAs in GAMA – Framework Agreement GH- MSWR/GSWP/AF/GK/GDS/ Component 1 - Provision of Pending C4/4207 / Procurement of Request for 2021-06- 2021-08- 2022-01- IDA / 67810 environmental sanitation and Post 50,000.00 0.00 Implementati Data Collection Devices (ICT Quotations 06 01 28 water supply services on Logistics) for implementation of ESICApps in GKMA GH-MSWR/GSWP/AF/GAK/ GDS/ C4/4208 / Supply and Installation of Component 1 - Provision of Telecomminication & Request for Single Stage - One 2021-05- 2021-04- 2021-07- 2021-07- 2022-01- IDA / 67810 environmental sanitation and Post Limited 100,000.00 16,840.73 Signed Conference Facilities in the Quotations Envelope 19 29 14 13 10 water supply services PCU Office in Accra and PCU- Sub Office in GKMA & MSWR Conference Room GH-MSWR/GSWP/AF/GAK/ GDS/ C4/4204 / Designing, printing and dissemination of Component 1 - Provision of Pending Behaviour Change & Request for Single Stage - One 2021-04- 2021-06- 2021-12- IDA / 67810 environmental sanitation and Post Limited 75,000.00 0.00 Implementati Communication Materials – Quotations Envelope 11 06 03 water supply services on Posters, Flyers, Banners, Stickers, etc. – GKMA & GAMA: Framework Agreement GH-MSWR/GSWP/AF/GAK/ GDS/ C1/1202 / Component 1 - Provision of Pending Reproduction of project Request for Single Stage - One 2021-04- 2021-06- 2021-12- IDA / 67810 environmental sanitation and Post Limited 100,000.00 0.00 Implementati materials e,g, reports, Quotations Envelope 11 06 03 water supply services on brochures, manuals, etc. – GKMA & GAMA – Framework GH-MSWR/GSWP/AF/GAK/ GDS/ C4/4205 / Designing, printing and dissemination of Component 1 - Provision of Pending Behaviour Change & Request for Single Stage - One 2021-07- 2021-09- 2022-03- IDA / 67810 environmental sanitation and Post Limited 100,000.00 0.00 Implementati Communication Materials – T- Quotations Envelope 11 05 04 water supply services on Shirts, Polo-Shirts, Caps, etc. – GKMA and GAMA – Framework Agreement Page 10 GH-MSWR/GSWP/AF/GAK /GD/ C4/4211 / Office Equipment (25 Laptop Component 1 - Provision of Under Request for Single Stage - One 2021-06- 2021-04- 2021-08- 2022-02- Computers, 2 Photocopiers, IDA / 67810 environmental sanitation and Post Limited 90,000.00 0.00 Implementati Quotations Envelope 13 29 08 04 Printers, c) for the 8 MMAs, water supply services on PCU-Sub Office in GKMA & GAMA NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSWR/GSWP/NC/1212 / Non- consulting services for using Component 1 - Provision of Under mobile money Request for Single Stage - One 2019-06- 2019-09- 2019-07- 2020-05- IDA / H8540 environmental sanitation and Post Limited 10,000.00 0.00 Implementati (interoprability) for Quotations Envelope 03 18 29 29 water supply services on mobilization of beneficiary contribution for household toilet CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSWR/GSWP/PM/023 / Consultancy services an Component 1 - Provision of Consultant 2018-11- 2018-11- 2019-01- 2019-02- 2019-02- 2019-05- 2019-02- 2019-05- 2020-02- independent verification IDA / H8540 environmental sanitation and Post Qualification Open - National 300,000.00 146,131.99 Signed 2018-10-31 12 21 04 07 03 30 24 30 24 agency for household toilet water supply services Selection construction MSWR/GSWP/PM/021 / Component 1 - Provision of Least Cost Under 2019-01- 2019-03- 2019-05- 2019-02- 2019-06- 2019-02- 2019-07- 2019-03- 2019-08- 2019-05- 2019-09- 2020-03- Selection of Project External IDA / H8540 environmental sanitation and Post Open - National 100,000.00 0.00 2019-03-05 Selection Implementation 25 26 09 07 06 26 06 12 10 07 14 12 Auditors water supply services MSWR/GSWP/C/4514 / Consultancy Services for Consultant Component 4 – Institutional 2019-06- 2019-06- 2019-08- 2019-08- 2019-09- 2020-02- 2019-09- 2020-02- 2019-12- implementation support for IDA / H8540 Post Qualification Open - National 100,000.00 100,048.00 Signed 2019-05-30 Strengthening 03 20 03 09 02 14 23 14 30 scalling up solutions from Selection Hackaton MSWR/GSWP/IC/19/3114 / Consulting Services for a Study of the Institutional, Policy, Financial and Legal Consultant Component 4 – Institutional Open - Under 2019-12- 2019-12- 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- situation of the WASH Sector IDA / H8540 Post Qualification 300,000.00 0.00 2019-11-12 Strengthening International Implementation 09 03 12 16 15 21 17 in Ghana; A review of the Selection current situation and proposal for reforms to improve WASH management in Ghana MSWR/GSWP/C/4516 / Consultancy Services to Consultant conduct study to assess Component 4 – Institutional 2019-07- 2019-08- 2019-09- 2019-10- 2020-04- IDA / H8540 Post Qualification Open - National 150,000.00 0.00 Canceled 2019-06-25 business opportunity for the Strengthening 16 29 28 26 23 Selection market for deslufging services in Ghana MSWR/GSWP/C/491/20/04 / Consultancy Services to undertake Beneficiary Consultant Component 4 – Institutional 2019-12- 2020-02- 2020-03- 2020-04- 2020-06- 2020-08- Assessment of the GAMA IDA / H8540 Post Qualification Open - National 100,000.00 0.00 Under Review 2020-01-30 Strengthening 05 20 12 27 25 24 Project intervention for the Selection Implementation Completion Report MSWR/GSWP/PM/018 / Consultancy services to Component 4 – Institutional Least Cost Pending 2020-02- 2020-04- 2020-04- 2020-05- 2020-06- 2020-07- 2020-10- IDA / H8540 Post Open - National 100,000.00 0.00 2020-02-04 undertake Safeguards Audit Strengthening Selection Implementation 18 02 30 23 27 18 16 of the GAMA Project GH- MSWR/GSWP/AF/GA/CON/C1 /1401 LOT1 / Consultancy services for packaging, preparation of safeguards Component 1 - Provision of Consultant 2020-11- 2021-02- 2021-03- 2021-02- 2021-04- 2021-04- 2021-05- 2021-05- 2021-11- instruments, preparation of IDA / 67810 environmental sanitation and Post Qualification Open - National 350,000.00 358,500.00 Signed 2021-01-27 02 01 17 23 16 19 21 10 17 tender document and water supply services Selection construction supervision of Gender Friendly Institutional Toilet Facilities (2 Lots in GAMA) GH-MSWR/GSWP/AF/GA/ CON/C1/1401 - LOT 2 / Consultancy services for packaging, preparation of Component 1 - Provision of Consultant safeguards instruments, 2020-11- 2021-01- 2021-03- 2021-02- 2021-04- 2021-04- 2021-05- 2021-05- 2021-11- IDA / 67810 environmental sanitation and Post Qualification Open - National 350,000.00 375,605.00 Signed 2021-01-27 preparation of tender 02 27 12 23 11 15 16 10 12 water supply services Selection document and construction supervision of Gender Friendly Institutional Toilet Facilities (Lot 2 in GAMA) GH- MSWR/GSWP/AF/GK/CON/ Component 1 - Provision of Consultant Pending 2021-03- 2021-05- 2021-06- 2021-07- 2022-01- C4/4401 / Consultancy IDA / 67810 environmental sanitation and Post Qualification Open - National 200,000.00 0.00 2021-02-27 Implementation 20 03 02 07 03 Services for preparation water supply services Selection WASH Baseline Studies in GKMA. GH- MSWR/GSWP/AF/GK/CON/ C1/1403 - LOT 1 / Consultancy Services for Provision of Gender and Component 1 - Provision of Consultant Disability Inclusive Under 2020-11- 2021-02- 2021-03- 2021-06- 2021-04- 2021-08- 2021-05- 2021-11- IDA / 67810 environmental sanitation and Post Qualification Open - National 300,000.00 0.00 2021-01-20 Institutional Sanitation and Implementation 02 10 26 22 25 05 30 26 water supply services Selection Water Supply Facilities, covering needs assessment, designs, Packaging for Project Intervention, Preparation of Tender Documents etc GH- MSWR/GSWP/AF/GK/CON/ C1/1403 - LOT 2 / Consultancy Services for Provision of Gender and Component 1 - Provision of Consultant Disability Inclusive Under 2020-11- 2021-02- 2021-03- 2021-06- 2021-04- 2021-05- 2021-11- IDA / 67810 environmental sanitation and Post Qualification Open - National 300,000.00 0.00 2021-01-20 Institutional Sanitation and Implementation 02 10 26 22 25 30 26 water supply services Selection Water Supply Facilities, covering needs assessment, designs, Packaging for Project Intervention, Preparation of Tender Documents etc Page 11 GH- MSWR/GSWP/AF/GK/CON/ C1/1403 - LOT 3 / Consultancy Services for Provision of Gender and Component 1 - Provision of Consultant Disability Inclusive Under 2020-11- 2021-02- 2021-03- 2021-06- 2021-04- 2021-05- 2021-11- IDA / 67810 environmental sanitation and Post Qualification Open - National 300,000.00 0.00 2021-01-20 Institutional Sanitation and Implementation 02 10 26 22 25 30 26 water supply services Selection Water Supply Facilities, covering needs assessment, designs, Packaging for Project Intervention, Preparation of Tender Documents etc GH- MSWR/GSWP/AF/GK/CON/ C1/1403 - LOT 4 / Consultancy Services for Provision of Gender and Component 1 - Provision of Consultant Disability Inclusive Under 2020-11- 2021-02- 2021-03- 2021-06- 2021-04- 2021-05- 2021-11- IDA / 67810 environmental sanitation and Post Qualification Open - National 300,000.00 0.00 2021-01-20 Institutional Sanitation and Implementation 02 10 26 22 25 30 26 water supply services Selection Water Supply Facilities, covering needs assessment, designs, Packaging for Project Intervention, Preparation of Tender Documents etc GH- MSWR/GSWP/AF/GK/CON/ C3/3403 / Consultancy services for assessment, detail designs of sewerage Component 3 – Planning, rehabilitation and expansion, improvement & expansion of Quality And Cost- Under 2021-04- 2021-02- 2021-04- 2021-02- 2021-05- 2021-06- 2021-07- 2021-08- 2022-02- IDA / 67810 Post Open - National 450,000.00 0.00 2021-02-10 preparation of tender Environmental Sanitation Based Selection Implementation 07 24 09 10 07 06 11 15 11 document for proposed Services system improvement/development in the Greater Kumasi Metropolitan Area (GKMA) GH- MSWR/GSWP/AF/GA/CON/ Component 1 - Provision of Least Cost Pending 2021-09- 2021-10- 2021-11- 2021-12- 2022-02- 2022-03- 2022-09- C1/1402 - LOT 1 / Services IDA / 67810 environmental sanitation and Post Open - National 100,000.00 0.00 2021-08-27 Selection Implementation 17 31 28 28 01 08 04 as an Independent water supply services Verification Agency – GAMA GH- MSWR/GSWP/AF/GA/CON/ Component 1 - Provision of Least Cost Pending 2021-09- 2021-10- 2021-11- 2021-12- 2022-02- 2022-03- 2022-09- C1/1402 - LOT 2 / Services IDA / 67810 environmental sanitation and Post Open - National 100,000.00 0.00 2021-08-27 Selection Implementation 17 31 28 28 01 08 04 as an Independent water supply services Verification Agency – GAMA GH- MSWR/GSWP/AF/GAK/CON/ Component 1 - Provision of Least Cost Under 2021-10- 2021-09- 2021-10- 2021-11- 2021-12- 2021-12- 2022-02- 2022-03- 2022-09- C4/4402 / Services for IDA / 67810 environmental sanitation and Post Open - National 100,000.00 0.00 2021-08-30 Selection Implementation 18 20 27 03 01 31 04 11 07 Independent Annual Financial water supply services Audits for GAMA – AF Project GH- MSWR/GSWP/AF/GAK/CON/C Component 1 - Provision of Consultant 3/3406 / Consultancy Pending 2021-12- 2022-01- 2022-02- 2022-03- 2022-08- IDA / 67810 environmental sanitation and Post Qualification Open - National 100,000.00 0.00 2021-11-23 Services for Feasibility Study Implementation 14 18 17 04 31 water supply services Selection for Proposed Bio-Digester Treatment Facility INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSWR/GSWP/C3-CS/002 / Consultancy services for prepartion of detailed engineering design and Component 1 - Provision of preparation of tender 2018-03- 2018-05- 2018-09- IDA / H8540 environmental sanitation and Prior Direct Selection Direct 550,000.00 0.00 Under Review 2018-02-28 documents of the proposed 29 19 13 water supply services rehabilitation of faecal sludge treatment plant(s) and construction supervision - NUNGUA FARM MSWR/GSWP/PM/014 / Individual Consultancy Services as Component 4 – Institutional 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- 2019-04- IDA / H8540 Post Consultant Limited 50,000.00 0.00 Canceled 2018-02-28 Monitoring and Evaluation Strengthening 22 05 29 26 23 16 16 Selection Expert MSWR/GSWP/PM/020 / Consultancy services to Individual Component 4 – Institutional 2018-10- 2018-05- 2018-06- 2018-06- 2018-12- undertake Indepth Financial IDA / H8540 Post Consultant Limited 30,000.00 0.00 Canceled 2018-05-08 Strengthening 03 13 03 24 21 Management Review of the Selection GAMA Project MSWR/GSWP/PM/022A / Component 1 - Provision of Individual Assistance Engineer for 2018-05- 2018-11- 2018-08- 2018-11- 2019-05- 2018-12- 2019-06- 2019-12- IDA / H8540 environmental sanitation and Post Consultant Open 15,000.00 2,263.46 Signed 2018-10-09 Household Toilet Delivery - 17 11 29 25 29 30 03 25 water supply services Selection GSMA MSWR/GSWP/PM/022B / Component 1 - Provision of Individual Assistance Engineer for 2018-05- 2018-11- 2018-08- 2018-11- 2019-05- 2018-12- 2019-06- 2019-12- IDA / H8540 environmental sanitation and Post Consultant Open 15,000.00 2,263.46 Signed 2018-10-09 Household Toilet Delivery - 17 11 29 25 29 30 03 25 water supply services Selection GCMA MSWR/GSWP/PM/022C / Component 1 - Provision of Individual Assistance Engineer for 2018-11- 2018-08- 2018-12- 2019-01- 2020-01- IDA / H8540 environmental sanitation and Post Consultant Open 15,000.00 0.00 Canceled 2018-10-24 Household Toilet Delivery - 26 29 10 14 09 water supply services Selection GSMA MSWR/GSWP/PM/022D / Component 1 - Provision of Individual Assistance Engineer for 2018-11- 2018-08- 2018-12- 2019-01- 2020-01- IDA / H8540 environmental sanitation and Post Consultant Open 15,000.00 0.00 Canceled 2018-10-24 Household Toilet Delivery - 26 29 10 14 09 water supply services Selection GCMA MSWR/GSWP/PM/022E / Component 1 - Provision of Individual Assistance Engineer for 2018-11- 2018-08- 2018-12- 2019-01- 2020-01- IDA / H8540 environmental sanitation and Post Consultant Open 15,000.00 0.00 Canceled 2018-10-24 Household Toilet Delivery - 26 29 10 14 09 water supply services Selection GSMA MSWR/GSWP/C4-CB/011 / Consulting Services as a Individual LEGAL EXPERT to support Component 4 – Institutional 2018-11- 2018-05- 2018-12- 2018-07- 2018-12- 2018-08- 2019-12- IDA / H8540 Post Consultant Open 60,000.00 48,000.00 Signed 2018-10-24 MSWR for the extablishment Strengthening 26 17 10 26 31 08 26 Selection of the National Sanitation Authority MSWR/GSWP/C4-CB/012 / Consulting Services as a Individual COMMUNICATIONS EXPERT to Component 4 – Institutional 2018-11- 2018-12- 2018-12- 2019-12- IDA / H8540 Post Consultant Open 60,000.00 0.00 Canceled 2018-10-24 support MSWR for the Strengthening 26 10 31 26 Selection extablishment of the National Sanitation Authority MSWR/GSWP/PM/017 / Consultancy services for the Component 1 - Provision of Individual assessment of the 2018-12- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-07- IDA / H8540 environmental sanitation and Post Consultant Open 50,000.00 64,500.00 Signed 2018-10-31 effectiveness of the GRM 19 18 09 21 30 25 29 water supply services Selection Systems implemented under the GAMA Page 12 MSWR/GSWP/IC/19/3113 / Consultancy Services for WASH Assessment of the Greater Kumasi Metropolitan Individual Component 4 – Institutional Pending 2019-12- 2019-12- 2020-01- 2020-03- Area Sanitation and Water IDA / H8540 Post Consultant Limited 70,000.00 0.00 2019-11-27 Strengthening Implementation 02 23 27 27 Project to Replicate the Selection Results and Impact of the GAMA Sanitation and Water Project MSWR/GSWP/PM/493/20/01 / Consultancy Services for the Individual Preparation of Borrowers Component 4 – Institutional Pending 2020-02- 2020-03- 2020-04- 2020-07- IDA / H8540 Post Consultant Limited 100,000.00 0.00 2020-02-20 Implementation Completion Strengthening Implementation 25 17 21 20 Selection Report (ICR) for the GAMA Project MSWR/GSWP/C/41112 / Selection of an Individual Individual Component 4 – Institutional 2019-04- 2019-04- 2019-05- 2020-05- Consultant for the position of IDA / H8540 Post Consultant Limited 15,000.00 0.00 Canceled 2019-03-28 Strengthening 02 23 17 16 Assistant Behaviour Change Selection Communications (BCC) Officer MSWR/GSWP/C/4727 / Consultancy Services to Individual develop learning and Component 4 – Institutional 2020-02- 2020-03- 2020-03- 2020-06- IDA / H8540 Post Consultant Limited 40,000.00 0.00 Canceled 2020-02-18 knowledge materials on all Strengthening 23 15 23 21 Selection componets of the GAMA projects MSWR/GSWP/C/4515 / Consulting Services to Individual Component 4 – Institutional 2020-02- 2020-03- 2020-04- 2020-06- conduct market sounding IDA / H8540 Post Consultant Limited 30,000.00 0.00 Canceled 2020-02-18 Strengthening 23 15 05 04 exposition to obtain and Selection packahge bankable proposals MSWR/GSWP/C/41233 / Selection of an Independent Individual Component 4 – Institutional 2020-02- 2020-03- 2020-03- 2020-05- Consultant to undertake IDA / H8540 Post Consultant Limited 50,000.00 0.00 Canceled 2020-02-04 Strengthening 09 01 15 14 Procurement Audit of the Selection GAMA GH- Individual MSWR/GSWP/AF/GAK/CON/ Component 4 – Institutional 2020-08- 2021-01- 2020-09- 2021-02- 2021-06- 2021-03- 2021-06- 2021-09- IDA / 67810 Post Consultant Limited 240,000.00 4,000.00 Signed 2021-01-22 C4/4415 / Social Strengthening 25 27 10 17 01 24 29 20 Selection Development Expert GH- Individual MSWR/GSWP/AF/GAK/CON/ Component 4 – Institutional Pending 2021-03- 2021-04- 2021-05- 2021-11- IDA / 67810 Post Consultant Limited 240,000.00 0.00 2021-03-14 C4/4419 / WASH Technical Strengthening Implementation 19 09 14 10 Selection Expert for CBT Team GH- MSWR/GSWP/AF/GAK/CON/ Individual Component 4 – Institutional Under 2021-06- 2021-03- 2021-04- 2021-05- 2021-11- C4/4420 / Knowledge IDA / 67810 Post Consultant Limited 240,000.00 0.00 2021-03-14 Strengthening Implementation 18 19 09 14 10 Management Expert for CBT Selection Team GH- Individual MSWR/GSWP/AF/GAK/CON/ Component 4 – Institutional Pending 2021-03- 2021-04- 2021-05- 2021-11- IDA / 67810 Post Consultant Limited 160,000.00 0.00 2021-03-14 C4/4421 / IT Officer for CBT Strengthening Implementation 19 09 14 10 Selection Team GH- MSWR/GSWP/AF/GK/CON/ Individual Component 4 – Institutional Under 2020-08- 2021-01- 2021-02- 2021-03- 2021-09- C4/4422 / GKMA IDA / 67810 Post Consultant Limited 240,000.00 0.00 2021-01-22 Strengthening Implementation 25 27 17 24 20 Infrastructure Engineer - Selection Office Manager GH- MSWR/GSWP/AF/GK/CON/ C4/4423 - LOT 1 / Individual Consultancy Services as a Team Coach to facilitate Individual results-oriented work of the Component 4 – Institutional Pending 2021-03- 2021-04- 2021-05- 2021-11- IDA / 67810 Post Consultant Open 60,000.00 0.00 2021-01-22 MMA teams and other project Strengthening Implementation 12 02 07 03 Selection actors for the Provision of Improved Household Toilets in Low Income Communities of Greater Kumasi Metropolitan Area (GKMA) GH- MSWR/GSWP/AF/GK/CON/ C4/4423 - LOT 2 / Individual Consultancy Services as a Team Coach to facilitate Individual results-oriented work of the Component 4 – Institutional Pending 2021-03- 2021-04- 2021-05- 2021-11- IDA / 67810 Post Consultant Open 60,000.00 0.00 2021-01-22 MMA teams and other project Strengthening Implementation 12 02 07 03 Selection actors for the Provision of Improved Household Toilets in Low Income Communities of Greater Kumasi Metropolitan Area (GKMA) GH- MSWR/GSWP/AF/GK/CON/ C4/4423 - LOT 3 / Individual Consultancy Services as a Team Coach to facilitate Individual results-oriented work of the Component 4 – Institutional Pending 2021-03- 2021-04- 2021-05- 2021-11- IDA / 67810 Post Consultant Open 60,000.00 0.00 2021-01-22 MMA teams and other project Strengthening Implementation 12 02 07 03 Selection actors for the Provision of Improved Household Toilets in Low Income Communities of Greater Kumasi Metropolitan Area (GKMA) GH- MSWR/GSWP/AF/GK/CON/ C4/4423 - LOT 4 / Individual Consultancy Services as a Team Coach to facilitate Individual results-oriented work of the Component 4 – Institutional Pending 2021-03- 2021-04- 2021-05- 2021-11- IDA / 67810 Post Consultant Open 60,000.00 0.00 2021-01-22 MMA teams and other project Strengthening Implementation 12 02 07 03 Selection actors for the Provision of Improved Household Toilets in Low Income Communities of Greater Kumasi Metropolitan Area (GKMA) GH- MSWR/GSWP/AF/GK/CON/ C4/4406 / Consultancy Component 4 – Institutional Pending 2021-08- 2021-10- 2022-04- Services to update ESICApp IDA / 67810 Post Direct Selection Direct 100,000.00 0.00 2021-07-30 Strengthening Implementation 09 13 11 Mobile Application and Roll- out Implementation and Management in GKMA GH- MSWR/GSWP/AF/GK/CON/ C3/3405 / Consultancy Services for the preparation Component 1 - Provision of Individual Pending 2021-12- 2022-01- 2022-02- 2022-08- of Environmental & Social IDA / 67810 environmental sanitation and Post Consultant Open 100,000.00 0.00 2021-10-27 Implementation 15 05 09 08 Management Plans and water supply services Selection Resettlement Action Plans for Specialised Bio-digester Treatment Facility – GKMA Page 13 GH- MSWR/GSWP/AF/GK/CON/ C3/3402 / Consultancy Component 1 - Provision of Individual services for the preparation Pending 2021-01- 2021-02- 2021-03- 2021-09- IDA / 67810 environmental sanitation and Post Consultant Limited 100,000.00 0.00 2021-01-21 of environmental and social Implementation 26 16 23 19 water supply services Selection impact assessment (ESIA) for the construction of simplified sewerage system – GKMA GH- MSWR/GSWP/AF/GK/CON/ C1/1404 / Consultancy Component 1 - Provision of Individual Services for the preparation Pending 2021-11- 2021-12- 2022-01- 2022-07- IDA / 67810 environmental sanitation and Post Consultant Open 100,000.00 0.00 2021-09-30 of Environmental & Social Implementation 18 09 13 12 water supply services Selection Management Plans for Institutional Toilet Facilities – GKMA GH- MSWR/GSWP/AF/GK/CON/ Component 1 - Provision of Individual C3/3404 / Preparation of Pending 2021-10- 2021-10- 2021-11- 2022-05- IDA / 67810 environmental sanitation and Post Consultant Limited 100,000.00 0.00 2021-09-30 resettlement action plan for Implementation 05 26 30 29 water supply services Selection the construction of simplified sewerage system – GKMA GH- MSWR/GSWP/AF/GAK/CON/ C3/3401 / Consultancy services for the preparation Component 1 - Provision of Individual of environmental and social Pending 2021-12- 2022-01- 2022-02- 2022-08- IDA / 67810 environmental sanitation and Post Consultant Open 100,000.00 0.00 2021-11-07 impact assessment (ESIA) and Implementation 16 06 10 09 water supply services Selection Resettlement Action Plan for Specialised Bio-digester Treatment Facility – GAMA & GKMA GH- MSWR/GSWP/AF/GK/CON/ C1/12801 / Consultancy Component 1 - Provision of Individual Services for the preparation Under 2021-09- 2021-06- 2021-09- 2021-07- 2021-10- 2021-08- 2021-10- IDA / 67810 environmental sanitation and Post Consultant Limited 100,000.00 0.00 2021-06-15 of Environmental & Social Implementation 22 20 22 11 17 15 14 water supply services Selection Management Plans for Institutional Toilet Facilities – GAMA GH- MSWR/GSWP/AF/GAK/CON/ C4/4403 / Services for Component 1 - Provision of Individual Pending 2021-11- 2021-12- 2022-01- 2022-07- Independent Annual IDA / 67810 environmental sanitation and Post Consultant Open 50,000.00 0.00 2021-09-30 Implementation 18 09 13 12 Procurement Audit by an water supply services Selection Independent Consultant for GKMA & GAMA GH- MSWR/GSWP/AF/GAK/CON/ Individual C4/4404 / Services for Component 4 – Institutional Pending 2021-11- 2021-11- 2021-12- 2022-06- IDA / 67810 Post Consultant Limited 50,000.00 0.00 2021-10-30 Independent Annual Strengthening Implementation 04 25 30 28 Selection Safeguards Audit for GKMA & GAMA GH- MSWR/GSWP/AF/GK/CON/ C4/4405 / Consultancy Component 1 - Provision of Individual Pending 2021-06- 2021-06- 2021-08- 2022-01- Services to conduct capacity IDA / 67810 environmental sanitation and Post Consultant Limited 50,000.00 0.00 2021-06-03 Implementation 08 29 03 30 needs assessment of the water supply services Selection participating MMAs and RCC in GKMA GH- MSWR/GSWP/AF/GK/CON/ C4/4407 / Consultancy Services to develop Integrated Component 1 - Provision of Individual Pending 2021-07- 2021-08- 2021-09- 2022-03- Sustainable Gender Based IDA / 67810 environmental sanitation and Post Consultant Open 50,000.00 0.00 2021-05-30 Implementation 18 08 12 11 Violence guidelines, water supply services Selection tools/toolkits and indicators for project implementers – GKMA GH- MSWR/GSWP/AF/GAK/CON/ C4/4408 / Consultancy Component 1 - Provision of Individual Services to undertake Pending 2021-08- 2021-09- 2021-10- 2022-04- IDA / 67810 environmental sanitation and Post Consultant Open 50,000.00 0.00 2021-06-30 baseline study for the girls Implementation 18 08 13 11 water supply services Selection school attendance in relation to WASH Infrastructure availability GH- MSWR/GSWP/AF/GAK/CONS/ C3/3401 / Consultancy services for the preparation Component 1 - Provision of Individual of environmental and social Pending 2021-11- 2021-12- 2022-02- 2022-08- IDA / 67810 environmental sanitation and Post Consultant Limited 100,000.00 0.00 2021-11-07 impact assessment (ESIA) and Implementation 12 03 05 04 water supply services Selection Resettlement Action Plan for Specialised Bio-digester Treatment Facility – GAMA & GKMA Page 14