Updated on : 13/02/2013 Procurement Plan for Works Contract Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method 2 Opening (Actual of Contract Completion Contractor Procurement Review (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 01. BRA/UZR-1 UZR-1.1 Mogra Bazar (GC)-Satpara R&H Road via Km 7.02 81.44 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Kornel Bazar,Dhaturpohela UZR-1.2 Tinlacpir R&H to Shimrail GC via Chargas Km 3.91 45.36 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Bazar & Bhallabpur Road 02. CHA/UZR-2 Belchow-Ramchandrapur-Sameshpur- Km 8.00 92.80 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Nadighat road. 03. CTG/UZR-3 Chunati pantissa via narinna chandah patial Km 8.33 96.63 NCB BG No 11/1/2013 12/31/2013 7/4/2015 para road 04. COM/UZR-4 UZR-4.1 Comilla- Mazigacha Palpara-B. Para-Mirpur Km 7.00 81.20 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Rd UZR-4.2 Comilla- Mazigacha Palpara-B. Para-Mirpur Km 7.75 89.90 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Rd 05. COM/UZR-5 Upazila H/Q (Nabagram)-Munshirhat- Km 6.10 70.76 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Kashinagar UP-Suagonj(Isshor Mazumder) Road 06. COM/UZR-6 Rajeshpur-Kamalpur-Nalkuri-Matiara- Km 6.49 75.28 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Srimantapur-Chandpur ROAD 07. GAZ/UZR-7 Goshinga-Rajabari Km 5.00 58.00 NCB BG No 11/1/2013 12/31/2013 7/4/2015 08. HAB/UZR-8 UZR-8.1 Assampara Bazar-Amorote Bazar via Manik Km 5.00 58.00 NCB BG No 11/1/2013 12/31/2013 7/4/2015 vander & saddam bazar UZR-8.2 Assampara Bazar-Amorote Bazar via Manik Km 5.13 59.51 NCB BG No 11/1/2013 12/31/2013 7/4/2015 vander & saddam bazar UZR-8.3 Hobigonj-Baniachong R&H Road Km 3.35 38.86 NCB BG No 11/1/2013 12/31/2013 7/4/2015 (Chilapanja)-Azmiregonj gc Road via Shibpasha 09. JAM/UZR-9 Ambaria R&H to Pachabohola GC via Km 6.07 70.41 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Ruknai bazar. 10. KIS/UZR-10 UZR-10.1 Tarail-Karimgonj Road Km 5.16 59.80 NCB BG No 11/1/2013 12/31/2013 7/4/2015 UZR-10.2 Karimganj-Tarail GC Road Km 3.68 42.63 NCB BG No 11/1/2013 12/31/2013 7/4/2015 11. MOU/UZR-11 Shindurkhan-khejuricherra bazar Road Km 4.50 52.20 NCB BG No 11/1/2013 12/31/2013 7/4/2015 12. MYM/UZR-12 UZR-12.1 Hatkalir Bazar to Patira Bazar R&H via Km 7.00 81.20 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Keshoregonj GC UZR-12.2 Hatkalir Bazar to Patira Bazar R&H via Km 5.97 69.25 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Keshoregonj GC 13. NARA/UZR-13 Araihazar-Elomdi-Jangalia Bazar-Uchitpura. Km 8.49 98.48 NCB BG No 11/1/2013 12/31/2013 7/4/2015 14. NET/UZR-14 Teosree GC-Taral GC (Dhankunia Ferry Km 9.48 109.97 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Ghat) road via Akarsree & Singher Bazar c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 1 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 15. PAB/UZR-15 UZR-15.1 Mirjapur GCM-Chhaikola GCM via Km 10.00 116.00 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Bardanager , Langolmora & Charnabin road. UZR-15.2 Chatmohar R & H at Janata Bank to Km 2.00 23.20 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Mirjapur GCM Via Noornagar 16. PAB/UZR-16 Faridpur UZ H/Q-Bhangura UZ H/Q Rd. Km 7.58 87.93 NCB BG No 11/1/2013 12/31/2013 7/4/2015 (Via B.L. Bari Up. Office) 17. SHE/UZR-17 UZR-17.1 Chandrakona G.C-Nurundi G.C Road. Km 5.00 58.00 NCB BG No 11/1/2013 12/31/2013 7/4/2015 UZR-17.2 Gobindagonj GC-Paglarmore Km 4.23 49.03 NCB BG No 11/1/2013 12/31/2013 7/4/2015 18. SUN/UZR-18 Chattak-Doara via Ambari Rd. Km 4.35 50.46 NCB BG No 11/1/2013 12/31/2013 7/4/2015 19. BRA/UZR-19 UZR-19.1 Morichakandi GC - Doshani R&H Road via Km 6.00 69.60 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Kanainagar, Charmorichakandi, Santipur, Ichapur & Shibpur road. UZR-19.2 Morichakandi GC - Doshani R&H Road via Km 6.00 69.60 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Kanainagar, Charmorichakandi, Santipur, Ichapur & Shibpur road. 20. SYL/UZR-20 Khadimnagar RHD-Shaheber bazar GC Km 6.00 69.60 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Road. 21. TAN/UZR-21 Dhanbari-Nandina Road Km 5.90 68.44 NCB BG No 11/1/2013 12/31/2013 7/4/2015 22. NET/UZR-22 Netrokona-Mym.R&H (Challisha)- Km 6.98 80.91 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Simulkandi GC Road 23. CTG/UZR-23 Kalurghat-Sarandeep-Banderjari-Sharafvatta Km 6.20 71.92 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Rd (Rangunia Part) (From RHD #96) 24. DHA/UZR-24 UZR-24.1 Dhantara GC to Pakutia GC (Nagarpur, Km 7.00 81.20 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Tangail) Road UZR-24.2 Dhantara GC to Pakutia GC (Nagarpur, Km 8.20 95.12 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Tangail) Road 25. JAM/UZR-25 UZR-25.1 Islampur-Jhagrarchar GC Rd. Km 6.00 69.60 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UZR-25.2 Islampur-Jhagrarchar GC Rd. Km 5.85 67.86 NCB BG No 4/1/2014 5/31/2014 12/2/2015 26. MAN/UZR-26 Jhitka G.C-Kanchanpur,Balla (Arua) Km 6.33 73.43 NCB BG No 4/1/2014 5/31/2014 12/2/2015 G.C.road. 27. MOU/UZR-27 Talimpur RHD-Azimganj GC via Talimpur Km 4.75 55.10 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Up Office 28. MUN/UZR-28 Sreenagar GC- Satvita Hat GC (Dohar) via Km 8.92 103.47 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Gadighat bazar, Chatrabough Bazar road (Sreenagar Portion). 29. MYM/UZR-29 UZR-29.1 Kandipara-Goyeshpur Rd. Km 6.00 69.60 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UZR-29.2 Kandipara-Goyeshpur Rd. Km 6.13 71.11 NCB BG No 4/1/2014 5/31/2014 12/2/2015 30. MYM/UZR-30 UZR-30.1 Taldighi R&H-Munshir hat GC Rd. Km 6.00 69.60 NCB BG No 4/1/2014 5/31/2014 12/2/2015 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 2 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) UZR-30.2 Taldighi R&H-Munshir hat GC Rd. Km 5.58 64.73 NCB BG No 4/1/2014 5/31/2014 12/2/2015 31. NET/UZR-31 Kalmakanda GC-Pachgaon GC Road. Km 9.95 115.42 NCB BG No 4/1/2014 5/31/2014 12/2/2015 32. SIR/UZR-32 Sonamukhi GC-Upazila HQ Via Alampur Km 6.25 72.50 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Chowrasta. 33. SUN/UZR-33 Derai-Jagannathpur via Jagdal,Bhurakhali Km 10.06 116.70 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Road. 34. TAN/UZR-34 Barachowna GC-Bhandeshwar GC via Km 4.50 52.20 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Indrajani GC Road 35. SYL/UZR-35 Beanibazar-Sarupar Gc - Sylhetypara RHD - Km 8.48 98.37 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Gojukata Road. 36. BRA/UZR-36 Nasirnagar R&H-Bholakot Bazar-Chatalpar Km 8.89 103.12 NCB BG No 4/1/2014 5/31/2014 12/2/2015 GC-Aurail Road (Nasirnagar Part) 37. BRA/UZR-37 Nasirnagar R&H-Bholakot Bazar-Chatalpar Km 9.00 104.40 NCB BG No 4/1/2014 5/31/2014 12/2/2015 GC-Aurail Road (Nasirnagar Part) 38. JAM/UZR-38 Bagharchar-Sanandabari Hat via Goalkanda Km 4.78 55.47 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Rd. 39. TAN/UZR-39 Barachowna GC-Bhandeshwar GC via Km 7.53 87.29 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Indrajani GC Road 40. BRA/UZR-40 UZR-40.1 Panchabati R&H road-Akhaura Bara bazar Km 2.96 34.34 NCB BG No 4/1/2014 5/31/2014 12/2/2015 road. (Haliday road) UZR-40.2 Nabinagar-B.Baria Rd-Border of Sadekpur Km 6.36 73.78 NCB BG No 4/1/2014 5/31/2014 12/2/2015 U.P 41. COM/UZR-41 UZR-41.1 Baichapukuria-Adda Bazar-Kachua Road Km 2.96 34.34 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UZR-41.2 Dhaka-Chittagong highway- Comilla Km 3.00 34.80 NCB BG No 4/1/2014 5/31/2014 12/2/2015 University 42. NARA/UZR-42 Damra GC-Chanpara-Baraid via Kamshair Km 7.64 88.62 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Rd. 43. SHE/UZR-43 Jhenaigati GC - Nuton Bazar Border road Km 8.60 99.76 NCB BG No 4/1/2014 5/31/2014 12/2/2015 via Bakakura bazar road. 44. SIR/UZR-44 UZR-44.1 Katagari hat G.C.-Ranir hat (Tarash Part) Km 3.92 45.47 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UZR-44.2 Goyhatta GC-Kuchiamara R&H Km 3.90 45.24 NCB BG No 4/1/2014 5/31/2014 12/2/2015 45. SYL/UZR-45 UZR-45.1 Kasrupur bazar GC-Pailanpur-Balaganj GC Km 7.00 81.20 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Road. UZR-45.2 Kasrupur bazar GC-Pailanpur-Balaganj GC Km 6.24 72.38 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Road. 46. TAN/UZR-46 UZR-46.1 Hatubhanga-Kaliakore-Fulbaria Road via Km 6.50 75.40 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Khatar Hat road. UZR-46.2 Hatubhanga-Kaliakore-Fulbaria Road via Km 4.00 46.40 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Khatar Hat road. UZR-46.3 Hatubhanga-Kaliakore-Fulbaria Road via Km 4.52 52.37 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Khatar Hat road. c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 3 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 47. SYL/UZR-47 Haripur GC-Gachbari GC Road. (Kanaighat Km 7.07 82.01 NCB BG No 4/1/2014 5/31/2014 12/2/2015 part) 48. CHA/UZR-48 Thakur bazar (U.H.C) GC-Jadabpur R& H Km 5.98 69.37 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Net work. (Ch. 00-1700m, 2200-3860m & 9470-9450m) 49. CTG/UZR-49 Hazrat Mohsin Awolia-Gahira-Fakirhat- Km 4.27 49.53 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Dhalghat 50. CTG/UZR-50 UZR-50.1 Heako G.C. to Sikdarkhil Road Km 3.50 40.60 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UZR-50.2 Mohammed Takirhat G.C.to Katirhat Road Km 2.25 26.10 NCB BG No 4/1/2014 5/31/2014 12/2/2015 via Samitirhat Bazar (Fatickchari portion) UZR-50.3 Borer Hat-Sitakunda Mirer Hat G.C. Road Km 2.84 32.94 NCB BG No 4/1/2014 5/31/2014 12/2/2015 51. COM/UZR-51 UZR-51.1 Debidwar G.C to Dulalpur G.C Km 6.00 69.60 NCB BG No 4/1/2014 5/31/2014 12/2/2015 via.Abdullapur (Debidwar Portion) UZR-51.2 Debidwar G.C to Dulalpur G.C Km 5.55 64.38 NCB BG No 4/1/2014 5/31/2014 12/2/2015 via.Abdullapur (Debidwar Portion) 52. COM/UZR-52 UZR-52.1 Monohorgonj GC -Laksmanpur- Bipulasar Km 7.70 89.32 NCB BG No 4/1/2014 5/31/2014 12/2/2015 R&H Rd. UZR-52.2 Gouripur - Jiarkandi - Bakhrabad Km 6.90 80.04 NCB BG No 4/1/2014 5/31/2014 12/2/2015 (Muradnagar)Road.(From RHD#189) 53. DHA/UZR-53 UZR-53.1 Paragram GC to Kolatia GC rd via Km 4.36 50.58 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Dhalikandi F.Ghat(N.Por). UZR-53.2 Komorgonj G.C - Paragram G.C via Koilail Km 5.90 68.44 NCB BG No 4/1/2014 5/31/2014 12/2/2015 U.P road. 54. FEN/UZR-54 Fazilpur-Bhorerbazar-Nababpur Road (From Km 3.73 43.27 NCB BG No 4/1/2014 5/31/2014 12/2/2015 RHD #248) 55. GAZ/UZR-55 UZR-55.1 Boardghar (R&H)-Chandabaha G.C. Km 7.00 81.20 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UZR-55.2 Boardghar (R&H)-Chandabaha G.C. Km 6.83 79.23 NCB BG No 4/1/2014 5/31/2014 12/2/2015 56. HAB/UZR-56 UZR-56.1 Pakuria Battala-Asampara bazar Via Rema Km 5.00 58.00 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Tea garden. UZR-56.2 Pakuria Battala-Asampara bazar Via Rema Km 4.23 49.07 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Tea garden. 57. JAM/UZR-57 UZR-57.1 Nandina G.C-Dhanbari G. C Road [ Km 7.00 81.20 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Jamalpur part]. UZR-57.2 Nandina G.C-Dhanbari G. C Road [ Km 6.05 70.18 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Jamalpur part]. 58. KIS/UZR-58 UZR-58.1 Guzadia bazar-Tarail R&H Road via Raijani Km 2.64 30.62 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UZR-58.2 Nilgonj GC to Kishorejong Mymensingh Km 3.58 41.53 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Road 59. LAX/UZR-59 UZR-59.1 Torabganj GC - Shantirhat - Hajiganj Bazar - Km 6.67 77.37 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Banderhat - Chowdhuryhat - Ramgati Bazar Road c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 4 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) UZR-59.2 Torabganj GC - Shantirhat - Hajiganj Bazar - Km 6.00 69.60 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Banderhat - Chowdhuryhat - Ramgati Bazar Road 60. MAN/UZR-60 Ghior-Tepra Via Baratia Bazar Road Km 2.87 33.29 NCB BG No 4/1/2014 5/31/2014 12/2/2015 61. MUN/UZR-61 Bausia NH road-Kali Bazar hat.(Engr.Staff Km 4.05 46.98 NCB BG No 4/1/2014 5/31/2014 12/2/2015 College road ) 62. MYM/UZR-62 Chechua-Khamarer Bazar Road Via Km 8.81 102.20 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Mogaltola & Syedpara Bazar Road. 63. NAR/UZR-63 Gopinathpur-Hasnabad upto Thana Border Km 2.00 23.20 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Rd. 64. SHE/UZR-64 Narayankhola GC-Austadhar GC Road. Km 3.25 37.70 NCB BG No 4/1/2014 5/31/2014 12/2/2015 65. SIR/UZR-65 Alokdiar (Jamtoil)-Shomeshpur (Belkuchi Km 3.70 42.92 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Upazila) GC Road 66. SIR/UZR-66 UZR-66.1 Nimgachi GC-Sheerpur via Shaliagari- Km 3.30 38.28 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Bhabanipur (Raigong part) UZR-66.2 Shimla NHW-Katagari GC Km 2.25 26.10 NCB BG No 4/1/2014 5/31/2014 12/2/2015 67. SIR/UZR-67 Talgachi GC-Krishokgong GC via Km 3.60 41.76 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Nolshondha hat. 68. SUN/UZR-68 UZR-68.1 Kalipur to Pagla-Jagannathpur RHD via Km 3.00 34.80 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Haiderpur UZR-68.2 Kalipur to Pagla-Jagannathpur RHD via Km 3.30 38.28 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Haiderpur 69. SUN/UZR-69 UZR-69.1 Dharmpassa-Joysree Road. Km 3.00 34.80 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UZR-69.2 Dharmpassa-Joysree Road. Km 3.83 44.43 NCB BG No 4/1/2014 5/31/2014 12/2/2015 70. TAN/UZR-70 UZR-70.1 Kalihati (Dhunail)-Shayahat-Hatia JBA Km 3.00 34.80 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Road UZR-70.2 Kalihati (Dhunail)-Shayahat-Hatia JBA Km 4.93 57.19 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Road 71. BRA/UZR-71 UZR-71.1 Bancharampur H/Q-Morichakandi GC via Km 2.50 29.00 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Dariadaulat UP & Kadamtali UZR-71.2 Bancharampur H/Q-Morichakandi GC via Km 2.54 29.46 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Dariadaulat UP & Kadamtali UZR-71.3 Bancharampur H/Q-Morichakandi GC via Km 2.50 29.00 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Dariadaulat UP & Kadamtali 72. BRA/UZR-72 UZR-72.1 Kharera R&H to Shimrail GC via Kheora Km 3.06 35.50 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Bazar Road UZR-72.2 Sarail-Arail hat road-Rosulpur Azabpur- Km 5.00 58.00 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Notunhati 73. BRA/UNR-1 Salimabad UP (Asrafbad)-Rupasdi bazar Km 6.45 38.25 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Road via Hogla Kanda 74. BRA/UNR-2 Ramrail Bazar-Sultanpur UP upto Sultanpur Km 3.27 19.39 NCB BG No 11/1/2013 12/31/2013 7/4/2015 chawmahani Rd. 75. CHA/UNR-3 UNR-3.1 Latifgonj Bazar-Paschim Subidpur UP Km 3.00 17.79 NCB BG No 11/1/2013 12/31/2013 7/4/2015 (Uttali) Road via Guher Bazar c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 5 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) UNR-3.2 Latifgonj Bazar-Paschim Subidpur UP Km 4.67 27.69 NCB BG No 11/1/2013 12/31/2013 7/4/2015 (Uttali) Road via Guher Bazar 76. CHA/UNR-4 Khila Bazar (Khila Eidgah)-Shahrasti Bazar Km 3.85 22.83 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Road via Gabtoli 77. CTG/UNR-5 UNR-5.1 Bhujpur U.P. H.Q. to Mirzerhat Road via Km 4.50 26.69 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Sandip Para. UNR-5.2 Bhujpur U.P. H.Q. to Mirzerhat Road via Km 5.41 32.08 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Sandip Para. 78. COM/UNR-6 UNR-6.1 Bizra-Laksam Rd. Km 5.40 32.02 NCB BG No 11/1/2013 12/31/2013 7/4/2015 UNR-6.2 Paranpur Bazar[ R&H]-Payelgacha UP Km 6.64 39.38 NCB BG No 11/1/2013 12/31/2013 7/4/2015 office Road 79. COM/UNR-7 UNR-7.1 Adra-Volainbazar-Chatitala-Ghoramaidan- Km 2.66 15.77 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Manikmura Rd. UNR-7.2 Alkara UP office-Ranir bazar-Rajballovpur Km 2.70 16.01 NCB BG No 11/1/2013 12/31/2013 7/4/2015 bazar Rd. 80. COM/UNR-8 Mokam UP Office-Abidpur Bazar Rd. via Km 6.00 35.58 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Mitholma. 81. COX/UNR-9 Chakmarkul-Montergoda(P.M Khali) Road. Km 2.70 16.01 NCB BG No 11/1/2013 12/31/2013 7/4/2015 82. DHA/UNR-10 Dhamrai Pourasava to Savar Bazar via Km 1.65 9.78 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Mamura Road 83. GAZ/UNR-11 UNR-11.1 Mediasolay (Chapair UP)-Bangla bazar Via Km 5.00 29.65 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Boraibari Paikpara Via kotbari Chowrasta Bazar UNR-11.2 Mediasolay (Chapair UP)-Bangla bazar Via Km 4.66 27.63 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Boraibari Paikpara Via kotbari Chowrasta Bazar 84. HAB/UNR-12 Chanbangha bazar-Shankhola U.P Office via Km 2.50 14.83 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Barkota road. 85. JAM/UNR-13 Char Goalini UP-4 No. Char Bazar Rd. Km 6.00 35.58 NCB BG No 11/1/2013 12/31/2013 7/4/2015 86. KIS/UNR-14 UNR-14.1 Banagram UP H/Q.-Sararchar GCvia Km 3.80 22.53 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Magura Bazar Rd. UNR-14.2 Sayedgaon chowwrasta-Hossendi UP- Km 4.54 26.92 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Modhapara Bus Stand RD(Hat) 87. LAX/UNR-15 UNR-15.1 Goni Ramiz Alam Road.[From 5 No Beri to Km 4.00 23.72 NCB BG No 11/1/2013 12/31/2013 7/4/2015 2 No & 1 No up ] Road. UNR-15.2 Goni Ramiz Alam Road.[From 5 No Beri to Km 4.39 26.03 NCB BG No 11/1/2013 12/31/2013 7/4/2015 2 No & 1 No up ] Road. 88. MAN/UNR-16 Ghior GC-Ulail bazar Via Terosree Km 2.37 14.05 NCB BG No 11/1/2013 12/31/2013 7/4/2015 road.(Ghior portion) 89. MOU/UNR-17 UNR-17.1 Kathaltali-Madhabkunda Road Km 3.63 21.53 NCB BG No 11/1/2013 12/31/2013 7/4/2015 UNR-17.2 Adampur U.P.office-Alinagarbazar Road via Km 6.00 35.58 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Changaon Jangalia . 90. MUN/UNR-18 Balurchar UP-to Taltala G.C. via Km 6.50 38.55 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Kumarkhali c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 6 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 91. MYM/UNR-19 UNR-19.1 Bhaitkandi U.P. to Chargoadanga bazar Km 5.00 29.65 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Road via Rambhadrapur. UNR-19.2 Bhaitkandi U.P. to Chargoadanga bazar Km 5.50 32.62 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Road via Rambhadrapur. 92. MYM/UNR-20 Dhudnoy bazar-Gamaretola UP (Kolsindur Km 5.10 30.24 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Gc) Rd 93. NARA/UNR-21 Khaliarchar-Modhorchar. Km 6.32 37.48 NCB BG No 11/1/2013 12/31/2013 7/4/2015 94. NAR/UNR-22 Mahamudabad R&H-Dulatkandi-Algi Bazar Km 6.46 38.31 NCB BG No 11/1/2013 12/31/2013 7/4/2015 95. NET/UNR-23 Nowpara UP office-Amlitala Bazar via Km 4.60 27.28 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Bolishimul UP office 96. NOA/UNR-24 UNR-24.1 Shahajir hat-Char Algi bazar Road. Km 3.53 20.93 NCB BG No 11/1/2013 12/31/2013 7/4/2015 UNR-24.2 Chor Amanullah UP Office-Khaserhat- Km 3.00 17.79 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Banglabazar-Karimbazar Road. 97. PAB/UNR-25 UNR-25.1 Mathurapur U.P.-D.B.gram U.P.road. Km 4.00 23.72 NCB BG No 11/1/2013 12/31/2013 7/4/2015 UNR-25.2 Mathurapur U.P.-D.B.gram U.P.road. Km 4.35 25.80 NCB BG No 11/1/2013 12/31/2013 7/4/2015 98. SHE/UNR-26 UNR-26.1 Ranishimul U.P.-Bhatpur Bazar Km 3.00 17.79 NCB BG No 11/1/2013 12/31/2013 7/4/2015 UNR-26.2 Ranishimul U.P.-Bhatpur Bazar Km 4.40 26.09 NCB BG No 11/1/2013 12/31/2013 7/4/2015 99. SIR/UNR-27 UNR-27.1 Purnimaganti UP-Rajman Hat via Koyra hat Km 6.00 35.58 NCB BG No 11/1/2013 12/31/2013 7/4/2015 road UNR-27.2 Purnimaganti UP-Rajman Hat via Koyra hat Km 5.29 31.37 NCB BG No 11/1/2013 12/31/2013 7/4/2015 road 100. SUN/UNR-28 Sachna hat-Ramnagor bazar via Sachna Km 5.20 30.84 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Bazar UP Office Road. 101. SYL/UNR-29 Jalalabad UP-Kalirgaon bazar Road. Km 3.30 19.57 NCB BG No 11/1/2013 12/31/2013 7/4/2015 102. TAN/UNR-30 UNR-30.1 Gobindashi UP-Nikrail Bazar Road Km 6.72 39.85 NCB BG No 11/1/2013 12/31/2013 7/4/2015 UNR-30.2 Kadamtoli (Digar UP)-Teghory-Maiderchala Km 4.62 27.40 NCB BG No 11/1/2013 12/31/2013 7/4/2015 Bazar Road 103. BRA/UNR-31 UNR-31.1 Dharmondal UP Office-Marakut Bazar Road Km 5.00 29.65 NCB BG No 4/1/2014 5/31/2014 12/2/2015 (Fundauk Bazar) UNR-31.2 Dharmondal UP Office-Marakut Bazar Road Km 4.85 28.76 NCB BG No 4/1/2014 5/31/2014 12/2/2015 (Fundauk Bazar) 104. CHA/UNR-32 UNR-32.1 Matlab-Master Bazar Ghosherhat Road Km 3.00 17.79 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UNR-32.2 Matlab-Master Bazar Ghosherhat Road Km 4.80 28.46 NCB BG No 4/1/2014 5/31/2014 12/2/2015 105. CTG/UNR-33 Abdus Sattara Road Km 1.65 9.78 NCB BG No 4/1/2014 5/31/2014 12/2/2015 106. COM/UNR-34 Baradushia bazar[ R&H]-Shashidal UP Km 1.99 11.80 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Office Rd. c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 7 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 107. COM/UNR-35 Dakshin Elliotganj UP Office (Elliotganj Km 5.25 31.13 NCB BG No 4/1/2014 5/31/2014 12/2/2015 G.C.)-Mohamadpur Natunbazar via Kalasona bazar Road 108. COM/UNR-36 UNR-36.1 Kurbanpur-Kaligonj Rd. Km 5.00 29.65 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UNR-36.2 Kurbanpur-Kaligonj Rd. Km 4.75 28.17 NCB BG No 4/1/2014 5/31/2014 12/2/2015 109. COX/UNR-37 UNR-37.1 Kakara-Surajpur Manikpur Yangacha Km 3.00 17.79 NCB BG No 4/1/2014 5/31/2014 12/2/2015 connecting Road. UNR-37.2 Kakara-Surajpur Manikpur Yangacha Km 3.80 22.53 NCB BG No 4/1/2014 5/31/2014 12/2/2015 connecting Road. UNR-37.3 Harbung Baraitali Road Km 6.05 35.88 NCB BG No 4/1/2014 5/31/2014 12/2/2015 110. COX/UNR-38 Eid Gaon G.C-Gomatoli Bazar Via Pokkali Km 2.31 13.70 NCB BG No 4/1/2014 5/31/2014 12/2/2015 U.P 111. DHA/UNR-39 UNR-39.1 Dhamrai Pourasava (Bata gate) to Jalsin Km 3.00 17.79 NCB BG No 4/1/2014 5/31/2014 12/2/2015 bazar Road UNR-39.2 Dhamrai Pourasava (Bata gate) to Jalsin Km 4.40 26.09 NCB BG No 4/1/2014 5/31/2014 12/2/2015 bazar Road 112. DHA/UNR-40 Dhaka-Aricha RHD. 20 Mile Army check Km 1.40 8.30 NCB BG No 4/1/2014 5/31/2014 12/2/2015 post-Pathalaia UP (Ghugudia) Road 113. FEN/UNR-41 UNR-41.1 Mohamaya UP (Chandgazi Bazar)-Diabibi Km 2.04 12.10 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Road via Bangla Bazar, Mohamaiya Gat Road st. Mohamaiya UP & end of Diabib Bazar. UNR-41.2 Gabtala-Paithara-Munshirhat road. Km 4.00 23.72 NCB BG No 4/1/2014 5/31/2014 12/2/2015 114. FEN/UNR-42 Charcandia UP-Sonagazi Up via Via Km 4.37 25.91 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Bhuyanrhat,Modinabazar,BRRI&Bahadderh at Road. 115. GAZ/UNR-43 UNR-43.1 Muktarpur UP-Moisher Bazar via Chopair, Km 2.84 16.84 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Dollan Bazar Road UNR-43.2 Singhasree Union H/Q-Amraid bazar via Km 3.00 17.79 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Sohagpurbazar Rd. UNR-43.3 Singhasree Union H/Q-Amraid bazar via Km 3.90 23.13 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Sohagpurbazar Rd. 116. HAB/UNR-44 UNR-44.1 Shatiajuri UP Office-Ranigaon UP-Mirashi Km 2.61 15.48 NCB BG No 4/1/2014 5/31/2014 12/2/2015 notun bazar Road. UNR-44.2 Montala-Kashim nagar Rail Station- Km 4.15 24.61 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Horashpur road 117. JAM/UNR-45 UNR-45.1 Char Amkhawa (Sanandabari) UP-kather Km 3.00 17.79 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Bill Bazar via Lonker Char Rd. UNR-45.2 Char Amkhawa (Sanandabari) UP-kather Km 4.50 26.69 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Bill Bazar via Lonker Char Rd. 118. KIS/UNR-46 UNR-46.1 Aribaria UP H/Q-Rampur bazar via SRD Km 5.00 29.65 NCB BG No 4/1/2014 5/31/2014 12/2/2015 (Zia road) Road UNR-46.2 Aribaria UP H/Q-Rampur bazar via SRD Km 4.42 26.21 NCB BG No 4/1/2014 5/31/2014 12/2/2015 (Zia road) Road c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 8 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 119. LAX/UNR-47 UNR-47.1 Kazir Char-Mitali-Bazar-Char-Kasia Road Km 4.00 23.72 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UNR-47.2 Kazir Char-Mitali-Bazar-Char-Kasia Road Km 4.85 28.76 NCB BG No 4/1/2014 5/31/2014 12/2/2015 120. LAX/UNR-48 UNR-48.1 Bangla bazar-Charsekander-Sufir hat Road. Km 4.00 23.72 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UNR-48.2 Bangla bazar-Charsekander-Sufir hat Road. Km 3.87 22.95 NCB BG No 4/1/2014 5/31/2014 12/2/2015 121. MUN/UNR-49 Satullah-Panchgaon Bazar-Boloi-Fazusha Km 5.33 31.61 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Road. 122. MYM/UNR-50 UNR-50.1 Shambugonj old bus stand bazar-Parangonj Km 5.00 29.65 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Bazar via Sirta UP. Office UNR-50.2 Shambugonj old bus stand bazar-Parangonj Km 5.75 34.10 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Bazar via Sirta UP. Office UNR-50.3 Shambugonj old bus stand bazar-Parangonj Km 5.00 29.65 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Bazar via Sirta UP. Office 123. NARA/UNR-51 Aukhabo RHD-Upazila HQ via Majhipara Km 3.60 21.35 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Mirkutire Saw Road 124. NAR/UNR-52 UNR-52.1 Shilmandi U.P Office (South Shilmandi)- Km 3.15 18.68 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Shilmandi Natun Bazar Road. UNR-52.2 Mirzapur U.P. Office-Chanderkandi U.P. Km 3.00 17.79 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Office Road. UNR-52.3 Mirzapur U.P. Office-Chanderkandi U.P. Km 4.45 26.39 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Office Road. 125. NET/UNR-53 UNR-53.1 Trimohoni( R&H)-Jamdhala Bazar road via Km 5.00 29.65 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Dhalamolgaon UP office UNR-53.2 Trimohoni( R&H)-Jamdhala Bazar road via Km 5.50 32.62 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Dhalamolgaon UP office 126. NOA/UNR-54 Talmohammadar hat-Pashkar hat-Char Km 2.00 11.86 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Kasspia Bhumihin Bazar 127. PAB/UNR-55 UNR-55.1 Khanmorich UP H/Q-Mirzapur G C M road. Km 6.00 35.58 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UNR-55.2 Khanmorich UP H/Q-Mirzapur G C M road. Km 6.00 35.58 NCB BG No 4/1/2014 5/31/2014 12/2/2015 128. SHE/UNR-56 UNR-56.1 Marichpuran UP office-Madrasha Bazar- Km 4.00 23.72 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Mirzabazar road UNR-56.2 Marichpuran UP office-Madrasha Bazar- Km 4.00 23.72 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Mirzabazar road 129. SIR/UNR-58 UNR-58.1 Tarash U.P. Office-Nadosayedpur hat Road Km 5.00 29.65 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UNR-58.2 Tarash U.P. Office-Nadosayedpur hat Road Km 5.20 30.84 NCB BG No 4/1/2014 5/31/2014 12/2/2015 130. SYL/UNR-59 Mayakhali Bazar-R&H(Barohal UP Office) Km 4.50 26.69 NCB BG No 4/1/2014 5/31/2014 12/2/2015 Via Hatubill Madrasha Road. 131. TAN/UNR-60 UNR-60.1 Kashil UP Office-Aisara Bazar via Janjania. Km 5.66 33.56 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UNR-60.2 Baoikhula Bazar-Nallapara hat via Dubail Km 4.00 23.72 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UP office, Bathuli hat, Fultara Hat Road c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 9 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) UNR-60.3 Baoikhula Bazar-Nallapara hat via Dubail Km 4.39 26.03 NCB BG No 4/1/2014 5/31/2014 12/2/2015 UP office, Bathuli hat, Fultara Hat Road 132. PAB/RPM-1 Nalkhola GC - Badherhat on RHD road Km 2.50 3.65 NCB BG No 12/10/2012 2/8/2013 2/8/2014 133. PAB/RPM-2 RPM-2.1 Mulgram U.P.-Failzana U.P. road Km 6.11 12.81 NCB BG No 12/27/2012 2/25/2013 2/25/2014 RPM-2.2 Mulgram U.P.-Failzana U.P. road Km 6.15 11.28 NCB BG No 12/27/2012 2/25/2013 2/25/2014 134. PAB/RPM-3 RPM-3.1 Sahapur UP-Charkurulia hat(End of Al-Haj Km 4.72 12.03 NCB BG No 12/27/2012 2/25/2013 2/25/2014 more) road RPM-3.2 Dhopaghata RHD-Dogachi GCM (Golam Km 5.33 7.26 NCB BG No 12/27/2012 2/25/2013 2/25/2014 Murtoza) Road RPM-3.3 Santhia Upazila H/Q - Demra GC (Dohore Km 11.20 17.90 NCB BG No 12/27/2012 2/25/2013 2/25/2014 jani more) 135. SIR/RPM-4 RPM-4.1 Simanta bazar RHD-Sonamukhi GC Km 4.20 8.86 NCB BG No 12/19/2012 2/17/2013 2/17/2014 RPM-4.2 Simanta bazar RHD-Sonamukhi GC Km 4.35 8.30 NCB BG No 12/19/2012 2/17/2013 2/17/2014 136. SIR/RPM-5 Dubil UP to Amsara Hat Via Maltinagar Km 7.29 17.53 NCB BG No 12/19/2012 2/17/2013 2/17/2014 137. SIR/RPM-6 RPM-6.1 Tarash-Katagari hat GCC Rd Km 6.00 10.27 NCB BG No 12/19/2012 2/17/2013 2/17/2014 RPM-6.2 Tarash-Katagari hat GCC Rd Km 5.54 7.55 NCB BG No 12/19/2012 2/17/2013 2/17/2014 RPM-7.2 Kaliganj-Kapasia Rd Km 9.50 19.45 NCB BG No 12/11/2012 2/9/2013 2/9/2014 138. GAZ/RPM-8 Hotapara-Perojali Hatkhola bazar Road Km 6.70 22.89 NCB BG No 12/12/2012 2/10/2013 2/10/2014 139. GAZ/RPM-9 RPM-9.1 Kapasia GC-Monohordi Rd Km 7.10 21.85 NCB BG No 12/20/2012 2/18/2013 2/18/2014 RPM-9.2 Kapasia GC-Monohordi Rd Km 6.90 24.31 NCB BG No 12/20/2012 2/18/2013 2/18/2014 140. JAM/RPM-11 RPM-11.1 Dewanganj-Sanandabari viaTaratia Rd Km 10.90 17.21 NCB BG No 3/5/2013 4/30/2013 4/30/2014 RPM-11.2 Dewanganj-Sanandabari viaTaratia Rd Km 10.70 8.80 NCB BG No 3/5/2013 4/30/2013 4/30/2014 141. JAM/RPM-12 RPM-12.1 Patharshi UP-Molomgonj Bazar Rd Km 4.50 7.49 NCB BG No 2/12/2013 4/13/2013 4/13/2014 RPM-12.2 Melandah GC to Gobindagonj R& H Road Km 4.27 6.74 NCB BG No 2/12/2013 4/13/2013 4/13/2014 RPM-12.3 Raygonj bazar-Adervita U/P. Rd Km 3.50 5.51 NCB BG No 2/12/2013 4/13/2013 4/13/2014 142. JAM/RPM-13 RPM-13.1 Rashidpur U. P to Jamtala bazar Km 6.70 12.76 NCB BG No 2/12/2013 4/13/2013 4/13/2014 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 10 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) RPM-13.2 Doail U/P-Shaincherpar Road Km 6.15 13.60 NCB BG No 2/12/2013 4/13/2013 4/13/2014 143. KIS/RPM-14 Sararchar-Pirijpur Bazar Rd Km 5.10 5.34 NCB BG No 1/14/2013 3/15/2013 3/15/2014 144. KIS/RPM-15 RPM-15.1 Tarail HQ-Cherang GCC Road Km 3.60 12.34 NCB BG No 1/14/2013 3/15/2013 3/15/2014 RPM-15.2 Karimganj-Gundhar GC Road Km 10.00 9.91 NCB BG No 1/14/2013 3/15/2013 3/15/2014 145. KIS/RPM-16 RPM-16.1 Jalia bazar-Josodal UP Rd Km 5.35 5.47 NCB BG No 1/14/2013 3/15/2013 3/15/2014 RPM-16.2 Hossainpur-Bakchanda GC Km 9.83 29.63 NCB BG No 1/14/2013 3/15/2013 3/15/2014 146. MUN/RPM-19 RPM-19.1 Dighali (Maliranka)-Nowpara-Kusumpur Km 3.70 7.97 NCB BG No 1/7/2013 3/8/2013 3/8/2014 (Lauhajong Portion7.5Km) Road RPM-19.2 Makahati-Chardumuria Km 1.54 3.78 NCB BG No 1/7/2013 3/8/2013 3/8/2014 RPM-19.3 Tongibari-Hashail Road Km 7.55 11.45 NCB BG No 1/7/2013 3/8/2013 3/8/2014 147. MYM/RPM-20 RPM-20.1 Dhaka-Mym. H/Way (Seed Store GC)- Km 6.00 9.15 NCB BG No 2/19/2013 4/20/2013 4/20/2014 Shakhipur RPM-20.2 Dhaka-Mym. H/Way (Seed Store GC)- Km 7.75 10.93 NCB BG No 2/19/2013 4/20/2013 4/20/2014 Shakhipur 148. MYM/RPM-21 RPM-21.1 Ramgopalpur RHD to Shyamgonj GC via Km 4.35 7.90 NCB BG No 3/5/2013 4/30/2013 4/30/2014 Gouripur. RPM-21.2 Ramgopalpur RHD to Shyamgonj GC via Km 7.73 26.67 NCB BG No 3/5/2013 4/30/2013 4/30/2014 Gouripur. 149. MYM/RPM-22 RPM-22.1 Pabiajuri Bailly Bridge (Nalitabari)-Dara Km 9.80 18.22 NCB BG No 2/19/2013 4/20/2013 4/20/2014 Road(Mymensingh part). RPM-22.2 Bhaitkandi R&H. Road-Narayankhula G.C. Km 5.65 8.57 NCB BG No 2/19/2013 4/20/2013 4/20/2014 Bhaitkandi G.C. 150. MYM/RPM-23 Fulbaria-Hat kalirbajar Road. Km 9.30 29.04 NCB BG No 2/19/2013 4/20/2013 4/20/2014 151. MYM/RPM-24 Nandail H.Q-Bakchanda G.C Rd. Km 8.80 30.36 NCB BG No 2/25/2013 3/20/2013 3/20/2014 152. NARA/RPM-25 RPM-25.2 Sanmandi UP Office-Kikertek bazar Road Km 5.04 13.08 NCB BG No 1/10/2013 3/11/2013 3/11/2014 via Darikandi, Sonakhali, Pachpir Darga 153. NARA/RPM-26 RPM-26.2 Porshi G.C.-Rupganj-Kayetpara-Demra Km 10.06 28.77 NCB BG No 1/10/2013 3/11/2013 3/11/2014 RHD rd. 154. NAR/RPM-28 RPM-28.1 Jangli Shibpur bazar-Dhukandi-Baznabo UP Km 10.13 17.66 NCB BG No 1/31/2013 4/1/2013 4/1/2014 office Road. RPM-28.2 Gazaria UP - Jangalia bazar Via Bariatola. Km 4.70 10.05 NCB BG No 1/31/2013 4/1/2013 4/1/2014 155. NAR/RPM-29 RPM-29.1 Monohordi H/Q-Drinerghat R&H Km 6.00 15.77 NCB BG No 1/31/2013 4/1/2013 4/1/2014 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 11 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) RPM-29.2 Monohordi H/Q-Drinerghat R&H Km 6.57 12.08 NCB BG No 1/31/2013 4/1/2013 4/1/2014 156. NAR/RPM-30 RPM-30.1 Sreerampur Rail gate R&H-Monipura Gc Km 9.00 26.67 NCB BG No 1/31/2013 4/1/2013 4/1/2014 RPM-30.2 Sreerampur Rail gate R&H-Monipura Gc Km 7.46 29.12 NCB BG No 1/31/2013 4/1/2013 4/1/2014 157. NET/RPM-31 RPM-31.1 Durgapur (GC)-Nazirpur(GC) road Km 5.00 16.75 NCB BG No 1/9/2013 3/10/2013 3/10/2014 RPM-31.2 Durgapur (GC)-Nazirpur(GC) road Km 4.80 14.40 NCB BG No 1/9/2013 3/10/2013 3/10/2014 158. NET/RPM-32 RPM-32.1 Kalmakanda (GC)-Nazirpur GC Road. Km 7.00 17.73 NCB BG No 1/9/2013 3/10/2013 3/10/2014 RPM-32.2 Kalmakanda (GC)-Nazirpur GC Road. Km 7.45 15.48 NCB BG No 1/9/2013 3/10/2013 3/10/2014 159. NET/RPM-33 Madan to Kendua GC road via Kaitail & Km 9.22 29.35 NCB BG No 1/9/2013 3/10/2013 3/10/2014 Borory Bazar. 160. SHE/RPM-34 RPM-34.1 Jhenaigati-Gobindaganj. Km 10.57 13.74 NCB BG No 2/12/2013 4/13/2013 4/13/2014 RPM-34.2 Sherpur-Chandrakona Road Km 10.70 20.20 NCB BG No 2/12/2013 4/13/2013 4/13/2014 161. SHE/RPM-35 RPM-35.1 Sreebordi-Karnajhora GC Km 7.00 19.59 NCB BG No 3/5/2013 4/30/2013 4/30/2014 RPM-35.2 Sreebordi-Karnajhora GC Km 7.31 19.50 NCB BG No 3/5/2013 4/30/2013 4/30/2014 162. TAN/RPM-36 Basail-Shakhipur (Nalua) Road. Km 6.08 15.03 NCB BG No 1/3/2013 3/4/2013 3/4/2014 163. TAN/RPM-37 Gopalpur-Nalin Hat Km 6.35 13.89 NCB BG No 1/3/2013 3/4/2013 3/4/2014 164. TAN/RPM-38 RPM-38.1 Suruz G.C.-Dhalapara G.C. Road Km 5.40 12.68 NCB BG No 1/3/2013 3/4/2013 3/4/2014 RPM-38.2 Suruz G.C.-Dhalapara G.C. Road Km 9.89 21.01 NCB BG No 1/3/2013 3/4/2013 3/4/2014 165. TAN/RPM-39 Shahbatpur-Batra Bazar Road via Mailjani Km 3.88 8.76 NCB BG No 1/3/2013 3/4/2013 3/4/2014 road 166. BRA/RPM-41 RPM-41.1 Bancharampur GC-Jibonganj GC Road via Km 5.41 8.86 NCB BG No 11/29/2012 1/28/2013 1/28/2014 Sonarampur Bazar RPM-41.2 Bancharampur GC-Jibonganj GC Road via Km 6.37 17.05 NCB BG No 11/29/2012 1/28/2013 1/28/2014 Sonarampur Bazar 167. BRA/RPM-42 RPM-42.1 Nasirnagar R&H-Haripur GC-Madhabpur Km 4.90 14.80 NCB BG No 11/29/2012 1/28/2013 1/28/2014 R&H Road via Chairkuri GC RPM-42.2 Nasirnagar R&H-Haripur GC-Madhabpur Km 9.16 33.61 NCB BG No 11/29/2012 1/28/2013 1/28/2014 R&H Road via Chairkuri GC c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 12 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 168. CHA/RPM-43 RPM-43.1 Chandpur (Bagadi R&H)-Chandra GC Road. Km 8.25 17.82 NCB BG No 12/12/2012 2/10/2013 2/10/2014 RPM-43.2 Faridganj GC-Rupsha GC Road. Km 5.40 9.83 NCB BG No 12/12/2012 2/10/2013 2/10/2014 169. CHA/RPM-44 RPM-44.1 Senganchar-Kalirbazar Road. Km 6.00 16.28 NCB BG No 12/19/2012 2/17/2013 2/17/2014 RPM-44.2 Senganchar-Kalirbazar Road. Km 7.50 13.91 NCB BG No 12/19/2012 2/17/2013 2/17/2014 170. CHA/RPM-45 RPM-45.1 Tamta U.P H/Q-Khorda Fery Ghat Road Km 3.52 6.64 NCB BG No 12/19/2012 2/17/2013 2/17/2014 RPM-45.2 Balakhal-Rampur-Narayanpur road Km 5.35 17.20 NCB BG No 12/19/2012 2/17/2013 2/17/2014 171. CTG/RPM-46 Bengura D.C. Road. Km 9.05 16.05 NCB BG No 1/30/2012 3/30/2012 3/30/2013 172. CTG/RPM-47 Chittagong Khagrachari Road to Binajhuri Km 1.10 2.62 NCB BG No 1/30/2012 3/30/2012 3/30/2013 Road via Nazirhat GC and Maijbhandar Darbar Sharip 173. CTG/RPM-49 RPM-49.1 Parua D. C. Rd. (From RHD #99) Km 7.00 14.82 NCB BG No 1/30/2012 3/30/2012 3/30/2013 RPM-49.2 Parua D. C. Rd. (From RHD #99) Km 7.13 16.05 NCB BG No 1/30/2012 3/30/2012 3/30/2013 174. COM/RPM-50 RPM-50.1 Comilla-Fakir bazar-Salda Nodi road Km 6.59 18.58 NCB BG No 3/5/2013 4/30/2013 4/30/2014 RPM-50.2 Burichang UP office -Anandapur via Km 7.30 25.19 NCB BG No 3/5/2013 4/30/2013 4/30/2014 Bakshimul UP Office Rd. 175. COM/RPM-51 Laksam-Monohargonj Km 6.40 16.08 NCB BG No 12/20/2012 2/18/2013 2/18/2014 176. COM/RPM-52 Kutumbapur-Kaliarchar Bazar Road. Km 11.44 31.73 NCB BG No 12/20/2012 2/18/2013 2/18/2014 177. COX/RPM-54 RPM-54.1 Napith Khali-Islampur-Pokkhali- Km 7.00 27.68 NCB BG No 1/15/2013 3/16/2013 3/16/2014 Chowfaldandi Road RPM-54.2 Napith Khali-Islampur-Pokkhali- Km 6.95 16.48 NCB BG No 1/15/2013 3/16/2013 3/16/2014 Chowfaldandi Road 178. COX/RPM-55 Charapara RHD to PABT Via Sowdagarhat Km 5.60 10.31 NCB BG No 3/5/2013 4/30/2013 4/30/2014 GC Road. 179. FEN/RPM-56 RPM-56.1 Shebar hat-dudmukha bazar road Km 6.17 12.43 NCB BG No 3/5/2013 4/30/2013 4/30/2014 RPM-56.2 Miar Bazar-Amiruddin Munshi Rd Km 3.89 7.13 NCB BG No 3/5/2013 4/30/2013 4/30/2014 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 13 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 180. FEN/RPM-57 RPM-57.1 Parashuram-Subar bazar-Montola-Fulgazi Km 6.00 8.40 NCB BG No 1/29/2013 3/30/2013 3/30/2014 Bazar Road RPM-57.2 Parashuram-Subar bazar-Montola-Fulgazi Km 6.95 11.22 NCB BG No 1/29/2013 3/30/2013 3/30/2014 Bazar Road 181. LAX/RPM-58 RPM-58.2 Baluachowmuhani-Shampur Miahr hat Km 6.30 17.89 NCB BG No 2/5/2013 4/5/2013 4/5/2014 Road. 182. LAX/RPM-59 RPM-59.2 Char Ababil Char ruhita Embank Cum Road. Km 11.15 22.40 NCB BG No 2/5/2013 4/5/2013 4/5/2014 183. NOA/RPM-60 RPM-60.1 Bangla Bazar-Padipara-Amishapara Bazar Km 5.21 14.58 NCB BG No 2/19/2013 4/20/2013 4/20/2014 road RPM-60.2 Chatkhil-Chandragong road Km 9.66 15.08 NCB BG No 2/19/2013 4/20/2013 4/20/2014 184. NOA/RPM-61 RPM-61.1 Maijdee-Oter hat-Bhuiar hat Road (Old Km 8.05 24.95 NCB BG No 2/11/2013 4/12/2013 4/12/2014 Hospital Road). RPM-61.2 Bashur hat-Moulovi Bazar Road towards Km 5.05 12.69 NCB BG No 2/11/2013 4/12/2013 4/12/2014 Boktar munshi GCC 185. NOA/RPM-62 RPM-62.1 Kachihata-Thanar hat Road (Paloan pol Km 7.00 24.15 NCB BG No 3/5/2013 4/30/2013 4/30/2014 RHW-Amannullapur UP-Eadgha Amin bazar-Amishapara UP) RPM-62.2 Kachihata-Thanar hat Road (Paloan pol Km 7.70 26.57 NCB BG No 3/5/2013 4/30/2013 4/30/2014 RHW-Amannullapur UP-Eadgha Amin bazar-Amishapara UP) 186. HAB/RPM-63 RPM-63.1 Madhabpur-Chowmohoni bazar road Km 6.00 5.34 NCB BG No 2/12/2013 4/13/2013 4/13/2014 RPM-63.2 Madhabpur-Chowmohoni bazar road Km 6.05 16.92 NCB BG No 2/12/2013 4/13/2013 4/13/2014 187. HAB/RPM-64 RPM-64.1 Nabigonj-Rudra Gram Rd. Km 3.92 10.63 NCB BG No 2/12/2013 4/13/2013 4/13/2014 RPM-64.2 Jangalia-Katiadibazar via Nandanpur Bazar Km 8.75 11.64 NCB BG No 2/12/2013 4/13/2013 4/13/2014 188. HAB/RPM-65 RPM-65.1 Chunarughat-Shakir Mohammad Road Km 3.25 6.29 NCB BG No 3/5/2013 4/30/2013 4/30/2014 RPM-65.2 Shaistanagar Bazar-Poil UP Office- Km 4.47 10.33 NCB BG No 3/5/2013 4/30/2013 4/30/2014 Moshajan Bazar Rd. 189. MOU/RPM-66 RPM-66.1 Kamolgonj HQ.-Munshibazar G.C. Road . Km 7.00 30.18 NCB BG No 1/2/2013 3/3/2013 3/3/2014 190. MOU/RPM-67 RPM-67.1 Rajnagor-Fatepur (Balagonj) Km 8.00 32.13 NCB BG No 1/2/2013 3/3/2013 3/3/2014 RPM-67.2 Rajnagor-Fatepur (Balagonj) Km 8.81 20.22 NCB BG No 1/2/2013 3/3/2013 3/3/2014 191. SUN/RPM-68 RPM-68.1 Jagannathpur-Biswanath Km 6.00 14.80 NCB BG No 12/31/2012 3/1/2013 3/1/2014 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 14 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) RPM-68.2 Jagannathpur-Biswanath Km 7.20 20.23 NCB BG No 12/31/2012 3/1/2013 3/1/2014 192. SUN/RPM-69 RPM-69.1 Jalalpur-Dularbazar-Lamarasulganj Km 8.30 27.43 NCB BG No 3/5/2013 4/30/2013 4/30/2014 RPM-69.2 Jalalpur-Dularbazar-Lamarasulganj Km 10.70 19.13 NCB BG No 3/5/2013 4/30/2013 4/30/2014 193. SYL/RPM-70 RPM-70.1 Atgram (R&H)-Zakigonj (G.C) Road. Km 5.00 16.85 NCB BG No 12/31/2012 3/1/2013 3/1/2014 RPM-70.2 Atgram (R&H)-Zakigonj (G.C) Road. Km 7.00 23.50 NCB BG No 12/31/2012 3/1/2013 3/1/2014 194. SYL/RPM-71 Sylhet-Kamalbazar-Ponaullahbazar- Km 7.70 17.53 NCB BG No 12/31/2012 3/1/2013 3/1/2014 Biswanath GC Road (Sadar portion) 195. SYL/RPM-72 RPM-72.1 Sylhet-Gasbari GC-Kanaighat Rd Km 5.00 10.85 NCB BG No 12/31/2012 3/1/2013 3/1/2014 (Golapgonj Portion) RPM-72.2 Sylhet-Gasbari GC-Kanaighat Rd Km 6.70 15.13 NCB BG No 12/31/2012 3/1/2013 3/1/2014 (Golapgonj Portion) 196. SYL/RPM-73 Shiber bazar GC-Companigonj RHD Road Km 6.50 18.63 NCB BG No 12/31/2012 3/1/2013 3/1/2014 (Sadar Portion). 197. DHA/RPM-74 RPM-74.1 Hasnabad Power Station-Mollarhat Road via Km 5.50 11.08 NCB BG No 1/2/2013 3/3/2013 3/3/2014 Bibir Bazar,Mawa,Paina Bazar, purbadi Ghoshbar. RPM-74.2 Hasnabad Power Station-Mollarhat Road via Km 6.30 14.34 NCB BG No 1/2/2013 3/3/2013 3/3/2014 Bibir Bazar,Mawa,Paina Bazar, purbadi Ghoshbar. 198. DHA/RPM-75 RPM-75.1 Nawabgonj-Paragramhat GC Km 8.00 27.60 NCB BG No 1/15/2013 3/16/2013 3/16/2014 RPM-75.2 Nawabgonj-Paragramhat GC Km 8.43 29.08 NCB BG No 1/15/2013 3/16/2013 3/16/2014 199. B.BARIA Rehabilitation & Maintenance of UZR & Km 34.00 117.30 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 200. CHANDPUR Rehabilitation & Maintenance of UZR & Km 36.00 124.20 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 201. CHITTAGONG Rehabilitation & Maintenance of UZR & Km 45.00 155.25 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 202. COMILLA Rehabilitation & Maintenance of UZR & Km 69.00 238.05 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 203. COX'S BAZAR Rehabilitation & Maintenance of UZR & Km 31.00 106.95 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 204. DHAKA Rehabilitation & Maintenance of UZR & Km 32.00 110.40 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 205. FENI Rehabilitation & Maintenance of UZR & Km 23.00 79.35 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 15 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 206. GAZIPUR Rehabilitation & Maintenance of UZR & Km 42.00 144.90 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 207. HABIGANJ Rehabilitation & Maintenance of UZR & Km 37.00 127.65 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 208. JAMALPUR Rehabilitation & Maintenance of UZR & Km 43.00 148.35 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 209. KISHOREGANJ Rehabilitation & Maintenance of UZR & Km 36.00 124.20 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 210. LAXMIPUR Rehabilitation & Maintenance of UZR & Km 36.00 124.20 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 211. MANIKGANJ Rehabilitation & Maintenance of UZR & Km 26.00 89.70 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 212. MOULVIBAZAR Rehabilitation & Maintenance of UZR & Km 37.00 127.65 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 213. MUNSHIGANJ Rehabilitation & Maintenance of UZR & Km 23.00 79.35 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 214. MYMENSINGH Rehabilitation & Maintenance of UZR & Km 62.00 213.90 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 215. NARAYANGANJ Rehabilitation & Maintenance of UZR & Km 31.00 106.95 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 216. NARSHINGDI Rehabilitation & Maintenance of UZR & Km 44.00 151.80 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 217. NETROKONA Rehabilitation & Maintenance of UZR & Km 32.00 110.40 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 218. NOAKHALI Rehabilitation & Maintenance of UZR & Km 47.00 162.15 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 219. PABNA Rehabilitation & Maintenance of UZR & Km 39.00 134.55 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 220. SHERPUR Rehabilitation & Maintenance of UZR & Km 33.00 113.85 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 221. SIRAJGANJ Rehabilitation & Maintenance of UZR & Km 43.00 148.35 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 222. SUNAMGANJ Rehabilitation & Maintenance of UZR & Km 34.00 117.30 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 223. SYLHET Rehabilitation & Maintenance of UZR & Km 39.00 134.55 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 224. TANGAIL Rehabilitation & Maintenance of UZR & Km 46.00 158.70 NCB BG No 8/1/2013 9/30/2013 9/30/2014 UNR 225. B.BARIA Rehabilitation & Maintenance of UZR & Km 34.00 117.30 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 226. CHANDPUR Rehabilitation & Maintenance of UZR & Km 36.00 124.20 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 227. CHITTAGONG Rehabilitation & Maintenance of UZR & Km 45.00 155.25 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 228. COMILLA Rehabilitation & Maintenance of UZR & Km 69.00 238.05 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 229. COX'S BAZAR Rehabilitation & Maintenance of UZR & Km 31.00 106.95 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 16 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 230. DHAKA Rehabilitation & Maintenance of UZR & Km 32.00 110.40 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 231. FENI Rehabilitation & Maintenance of UZR & Km 23.00 79.35 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 232. GAZIPUR Rehabilitation & Maintenance of UZR & Km 42.00 144.90 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 233. HABIGANJ Rehabilitation & Maintenance of UZR & Km 37.00 127.65 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 234. JAMALPUR Rehabilitation & Maintenance of UZR & Km 43.00 148.35 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 235. KISHOREGANJ Rehabilitation & Maintenance of UZR & Km 36.00 124.20 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 236. LAXMIPUR Rehabilitation & Maintenance of UZR & Km 36.00 124.20 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 237. MANIKGANJ Rehabilitation & Maintenance of UZR & Km 26.00 89.70 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 238. MOULVIBAZAR Rehabilitation & Maintenance of UZR & Km 37.00 127.65 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 239. MUNSHIGANJ Rehabilitation & Maintenance of UZR & Km 23.00 79.35 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 240. MYMENSINGH Rehabilitation & Maintenance of UZR & Km 62.00 213.90 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 241. NARAYANGANJ Rehabilitation & Maintenance of UZR & Km 31.00 106.95 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 242. NARSHINGDI Rehabilitation & Maintenance of UZR & Km 44.00 151.80 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 243. NETROKONA Rehabilitation & Maintenance of UZR & Km 32.00 110.40 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 244. NOAKHALI Rehabilitation & Maintenance of UZR & Km 47.00 162.15 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 245. PABNA Rehabilitation & Maintenance of UZR & Km 39.00 134.55 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 246. SHERPUR Rehabilitation & Maintenance of UZR & Km 33.00 113.85 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 247. SIRAJGANJ Rehabilitation & Maintenance of UZR & Km 43.00 148.35 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 248. SUNAMGANJ Rehabilitation & Maintenance of UZR & Km 34.00 117.30 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 249. SYLHET Rehabilitation & Maintenance of UZR & Km 39.00 134.55 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 250. TANGAIL Rehabilitation & Maintenance of UZR & Km 46.00 158.70 NCB BG No 4/1/2014 5/31/2014 5/31/2015 UNR 251. NOA/PBMC-1 PBMC-1.1 Sonapur-Thanar hat-Akther Miar Hat Road. Km 16.30 40.42 NCB BG No 3/5/2013 4/30/2013 6/30/2018 PBMC-1.2 Upazilla H.Q-Halim Bazar-Al -Amin Bazar- Km 8.25 20.46 NCB BG No 3/5/2013 4/30/2013 6/30/2018 Banglabazar Road. 252. COM/PBMC-2 Rajabazar-Alkara (Shah Fakruddin Road) Km 34.50 85.56 NCB BG No 3/5/2013 4/30/2013 6/30/2018 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 17 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 253. MOU/PBMC-3 Brahman Bazar-Fenchugonj Km 15.00 37.20 NCB BG No 3/5/2013 4/30/2013 6/30/2018 254. COX/PBMC-4 PBMC-4.1 Teknaf Bus Station-Shamlapur Road. Km 30.10 74.65 NCB BG No 3/5/2013 4/30/2013 6/30/2018 PBMC-4.2 Coat bazar-Shaplapur GC Road Via- Km 31.29 77.60 NCB BG No 3/5/2013 4/30/2013 6/30/2018 Sonarpara Monkhali Road. 255. 1 Package PBMC (NOAKHALI) Km 28.00 69.44 NCB BG No 10/1/2013 11/30/2013 6/30/2018 256. 1 Package PBMC (COMILLA) Km 50.00 124.00 NCB BG No 10/1/2013 11/30/2013 6/30/2018 257. 1 Package PBMC (MOULVIBAZAR) Km 20.00 49.60 NCB BG No 10/1/2013 11/30/2013 6/30/2018 258. 1 Package PBMC (MYMENSINGH) Km 30.00 74.40 NCB BG No 10/1/2013 11/30/2013 6/30/2018 259. 1 Package PBMC (KISHOREGANJ) Km 30.00 74.40 NCB BG No 10/1/2013 11/30/2013 6/30/2018 260. DHA/GCM-1 Improvement of Gobindapur GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 261. GAZ/GCM-2 Improvement of Shaoraid GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 262. NARA/GCM-3 Improvement of Araihazar GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 263. NAR/GCM-4 Improvement of Hatirdia GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 264. PAB/GCM-5 Improvement of Nakalia GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 265. SIR/GCM-6 Improvement of Jamtali GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 266. TAN/GCM-7 Improvement of Ishorganj GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 267. JAM/GCM-8 Improvement of Kapasata Hajipur GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 268. KIS/GCM-9 Improvement of Sabinagar GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 269. MYM/GCM-10 Improvement of Mohammadnagar GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 270. NET/GCM-11 Improvement of Krishnapur GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 271. SHE/GCM-12 Improvement of Nayabil GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 272. HAB/GCM-13 Improvement of Choumohani GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 273. SUN/GCM-14 Improvement of Biswamvarpur GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 274. BRA/GCM-15 Improvement of Talsahar GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 275. CHA/GCM-16 Improvement of Mohamaya GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 18 of 43 Sl. Contract Package Number Contract Description Unit Qty/ Estimated Price (in Procedure/ PPA/BG Prior Planned Date of Bid Planned Date Planned Date of Name of Progress of No. Nos. million Taka) Method Review2 Opening (Actual of Contract Completion Contractor Procurement (Actual Contract (Yes / No) Date of Bid Opening) Signing (Actual Date of as of Price in Contract (Actual Date Completion) ________ Currency) of Contract (date) Signing) 276. CHA/GCM-17 Improvement of Chengarchar GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 277. COM/GCM-18 Improvement of Badarpur GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 278. FEN/GCM-19 Improvement of Panchgachiya Hat GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 279. CTG/GCM-20 Improvement of Adhunagar Khan Hat GCM No 1 7.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 280. 20 Packages Market Operation and Management No 20 16.50 NCB BG No 9/1/2013 10/31/2013 5/4/2015 281. GAZ/RJ-1 Kaliakoir Ghat No 1 6.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 282. TAN/RJ-2 Kodalia Ghat No 1 6.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 283. TAN/RJ-3 Kodalia Ghat No 1 6.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 284. TAN/RJ-4 Hatubhanga Ghat No 1 6.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 285. TAN/RJ-5 Mirzapur Ghat No 1 6.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 286. COM/RJ-6 Batikandi Ghat No 1 6.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 287. COM/RJ-7 Char Kumeria Ghat No 1 6.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 288. COM/RJ-8 Khatalia Ghat No 1 6.50 NCB BG No 9/1/2013 10/31/2013 10/31/2014 Sub-Total : 4131.49 19,046.85 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 19 of 43 Updated on : 13/02/2013 Remarks 15 c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 20 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 21 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 22 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 23 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 24 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 25 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 26 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 27 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 28 of 43 Remarks NOA issued Evaluation under process NOA issued NOA issued NOA issued NOA issued NOA issued Evaluation under process Evaluation under process NOA issued NOA issued Re-bidding under process Re-bidding under process Re-bidding under process Re-bidding under process To be procured through eGP tendering To be procured through eGP tendering IFT invited IFT invited IFT invited IFT invited c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 29 of 43 Remarks IFT invited Evaluation under process Evaluation under process Evaluation under process Evaluation under process Evaluation under process Evaluation under process Evaluation under process Evaluation under process To be procured through eGP tendering Evaluation under process Evaluation under process Tender received Tender received Tender received c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 30 of 43 Remarks Tender received Tender received Tender received Evaluation under process Evaluation under process Evaluation under process Evaluation under process Evaluation under process IFT invited IFT invited To be procured through eGP tendering To be procured through eGP tendering Evaluation under process Evaluation under process NOA issued NOA issued Evaluation under process NOA issued NOA issued NOA issued NOA issued c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 31 of 43 Remarks NOA issued NOA issued NOA issued NOA issued NOA issued NOA issued Evaluation under process Evaluation under process Evaluation under process Evaluation under process To be procured through eGP tendering To be procured through eGP tendering Evaluation under process Evaluation under process Approval for tender Approval for tender To be procured through eGP tendering To be procured through eGP tendering To be procured through eGP tendering c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 32 of 43 Remarks IFT invited IFT invited IFT invited IFT invited IFT invited IFT invited IFT invited IFT invited To be procured through eGP tendering To be procured through eGP tendering IFT invited IFT invited IFT invited IFT invited To be procured through eGP tendering To be procured through eGP tendering NOA issued NOA issued NOA issued Evaluation under process c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 33 of 43 Remarks Evaluation under process To be procured through eGP tendering To be procured through eGP tendering Evaluation under process Evaluation under process Evaluation under process Evaluation under process Evaluation under process Evaluation under process Re-bidding under process Evaluation under process Estimate preparation under process Estimate preparation under process c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 34 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 35 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 36 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 37 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Works 38 of 43 Procurement Plan for Goods Contract Sl. Contract Contract Description Unit Qty/ Estimated Price (in Procedure/ Procurement Prior Planned Date of Bid Planned Date Planned Date of Name of Supplier Progress of Remarks No. Package Nos. million Taka) Method Guideline 2 Opening (Actual Date of Contract Delivery (Actual Procurement Review Number (Actual Contract (PPA / BG) (Yes / No) of Bid Opening) Signing Date of Delivery) as of ________ Price in Contract (Actual Date (date) Currency) of Contract Signing) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 G1 Bitumen Mixing Plant No. 6 18.00 ICB BG No 4/30/2013 5/30/2013 11/26/2013 Q 2 G2 Supervision Vehicle No. 25 222.00 ICB BG Yes 4/30/2013 6/30/2013 12/27/2013 M 3 G3 Computer and Accessories No. 300 24.00 NCB/NS BG No 2/28/2013 4/30/2013 10/27/2013 IT 4 G4 Photocopier No. 25 3.75 NCB/NS BG No 2/28/2013 4/29/2013 10/26/2013 IT 6 G6 Traffic Logging System No. 5 15.00 NCB/NS BG No 4/30/2013 6/30/2013 12/27/2013 M 7 G7 Roughometer No. 16 28.80 NCB/NS BG No 6/30/2013 8/30/2013 2/26/2014 M 8 G8 Portable weigh bridge No. 5 7.50 NCB/NS BG No 8/31/2013 10/31/2013 4/29/2014 M 9 G9 Bitumen heating & distributing equipment No. 10 7.50 NCB/NS BG No 5/30/2013 7/30/2013 1/26/2014 Q 10 G10 Densometer No. 26 24.70 ICB/NCB/ BG No 5/30/2013 7/30/2013 1/26/2014 M NS 11 G11 Multimedia Video Projector No. 26 6.50 NCB/NS BG No 8/30/2013 10/30/2013 4/28/2014 IT 12 G12 Local Area Network (LAN) - 76.60 ICB BG Yes 4/30/2014 6/30/2014 12/27/2014 IT (online UPS & other related accessories) 13 G13 MIS Data Center - 61.11 ICB BG Yes 5/31/2014 7/30/2014 1/26/2015 IT 14 G14 ICT Equipments and Software - 50.04 ICB BG Yes 6/30/2014 8/30/2014 2/26/2015 IT 15 G16 Equipment for road safety - 11.25 NCB/NS BG No 2/28/2013 4/29/2013 10/26/2013 Sub-Total : 556.75 PPR Public Procurement Rules 2008 BG Bank Guideline for Procurement \2 As per "Procurement Threshold Table" c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Goods 39 of 43 Procurement Plan for Consultancy Services Contract Sl. Contract Contract Description Unit Qty/ Nos. Estimated Price (in Procedure/ Procurement Prior Planned Date of Planned Date Planned Date of Name of Progress of No. Package million Taka) Method Guideline Review2 Proposals Submission of Contract Completion Consultant/ Firm Procurement Number (Actual Contract (PPA / BG) (Yes / No) (Actual Date of Signing (Actual Date of as of ________ Price in Contract Proposals Submission) (Actual Date Completion) (date) Currency) of Contract Signing) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1 MS-1 Management Support Consultancy (MSC) 200.00 QCBS BG Yes 12/10/2012 3/10/2013 6/30/2017 2 R-1 Design and Supervision Consultancy 400.00 QCBS BG Yes 11/29/2012 2/27/2013 6/30/2017 (D&SC) 3 R-2 Design and Supervision Consultancy 400.00 QCBS BG Yes 11/29/2012 2/27/2013 6/30/2017 (D&SC) 4 P-1 Integrated Performance Audit Consultant 100.00 FBS BG Yes 10/1/2013 3/30/2014 6/30/2017 5 PBMC 15.00 IC BG Yes 3/15/2013 9/11/2013 6/30/2017 6 Inland Water Transport (IWT) 15.00 IC BG Yes 7/1/2013 12/28/2013 6/30/2017 7 Maintenance Policy & Management 127.50 QBS BG Yes 6/15/2013 12/12/2013 12/2/2015 8 Design Quality 81.70 QBS BG Yes 6/15/2013 9/13/2013 3/7/2015 9 Hydrological data collection from 330 9.75 SSS BG Yes 5/15/2013 11/11/2013 11/6/2014 gauges’ stations country-wide and analysis for Bridge planning, design and maintenance needs. 10 Implementation of ‘pilot’ collaborative 3- 26.20 SSS BG Yes 6/30/2013 12/27/2013 12/11/2016 years LGED / BUET program for small-to- medium scale Research projects determined by LGED priorities and needs 11 EMS/EMIS upgrading 19.50 QCBS BG Yes 12/31/2013 3/31/2014 12/26/2014 12 Performance Management & MIP Support 32.25 FBS BG Yes 12/31/2013 3/31/2014 12/26/2014 13 IT-ICT-MIS Strategy Implementation 73.50 QCBS BG Yes 6/30/2013 9/28/2013 9/18/2015 14 TA / Capacity Building: Road Safety 24.00 IC BG Yes 3/31/2013 5/30/2013 5/30/2016 Adviser -international expert to conduct RSA of designs of second year projects, develop standard layouts and clauses for BoQ, guide development of training programs, develop guidelines and manuals - 3 years 16 TA / Consultancy Services: Develop and 11.25 IC BG Yes 6/15/2013 12/12/2013 10/8/2014 trial an IT-based RTS database under CRRSU charge (linked to AMS) for field RTS data input and HQ- level data analysis / reporting c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Services 40 of 43 Sl. Contract Contract Description Unit Qty/ Nos. Estimated Price (in Procedure/ Procurement Prior Planned Date of Planned Date Planned Date of Name of Progress of No. Package million Taka) Method Guideline Review2 Proposals Submission of Contract Completion Consultant/ Firm Procurement Number (Actual Contract (PPA / BG) (Yes / No) (Actual Date of Signing (Actual Date of as of ________ Price in Contract Proposals Submission) (Actual Date Completion) (date) Currency) of Contract Signing) 17 TA / Consultancy Services: develop and 56.00 FBS BG Yes 6/1/2013 11/28/2013 11/18/2015 conduct awareness campaigns and road safety training for schools, LGIs, drivers, etc, - in 26 districts including publication of materials 18 TA for transport safety collaboration (e.g. 7.50 IC BG No 1/15/2014 7/14/2014 6/28/2017 rickshaw, water transport and/or rural vehicles’ safety) 19 Long-term framework contract with ARI- 40.00 SSS BG Yes 3/30/2013 4/30/2013 4/10/2017 BUET to conduct training program for LGED on road safety, develop a training program for LGED training unit, develop specific modules, road safety research and development, evaluation of effectiveness of treatments c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Services 41 of 43 Remarks 15 Evaluation of technical proposal sent to WB Evaluation of technical proposal sent to WB c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Services 42 of 43 Remarks c:\re\000442464_20130225142256_D\original\755120PROP0P1200months0upto0June014.xls.xls \ PP-Services 43 of 43