Sample Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan Original: March, 2014 : Revision: March, 2017 3. Date of General Procurement Notice: April, 2014 4. Period covered by this procurement plan: The procurement period of project covered from year May 1, 2015 to July 31, 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1 NCB (Goods) ; IT and Non-consulting Equivalent and Below US$ Above USD 2 mil. services 1,000,000 2 NCB (Works) Equivalent and Below US$ Above USD 10 mil. 10 million 3 Shopping (Goods) Equivalent and Below US$ None 100,000 4 Shopping (Works) Equivalent and Below US$ None 200,000 2. Prequalification. Bidders for Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P133828 is developed by MoA (for Parts A and C1) and the Guidelines for implementation of activities under parts B and C2 are developed by NAPR 5. Any Other Special Procurement Arrangements: None 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estim Packag Domest Review Comments No. ated es ic by Cost Prefere Bank nce (Prior / (yes/no) Post) US$ millio n Summary of the ICB (Works) 22.4 2 No Prior The first one has been already signed Summary of the NCB (Works) 1.15 1 No Post Summary of the NCB (Goods) 0.75 3 No Post Summary of the ICB (Non- 0.8 2 No Post Consultant Services) Summary of the Shopping 0.4 13 No Post (Goods) Summary of the Shopping (Non- 0.074 1 No Post Consultant Services) Summary of the Direct 0.2 2 Contracting III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods Above US$ (Firms) 1,000,000 2. CQS Applicable for assignments with estimation below USD 300K 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packag Review Comments Assignment Cost es by Bank US$ (Prior / million Post) Summary of number of contracts 3.5 3 Prior that will be let under QCBS Summary of number of contracts 0.51 7 Post LCS, FB, CQS that will be let under other methods Summary of number of contracts 1.01 35 Prior/Post 4 signed contracts were subject that will be let under IC to the Prior reviewer Summary of number of contracts 0.33 11 Prior/Post 9 signed contracts were subject that will be let under SSS to the Prior reviewer PROCUREMENT Georgia : Irrigation and Land Market Development Project PLAN General Information Country: Georgia Banks Approval Date of the Original Procurement Plan: 2016-09-15 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-02-27 Project ID: P133828 GPN Date: Project Name: Irrigation and Land Market Development Project Loan / Credit No: IDA / 54560 Executing Agency(ies): Ministry of Agriculture of Georgia, National Agency for Public Registry WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1 Irrigation and IDIC/CW/ICB/01 / Rehabilitation Drainage Improvement of Irrigation Scheme Main Canals Component 3 Project Single Stage - One and Electrical and Mechanical IDA / 54560 Prior Request for Bids Open - International N 0.00 14,506,615.02 Under Review 2016-02-23 2016-03-17 Management Envelope parts of main canal and Component 2 Land Market headwork Development IDIC/CW/NCB/01 / Sioni and Component 1 Irrigation and Single Stage - One Pending IDA / 54560 Post Request for Bids Open - National 1,150,000.00 0.00 2017-12-01 2017-12-15 2018-01-14 2018-02-13 2018-03-13 2018-09-09 Algeti Dams Safety Works Drainage Improvement Envelope Implementation IDIC/CW/ICB/02 / Rehabilitation of secondary networks for Zeda Component 1 Irrigation and Single Stage - One Pending IDA / 54560 Prior Request for Bids Open - International 19,700,000.00 0.00 2018-11-05 2018-11-19 2018-12-31 2019-01-30 2019-02-27 2019-07-27 Ru, Tbisi-Kumisi and Zemo Drainage Improvement Envelope Implementation Samgori Irrigation Schemes GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDIC/G/SH/07 / PPMD office Component 3 Project Request for Single Stage - One Pending IDA / 54560 Post Open - National 20,000.00 0.00 2018-01-17 2018-02-14 2018-04-15 Furniture Management Quotations Envelope Implementation IDIC/G/SH/08 / Environmental Component 3 Project Request for Single Stage - One Pending IDA / 54560 Post Open - National 15,000.00 0.00 2018-01-17 2018-02-14 2018-04-15 Monitoring Field Equipment Management Quotations Envelope Implementation IDIC/G/SH/09 / Environmental Component 3 Project Request for Single Stage - One Pending IDA / 54560 Post Open - National 5,000.00 0.00 2018-01-17 2018-02-14 2018-04-15 Monitoring Program Management Quotations Envelope Implementation LMDC/G/SH/01 / GPS Rover Component 2 Land Market Request for Single Stage - One IDA / 54560 Post Open - National 75,000.00 74,273.86 Signed 2017-03-20 2017-04-13 2017-05-16 2017-06-12 and tablet controller Development Quotations Envelope LMDC/G/SH/02 / Supply of Component 2 Land Market Request for Single Stage - One IDA / 54560 Post Open - National 26,000.00 25,726.14 Signed 2017-03-23 2017-04-16 2017-05-16 2017-06-15 Electronic tachometer Development Quotations Envelope LMDC/G/SH/05 / Supply of off- Component 2 Land Market Request for Single Stage - One IDA / 54560 Post Open - National 92,000.00 86,710.96 Signed 2017-03-27 2017-04-20 2017-06-09 2017-06-19 road vehicles Development Quotations Envelope LMDC/G/SH/03 / Supply of Computers and Office Equipment Component 2 Land Market Request for Single Stage - One IDA / 54560 Post Open - National 65,000.00 0.00 Canceled 2017-05-11 2017-06-04 2017-08-03 for Pilot Project Team and Development Quotations Envelope Administration LMDC/G/SH/03-1 / Supply of Computers and Office Equipment Component 2 Land Market Request for Single Stage - One IDA / 54560 Post Open - National 65,000.00 53,217.19 Signed 2017-05-16 2017-06-21 2017-06-12 2017-08-05 for Pilot Project Team and Development Quotations Envelope Administration IDIC/G/DC/01 / Procurement of Component 1 Irrigation and IDA / 54560 Post Direct Selection Direct 19,000.00 0.00 Canceled 2017-02-17 2017-02-27 2017-03-11 2017-05-10 Agricultural software - Sic^2 Drainage Improvement LMDC/G/SH/06 / Procurement Component 2 Land Market Request for Single Stage - One of office furniture for Pilot Project IDA / 54560 Post Open - National 52,800.00 23,166.02 Signed 2017-09-05 2017-09-29 2017-10-23 2017-11-13 Development Quotations Envelope Team and Administration LMDC/G/SH/07 / Supply of 6 Component 2 Land Market Request for Single Stage - One IDA / 54560 Post Open - National 4,000.00 3,386.90 Signed 2017-09-06 2017-09-23 2017-08-29 2017-10-23 units of laser distance meters Development Quotations Envelope LMDC/G/SH/04 / Supply of Component 2 Land Market Request for Single Stage - One IDA / 54560 Post Open - National 7,000.00 0.00 Canceled 2017-03-23 2017-04-16 2017-06-15 Metal Field markers (1000 units) Development Quotations Envelope LMDC/G/SH/10 / Supply of Component 2 Land Market Request for Single Stage - One Electronic Tachometer for in- IDA / 54560 Post Open - National 12,863.00 8,901.67 Signed 2017-09-19 2017-10-14 2017-11-22 2017-11-28 Development Quotations Envelope house team IDIC/G/SH/10 / Supply of Component 1 Irrigation and Request for Single Stage - One Tachometer for Georgian IDA / 54560 Post Open - National 17,000.00 0.00 Canceled 2017-07-06 2017-08-08 2017-10-07 Drainage Improvement Quotations Envelope Amelioration IDIC/G/SH/13 / Supply of 5 units Component 1 Irrigation and Request for Single Stage - One of off-road small size trucks to IDA / 54560 Post Open - National 100,000.00 0.00 Canceled 2017-10-05 2017-10-28 2017-12-27 Drainage Improvement Quotations Envelope the Georgian Amelioration (GA) IDIC/G/NCB/02 / Supply of Component 1 Irrigation and Single Stage - One Machinery and Equipment to IDA / 54560 Post Request for Bids Open - National 450,000.00 80,241.94 Signed 2017-12-04 2017-11-13 2017-12-18 2018-01-17 2017-12-15 2018-02-16 2018-01-30 2018-03-09 2018-02-12 2018-06-07 Drainage Improvement Envelope Georgian Amelioration LMDC/G/DC/01 / Supply of Component 2 Land Market IDA / 54560 Post Direct Selection Direct 44,565.00 45,818.18 Signed 2017-11-27 2017-11-30 2017-10-09 2017-12-09 2017-11-30 2018-01-23 GNSS Rovers for in-house team Development LMDC/G/SH/08 / Supply of Component 2 Land Market Request for Single Stage - One Computers and Office Equipment IDA / 54560 Post Open - National 86,368.00 0.00 Canceled 2017-09-26 2017-10-21 2017-12-20 Development Quotations Envelope and Plotter for in-house team Page 1 LMDC/G/SH/11 / Supply of Mini Component 2 Land Market Request for Single Stage - One Under IDA / 54560 Post Open - National 40,000.00 0.00 2018-01-16 2018-02-03 2018-03-05 Bus Development Quotations Envelope Implementation LMDC/G/SH/08-1 / Supply of Component 2 Land Market Request for Single Stage - One Pending Computers, office equipment and IDA / 54560 Post Open - National 86,368.00 0.00 2018-01-16 2018-02-03 2018-03-05 Development Quotations Envelope Implementation plotter for in-house team LMDC/G/DC/03 / Supply of Component 2 Land Market Canopy for the Mitsubishi Pickup IDA / 54560 Post Direct Selection Direct 1,740.00 3,515.15 Signed 2018-01-15 2018-01-17 2018-01-24 2018-01-12 2018-02-23 Development Truck - 2 Units IDIC/G/SH/12 / Supply of 3 units of Automatic Flow Measuring Devices and 15 units of water Component 1 Irrigation and Request for Single Stage - One Pending IDA / 54560 Post Open - National 54,000.00 0.00 2018-02-08 2018-03-11 2018-05-10 flow velocity measurement Drainage Improvement Quotations Envelope Implementation equipment for Georgian Amelioration (GA) IDIC/G/NCB/03 / PPMD Component 3 Project Single Stage - One IDA / 54560 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2018-01-10 2018-01-24 2018-02-23 2018-03-25 2018-04-22 2018-06-21 Equipment - Vehicles Management Envelope IDIC/G/NCB/01 / Supply of IT Component 1 Irrigation and Single Stage - One equipment to Georgian IDA / 54560 Post Request for Bids Open - National 375,000.00 0.00 Canceled 2017-04-25 2017-10-23 2017-05-09 2017-06-08 2017-12-05 2017-07-08 2017-12-15 2017-07-29 2017-09-27 Drainage Improvement Envelope Amelioration LMDC/G/SH/12 / Supply of Component 2 Land Market Request for Single Stage - One Pending IDA / 54560 Post Open - National 16,000.00 0.00 2018-01-16 2018-02-03 2018-03-05 Photo Video Camera and Drone Development Quotations Envelope Implementation LMDC/G/DC/02 / Supply of Component 2 Land Market Leica GS14 GSM/UFH base and IDA / 54560 Post Direct Selection Direct 26,000.00 26,720.80 Signed 2018-01-15 2017-12-22 2018-01-17 2018-01-09 2018-01-24 2018-01-17 2018-02-23 Development rover package IDIC/G/SH/06 / Supply of IT Office Equipment for DPMMU Component 3 Project Request for Single Stage - One Under IDA / 54560 Post Open - National 80,000.00 0.00 2018-01-17 2018-02-14 2018-04-15 and Amelioration and Land Management Quotations Envelope Implementation Management Department of MoA IDIC/G/SH/11 / Supply Echo- sounder and 10 units of Leveling Component 1 Irrigation and Request for Single Stage - One IDA / 54560 Post Open - National 26,000.00 0.00 Canceled 2017-03-02 2017-01-26 2017-04-02 2017-06-01 Instrument to Georgian Drainage Improvement Quotations Envelope Amelioration IDIC/G/NCB/01-1 / Supply of IT Component 1 Irrigation and Single Stage - One Pending equipment to Georgian IDA / 54560 Post Request for Bids Open - National 375,000.00 0.00 2018-01-29 2018-02-03 2018-03-05 2018-04-04 2018-04-25 2018-07-24 Drainage Improvement Envelope Implementation Amelioration IDIC/G/NCB/02-1 / Supply of Component 1 Irrigation and Single Stage - One Pending Machinery and Equipment to IDA / 54560 Post Request for Bids Open - National 357,200.00 0.00 2018-02-27 2018-02-27 2018-03-29 2018-04-28 2018-05-19 2018-07-18 Drainage Improvement Envelope Implementation Georgian Amelioration NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LMDC/NCS/SH/01 / Manglisi Component 2 Land Market Request for Single Stage - One IDA / 54560 Post Open - National 74,743.00 0.00 Canceled 2017-03-02 2017-03-26 2017-05-25 Registration Services - field work Development Quotations Envelope LMDC/NCS/NCB/02-1 / Manglisi Component 2 Land Market Single Stage - One Land Registration Services - IDA / 54560 Post Request for Bids Open - National 74,743.00 72,769.93 Signed 2017-05-22 2017-05-12 2017-05-27 2017-05-12 2017-06-26 2017-06-12 2017-07-10 2017-06-23 2017-08-07 2017-07-12 2017-11-20 Development Envelope Technical Fieldwork LMDC/NCS/NCB/02 / Manglisi Component 2 Land Market Single Stage - One IDA / 54560 Post Request for Bids Open - National 74,743.00 0.00 Canceled 2017-04-07 2017-03-28 2017-04-12 2017-03-28 2017-05-12 2017-05-26 2017-06-23 2017-08-22 Registration Services - field work Development Envelope LMDC/NCS/NCB/05 / Zaridzeebi, Saguramo and Component 2 Land Market Single Stage - One Under IDA / 54560 Post Request for Bids Open - National 101,000.00 0.00 2017-08-21 2017-08-07 2017-08-24 2017-09-23 2017-09-07 2017-10-14 2017-10-10 2017-11-11 2018-05-10 Karaleti Land Registration Development Envelope Implementation Services - Technical Fieldwork LMDC/NCS/NCB/07 / Arboshiki and Arkiloskalo Land Component 2 Land Market Single Stage - One Pending IDA / 54560 Post Request for Bids Open - National 133,000.00 0.00 2017-11-30 2017-12-03 2018-01-02 2018-01-23 2018-02-20 2018-08-19 Registration Services - Technical Development Envelope Implementation Fieldwork LMDC/NCS/NCB/04 / Component 2 Land Market Request for Single Stage - One Under Lakhamula Land Registration IDA / 54560 Post Open - National 7,500.00 0.00 2017-09-07 2017-10-05 2018-02-02 Development Quotations Envelope Implementation Services - Technical Fieldwork LMDC/NCS/NCB/03 / Shuakhevi Component 2 Land Market Request for Single Stage - One Under Land Registration Services - IDA / 54560 Post Open - National 53,000.00 0.00 2017-09-04 2017-10-02 2018-03-11 Development Quotations Envelope Implementation Technical Fieldwork LMDC/NCS/NCB/01 / Jimiti and Component 2 Land Market Single Stage - One Mzisguli Land Registration IDA / 54560 Post Request for Bids Open - National 103,000.00 0.00 Canceled 2017-10-30 2017-11-02 2017-12-02 2017-12-23 2018-01-20 2018-07-19 Development Envelope Services - Technical Fieldwork IDIC/NCS/NCB/02 / Bathymetric Component 1 Irrigation and Single Stage - One Pending survey for Algeti, Sioni and Tbilisi IDA / 54560 Post Request for Bids Open - National 157,000.00 0.00 2018-02-12 2018-02-17 2018-03-19 2018-04-18 2018-05-09 2018-11-05 Drainage Improvement Envelope Implementation Reservoirs IDIC/NCS/NCB/01 / Topographic Survey for Tbisi Kumisi, Kvemo Component 1 Irrigation and Single Stage - One IDA / 54560 Post Request for Bids Open - National 297,040.00 0.00 Canceled 2017-02-27 2017-03-10 2017-03-06 2017-03-10 2017-03-27 2017-04-18 2017-04-10 2017-04-17 2017-08-15 Samgori and Zeda Ru Irrigation Drainage Improvement Envelope Schemes LMDC/NCS/NCB/06 / Salkhino Component 2 Land Market Single Stage - One Under Land Registration Services - IDA / 54560 Post Request for Bids Open - National 70,320.00 0.00 2018-01-15 2018-01-15 2018-01-15 2018-02-14 2018-02-14 2018-02-21 2018-02-26 2018-05-27 Development Envelope Implementation Technical Fieldwork CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ILMDP/C/QCBS/01-2015 / Consulting Services for Component 1 Irrigation and Supervision of Civil Works to be Drainage Improvement implemented under Irrigation and Component 3 Project Quality And Cost- IDA / 54560 Prior Open - International N 1,500,000.00 2,366,014.45 Signed 2016-02-03 2016-02-29 Land Market Development Management Based Selection Project - Irrigation And Drainage Component 2 Land Market Improvement Component Development (ILMDP) IDIC/CS/LCS/02 / GILMDP Component 1 Irrigation and Project Financial Audit for 2015- IDA / 54560 Post Least Cost Selection Open - International 60,000.00 36,167.00 Signed 2016-11-07 2016-11-10 2016-11-17 2016-11-10 2016-12-22 2017-01-11 2017-01-12 2017-02-01 2017-02-11 2017-02-27 2017-03-11 2017-03-13 2017-03-18 2017-03-15 2019-07-31 Drainage Improvement 2019 fiscal years IDIC/CS/CQS/01 / Strengthening Consultant of Designing Capacity and Component 1 Irrigation and Pending IDA / 54560 Post Qualification Open - National 100,000.00 0.00 2017-12-11 2017-12-25 2018-01-15 2018-02-05 2018-02-12 2019-02-12 Technical maintenance of Drainage Improvement Implementation Selection Georgian Amelioration IDIC/CS/QCBS/03 / Institutional Component 1 Irrigation and Quality And Cost- Pending Strengthening of Georgian IDA / 54560 Prior Open - International 1,200,000.00 0.00 2017-11-01 2017-11-15 2017-12-13 2018-01-10 2018-02-09 2018-03-02 2018-03-16 2019-09-07 Drainage Improvement Based Selection Implementation Amelioration Consultant LMDC/CS/CQS/02 / Monitoring Component 2 Land Market Pending IDA / 54560 Post Qualification Open - National 100,000.00 0.00 2017-03-27 2017-04-10 2017-05-08 2017-05-15 2017-05-18 2018-05-18 and Impact Evaluation Analysis Development Implementation Selection LMDC/CS/CQS/03 / Consultant Component 2 Land Market Pending Implementation of baseline IDA / 54560 Post Qualification Open - National 100,000.00 0.00 2017-03-31 2017-04-14 2017-05-12 2017-05-19 2017-05-22 2018-05-22 Development Implementation survey Selection Consultant IDIC/CS/CQS/05 / National Component 3 Project Pending IDA / 54560 Post Qualification Open - National 20,000.00 0.00 2018-03-01 2018-03-15 2018-04-19 2018-05-03 2018-05-10 2018-11-06 Technical Assistance Management Implementation Selection IDIC/CS/CQS/03 / Independent Dam Safety Assessment and Consultant Component 1 Irrigation and Under Design and Supervision of Dam IDA / 54560 Post Qualification Open - International 220,000.00 0.00 2017-07-31 2017-10-11 2017-08-14 2017-10-12 2017-09-18 2017-10-09 2017-10-23 2019-02-15 Drainage Improvement Implementation Safety Activities for Algeti and Selection Sioni Dams IDIC/CS/CQS/07 / Design Consultant Component 1 Irrigation and Engineering Consultancy IDA / 54560 Post Qualification Open - National 50,000.00 0.00 Canceled 2017-02-27 2017-01-25 2017-03-13 2017-01-25 2017-04-24 2017-03-16 2017-05-08 2017-05-15 2018-02-09 Drainage Improvement Services Selection LMDC/CS/CQS/04 / Consultant Component 2 Land Market Pending Consultancy Services for Web- IDA / 54560 Post Qualification Open - National 123,640.00 0.00 2017-09-15 2017-09-29 2017-11-03 2017-11-17 2017-11-24 2018-11-24 Development Implementation development Selection Consultant LMDC/CS/CQS/01 / Public Component 2 Land Market IDA / 54560 Post Qualification Open - National 80,000.00 0.00 Canceled 2017-03-31 2017-04-14 2017-05-12 2017-05-19 2017-05-22 2018-05-22 Awareness Development Selection IDIC/CS/QCBS/02 / Preparation of Detailed Engineering Design and Construction Supervision Component 1 Irrigation and Quality And Cost- Under services for Kvemo Samgori, IDA / 54560 Prior Open - International 4,000,000.00 0.00 2017-09-25 2017-10-09 2017-10-09 2017-11-13 2017-12-11 2018-01-10 2018-01-31 2018-02-21 2019-08-15 Drainage Improvement Based Selection Implementation Tbisi-Kumisi and Zeda Ru irrigation system's secondary, tertiary and on-farm network INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1 Irrigation and Drainage Improvement CS/IC/10 / Procurement Component 3 Project Individual Consultant IDA / 54560 Prior Open N 9,000.00 159,961.41 Signed 2015-02-25 2015-02-25 Consultant Management Selection Component 2 Land Market Development Component 1 Irrigation and IDIC/CS/IC/03 / Water Resource Drainage Improvement and Climate Advisor for Component 3 Project Individual Consultant IDA / 54560 Prior Open N 0.00 42,611.12 Signed 2015-04-24 2015-04-24 Institutional Strengthening of Management Selection UASCG Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/IC/04 / Agricultural Component 3 Project Individual Consultant IDA / 54560 Prior Open N 60,000.00 43,266.65 Signed 2015-04-23 2015-04-23 Economist Management Selection Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/IC/05 / Water Resource Component 3 Project Individual Consultant IDA / 54560 Prior Open N 0.00 34,272.44 Signed 2015-05-22 2015-06-15 Legal Advisor Management Selection Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/IC/01 / Management Component 3 Project Individual Consultant Operation and Maintenance IDA / 54560 Prior Open N 60,000.00 55,932.00 Signed 2015-04-24 2015-06-27 Management Selection (MOM) Advisor Component 2 Land Market Development Page 3 Component 1 Irrigation and Drainage Improvement IDIC/CS/SSS/01 / Local-level Component 3 Project Water Management Institutions IDA / 54560 Prior Direct Selection Direct N 80,000.00 114,971.33 Signed 2015-07-07 Management Advisor Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/SSS/04 / Component Component 3 Project Under IDA / 54560 Prior Direct Selection Direct N 18,000.00 72,661.24 2015-07-01 Director Management Implementation Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/SSS/05 / Financial Component 3 Project Under IDA / 54560 Prior Direct Selection Direct N 17,000.00 69,607.37 2015-07-01 Manager Management Implementation Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/SSS/06 / Accountant Component 3 Project Under IDA / 54560 Prior Direct Selection Direct N 13,000.00 54,506.46 2015-07-01 and Disbursement Specialist Management Implementation Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/SSS/02 / Irrigation Component 3 Project Policy Specialist and Strategy IDA / 54560 Prior Direct Selection Direct N 35,000.00 37,366.67 Signed 2015-07-15 Management Team Leader Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/IC/14 / Component Component 3 Project Individual Consultant Under IDA / 54560 Prior Open N 33,000.00 127,144.73 2015-07-08 2015-07-09 Coordinator Management Selection Implementation Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/SSS/03 / Accounting Component 3 Project IDA / 54560 Prior Direct Selection Direct N 0.00 16,372.07 Signed 2015-11-15 Software Maintenance Specialist Management Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/SSS/08 / Water Component 3 Project IDA / 54560 Prior Direct Selection Direct N 20,000.00 23,862.23 Signed 2016-02-17 Resource and Climate Advisor Management Component 2 Land Market Development Component 1 Irrigation and Drainage Improvement IDIC/CS/SSS/09 / Agricultural Component 3 Project IDA / 54560 Prior Direct Selection Direct N 55,000.00 55,263.33 Signed 2016-02-17 Economist Management Component 2 Land Market Development Component 1 Irrigation and IDIC/CS/SSS/10 / Water Drainage Improvement Resource Legal advisory services Component 3 Project Under IDA / 54560 Prior Direct Selection Direct N 65,000.00 67,587.78 2016-03-30 for Institutional Strengthening of Management Implementation GA Component 2 Land Market Development IDIC/CS/IC/29 / Designing advisory services for Institutional Component 1 Irrigation and Individual Consultant Under Strengthening of Georgian IDA / 54560 Post Open 100,000.00 45,076.00 2016-10-10 2016-09-20 2016-11-19 2016-10-26 2016-12-03 2016-10-28 2016-12-17 2016-11-01 2017-12-17 Drainage Improvement Selection Implementation Amelioration (Consultant with international experience) IDIC/CS/SSS/13 / Team Leader Component 1 Irrigation and for finalization of Irrigation IDA / 54560 Post Direct Selection Direct 20,257.00 20,256.67 Signed 2016-10-24 2016-10-24 2016-11-03 2016-11-04 2016-11-24 2016-11-18 2017-05-23 Drainage Improvement Strategy IDIC/CS/IC/17 / PPMD Engineer Component 3 Project Individual Consultant IDA / 54560 Post Open 70,000.00 22,675.43 Signed 2017-02-20 2017-02-06 2017-03-18 2017-02-13 2017-03-25 2017-02-13 2017-03-30 2017-02-13 2019-07-28 2 Management Selection IDIC/CS/IC/21 / Environmental Component 3 Project Individual Consultant Pending IDA / 54560 Post Open 20,000.00 0.00 2018-01-11 2018-02-13 2018-02-27 2018-03-04 2019-03-04 Specialist Management Selection Implementation IDIC/CS/IC/30 / Agricultural Economics advisory services for Institutional Strengthening of Component 1 Irrigation and Individual Consultant IDA / 54560 Post Open 40,000.00 45,217.60 Signed 2017-02-27 2017-02-22 2017-03-30 2017-03-22 2017-04-09 2017-03-31 2017-04-12 2017-03-31 2018-01-07 Georgian Amelioration Drainage Improvement Selection (Consultant with international experience) LMDC/CS/IC/15 / International Component 2 Land Market Individual Consultant Pending Technical Assistance on data IDA / 54560 Post Open 33,000.00 0.00 2017-04-10 2017-05-05 2017-05-10 2017-05-10 2018-05-10 Development Selection Implementation management LMDC/CS/SSS/01 / Accounting Component 3 Project IDA / 54560 Post Direct Selection Direct 7,500.00 7,069.67 Signed 2017-03-20 2017-04-25 2017-03-24 2017-04-25 2017-03-30 2017-05-01 2018-06-23 soft upgrading/maintenance Management Component 2 Land Market Individual Consultant LMDC/CS/IC/13-1 / Developer IDA / 54560 Post Open 49,500.00 15,760.50 Signed 2017-03-27 2017-08-15 2017-04-21 2017-04-26 2017-04-26 2017-10-09 2018-07-20 Development Selection LMDC/CS/IC/12 / Assistant to Component 3 Project Individual Consultant IDA / 54560 Post Open 22,500.00 14,283.18 Signed 2017-03-31 2017-05-04 2017-04-25 2017-06-20 2017-04-30 2017-06-20 2017-04-30 2017-06-26 2018-07-24 Component Manager Management Selection LMDC/CS/IC/06-1 / Regional Component 2 Land Market Individual Consultant IDA / 54560 Post Open 16,500.00 14,680.81 Signed 2017-03-16 2017-03-23 2017-04-10 2017-05-18 2017-04-15 2017-05-19 2017-04-15 2017-05-22 2018-03-11 facilitator Development Selection LMDC/CS/IC/06-2 / Regional Component 2 Land Market Individual Consultant IDA / 54560 Post Open 16,500.00 14,680.81 Signed 2017-03-16 2017-03-23 2017-04-10 2017-05-18 2017-04-15 2017-05-19 2017-04-15 2017-05-22 2018-03-11 facilitator Development Selection Page 4 LMDC/CS/IC/06-3 / Regional Component 2 Land Market Individual Consultant IDA / 54560 Post Open 16,500.00 17,178.42 Signed 2017-03-16 2017-03-23 2017-04-10 2017-06-20 2017-04-15 2017-06-20 2017-04-15 2017-06-26 2018-03-11 facilitator Development Selection LMDC/CS/IC/05-1 / Quality Component 2 Land Market Individual Consultant IDA / 54560 Post Open 15,000.00 3,051.45 Terminated 2017-03-09 2017-03-28 2017-04-03 2017-04-08 2017-05-18 2017-04-08 2017-05-30 2018-07-02 Control Surveyor Development Selection LMDC/CS/IC/05-2 / Quality Component 2 Land Market Individual Consultant IDA / 54560 Post Open 15,000.00 11,452.28 Signed 2017-03-09 2017-03-28 2017-04-03 2017-06-20 2017-04-08 2017-06-20 2017-04-08 2017-06-26 2018-07-02 Control Surveyor Development Selection LMDC/CS/IC/05-3 / Quality Component 2 Land Market Individual Consultant IDA / 54560 Post Open 15,000.00 11,452.28 Signed 2017-03-09 2017-03-28 2017-04-03 2017-06-20 2017-04-08 2017-06-20 2017-04-08 2017-06-26 2018-07-02 Control Surveyor Development Selection LMDC/CS/IC/05-4 / Quality Component 2 Land Market Individual Consultant IDA / 54560 Post Open 15,000.00 11,452.28 Signed 2017-03-09 2017-03-28 2017-04-03 2017-06-20 2017-04-08 2017-06-20 2017-04-08 2017-07-03 2018-07-02 Control Surveyor Development Selection LMDC/CS/IC/03-1 / Legal Component 2 Land Market Individual Consultant IDA / 54560 Post Open 19,500.00 14,918.92 Completed 2017-03-01 2017-03-23 2017-03-26 2017-05-18 2017-03-31 2017-05-19 2017-03-31 2017-05-22 2018-06-24 2017-11-27 advisor Development Selection LMDC/CS/IC/03-2 / Legal Component 2 Land Market Individual Consultant IDA / 54560 Post Open 19,500.00 14,918.92 Signed 2017-03-01 2017-03-23 2017-03-26 2017-05-18 2017-03-31 2017-05-19 2017-03-31 2017-05-22 2018-06-24 advisor Development Selection LMDC/CS/IC/03-3 / Legal Component 2 Land Market Individual Consultant IDA / 54560 Post Open 19,500.00 14,918.92 Signed 2017-03-01 2017-03-23 2017-03-26 2017-05-18 2017-03-31 2017-05-19 2017-03-31 2017-05-22 2018-06-24 advisor Development Selection IDIC/CS/IC/32 / Local Consultant Component 1 Irrigation and Individual Consultant for Preparation of Georgian IDA / 54560 Post Open 7,500.00 7,069.67 Signed 2017-04-17 2017-03-30 2017-05-16 2017-05-01 2017-05-23 2017-05-01 2017-05-24 2017-05-01 2017-08-22 Drainage Improvement Selection National Drainage Strategy Component 2 Land Market Individual Consultant LMDC/CS/IC/13-2 / Developer IDA / 54560 Post Open 49,500.00 0.00 Canceled 2017-03-27 2017-04-21 2017-04-26 2017-04-26 2018-07-20 Development Selection Component 2 Land Market Individual Consultant LMDC/CS/IC/13-3 / Developer IDA / 54560 Post Open 49,500.00 0.00 Canceled 2017-03-27 2017-04-21 2017-04-26 2017-04-26 2018-07-20 Development Selection LMDC/CS/IC/09 / Database Component 2 Land Market Individual Consultant IDA / 54560 Post Open 37,500.00 0.00 Canceled 2017-03-20 2017-04-14 2017-04-19 2017-04-19 2018-07-13 Architecture Development Selection LMDC/CS/IC/08 / System Component 2 Land Market Individual Consultant IDA / 54560 Post Open 45,000.00 0.00 Canceled 2017-03-20 2017-04-14 2017-04-19 2017-04-19 2018-07-13 Architecture Development Selection LMDC/CS/IC/01-1 / Chief legal Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 27,000.00 0.00 2017-08-15 2017-08-01 2017-09-22 2017-09-29 2017-09-29 2018-12-23 adviser Development Selection Implementation LMDC/CS/IC/01 / Chief legal Component 2 Land Market Individual Consultant IDA / 54560 Post Open 27,000.00 0.00 Canceled 2017-03-01 2017-03-23 2017-03-26 2017-03-31 2017-03-31 2018-06-24 advisor Development Selection LMDC/CS/IC/02-1 / Senior legal Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 22,500.00 0.00 2017-08-15 2017-08-01 2017-09-15 2017-09-29 2017-09-29 2018-12-23 adviser Development Selection Implementation LMDC/CS/IC/02 / Senior legal Component 2 Land Market Individual Consultant IDA / 54560 Post Open 22,500.00 0.00 Canceled 2017-03-01 2017-03-23 2017-03-26 2017-03-31 2017-03-31 2018-06-24 advisor Development Selection LMDC/CS/IC/06-4-1 / Regional Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 16,500.00 0.00 2017-08-15 2017-08-01 2017-09-15 2017-09-29 2017-09-29 2018-12-23 facilitator Development Selection Implementation LMDC/CS/IC/06-4 / Regional Component 2 Land Market Individual Consultant IDA / 54560 Post Open 16,500.00 0.00 Canceled 2017-03-16 2017-03-23 2017-04-10 2017-04-15 2017-04-15 2018-03-11 facilitator Development Selection LMDC/CS/IC/06-5-1 / Regional Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 16,500.00 0.00 2017-08-15 2017-08-01 2017-09-15 2017-09-29 2017-09-29 2018-12-23 facilitator Development Selection Implementation LMDC/CS/IC/06-5 / Regional Component 2 Land Market Individual Consultant IDA / 54560 Post Open 16,500.00 0.00 Canceled 2017-03-16 2017-03-23 2017-04-10 2017-04-15 2017-04-15 2018-03-11 facilitator Development Selection LMDC/CS/IC/05-5 / Quality Component 2 Land Market Individual Consultant IDA / 54560 Post Open 15,000.00 11,165.05 Signed 2017-08-15 2017-08-01 2017-09-15 2017-09-07 2017-09-29 2017-09-08 2017-09-29 2017-09-11 2018-12-23 Control Surveyor Development Selection LMDC/CS/IC/04 / Senoir Quality Component 2 Land Market Individual Consultant IDA / 54560 Post Open 22,500.00 0.00 Canceled 2017-03-09 2017-03-28 2017-04-03 2017-04-08 2017-04-08 2018-07-02 Control Surveyor Development Selection LMDC/CS/SSS/02 / Senior Component 2 Land Market IDA / 54560 Post Direct Selection Direct 22,500.00 16,747.57 Signed 2017-09-01 2017-08-31 2017-09-05 2017-09-01 2017-09-12 2017-09-01 2018-12-06 Quality Control Surveyor Development LMDC/CS/IC/24 / Lawyer (in- Component 2 Land Market Individual Consultant IDA / 54560 Post Open 4,000.00 3,090.29 Signed 2017-09-11 2017-10-06 2017-10-08 2017-10-09 2017-10-27 2018-02-06 house team member) Development Selection LMDC/CS/IC/25 / Lawyer (in- Component 2 Land Market Individual Consultant IDA / 54560 Post Open 4,000.00 3,090.29 Signed 2017-09-11 2017-10-06 2017-10-08 2017-10-09 2017-10-27 2018-02-06 house team member) Development Selection LMDC/CS/IC/28 / GIS operator Component 2 Land Market Individual Consultant IDA / 54560 Post Open 6,000.00 3,090.29 Signed 2017-09-11 2017-10-06 2017-10-08 2017-10-09 2017-10-16 2018-02-06 (in-house team member) Development Selection LMDC/CS/IC/29 / Public Component 2 Land Market Individual Consultant Relation (PR) Manager for Land IDA / 54560 Post Open 16,500.00 1,499.82 Terminated 2017-09-20 2017-10-13 2017-10-15 2017-10-17 2017-10-18 2017-12-06 2018-10-18 Development Selection Market Development Component LMDC/CS/IC/30 / Assistant Component 3 Project Individual Consultant Procurement Consultant for Land IDA / 54560 Post Open 19,560.00 1,515.15 Terminated 2017-09-11 2017-09-06 2017-10-06 2017-09-18 2017-10-08 2017-09-18 2017-10-09 2017-09-19 2018-10-09 2017-10-26 Management Selection Market Development Component IDIC/CS/IC/33 / Regional Advisor to the Georgian Amelioration Component 1 Irrigation and Individual Consultant (GA) for Water Users IDA / 54560 Post Open 79,240.00 71,213.00 Signed 2017-09-25 2017-09-13 2017-10-24 2017-11-08 2017-11-03 2017-11-10 2017-11-08 2017-11-10 2019-02-01 Drainage Improvement Selection Organisations (WUO) strategy development Page 5 IDIC/CS/IC/34 / Consultant for supervision of implementation of civil works under Batch 1 for Zeda Ru, Kvemo Samgori and Component 1 Irrigation and Individual Consultant IDA / 54560 Post Open 12,000.00 13,136.62 Signed 2017-09-25 2017-09-28 2017-10-13 2017-10-05 2017-10-20 2017-10-05 2017-10-21 2017-10-06 2018-07-08 Tbisi-Kumisi Irrigation Schemes Drainage Improvement Selection in compliance with the ESMF and EMPs and consultations for Drainage Strategy LMDC/CS/IC/17 / Quality Component 2 Land Market Individual Consultant Control Surveyor (in-house team IDA / 54560 Post Open 4,000.00 6,904.11 Signed 2017-09-18 2017-09-21 2017-10-13 2017-10-06 2017-10-15 2017-10-06 2017-10-16 2017-10-06 2018-02-13 Development Selection member) LMDC/CS/IC/19 / Quality Component 2 Land Market Individual Consultant Control Surveyor (in-house team IDA / 54560 Post Open 4,000.00 6,909.85 Signed 2017-09-18 2017-09-21 2017-10-13 2017-10-06 2017-10-15 2017-10-06 2017-10-16 2017-10-06 2018-02-13 Development Selection member) LMDC/CS/IC/20 / Quality Component 2 Land Market Individual Consultant Pending Control Surveyor (in-house team IDA / 54560 Post Open 4,000.00 0.00 2017-09-18 2017-10-13 2017-10-15 2017-10-16 2018-02-13 Development Selection Implementation member) LMDC/CS/IC/22 / Quality Component 2 Land Market Individual Consultant Control Surveyor (in-house team IDA / 54560 Post Open 4,000.00 3,553.84 Signed 2017-09-18 2017-10-13 2017-10-15 2017-10-16 2017-11-27 2018-02-13 Development Selection member) LMDC/CS/IC/23 / Quality Component 2 Land Market Individual Consultant Pending Control Surveyor (in-house team IDA / 54560 Post Open 4,000.00 0.00 2017-09-18 2017-10-13 2017-10-15 2017-10-16 2018-02-13 Development Selection Implementation member) LMDC/CS/IC/18 / Quality Component 2 Land Market Individual Consultant Control Surveyor (in-house team IDA / 54560 Post Open 4,000.00 6,909.85 Signed 2017-09-18 2017-09-21 2017-10-13 2017-10-06 2017-10-15 2017-10-06 2017-10-16 2017-10-06 2018-02-13 Development Selection member) LMDC/CS/IC/21 / Quality Component 2 Land Market Individual Consultant Pending Control Surveyor (in-house team IDA / 54560 Post Open 4,000.00 0.00 2017-09-18 2017-10-13 2017-10-15 2017-10-16 2018-02-13 Development Selection Implementation member) LMDC/CS/IC/26 / Regional Component 2 Land Market Individual Consultant facilitator (in-house team IDA / 54560 Post Open 6,000.00 4,040.40 Signed 2017-09-18 2017-09-20 2017-10-13 2017-10-20 2017-10-15 2017-10-25 2017-10-16 2017-10-27 2018-02-13 Development Selection member) LMDC/CS/IC/16 / Quality Component 2 Land Market Individual Consultant Control Surveyor (in-house team IDA / 54560 Post Open 4,000.00 6,904.11 Signed 2017-09-18 2017-09-21 2017-10-13 2017-10-06 2017-10-15 2017-10-06 2017-10-16 2017-10-06 2018-02-13 Development Selection member) LMDC/CS/IC/27 / Regional Component 2 Land Market Individual Consultant Pending facilitator (in-house team IDA / 54560 Post Open 6,000.00 0.00 2017-09-18 2017-10-13 2017-10-15 2017-10-16 2018-02-13 Development Selection Implementation member) LMDC/CS/IC/14-1 / National Technical Assistance on Data Component 2 Land Market Individual Consultant IDA / 54560 Post Open 18,750.00 18,750.00 Signed 2017-10-16 2017-12-01 2017-11-10 2017-11-27 2017-11-13 2017-11-30 2017-11-16 2017-12-11 2018-11-16 Management (Monitoring and Development Selection Evaluation) LMDC/CS/IC/14 / National Component 2 Land Market Individual Consultant Technical Assistance on data IDA / 54560 Post Open 18,750.00 0.00 Canceled 2017-04-10 2017-06-29 2017-05-05 2017-05-10 2017-05-10 2018-05-10 Development Selection management LMDC/CS/IC/31 / GIS operator Component 2 Land Market Individual Consultant Pending IDA / 54560 Post Open 2,610.00 0.00 2017-11-06 2017-12-01 2017-12-03 2017-12-04 2018-04-03 (in-house team member) Development Selection Implementation LMDC/CS/IC/32 / GIS operator Component 2 Land Market Individual Consultant IDA / 54560 Post Open 2,610.00 3,086.42 Signed 2017-11-06 2017-12-01 2017-12-03 2017-12-04 2017-11-08 2018-04-03 (in-house team member) Development Selection LMDC/CS/IC/33 / GIS operator Component 2 Land Market Individual Consultant Pending IDA / 54560 Post Open 2,610.00 0.00 2017-11-06 2017-12-01 2017-12-03 2017-12-04 2018-04-03 (in-house team member) Development Selection Implementation LMDC/CS/IC/34 / Part Time Component 2 Land Market Individual Consultant IDA / 54560 Post Open 6,250.00 8,691.45 Signed 2017-11-13 2017-12-01 2017-12-08 2017-12-09 2017-12-19 2018-12-09 Video Operator Development Selection LMDC/CS/IC/35 / Procurement Component 3 Project Individual Consultant Consultant for Land Market IDA / 54560 Post Open 19,560.00 17,892.64 Signed 2017-11-27 2017-11-20 2017-12-09 2017-11-30 2017-12-16 2017-11-30 2017-12-17 2017-12-01 2018-12-17 Management Selection Development Component Component 2 Land Market Individual Consultant Under LMDC/CS/IC/37 / Web developer IDA / 54560 Post Open 18,000.00 0.00 2018-01-15 2018-01-19 2018-02-09 2018-02-14 2018-02-15 2019-02-15 Development Selection Implementation LMDC/CS/IC/39 / Regional Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 12,000.00 0.00 2018-01-15 2018-02-02 2018-02-09 2018-02-14 2018-02-15 2019-02-15 Facilitator Development Selection Implementation LMDC/CS/IC/40 / Regional Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 12,000.00 0.00 2018-01-15 2018-02-02 2018-02-09 2018-02-14 2018-02-15 2019-02-15 Facilitator Development Selection Implementation LMDC/CS/IC/41 / Regional Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 12,000.00 0.00 2018-01-15 2018-02-02 2018-02-09 2018-02-14 2018-02-15 2019-02-15 Facilitator Development Selection Implementation LMDC/CS/IC/42 / Regional Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 12,000.00 0.00 2018-01-15 2018-02-02 2018-02-09 2018-02-14 2018-02-15 2019-02-15 Facilitator Development Selection Implementation LMDC/CS/IC/43 / Regional Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 12,000.00 0.00 2018-01-15 2018-02-02 2018-02-09 2018-02-14 2018-02-15 2019-02-15 Facilitator Development Selection Implementation LMDC/CS/IC/44 / Lawyer for in- Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 14,352.00 0.00 2018-01-15 2018-01-15 2018-02-09 2018-02-14 2018-02-15 2019-02-15 house team Development Selection Implementation IDIC/CS/IC/35 / Team Leader for Component 1 Irrigation and Individual Consultant Pending Water Users Development IDA / 54560 Post Open 10,435.00 0.00 2018-01-22 2018-02-18 2018-02-23 2018-02-26 2018-08-25 Drainage Improvement Selection Implementation Support Unit IDIC/CS/IC/36 / Assistant Component 3 Project Individual Consultant IDA / 54560 Post Open 32,283.00 29,117.65 Signed 2018-01-08 2018-01-05 2018-01-23 2018-01-26 2018-01-27 2018-01-15 2019-07-21 Procurement Consultant Management Selection Page 6 IDIC/CS/IC/37 / Senior Specialist for irrigation Component 1 Irrigation and Individual Consultant Pending engineering, operation and IDA / 54560 Post Open 9,130.00 0.00 2018-01-22 2018-02-18 2018-02-23 2018-02-26 2018-08-25 Drainage Improvement Selection Implementation maintenance of Water Users Development Support Unit IDIC/CS/IC/26 / Preparation of Component 1 Irrigation and Individual Consultant Environment Management Plan IDA / 54560 Post Open 20,000.00 0.00 Canceled 2017-11-15 2017-12-18 2018-01-01 2018-01-06 2018-03-07 Drainage Improvement Selection for Batch 2 LMDC/CS/IC/36 / Web Component 2 Land Market Individual Consultant Under IDA / 54560 Post Open 18,000.00 0.00 2018-01-15 2018-01-19 2018-02-09 2018-02-14 2018-02-15 2019-02-15 Developer Development Selection Implementation LMDC/CS/SSS/03 / Component 2 Land Market IDA / 54560 Post Direct Selection Direct 18,000.00 6,060.61 Signed 2018-01-15 2018-01-05 2018-01-21 2018-01-22 2018-01-25 2018-01-22 2019-01-25 Interpreter/translator Development IDIC/CS/IC/31 / Complete legislative framework analysis Component 1 Irrigation and Individual Consultant IDA / 54560 Post Open 15,600.00 0.00 Canceled 2017-04-03 2017-05-04 2017-05-02 2017-05-12 2017-05-15 2017-07-14 regarding agricultural land in Drainage Improvement Selection Georgia Component 2 Land Market Individual Consultant Under LMDC/CS/IC/38 / Web Designer IDA / 54560 Post Open 18,000.00 0.00 2018-01-15 2018-01-10 2018-02-09 2018-02-14 2018-02-15 2018-03-17 Development Selection Implementation Page 7