PROCUREMENT PLAN (Textual Part) Project information: BURUNDI LANDSCAPE RESTORATION AND RESILIENCE PROJECT P160613 Project Implementation agency: MINISTRY OF AGRICULTURE AND LIVESTOCK Date of the Procurement Plan: February 15, 2019 Period covered by this Procurement Plan: February 2019 - October 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the country procurement handbook, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. - Rights for the Bank to review procurement documentation and activities. - An effective complaints mechanism. - Maintenance of records of the Procurement Process When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Burundi : Burundi Landscape Restoration and Resilience Project PLAN General Information Country: Burundi Bank’s Approval Date of the Original Procurement Plan: 2019-02-20 2021-06-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160613 GPN Date: Project Name: Burundi Landscape Restoration and Resilience Project Loan / Credit No: IDA / D2760 Burundi Landscape Restoration and Resilience Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BI-BLRRP-162193-CW-RFB / Travaux de construction et de réhabilitation des centres Improved Management of Single Stage - One En cours 2020-12- IDA / D2760 A posteriori Appel d'offres Open - National 210,000.00 0.00 2020-03-10 2021-02-09 2020-03-15 2021-02-17 2020-04-26 2021-03-23 2020-05-26 2021-05-10 2020-06-30 visiteurs et des postes de Protected Areas and Reserves Envelope d'exécution 27 surveillances pour le compte de l'OBPE BI-BLRRP-173980-CW-RFQ / Travaux de rénovation, Institutional Development d'équipement des bureaux and Capacity Building for Single Stage - One 2021-01- des SFC d'Isare et Buhinyuza IDA / D2760 A posteriori Demande de prix Limited 20,383.00 29,059.19 Signé 2020-05-27 2020-07-15 2020-07-22 2021-01-22 Landscape Restoration and Envelope 18 et d'éclairage et équipement Resilience du bureau communal de Buhinyuza BI-BLRRP-207814-CW-RFQ / Travaux de réhabilitation et Institutional Development équipement du Centre and Capacity Building for Single Stage - One En cours 2021-11- IDA / D2760 A posteriori Demande de prix Limited 70,000.00 0.00 2021-03-10 2021-03-16 2021-05-05 d'Information Landscape Restoration and Envelope d'exécution 01 Environnementale/SIG de Resilience l'OBPE BI-BLRRP-207843-CW-RFQ / Travaux de réhabilitation des Project Management, Single Stage - One 2020-04- bureaux de l'Unité Provinciale IDA / D2760 A posteriori Demande de prix Limited 9,700.00 9,695.64 Signé 2019-08-12 2019-08-07 2019-10-07 2019-09-20 Coordination, and Monitoring Envelope 04 de Coordination du Projet (UCPC) de Bujumbura GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-MINAGRIE-99975-GO-RFB / Achat groupes Sustainable Landscape Single Stage - One IDA / D2760 A posteriori Appel d'offres Open - National 154,500.00 94,784.80 Achevé 2019-02-10 2019-06-19 2019-02-15 2019-03-29 2019-06-26 2019-04-28 2019-11-22 2019-06-02 2019-11-06 2019-11-29 2020-02-17 d'equipements informatique Management Practices Envelope et bureautique Institutional Development Passation de BI-MINAGRIE-99974-GO-UN and Capacity Building for marchés auprès IDA / D2760 A posteriori Direct 475,000.00 317,993.98 Signé 2019-02-10 2019-03-13 2019-02-15 2019-03-22 2019-03-28 2019-09-18 / Achat de véhicules (10) Landscape Restoration and des agences de Resilience l'ONU BI-BLRRP-144859-GO-RFQ / Project Management, Single Stage - One Fourniture du mobilier de IDA / D2760 A posteriori Demande de prix Limited 30,000.00 24,660.08 Achevé 2019-11-13 2019-10-24 2020-01-08 2019-12-03 2020-07-06 2019-12-31 Coordination, and Monitoring Envelope bureau BI-BLRRP-147918-GO-RFQ / Acquisition des équipements Project Management, Single Stage - One En attente IDA / D2760 A posteriori Demande de prix Limited 2,250.00 0.00 2019-12-04 2020-01-29 2020-07-27 de collecte des données Coordination, and Monitoring Envelope d'exécution (Smartphones) BI-BLRRP- 99975-GO-UN/ Institutional Development ACHAT VÉHICULE / Achat d'un Passation de and Capacity Building for véhicule pick up Double IDA / D2760 A posteriori marché de gré à Direct 50,000.00 32,708.83 Achevé 2019-10-29 2020-01-02 2019-11-03 2020-03-28 2019-12-08 2019-11-22 2020-06-05 2020-06-08 Landscape Restoration and cabine pour le compte du SP/ gré Resilience CFN BI-BLRRP-152621-GO-RFB / Sustainable Landscape Single Stage - One Achat et distribution des IDA / D2760 A posteriori Appel d'offres Open - International 800,000.00 465,809.72 Résilié 2020-01-13 2020-01-27 2020-01-18 2020-01-30 2020-02-29 2020-03-19 2020-03-30 2020-08-26 2020-05-04 2020-06-29 2020-10-31 Management Practices Envelope vaches BI-BLRRP-150671-GO-RFQ / Project Management, Single Stage - One Acquisition des IDA / D2760 A posteriori Demande de prix Limited 12,000.00 12,270.64 Achevé 2019-12-22 2020-02-27 2020-02-16 2020-04-28 2020-08-14 2020-06-23 Coordination, and Monitoring Envelope consommables de bureau BI-BLRRP-147411-GO-RFB / Acquisition groupée des Institutional Development motos et des vélos pour les and Capacity Building for Single Stage - One IDA / D2760 A posteriori Appel d'offres Open - National 111,850.00 65,704.68 Achevé 2019-11-27 2020-02-13 2019-12-02 2020-02-13 2020-01-13 2020-03-30 2020-02-12 2020-06-11 2020-03-18 2020-06-25 2020-09-14 2020-08-04 services fonciers communaux, Landscape Restoration and Envelope l'OBPE et les chefs de collines Resilience de la zone d'action du projet Passation de BI-BLRRP-158870-GO-DIR / Improved Management of marchés auprès Achat de deux (02) véhicules IDA / D2760 A posteriori Direct 102,000.00 62,111.19 Achevé 2020-02-24 2020-03-27 2020-02-27 2020-04-05 2020-04-02 2020-04-02 2020-09-29 2020-09-04 Protected Areas and Reserves des agences de pick up Double cabine l'ONU BI-BLRRP-159824-GO-RFQ / Project Management, Single Stage - One Fourniture et installation des IDA / D2760 A posteriori Demande de prix Limited 4,500.00 3,378.03 Achevé 2020-02-22 2020-03-03 2020-04-18 2020-04-13 2020-10-15 2020-06-23 Coordination, and Monitoring Envelope équipements téléphoniques BI-BLRRP-160641-GO-RFQ / Acquisition des boucles Sustainable Landscape Single Stage - One IDA / D2760 A posteriori Demande de prix Limited 1,500.00 5,101.15 Signé 2020-02-29 2020-02-25 2020-04-25 2020-05-19 2020-10-22 d'oreilles pour vaches et des Management Practices Envelope applicateurs (pointeaux) Page 1 BI-BLRRP-162192-GO-RFB / Acquisition du matériel de surveillance des Parcs Improved Management of Single Stage - One IDA / D2760 A posteriori Appel d'offres Open - National 100,000.00 260,417.27 Achevé 2020-03-05 2020-03-14 2020-03-10 2020-03-14 2020-04-21 2020-05-06 2020-05-21 2020-05-19 2020-06-25 2020-08-06 2020-12-22 2021-02-11 Nationaux et des Réserves Protected Areas and Reserves Envelope Naturelles Forestières pour le compte de l'OBPE BI-BLRRP-162288-GO-RFB / Institutional Development Acquisition d'une and Capacity Building for Single Stage - One Vidéoconférence et des IDA / D2760 A posteriori Appel d'offres Open - National 60,000.00 53,869.92 Achevé 2020-03-06 2020-03-14 2020-03-11 2020-03-14 2020-04-22 2020-04-30 2020-05-22 2020-05-28 2020-06-26 2020-06-23 2020-12-23 2020-10-30 Landscape Restoration and Envelope équipements de Resilience communication du MINEAGRIE BI-BLRRP-154434-GO-RFQ / Acquisition d'appareils photo Project Management, Single Stage - One IDA / D2760 A posteriori Demande de prix Limited 4,500.00 0.00 Annulé 2020-01-23 2020-02-21 2020-03-19 2020-09-15 numériques professionnels et Coordination, and Monitoring Envelope de Vidéoprojecteurs BI-BLRRP-144875-GO-RFB / Achat groupé d'équipements Institutional Development informatiques pour les and Capacity Building for Single Stage - One bureaux des gouverneurs, des IDA / D2760 A posteriori Appel d'offres Open - National 30,000.00 0.00 Annulé 2019-11-08 2019-11-13 2019-12-25 2020-01-24 2020-02-28 2020-08-26 Landscape Restoration and Envelope administrateurs communaux , Resilience des SFC, des parcs nationaux, de l'OBPE et des BPEAE BI-BLRRP-162291-GO-DIR / Acquisition de pré-imprimés Passation de Sustainable Landscape pour le compte des services IDA / D2760 A posteriori marché de gré à Direct 5,807.00 5,574.74 Achevé 2020-03-31 2020-11-19 2020-04-05 2020-04-22 2020-05-10 2020-05-18 2020-11-06 2020-08-05 Management Practices Fonciers Communaux gré (SFC)d'Isare et Buhinyuza BI-BLRRP-167656-GO-RFQ / Project Management, Single Stage - One Acquisition d'un Serveur avec IDA / D2760 A posteriori Demande de prix Open - National 20,000.00 15,541.74 Signé 2020-04-15 2020-08-26 2020-06-10 2020-08-26 2020-12-07 Coordination, and Monitoring Envelope accessoires pour l'UCP BI-BLRRP-167904-GO-DIR / Project Management, Single Stage - One Acquisition des Routeurs pour IDA / D2760 A posteriori Demande de prix Limited 2,000.00 1,395.23 Achevé 2020-05-23 2020-05-19 2020-07-18 2020-06-17 2021-01-14 2020-06-22 Coordination, and Monitoring Envelope connections internet BI-BLRRP- 147697-GO-RFQ / Achat du matériel Sustainable Landscape Single Stage - One IDA / D2760 A posteriori Demande de prix Limited 13,703.00 0.00 Annulé 2019-12-04 2020-02-07 2020-01-29 2020-07-27 topographique pour les SEC Management Practices Envelope d'Isare et Buhinyuza BI-BLRRP-175511-GO-DIR / Acquisition des semences Passation de Sustainable Landscape pour la mise en place et le IDA / D2760 A posteriori marché de gré à Direct 4,184.73 4,105.97 Signé 2020-06-09 2020-06-15 2020-06-14 2020-06-18 2020-07-19 2020-06-26 2021-01-15 Management Practices développement des pépinières gré communautaires BI-BLRRP-175515-GO-RFQ / Acquisition des intrants et du Sustainable Landscape Single Stage - One matériel pour la mise en place IDA / D2760 A posteriori Demande de prix Open - National 63,836.50 82,886.39 Achevé 2020-06-14 2020-08-09 2020-08-10 2021-02-05 2020-09-11 Management Practices Envelope et le développement des pépinières communautaires BI-BLRRP-188899-GO-RFQ / Achat d'un véhicule pour le compte Bioversity Sustainable Landscape Single Stage - One IDA / D2760 A posteriori Demande de prix Open - National 57,000.00 55,791.72 Achevé 2020-09-05 2020-09-05 2020-10-31 2020-11-18 2021-04-29 2020-12-17 International dans le cadre Management Practices Envelope d'un contrat de prestation de services de consultant BI-BLRRP-188901-GO-RFQ / Institutional Development Achat de 159 vélos pour le and Capacity Building for Single Stage - One IDA / D2760 A posteriori Demande de prix Limited 23,850.00 0.00 Annulé 2020-09-14 2020-08-31 2020-09-19 2020-08-31 2020-10-03 2021-02-13 compte des chefs collinaires Landscape Restoration and Envelope de la zone d'action du projet Resilience BI-BLRRP-190789-GO-RFQ / Sustainable Landscape Single Stage - One En attente Fourniture d'un kit vétérinaire IDA / D2760 A posteriori Demande de prix Limited 68,400.00 0.00 2020-10-11 2020-12-06 2021-06-04 Management Practices Envelope d'exécution au PRRPB BI-BLRRP-188902-GO-RFQ / Institutional Development Achat de 159 vélos pour le and Capacity Building for Single Stage - One En cours IDA / D2760 A posteriori Demande de prix Limited 23,850.00 22,527.12 2020-09-19 2020-12-11 2020-11-14 2021-05-13 compte des Chefs collinaires Landscape Restoration and Envelope d'exécution de la zone d'action du Projet Resilience BI-BLRRP-207840-GO-RFB / Sustainable Landscape Single Stage - One En attente Achat et distribution des IDA / D2760 A posteriori Appel d'offres Open - National 480,000.00 0.00 2021-06-01 2021-06-06 2021-07-18 2021-08-17 2021-09-21 2022-03-20 Management Practices Envelope d'exécution vaches BI-BLRRP-207830-GO-RFQ / Sustainable Landscape Single Stage - One En attente acquisition du matériel pour IDA / D2760 A posteriori Demande de prix Limited 44,000.00 0.00 2021-07-03 2021-08-28 2022-02-24 Management Practices Envelope d'exécution le pépinières BI-BLRRP-207786-GO-RFB / Achat et distribution des Sustainable Landscape Single Stage - One En attente IDA / D2760 A posteriori Appel d'offres Open - National 114,300.00 0.00 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 semences pour Management Practices Envelope d'exécution l'intensification agricole BI-BLRRP-207831-GO-RFQ / Achat du mobilier (Armoires pour classement et chaises) Project Management, Single Stage - One En attente IDA / D2760 A posteriori Demande de prix Limited 16,000.00 0.00 2021-03-31 2021-05-26 2021-11-22 des extincteurs et des rideaux Coordination, and Monitoring Envelope d'exécution pour l'UCP et les UPCP Bujumbura et Muyinga BI-BLRRP-207827-GO-RFQ / Achat des consommables Project Management, Single Stage - One IDA / D2760 A posteriori Demande de prix Limited 18,000.00 17,016.33 Signé 2021-03-31 2021-03-01 2021-05-26 2021-04-29 2021-11-22 pour l'UCP et les UCPC de Coordination, and Monitoring Envelope Bujumbura et Muyinga BI-BLRRP-166822-GO-RFQ / Project Management, Single Stage - One Acquisition des appareils IDA / D2760 A posteriori Demande de prix Open - National 4,500.00 0.00 Annulé 2020-04-05 2020-05-31 2020-11-27 Coordination, and Monitoring Envelope photos et Vidéoprojecteur BI-BLRRP-207817-GO-DIR / Acqusition des pré-imprimés Passation de Sustainable Landscape En attente pour les Services Fonciers IDA / D2760 A posteriori marché de gré à Direct 5,800.00 0.00 2021-04-30 2021-05-05 2021-06-09 2021-12-06 Management Practices d'exécution Communaux d'Isare et gré Buhinyuza Page 2 BI-BLRRP-207839-GO-RFQ / Achat groupé des des Institutional Development équipements informatiques and Capacity Building for Single Stage - One En cours IDA / D2760 A posteriori Demande de prix Open - National 37,776.00 0.00 2021-02-24 2021-04-17 2021-04-21 2021-10-18 (ordinateurs, tablettes) des Landscape Restoration and Envelope d'exécution imprimantes et reprocopieur Resilience multifonctionnel BI-BLRRP-214162-GO-RFQ / Fourniture du matériel Sustainable Landscape Single Stage - One topographique pour les IDA / D2760 A posteriori Demande de prix Open - National 13,703.00 12,110.21 Signé 2021-02-17 2021-02-03 2021-04-14 2021-04-19 2021-10-11 Management Practices Envelope Services Fonciers des communes Isare et Buhinyuza BI-BLRRP-218665-GO-RFQ / Production des outils de sensibilisation des Improved Management of Single Stage - One En cours communautés riveraines des IDA / D2760 A posteriori Demande de prix Limited 20,000.00 0.00 2021-02-28 2021-02-26 2021-04-25 2021-10-22 Protected Areas and Reserves Envelope d'exécution aires protégées et des réserves (Pancartes, posters, Dépliants et Brochures) BI-BLRRP-233942-GO-RFQ / Fourniture des équipements Improved Management of Single Stage - One En attente TIC de surveillance des Airs IDA / D2760 A posteriori Demande de prix Open - National 84,000.00 0.00 2021-06-02 2021-07-28 2022-01-24 Protected Areas and Reserves Envelope d'exécution Protégées (AP) et formation des utilisateurs BI-BLRRP-207802-GO-RFB / Fourniture et installation des équipements pour les stations Institutional Development météorologiques and Capacity Building for Single Stage - One En cours automatiques et les stations IDA / D2760 A posteriori Appel d'offres Open - National 266,500.00 0.00 2021-06-28 2021-06-01 2021-07-03 2021-06-01 2021-08-14 2021-09-13 2021-10-18 2022-04-16 Landscape Restoration and Envelope d'exécution hydrologiques automatiques à Resilience Isare et Buhinyuza pour l'alerte précoce y compris la formation des utilisateurs BI-BLRRP-207816-GO-RFQ / Achat des équipements de station hydrologiques Sustainable Landscape Single Stage - One IDA / D2760 A posteriori Demande de prix Open - National 64,000.00 0.00 Annulé 2021-03-03 2021-04-28 2021-10-25 automatique d'Isare et Management Practices Envelope Buhinyuza pour l'alerte précoce BI-BLRRP-240994-CS-CDS / Fourniture des équipements Improved Management of Single Stage - One En attente TIC pour le compte de l'OBPE IDA / D2760 A posteriori Demande de prix Limited 51,000.00 0.00 2021-07-21 2021-09-15 2022-03-14 Protected Areas and Reserves Envelope d'exécution pour la surveillance et la collecte des données NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-MINAGRIE-109665-NC- DIR / Conclusion d'un contrat Passation de Improved Management of avec BIOVERSITY pour le IDA / D2760 A posteriori marché de gré à Direct 1,000,000.00 0.00 Annulé 2019-04-09 2019-11-05 2019-04-14 2019-11-19 2019-05-19 2019-11-15 Protected Areas and Reserves développement des semences gré améliorées BI-MINAGRIE-112698-NC- DIR / Acquisition et mise à Passation de Sustainable Landscape jour des logiciels de gestion IDA / D2760 A posteriori marché de gré à Direct 35,000.00 35,255.99 Achevé 2019-04-30 2019-06-20 2019-05-05 2019-11-14 2019-06-09 2019-12-10 2019-12-06 2020-05-20 Management Practices comptable et formations sur gré ces logiciels (Multi-site)/UCP BI-BLRRP-135159-NC-DIR / Convention avec la Direction Passation de de l'Aménagement du Improved Management of IDA / D2760 A posteriori marché de gré à Direct 150,000.00 150,000.00 Signé 2019-10-24 2019-11-23 2019-10-29 2019-12-10 2019-12-03 2019-12-02 2020-05-31 Territoire (DGAT) pour la mise Protected Areas and Reserves gré en oeuvre de la Composante B du Projet Institutional Development BI-BLRRP-190817-NC-RFQ / and Capacity Building for Single Stage - One Production et multiplication IDA / D2760 A posteriori Demande de prix Limited 30,000.00 25,413.49 Signé 2020-09-26 2020-09-25 2020-11-21 2020-12-11 2021-05-20 Landscape Restoration and Envelope des boîtes à image Resilience BI-BLRRP-207835-NC-RFQ / Recrutement d'une maison pour l'entretien des Project Management, Single Stage - One En cours IDA / D2760 A posteriori Demande de prix Limited 5,850.00 0.00 2021-03-31 2021-05-26 2021-11-22 équipemets informatiques de Coordination, and Monitoring Envelope d'exécution l'UCP et des UPCP Bujumbura et Muyinga BI-BLRRP-207867-NC-RFQ / Institutional Development Achat des logiciels pour le and Capacity Building for Single Stage - One En attente Centre d'Information IDA / D2760 A posteriori Demande de prix Open - National 47,500.00 0.00 2021-05-05 2021-06-30 2021-12-27 Landscape Restoration and Envelope d'exécution Environnementale (CIE/SIG) de Resilience l'OBPE BI-BLRRP-135155-NC-DIR / Convention avec l'Office Institutional Development Passation de Burundais pour la Protection and Capacity Building for IDA / D2760 A posteriori marché de gré à Direct 1,927,500.00 0.00 Annulé 2019-10-15 2019-12-15 2019-10-29 2020-01-15 2019-12-17 2020-06-14 de l'Environnement pour la Landscape Restoration and gré mise en oeuvre de la Resilience composante C du Projet CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 BI-MINAGRIE-99911-CS- QCBS / Recrutement d'un consultant pour faire les Sélection fondée etudes de faisabilite pour la Improved Management of IDA / D2760 A priori sur la qualité et le Open - International 350,000.00 0.00 Annulé 2019-02-09 2019-03-02 2019-04-15 2019-05-13 2019-06-12 2019-07-17 2019-08-21 2020-08-20 mise en place des terrasses Protected Areas and Reserves coût progressives et radicales ainsi que le supervision par methode HIMO BI-MINAGRIE-108118-CS- QCBS / Recrutement d'un consultant pour faire des Sélection fondée études des faisabilité pour la Improved Management of IDA / D2760 A priori sur la qualité et le Open - International 350,000.00 1,759,096.95 Signé 2019-03-27 2019-10-01 2019-04-17 2019-06-24 2019-05-31 2020-01-16 2019-06-28 2020-03-10 2019-07-28 2020-02-25 2019-09-01 2020-10-18 2019-10-06 2020-10-26 2020-10-05 mise en place des terrasses Protected Areas and Reserves coût progressives et radicales ainsi que la supervision par méthode HIMO BI-BLRRP-142816-CS-QBS / Recrutement d'un bureau de Sélection fondée services de consultants pour Project Management, sur les IDA / D2760 A posteriori Open - National 20,000.00 0.00 Annulé 2019-11-07 2019-11-28 2020-01-11 2020-02-10 2020-03-16 2020-09-12 la mise en place d'un système Coordination, and Monitoring qualifications des informatisé de Suivi- consultants Evaluation BI-BLRRP-147225-CS-CQS / Recrutement d'un bureau de Sélection fondée services de consultants pour Project Management, sur les En cours IDA / D2760 A posteriori Open - National 20,000.00 0.00 2019-11-26 2019-12-17 2019-12-17 2020-02-04 2020-01-30 2020-02-29 2020-04-04 2020-10-01 la mise en place d'un système Coordination, and Monitoring qualifications des d'exécution informatisé de Suivi- consultants Evaluation BI-MINAGRIE-99907-CS- Sélection fondée QCBS / Recrutement d'un Improved Management of IDA / D2760 A priori sur la qualité et le Open - International 1,884,300.00 0.00 Annulé 2019-02-09 2019-05-09 2019-03-02 2019-06-29 2019-04-15 2019-05-13 2019-06-12 2019-07-17 2019-08-21 2020-08-20 consultant pour la Protected Areas and Reserves coût certification foncière BI-BLRRP- 99907-CS-QBS / Sustainable Landscape Sélection fondée Recrutement d'un consultant IDA / D2760 A priori Open - International 1,884,300.00 2,328,363.00 Signé 2019-02-09 2020-01-15 2019-03-02 2019-04-15 2020-02-11 2019-05-13 2020-04-21 2019-06-12 2020-11-14 2019-07-12 2020-12-06 2019-08-16 2020-12-23 2020-08-15 Management Practices sur la qualité pour la certification foncière BI-BLRRP-154534-CS-QCBS / Audit externe des comptes du Project Management, Sélection au IDA / D2760 A posteriori Open - International 25,000.00 27,672.82 Signé 2020-01-21 2020-02-14 2020-02-11 2020-02-29 2020-03-26 2020-10-16 2020-04-23 2020-11-26 2020-05-23 2020-11-30 2020-06-27 2020-12-21 2020-08-01 2021-01-13 2021-01-28 PRRPB pour la période de Coordination, and Monitoring moindre coût juillet 2019 à juin 2020 BI-BLRRP-158815-NC-RFQ / Sélection fondée Recrutement d'un prestataire Project Management, sur les pour la conception, création IDA / D2760 A posteriori Open - National 7,500.00 0.00 Annulé 2020-02-24 2020-03-16 2020-04-29 2020-05-29 2020-07-03 2020-12-30 Coordination, and Monitoring qualifications des et hébergement d'un site web consultants du projet BI-MINAGRIE-99905-CS- Sélection fondée QCBS / Recrutement d'un Improved Management of IDA / D2760 A priori sur la qualité et le Open - International 1,000,000.00 0.00 Annulé 2019-02-09 2019-05-10 2019-03-02 2019-12-26 2019-04-15 2020-03-11 2019-05-13 2020-04-24 2019-06-12 2019-07-17 2019-08-21 2020-08-20 consultant pour la Protected Areas and Reserves coût mobilisation communautaire BI-MINEAGRIE-180453-CS- QCBS / Recrutement d'une ONG chargée d'appuyer l'Unité Sélection fondée Sustainable Landscape Nationale de Coordination du IDA / D2760 A priori sur la qualité et le Open - International 957,000.00 718,506.82 Signé 2019-02-09 2020-06-30 2019-03-02 2019-04-15 2020-07-20 2019-05-13 2020-09-11 2019-06-12 2020-09-27 2019-07-17 2020-12-15 2019-08-21 2020-12-31 2020-08-20 Management Practices PRRPB dans la mobilisation coût des communautés de la zone du projet BI-BLRRP-207824-CS-INDV / Recrutement d'un cabinet de Institutional Development services de Consultants pour and Capacity Building for Sélection fondée IDA / D2760 A posteriori Open - National 25,800.00 0.00 Annulé 2021-02-25 2021-03-18 2021-05-01 2021-05-29 2021-06-28 2021-07-28 2021-09-01 2022-09-01 l'élaboration des textes Landscape Restoration and sur la qualité d'application du code de l'eau Resilience et du code forestier BI-BLRRP-221892-CS-CQS / Recrutement de services de Institutional Development Sélection fondée consultants pour l'élaboration and Capacity Building for sur les En cours IDA / D2760 A posteriori Open - National 25,800.00 0.00 2021-03-26 2021-03-18 2021-04-16 2021-05-30 2021-06-29 2021-08-03 2022-01-30 des textes d'application du Landscape Restoration and qualifications des d'exécution code de l'eau et du code Resilience consultants forestier BI-MINAGRIE-128750-CS- CQS / Recrutement d’un Sélection fondée bureau de consultants pour la Sustainable Landscape sur les réalisation de l’étude de IDA / D2760 A posteriori Open - International 30,000.00 0.00 Annulé 2019-09-19 2019-11-21 2019-10-10 2019-11-26 2019-11-23 2020-03-24 2019-12-23 2020-01-27 2020-07-25 Management Practices qualifications des référence du Projet de consultants Restauration et Résilience du Paysage du Burundi BI-BLRRP-216466-CS-CQS / Sélection fondée Recrutement d'un bureau de Project Management, sur les Services de Consultants pour IDA / D2760 A posteriori Open - National 35,000.00 0.00 Annulé 2021-02-15 2021-03-09 2021-03-08 2021-04-21 2021-05-25 2021-05-21 2021-06-25 2021-12-22 Coordination, and Monitoring qualifications des appui dans l'évaluation à mi- consultants parcours du PRRPB INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-MINAGRIE-99903-CS- INDV / Recrutement d'un Contingency Emergency IDA / D2760 A posteriori Individuel Open 15,000.00 0.00 Annulé 2019-02-09 2019-03-30 2019-04-20 2019-05-25 2019-11-21 consultant pour l'élaboration Response (CERC) de la situation genre du projet BI-MINAGRIE-101091-CS- CDS / Conclusion d'un contrat avec l'Université de Florence Sélection de Improved Management of pour le renforcement des IDA / D2760 A posteriori consultants par Direct 400.00 0.00 Annulé 2019-02-15 2019-02-27 2019-03-16 2022-02-28 Protected Areas and Reserves capacités et la supervision des entente directe travaux de construction des terrasses radicales Page 4 BI-MINAGRIE-101101-CS- CDS / Conclusion d'un contrat Sélection de Improved Management of avec BIOVERSITY pour le IDA / D2760 A priori consultants par Direct 1,000,000.00 0.00 Annulé 2019-02-15 2019-02-25 2019-05-01 2019-10-28 Protected Areas and Reserves developpement des semences entente directe améliorées BI-MINAGRIE-103392-CS- INDV / Recrutement d'un Sustainable Landscape IDA / D2760 A posteriori Individuel Open 7,500.00 0.00 Annulé 2019-02-27 2019-04-17 2019-05-08 2019-06-12 2019-12-09 consultant pour la mise à jour Management Practices du document du PAD BI-MINAGRIE-108107-CS- CDS / Recrutement de l'Université de Florence pour Sélection de Improved Management of En cours le renforcement des capacités IDA / D2760 A priori consultants par Direct 400,000.00 0.00 2019-03-27 2019-06-10 2019-04-06 2019-09-10 2019-06-10 2019-12-07 Protected Areas and Reserves d'exécution et la supervision des travaux entente directe de construction des terrasses radicales. BI-MINAGRIE-108111-CS- INDV / Recrutement d'un Contingency Emergency IDA / D2760 A posteriori Individuel Open 15,000.00 7,564.21 Signé 2019-03-27 2019-05-31 2019-05-15 2019-08-07 2019-06-05 2019-09-24 2019-07-10 2019-09-24 2020-01-06 consultant pour l'élaboration Response (CERC) de la situation genre du projet BI-MINAGRIE-108193-CS- INDV / Recrutement d'un consultant pour une étude Sustainable Landscape IDA / D2760 A posteriori Individuel Open 15,000.00 10,232.93 Achevé 2019-03-28 2019-06-13 2019-05-16 2019-11-14 2019-06-06 2019-11-14 2019-07-11 2020-07-03 2020-01-07 2021-02-08 d'impact environnemental et Management Practices social du projet et sa vulgarisation BI-MINAGRIE-112706-CS- INDV / Recrutement d'un Sustainable Landscape IDA / D2760 A posteriori Individuel Open 18,000.00 18,000.00 Signé 2019-04-30 2019-06-16 2019-06-18 2019-11-06 2019-07-09 2019-11-06 2019-08-13 2019-11-08 2020-02-09 comptable pour le compte de Management Practices l'UC-PRRPB BI-MINAGRIE-112711-CS- INDV / Recrutement d'un (e) Sustainable Landscape IDA / D2760 A posteriori Individuel Open 18,000.00 18,000.00 Signé 2019-04-30 2019-06-16 2019-06-18 2019-10-03 2019-07-09 2019-10-08 2019-08-13 2019-10-09 2020-02-09 assistant du Coordonnateur Management Practices du PRRPB BI-MINAGRIE-112713-CS- INDV / Recrutement d'un (e) Sustainable Landscape En cours Secrétaire IDA / D2760 A posteriori Individuel Open 9,600.00 0.00 2019-04-30 2019-07-25 2019-06-18 2019-07-09 2019-08-13 2020-02-09 Management Practices d'exécution receptionniste/standardiste pour le compte de l'UC- PRRPB. BI-MINAGRIE-125656-CS- INDV / Recrutement d'une Sustainable Landscape En cours Unité de Suivi Évaluation pour IDA / D2760 A posteriori Individuel Open 18,000.00 0.00 2019-07-31 2019-08-23 2019-09-18 2019-10-09 2019-11-13 2020-05-11 Management Practices d'exécution l'unité provinciale du Projet dans la Province de Bujumbura BI-MINAGRIE-123980-CS- INDV / Recrutement d'un agent de suivi évaluation pour Sustainable Landscape IDA / D2760 A posteriori Individuel Open 18,000.00 18,000.00 Signé 2019-08-14 2019-08-23 2019-10-02 2019-11-11 2019-10-23 2019-11-18 2019-11-27 2019-11-18 2020-05-25 l'unité provinciale de Management Practices coordination du projet à Muyinga BI-BLRRP-135167-CS-INDV / Recrutement d'un consultant Sustainable Landscape IDA / D2760 A posteriori Individuel Open 10,000.00 5,688.81 Signé 2019-09-20 2019-10-10 2019-11-08 2020-06-17 2019-11-29 2020-07-30 2020-01-03 2020-08-14 2020-07-01 pour l'élaboration de la Management Practices stratégie communication BI-BLRRP-135179-CS-INDV / Recrutement d'un consultant Contingency Emergency IDA / D2760 A posteriori Individuel Open 150,000.00 5,829.88 Signé 2019-09-20 2019-08-20 2019-11-08 2020-02-10 2019-11-29 2020-05-18 2020-01-03 2020-09-16 2020-07-01 pour la formation en gestion Response (CERC) axée sur les résultats BI-BLRRP-138414-CS-INDV / Recrutement d'un consultant pour l'adaptation du Manuel Sustainable Landscape IDA / D2760 A posteriori Individuel Open 3,000.00 0.00 Annulé 2019-10-15 2019-11-25 2019-12-03 2019-12-24 2020-01-28 2020-07-26 des procédures du PACSC Management Practices pour produire le Manuel des Procédures du PRRPB BI-BLRRP-137037-CS-LCS / Recrutement d'un consultant Sélection de Project Management, pour l'audit du PRRPB pour la IDA / D2760 A posteriori consultants par Direct 10,000.00 8,869.32 Achevé 2019-10-24 2019-11-06 2019-11-03 2019-11-22 2020-01-07 2019-12-02 2020-07-05 2019-12-30 Coordination, and Monitoring période courant à partir du entente directe 01/10/2018 au 30/06/2019 BI-BLRRP-143000-CS-INDV / Recrutement d'un consultant Institutional Development pour l'élaboration d'un Plan de and Capacity Building for mobilisation des parties IDA / D2760 A posteriori Individuel Open 15,000.00 11,802.56 Signé 2019-10-28 2019-11-08 2019-12-16 2020-02-24 2020-01-06 2020-05-04 2020-02-10 2020-06-10 2020-08-08 Landscape Restoration and prenantes du Projet de Resilience Restauration et de Résilience du Paysage du Burundi (PRRPB) BI-BLRRP-143005-CS-INDV / Recrutement d'un consultant individuel pour l'élaboration d'un plan spécifique en faveur en faveur des peuples Improved Management of autochtones (Batwa) dans les IDA / D2760 A posteriori Individuel Open 15,000.00 11,998.76 Achevé 2019-10-28 2019-11-08 2019-12-16 2020-01-15 2020-01-06 2020-03-28 2020-02-10 2020-02-07 2020-08-08 2021-02-08 Protected Areas and Reserves communes de Buhinyuza et d’Isale dans le cadre du Projet de Restauration et de Résilience du Paysage du Burundi BI-BLRRP-144837-CS-INDV / Institutional Development Recrutement d'un Consultant and Capacity Building for individuel pour l'élaboration IDA / D2760 A posteriori Individuel Open 15,000.00 7,074.36 Achevé 2019-11-07 2019-11-26 2019-12-26 2020-01-13 2020-01-16 2020-02-03 2020-02-20 2020-03-03 2020-08-18 2021-02-08 Landscape Restoration and d'un Plan de Gestion des Resilience Pestes et Pesticides BI-BLRRP-135163-NC-DIR / Convention avec le Secrétariat Institutional Development Sélection de Permanent de la Commission and Capacity Building for IDA / D2760 A posteriori consultants par Direct 180,000.00 0.00 Annulé 2019-11-07 2019-11-17 2020-01-21 2020-07-19 Nationale Foncière pour la Landscape Restoration and entente directe mise en en oeuvre de la Resilience composante A du Projet Page 5 BI-BLRRP-150250-CS-CDS / Recrutement d'un consultant Sélection de individuel pour la mise à jour Project Management, IDA / D2760 A posteriori consultants par Direct 5,000.00 5,452.87 Achevé 2019-12-13 2019-12-23 2019-12-23 2020-01-07 2020-02-26 2020-01-14 2020-08-24 2020-03-26 du Cadre de Gestion Coordination, and Monitoring entente directe Environnemental et social (CGES) pour le PRRPB BI-BLRRP-150256-CS-CDS / Recrutement d'un consultant Sélection de individuel pour la mise à jour Project Management, IDA / D2760 A posteriori consultants par Direct 5,000.00 6,012.61 Achevé 2019-12-13 2019-12-23 2019-12-23 2020-01-07 2020-02-26 2020-01-14 2020-08-24 2020-03-26 du Cadre de Politique de Coordination, and Monitoring entente directe Réinstallation Involontaire pour le PRRPB BI-BLRRP-150260-CS-CDS / Recrutement d'un consultant Sélection de individuel pour la mise à jour Project Management, IDA / D2760 A posteriori consultants par Direct 5,000.00 5,452.87 Achevé 2019-12-13 2019-12-23 2019-12-23 2020-01-07 2020-02-26 2020-01-14 2020-08-24 2020-03-26 d'un cadre de Planification en Coordination, and Monitoring entente directe Faveur des Peuples Autochtones pour le PRRPB BI-BLRRP-150301-CS-CDS / Recrutement d'un Consultant Sélection de Project Management, individuel pour la mise à jour IDA / D2760 A posteriori consultants par Direct 5,000.00 6,012.61 Achevé 2019-12-13 2019-12-23 2019-12-23 2020-01-07 2020-02-26 2020-01-13 2020-08-24 2020-03-26 Coordination, and Monitoring du Cadre fonctionnel pour le entente directe PRRPB BI-MINAGRIE-99909-CS-CDS Sélection de / Contrat avec FAO pour la Improved Management of IDA / D2760 A priori consultants par Direct 1,190,000.00 0.00 Annulé 2019-02-09 2019-11-20 2019-02-19 2019-04-25 2019-10-22 mise place des champs écoles Protected Areas and Reserves entente directe paysans BI-BLRRP-135176-CS-INDV / Recrutement d'un consultant Sustainable Landscape IDA / D2760 A posteriori Individuel Open 10,000.00 0.00 Annulé 2019-09-20 2019-10-10 2019-11-08 2019-11-29 2020-01-03 2020-07-01 pour l'élaboration d'un Manuel Management Practices de Suivi-Évaluation BI-BLRRP- 99909-CS-CDS CONTRAT AVEC FAO / Contrat Sélection de Improved Management of avec la FAO pour la mise en IDA / D2760 A priori consultants par Direct 1,190,000.00 1,394,472.00 Signé 2019-02-09 2020-01-15 2019-02-19 2020-03-14 2019-04-25 2020-11-09 2019-10-22 Protected Areas and Reserves place des Champs Ecole entente directe Paysans (CEP) BI-BLRRP-154292-CS-INDV / Recrutement d'un consultant individuel pour l'élaboration Project Management, d'un Manuel des Procédures IDA / D2760 A posteriori Individuel Open 15,000.00 10,248.77 Signé 2020-01-17 2020-02-03 2020-03-06 2020-04-06 2020-03-27 2020-04-29 2020-05-01 2020-04-29 2020-10-28 Coordination, and Monitoring de Gestion Administrative, Financière et Comptable du PRRPB BI-BLRRP-154313-CS-INDV / Recrutement d'un consultant individuel pour l'élaboration Project Management, IDA / D2760 A posteriori Individuel Open 15,000.00 10,888.23 Achevé 2020-01-17 2020-02-03 2020-03-06 2020-05-04 2020-03-27 2020-06-28 2020-05-01 2020-06-25 2020-10-28 2021-04-15 d'un Manuel des Procédures Coordination, and Monitoring de Passation des Marchés du PRRPB BI-BLRRP-158811-CS-INDV / Recrutement d'un consultant Project Management, individuel temporaire chargé IDA / D2760 A posteriori Individuel Open 7,500.00 0.00 Annulé 2020-02-12 2020-02-18 2020-04-01 2020-04-22 2020-05-27 2020-11-23 Coordination, and Monitoring des Sauvegardes Sociales pour une période de 3 mois BI-BLRRP-159902-CS-CDS / Contrat avec Bioversity International pour assistance Sélection de technique dans l'acquisition Improved Management of IDA / D2760 A priori consultants par Direct 500,000.00 517,633.00 Signé 2020-02-17 2020-02-20 2020-02-27 2020-03-14 2020-05-02 2020-10-23 2020-10-29 des semences améliorées et la Protected Areas and Reserves entente directe formation en développement des pépinières communautaires BI-BLRRP-160473-CS-INDV / Recrutement d'un consultant individuel national chargé Project Management, d'appuyer l'UCP-PRRPB dans la IDA / D2760 A posteriori Individuel Limited 10,000.00 12,500.00 Signé 2020-02-19 2020-02-20 2020-02-24 2020-02-24 2020-03-16 2020-03-27 2020-04-20 2020-04-07 2020-10-17 Coordination, and Monitoring mise en oeuvre des activités de sauvegarde environnementale et sociale BI-BLRRP-166821-CS-INDV / Recrutement d'un consultant individuel charger d'élaborer Improved Management of IDA / D2760 A posteriori Individuel Limited 8,000.00 7,958.00 Signé 2020-03-31 2020-04-22 2020-04-05 2020-05-04 2020-04-26 2020-10-27 2020-05-31 2020-10-30 2020-11-27 un plan d'affaire Protected Areas and Reserves d'écotourisme pour la réserve naturelle forestière de Bururi BI-BLRRP-160478-CS-INDV / Recrutement d'un Spécialiste Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-02-28 2020-03-18 2020-04-17 2020-05-08 2020-06-12 2020-12-09 en Sauvegardes Coordination, and Monitoring Environnementales et Sociales BI-BLRRP-173989-CS-INDV / Recrutement d'un spécialiste chargé d'appuyer le projet Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2020-05-22 2020-06-06 2020-07-10 2020-08-31 2020-07-31 2020-08-31 2020-09-04 2020-09-15 2021-03-03 dans la mise en oeuvre des Coordination, and Monitoring activités de Sauvegardes Environnementales et Sociales BI-BLRRP-194762-CS-INDV / Recrutement d'un d'un Project Management, IDA / D2760 A posteriori Individuel Open 360,000.00 36,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-06-05 2019-12-21 2019-06-12 2020-01-25 2019-06-12 2020-07-23 Coordonnateur/une Coordination, and Monitoring Coordonnatrice du PRRPB BI-BLRRP-194765-CS-INDV / Recrutemen d'un spécialiste Project Management, IDA / D2760 A posteriori Individuel Open 31,200.00 31,200.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-05-27 2019-12-21 2019-06-12 2020-01-25 2019-06-12 2020-07-23 en Gestion Financière au Coordination, and Monitoring PRRPB BI-BLRRP-194751-CS-INDV / Recrutemen d'un spécialiste Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-05-27 2019-12-21 2019-06-12 2020-01-25 2019-06-12 2020-07-23 en Restauration des Paysages Coordination, and Monitoring au PRRPB Page 6 BI-BLRRP-194748-CS-INDV / Recrutemen d'un spécialiste Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-06-14 2019-12-21 2019-06-17 2020-01-25 2019-06-17 2020-07-23 en Productivité Agricole au Coordination, and Monitoring PRRPB BI-BLRRP-194753-CS-INDV / Project Management, Recrutement d'un Auditeur IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-07-16 2019-12-21 2019-07-24 2020-01-25 2019-07-24 2020-07-23 Coordination, and Monitoring Interne au PRRPB BI-BLRRP-194749-CS-INDV / Project Management, Recrutemen d'un spécialiste IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-05-27 2019-12-21 2019-05-27 2020-01-25 2019-06-12 2020-07-23 Coordination, and Monitoring en Suivi-Evaluation au PRRPB BI-BLRRP-194747-CS-INDV / Project Management, Recrutemen d'un spécialiste IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-06-11 2019-12-21 2019-06-17 2020-01-25 2019-06-17 2020-07-23 Coordination, and Monitoring en Communication au PRRPB BI-BLRRP-194758-CS-INDV / Recrutemen d'un spécialiste Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 37,500.00 Résilié 2019-10-12 2018-10-12 2019-11-30 2019-06-10 2019-12-21 2019-06-12 2020-01-25 2019-06-12 2020-07-23 en Sauvegardes sociales au Coordination, and Monitoring PRRPB BI-BLRRP-194754-CS-INDV / Recrutemen d'un spécialiste Project Management, En cours IDA / D2760 A posteriori Individuel Open 30,000.00 0.00 2019-10-12 2018-10-12 2019-11-30 2019-12-21 2020-01-25 2020-07-23 en Passation des Marchés au Coordination, and Monitoring d'exécution PRRPB BI-BLRRP-194759-CS-INDV / Recrutemen d'un spécialiste Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-09-03 2019-12-21 2019-09-09 2020-01-25 2019-09-09 2020-07-23 en Certification Foncière au Coordination, and Monitoring PRRPB BI-BLRRP-194761-CS-INDV / Recrutemen d'un spécialiste Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2020-02-04 2019-12-21 2020-02-10 2020-01-25 2020-02-10 2020-07-23 en Genre et Inclusion Sociale Coordination, and Monitoring au PRRPB BI-BLRRP-194755-CS-INDV / Recrutemen d'un Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-06-04 2019-12-21 2019-06-12 2020-01-25 2019-06-12 2020-07-23 Coordonnateur Provincial de Coordination, and Monitoring Bujumbura BI-BLRRP-194756-CS-INDV / Recrutemen d'un Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 30,000.00 Signé 2019-10-12 2018-10-12 2019-11-30 2019-06-10 2019-12-21 2019-06-12 2020-01-25 2019-06-12 2020-07-23 Coordonnateur Provincial de Coordination, and Monitoring Muyinga BI-BLRRP-194750-CS-INDV / Project Management, Recrutemen d'un Comptable IDA / D2760 A posteriori Individuel Open 18,000.00 18,000.00 Signé 2019-04-30 2019-07-25 2019-06-18 2019-11-26 2019-07-09 2019-11-28 2019-08-13 2019-11-28 2020-02-09 Coordination, and Monitoring N°2 du PRRPB BI-BLRRP-194760-CS-INDV / Recrutement d'un Secrétaire Project Management, En cours IDA / D2760 A posteriori Individuel Open 7,200.00 0.00 2019-04-30 2019-08-23 2019-06-18 2019-07-09 2019-08-13 2020-02-09 comptable en province de Coordination, and Monitoring d'exécution Bujumbura BI-BLRRP-194757-CS-INDV / Recrutement d'un Secrétaire Project Management, En cours IDA / D2760 A posteriori Individuel Open 7,200.00 0.00 2019-04-30 2019-08-23 2019-06-18 2019-07-09 2019-08-13 2020-02-09 comptable en province de Coordination, and Monitoring d'exécution Muyinga BI-BLRRP-205825-CS-INDV / Recrutement d'un Consultant Institutional Development individuel chargé de and Capacity Building for IDA / D2760 A posteriori Individuel Open 15,000.00 26,649.28 Signé 2020-12-15 2020-12-09 2021-02-02 2021-03-01 2021-02-23 2021-03-12 2021-03-30 2021-05-19 2021-09-26 l'élaboration d'un Plan Landscape Restoration and d'Action de Réinstallation Resilience (PAR) pour le PRRPB BI-BLRRP-167913-CS-INDV / Recrutement d'un Consultant Individuel facilitateur pour Project Management, l'élaboration d'un plan de IDA / D2760 A posteriori Individuel Open 15,000.00 0.00 Annulé 2020-04-13 2020-04-22 2020-06-01 2020-06-22 2020-07-27 2021-01-23 Coordination, and Monitoring suivi-évaluation (Production d'un manuel de suivi- Evaluation) du PRRPB BI-BLRRP-207828-CS-INDV / Recrutement d'un Consultant individuel pour l'élaboration Institutional Development des Plans de Gestion and Capacity Building for En attente IDA / D2760 A posteriori Individuel Open 15,000.00 0.00 2021-03-31 2021-05-19 2021-06-09 2021-07-14 2022-01-10 Environnementale et Sociale Landscape Restoration and d'exécution des sites d'aménagement des Resilience terrasses progressives et radicales BI-BLRRP-207833-CS-INDV / Recrutement d'un Consultant individuel pour la formation Institutional Development du personnel du projetet and Capacity Building for IDA / D2760 A posteriori Individuel Open 10,000.00 0.00 En cours d'examen 2021-01-29 2021-05-10 2021-03-19 2021-04-09 2021-05-14 2021-11-10 d'autres intervenants sur les Landscape Restoration and outils de communication Resilience sensibles au genre et sur le genre et développement BI-BLRRP-147343-NC-DIR / Convention avec le Secrétariat Institutional Development Permanent de la Commission Sélection de and Capacity Building for Foncière Nationale (SP/CFN) IDA / D2760 A posteriori consultants par Direct 180,000.00 0.00 Annulé 2019-12-13 2020-01-16 2019-12-23 2020-01-29 2020-02-26 2020-08-24 Landscape Restoration and pour la supervision des entente directe Resilience activités en rapport avec la certification foncière BI-BLRRP-207790-CS-INDV / Recrutement d'un Consultant Institutional Development Individuel pour la formation and Capacity Building for En attente du personnel technique du IDA / D2760 A posteriori Individuel Open 23,000.00 0.00 2021-03-02 2021-04-20 2021-05-11 2021-06-15 2021-12-12 Landscape Restoration and d'exécution Centre d'Information Resilience Environnementale de l'OBPE et du du PRRPB en SIG Page 7 BI-BLRRP-221887-CS-INDV / Recrutement d'un Spécialiste Project Management, En cours IDA / D2760 A posteriori Individuel Direct 23,660.90 0.00 2021-03-05 2021-03-01 2021-03-15 2021-03-12 2021-04-05 2021-03-29 2021-05-10 2021-11-06 en Genre et Inclusion Sociale Coordination, and Monitoring d'exécution au PRRPB BI-BLRRP-194764-CS-INDV / Recrutemen d'une unité de Project Management, IDA / D2760 A posteriori Individuel Open 30,000.00 0.00 Annulé 2019-04-30 2019-08-23 2019-06-18 2019-07-09 2019-08-13 2020-02-09 suivi-évaluation en province Coordination, and Monitoring de Muyinga BI-BLRRP-207825-CS-INDV / Recrutement d'un Consultant individuel pour appuyer l'UCP Institutional Development dans les activités and Capacity Building for IDA / D2760 A posteriori Individuel Open 18,000.00 0.00 Annulé 2021-02-26 2021-02-16 2021-04-16 2021-05-07 2021-06-11 2021-12-08 d'autonomisation économique Landscape Restoration and des bénéficiaires Resilience principalement des femmes et autres groupes vulnérables BI-BLRRP-232384-CS-INDV / Recrutement d'un Consultant individuel pour appuyer l'UCP Institutional Development dans les activités and Capacity Building for En cours IDA / D2760 A posteriori Individuel Open 38,000.00 0.00 2021-05-21 2021-05-10 2021-07-09 2021-07-30 2021-09-03 2022-03-02 d'autonomisation économique Landscape Restoration and d'exécution des bénéficiaires Resilience principalement des femmes et autres groupes vulnérables BI-BLRRP-207832-CS-INDV / Institutional Development Recrutement d'un Consultant and Capacity Building for Individuel pour la conception IDA / D2760 A posteriori Individuel Open 30,000.00 0.00 Annulé 2021-03-26 2020-12-23 2021-05-14 2021-06-04 2021-07-09 2022-01-05 Landscape Restoration and du système d'aletre Resilience opérationnel BI-BLRRP-232361-CS-INDV / Recrutement de Monsieur Project Management, Ferdinand NDERAGAKURA, IDA / D2760 A posteriori Individuel Direct 24,647.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Coordination, and Monitoring Spécialiste en Restauration des Paysages au PRRPB BI-BLRRP-232370-CS-INDV / Recrutement de Monsieur Project Management, Joseph NAHAYO, IDA / D2760 A posteriori Individuel 24,648.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Coordination, and Monitoring Coordonnateur de l'Unité provinciale de Muyinga BI-BLRRP-232348-CS-INDV / Recrutement de Madame Odette KAYITESI, Project Management, Coordonnatrice National du IDA / D2760 A posteriori Individuel 37,956.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Coordination, and Monitoring Projet de Restauration et de Résilience du Paysage du Burundi (PRRPB) BI-BLRRP-232354-CS-INDV / Recrutement de Monsieur Jean Project Management, Claude MASABO, Spécialiste IDA / D2760 A posteriori Individuel Direct 27,444.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Coordination, and Monitoring en Gestion Financière au PRRPB BI-BLRRP-232382-CS-INDV / Recrutement de Monsieur Project Management, En cours Félicien HATUNGIMANA, IDA / D2760 A posteriori Individuel Direct 24,648.00 0.00 2021-08-06 2021-08-16 2021-09-06 2021-10-11 2022-04-09 Coordination, and Monitoring d'exécution Spécialiste en Certification Foncière au PRRPB BI-BLRRP-232356-CS-INDV / Recrutement de Monsieur Project Management, Déogratias SIMBAVIMBERE, IDA / D2760 A posteriori Individuel Direct 25,164.00 0.00 En cours d'examen 2021-08-20 2021-05-18 2021-08-30 2021-09-20 2021-10-25 2022-04-23 Coordination, and Monitoring Spécialiste en Passation des Marchés au PRRPB BI-BLRRP-232363-CS-INDV / Recrutement de Monsieur Project Management, Bonith BARAGURANA, IDA / D2760 A posteriori Individuel Direct 25,164.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Coordination, and Monitoring Spécialiste en Suivi-Evaluation au PRRPB BI-BLRRP-232364-CS-INDV / Recrutement de Monsieur Project Management, Emmanuel RUFYIKIRI, IDA / D2760 A posteriori Individuel Direct 24,648.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Coordination, and Monitoring Spécialiste en Productivité Agricole BI-BLRRP-232380-CS-INDV / Recrutement de Monsieur Prosper BARAKAMFITIYE, Project Management, IDA / D2760 A posteriori Individuel Direct 24,648.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Coordonnateur de l'Unité Coordination, and Monitoring provinciale du Projet à Bujumbura BI-BLRRP-232366-CS-INDV / Recrutement de Monsieur Project Management, IDA / D2760 A posteriori Individuel Direct 24,304.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Balthazar BARAYANDEMA, Coordination, and Monitoring Auditeur Interne au PRRPB BI-BLRRP-232365-CS-INDV / Recrutement de Madame Project Management, Clarette INAMAHORO, IDA / D2760 A posteriori Individuel Direct 24,648.00 0.00 En cours d'examen 2021-05-21 2021-05-18 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Coordination, and Monitoring Spécialiste en Communication au PRRPB BI-BLRRP-232369-CS-INDV / Recrutement de Madame Antoinette MACUMI, Project Management, IDA / D2760 A posteriori Individuel Direct 24,648.00 0.00 En cours d'examen 2021-07-16 2021-05-18 2021-07-26 2021-08-16 2021-09-20 2022-03-19 Spécialiste en Sauvegardes Coordination, and Monitoring Sociale et Environnementale au PRRPB BI-BLRRP-240990-CS-CDS / Recrutement d'un Consultant Sélection de individuel, Monsieur Eloi Project Management, En attente IDA / D2760 A posteriori consultants par Direct 35,000.00 0.00 2021-06-28 2021-07-08 2021-09-11 2022-03-10 Edouard KWIZERA, chargé Coordination, and Monitoring d'exécution entente directe d'une évaluation à mi- parcours du PRRPB Page 8 Page 9