Large Scale Irrigation Modernization Project Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: 5 may 2015]: Revision 2 of Updated Procurement Plan, March 28, 2017 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. Works Above US$ 15 million All 2. Goods Above US$ 4 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2 million 2. Single Source All 3. Individual Above US$ 400,000 July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule July 9, 2010 PROCUREMENT Morocco : MA-Large Scale Irrigation Modernization Project PLAN General Information Country: Morocco Bank’s Approval Date of the Original Procurement Plan: 2017-03-31 2019-10-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150930 GPN Date: Project Name: MA-Large Scale Irrigation Modernization Project Loan / Credit No: IBRD / 85140 Executing Agency(ies): Office Regionale de Mise en Valeur Agricole de TADLA (ORMVA TADLA WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REF-14/2016/TA-DA / Travaux du laboratoire pour Component 1: Improving Single Stage - One le contrôle de qualité pour IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 440,000.00 215,224.65 Signé 2016-03-16 2016-03-28 2016-04-21 2016-04-21 2016-04-21 2016-04-21 Envelope secteur M et G et travaux Infrastructure bassin REF-28/2016/TA-DA / Travaux d'exécution des Component 1: Improving conduites du réseau de Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 890,000.00 10,333,713.35 Signé 2016-06-28 2016-07-12 2016-09-06 2016-09-06 2016-09-06 2016-09-06 distribution y compris Envelope Infrastructure ouvrage annexes des secteurs M10-M18 ( L1 ) REF-29/2016/TA-DA / Component 1: Improving Travaux d'exécution de la Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 15,780,000.00 7,025,507.78 Signé 2016-06-28 2016-07-12 2016-09-06 2016-09-06 2016-09-06 2016-09-06 conduite d'adducteur A5 des Envelope Infrastructure secteurs M10-M18 ( L2 ) REF-10/2017/TA-DA / Travaux de réalisation des prises bornes,prises Component 1: Improving Single Stage - One propriétés et les conduite de IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 5,890,000.00 4,909,254.84 Signé 2017-01-03 2017-01-17 2017-02-28 2017-02-28 2017-02-28 2017-02-28 Envelope raccordement y compris la Infrastructure télégestion des secteurs M10- M13 (Lot 1) REF-15/2017/TA-DA / Component 1: Improving Travaux d'exécution des Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 8,000,000.00 7,211,688.62 Signé 2017-02-07 2017-02-17 2017-03-14 2017-03-14 2017-03-14 2017-03-14 conduites d'adducteur A6 des Envelope Infrastructure secteurs G13-G18 REF-11/2017/TA-DA / Travaux de réalisation des prises bornes,prises Component 1: Improving Single Stage - One propriétés et les conduite de IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 4,780,000.00 4,047,710.58 Signé 2017-01-03 2017-01-17 2017-02-28 2017-02-28 2017-02-28 2017-02-28 Envelope raccordement y compris la Infrastructure télégestion des secteurs M14-M18 (Lot 2) REF-40/2015/TA-DA / Travaux d'exécution des conduites des adducteurs A5, Component 1: Improving Single Stage - One A6-1 et A6-2 de la partie IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 8,864,562.00 8,345,909.83 Signé 2015-11-10 2015-11-23 2015-12-17 2015-12-17 2015-12-17 2015-12-17 Envelope amont sur 5.3 km y compris Infrastructure les ouvrages de prises principaux REF-30/2017/TA-DA / Fourniture et installation du Component 1: Improving matériel d'équipement de la Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 900,000.00 946,912.70 Signé 2017-03-24 2017-03-29 2017-05-10 2017-06-09 2017-07-14 2018-01-10 station de filtration du Envelope Infrastructure secteur M10/M18 y compris génie civil. Page 1 REF-32/2017/TA-DA / Component 1: Improving Travaux de construction d'un Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 7,440,000.00 5,894,336.29 Signé 2017-05-25 2017-05-30 2017-07-11 2017-08-10 2017-09-14 2018-03-13 bassin de régulation Envelope Infrastructure hydraulique ( 1ère Tranche ) REF-40/2017/TA-DA / Travaux de génie civil, de fourniture,transport et pose de conduites et Component 1: Improving Single Stage - One équipements nécessaires, IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 5,200,000.00 5,121,569.31 Signé 2018-01-22 2018-01-27 2018-03-10 2018-04-09 2018-05-14 2018-11-10 Envelope pour la réalisation des Infrastructure réseaux de distribution d'eau d'irrigation des secteurs G15 Bis- G18 REF-41/2017/TA-DA / Travaux de génie civil, de fourniture,transport et pose de conduites et Component 1: Improving Single Stage - One équipements nécessaires, IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 7,000,000.00 6,584,511.57 Signé 2018-01-22 2018-01-27 2018-03-10 2018-04-09 2018-05-14 2018-11-10 Envelope pour la réalisation des Infrastructure réseaux de distribution d'eau d'irrigation des secteurs G13- G15 REF-16/2018/TA-DA / Component 1: Improving Single Stage - One Fourniture et installation IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 1,500,000.00 1,326,558.27 Signé 2018-11-06 2018-11-11 2018-12-23 2019-01-22 2019-02-26 2019-08-25 Envelope des stations de filtration Infrastructure REF-03/2019/TA-DA / Travaux d'execution des Component 1: Improving Single Stage - One prises bornes et prises IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 14,000,000.00 0.00 Annulé 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-12-18 Envelope propriétés secteur G en 3 Infrastructure lots REF-33/2018/TA-DGRID / Fourniture, installation et mise en service de matériel pour l'avertissement de Component 1: Improving l'irrigation dans les secteurs Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 80,000.00 90,629.95 Signé 2019-03-11 2019-03-16 2019-04-27 2019-05-27 2019-07-01 2019-12-28 M10/M18 et G13/G18? Envelope Infrastructure concernés par le Projet de Modernisation de la Grande Irrigation dans le périmètre du Tadla (PMGI) Component 3: Supporting REF-02/2019/TA-SMG / the Project Implementing Equipement des locaux Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2019-07-29 2019-09-23 2020-03-21 administratifs dans la zone Envelope Irrigation Network and to de reconversion Implement the Project REF-04/2019/TA-DA / Travaux de Génie Civil et Component 1: Improving d'équipement des prises Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 5,000,000.00 3,734,924.87 Signé 2019-06-21 2019-06-26 2019-08-07 2019-09-06 2019-10-11 2020-04-08 bornes et prises propriétés Envelope Infrastructure du réseau d'irrigation des secteurs G13/G14 REF-05/2019/TA-DA / Travaux de Génie Civil et Component 1: Improving d'équipement des prises Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 4,000,000.00 3,254,481.57 Signé 2019-06-21 2019-06-26 2019-08-07 2019-09-06 2019-10-11 2020-04-08 Bornes et prises propriétés Envelope Infrastructure du réseau G15/G16/G15bis/G16bis Page 2 REF-06/2019/TA-DA / Travaux de Génie Civil et d'équipement des prises Component 1: Improving Single Stage - One bornes et prises propriétés IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 4,000,000.00 3,238,720.36 Signé 2019-06-21 2019-06-26 2019-08-07 2019-09-06 2019-10-11 2020-04-08 Envelope du réseau d'irrigation des Infrastructure secteurs G17/G18/G17bis/G18bis REF-02/2019/TA-DA / Component 1: Improving Aménagement des locaux Single Stage - One En attente IBRD / 85140 Irrigation Network A posteriori Appel d'offres Limited 160,000.00 0.00 2019-08-24 2019-08-29 2019-10-10 2019-11-09 2019-12-14 2020-06-11 administratifs dans la zone Envelope d'exécution Infrastructure de reconversion GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REF-37/2016/TA-DGRID / Component 3: Supporting Fournitures de materiel pour the Project Implementing le suivi des paramètres de Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 69,000.00 76,569.48 Signé 2017-01-22 2017-01-27 2017-03-10 2017-04-09 2017-05-14 2017-11-10 la nappe au niveau des Envelope Irrigation Network and to secteurs M10/M18 et Implement the Project G13/G18 Component 3: Supporting REF-58/2017/TA-SMG / the Project Implementing Single Stage - One Aménagement et équipement IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 74,000.00 69,778.78 Signé 2017-12-20 2018-02-14 2018-08-13 Envelope des locaux administratifs Irrigation Network and to Implement the Project Component 3: Supporting the Project Implementing REF-59/2017/TA-SMG / Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 31,000.00 28,983.93 Signé 2017-12-11 2018-02-05 2018-08-04 Mobilier de bureau Envelope Irrigation Network and to Implement the Project Component 3: Supporting the Project Implementing REF-08/2016/TA-SMG / Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 40,000.00 36,961.73 Signé 2016-04-11 2016-06-06 2016-12-03 Acquisition micro ordinateurs Envelope Irrigation Network and to Implement the Project Component 3: Supporting the Project Implementing REF-17/2016/TA-SMG / Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 1,700.00 1,758.89 Signé 2016-05-21 2016-07-16 2017-01-12 Acquisition tablette tactile Envelope Irrigation Network and to Implement the Project Component 3: Supporting REF-66/2017/TA-SMG / the Project Implementing Aménagement et équipement Single Stage - One IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 20,000.00 18,593.94 Signé 2018-01-12 2018-03-09 2018-09-05 des locaux administratifs Envelope Irrigation Network and to dans la zone de reconversion Implement the Project Component 3: Supporting REF-12/2017/TA-SMG / the Project Implementing Single Stage - One Achat de matériel IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 30,000.00 26,148.71 Signé 2017-05-15 2017-07-10 2018-01-06 Envelope informatique Irrigation Network and to Implement the Project Component 3: Supporting REF-01/2019/TA-SMG / the Project Implementing Fournitures des locaux Single Stage - One En attente IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 53,000.00 0.00 2019-11-06 2020-01-01 2020-06-29 administratifs dans la zone Envelope d'exécution Irrigation Network and to de reconversion Implement the Project Page 3 Component 3: Supporting the Project Implementing REF-03/2019/TA-SMG / Single Stage - One En attente IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 40,000.00 0.00 2019-10-18 2019-12-13 2020-06-10 Voyage d'études à l'étranger Envelope d'exécution Irrigation Network and to Implement the Project NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REF-29/2017/TA-DGRID / Component 3: Supporting Mise à niveau de la station the Project Implementing Single Stage - One des éxpérimentations hydro IBRD / 85140 Entities to Manage the A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2017-02-19 2017-04-16 2017-10-13 Envelope agricoles de Oulad Gnaou ( Irrigation Network and to Expertise + Etude) Implement the Project REF-21/2017/DGRID / Component 3: Supporting Réalisation de la situation the Project Implementing Single Stage - One de référence des paramètres IBRD / 85140 Entities to Manage the A posteriori Appel d'offres Open - National 50,000.00 35,966.57 Signé 2017-05-08 2017-05-11 2017-06-20 2017-06-30 2017-08-09 2018-02-05 Envelope environnenomentaux et mise Irrigation Network and to en place d'un PGES Implement the Project REF-04/2019/TA-DGRID / Assistance technique et Component 1: Improving accompagnement pour Single Stage - One IBRD / 85140 Irrigation Network A posteriori Appel d'offres Open - National 20,000.00 0.00 Annulé 2019-10-01 2019-10-06 2019-11-17 2019-12-17 2020-01-21 2020-07-19 l'exploitation et la Envelope Infrastructure maintenance des équipements hydro-agricoles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-23 / Assistance Component 1: Improving Sélection fondée technique pour le suivi et Open - IBRD / 85140 Irrigation Network A priori sur la qualité et 2,000,000.00 1,407,946.04 Signé 2015-04-23 2015-05-24 2015-07-07 2016-03-10 2016-04-07 2016-05-04 2016-08-08 2020-08-21 contrôle des travaux des International Infrastructure le coût secteurs M10-M18 MOF-REF-24 / Assistance Component 1: Improving Sélection fondée technique pour le suivi et Open - IBRD / 85140 Irrigation Network A priori sur la qualité et 2,670,000.00 1,095,553.21 Signé 2016-07-26 2016-08-16 2016-09-29 2016-10-27 2016-11-26 2016-12-31 2017-02-04 2018-02-04 contrôle des travaux des International Infrastructure le coût secteurs G13-G18 REF-01/2017/DDA / Appuis Component 2: Supporting Sélection fondée aux agriculteurs pour la Open - IBRD / 85140 Farmers’ Access to Improved A priori sur la qualité et 2,780,000.00 2,062,027.32 Signé 2016-08-27 2016-09-17 2016-10-31 2016-11-28 2016-12-28 2017-02-01 2017-03-08 2018-03-08 valorisation de l'eau International Irrigation Technologies le coût d'irrigation INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 C6/DRH / Il s'agit d'une formation des cadres et techniciens portant sur "études géotechniques et Component 3: Supporting dimensionnement des the Project Implementing ouvrages hydrauliques" afin IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 3,600.00 0.00 Annulé 2018-11-11 2018-11-26 2018-12-06 2018-12-21 2019-03-21 de permettre aux Irrigation Network and to participants de disposer d'un Implement the Project savoir faire pour la conception et le dimensionnement des ouvrages hydr Component 3: Supporting REF-03/2017/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 8,000.00 3,639.10 Signé 2017-10-30 2017-11-04 2017-11-25 2017-12-30 2018-06-28 formation Irrigation Network and to Implement the Project Component 3: Supporting REF-07/2017/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 4,000.00 3,213.60 Signé 2017-12-05 2017-12-10 2017-12-31 2018-02-04 2018-08-03 formation Irrigation Network and to Implement the Project Component 3: Supporting REF-09/2017/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 4,000.00 3,084.02 Signé 2018-03-19 2018-03-24 2018-04-14 2018-05-19 2018-11-15 formation Irrigation Network and to Implement the Project Component 3: Supporting REF-10/2017/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 6,000.00 4,975.90 Signé 2018-04-16 2018-04-21 2018-05-12 2018-06-16 2018-12-13 formation Irrigation Network and to Implement the Project Component 3: Supporting REF-11/2017/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 2,300.00 2,126.16 Signé 2018-04-04 2018-04-09 2018-04-30 2018-06-04 2018-12-01 formation Irrigation Network and to Implement the Project Component 3: Supporting REF-03/2018/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 3,000.00 2,692.73 Signé 2018-10-29 2018-11-03 2018-11-24 2018-12-29 2019-06-27 formation Irrigation Network and to Implement the Project Component 3: Supporting REF-06/2017/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 6,000.00 5,398.95 Signé 2017-12-18 2017-12-23 2018-01-13 2018-02-17 2018-08-16 formation Irrigation Network and to Implement the Project Component 3: Supporting REF-04/2017/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 5,000.00 4,256.87 Signé 2017-12-26 2017-12-31 2018-01-21 2018-02-25 2018-08-24 formation Irrigation Network and to Implement the Project Component 3: Supporting REF-02/2018/TA-DRH / the Project Implementing Animation module de IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 6,000.00 5,658.52 Signé 2018-10-30 2018-11-04 2018-11-25 2018-12-30 2019-06-28 formation Irrigation Network and to Implement the Project Page 5 MA-ORMVA TADLA-102215- CS-INDV / Valorisation des produits agricoles (olivier et Component 3: Supporting niora). L'objectif est de the Project Implementing permettre aux participants IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 4,200.00 4,353.91 Signé 2018-11-11 2018-11-16 2018-12-01 2018-12-21 2019-03-21 d'accompagner les Irrigation Network and to agriculteurs en matière de Implement the Project valorisation des produits de ces filières. MA-ORMVA TADLA-102218- CS-INDV / La mise en Component 3: Supporting œuvre d'un observatoire the Project Implementing technico-économique pour le IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 4,000.00 4,146.58 Signé 2018-11-11 2018-11-26 2018-12-06 2018-12-25 2019-03-25 suivi-évaluation des Irrigation Network and to indicateurs d'impact du Implement the Project projet de modernisation de l'irrigation. M-29/2017/TA/DGRID / Mise Component 3: Supporting à niveau de la station des the Project Implementing expérimentations Hydro- IBRD / 85140 Entities to Manage the A posteriori Individuel Limited 40,000.00 38,872.45 Signé 2019-02-21 2019-02-26 2019-03-19 2019-04-23 2019-10-20 agricoles de Oulad Gnaou Irrigation Network and to (expertise+étude) Implement the Project Page 6